REQUEST FOR QUOTATION FOR
THE SUPPLY
INSTALLATION,TESTING AND
COMMISSIONING OF 10KVA
ONLINE UPS ALONG WITH
ADDITIONAL BATTERY PACK AT
HEAD OFFICE PIEDMC PUNJAB
INDUSTRIAL ESTATE
PROJECT OUTLINE
AND
PREQUALIFICATION CRITERIA
`
- 1 - | P a g e
Punjab Industrial Estates Development and Management Company
BACKGROUND.
The Government of Punjab has set up Punjab Industrial Estates Development and
Management Company (PIEDMC) Ltd. to achieve orderly, planned and rapid
industrialization of Punjab by developing a chain of industrial estates in a dynamic and
innovative manner, this aims at providing turnkey solutions to the problems by prospective
entrepreneurs.
`
- 2 - | P a g e
PUNJAB INDUSTRIAL ESTATES
DEVELOPMENT AND MANAGEMENT COMPANY
REQUEST FOR QUOTATION FOR THE SUPPLY OF 10KVA ONLINE UPS AT PIEDMC HEAD OFFICE
Punjab Industrial Estates Development and Management Company (PIE) was established by Govt. of the
Punjab with Public Private Partnership, to facilitate the industrial growth of Punjab.
o PIEDMC requests for quotation for the supply of 10 KVA online UPS at PIEDMC head office of the following specifications from interested companies / firms.
Sr. No Items Description
01
10KVA online UPS
Output: Output power capacity 10.0 kVA Output Voltage 230V Output Voltage Distortion Less than 2% Output Frequency (sync to mains) 50/60Hz +/- 3 Hz Other Output Voltages 220, 240
Input: Nominal Input Voltage 230V , 400V 3PH Input frequency 40 - 70 Hz (auto sensing) Input Voltages 220, 240, 380, 415
Brand: APC by Schneider USA, Emerson USA or approved equivalent (USA or Europe manufactured)
o The bidders must: o Be registered with the FBR for income tax & sales tax. o Submit the Undertaking on Rs.100/- Stamp paper that company has never been Black listed by any
department. Failure to provide this undertaking will result into REJECTION of the prequalification
application. o Have sufficient financial, technical and human resource to complete the project within the prescribed
time limit in the contract. o Enclose Rs 30,000/- as bid security with financial proposal, which should be in form of CDR/DD from
a scheduled bank of Pakistan in favor of PIEDMC o Submit the bid in accordance with the Single Stage-Two Envelope procedure of PPRA (Punjab)
Rules 2014. o Submit Technical and Financial bids addressed to General Manager Technical PIEDMC up to
13th
July 2016 at 1100/- HRs. Technical proposals will be opened publically on 13thJuly 2016 at 1130
HRS. o Qualified bidders will be informed after evaluation of technical proposals for the opening of financial
proposals accordingly. o The TORs along with antecedent specification of the above mentioned material can be obtained
from the office of the Chief Engineer Electrical PIEDMC during the office hours, on payment of Rs. 500/- in the form of pay order in the name PIEDMC. The TORs document can be downloaded from websites www.ppra.punjab.gov.pk or www.pie.com.pk, the bidder must attach Pay order of Rs. 500
with his bid as cost of bidding document if downloaded from website. The bid evaluation criteria are
included in the TORs. o Procurement shall be made in compliance of PPRA Rules, 2014; award shall be made on Least
Cost method. o Incomplete bids, defective bids and bids not confirming to the TOR documents shall be liable to
reject. No Bids will be received after due time & date.
General Manager (Technical)-PIEDMC
Punjab Industrial Estates, Head Office, Commercial Area(North), Sunder Industrial Estate, Sunder-Raiwind Road, Lahore. Tel :- 042-35297203-6 Fax :- 042-35297207 City Office, 27-Egerton Road, 3
rd Floor Ajmal house, Adjacent Hotel Holiday Inn, Lahore.
Tel :- 042-99203661-3 Fax :- 042-99203660 URL: www.pie.com.pk, Email: [email protected]
Bid Reference No.: PIE/UPS/01 INVITATION TO BIDDERS
`
- 3 - | P a g e
a) Brand Description:
The brands recommended for the 10.0 KVA Online UPS along with additional
battery Pack Set are as follows:
b) UPS(Latest Model)
10KVA online UPS brand Emerson USA/ APC by Schneider USA or
approved equivalent. (USA / European manufactured)
c) Battery Pack
One additional battery pack built in as per brand offered.
d) Pre Delivery Inspection:
Pre delivery inspection will be carried out at supplier premises by
PIEDMC Engineer.
e) Scope of Work:
a) Supply, Loading and Unloading at PIEDMC Head Office Raiwind road
Lahore.
b) Installation, Connection, Testing, Commissioning and on load
operational testing to verify parameters.
f) Warranties:
a) Warranty will be for three complete years with parts from the date of
commissioning.
b) On call, immediate service response against trouble shooting.
TERMS AND CONDITIONS
a. Incomplete, defective bids not confirming to the TORs shall be liable to
rejection, and the bids received after due time & date shall be summarily
rejected.
b. PIEDMC reserves right to cancel the process at any stage and reject all
bids, before assigning the contract.
c. Validity of bid will be 128 days after the bid submission date.
d. Bids will be evaluated on lowest rate quoted criteria and contract will be
awarded to lowest evaluated responsive bidder.
`
- 4 - | P a g e
e. In case of delay in Project completion 0.5% per day of Contract Amount
will be charged as Liquidity Damage to Contractor and maximum up to 10
% of Contract Amount.
f. Technical and Financial evaluation will be carried out according to the
product document and further documents will be demanded/ accepted
after submission of proposal.
DOCUMENTS REQUIRED TO BE ATTACHED WITH TECHNICAL PROPOSAL
Following Documents are required to be attached with Technical Proposal.
a) Detail Profile of company.
b) Letter of authorization from the manufacturer /dealer in Pakistan.
c) Complete detail and specifications (brochure) of offered Product.
d) Documentary evidence of registration with FBR regarding Income &
Sale Tax.
e) Undertaking on Rs.100/- Stamp paper that company has never been
Black listed by any department. Failure to provide this undertaking will
result into REJECTION of the prequalification application.
f) Delivery, loading/unloading, installation, Load testing and
commissioning should be completed within 08 weeks after issuance of
purchase order. Agreed delivery schedule to be provided.
g) List of projects of similar nature completed in the last 5 years of same
capacity or above. No marks, if Purchase orders and
Completion/Performance certificates not attached as per Technical bid
evaluation criteria.(At least 02 Projects are mandatory)
h) List of Projects of similar nature in hand of same capacity or above. No
marks, if Purchase orders not attached as per Technical bid evaluation
criteria.
i) If any firm already worked with PIEDMC then performance certificate
issued by PIEDMC is mandatory to be attached with Technical
Proposal.
`
- 5 - | P a g e
DOCUMENTS TO BE ATTACHED WITH FINANCIAL PROPOSAL
Following Documents are to be attached with Financial Proposal.
a) Bid security in form of CDR/DD issued by a schedule bank in favor of
PIEDMC as per advertisement (Request for Quotation).
b) Quotation shall be inclusive of all Taxes, duties with G.S.T and other
levies applicable under Pakistan Law.
Price and Delivery Schedule
Description Quantity
Quoted
Price
including
all Taxes
Discount
(if any)
Final Bid
Price
Completion
Time
Supply, Installation,
Connecting, Load testing
and commissioning of
10.0KVAonline UPS along
with built in 12V 8AMP
32Nos, backup time Full
Load 11.5/3.8 minutes
and with additional
battery backup time
28/11.6 minutes
01 No
Eight
Weeks After
Issuance of
Purchase
Order
PAYMENT SCHEDULE:
a) 50% advance against Bank Guarantee issued by schedule bank of Pakistan
b) 50% will be made on installation, connecting, Load testing, commissioning of
UPS and after issuance of competition certificate.
`
- 6 - | P a g e
TECHNICAL BID EVALUATION CRITERIA: Following criteria shall be used for the selection of the firm:
Sr. No. Category Weight
age/Marks
1. Brand/ Product detailed offered as specified /
approved 30
2.. General Experience 35
3. Personnel Capabilities 8
4. Equipment Capabilities 12
5. General Requirement 5
6. Financial Soundness 10
Total: 100/-
Note: Technical Qualification status shall be decided on the basis of Pass/Fail basis. The
applicant must secure at least 60% score in each category.Incaseoflessthan60% marks in
any category will be treated as Fail.
The further detailed criteria for each category given under the each head as follows:
1. Brand Product Detail Offered
Credit marks shall be awarded on the basis of following criteria
Sr. No. Description Maximum
Points
i) Emerson USA / APC by Schneider USA or approved
equivalent. (USA/ European manufactured)
30
Sub-Total: 30
`
- 7 - | P a g e
2. General Experience
Credit Marks for experience shall be awarded on the basis of following
qualifications:
Sr. No. Description Maximum
Points
i) Projects of similar nature and complexity completed over
last 5 years.(4 Marks Against Each Project)
No marks will be awarded If Purchase Orders, completion
certificates and Performance Certificates not attached
(At least 02 Projects are mandatory require)
20
ii) Projects of similar nature and complexity in hand. (2 Marks
Against Each Project)
No marks will be awarded If Purchase Orders/Award
Letters not attached
15
Sub-Total: 35
3. Personnel Capabilities
Credit Marks shall be awarded under this category using the following criteria:
Sr. No. Description Maximum
Points
i) Electrical Engineer, Must be graduate in Electrical
engineering with minimum 10 years experience in relevant field
(01 No’s)
3
ii) Supervisor Electronics, DAE Electronics with minimum 10-
15 years experiencein relevant field. (01 No’s) 2
iii) Supervisor Electrical, DAE Electrical with minimum 10-15
years experiencein relevant field. (01 No’s) 2
iv) Electrician, DAE Electrical with minimum 5-10years
experiencein relevant field(01 No’s) 1
Sub-Total: 8
`
- 8 - | P a g e
Note:-For Engineers and Staff, Marks will be as under;
i. Qualification – 20%
ii. Experience – 70%
iii. Association – 10%(Minimum 1 year association with this Firm)
4. Equipment Capabilities
Credit Marks shall be granted on the basis of the following criteria for various kinds
of equipment relevant for the Project:
Sr.
No. Equipment Type
Maximum
Marks
1. Digital Multi meter 1
2. Insulation Tester 1
3. Tool Kit 2
4. Battery Tester 1
5. Hammer Drill Machine 1
6. Electrician Tool Box 1
7. Phase Sequence Meter 1
8. Earth Tester 1
9. Battery Load tester 2
10. Earth Resistance Tester 1
Sub-Total 12
5. General Requirement
Credit Marks shall be granted on the basis of the following criteria for various kinds
of documents relevant for the Project:
Sr. No. Description Maximum
Marks
i) Registration with FBR for Income & Sale Tax.(1 Marks for Income Tax
Certificate and 1 Marks for Sale tax Certificate)
2
ii) Dealer Ship/ Authorized Firm Certificate 3
Sub-Total 5
`
- 9 - | P a g e
6. Financial Soundness
Marks shall be awarded under this category using the following criteria:
Sr. no. Description Maximum
Marks
i) Working Capital in last three years 4
ii) Bank statement in last three years 3
iii) Audit report of last three years 3
Sub-Total 10
`
- 10 - | P a g e
EVALUATION/SHORTLISTING CRITERIA FOR TECHNICAL
QUALIFICATION
Following criteria (Mandatory) required for short listing of firm/company:
- Must be registered with FBR regarding income tax and sale tax.
- Detail of organization with office address and similar experience record.
- List of Key Personnel/Staff available along with their experience.
- List of Engineering Staff with the experience.
- Product Detail.
- Complete details of similar projects (Installation of Online UPS Similar or above
capacity required) executed during the last 5 years.(At least 2 No’s same
nature projects Mandatory executed)
- Complete details of similar projects (Installation of Online UPS) in hand.
- List of Equipment Capabilities of the firm.
- If any firm already worked with PIEDMC then performance certificate issued by
PIEDMC is to be attached with Technical Proposal.
- Certificate to the effect that the applicant is not involved in litigation with any
department on Stamp Paper worth Rs.100/-/- or above
- Undertaking on Rs.100/- Stamp paper that company has never been
Black listed by any department. Failure to provide this undertaking will
result into REJECTION of the prequalification application.
`
- 11 - | P a g e
Table of Forms
1. CONTRACT AGREEMENT
`
- 12 - | P a g e
Contract Agreement
[The successful Bidder shall fill in this form in accordance with the instructions indicated]
THIS CONTRACT AGREEMENT is made
the [ insert: number ] day of [ insert: month ], [ insert: year ].
BETWEEN
(1) Punjab Industrial Estates Development Management Company, a [ insert
description of type of legal entity, for example, an agency of the Ministry of ....
of the Government of Pakistan, or corporation incorporated under the laws of
Pakistan and having its principal place of business at Commercial Area
(North) Sundar Industrial Estate Raiwind Road Lahore (hereinafter called “the
Employer”), and
(2) [Insert name of Supplier], a corporation incorporated under the laws of
[Insert: country of Supplier] and having its principal place of business at [insert:
address of Supplier ] (hereinafter called “the Supplier”).
WHEREAS the Purchaser invited bids for certain Goods and ancillary services, viz., [insert
brief description of Goods and Services] and has accepted a Bid by the Supplier for the
supply of those Goods and Services in the sum of [insert Contract Price in words and
figures, expressed in the Contract currency (is)] (hereinafter called “the Contract Price”).
NOW THIS AGREEMENT WITNESSETH AS FOLLOWS:
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall constitute the Contract between the Purchaser and the
Supplier, and each shall be read and construed as an integral part of the Contract:
(a) This Contract Agreement
(b) General Conditions of Contract
(c) Technical Requirements (including Schedule of Requirements and Technical Specifications)
(d) The Supplier’s Bid and original Price Schedules
(e) The Purchaser’s Notification of Award
`
- 13 - | P a g e
3. This Contract shall prevail over all other Contract documents. In the event of any
discrepancy or inconsistency within the Contract documents, then the documents shall
prevail in the order listed above.
4. In consideration of the payments to be made by the Purchaser to the Supplier as
hereinafter mentioned, the Supplier hereby covenants with the Purchaser to provide
the Goods and Services and to remedy defects therein in conformity in all respects with
the provisions of the Contract.
5. The Purchaser hereby covenants to pay the Supplier in consideration of the provision
of the Goods and Services and the remedying of defects therein, the Contract Price or
such other sum as may become payable under the provisions of the Contract at the
times and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of [insert the name of the Contract governing law country] on the
day, month and year indicated above.
For and on behalf of the Purchaser
Signed: [insert signature]
in the capacity of [ insert title or other appropriate designation ]
in the presence of [insert identification of official witness]
For and on behalf of the Supplier
Signed: [insert signature of authorized representative(s) of the Supplier]
in the capacity of [ insert title or other appropriate designation ]
in the presence of [ insert identification of official witness]
`
- 14 - | P a g e
THE TECHNICAL SPECIFICATION
`
- 15 - | P a g e
10 KVA ONLINE UPS ALONG WITH ADDITIONAL 10KVABATTERY PACK
10.0 KVA online Ups
UPS 10.0KVA online UPS
Output Output Power Capacity 10.0 KVA,
Output voltage 230V, Output voltage distortion 2%
Output frequency (sync to mains) 50/60Hz +/-3HZ
Output Voltage 220, 240 load
Input Normal input voltage 230V, 400V 3PH
Input frequency 40-70 HZ (auto Sensing)
Input voltage 220, 240, 380, 415
Brand Emerson USA, APC by Schneider USA or approved
Equivalent
Built in Battery 12v 8Amps, 32nos (Back up Time 11.5 min / 3.8 min)
Additional Battery Pack 28/11.6 Minutes Backup Time
`
- 16 - | P a g e
General Conditions of Contract
Table of Contents
1. DEFINITIONS .......................................................................................................... 17
2. CONTRACT DOCUMENTS .................................................................................... 18
3. CORRUPT AND FRAUDULENT PRACTICES ....................................................... 18
4. INTERPRETATION ................................................................................................. 18
5. JOINT VENTURE, CONSORTIUM OR ASSOCIATION .......................................... 19
6. ELIGIBILITY............................................................................................................ 19
7. GOVERNING LAW ................................................................................................. 19
8. DELIVERY .............................................................................................................. 20
9. SUPPLIER’S RESPONSIBILITIES ......................................................................... 20
10. TERMS OF PAYMENT ........................................................................................... 20
11. TAXES AND DUTIES .............................................................................................. 20
12. PERFORMANCE SECURITY ................................................................................. 20
13. SPECIFICATIONS AND STANDARDS ................................................................... 20
14. PACKING AND DOCUMENTS ............................................................................... 21
15. TRANSPORTATION ............................................................................................... 21
16. INSPECTIONS AND TESTS ................................................................................... 21
17. LIQUIDATED DAMAGES ....................................................................................... 21
18. WARRANTY ........................................................................................................... 21
19. EXTENSIONS OF TIME .......................................................................................... 22
`
- 17 - | P a g e
Definitions
The following words and expressions shall have the
meanings hereby assigned to them:
“Contract” means the Agreement entered into between
the Purchaser and the Supplier, together with the
Contract Documents referred to therein, including all
attachments, appendices, schedules and all documents
incorporated by reference therein.
“Contract Documents” means the documents listed in
the Agreement, including any amendments thereto.
“Contract Price” means the price payable to the Supplier
as specified in the Agreement, subject to such additions
and adjustments thereto or deductions there from, as
may be made pursuant to the Contract.
“Day” means calendar day.
“Delivery” means the transfer of the Goods from the
Supplier to the Purchaser in accordance with the terms
and conditions set forth in the Contract.
“Completion” means the fulfillment of the supply of
Goods by the Supplier in accordance with the terms and
conditions set forth in the Contract.
“Eligible Countries” means the countries as per Brand
Description.
“GCC” mean the General Conditions of Contract.
“Goods” means all of the commodities, raw material,
machinery and equipment, and/or other materials that the
Supplier is required to supply to the Purchaser under the
Contract.
“Purchaser’s Country” is the country specified in the
Particular Conditions of Contract (PCC).
The “Purchaser” means the Employer who is the entity
purchasing the Goods, as specified in the PCC, and
includes the legal successors or assigns of the Purchaser.
“PCC” means the Particular Conditions of Contract.
“Subcontractor” means any natural person, private or
`
- 18 - | P a g e
government entity or a combination of the above, including
its legal successors or permitted assigns, to whom any part
of the Goods to be supplied is subcontracted by the
Supplier.
“Supplier” means the natural person, private or government
entity, or a combination of the above, whose bid to
perform the Contract has been accepted by the
Purchaser and is named as such in the Agreement, and
includes the legal successors or permitted assigns of the
Supplier.
“The Site,” where applicable, means the place named in the PCC.
Contract
Document
Subject to the order of precedence set forth in the
Agreement,
All documents forming the Contract (and all parts thereof)
are intended to be correlative, complementary, and
mutually explanatory.
Corrupt and
Fraudulent
Practices
For the purposes of this provision, the term “Corrupt
and Fraudulent Practices” includes the offering, giving,
receiving, or soliciting of any thing of value to influence
the action of a public official or the supplier or
contractor in the procurement process or in contract
execution to the detriment of the procuring agencies; or
misrepresentation of facts in order to influence a
procurement process or the execution of a contract,
collusive practices among bidders (prior to or after bid
submission) designed to establish bid prices at artificial,
non-competitive levels and to deprive the procuring
agencies of the benefits of free and open competition
and any request for, or solicitation of anything of value
by any public official in the course of the exercise of his
duty.
The Purchaser will reject a proposal for award if it
determines that the bidder recommended for award has,
directly or through an agent, engaged in corrupt and
fraudulent practices in competing for the Contract.
The Supplier shall permit the Purchaser to inspect the
Supplier’s accounts and records relating to the
performance of the Supplier and to have them audited
by auditors appointed by the Purchaser, if so required by
the Purchaser.
`
- 19 - | P a g e
Interpretation If the context so requires it, singular means plural and
vice versa where the context requires.
Entire Agreement
The Contract constitutes the entire agreement between
the Purchaser and the Supplier and supersedes all
communications, negotiations and agreements (whether
written or oral) of parties with respect thereto made
prior to the date of Contract.
Amendment
No amendment or other variation of the Contract shall
be valid unless it is in writing, is dated, expressly refers
to the Contract, and is signed by a duly authorized
representative of each party thereto.
No waiver
no relaxation, forbearance, delay, or indulgence by
either party in enforcing any of the terms and conditions
of the Contract or the granting of time by either party to
the other shall prejudice, affect, or restrict the rights of
that party under the Contract, neither shall any waiver
by either party of any breach of Contract operate as
waiver of any subsequent or continuing breach of
Contract.
Any waiver of a party’s rights, powers, or remedies
under the Contract must be in writing, dated, and signed
by an authorized representative of the party granting
such waiver, and must specify the right and the extent to
which it is being waived.
Joint Venture,
Consortium
If the Supplier is joint venture, consortium, or
association, all of the parties shall be jointly and
severally liable to the Purchaser for the fulfillment of
the provisions of the Contract and shall designate one
party to act as a leader with authority to bind the joint
venture, consortium, or association. The composition or
the constitution of the joint venture, consortium, or
association shall not be altered without the prior
permission of the Purchaser.
Eligibility The Supplier and its Subcontractors shall have the
nationality of an Eligible Country in case of
International Competitive Bidding but only of Pakistan
in case National Competitive Bidding. A Supplier or
Subcontractor shall be deemed to have the nationality of
a country if it is a citizen or constituted or incorporated,
`
- 20 - | P a g e
and operates in conformity with the provisions of the
laws of that country.
All Goods to be supplied under the Contract and
financed by the Purchaser shall have their origin in
Eligible Countries. For the purpose of this Clause,
origin means the country where the goods have been
grown, mined, cultivated, produced, manufactured, or
processed; or through manufacture, processing, or
assembly.
Governing Law The Contract shall be governed by and interpreted in
accordance with the laws of the Purchaser’s country.
Delivery The Delivery of the Goods shall be in accordance as
specified in the “Price and Delivery Schedule”.
Supplier’s
Responsibilities
The Supplier shall supply all the Goods as mentioned in
the “Technical Specification” of Contract Document.
Terms of Payment The Contract Price shall be paid as specified in the
“Payment Schedule”.
The Supplier’s request for payment shall be made to the
Purchaser in writing, accompanied by invoices
describing, as appropriate, the Goods delivered by the
documents submitted upon fulfillment of all the
obligations stipulated in the Contract.
Payments shall be made promptly by the Purchaser, no
later than sixty (60) days after submission of an invoice
or request for payment by the Supplier, and the
Purchaser has accepted it.
Taxes and Duties For Goods supplied from outside the Purchaser’s
Country, the Supplier shall be entirely responsible for
all taxes, stamp duties, license fees, and other such
levies imposed outside the Purchaser’s Country.
For Goods supplied from within the Purchaser’s
Country, the Supplier shall be entirely responsible for
all taxes, duties, license fees, etc., incurred until
delivery of the contracted Goods to the Purchaser.
`
- 21 - | P a g e
Specifications and
Standards
Technical Specifications and Drawings
The Supplier shall ensure that the Goods comply with
the technical specifications and other provisions of the
Contract.
The Supplier shall be entitled to disclaim responsibility
for any design, data, drawing, specification or other
document, or any modification thereof provided or
designed by or on behalf of the Purchaser, by giving a
notice of such disclaimer to the Purchaser.
The Goods supplied under this Contract shall conform
to the standards mentioned in the Schedules to Bid and,
when no applicable standard is mentioned, the standard
shall be equivalent or superior to the official standards
whose application is appropriate to the country of origin
of the Goods.
Packing The Supplier shall provide such packing of the Goods
as is required to prevent their damage during shipment
to their final destination.
Transportation Specified in “the Scope of work”.
Inspections and
Tests
The Supplier shall at its own expense and at no cost to
the Purchaser carry out all such tests and /or inspections
of the Goods as are specified in “the Scope of work”.
Purchaser or its designated representative shall be
entitled to attend the tests and/or inspections provided
that the Supplier bear traveling expense of purchaser for
testing and inspection.
Whenever the Supplier is ready to carry out any such
test and inspection, it shall give a reasonable advance
notice, including the place and time, to the Purchaser.
The Supplier shall obtain from any relevant third party
or manufacturer any necessary permission or consent to
enable the Purchaser or its designated representative to
attend the test and/or inspection.
The Supplier shall provide the Purchaser with a report
of the results of any such test and/or inspection.
The Purchaser may reject any Goods or any part thereof
that fail to pass any test and/or inspection or do not
conform to the specifications. The Supplier shall either
rectify or replace such rejected Goods or parts thereof or
make alterations necessary to meet the specifications at
`
- 22 - | P a g e
no cost to the Purchaser, and shall repeat the test and/or
inspection, at no cost to the Purchaser, upon giving a
notice.
Liquidated
Damages
If the Supplier fails to deliver any or all of the Goods
within the period specified in the Term and Condition,
the Purchaser may deduct amount from the Contract
Price, as liquidated damages, a sum equivalent to the
percentage specified in the “Term and Conditions”, up
to a maximum deduction of the percentage specified in
the “Term and conditions”. Once the maximum is
reached, the Purchaser may terminate the Contract with
Supplier.
Warranty The Supplier warrants that all the Goods are new &
unused.
The Supplier further warrants that the Goods shall be
free from defects arising from any act or error of the
Supplier or arising from design, materials, and
workmanship, under normal use in the conditions
prevailing in the country of final destination.
The warranty shall remain valid for Thirty six (36)
months after the Goods, or any portion thereof as the
case may be, have been delivered to and accepted at the
final destination indicated in the Scope of work.
The Purchaser shall give Notice to the Supplier stating
the nature of any such defects together with all available
evidence thereof, promptly following the discovery
thereof. The Purchaser shall afford all reasonable
opportunity for the Supplier to inspect such defects.
Upon receipt of such Notice, the Supplier shall, within
the 30 Days, expeditiously repair or replace the
defective Goods or parts thereof, at no cost to the
Purchaser.
If having been notified, the Supplier fails to remedy the
defect within the 30 Days; the Purchaser may proceed to
take within a reasonable period such remedial action as
may be necessary, at the Supplier’s risk and expense
and without prejudice to any other rights which the
Purchaser may have against the Supplier under the
Contract.
Extensions of The Supplier shall promptly notify the Purchaser in
`
- 23 - | P a g e
Time writing of the delay, it’s likely duration, and its cause.
As soon as practicable after receipt of the Supplier’s
notice, the Purchaser shall evaluate the situation and
may at its discretion extend the Supplier’s time for
performance, in which case the extension shall be
ratified by the parties by amendment of the Contract.
A delay by the Supplier in the performance of its
Delivery and Completion obligations shall render the
Supplier liable to the imposition of liquidated damages
unless an extension of time is agreed by purchaser.