report on midterm progress review on … · 2019. 3. 7. · report on midterm progress review on...
TRANSCRIPT
REPORT ON
MIDTERM PROGRESS REVIEW ON
IMPLEMENTATION OF STRATEGIC DEVELOPMENT
PLAN 2011-15
Review Timeframe
January 2011-June 2013
PLANNING, MONITORING, EVALUATION AND REPOTING (PMER)
SECTION
PLANNING AND DEVELOPMENT DEPARTMENT
BANGLADESH RED CRESCENT SOCIETY (BDRCS)
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
2
Study Design, Implementation and Report Preparation
Md. Kamrul Hasan Sr. PMER Officer,
PMER Section, BDRCS
Afroza Sultana PMER Officer,
PMER Section, BDRCS
Md. Sazzad Ansari
PMER Officer, Organizational Development, IFRC, BD Delegation
Document Review
Md. Matiur Rahman
Director, Planning & Development Department, BDRCS
Moa Chenon
PMER Delegate IFRC, BD Delegation
Md. Adith Shah Durjoy
Manager, Organizational Development, IFRC, BD Delegation
Data Collection Team
Sl. No Name Sl. No. Name
1 Khandaker A. K. M. Iqbal 14 Halima Tarafader 2 Md. Afsar Uddin Siddique 15 Abul Kalam Azad 3 Rezina Halim 16 Ripan Das 4 Bashir Ahmed 17 Mst. Reksona Khatun 5 Md. Jiaul Ahasan 18 Mohammad Keramot Ali 6 Sayma Ferdowsy 19 Mohammad Kamrul Hasan 7 Sultana Nelofar Banu 20 Modasher Ahmed 8 Joynal Abedin 21 A K M Mohsin 9 Abdul Karim 22 Md. Emranul Hassan 10 Mizanur Rahman 23 Farook Rahman 11 Khonduker Enayetullah Akram 24 Fazlur Rahman Khan 12 Farzana Akther 25 Md. Kamrul Hasan 13 Afroza Sultana 26 Md. Sazzad Ansari 27 Mohammad Shahjahan (Saju)
Financial Support: Canadian Red Cross
Copyright@BDRCS, 684-686, Red Crescent Sarak, Bara Moghbazar, Dhaka, Bangladesh
All rights reserved. Any part of this document may be reproduced, stored in a database
or retrieval system, or transmitted in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, with proper reference.
Reference: Bangladesh Red Crescent Society. (2014). Midterm Progress Review of
Implementation of Strategic Development Plan 2011-15. Dhaka, Bangladesh: Author.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
3
Source: DRM Department, BDRCS, 2013
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
4
Acknowledgement
First of all PMER Section would like to thank the project communities of Rangpur and
Kurigram district for their well understanding and giving us time to conduct FGDs.
Unit/Branch representatives of Cox’s Bazar, Khulna, Jessore, Rangpur, Kirigram,
Lalmonirhat and respective volunteers were so helpful which made our work more
comfortable and smooth. Technical and non technical staff of Khulna and Jessore MCH
centres was generous to provide required information during KII and queries.
We want to express our sincere thanks to the representatives of Departments, Section,
Programme, and Projects of BDRCS and specifically the reporting focal persons and DRM
PMER Officer for their enormous cooperation and coordination with us regarding data
collection and SWOT Analysis.
Our honest appreciation goes to the Director of Planning and Development of BDRCS and
OD Manager, IFRC for their continuous support and inspiration for accomplishing this
pioneer task in this National Society. And also PMER Delegate for her knowledgeable
feedback on various parts of the process.
We are also thankful to IFRC, ICRC and PNSs for their spontaneous participation in
primary data collection process and in SWOT analysis. More specifically, the Canadian
Red Cross (CRC) for their long lasting support to OD initiatives in BDRCS.
Lastly, we are grateful to the Honourable Chairman and Secretary General of BDRCS for
whom the Midterm Review Report came to light.
Progress Review Team
Planning, Monitoring, Evaluation and Reporting (PMER) Section
Bangladesh Red Crescent Society
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
5
Abbreviation
ANC Antenatal Care
AGM Annual General Meeting
BDRCS Bangladesh Red Crescent Society
BD Bangladesh
BDT Bangladeshi Taka
BOM Branch Operational Manual
BRAC Bangladesh Rural Advancement Committee
BRC British Red Cross
CoC Code of Conduct
CBHFA Community Based Health and First Aid
CDRT Community Disaster Response Team
CHT Chittagong Hill Tracts
CDI Community Development Initiative
CBDRR Community Based Disaster Risk Reduction
CCA Climate Change Adaptation
CBO Community Based Organization
CPP Cyclone Preparedness Programme
CHF Swiss Franc
CRC Canadian Red Cross
DREF Disaster Response Emergency Fund
DP Disaster Preparedness
DRR Disaster Risk Reduction
DM Disaster Management
DD Digital Divide
EPI Extended Programme of Immunization
ECHO European Commission's Office for Humanitarian Aid and Civil Protection
FA First Aid
FGD Focus Group Discussion
FACT Field Assessment Coordination Team
Govt Government
GRC German Red Cross
HR Human Resources
HRC Hong Kong Red Cross
ICT Information and Communication Technology
IEC Information Education and Communication
IFRC International Federation of Red Cross and Red Crescent Societies
ICRC International Committee of the Red Cross
IGA Income Generating Activity
ID Identity Card
JD Job Description
KII Key Informant Interview
MCH Mother and Child Health Care
MDG Millennium Development Goal
NS National Society
NHQ National Head Quarter
NDRT National Disaster Response Team
NDWRT National Disaster WATSAN Team
OD Organizational Development
OCAC Organizational Capacity Assessment and Certification
PHiE Primary Health in Emergency
PASSA Participatory Approach for Safe Shelter Awareness
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
6
PHAST Participatory Hygiene and Sanitation Transformation
PNC Postnatal Care
PNS Partner national Society
P&D Planning and Development department
PMER Planning Monitoring Evaluation and Reporting
RCRC Red Cross and Red Crescent
RFL Restoring Family Linkage
RMS Recourse Management System
RDRT Regional Disaster Response team
RCY Red Crescent Youth
RCM Red Crescent Message
SP Strategic Development plan
SOP Standard Operating Procedure
SWOT Strength Weakness Opportunity and Threat
SPSS Satirical Package for the Social Sciences
SAR Search and Rescue
ToT Training of Trainers
UDRR Urban Disaster Risk Reduction
UDRT Urban Disaster Response Team
UEC Unit Executive Committee
ULO Unit Level Officer
V2R Vulnerability to Resilience
WASH Water Sanitation and Hygiene
YABC Youth as Agent of Behavioural Change
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
7
Table of Contents
Acknowledgement .................................................................................................. 4
Abbreviation .......................................................................................................... 5
List of figures ......................................................................................................... 9
List of tables ........................................................................................................ 11
List of boxes ........................................................................................................ 11
Executive Summary ........................................................................................... 12
Chapter One: Introduction ................................................................................ 15
1.1 Organizational Background ........................................................................... 15
1.2 Strategic Development Plan 2011-15, BDRCS ................................................. 15
1.3 Objective of the progress review ................................................................... 16
1.4 Justification and Scope ................................................................................. 16
1.5 Limitations .................................................................................................. 16
1.6 Outline of the report .................................................................................... 17
Chapter Two: Methodology ................................................................................ 18
2.1 Conceptualization ........................................................................................ 18
2.2 Sampling design .......................................................................................... 18
2.3 Data collection ............................................................................................ 19
2.3.1 Primary data collection ........................................................................... 19
2.3.1.1 Survey ........................................................................................... 19
2.3.1.2 Focus Group Discussion (FGD) ........................................................... 20
2.3.1.3 Key Informant Interviews (KII) .......................................................... 20
2.3.1.4 Interview ........................................................................................ 20
2.3.2 Secondary data collection ....................................................................... 20
2.4 Strength, Weakness, Opportunity and Threat (SWOT) Analysis .......................... 20
2.5 Data compilation, analysis and reporting ........................................................ 21
2.6 Findings sharing workshop ............................................................................ 21
Chapter Three: Progress Review Findings ......................................................... 23
3.1 Core Programme: Organizational Development ............................................... 23
3.1.1 Planning and Development interventions .................................................. 23
3.1.1.1 Enactment of New Legal Base ............................................................ 23
3.1.1.2 Formulation and implementation of Strategic Development Plan (SP) 2011-
15 ............................................................................................................. 24
3.1.1.4 Planning, Monitoring, Evaluation and Reporting (PMER) initiative ........... 24
3.1.1.5 Information and Communication Technology (ICT) strengthening .......... 24
3.1.2 Conduction of Organizational Capacity Assessment and Certification (OCAC) . 25
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
8
3.1.3 Strengthening of Unit/Branch capacity ...................................................... 25
3.1.4 Fund raising and resource mobilization initiatives ....................................... 25
3.1.5 Staff management and administration ...................................................... 27
3.1.6 Capacity building of volunteers for effective service delivery ....................... 27
3.1.7 Initiatives to protect miss use of RC Emblem ............................................. 29
3.1.8 Human resource development initiatives ................................................... 29
3.1.8.1 Training for staff capacity building ...................................................... 30
3.1.8.2 Revenue collection through commercial trainings ................................. 31
3.2 Core Programme: Disaster Management (DM) ................................................. 33
3.2.1 Community mobilisation toward building resilience ..................................... 33
3.2.2 Disaster response tool: Formation and Functionality ................................... 34
3.2.2.1 National Disaster Response Team (NDRT) ........................................... 34
3.2.2.3 Community Disaster Response Team (CDRT) ....................................... 36
3.2.2.4 National Disaster WATSAN Response Team ......................................... 36
3.2.3 Community resilience through programmes .............................................. 37
3.2.4 Status of Standing Operating Procedure (SoP) and Contingency Plan ........... 37
3.2.5 Capacity Building Initiatives for staff and volunteers................................... 38
3.2.5.1 Search & Rescue Issue ..................................................................... 38
3.2.5.2 First Aid and service Delivery ............................................................ 38
3.2.6 Integration of Water, Sanitation and Hygiene (WASH) in Programmes .......... 40
3.2.7 Disaster response: Effectiveness, Management and way forward ................. 41
3.3 Core Programme: Health .............................................................................. 47
3.3.1 Service provided through MCH services .................................................... 47
3.3.2 Safe blood services ................................................................................ 50
3.3.3 Primary health services during emergency ................................................ 51
3.3.4 Service delivery through Hospitals ........................................................... 52
3.4 General Understanding on Strategic Development Plan 2011-15 ........................ 53
3.4.1 Status of hearing about SP 2011-15, BDRCS ............................................. 53
3.4.2 Status of involvement of different groups in SP development ...................... 54
3.4.3 Division where groups provided institutional input/support .......................... 55
3.4.4 Alignment of 4 Years Development Plan with SP 2011-15, BDRCS ................ 58
3.4.5 Recommendation on the SP 2011-15 and its implementation ...................... 59
3.5 Strength, Weakness, Opportunity and Threat (SWOT) Analysis .......................... 59
Chapter Four: Conclusion and Recommendations .............................................. 63
4.1 Organizational Development ......................................................................... 63
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
9
4.2 Disaster Management................................................................................... 64
4.3 Health ........................................................................................................ 66
4.4 The document: SP 2011-15 .......................................................................... 67
5. Annex ............................................................................................................ 68
5.1: Indicators under SP 2011-15 ....................................................................... 68
5.2: Qualitative indicators and checklist of FGD, KII and Interview .......................... 73
5.3: Questionnaire for general understanding of SP 2011-15 .................................. 79
5.4: Secondary data collection tool ...................................................................... 81
5.5 List of reporting focal persons ....................................................................... 82
5.6 Pictures: captures during workshop, meeting, and data collection ...................... 83
List of Figures
Sl. No. Title of the figure Page No.
1.1 Programmatic areas of SP 2011-15, BDRCS 15
2.1 Chronology of the concept development 18 2.2 Flow chart of the Methodology of Mid Term Review of Strategic
Development Plan 2011-15, BDRCS. 22
3.1 Above graph is representing the amount of money collected from donation box
26
3.2 The chart is presenting the information of fund collection from selling
souvenir items
26
3.3 Status on accomplishment of Search & Rescue ToT among the RCY. 28 3.4 Status of conduction of orientation on RCRC Basic and Emblem Campaign
with the Unit/Branch volunteers and officials. 29
3.5 The above figure shows the comparison between plan and achievement of number of First Aid training for Staff capacity building in 2011-2013 (June)
30
3.6 The above figure depicts the comparison between plan and achievement of number of commercial training conducted on Search and Rescue (SAR).
31
3.7 The above figure shows the comparison between plan and achievement of number of commercial training on First Aid conducted by the Training Department.
32
3.8 The above pie chart depicts the comparison between total number of Commercial training and Staff Capacity Building training organized by the
Training Department.
32
3.9 This bar graph represents the status of conduction of awareness raising sessions and beneficiary coverage through preparedness activity
33
3.10 This bar diagram is representing the data of deployment and training status of the NDRT member
34
3.11 The chart showing the deployment status and training status of UDRT
member during 2011~2013
35
3.12 This graph presenting the status of CDRT formation and training conduction of CDRT member
36
3.13 Beneficiary coverage ubder community resilience initatives during 2011 -13 by CDI & CCA project.
37
3.14 Gender perspective in beneficiary coverage 37 3.15 Status of recipient of First Aid services 39
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
10
3.16 Graph shows the comparison of target and achievement of conduction of
First Aid training.
39
3.17 Male-female ration of FA training recipient and FA service recipient 39 3.18 Status of male and female members in First Aid training recipient and First
Aid Service Recipient 40
3.19 Comparison between plan and achievement of conducting awareness raising session on WASH
40
3.20 Comparison between plan and achievement of installation of safe water
sources
41
3.21 Comparison between plan and achievement of number of sanitation system installed
41
3.22 Yearly financial assistance provided to beneficiaries during disaster by the Disaster Response Department of BDRCS.
42
3.23 Flow chart of the response initiative by Disaster Response Department 43 3.24 Number of BDRCS volunteers received RFL training during 2011-13. 44 3.25 Number of Unit/Branch Secretary and ULO received RFL training during
2011-13.
44
3.26 Status of family coverage through RFL services, exchange of RC Message
and distribution of hygiene kits to foreign detainees.
46
3.27 The bar graph is showing the comparative progress status of Antenatal Care
47
3.28 The figure representing yearly basis plan and achievement of Postnatal Care
47
3.29 The Chart is representing the progress status of Non Complicated delivery 48 3.30 The chart presenting beneficiary coverage through EPI and counselling
session
48
3.31 This line graph representing the status of collection and supply of blood bags.
50
3.32 The chart representing the status of blood transfusion for the Thalassemia patients
51
3.33 The figure represents the number of volunteers trained on CBHFA and
Hand Wash.
51
3.34 The above grahp shows the number of outdoor consultation in 2011, 2012 and 2013
52
3.35 The male female ratio in patient coverage. 52 3.36 Number of surgery undertaken conducted in the hospitals 53 3.37 Number of delivery conducted in the hospitals 53 3.38 The figure represents the SP hearing status by the different group of
respondents (N=55)
54
3.39 The figure represents the status of involvement of different group of people in preparing the SP 2011-15 document (N=56).
54
3.40 The figure represents the level of involvement of different group of respondents on different criteria in preparing SP 2011-15, BDRCS (N=22).
55
3.41 The figure represents the status of contribution by different group of respondents in developing Core Areas of SP 2011-15 (N=23).
56
3.42 The figure represents the status of contribution by different group of
respondents in core areas of SP 2011-15 (N=21).
56
3.43 Status of receiving formal orientation on Strategic Development Pan 2011-15 by different group of respondents (N=46).
57
3.44 Status of addressing SP 2011-15 in formulating 4-Year Development Plan
58
3.45 Status of considering SP 2011-15 in formulating 4-Year Development Plan 58 3.46 Status of having hard copy of Strategic Development Plan 2011-15,
BDRCS. 59
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
11
List of Tables
Table No. Title of the table Page No.
2.1 Coverage of Unit/Branches, volunteers and the project areas for progress review and use of different methods for assessing qualitative
indicators.
18
3.1 The table representing the progress status of mock drill, volunteer’s training and meetings conducted with CBOs during 2011 to 2013.
34
3.2 Year wise household coverage and financial assistance provided during
different category of disaster during 2011-13 by the Disaster Response Department.
43
3.3 Status of reviewing provided input before finalization (N=29). 57
3.4 Areas checked in the proposed proposal (N=14) before financial resource mobilization to National Society (NS).
58
List of Boxes
Box No. Title of the box Page No.
3.1 Effective Disaster Response Tool: NDRT, BDRCS 35
3.2 Hearing the Beneficiary: Early Recovery Project, Kurigram 45
3.3 Current modality and way forward of MCH Centre 49
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
12
Executive Summary The report on midterm progress review of implementation of Strategic Development Plan
2011-15 of Bangladesh Red Crescent Society (BDRCS) focuses on the key findings on the
planned interventions under three core programme areas, covering Organizational
Development, Disaster Management and Health, and also put some recommendations for
further improvement. The review considers half way mark of the implementation period
of SP 2011-15 covering 2011 to June 2013. The study findings are the triangulation of
information and data from BDRCS, Its internal stakeholders and project beneficiaries.
Apart from quantitative data collection, qualitative information was also incorporated to
conduct this progress review. The progress review has been completed based on the
results mentioned in the three core programmatic areas under the Strategic Development
Plan 2011-15.
The Organizational Development (OD) of BDRCS is a combination of Administration and
Human Resource, Fundraising, Unit Affairs, Planning and Development, Training,
International Relation and Communication and Youth & Volunteer Department. Several
achievements like endorsement of the Legal base, finalization of Branch Operational
Manual (BOM), formulation of 4-Year development Plan, conduction of Organizational
Capacity Assessment and Certification, (OCAC) have been made in capacity building of
the BDRCS. The new Legal Base has been drafted which was planned to get enacted by
the parliament in the middle of 2013. The formulation of 4- Year Development Plan 2014-
17 of all Departments and Branches, in line with Strategic Development Plan 2011-15,
was not completed within the stipulated timeframe however the document was drafted by
a consultant. For building well-functioning Branches, the BOM was drafted by a
consultancy firm under the supervision of P&D Department of BDRCS. Development of
new organogram and job descriptions for all staff didn’t happen as per plan but it was
initiated during the reporting period. Moreover, the process of Organizational Capacity
Assessment and Certification (OCAC) was planned twice during the evaluation period but
it did not happen due to country wide political instability.
PMER and ICT Sections were functional with limited activities throughout the review
timeframe. A total of 15 Monthly Activity Reports (MAR), compiling an average of 15
Departments, Programs and Project updates’ were prepared and published in BDRCS
Website. Apart from these, ICT logistics were provided to Units and NHQ of BDRCS under
Digital Divide (DD) Project by ICT Section under the supervision of P&D Department.
Fund raising through selling souvenir items and donation boxes contributed to BDRCS
revenue and also in emergency response operation. Besides, collection of rent from
different sources was about 90% against the plan. Moreover, Training Department
contributed in BDRCS revenue through conducting commercial trainings like First Aid,
Search & Rescue and Fire Safety to other institutions and organizations.
Disaster response and management interventions were accomplished through several
programmes and projects like Climate Change Adaptation (CCA), Community Based
Disaster Risk Reduction (CBDRR), Vulnerability to Resilience (V2R), Urban Disaster Risk
Reduction (UDRR) and Community Development Initiative (CDI) by three Departments of
BDRCS: Disaster Risk Reduction, Disaster Response and Tracing. Community mobilization
towards building resilience community and humanitarian assistance were the key areas
where BDRCS put its contribution during the evaluation time frame. Awareness raising
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
13
session, community consultation, meeting and mock drills were conducted in the targeted
communities for building resilience through sharing necessary information and
demonstrations by the trained volunteers and staff. Average achievement was slightly
more than target (107.7%) and 179980 community people were covered through
mobilization initiatives. Besides, income generating support like tailoring, homestead
gardening, handicraft, livestock rearing, carpenter and cash grants were provided to
4552 families to contribute to their sustainability. In depth analysis found that the
average achievement of these initiatives was 100% and female beneficiaries (57%) were
prioritized in terms of providing training and income generating support over male
(43%).
Simultaneously, disaster response operations were undertaken in major natural and man-
made calamities in Bangladesh during 2011-13 like South-East Flood, Flood Early
Recovery, Water Logging and Cold Wave. The operations were led by Disaster Response
Department, with the support of other Departments and Branches. Moreover, globally
recognized response tools like NDRT, NDWRT, UDRT, RDRT, CDRT, warehouses,
contingency plan for cyclone and floods were effectively utilized in conducting the
aforementioned humanitarian responses. Besides, Restoring family linkage (RFL)
interventions in disaster and related events was an unique approach in every
humanitarian assistance conducted by BDRCS. Moreover, WASH initiatives like
installation and reparation of safe water sources, sanitation systems and awareness
raising sessions were also embedded in disaster response and community development
projects.
Health interventions of the BDRCS encompass the Maternal and Child Health (MCH)
centres, the Blood Programme and the hospitals. The 56 community based 56 MCH
centres of the Health Department delivered primary health care services to the people in
remote rural areas. Sustainability of the MCH Centre is one of the main targets of BDRCS
Health Department and 32 MCH out of 56 are now financially sustainable. A significant
coverage of ANC, PNC, non complicated delivery and surgery was found against the plan
in MCH and hospitals during evaluation period. A total of 260583 beneficiaries received
health care and health message through MCH centres.
Blood collection and supply is one of the main activities of BDRCS blood banks under the
Blood programme. Average rate of blood bag supply and distribution was found as
85.15% which is contributing meeting our national blood demand. However, the Health
Department couldn’t expand blood bank as per plan although there was an increasing
demand of safe blood supply across the country.
Moreover, capacity building training on different issues like First Aid (FA), Search &
Rescue (SAR), Leadership, Fire Safety, Safe Delivery and other relevant technical & non
technical issues were regularly conducted for the staff and volunteers of BDRCS. Besides,
some of the trainings were also conducted by specific Department of BDRCS with
coordination of Training department.
The study found areas where the core programmes of the BDRCS where there still is
room for improvements which will ultimately contribute towards achieving the status of a
well-functioning National Society. The overall areas are mentioned below:
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
14
There should be a clear alignment between strategic and operational plans. It is
recommended to formulate operational plans for a period of no more than 2 years so
that the respective departments, programmes, project will have sufficient scopes to
accomplish the planned interventions effectively, track the progress and also act upon
the drawbacks explored during implementation.
Legal base, Branch Operation Manual (BOM), Resource mobilization guideline, human
resource and procurement policy for BDRCS need to be in place to create a common
understanding and also to provide a standard guideline to accomplish planned
activities.
Organize more capacity building training, orientation on Basic Principle and Code of
Conduct of the RCRC Movement for the staff and volunteers for effective service
delivery and maintaining transparency and accountability.
School co-curriculum activities need to be expanded through designing more
programs in order to ensure effective utilization of the collected money from school
and college students.
Emphasis should be given on program monitoring and supervision in order to ensure
quality of services, accountability and transparency at all level.
There is a need to develop sustainability and phase out plan for the MCH centres for
ensuring sustainable health service delivery to the community people.
More initiatives are required to increase the number of non remunerated blood donors
across the country and number of blood bank need to be increased for providing more
contribution to national safe blood demand.
The shortcomings found in the SP 2011-15 document need to be carefully considered
during formulating next version of this document. In this connection, an internal
resource pool could be developed through effective training.
A comprehensive Monitoring & Evaluation plan needs to be developed for each
department, programme and project of BDRCS for tracking the progress, improving
the quality of services and also ensuring transparency.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
15
Organizarional Development
Health Disaster
Management
Figure 1.1: Programmatic areas of SP 2011-15, BDRCS
Chapter One: Introduction
1.1 Organizational Background
The Bangladesh Red Cross Society (BDRCS) was constituted on 31 March, 1973 by the
President's Order No.26 of 1973 with retrospective effect from the 16th December 1971.
The Society was recognized by International Committee of the Red Cross (ICRC) on 20th
September, 1973 and admitted to the International Federation of Red Cross and Red
Crescent Societies (IFRC) on 2nd November, 1973. The name and emblem were changed
from Red Cross to Red Crescent on 4th April 1988 vide Act 25 of 1988. The BDRCS has 68
Units. A Unit is constituted in each district and in the Metropolitan Cities of Dhaka,
Chittagong, Rajshahi & Khulna. Besides, it has 17 Departments to implement various
programme and projects across the country.
Vision
The Vision of the Society is to become an effective and efficient humanitarian
organization in Bangladesh by ‘doing more, doing better and reaching further’.
Mission
The Mission of the BDRCS is to prevent and reduce human sufferings and saves lives of
the vulnerable people.
1.2 Strategic Development Plan 2011-15,
BDRCS
Strategic Development Plan 2011-15 is the 4th
Strategic Plan of Bangladesh Red Crescent Society
which has been formulated as per the result of review
of 3rd Strategic Plan 2005-2008. A consultancy firm
named Development Support Link had been contracted
to carry out the review who submitted a review report
on 30 August, 2011 to the Society. Later on, the
review report was circulated among Departmental
Heads, IFRC, ICRC and PNSs for their comment.
Subsequently the OD Core Group took initiative for
formulating 4th Strategic Development Plan of BDRCS in line with the recommendations of
the review report. The SP 2011-15 was approved in 40th Annual General Meeting in 2012.
The Strategic Plan 2011-15 has stated the vision and mission of BDRCS and 5 strategic
goals of the Society for 2011-2015 which are:
To increase the capacity and efficiency of the BDRCS in emergency preparedness,
emergency response and recovery
To improve the quality and availability of health services and save lives of the
people in need
Organizational Development for a well-functioning National Society and effective
service delivery
To enhance community resilience through sustainable development
To promote the culture of non-violence and peace through effective Humanitarian
Diplomacy and advocacy
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
16
The strategic development plan 2011-15 has also identified six strategies to implement
planned activities to attain the strategic goals.
1.3 Objective of the progress review
The midterm progress review of Strategic Development Plan 2011-15, BDRCS was
initiated to determine the following objectives:
To assess the progress of the planned interventions designed under each of the five
Strategic Goals formulated in the Strategic Development Plan 2011-15, BDRCS
To assess general understanding on SP 2011-15 of the BDRCS management that are
leading different departments/ programme/ projects and also internal stakeholders of
BDRCS who are continuously supporting to implement different interventions.
To explore the strength, weakness, opportunity and threat in accomplishing the
planned initiatives of Strategic Development Plan 2011-15
To identify the challenges in implementing Strategic Development Plan 2011-15 and
propose corrective measures in future programming.
1.4 Justification and Scope
The BDRCS management wanted to know the progress of the activities planned for two
and a half years in the implementation period of the SP 2011-2015. Besides, the Planning
and Development (P&D) Department was also committed to conduct the midterm review
of the plan. In this connection, the progress review was initiated and carried out by the
PMER Section of the Department.
In addition, this mid-term review process is the first internal process of major scale
carried out by the BDRCS. It was carried out with the aim to create a positive
understanding and motivation among the BDRCS management and Movement partners to
undertake similar initiatives in the future. The mid-term review process has capacitated
the PMER staff to carry out similar reviews and evaluations of the BDRCS. of the process
has also entailed capacity building of BDRCS staff, through the appointment of BDRCS
reporting focal persons in the review process. The reporting focal persons have been
actively involved in the process with a view to build their technical skills and motivate
them to support other initiatives of this kind.
1.5 Limitations
The limitations of the midterm progress review of the Strategic Development Plan 2011-
15 are:
The progress review considered sample basis Unit/Branch and projects (accomplished
& ongoing) for collecting required qualitative and quantitative data on various
indicators. It couldn’t cover all the Units/Branches and project due to time and budget
constraint
The quantitative data collection from relevant Departments, Sections, Programme and
Projects consumed longer period of time than expected (after finalizing the indicators
and orientation of data entry tool)
There was challenge to manage data on ‘achievement’ against ‘plan’ in some cases
(except ongoing and recently accomplished programmes and projects of BDRCS).
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
17
Inadequate and delayed response from the respective Department, Section,
Programme, and Project also hindered smooth movement of the process.
1.6 Outline of the report
In introduction chapter, the reader will find basic information about the organization,
strategic development plan 2011-15, objective of the midterm progress review,
justification & scope and limitation of the study.
Methodology chapter of the review describes different methods by which qualitative
and quantitative data, on various indicators under outputs, were collected, analyzed
and reported.
Progress review findings, in the chapter three, represents indicator wise progress
under three core programmatic areas of Strategic Development Plan 2011-15, general
understanding on the document and SWOT analysis.
The last chapter concludes the overall findings and provides recommendations under
each of the core areas for further improvement on the implementation of SP 2011-15.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
18
Initial planning by PMER Section and P&D
Department
Context analysis and identfied areas need to be
considered
Drafted the progress review methodology
Commitment from BDRCS management
Sensitized moninated reporting focal person from Dept./Progr./Proj
Organized orientation on data collection tool
Started the Midterm Progresss Review process
Figure 2.1: Chronology of the concept development
Chapter Two: Methodology
2.1 Conceptualization PMER Section, along with Planning & Development Department
started the Initial thinking of conducting the midterm progress
review of SP 2011-15, BDRCS. The idea was to assess the
progress against the expected result in SP 2011-15 and to
create a platform for the PMER Section to conduct further work
in PMER at the national society and with its partners. A
workshop with the Chairman, Secretary General, Directors/ In
Charge/ Program Managers of all the
Departments/Programmes/Projects of BDRCS was organised to
attain the endorsement of the mid-term review by the BDRCS
senior management. The workshop covered formal
announcement of conducting the midterm progress review,
selecting reporting focal person from the
Department/Programme/Project (Annex 5.5 List of reporting
focal person) and sharing the methodology. There are no
indicators or benchmarks in the SP 2011-2015 to measure the
expected results, why the PMER Section developed indicators
against the outputs in the SP 2011-15. Later on, the
methodology and indicators were shared with the nominated
reporting focal person through another day long workshop. The
participants worked together and finalize those per-developed
indicators by adding with and deducting some from existing
indicators (Annex 5.1: Indicators for the progress review).
Through afore mentioned approaches, the review process
made participatory, so that all the relevant stakeholders can own and act upon the
desired requirements.
2.2 Sampling design
The midterm review includes Departments, Programmes, Projects, Branches and
volunteers as sample units. BDRCS has 64 Units and 4 city Branches, so all together it
has 68. The data collection team covered 10% of the Units (7 Units/Branches) to assess
qualitative indicators developed on the five strategic goals under Strategic Development
Plan 2011-15. Unit volunteers, who are trained on various issues and deployed in
responses, were selected for Focus Group Discussion (FGD). Besides, Unit Level Officers
(ULOs) were involved as Key Informant Interviews (KII) participants as they are
managing interventions through the at Unit level. Moreover, project beneficiaries under
CDI, flood early recovery operation and emblem campaign were selected for FGD
participants to assess the programmatic issues relevant to SP 2011-15, BDRCS.
Maternal and Child Health (MCH) centres were also included in the sample unit. KII with
midwifery was conducted in Khulna and Jessore MCH centre.
Purposive random sampling was applied in case of selecting KII, FGD and interview
participants and respondents for questionnaire survey. Besides, systematic random
sampling was followed for selecting Unit/Branch of BDRCS where representative Units
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
19
from Dhaka, Chittagong, Khulna and Rangpur Division of Bangladesh were considered in
the study.
Table 2.1: Coverage of Unit/Branches, volunteers and the project areas for progress
review and use of different methods for assessing qualitative indicators.
Sl. No.
Coverage Qualitative methods & participant coverage
FGD KII Interview Observation 01 NHQ,
BDRCS 2 FGDs with NDRT & NDWRT members, Disaster Response Department officials
3 KIIs with the Director of P&D, Tracing and Estate Department of BDRCS
- -
02 Cox’s Bazar Unit & project areas.
3 FGDs with trained Unit volunteers and Tracing Team members, CPP volunteers
1 KII with Unit Level Officer (ULO), Cox’s Bazar RC Unit
12 short interview with pharmacy owners and 5 ambulance drivers
12 pharmacies and 5 ambulances
03 Khulna and
Jessore Unit
1 FGD with the
volunteers of Khulna Unit
2 KIIs with Unit
Level Officers (ULO)
- -
04 MCH Centre (Khulna & Jessore)
- 2 KIIs with MCH staff in Khulna and Jessore MCH centre
2 interviews with midwifery and one with One pregnant
mother
-
05 Rangpur
and Kurigram Unit
2 FGDs with
volunteers of Unit
2 KIIs with Unit
Level Officers
- -
06 CDI Programme,
Rangpur
2 FGDs with CRDT members and CDI
programme beneficiary
- - -
07 Early Recovery Operation, Kurigram
FGD with project beneficiary
- - -
2.3 Data collection
2.3.1 Primary data collection
Qualitative indicators, linking several results mentioned in the Strategic Development
Plan 2011-15 of BDRCS, were assessed through collecting primary data. Methods
including survey, Key Informant Interviews (KII), Focus Group Discussion (FGD) and
interview were employed with different level of officials and stakeholders of BDRCS.
2.3.1.1 Survey
General understanding on Strategic Development Plan 2011-15, BDRCS, among the top
and mid level management staff covering different Department/Programme/Project of
BDRCS, representatives from IFRC and Participating National Societies (PNSs), was
assessed through a structured questionnaire. Two different types of question paper were
prepared, based on the responsibilities of BDRCS and IFRC, ICRC & PNSs in implementing
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
20
the interventions mentioned in the Strategic Development Plan 2011-15 for capturing
different views. A total of 52 respondents were covered in this survey (Annex 5.3: Survey
tool).
2.3.1.2 Focus Group Discussion (FGD)
FGD was implied to capture in depth information on pre defined qualitative indicators
from different level of participants from National Headquarters, Unit/Branch, volunteers
and project beneficiaries of BDRCS. FGDs with NDRT & NDWRT members, Cyclone
Preparedness Programme (CPP) volunteers & staff and Disaster Response Department
were conducted at Dhaka, Cox’s Bazar, Khulna, Jossore, Kurigram, and Rangpur Unit.
Key FGD issues were capacity building, utilization of acquired knowledge, beneficiary
satisfaction etc. Volunteers who were involved in project implementation selected as FGD
participants. Besides, beneficiaries of the Community Development Initiative (CDI)
programme and Flood Early Recovery project and CDRT (Community Disaster
Management Committee) were also included in the FGD. Standardized rules and FGD
checklist were followed during conducting the session at the NHQ, Unit level and
community level (Annex 5.2: FGD checklist).
2.3.1.3 Key Informant Interviews (KII)
KIIs were conducted with the specific Department Directors of BDRCS and Unit Level
Officers for assessing analytical aspects on various results of SP 2011-15. This approach
was also helpful to explore the challenges they faced and actions that were taken to
resolves those (Annex 5.2: KII checklist).
2.3.1.4 Interview
Short interviews were carried out with the 12 pharmacy owner, 5 ambulance driver and
other health institutions focusing appropriate using of BDRCS emblem at Cox’s Bazar
District. Besides, 2 interviews were conducted with the midwifery under Jessore and
Khulna MCH centre. The review team also visited 12 pharmacy setups and 5 ambulances
to actually observe which logo they are currently using. Moreover, evidence based
photography was also taken during observation (Annex 5.2: Key interview issue).
2.3.2 Secondary data collection
Secondary data, on pre selected indictors on the strategic goal, was collected through a
data collection template which was oriented and disseminated to the reporting focal
person nominated by the relevant Department, Programme, Section and Projects of
BDRCS. They filled the template with the support of monthly activity report (MAR),
quarterly & annual donor report, small scale MIS (Management Information System),
project completion report and other preserved documents. Later on, they submitted the
filled up template to PMER Section through proper channel (Annex 5.4: data entry
template).
2.4 Strength, Weakness, Opportunity and Threat (SWOT) Analysis
SWOT analysis, with the representatives of relevant Departments, Section, Programme
and Projects of the BDRCS and IFRC staff, was conducted in a workshop at the BDRCS
conference room. The participants discussed together minutely in groups and explored
key points under strength, weakness, opportunity and threat issues. Four core individual
SWOT analyses were compiled into one.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
21
2.5 Data compilation, analysis and reporting
Primary and secondary data on pre-defined indicators based on Strategic Goals of
Strategic Development Plan 2011-15 were compiled and analysed using Statistical
Package on Social Sciences (SPSS) and Microsoft excel software. A comprehensive
progress review report was prepared by the PMER team and initially shared among OD
staff and PMER Delegate for internal feedback. Later on the document circulated to all
Departments, section, Programmes and Projects of BDRCS and its stakeholders for
further feedback. The report was finalized through incorporating all the necessary
feedback and shared hard copy.
2.6 Findings sharing workshop
A workshop was organized with the Director/In Charge, Reporting Focal Point of
Department/Section/Programme/Project of BDRCS and IFRC, PNSs representative to
share the midterm progress review findings.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
22
Secondary Data For quantitative indicators, data will be collected from different sources like -
- Quarterly/semester/annual report - Event report - MARs - Review of existing & supportive
documents
Primary Data For measuring qualitative /quantitative indicators perception of BDRCS staffs & volunteers and stakeholders will be assessed by applying -
- Questionnaire survey - Key Informant Interviews (KII) - Focus Group Discussion (FGD)
Finalize the indicators by incorporating feedback from respective
Department/programme/project of BDRCS
Identify the objectives of Mid Term Review of Strategic Development Plan 2011-15
Setup of SMART Indicators - - Formulate SMART indicators (both
qualitative and quantitative) on outcomes and outputs mentioned in SP
Data collection
Develop tools for assessing indicators
- tools for qualitative and quantitative indicator will be developed
- Share tools with Department/ programme/project focal for more clarity
Data compilation, analysis and interpretation
Prepare Mid Term Review Report
Organize workshop for disseminating review findings with BDRCS and its stakeholders
Incorporate workshop feedback and finalize the report
Print and disseminate review report to BDRCS Stakeholders
Finalize all the tools/checklist/excel & ward formats developed for the review
Organize strategic workshop on Review of Strategic Development Plan 2011-15
Further clarification of indicators
- - Share drafted indicators with respective Department/Programme persons
Discussion among BDRCS PMERs (OD & DRM)
Study on SP 2011-15/ formation of initial team
Communication & coordination among members
Nominate focal from each department & programme
Review of drafted indicator by participants
Progress measurement excel sheet & SPSS for qualitative data analysis
SMART Indicator: S – Specific M - Measurable A - Achievable R – Realistic/relevant T – Time bound
Ensure effective communication with review stakeholders
Prepare comprehensive data collection schedule
SWOT Analysis for 3 core divisions of SP 2011-15
Figure 2.2: Flow chart of the Methodology of Mid Term Review of Strategic Development
Plan 2011-15, BDRCS.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
23
Chapter Three: Progress Review Findings
The chapter is the presentation of data and information which were collected from
relevant departments, programmes and project of BDRCS, different stakeholders and
project beneficiaries through qualitative and quantitative data collection method and their
analysis. The overall findings are classified under four parts entitled as:
3.1 Core Programme: Organizational development
3.2 Core Programme: Disaster Management
4.3 Core Programme: Health
3.4 General Understanding on SP 2011-15
However, the detail findings are discussed in the following:
3.1 Core Programme: Organizational Development
Organizational Development, commonly familiar as OD, is one of the three core programs
of BDRCS as per the SP 2011-15. OD of BDRCS mainly comprises Planning and
Development, Youth and Volunteer Development, Fund Raising and Resource
Mobilization, Administration and Human Resource Management, real estate management,
training, PMER, Strategic Planning, Unit Management and Development etc. Humanitarian
Diplomacy and Gender also falls under OD activities as cross-cutting issues. All these
endeavours are supposed to contribute toward achievement of Strategic Goal-3; to
ensure organizational development for a well-functioning National Society and effective
service delivery and Strategic Goal-5; to promote the culture of non-violence and peace
through effective humanitarian diplomacy and advocacy. This Mid-Term Evaluation
measured the progress of above OD issues toward attaining the relevant strategic goals
against the plan for the period of 2011- June 2013.
3.1.1 Planning and Development interventions
3.1.1.1 Enactment of New Legal Base
One of the major OD issues in the Society over the last Decade is Legal Base reform in
order to make it in comply with the Movement Model Law. In this connection, as per
recommendation of Joint Statutes Commission in 2001, the process was started in 2002.
As per the SP 2011-15, there was a plan to get the new legal base approved by the
Parliament by 2011 which was not done and as per review data new legal base was not
approved by the middle of 2013. Therefore, the plan to conduct orientation of new legal
base and formulation of corresponding statutes during 2012 and 2013 did not take place
as the new LB was not approved. Meanwhile, several initiatives including regular follow
up and communication, inter-Ministerial orientation (in 17-21 June 2012), Chairman’s
letter to the Prime Minister (17 Feb, 2013), Inter-Ministerial Meeting (in 12 June, 2013)
and other correspondence took place between different level of BDRCS, Line Ministry
(Ministry of Health and Family Welfare) and other relevant Ministries like Ministry of Law
and Parliament Affairs, Ministry of Finance, the Cabinet Division etc. (BDRCS Annual
Report 2012 and 2013).
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
24
3.1.1.2 Formulation and implementation of Strategic Development Plan (SP)
2011-15
Strategic Plan formulation was also another vital OD activity for the Society. The
Strategic Plan 2011-15 of BDRCS has been formulated under the coordination of Planning
and Development Department. The SP, dividing BDRCS programs into three core areas
i.e. Disaster Management, Health and Organizational Development, outlined 5 strategic
goals and corresponding output level result statements to be achieved by the Society.
However, absence of Outcome statement and indicator against any level of result
statement should be the issues to be addressed in the next planning.
It was a plan to formulate the ‘SP 2011-15’ in 2011 and start implementation from 2012
and onwards. Although the initiative, as planned, of SP formulation was taken in 2011
through hiring a consultancy firm with a target to complete it by the same year, the
review data depicts that formulation of SP was not completed during the stipulated time.
It was just half done in 2011 and took almost the whole year of 2012 to get it finalized.
Finally, the SP 2011-15 was approved by the Managing Board in the AGM of 2012 and
was printed and distributed among internal stakeholders through different meeting and
workshop. It was also been circulated among the delegates and the Movement Partners.
No formal orientation session was arranged for orienting the SP at NHQ and Unit level.
3.1.1.3 Formulation Four Years Development Plan
In order to have all operational plans of Departments and Units aligned with the Strategic
Plan, P&D Department hired a consultant to develop 4-Year Development plan of 22
Departments and 68 Units. The target was to formulate it in 2012, as an immediate
action after completion of SP in 2011, and forced into implementation from 2013 and
onwards. However, as per data, formulation of 4-year development plan was not done in
the stipulated timeframe. The consultant was working on the plan in consultation with
respective Departments and Units. Earlier, the consultant organized workshop with all 68
Unit representatives and at NHQ level as a part of formulation of the development plan.
3.1.1.4 Planning, Monitoring, Evaluation and Reporting (PMER) initiative
PMER Section under P&D Department was established in November 2011. Compilation of
Monthly Activity Reports (MARs) of different Department of BDRCS and uploading in the
website was the main activity at the beginning of the Section. Since inception, a total of
15 MARs were published and uploaded in BDRCS website. However, the Section was
supposed to publish 19 reports during the evaluation period which was not done due to
resignation of staff and subsequent delay in filling up the position. There was also a plan
to conduct Mid-Term Evaluation of all on-going project led by PMER Section in 2013
which was also not done.
3.1.1.5 Information and Communication Technology (ICT) strengthening
ICT Section implemented the Digital Divide (DD) project in BDRCS. Under this DD
project, the plan was to develop ICT Capacity of 4, 20 and 10 Units in the respective year
of 2011, 2012 and 2013 (June). The review data depicts, there was no support provided
to any Unit in 2011. However, 6 Units in 2012 and 10 Units in 2013 received ICT
logistics like computer, UPS, internet modem together with informal orientation to Unit
officials and volunteers.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
25
Besides, as a part of the project, 187 email accounts were created against the target of
472. Moreover, a total of 20 email and 80 email accounts, in respect to target of 187 and
167 created email accounts, were distributed to BDRCS staff in 2012 and 2013
respectively.
3.1.2 Conduction of Organizational Capacity Assessment and
Certification (OCAC)
Organizational Capacity Assessment and Certification (OCAC) self-assessment was
planned to be conducted in 2012 and implementation of OCAC recommendation was
supposed to be underway subsequently after the assessment. However, it was not
conducted during the planned timeline. As per data, initiative was taken in 2012 and P&D
Department prepared everything including office circular, venue confirmation, participant
list, stationary etc. to hold it in June 2013 but was postponed due to country wide
political instability and crisis (KII 2014).
3.1.3 Strengthening of Unit/Branch capacity
As per the SP 2011-15 there was a plan to develop 30 C category Branches to B
category and 4 B Category to A Category during the period of 2011-2013 (June). As a
part of this, there was a target of supporting 34 Units for renovation and construction of
office building during the review period which was not achieved. Only 4 Units received
fund for office renovation and due to fund constraints rest of the Units could not be
covered. Also there was no further assessment carried out to identify if the Units made
any progress.
Development of Branch Operation Manual (BOM) together with Governance Manual, Asset
Management Policy, Code of Conduct and Integrity Policy was one of the initiatives of
Unit capacity strengthening by the P&D Department which was planned to be done in
2012. The process of developing those documents was started by appointing a consultant
in the middle of 2012 with a target to complete them within the same year which was not
achieved. It was found that the consultant could only manage to submit a first draft by
the middle of 2013 for the review of OD Core Group and subsequently by the Federation.
3.1.4 Fund raising and resource mobilization initiatives
Fund raising Department, one of the oldest Department of BDRCS, was established to
raise fund for the Society. An amount of BDT 330240, 843455 and 1034195 were
collected against the target of 300000, 60000 and 1200000 respectively in 2011, 2012
and 2013. Likewise, an amount of BDT 180861, 107321 and 64748 was collected through
Donation Boxes respectively in 2011, 2012 and 2013. Looking more closely, the data
reveals that fund collection through selling souvenir items had a very positive upward
trend and was higher than the target in 2011 and 2012. On the other hand, collection
from donation boxes was inconsistent through the review period and was slightly lower
than the target.
Apart from these, a high level dinner for fund raising with the presence of Honourable
President and Prime Minister of Bangladesh was planned to be conducted in 2012 which
was also not done.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
26
0 50000 100000 150000 200000
2011
2012
2013
200000
150000
100000
180861
107321
64748
Achievement Plan
0
200000
400000
600000
800000
1000000
1200000
2011 2012 2013
300000
600000
1200000
330240
843455 1034195
Plan Achievement
There was a plan to formulate asset management policy in 2012 which was not
completed during the stipulated timeframe. However, a consultant was hired in the
middle of 2012 to formulate asset management policy together with Branch Operation
Manual who submitted the draft in the middle of 2013 for BDRCS review.
As a part of resource mobilization, there was a plan to introduce RMS for BDRCS staff and
volunteers in 2012 which was also not started in the stipulated timeframe.
Real estate is the main source of earning of unrestricted revenue for BDRCS. Estate
Department mainly responsible to perform duties related to management and
maintenance of Society’s properties like land and building that includes rent collection,
agreement renew, dispute resolution, warehouse maintenance, updating land documents,
payment of holding and land taxes, recovering of dispossessed lands etc. Rents are being
collected from different buildings, shops, and warehouse as well as leasing of NHQ pond
and trees. Estate Department during the period of 2011-13 (June) collected an average
of 90% of their forecasted rent (KII 2014). However, there is a big amount of arrear
rents that been carried over for years denting the yearly percentage of achievement.
Recovering of grabbed and dispossessed lands is also a big concern for the Society.
During the evaluation period, Estate Department with the help local RC Unit identified 11
lands in Noakhali being grabbed by others and started legal action for repossession. The
Department also started legal process for protecting NHQ land from encroachers.
Having no policy for asset management is a massive drawback in terms of real estate and
other asset management of BDRCS. Lack of ownership documents of lands, political
influence, tenants’ non-cooperation, absence of land surveyor, having no fund for
maintenance and tax further intensify the problems. They also raised some
recommendations which will support further smooth interventions (KII 2014):
Figure 3.1: Above graph is representing the
amount of money collected from donation box
Figure 3.2: The chart is presenting the
information of fund collection from selling
souvenir items
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
27
There should be a Policy for managing asset and real estate of BDRCS.
A database should also be maintained with information of all property and lands
including GPS.
There should be more close supervision over assets of all Units from NHQ
especially by Estate Department.
Proper procurement system should be followed in selection of developer, tenant or
any other procurement related issues.
ULOs should be trained on asset management and a Land Surveyor can be
recruited.
A portion of collected rents should be preserved for maintenance and paying
holding and land taxes.
3.1.5 Staff management and administration
Administration Department issued Identity Card (ID), visiting card, prepared absent
statement, prepared security guard roster and organized observation of national and
international days in a regular basis to ensure an effective and smooth running of the
society. During the evaluation period, a total of 90, 150 and 200 ID cards were issued
against the plan the plan of issuing 100, 150 and 250 cards in the respective year of
2011, 2012 and 2013. Likewise, the Department issued and distributed visiting cards to
30 staff. In regard to observation of national and international days, the Department fully
achieved its target. It organized observation of 13 main national and international days in
each year of 2011 and 2012 and 6 days up to June 2013. Besides, the Department
prepared absentee statement, issued office circular, paid electricity and telephone bills,
prepared security guards roster as per the plan. Apart from these, the Department
produced reports on a regular basis based on their planned activity which is noteworthy.
Under Human Resource reform initiatives there was a plan to develop an organogram in
2012 for BDRCS with the support of Canadian Red Cross OD Fund and implemented by
Planning and Development Department. But the progress was not made in 2012.
However, the initiative was started in 2013 which was also not completed in that year but
half done. As part of HR reform process, it was also planned to develop Job Description
for BDRCS staff and in this connection, Job Description for Secretary General, Directors
and Deputy Directors of all the Departments of BDRCS were drafted needing approval
from the Managing Board. However, the plan of preparing of job description for rest of
the staff during 2011 to 2013 was not completed during the planned timeframe. As the
target of JD preparation was not achieved so the workshop and orientation on JD was not
organized although the activity was planned for 2013.
3.1.6 Capacity building of volunteers for effective service delivery
The Department was involved in the process of capacity building of the Red Crescent
Youth (RCY) through organizing training and workshop during the timeframe. Training
course on Basic RCRC Movement and First Aid, Youth as Agent for Behavioural Change
(YABC) and Dead Body Management were conducted with the volunteers of BDRCS. The
Youth and Volunteer Department planned to organize 10 training on Basic RCRC
Movement and FA in 2012 but couldn’t organize any event. However, in 2013 as per plan
similar training was conducted at 34 Unit/Branch which covered 1,020 participants.
Besides, 24 volunteers were trained on YABC in 2011 but the Department couldn’t
arrange any training in 2012 however they planned to conduct 2 training courses.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
28
0
10
20
30
40
50
60
70
2011 2012 2013 (Till June, 13)
30 30
68
3 4
34
Nu
mb
er
of
ToT
ToT on Search & Rescue Plan
Ach.
Figure 3.3: Status on accomplishment of Search & Rescue
ToT among the RCY.
Moreover, as a capacity building support, 2 training courses were organized on Dead
Body management with 20 volunteers in 2013.
Under youth co-curricular activity, yearly Youth Leadership workshop was organized
during 2011-13 as per plan which covered 189 male and 15 female participants from 68
Units/Branches of BDRCS. Under this initiative, the Department organized training of
Trainers (ToT) events for RCY and school teachers to develop resource persons on RCRC
Basic & First Aid and Search & Rescue issues. During the reporting period, 6 ToT courses
on RCRC Basic & First Aid were completed with 210 school teachers against planned 14
courses. Similarly, total 11 ToT courses were completed with RCY as per plan which
covered 440 participants during 2011 to 2012 and the Department had no plan for
conducting such ToT in 2013. Besides, there was plan to conduct 7 ToT courses on
Disaster Management with RCYs in 2013 but they could not organize any course till June
2013.
The Department stressed on conducting capacity building event on Search & Rescue
aspects during the time frame. In 2011 and 12, total 7 ToT course were organized and
the average achievement was very minimal as 11.66% in respect to the target. However,
in 2013, the Department was able to organize 34 ToT courses as per plan till June 2013.
Each of the ToT
events covered 30
participants and the
total number was
1230 RCYs.
In case of expanding
the youth co-
curricular activities,
the Department took
internal mechanisms
to increase the
coverage of school,
college and open
troops as well as the
total number of RCY
during the reporting
timeframe. More specifically, the total number of RCY has increased from 40,684 in 2012
to 440,269 in 2013. This status gives the insight on the expansion of Youth Co-curricular
initiatives of BDRCS to a great extent. However, the Plan of expanding co-curriculum
activities up to 70% by 2013 could not be measured due to lack proper data and baseline
status.
Besides, the Department organized 12th National Youth Red Crescent Camp in Chittagong
on 21-25th December 2012 although the plan was to organize camp in 3 Divisions. Unit
Level Officer (ULO), Secretary and 22 RCY Members from each 68 Units participated in
the National Camp. A total of 2,500 students gathered and were informed about RCRC
(Red Cross Red Crescent) Basic, First Aid, Tracing and Rescue, and Climate Change
Adaptation issues.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
29
3.1.7 Initiatives to protect miss use of RC Emblem
International Relation and Communication Department of BDRCS played the key role in
promoting BDRCS emblem with the support of ICRC and BDRCS revenue across the
country. In this regards, numbers of orientation sessions were conducted in different
District throughout the review period, although as per SP it was only planned for 2013. In
2011, the Department covered 7 Districts (viz Bandarban, Rangamati, Feni, Munshigong,
Magura, Comilla and Norshindi), 6 Districts (viz Luxmipur, Bagerhat, Habiganj,
Gopalganj, Kustia and Chuadanga) in 2012 and 5 Districts (viz Bhola, Narail, Khulna,
Cox’s Bazar and Bogra) in 2013 (up to June). Objective was to provide basic
understanding on RCRC Basic and Emblem Campaign to the volunteers and respective
Unit officials. Immediate after the orientation, the team moved to their assigned location
to conduct 5 days long door to door awareness raising campaign on BDRCS emblem.
Figure 3.4: Status of conduction of orientation on RCRC Basic and Emblem Campaign
with the Unit/Branch volunteers and officials.
The review team has found the campaign useful in raising awareness in BDRCS emblem
in the ground level. Trained volunteer covered health institutions including government
and private setups and disseminated their acquired knowledge to the stakeholders. The
common sharing was that the persons involved in the health aspects were not aware of
using correct logo. After receiving orientation, they started using correct logo for their
own purpose as well as encouraging others to use the logo rightly. Now, they can
distinguish BDRCS logo with others. 98% of the medical centres changed their logo after
awareness raising campaign (Field Observation, 2014).
3.1.8 Human resource development initiatives
During the review period the Training Department conducted numbers of training on First
Aid, Search and Rescue, Basic RCRC, Leadership Development, Disaster Risk Reduction
(DRR) and refresher course for strengthening the capacity of NHQ and Unit staff. At the
same time the Department also conducted training on the aforesaid courses commercially
for different organizations. However, the progress of the Training Department for mid-
term review was measured through few pre-defined indicators set jointly by the review
team and the focal point of the Training Department.
0 2 4 6 8 10
2011
2012
2013
10
10
5
7
6
5
Number of campaign
Orientation on BDRCS Emblem Ach.
Plan
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
30
3.1.8.1 Training for staff capacity building
Under capacity building initiative of BDRCS staff, the Department conducted 10 and 3
First Aid trainings courses against the plan of 11 and 5 training in the respective year of
2011 and 2012. A total of 311 participants with 244 male and 67 female were covered
through this training. However, as per data, no training was conducted in the 1st half of
2013.
Figure 3.5: The figure shows the status of conducting First Aid training for Staff
The Department organized only one training course on Search and Rescue for BDRCS
officials in 2011 with 25 participants where 10 participants were male and 15 were
female. There was no other training on SAR being organized in 2012 and 2013.
Training on RCRC Basic was conducted for Unit and NHQ officials to orient them about the
Movement. 2 trainings were organized in each year of 2011 and 2012 respectively
against the plan of 3 and 5. As per data no training took place on RCRC Basic in 2013.
The Department oriented a total of 104 staff and officials on Red Cross and Red Crescent
Basic during the reporting period where 84 were male and 24 were female.
Training on Disaster Risk Reduction (DRR) was conducted to build capacity of Unit and
NHQ officials. The Department conducted 1 course in 2011 and 6 courses in 2013 on DRR
with a total of 285 participants from NHQ and Units. No training took place in 2012. In
fact, the Training Department organizes DRR training on Demand basis and that’s why
they don’t set a target in advance about the number of training courses the Department
would like to organize in the following year.
The Department also conducts Training of Trainers (ToT) course on First Aid, Search and
Rescue, Disaster Risk Reduction issues. During the review period the Department
conducted ToT course only on First Aid. In 2011, there were 5 ToT with 144 participants
against the target of 5, in 2012, there were 6 ToT with 159 participants against the target
of 7 and in 2013 (up to June) the Department conducted 1 ToT with 24 participants
against the target of 2.
Only 1 induction training conducted in 2011 with 28 participants (22 male, 6 female).
Information of 2012 and 2013 was not found.
0
2
4
6
8
10
12
2011 2012 2013
11
5
0
10
3
0
Nu
mb
er
No. of FA training for staff
Plan
Achievement
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
31
3.1.8.2 Revenue collection through commercial trainings
It was found that the Department conducted numbers of trainings commercially in other
organizations on different issues like First Aid, Search and Rescue, Refresher on First Aid,
Fire Safety, and Disaster Risk Reduction etc. The Department, through conducting
commercial trainings, is contributing the reserve of unrestricted fund of BDRCS.
Search and Rescue (SAR) is one of the main courses that the Department offers to
different organizations. During the review period the Department conducted a total of 28
courses in different public and private organizations. However, evaluation team found
that the achievement of conducting SAR Training is a bit lower than the Department
planned for. There were 11 courses with 257 participants (172 male, 85 female) in 2011
and 17 courses with 439 participants (271 male, 168 female) in 2012 against the plan of
13 and 18 in the respective year. The Department had no plan to conduct SAR Training in
the first half of 2013.
Figure 3.6: The figure depicts status of conducting commercial training on SAR.
In depth data analysis shows that the Department conducted highest number of trainings
and orientations during the reporting period on First Aid. The Department, in every year,
nearly met the plan of conducting commercial First Aid training. Review data shows that a
total of 60, 49 and 12 training courses were organized respectively in 2011, 2012 and
2013 against the target of 62, 52 and 14 in the respective year. Altogether the
Department conducted 121 training and orientation on First Aid with a total of 2,798
participants among which 2,159 were male and 639 were female during the review
period.
0
5
10
15
20
2011 2012 2013
13
18
0
11
17
0
Trai
nin
g n
um
be
r
No. of commercial training on SAR
Plan Achievement
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
32
12%
88%
Staff Capacity building training Commercial training
Figure 3.8: The pie chart represents the ratio of
conducting commercial and staff capacity building
training by the Training Department.
Figure 3.7: The figure shows the status of conducting commercial training on First Aid.
Refresher on First Aid was also conducted on demand basis. The Department conducted
13 commercial refreshers with 252 participants in 2011, 8 refreshers with 111
participants in 2012 and 3 refreshers in 2013 (up to June) with 65 participants. As the
refresher course is usually conducted on demand basis so the Department had no target
for it.
Training on Fire Safety and Disaster Risk Reduction (DRR) was also conducted
commercially. There were 5 training courses on Fire Safety with 140 participants and 2
training on DRR with 64 participants in 2012 only.
The review found that 88% of the total trainings conducted by the Department are
commercial and rest 12% is for
the capacity development of
BDRCS staff and volunteers.
Training Department contributed
an amount of BDT 6,442,827 to
the Revenue of BDRCS during
2011 – June 2013 through
conducting commercial training in
different organizations. However,
the Department had no yearly
forecast for collecting fund through
conducting commercial training.
0
10
20
30
40
50
60
70
2011 2012 2013
62
52
14
60
49
12 Nu
mb
er
of
trai
nin
g
No. of commercial training on FA Plan Achievement
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
33
3.2 Core Programme: Disaster Management (DM)
3.2.1 Community mobilisation toward building resilience
Bangladesh Red Crescent Society (BDRCS) carried out a number of activities to mobilize
community people for developing disaster resilience communities through different
programmes and project entitled Under Disaster Management Division entitled Climate
Change Adaptation (CCA), Community Development Initiative (CDI), Vulnerability to
Resilience (V2R), urban disaster Risk Reduction (UDRR) and Community Based Disaster
Risk Reduction (CBDRR) across the country. Training, mock drill, awareness raising
session and meeting with CBOs are the key initiatives that were conducted for community
mobilization. Apart from these, a significant number of beneficiaries were covered
through community consultation/ awareness session and preparedness activity conducted
in afore mentioned programmes ns projects during 2011 to 2013. A total of 750, 1488
and 2050 awareness session were conducted against the target of 992, 1568 and 2186 in
2011, 2012 and 2013 respectively. At the same time, beneficiary coverage through all
the preparedness activities were 2024, 2306 and 2608 against the target of 1624, 1696
and 2496 in 2011, 2012 and 2013 respectively. The participation of male and female
were 6286 and 7802 in community awareness session and 31145 and 66575 were in
preparedness activity which also represents significant participation of female in these
initiatives.
Moreover, training, mock drill and meeting with Community Based Organizations (CBOs)
were conducted to accelerate the process of community mobilization. All the afore
mentioned programmes and projects conducted mock drill for raising mass awareness on
disaster preparedness in respective intervention areas. During the evaluation period, a
total of 44 mock drills were conducted as per plan which covered 42100 community
people including 18450 male and 23650 female.
Training for Unit/Branch volunteer is one of the main activities because they act as
mobilizing agent in the community through dissemination of information and conducting
various events. A total of 8, 8 and 12 training courses were conducted in 2011, 2012 and
2013 respectively which covered 506 volunteers.
Figure 3.9: This bar graph represents the status of conduction of awareness raising
sessions and beneficiary coverage through preparedness activity
0 500 1000 1500 2000 2500 3000
Plan
Achi.
Plan
Achi.
Plan
Achi.
20
11
2
01
2
20
13
992
750
1568
1488
2186
2050
1624
2024
1696
2306
2496
2608
Number
Community people participated in preparedness activity
Community consultation & awareness raising session
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
34
Moreover, 120, 202 and 292 meetings held with Community Based Organizations (CBOs)
in 2011, 2012 and 2013 respectively. A total of 8066 people including 4125 male and
3941 female participated in those meetings.
Table 3.1: The table representing the progress status of mock drill, volunteer’s training
and meetings conducted with CBOs during 2011 to 2013.
Activity
2011 2012 2013 Avg.
Achi.
Ben.
cover
age Plan Achi. Plan Achi. Plan Achi.
No of Mock Drill
conducted 8 8 0 0 36 36 100 42100
No of training conducted
with volunteers 8 8 8 6 12 12 92 506
No of meeting conducted
with CBOs 120 120 192 202 280 292 103 8066
3.2.2 Disaster response tool: Formation and Functionality
3.2.2.1 National Disaster Response Team (NDRT)
National Disaster Response Team (NDRT), who are primarily focused on needs
assessment covering damage occurred, beneficiary selection and distribution, is the key
tool to providing effective response during disaster situation.
In regards of NDRT formation, 2 NDRT were formed in 2011 which wasn’t not in plan,
however in 2012 and 2013, plan was to form 3 NDRT teams. Besides, Disaster Response
Department conducted two training for NDRT members in 2011 where 36 male and 7
female were participated. The data representing male and female status where we found
female participation is not remarkable.
NDRT members are deployed in time of disaster. During 2011 to 2013 a total of 21 male
and 1 female were deployed in response. Again, deployment of female NDRT has found
minimal in respect to male which needs to be carefully looked upon.
Figure 3.10: This bar diagram is representing the data of deployment and training
status of the NDRT member
0 5 10 15 20 25 30 35 40
ND
RT
me
mb
ers
de
plo
yed
in
re
spo
nse
Tr
ain
ing
rece
ive
d
21
36
1
7
Number
Ind
icat
ors
Female Male
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
35
Figure 3.11: The chart showing the deployment status
and training status of UDRT member during 2011~2013
0
50
100
150
Training conducted with UDRT member
Deployed in response
115
0
85
0
Male Female
Box 3.1: Effective Disaster Response Tool
The motivation of the BDRCS staff to be joined in NDRT and NDWRT is ‘to serve the
vulnerable people who are in need’. The trained NDRT members are capable of handling
damage & needs assessment, filling up of damage form, selection of area and
beneficiary, pre, during and post disaster initiatives, relief distribution etc. Most of the
participants utilized their acquired skills like leadership, decision making ability and
managerial capacity in different situations during conducting interventions. Majority of
the participants expressed their satisfaction regarding service delivery during response
in disaster. However, NDRT/NDWRT members have uttered dissatisfaction regarding
preparing and endorsement of the beneficiary list for providing support.
Besides the team members faced several challenges during conducting their assigned
tasks in the field like establishing their recommendations regarding area and beneficiary
selection, emergency relief distribution and other related aspects. They have also
provided recommendations for making most utilization of this tool in further
interventions (FGD, 2014):
o Besides basic NDRT/NDWRT training, sector wise expertise need to be developed
like monitoring and reporting in emergency response and others relevant issues
for more effective service delivery.
o Organize refresher training for NDRT/NDWRT members so that they can be in
touch with their acquired skills.
o Inclusion of NDRT/NDWRT members in lesson learned workshop which would
create opportunity to plan for the further actions based on actual scenario
o NDRT curriculum needs to be reviewed and BDRCS can invite RDRT (Regional
Disaster Response Team) Focal point to review and develop the document
o Allocate sufficient equipment, specialized vehicle and arrange insurance coverage
for the team members during deployment
o Commitment of team members and deployment of female NDRT members are
important regarding effective response during disaster.
o Communication and coordination among the Response Department, BDRCS
management and Local unit need to be improved.
3.2.2.2 Unit Disaster Response Team (UDRT)
Community Disaster Response Team (CDRT) and Unit Disaster Response Team (UDRT)
are also disaster response
tools of Bangladesh Red
Crescent Society to
contribute in fast response
during any types of disaster.
As per Strategic
Development Plan, 30 Unit
Disaster Response Team
were supposed to form at
Branch level. But only 8
UDRT were formed in branch
level during 2011 to 2013
where 115 were male
member and 85 were female
member. The achievement of team formation was not as per the plan and achievement
was far behind than the plan. Only Community Development Initiatives (CDI) formed
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
36
Figure 3.12: This graph presenting the status of CDRT
formation and training conduction with CDRT member
0 10 20 30 40
16
10
37
8
4
4
Training conducted CDRT formed
those 8 teams at Unit/Branch level. Other Department/Program/ Project didn’t take
initiatives to form the team. CDI Programme also conducted training for UDRT members.
3.2.2.3 Community Disaster Response Team (CDRT)
CBDRR, CDI programme, CCA and V2R project formed 63 Community Disaster Response
Team (CDRT) against the target of 57 during 2011-2013. A total of 1671 members were
involved including 1099 male and 572 female in those CDRTs.
Community
Development
Initiatives (CDI)
conducted a total of 16
training for the CDRT
member as per their
plan. A total 400 CDRT
members including 245
male and 155 female
participated in those
training courses.
Training issues were
Participatory Hygiene
and Sanitation
Transformation (PHAST), Participatory Approach for Safe Shelter Awareness (PASSA) and
Basic First Aid (FA).
A total of 4 communities under CDI programme in Rangpur received the training as a
CDRT member. Apart from theses a total of 25 members also received training on Basic
Disaster. CDRT members supported in early marriage issues and road construction issues
in the community. After getting the PASSA training CDRT members disseminated
acquired knowledge to the local people. CDRT members committed to support people in
case of need. They uttered some challenges regarding coordination with Unit team
members and Youth & Volunteers Department of NHQ BDRCS. They also put
recommendations for strengthening CDRT initiatives in future (FGD, 2014):
CDRT members need to be involved in Unit/Branch interventions
Enrolment of CDRT in Youth & Volunteers Department of BDRCS
Need to deploy CDRT member during response in disaster
3.2.2.4 National Disaster WATSAN Response Team
National Disaster WATSAN Response Team (NDWRT) is basically assigned for water and
sanitation related response initiatives. As per Strategic Development Plan 2011-15, total
3 NDWRTs were supposed to form during 2011 to 2013. However, only 1 team was
formed in 2013 comprising 27 members including 24 male and 3 female. In 2012 there
was plan to form 2 NDWRT teams but respective Department was unable to do so.
Besides, capacity building training was also organized for the newly formed NDWRT
members however there was plan for 3 training. Based on the data of Disaster Response
Department, 3 male NDWRT members were deployed in disaster response. Interesting
point is no female NDWRT member was deployed in the fields during the time frame.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
37
4600
5500
7400
1334 1590
738
1334
2236
982
0
1000
2000
3000
4000
5000
6000
7000
8000
2011 2012 2013
Nu
mb
er
of
be
ne
fici
ary
Awareness campaign
Provided IG training
Provided IG support
43%
57%
Gender
Male
Female
3.2.3 Community resilience through programmes
Community Development Initiative (CDI) and Climate Change Adaptation (CCA) project
of BDRCS were involved in building community resilience through including different
initiatives in the PoA (Plan of Action). Major activities under this issue were awareness
raising campaign on disaster vulnerabilities and self safety, organising income generating
(IG) training as preparedness and also providing IG support to the beneficiaries for
making them financially stronger to responding during and after any incident. Based on
quantitative data, a total of 62 awareness raising campaigns were conducted which have
covered 17500 people including 6750 male and 10750 female in the project intervention
area. Besides, an increasing trend was found in beneficiary coverage during 2011-13. For
capacity building in IG initiative, 3662 project beneficiaries covering 1660 male and 2002
female received income generating training like tailoring, homestead gardening,
handicraft, livestock rearing, carpenter training etc. Besides, income generating cash
grant was distributed to the trained beneficiaries in the communities. A total of 4552
beneficiaries including 2570 male and 1982 female received cash grant support from the
project. In depth analysis, also found that average achievement of these initiatives was
100% where female beneficiaries (57%) were prioritized in terms of providing training
and IG support than male (43%). Cyclone Sidr Left Over fund and Canadian Red Cross
fund were utilized to accomplished the initiatives under CDI and CCA project respectively.
Figure 3.13: Beneficiary coverage ubder community
resilience initatives during 2011 -13
Figure 3.14: Gender perspective in
beneficiary coverage
3.2.4 Status of Standing Operating Procedure (SoP) and Contingency
Plan
The disaster response Department initiated developing the Standard Operating Procedure
(SOP) for conducting disaster preparedness, response and recovery interventions in 2011
but couldn’t able to complete the document. However, agreement between IFRC and the
Unit regarding roles and responsibilities during response period are in place. This reduces
complications regarding activity accomplishment and also resolving major challenges.
Besides, contingency Plan for Flood and Cyclone are in place in BDRCS. Last year, during
Cyclone Mahasen Early Recovery Operation, cyclone contingency plan was activated
where staff of BDRCS was given alert for preparing immediate deployment in the affected
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
38
Figure 3.16: Graph shows the comparison of target
and achievement of conduction of First Aid training.
32 32
98
32
6
103
0
20
40
60
80
100
120
2011 2012 2013
Nu
mb
er
Plan Achievement
Figure 3.15: Status of recipient of First Aid services
320
400
480
250
320
340
0 100 200 300 400 500 600
2011
2012
2013
Number
Achievement Plan
areas (FGD, 2014). Response Department also organized a workshop on Contingency
Plan in 2011 as per plan where 18 participants contributed to revising the developed
plan.
Apart from these, Community Development Initiative (CDI) programme formulated
Contingency Plan for 28 communities where respective people identified the way how
they will respond to any natural and manmade incident along with prioritization and
distribution of specific roles and responsibilities.
3.2.5 Capacity Building Initiatives for staff and volunteers
3.2.5.1 Search & Rescue Issue
Data from different projects under DM division depicts that the training on Search and
Rescue was only planned in 2013 by Urban Disaster Risk Reduction (UDRR) programme.
The project organized 4 training courses in the first half of 2013 as per plan where 100
participants including 60 male and 40 female learnt different issues related to Search and
Rescue in emergency. As no other project of DM Division conducted SAR Training so
there was no deployment by them except UDRR. In 2013 UDRR Project deployed 8
trained volunteers in Search and Rescue operation among which 6 were male and 2 were
female.
3.2.5.2 First Aid and service Delivery
Scaling up of first aid service is mandatory to have an effective and efficient emergency
response. As a part of this, different programs/projects like Community Development
Initiative (CDI), Climate Change Adaptation (CCA) and Vulnerable to Resilience (V2R)
included First Aid training for the targeted beneficiaries. During the review period, overall
rate of achievement was found 75% (by the afore mentioned projects).
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
39
Figure 3.17: male-female ration of FA training recipient and FA service recipient
68%
32%
Male-female ratio of FA training participants
Male
Female
35%
65%
Male-Female ratio of FA service recipient
Male
Female
Figure 3.18: Status of male and female members in First
Aid training recipient and First Aid Service Recipient
323
587
462
221
0
100
200
300
400
500
600
700
Male Female
Nu
mb
er
Recipient of FA service Recipient of FA training
Specifically, the achievement in 2011 and 2013 is respectively 100% and 105% but in
2012 it is only 19% as CDI project couldn’t conduct any training against their plan of
conducting 24 in that year. A total of 141 First Aid Training were conducted by CDI, CCA
and V2R project with a total of 683 participants where female participants were 221 and
male participants were 462.
Participants of First Aid training involved themselves in providing First Aid services to the
targeted communities in the respective project areas. During the review period, CDI
programme provided First Aid services to 910 beneficiaries among whom 323 (35%)
were male and 587 (65%) were female. However, the Program has failed to reach target
in terms of providing FA services and overall achievement is about 76%. In 2011, the
program covered 250 people against the target of 320, in 2012, it covered 320 people
against the target of 400 and in 2013 (up to June) it covered 340 people against the
target of 480.
However, looking at the male-female ratio between number of First Aid training recipient
and number of First Aid service recipient the evaluation team found just a reverse trend.
In First Aid training,
participation of male
(68%) is way more than
female and on contrast
among the recipient of
First Aid services number
of female (65%) is more
than the number of male.
This indicates, females
are more vulnerable to
any disaster needing be
more focused in First Aid
training.
Besides, CDI and UDRR programme together planned to purchase first aid kits. CDI was
supposed to purchase of FA Kits in 2011 and 2013 and UDRR had a plan only in 2013.
CDI purchased all its planned 32 Kits in 2011 but failed in 2013 and purchased 24 Kits
against the plan of 75 that year. On the other hand UDRR program has purchased all 20
Kits that it planned up to June 2013.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
40
Figure 3.19: comparison between plan and achievement of
conducting awareness raising session on WASH
200
184
250
180
154
210
0 50 100 150 200 250 300
2011
2012
2013
Number
Ye
ar
Achievement Plan
Figure 3.20: Comparison between plan and
achievement of installation of safe water sources
100
222
422
80
233
386
0
100
200
300
400
500
2011 2012 2013
Nu
mb
er
Year
Plan Achievement
3.2.6 Integration of Water, Sanitation and Hygiene (WASH) in
Programmes
CDI, CCA and V2R project conducted numbers of awareness sessions on Water Sanitation
and Hygiene issues. Community Development Initiative (CDI) Project has been
implementing in 4 Districts, Magura, Kushtia, Natore, Nilphamari, of Bangladesh targeting
more than 10,000 beneficiaries to make them resilient to disasters and improvement of
living standard through income generation. Sidr left over fund was utilized to implement
CDI initiatives. The project conducted 180, 130 and 160 awareness session respectively
on 2011, 2012 and 2013.
Climate Change
Adaptation (CCA)
project, has been
implementing in
Noakhali,
Manikganj,
Gopalganj, Bogra
since 2011,
planned to conduct
WASH awareness
among
beneficiaries on
2012 and 2013.
V2R project is
going on since 2012 in Barguna and Patuakhali District targeting 60,000 beneficiaries.
During the review period CDI, CCA and V2R projects were able to conduct 86% of
awareness raising sessions on Water, Sanitation and Hygiene (WASH). In 2011, 210
sessions conducted against the plan of 250, in 2012, 154 sessions conducted against the
plan of 184 and in 2013, 180 sessions were conducted against the plan of 200 by CDI,
CCA and V2R project.
For improving Water and
Sanitation facilities and
increasing access to safe
drinking water for the
vulnerable community, CDI,
CCA and V2R project installed
numbers of safe water sources
like tube-wells, rain water
harvesting system and ponds
in their targeted project areas.
In 2011, CDI Programme
installed 80 Safe Water
Sources against the target of
installing 100. In 2012, CDI and CCA project together installed 222 safe water sources
against the target of installing 233. CCA project installed all its planned 22 water system
but CDI programme was able to install 200 water system against their target of 211.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
41
Figure 3.21: Comparison between plan and achievement of number of sanitation system installed
0 1000 2000 3000 4000 5000
2011
2012
2013
600
1350
4124
550
1291
3724
Number
Ye
ar
Achievement Plan
In 2013, CDI, CCA and V2R project had a plan to install safe water sources for their
beneficiaries. However, there were 386 safe water sources installed by these three
projects against the target of 422. CCA and V2R installed all their planned safe water
sources respectively 37 and 345. But CDI could only install 4 safe water sources against
the target of installing 40. As per the collected data, there is no information of beneficiary
coverage by the installation of safe water sources by CDI and CCA project. Only V2R
project has given the information of beneficiary coverage and the project covered about
35,450 community people (among which 16,800 male and 18,650 female) by installing
345 safe water sources in 2013.
Besides installing safe
water systems,
Community Development
Initiative (CDI), Climate
Change Adaptation
(CCA) and Vulnerable to
Resilient (V2R) projects
installed sanitation
system for the target
beneficiaries. In 2011,
there were 550
sanitation system
installed against the
target of 600 by CDI Project. In 2012, 1291 sanitation system were installed by CDI and
CCA project against the target of installing 1350, CDI installed 741 which are more than
their plan of installing 700 and CCA project installed 550 against the target of installing
650. In 2013, CDI, CCA and V2R project together installed 3,724 sanitation systems
against the plan of installing 4,124. Among these 3,724 systems, CCA installed all their
planned 100 sanitation system and V2R installed all their planned 3,624 sanitation
system. CDI could not install any of their planned 400 sanitation system by the 1st half of
2013.
However, CDI and CCA did not provide any information related beneficiary coverage. V2R
project covered around 16,878 community people (where 8,246 were male and 8,632
were female).
3.2.7 Disaster response: Effectiveness, Management and way forward
Disaster Response Department of BDRCS is fully engaged in humanitarian response
initiatives in Bangladesh. During 2011-13, the Department responded to major events
occurred in Bangladesh like South-East flood, flood early recovery and Satkhira water
logging operation.
More specifically, a total of 35 response initiatives were undertaken covering different
categories of disasters like flood & landslide, cyclone, tornado/norwester, cold wave, fire,
river erosion and manmade disaster like Other Situation of Violence (OSV) in various
parts of Bangladesh. Response interventions in terms of distributing financial assistance
and beneficiary coverage has increased over time; for instance, in 2011 the amount was
CHF 1358104.5 (BDT 10864836) which increased to CHF 1946235 (BDT 155698800) in
June 2013. Although the amount usually depends on scale of disaster, however there is
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
42
no doubt that the initiative has become more intensive these days. Total 196544
households were covered through financial assistance of CHF 4608535 (BDT 368682800)
in various disasters during 2011 to June 2013.
The assistance covered key items like Food Items (FI), Non Food Items (NFI), cash grant
for livelihood & shelter, materials support, WATSAN support like post excavation,
installation of PSF (Pond Sand Filter) and RWH (Rainwater Harvesting), blanket for cold
wave sufferers and beef distribution for the ultra poor families during Eid-Ul-Adha, cash
for work and training initiative in the intervention area.
Figure 3.22: Yearly financial assistance provided to beneficiaries during disaster by the
Disaster Response Department of BDRCS.
Table 3.2: Year wise household coverage and financial assistance provided during
different category of disaster during 2011-13 by the Disaster Response Department.
FY 2011 FY 2012 FY 2013 TOTAL
Sl Disaster Category HH
Support
(CHF) HH
Support
(CHF) HH
Support
(CHF) HH
Support
(CHF)
1 Flood/landslide 17420 559297 17420 559297 10000 1196975 44840 2315570
2 River erosion 75 27187 75 27187 0 0 150 54375
3 Manmade (OSV &
others) 12056 224780 12056 224780 262 59385 24374 508945
4 Tornado/ Norwester
5700 243437 5700 243437.5 2110 27500 13510 514375
5 Cold wave 36600 298125 21955 190216 50915 400875 109470 889216
6 Fire 100 32277 100 32277 0 0 200 64554
7 Cyclone 0 0 0 0 4000 261,500 4000 261500
Total 71951 1385104 57306 1277195 67287 1946235 196544 4608535
2011
2012
2013
1385104.5
1277195
1946235
71951
57306
67287
HH coverage Financial assistnace (CHF)
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
43
Project implementation
In large scale DREF Operation launch or Emargency Appeal
For small scale incident BDRCS & IFRC jointly decide to response
Then, held discussion with IFRC – Deploy assessment team for damage assessment
If possible Unit/Branch can response immediately, otherwise carried out response from Joint DP stock (at HNQ
BDRCS)
Disaster Response Department collects information & validation with government
After disaster – Request for assistance sent from the field
Figure 3.23: Flow chart of the response initiative by Disaster Response Department
Beneficiary selection usually
depends on mode of project.
BDRCS followed the selection
criteria mentioned in the field Relief
Manual which was developed in
1997. Later in 2012, a consultant
was haired to review the manual
which needs to be in surface. Based
on the criteria, person/family has to
be the affected and priority should
be given to female/widow and
physically challenged & autistics
person in the affected areas.
Although the selection process
includes community consultation
and further validation but still the
participation isn’t up to the mark.
The process of beneficiary selection
for any assistance need to be fully
community based. Besides, the
review team did not find any statement regarding Compliance & Response Mechanism
and monitoring & evaluation during response initiative which usually contributes towards
maintaining transparency and accountability. Meanwhile, BDRCS is familiar with preparing
beneficiary database after complete the beneficiary selection process in the intervention
areas.
There are five 5 warehouses located in Dhaka, Chittagong, Rangpur, Bagerhat and
Barguna district of Bangladesh. These are the response tools from where supports are
being reached to the affected communities immediately after the occurrence. Respective
Unit/Brach manages these with the support of IFRC logistics and active involvement of
NHQ BDRCS. The Department organized capacity building events during this period like
NDRT training & refresher, lesson learned workshop on Aila Recovery, South East Flood
and Land Slide, First Aid and Safe Shelter with the volunteers in 3 Units/Branches, Cash
for Training for 30 volunteers. Moreover, representatives of the Department participated
in a workshop on ‘Cash Based Programming’ at Geneva and ‘Cash Based Learning’ at
Nepal in 2013. The acquired knowledge also contributed towards effective relief
management. Financial contributions from IFRC, BRC, HRC, ICRC, ECHO and BDRCS own
fund were utilized for successful completion of the response initiatives (FGD, 2014).
However, representatives of Response Department shared some challenges they faced
during implementing response interventions and also put recommendations for further
improvement of the initiatives (FGD, 2014). The challenges are as follows:
Inadequate time allocation for implementing the interventions planned in Emergency
Appeal.
Constrain in receiving adequate fund for implementing project, for instance, in
Cyclone Mahasen Early Recovery Operation in South Central coastal areas of
Bangladesh, the Department could not respond to its planned beneficiary number.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
44
Figure 3.24: Number of BDRCS volunteers received
RFL training during 2011-13.
40 45 50 55 60
2011
2012
2013
56
51
54
55
48
56
Number of volunteers
Ye
ar
Achievement Plan
Figure 3.25: Number of Unit/Branch Secretary
and ULO received RFL training during 2011-13.
0
20
40
60
80
2011 2012 2013
63
0
40
60
0
26 Nu
mb
er
Year
Plan Achievement
Proper beneficiary selection for providing assistance due to political influence and lack
of following Code of Conduct by the local management.
The recommendations for effective relief management are:
Organize orientation with Unit Executive Committee (UEC) members on RCRC
Movement, Code of Conduct (CoC) and Relief Management at the Unit level in order
to facilitate transparency and accountability.
Unit/Branch based Unit/Branch Disaster Response Team (UDRT) need to be
formulated (now formulating only project basis) and trained them on RCRC Movement
and relief management for effective service delivery.
Qualitative human resources need to be in the response and other initiatives
(management and governance).
Enhance capacity of NHQ and local Units/Branches human resources on relief
management along with promoting accountability.
3.2.8 Restoring Family Linkage (RFL) services
Restoring Family Links Department of BDRCS has been providing support to families
separated during disaster, emergencies and migration aspects. Key interventions of the
Department are; firstly, restoring family linkage where missing family members are being
traced and exchanging family news through Red Crescent Message (RCM), phone call,
family notification and reuniting family members, Secondly, support to migrated person
who apprehend in foreign land. Thirdly, visiting foreign detainees in different jails of
Bangladesh to provide RFL services and distribution of hygiene kits annually or twice in a
year.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
45
Box 3.2: Hearing the Beneficiary, Early Recovery Project, Kurigram
FGD was carried out with the beneficiaries of Flood Early Recovery project conducted at
Char Jatrapur, Kirigram, Bangladesh. Disaster Response Department with the support of
Kurigram Unit Office implemented the project. British Red Cross (BRC) provided financial
support to this project.
The participants of the discussion had general understanding about BDRCS, its area of
interventions; for instance they were able to utter things like community development,
health care and distribution of relief during disaster situation.
Through ‘Flood Early Recovery project’, the beneficiaries received cash grant and training
support on different agricultural issues. Besides, people received First Aid training. Female
participants, who were trained on homestead gardening, of the project were able to utilize
their learning in family life.
Beneficiaries received BDT 20,000 in cash in two instalments; second instalment was
distributed after monitoring of first instalment. They purchased cow, goat with the money.
More than half of the respondents added some money with the support. All the
beneficiaries utilized their support in agricultural purpose like producing pulse, sugarcane,
banana and ground nuts.
According to project beneficiary, the support that BDRCS provided to them contributed to
improving their livelihood. Beneficiaries sold their cows, goat, vegetables and crops in the
market to generate income and after wards they utilized those profits to other areas for
continuing profit. They also agreed that the early recovery project has contributed in
overall ‘Community Development’. ‘We can hardly handle 5000 BDT after the devastated
flood but the timely support of BDRCS makes us stronger and visionary’.
However, they need further support for financial and institutional stability like
establishment of health care institution for the pregnant mother and other complications,
further training on agriculture for further livelihood improvement and enhancing
educational provision etc.
Pursuing the Departmental interventions, Tracing team was formed at each 68 Units level
consisting 6 members (including Secretary as Convener, ULO-Member Secretary, 1 UEC
(Unit Executive Committee)) member and 3 RCYs (Red Crescent Youths). For effective
RFL service delivery, the Department organized capacity building training for the
volunteers, ULO and Secretary of the respective Unit. A total of 159 volunteers received
training on RFL including 126 male and 33 female during 2011-13. In respect to plan, the
Department has achieved 98.67% of the participants’ coverage in the training. For ULO &
Secretary, 86 persons were trained on RFL where 80 were male and 6 female during
2011 and 2013. The Department had no plan for training in 2012. The average
achievement in respect of plan has found as 80.12% in terms of participant coverage.
The training covered different issues like effective RFL response, need assessment,
service delivery, case dealing process, dealing with beneficiaries, dead body
management, how to maintain formalities, record keeping, photograph taking, awareness
raising etc. The Department also provided need base training and on Job training in Units
where work load is relatively high.
Although the incidents are uncertain but Unit/Branch tracing team in Cox’s Bazaar,
Patuakhali, Norial, Serpur, Comilla, Chapainawabganj and Sylhet Branch utilized their
acquired knowledge effectively. However, without having any assignment for so long,
many tracing teams are gradually forgetting various training issues (KII findings, 2014).
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
46
Tracing Department of BDRCS provided various need based services to the people in
need like sending RC Message, notification, family reunification including repatriation,
hygiene kits distribution to the foreign detainees living in different jails of Bangladesh etc.
During the reporting period, need based beneficiary coverage and RC Message exchange
has found increased over time. The Department reached 995 families through its services
and majority (521 families) were covered in 2013. Besides, total of 2400 foreign
detainees including 2233 male and 167 female received hygiene kits in jails and highest
number (889 people) was reached in 2012. In average 32 District Jails had been covered
by conducting this initiative. Besides, RC Messages were also exchanged with 429 people
in and abroad of Bangladesh which covers 395 male and 34 female. The RFL services
usually conducted by the Unit/Branch Tracing Team and in case of emergency volunteers
are deployed in the field. During the reporting period, a total of 67 volunteers including
52 male and 15 female were deployed in Lybia crisis, Launch capsize incident and Bishwa
Istema.
Figure 3.26: Status of family coverage through RFL services, exchange of RC Message
and distribution of hygiene kits to foreign detainees.
Apart from these, Tracing Department organized 2 orientation programs on RFL with the
Board Members and also different ministry of the Government of Bangladesh in 2011 and
2013. A total of 40 participants including 37 male and 3 female received information on
relevant issues. The Department also published different IEC (Information, Education
and Communication) materials like short film on disaster tracing and migration, note
book, pen, coat pin, cap, jacket, life jacket, leaflet, poster and guideline during the
reporting period. The Department also conducted RFL capacity and needs assessment in
202 and 2013.
However, there are some challenges that Department faced in implementation phase like
decrease of financial resource mobilization from International Committee of the Red Cross
(ICRC), as ICRC is the key donor for this RFL activities, for Tracing Department and
influence of local government during conduction of RFL initiatives in the affected areas.
They have also some recommendations for strengthening RFL initiative in BDRCS like
(KII, 2014):
Enhance capacity of tracing team members in terms of convincing local
administration regarding smooth accomplishment of the RFL initiative during crises
Intervention of IFRC focusing their role in disaster tracing and migration initiatives
need to be conducted
239 235
521
126
51
252
773
889
738
0
200
400
600
800
1000
2011 2012 2013
Nu
mb
er
Family
received RFL service
Exchanged RC
Message
Hygiene kit
distribution
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
47 0 5000 10000 15000 20000 25000
2011
2012
2013
19946
19454
21081
20500
21000
22000
Number
Plan Achievement
0
2000
4000
6000
8000
10000
12000
14000
2011 2012 2013
12000 11000
13000
11592
6612
13964
Nu
mb
er
Plan Achievement
An archive on RFL initiative need to be in place in BDRCS
Allocate time or session on RFL activity in RCY co-curricular activity
Organize awareness raising campaigns on RFL with beneficiaries (specially migrant
communities) and authorities
3.3 Core Programme: Health
3.3.1 Service provided through MCH services
The Health Department has been implementing primary health care interventions through
56 Maternal and Child Health (MCH) centres throughout the country since inception of the
organization. The key objectives of this programme is to reduce maternal and child
mortality in remote rural Bangladesh. There are 56 MCH centres of which 32 are
financially sustainable and rests are in under process. The centres are community based
and BDRCS is supervising centres. A total of 126 Health workers and 62 midwives have
been working in MCH centres aiming to cover 1 million people in 27 districts through 56
MCH Centres. Primary health services like patient consultation, conduction of safe
delivery (non-complicated), antenatal care (ANC), Postnatal care (PNS), basic pathology
and family planning are being provided to the community. Besides, awareness raising
session on different health issues, counselling session and supporting to government’s
Extended Program of Immunization (EPI) are also being conducted in the target areas.
Quantitative data found an average achievement of conducting 10 non complicated
deliveries, 25 ANC, 10 pathology tests and 100 EPI doses in each MCH centre. Apart from
these the Department has emergency medical team in order to support disaster affected
people. Hospitals are providing supports in curative aspect.
A total of 19946, 19454 and 21081 pregnant mother were covered through ANC services
against the plan of 20500, 21000, and 22000 in 2011, 2012 and 2013 respectively.
Looking closely, it can be easily found that a gradual progress is happened in ANC
coverage against plan during review period and also average achievement was more than
90%. However, data on PNC conduction represents discontinuity in achieving its target.
In 2012, the achievement was found low in compare to 2011 and 2013, but progress was
more than the plan in 2013.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
48
0
2000
4000
6000
8000
2011 2012 2013
6000 6500 6500
5349 4934 5796
Nu
mb
er
Year
Plan Achievement
90.50% 96.66% 105.21%
83.33% 77.14%
90%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
2011 2012 2013
Pe
rce
nta
ge
Benificiaries covered by EPI Program benificiaries covered by Counselling session
Figure 3.27: The bar graph is showing the
comparative progress status of Antenatal Care
Figure 3.28: The figure representing yearly
basis plan and achievement of Postnatal Care
MCH centres are contributing to
Millennium Development Goal 4 &
5 through conducting non
complicated deliveries which
supporting in reducing maternal
and child mortality in the remote
rural areas. A total of 5349, 4934
and 5796 non complicated
deliveries were conducted in 56
MCH centres against the plan of
6000, 6500 and 6500 in 2011,
2012 and 2013 respectively. The
rate of achievement was quite
good against the plan during the
time frame.
Supporting government’s EPI and conducting counselling session are the regular activity
of general health component of
MCH programme. A gradual
increase of population coverage
through EPI has found increased
during 2011-13. In an average,
the percentage of achievement
was found as 80 to above 100 in
EPI Program. Moreover,
beneficiary coverage through
counselling session was significant
and the average achievement was
83.33% during 2011 to 2013. A
total of 20600, 21600 and 4600
female received counselling on
various health issues from
technical staff of MCH centre in
2011, 2012 and 2013
respectively.
Basic pathology tests like pregnancy, urine, sugar and haemoglobin are being provided in
the MCH centre under general health component. Yearly data shows a gradual increase of
number of pathological tests during evaluation period 2011-13. A total of 11001, 12622
and 17493 test were done against the plan of 12000, 13000 and 17000 in 2011, 2012
and 2013 respectively in MCH centres. The average achievement in 2011 and 2012 were
significant however achievement was more than the plan in 2013. It’s also contributing
towards sustainability of the centres. For strengthening existing MCH centres, a total of
27 MCH Centres renovated against the plan of 32 in 2011. In 2012 and 2013, Health
Department planned to renovate 10 and 6 MCH centres respectively. However, there was
no progress on that plan in 2012 and 2013 due to missing links between strategic
development plan and internal plan of the health department.
Figure 3.29: The Chart is representing the progress
status of Non Complicated delivery
Figure 3.30: The chart presenting beneficiary
coverage through EPI and counselling session
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
49
Box 3.3: Current modality and way forward of MCH Centre
MCH centre of Noihati, Khulna and Gopalpur, Jessore are the two self sustainable MCH
centres which are running with its own fund. An amount of BDT 11000-12000 and 13000-
14000 is the average income of Noihati, Khulna and Gopalpur Jessore respectively. The
services of the MCH centres are patient consultation, safe delivery, pathology, ANC, PNC.
Beneficiaries usually reached through both home delivery services and outdoor services.
However, it was found that the MCH Centre of Khulna running a small micro credit
program through their field staff for their sustainability. The centres also organized
awareness raising court yard sessions on adolescent health, WASH and HIV issues. Both of
the MCH centre has active committee to oversee and support the MCH centre in
implementing the activities more effectively. In order to provide quality health care
services to the communities, Health Department organized capacity building training
(technical and non technical) for both staff and volunteers of the MCH centres. The
training issues were safe delivery, pathology test, primary health care, nutrition, seasonal
diseases prevention and family planning in order to provide quality health services to the
community. The Centres are not facing challenges in conducting their activities in field
level due to their acceptance in the community. However they provided some
recommendations for further improvement of the MCH centre like (KII, 2014):
Ω Need to establish effective communication and coordination with other health
service providers in the MCH working areas like BRAC, Mere Stops and community
clinics, Upazila Parishad health setup of the government for referral services and
other support
Ω Necessary instruments for safe delivery conduction like oxygen cylinder, spare
blood pressure machine need to be available in MCH centre
Ω Capacity building training for both technical and non technical staff is required for
quality service delivery
Ω Arrange benefits for staff like provident fund, gratuity and remuneration package
for positive motivation in service delivery.
Apart from these, MCH programme organized capacity building refresher trainings on safe
delivery and other primary health care issues for midwives and other staff. In the same
period, epidemic control trainings were organized for 440 volunteers to support the
affected people during post disaster situations. Key objectives were to improve the
environment, promote the health services and referral of wounded survivors for
appropriate services. Besides, MCH programme supported to Aila Recovery Operation at
Kamarkhola area of Khulna District. A team comprising 2 doctors, 2 paramedics was
formed and supported in the response operation. However, in depth discussion with the
relevant staff was found some action points for further improvement of the MCH centres
and those are:
Ω More doctors and nurses are required for strengthening the service delivery and
update the MCH centres
Ω IFRC and other PNSs is needed extending their technical and financial support in
capacity building of MCH staff
Ω Review of organogram of the Health Department of BDRCS for effective service
delivery
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
50
46000
48000 47000
51000
54000
52000
42000
44000
46000
48000
50000
52000
54000
56000
2011 2012 2013
Nu
mb
er
of
bag
Blood Bag Collected Blood Bag Supplied
3.3.2 Safe blood services
Blood collection and supply is one
of the main activities of BDRCS
blood banks under the Blood
Department. Blood is collected
and supplied for wounded in
accident, major surgery,
maternity cases and Thalassemia
patients. A total of 46000, 48000
and 47000 bags of blood were
collected from non remunerated
blood donors respectively in 2011
to 2013. However, the status of
supplying number of blood bags
was found higher than the
collection. A total of 51000,
54000 and 52000 blood bags
were supplied respectively during 2011, 2012 and 2013. Blood banks were able to supply
more bags as in case of supplying blood to the children the usual blood bags are being
divided into two. So, the programme is managing more demand through their actual
collection.
In depth information depicts that a total of 48000 non remunerated blood donors donated
blood yearly and total 55000 bags distributed to the people in need. It is mentionable
that Blood Department of BDRCS contributed 20% of the national blood demand. Apart
from these, training also provided to the Unit/Branch volunteers on blood grouping and
blood donation, so that they can arrange blood collection and grouping program in school
level.
Quality of blood is being ensured through cross matching of the blood samples and after
having satisfactory result, blood bags are distributed in the hospitals based on their
requisition. Hospitals have to pay minimum service charges for collecting the blood bags.
However, non remunerated blood donors receive blood bags for free of cost. An amount
of BDT 400-600 and 800 is being charged for hospital Ward and Cabins respectively. The
challenge is having no database (software based) for the blood donors. However, the
Department is maintaining blood donors list manually. Blood Program is trying to develop
a database to maintain the donor’s data properly. The Department officials uttered
challenges like motivating non remunerated blood donors and also retain the existing
blood donors. They also recommended for arranging Club 25 for accelerating the
donation and increasing the number of blood donors (KII, 2014).
Figure 3.31: This line graph representing the
status of collection and supply of blood bags.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
51
7000 8000 9000 10000
2011
2012
2013
9000
9500
10000
8500
9100
9500
Number
Achievement Plan
0
200 205
0
125 118
0
50
100
150
200
250
2011 2012 2013
Nu
mb
er
Plan Achievement
Figure 3.33: The figure represents the number of
volunteers trained on CBHFA and Hand Wash.
Under safe blood service, blood
was supplied to the Thalassemia
patients. A total of 8500, 9100
and 9500 Thalassemia patients
were covered by blood
transfusion angst the target of
9000, 9500 and 10000 in 2011,
2012 and 2013 respectively. A
gradual increase of patient
coverage has been observed
throughout the time frame
however, the yearly
achievement remained less to
the plan.
3.3.3 Primary health services during emergency
Under Primary Health in Emergency Project (PHiE) Project, road safety initiatives were
conducted in Dhaka-
Chittagong, Dhaka-Benapole,
and Dhaka-Shylet
transportation road of
Bangladesh. Key objective
was to provide First Aid
service to the wounded people
in accident. A total of 125 and
118 volunteers were trained
on Community Based Health
and First Aid (CBHFA) in 2012
and 2013 against the plan of
200 and 205 volunteers
respectively. Among 243
training participants, 82 were
female and 161 were male. It’s mentionable that the road safety initiative was
undertaken in 2012 and 2013 that is why 2011 doesn’t represent any status. Trained
volunteers provided First Aid services in 18 selected spots under the afore mentioned
transport ways.
Raising awareness in the community people on emergency health was another key
activity of PHiE project. In this connection, the project conducted numbers of sessions to
aware the beneficiaries on different issues of emergency health, first aid and basic
hygiene. However, the review found that the project was slightly below to cover all its
targeted number of beneficiaries through awareness raising sessions and the overall rate
of achievement has found 85.75% against the target. There were 700 beneficiaries
including 280 male and 420 female against the target of 800 in 2011 and 588
beneficiaries including 200 male and 388 female against the plan of 700 in 2013 covered
through awareness sessions.
Figure 3.32: The chart representing the status of
blood transfusion for the Thalassemia patients
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
52
0
10000
20000
30000
40000
50000
60000
2011 2012 2013
1822 3500
60000
1792 3103
40052
Nu
mb
er
Plan Achievement
Figure 3.34: The above grahp shows the number of
outdoor consultation in 2011, 2012 and 2013
Male 38%
Female 62%
Figure 3.35: The male female ratio in
patient coverage.
3.3.4 Service delivery through Hospitals
Bangladesh Red Crescent
Society has 5 hospitals
throughout the country to
provide medical services to the
community people. These are
Jamison General Hospital in
Chittagong, Amanotgonj
General Hospital in Barisal,
Maternity Hospital in Sylhet,
Maternity Hospital in Chandpur
and Community Hospital in
Banglabazar, Dhaka. However,
some of the hospitals are
running with financial
limitations. Chandpur Maternity
Hospital and Banglabazar Community Hospital were closed for about a year during 2012-
2013. However, since the beginning of 2013 both the hospitals resumed their services.
The review found a gradual increase of
patient’s number who received outdoor
consultation from the hospitals during the
considered period although the program
failed to achieve the target. In 2011 a total
of 1,792 patients against the plan of 1,822,
in 2012, 3,103 patients against plan of
3,500 and in 2013 a total of 4052 patients
against the plan of 6000 were consulted in
the outdoor section of the hospitals. Within
the time frame, a total of 8947 patients
received consultation among which 62%
were female and rest 38% were male.
The above hospitals also provided different surgical and delivery services to the patients.
Numbers of surgeries undertaken by those hospitals were 42, 34 and 606 against the
target of 60, 80 and 800 in 2011, 2012 and 2013 respectively. The rate of overall
achievement was found as about 63%.
In terms of providing child delivery services, the evaluation found relatively improved
rate of achievement as 74% than surgery. The numbers of delivery conducted by those
hospitals were 50, 44 and 365 against the target of 60, 70 and 500 in 2011, 2012 and
2013 respectively.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
53
60 80
800
42 34
606
0 100 200 300 400 500 600 700 800 900
2011 2012 2013
Pat
ien
t N
um
be
r
Plan Achievement
60 70
500
50 44
365
0
100
200
300
400
500
600
2011 2012 2013
Nu
mb
er
of
pat
ien
t
Plan Achievement
Figure 3.36: Number of surgery undertaken
conducted in the hospitals
Figure 3.37: Number of delivery conducted in
the hospitals
Indoor patients consultation found not up to the mark in terms of yearly target that
reflected in the rate of overall achievement (i.g 54.18%) which is very poor. In 2011, 112
patients were consulted against the plan of consulting 250, in 2012 only 78 patients
consulted against the plan of consulting 300 and in 2013, there were 971 patients being
consulted against the plan of 1500. However, the trend seemed upward which gives a
positive indication.
3.4 General Understanding on Strategic Development Plan 2011-15
This part was designed to extract information on general perception about Strategic
Development Plan 2011-15 of BDRCS from four separate groups of respondents. The
groups consist of the representatives from BDRCS Top Management (e.g Chairman,
Secretary General, Director and Programme/Project In Charge), BDRCS Reporting Focal,
IFRC BD Delegation and ICRC & PNSs. This part of the result analyzed data on general
understanding, involvement of different group members in SP development and its
implementation. It also reports on the alignment of 4-Year Development Plan 2013-16
with SP 2011-15 of BDRCS. At the end of this section, recommendations on Strategic
Development Plan and its implementation from the respondents has been summarized.
3.4.1 Status of hearing about SP 2011-15, BDRCS
The four categories of the respondents were asked whether they have heard about
Strategic Development Plan (SP) 2011-15 or not. The status was found satisfactory as in
an average 90.75% of the respondents were able to respond positively regarding SP
2011-15, BDRCS. Meanwhile, a considerable percentage of respondents in BDRCS
Reporting Focal (15.38%) and IFRC BD Delegation (18.18%) were found unknown to this
document. Most of the respondents treated SP 2011-15 as Disaster Risk Management
document.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
54
Figure 3.38: The figure represents the SP hearing status by the different group of
respondents (N=55)
3.4.2 Status of involvement of different groups in SP development
In terms of involvement, query was raised whether the participant had any contribution
towards preparing the SP 2-11-15 document or not. Status was found varied among the
groups like BDRCS top management and reporting focal persons were more involved then
the IFRC and ICRC & PNSs officials in the SP preparation. More specifically, involvement
of BDRCS top management had the height percentage (65.21%) and IFRC BD Delegation
(9.09%) had the lowest participation in preparing the document. In depth assessment
also found that effective involvement of the ICRC, IFRC and PNSs in preparing the
prestigious document would contribute towards formulating more realistic and interactive
document.
Figure 3.39: The figure represents the status of involvement of different group of people
in preparing the SP 2011-15 document (N=56).
In depth statistical analysis also found a lower percentage of active involvement by the
respondents who were engaged in the process of preparing the document; only 20% of
the BDRCS Reporting Focal person was involved in the process actively. However, partial
contribution was found better in respect to other criteria’s of involvement and in an
average 65.35% of the respondents from all the groups were partially involved in the
0.000
20.000
40.000
60.000
80.000
100.000
BDRCS Top Management
BDRCS Reporting Focal
IFRC BD Delegation
ICRC & PNSs
95.652 84.615 81.818
100
4.348 15.385 18.182
0
Pe
rce
tage
(%
)
Yes
No
0.000 20.000 40.000 60.000 80.000 100.000
BDRCS Top Management
BDRCS Reporting Focal
IFRC BD Delegation
ICRC & PNSs
65.217
35.714
9.091
25
34.783
64.286
90.909
75
Percentage (%)
No
Yes
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
55
process. Besides, average 20% of the respondents from BDRCS top management and
reporting focal were engaged only at the beginning of the document development
process. Moreover, respondents from BDRCS reporting focal (20%) and ICRC & PNSs
(50%) were just attended in a meeting held on development of the document.
Figure 3.40: The figure represents the level of involvement of different group of
respondents on different criteria in preparing SP 2011-15, BDRCS (N=22).
3.4.3 Division where groups provided institutional input/support
Majority of the respondents who were involved in the SP developing process, contributed
in Organizational Development part among the three core programmes under the
Strategic Development Plan 2011-15, BDRCS. About half of the respondents from BDRCS
management, reporting focal and ICRC & PNSs and 100% from IFRC BD Delegation
provided their thought in developing Organizational Development part in the SP 2011-15.
In Disaster Management, as the second core area of SP 2011-15, 40% (in average) from
BDRCS management and reporting focal provided support in developing the inner part.
The contributor was found less in the Health part, as the third core area in SP 2011-15,
compare to last two; only 20% of the respondents from reporting focal and only 7 %
from the top management said they have contributed to prepare the health part. Most
interesting observation is, BDRCS Reporting Focal persons were engaged in all the core
areas of the document rather than the representatives from top management.
0.000
20.000
40.000
60.000
80.000
100.000
Active Partial Only at the begining of this process
Just attended a meeting
7.143
71.429
21.429
0
20
40
20 20
0
100
0 0 0
50
0
50
Pe
rce
nta
ge (
%)
BDRCS Top Management BDRCS Reporting Focal IFRC BD Delegation ICRC & PNSs
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
56
Figure 3.41: The figure represents the status of contribution by different group of
respondents in developing Core Areas of SP 2011-15 (N=23).
Immediate after, the respondents were asked to report on exactly where, i.e. narrative
writing, objective setting, preparing Plan o Action (PoA), and all the mentioned issues,
they have provided support. The assessment also found that half (50%) from BDRCS
Reporting Focal and ICRC & PNSs and all the respondents of IFRC BD Delegation
contributed in narrative writing, objective setting and preparing PoA in SP 2011-15.
Besides, 25% of the BDRCS reporting Focal person provided support in preparing PoA and
formulating objective. It’s interesting that involvement of BDRCS Top management, in
almost all afore mentioned issues, were not up to the mark; specifically 50% in preparing
PoA and 28.57% in objective setting.
Figure 3.42: The figure represents the status of contribution by different group of
respondents in core areas of SP 2011-15 (N=21).
In terms of reviewing the inputs provided in the document by the respondents under
different response group, 40% of the respondents of top management uttered that they
have reviewed their inputs before finalizing the document. On the contrary, majority
(72.72%) of the reporting focal person and considerable portion (26.66%) of top
management weren’t able to review their input in the SP. Besides, 33.33% respondents
0.000 50.000 100.000 150.000 200.000 250.000
Organizational Development
Disaster Management
Health
Missing
53.33
40
6.7
0
40
40
20
0
100 0
0
0
50 0
0
50
Percentage (%)
BDRCS Top Management BDRCS Reporting Focal IFRC BD Delegation ICRC & PNSs
7.14
28.57
50
7.14 7.14 0 0
25
50
25
0 0 0
100
0 0
50
0
50
0 0.000
10.000 20.000 30.000 40.000 50.000 60.000 70.000 80.000 90.000
100.000
Narrative Writing Objective setting Plan of Action All of the mentioned issues
Objective setting & PoA
BDRCS Top Management BDRCS Reporting Focal IFRC BD Delegation ICRC & PNSs
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
57
from the BDRCS Top Management status and all from ICRC & PNSs didn’t get opportunity
to review the inputs.
Table 3.43: Status of reviewing provided input before finalization (N=29).
Sl.
No. Respondents category
Response criteria
Yes, I reviewed
my input
No, I wasn't
able to do that
I didn't get
any
opportunity
1 BDRCS Top Management 6 (40) 4 (26.66) 5 (33.33)
2 BDRCS Reporting Focal 1 (9.09) 8 (72.72) 2 (18.18)
3 IFRC BD Delegation 0 1 (100) 0
4 ICRC & PNSs 0 0 2 (100)
After preparing the document, no formal orientation program was held in BDRCS with its
different level of audiences. However, respondents from BDRCS top management
(52.38%) and reporting focal person (25%) uttered that they receive informal orientation
on the developed SP 2011-15 through bi-lateral or multilateral discussion or different
meeting at different time. However, respondents from IFRC and ICRC & PNSs didn’t
receive any king of orientation on the document.
Figure 3.43: Status of receiving formal orientation on Strategic Development Pan 2011-
15 by different group of respondents (N=46).
IFRC BD Delegation (N=9) and ICRC & PNSs officials (N=8) were asked whether they
consider Strategic Development Plan 2011-15 during resource mobilization to any
Department/Programme/Project of BDRCS or not. It was found that all the ICRC & PNSs
and 66.66% of the IFRC officials treat SP document as a guiding tool for financial
contribution to the National Society (NS). In depth information also depicts that IFRC
checked the proposals whether it’s overall objective is aligned with SP, the plan is aligned
with 4 Years Development Plan and both of these criteria before supporting National
Society. Besides, majority (75%) of the ICRC & PNSs checked both of the criteria for fund
mobilization.
0.00 20.00 40.00 60.00 80.00 100.00
BDRCS Top Management
BDRCS Reporting Focal
IFRC BD Delegation
ICRC & PNSs
52.38
25
0
0
47.62
75
100
100
Percentage (%)
Yes
No
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
58
0.000
20.000
40.000
60.000
80.000
100.000
Yes No
83.33
16.66
50 50
Pe
rce
nta
ge (
%)
BDRCS Top Management BDRCS Reporting Focal
5.000 50.000
Development Objective is allaigned with SP
Objective
Activities are allaigned with SP Objective
Both of these
35.71
7.14
57.14
25
25
50
Percentage (%)
BDRCS Reporting Focal BDRCS Top Management
Table 3.4: Areas checked in the proposed proposal (N=14) before financial resource
mobilization to National Society (NS).
Respondents group
Response area
Whether the overall
objective is aligned
with SP or not
Whether the plan is
aligned with 4 Years
Development Plan or not
Both of
these
IFRC BD Delegation 2 (33.33) 2 (33.33) 2 (33.33)
ICRC & PNSs 2 (25) 0 6 (75)
3.4.4 Alignment of 4 Years Development Plan with SP 2011-15, BDRCS
Bangladesh Red Crescent Society has a 4 Years Development Plan which was formulated
to support achieving the goals of SP 2011-15. BDRCS Top Management and Reporting
Focal person reported on whether they were involved in the plan development process or
not. It was found that majority (65.217%) of the respondents from BDRCS top
management were involved but majority (61.53%) of the reporting focal person were not
involved in formulating 4-Year Development Plan 2013-16, BDRCS. In case of addressing
SP 2011-15 in formulating Development Plan, most of the respondents from BDRCS Top
Management uttered that they have considered that, however half of the reporting focal
responded that they did not consider in formulating their plan development.
In depth query also reported that half of the respondents from BDRCS top management
and more than half (57.14%) of the reporting focal person have considered both
alignment of activities of the development plan with SP objective and development
objectives with SP objective during formulating development plan. Moreover, the
respondents (N=33) also reported on the status of implementing 4-Year Development
Plan 2013-16 as per SP 2011-15 of BDRCS. It was found that majority of the respondents
from BDRCS top management (77.27%) and reporting focal (63.63%) are implementing
their development plan according to Strategic Development 2011-15, BDRCS.
The following figure represents the status of having hard copy of SP 2011-15 at different
category of respondents. The data indicates that majority of BFDRCS top management
Figure 3.44: Status of addressing SP 2011-15 in
formulating 4-Year Development Plan
Figure 3.45: Status of considering SP 2011-15 in
formulating 4-Year Development Plan
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
59
(87.95%) and ICRC & PNSs (75%) respondents have the hard copy of SP document and
majority of BDRCS reporting focal (69.23%) and IFRC & ICRC (81.81%) do not have the
copy of SP 2011-15.
Figure 3.46: Status of having hard copy of Strategic Development Plan 2011-15,
BDRCS.
3.4.5 Recommendation on the SP 2011-15 and its implementation
The respondents made some recommendations on the formulation, implementation and
progress tracking of the strategic development plan 2011-15. The summary flinging are
mentioned below:
All the staff of BDRCS need to have a formal orientation on Strategic Development
Plan 2011-15 to have clear understanding on the document.
The Four Years Development Plan of BDRCS and other plans need to be more aligned
with Strategic Development Plan 2011-15.
PMER Section needs to start the progress monitoring/periodic assessment of Strategic
Development Plan 2011-15, BDRCS and its measurement tool need to be in place.
Progress on Strategic Development Goals and 4-Year Development Plan (2013-16)
need to be followed up on regular basis
Outcome level results statements under five strategic goals of SP 2011-15 need to be
formulated
The document needs to be circulated officially to all Movement Partners, South Asian
Regional Delegate, Asia Pacific Zone and Geneva.
The SP has ambiguous theoretical goals which needs to be realistic and achievable
Guideline should be developed on how to implement and use of SP 2011-15
Shelter and WASH components need to be included in the strategic plan
3.5 Strength, Weakness, Opportunity and Threat (SWOT) Analysis
Four groups, including representatives from the Departments, Programmes and Projects
of Bangladesh Red Crescent Society (BDRCS) worked together for a half day to formulate
separate SWOT on Organizational Development, Disaster Management, Health and
Central Services. Later on, group leaders represented each of the areas under their
SWOT and made necessary clarifications and adjustment based on the comments made
by other participants in the house. Apart from these sectoral SWOTs, the aim was to have
an Organizational SWOT compiling all fur SWOTs. During compilation, PMER Section
BDRCS Top Management
BDRCS Reporting Focal
IFRC BD Delegation
ICRC & PNSs
86.957
30.769 18.182
75
13.043
69.231 81.818
25
Yes No
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
60
received all together 33 strengths, 29 weaknesses, 16 opportunities and 9 threats under
four sectors. Further discussion, with required justification, clarification and modification
on each of the issues mentioned in the SWOT, was carried for ‘Preparing Organizational
SWOT’. The process of elimination was implied to reduce the number of statements and
the following is the ‘Organizational SWOT’.
Strength Weakness
1. Significant, generous, volunteers based
humanitarian organization.
2. Performing an auxiliary role to Bangladesh
Government in line with 7 Fundamental Principles
of the RCRC Movement.
3. Immediate and effective disaster response
mechanism (i.e cyclone shelter, warehouse,
disaster preparedness stock, disaster response
emergency fund, appeal, contingency plan, and
other response tools like RDRD, NDRT, UDRT,
CDRT).
4. Experienced staff and trained volunteer network in
humanitarian service.
5. Regulating with relevant and required policies and
strategies (i.e Service rule, Gender policy, Cyclone
Management Policy, Fundraising Policy, Disaster
Risk Management and Climate Change Adaptation
Strategy, Response Manual, Branch Operational
Manual, Finance & Audit manual).
6. Unique Restoring Family Link services during
emergencies and missing cases
7. Contributing 20% of National blood demand
through non remunerated blood donation
8. Sustainable MCH centres in rural areas contributing
Millennium Development Goals.
9. Implementing joint flagship Cyclone Preparedness
Programme (CPP) with Bangladesh government in
vulnerable coastal districts of Bangladesh.
10. Well organized, structured and decentralized
operational set up at National Headquarters to 68
Branches.
11. Regular sources of funding, moveable and
immovable assets (i.e. land, buildings, vehicles
and others required logistics).
12. Strategic Development Plan (2011-15) and 4-
Year Development Plan (2014-17) for
Departments and Units are in place.
13. Existence of Participating National Societies
(PNSs), IFRC and ICRC in BDRCS.
1. Lack of policies and strategies
on Human Resource,
Procurement, Volunteer and
PMER issue
2. Inadequate promotional
initiatives, including
dissemination of auxiliary status
and 7 Fundamental Principles
with relevant stakeholders for
organizational branding
3. Inadequate funding and
resource mobilization
4. Lack of archiving, office
management and sharing of
knowledge
5. Lack of sustainability and phase
out strategy in programming
6. Insufficient practice of
transparency and accountability
7. Lack of proper safety, security
and insurance coverage for the
volunteers and staff
8. Traditional mind set and lack of
professionalism among BDRCS
management and governance
9. Governance interference in
management and malpractice
10. Lack of proper networking,
coordination and representation
of BDRCS at National and
International level
11. Implementing only donor based
project rather than utilizing
own fund.
Opportunity Threat
1. Emerging demand of First Aid and Search & rescue
training across the country.
2. Promote organizational sustainability (financial and
institutional) through effective communication and
coordination with GoB, like minded NGOs, potential
individuals and others institutions
3. Worldwide network of Red Cross and Red Crescent
1. Existence and performance of
other competitive organizations
in humanitarian and voluntary
services.
2. Political influence & instability,
national crisis and personal
threat during implementation.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
61
Movement and IFRC’s learning platform for
capacity building.
4. Online get way service and utilization of social
media for raising fund and organizational image
building.
5. Expansion of Navision software to Unit/Branch
level for financial management
3. Increased litigation challenges
for real estate of BDRCS.
Source: SWOT workshop, 2014
Sl.
No.
Indicator statement Unit
measurement Average % of
achievement
1 Early warning/ strengthen the warning system 83.33
2 Community mobilisation/ Community mobilisation
through training volunteers and effective networking
100.924
3 NDRT / Formulate NDRT (2 teams) / I NDRT 100.000
4 UDRT / Formulate UDRT (20 teams at Branch level) 100.000
5 CDRT/ Formulate CDRT - as per programme
requirements
113.880
6 NDRWT/ Formulate NDRWT (2 teams) 100
7 Community resilience through programmes 100.000
8 Formulating contingency and response plan 100.000
9 SOP formation and approval 100
10 Developing Regional/Domestic contingency plan/
review existing plan 100
11 Search & Rescue/capacity building on S&R 100
12 FA - First Aid/ Scaling up of First Aid service 75.460
13 WASH/ Introduce WASH and integrate in future
programme planning
92.64
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
62
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
63
Chapter Four: Conclusion and Recommendations
Based on the analysis of available data and rigorous discussion on the results, the review
team comes up with specific programmatic summary and also propose recommendations
on the areas where the organization has to put its further contribution for improvement.
4.1 Organizational Development
In keeping with the above information the review team concludes with mixed impression
on achievement and failure against the planned target of OD activities in the SP 11-15.
The new Legal Base was planned to get enacted by the parliament in 2011 which was not
done. Meanwhile several initiatives including regular communication, inter-ministerial
orientation and meeting, Chairman’s letter to hon’ble prime minister and other
correspondence took place between BDRCS and relevant Ministries to expedite the
process. However, things were not in the control of BDRCS as the process completely
depends on the Government.
Strategic plan formulation was also not completed in time resulting delay in preparation
of corresponding 4-Year Development plans of all Departments and Units. PMER section
was established as per the plan but lack of proper understanding and sensitization of
PMER issues in BDRCS got the strength of PMER Section be misused. Besides, one of the
major activities, the Organizational Capacity Assessment and Certification (OCAC), was
not conducted during stipulated timeline. In regard to support to Unit for capacity
building, Branch Operation Manual (BOM) was drafted but not finalized during planned
timeline. ICT Section under P&D Department successfully completed DD project However,
a huge gap has been identified between target and achievement in distributing official
email account.
In regard to asset management, a policy was supposed to be formulated in 2012 but no
progress found in the review during the period. However, overall all rent collection from
different sources of BDRCS was satisfactory and was about 90% of the target.
Performance of Administration Department was relatively better. They have almost met
the target of issuing and distributing ID and Visiting cards, taking effective security
measures and observing National and International days during the review period.
Besides, the progress on formulation and approval of new organogram and Job
Description was very low in terms of target.
It was found that various relevant trainings were planned and organized for skill
development of youth and volunteers. However, number of FA training, achievement of
ToT on Disaster Management and Search and Rescue wasn’t up to the target. Besides,
the progress of conducting staff capacity building, commercial and refresher training was
found satisfactory. However, the training department don’t have any training calendar for
systematic accomplishment of events.
Therefore, the above discussion reveals that the OD activities of BDRCS have both
positive and negative momentum in terms of implementation of SP 2011-15. As per the
result of this mid-term progress review, the OD practitioners of the Society needs to
emphasize on actions for addressing the gaps in order to attain the aforementioned
strategic goal by the stipulated time frame.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
64
In keeping with the above findings the review team came up with following
recommendations for improvement of OD intervention in BDRCS:
Proper sensitization and common understanding is very much important among all of
internal and external stakeholder of BDRCS regarding Organizational Development
issues to formulate the organizational as the strong one.
There should be clear alignment between strategic and operational plan. It is
recommended formulating operational plan for a period of no more than 2 years for
proper progress tacking and achieving expected result.
Resource mobilization guideline, human resource and procurement policy need to be
in place for effective and efficient utilization of both financial and human resources.
Database of all properties of BDRCS and its close supervision by the NHQ BDRCS is
necessary for better assets and real estate management.
The process of enactment of new legal base should be accelerated through
establishment of effective communication and follow up in the relevant Ministries and
Parliament with the support of Movement Partners.
The Branch/ Unit Operation Manual (BOM), Governance Manual, Asset Management
Policy, Code of Conduct and Integrity Policy need to be in place for strengthening
Branch and NHQ capacity.
A comprehensive Monitoring & Evaluation plan needs to be developed for each
departments for tracking the progress, improving the quality of services and also
ensuring transparency.
The Training Department should maintain a training calendar for both staff and
volunteer capacity building and also for commercial training. Training Needs
Assessment (TNA) should be carried out each year through the organization with the
lead of Training Department. Besides, coordination mechanism between Training and
other Department, Programme and Project should be established in terms of providing
training.
Organize more capacity building training and refresher for the volunteers for effective
service delivery. Besides, producing master trainers through ToT (Training of
Trainers) can be very effective way to replicate relevant capacity building initiatives
further.
School co-curriculum activities need to be more expanded by designing of more
programs for school and college students in return to their co-curriculum fee.
Otherwise, BDRCS may have loosing trust of school/college students, teachers and
even guardians.
4.2 Disaster Management
Six programmes and projects including CCA, CBDRR, V2R, UDRR and CDI along with
three Departments (e.g. Disaster Risk Reduction, Disaster Response and Tracing)
contributed towards achieving proposed Plan of Action (PoA) under Disaster Management
part of the SP 2011-15. Key finding against the plan are as follows:
BDRCS interventions altogether conducted awareness raising session, community
consultation, meeting and mock drill in the targeted communities for building resilience
through sharing necessary information and demonstrations by the trained volunteers
and staff. Average achievement was slightly more than our expectation (107.7%) and
162480 community people were covered through mobilization initiatives.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
65
Disaster responses were conducted in major natural and man-made calamities across
the country effectively by the Disaster Response Department along with the support of
other Departments and Units/Branches during the review time frame. Response
management tools like NDRT, NDWRT, UDRT, CDRT, warehouses in strategic locations,
contingency plan for cyclone and flood are in place and among which NDRT and
NDWRT were being deployed in the response operation in time. During the reporting
period, a total of CHF 4608535 were distributed to 196544 survivors’ families under
South-East, flood, flood early recovery, Satkhira water logging, cold wave response
and other.
Restoring family linkage (RFL) intervention in disaster and related events is being
treated as a unique response in humanitarian movement in Bangladesh. A specific
Department named ‘Tracing’ is implementing these activities through trained tracing
team in all 68 Units/Branches. Besides, foreign detainees were also supported in
District jails of Bangladesh through relief distribution. A total of 995 families received
RFL services during the reporting period.
WASH initiatives like installing or repairing of safe water sources, sanitation system
and awareness raising sessions were conducted in the project intervention areas.
Average achievement was found as 90.19%. A total of 85333 beneficiaries were
reached through WASH activities.
Strengthening the services, capacity building training on Search & Rescue and First Aid
were conducted with the volunteers and BDRCS staff. A total of 141 First Aid training
and 8 Search & Rescue were completed with 638 and 100 participants respectively.
Besides, 169 volunteers and staff received training on RFL. Moreover, staff from
different programme and project also received training cash based programming, relief
management etc.
Based on the progress review findings, the team concludes with the following
recommendations:
More training on response tools for developing human resources (both staff and
volunteers) and organizing refreshers course need to be included in Plan of Action
(PoA). Moreover, trained female representatives should be considered in the
deployment to handle gender sensitive cases during response which will also
contribute towards empowerment.
Local political influences are hindering proper selection of beneficiaries for providing
assistance which is also creating image crisis for the organization. In this connection,
making the beneficiary selection process fully community based may be an effective
option to make it so.
Orientation on Basic Principles and Code of Conduct of RCRC Movement needs to be
conducted among UEC, ULO, Volunteers and BDRCS staff for enhancing transparency
and accountability in programming.
A comprehensive Monitoring & Evaluation plan needs to be developed for each of the
programme, project under disaster management initiatives for tracking the progress,
improving the quality of services and also ensuring transparency.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
66
4.3 Health
In terms of service delivery, it can be said that MCH Centres, outdoors and indoors of the
hospitals and blood centres were played a vital role in achieving their targeted plan
during the review period. Under the Strategic Goal 2 of SP 2011-2015, number of
services were provided on ANC, PNC, Non-complicated delivery EPI, First Aid, emergency
health services, safe blood services, pathology test, safe blood services, surgery, patient
consultation in and outdoor to the community people in time of need.
It has been found that the average beneficiary coverage through the health care
services is 81.70% during the review period. It seems quite significant but there is
still room to increase the beneficiary coverage which we can take as a learning of our
past experience.
Capacity building training and basic knowledge sharing on health issues were
organized by the MCH Centre, Blood Program, Hospitals and PHiE project. Several
trainings on different health issues were organized during 2011 to June 2013 in order
to enhance capacity of the programme staffs and volunteers. The review data depicts
that volunteers and staff received numbers of trainings on health issues.
MCH Centres, a community based initiative are delivering services to the community
people. Sustainability of the MCH Centres is one of the main concern of BDRCS and
32 centres out of 56 are now financially sustainable. However, the centres are running
with financial limitations demand more concentration in order to become sustainable
one.
Blood programme is a one of the core programme of the Health Department but as
per data, there were very limited exceptions of blood centres against the target
during the review period. The average rate of blood collection and distribution through
current setup was found 85% which is contributing meeting national blood demand.
The increasing demand of safe blood transmission indicates expansion of the
programme in different areas to cover significant number of beneficiaries.
Based on the progress review findings, the team concludes with the following
recommendations:
Regular planned activities under MCH, Blood and Outdoor programmes hampered due
to shortage of technical staff like doctor, lab technician, midwives and non technical
staff at field level. Hence, skilled staff with proper orientation is required to run the
programme more effectively.
Staff should be given proper training like ToT on psychosocial support, basic midwifery,
advance pathology test and financial management to prepare themselves to deliver the
services to the community.
Sustainability of the community based MCH centres is one of the key priorities of
health programme of BDRCS. In this connection, community mobilization and
ownership, sustainability plan and donor support is required to ensure the
sustainability of the MCH Centres.
An monitoring and evaluation plan needs to be in place for health interventions of
BDRCS for tracking the progress and maintaining the quality of the services which will
contribute towards ensuring accountability and transparency. Besides, the supervision
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
67
that has been conducting in the field needs to have formal report which will also have
implications towards improving the staff performance and service quality.
Coordination among similar service providers like BRAC, Mere Stops and government
community clinic is required to establishing and making the referral services functional.
This will contribute towards supporting patients who needs specialised and secondary
health care services.
Further initiatives like organizing blood campaign and awareness raising sessions are
required to increase the number of non remunerated blood donors across the country.
Besides, to meet emerging demand of blood suggests increasing number of blood
banks.
4.4 The document: SP 2011-15 The formulation of SP 2011-15 document for BDRCS is being treated as the wise step
towards implementing systematic and planned interventions in Bangladesh. However, the
document doesn’t have wider well understanding due to having no formal orientation and
proper sensitization among the stakeholders. Moreover, the planned activities mentioned
under three core programmatic areas doesn’t have any year round target which also
hampered the actual measurement of progress in some cases. The following
recommendations need to following during formulating next version of the document.
The guideline on formulating strategic development plan developed by
International Federation of Red Cross and Red Crescent Societies should be
followed during preparing SP for BDRCS. Meanwhile, an internal resource pool
may be developed for formulating new Strategic development plan for BDRCS
through organizing capacity building training and other methods.
A participatory approach needs to be followed in formulating a comprehensive
strategic development plan document for BDRCS. In this regards, representation
of BDRCS top management, IFRC, ICRC and Participating National Societies
(PNSs) should be ensured at relevant stages in preparing the document.
Orientation session on the prepared SP document should be organized with
relevant stakeholders in proper time for common understanding and also
perceiving the importance of the document. Moreover, an annual tracking tool
needs to be in place so that the concerned authorities will be able to aware the
progress of the planed interventions.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
68
5. Annex
5.1: Indicators under SP 2011-15
Organizational Development:
Activity/setting of indicators (proposed) Methodology of Monitoring Source and Means of Verification (MoV)
Department/Programme/Project
Strategic Plan 2011-2015 formulation / implementation /Midterm evaluation of SP
- Published and distributed BDRCS SP - % of implemented activity according to SP - Conducted Midterm evaluation at the last quarter of 2013
- Review of doc - KII with dept. focal, FGD with
volunteers/programme persons/stakeholders
- KII, FGD, Document review
- Office order/P&D register - Primary data, review reports,
documents, financial document
- Evaluation report
- Planning & Development, all the Departments
HR Reform/Orientation and implementation - Developed and approved organogram for BDRCS - Prepared and approved JD for BDRCS staffs - No of workshops conducted to orient ogranogram and JD
- Review of document
- Office order/meeting resolution, workshop report & participant lists
- HR, P&D,
Branch capacity building (develop 20 C category Branches to B category) /12 C category to B and 7 B to A category.
- Capacity develop 20 C category Branches to B category - Capacity developed 12 C category to B - Capacity developed 7 B to A category
- KII, Observation, document
review
- Primary data, secondary document/ register, training report, photo
- P&D, Unit Affairs
NHQ Capacity building (strengthening Dept & Programmes) - Formulated and finalized 4 years plan by the departments - Distributed ICT logistics to departments - Provided training on reporting to 24 dept/programme/project
- Observation
- Document review, register, training report, logistics handover document
- P&D, ICT,
PMER–MAR / 4-years Development Plan for 68 Branches and NHQ, Branch Operations Manual, Partnership Building/ communication strategy develop
- 24 MARs published in BDRCS website - Conducted planning workshops in 68 Branches and 22
department - Developed and approved BOM for BDRCS - No of partnership with NS developed with BDRCS
- Observation, review of document, KII with consultant
- Workshop schedule, register, MoUs, record of discussion
- PMER
DD Project /Monitoring and expansion
- No of ICT logistic provided to Units & Departments - No of email account distributed
- Observation, review - Register, logistic handover
document
- ICT
ICT capacity development for the 20 Branches - No of ICT logistics provided to Branches - No of orientation on ICT conducted
- Observation, review - Register, handover document - ICT
Fund Raising (President / Prime minister dinner and other activities) - Conducted dinner for fund raising
Fundraising
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
69
- Amount of BDT collected by selling BDRCS souvenir items - Amount of BDT collected as house rent
Resource mobilisation - both Financial and Nonfinancial; develop Assets Management Policy, RMS
- Developed and approved Asset management Policy - Updated RMS database for NHQ and Units
Fund raising, Y&V, ICT
Orientation on Legal Base and Statutes - Conducted orientation on BDRCS Legal base and Statutes
- Observation - Participants list, photo - P&D
Introduce HD for all programme level planning - Conducted orientation/workshop on HD
- Observation - Participants list, photo - OD
Skills based development of RCY- Youth Pledge, Pledge 129, YABC - No of training on Search & Rescue, First Aid, RFL, Dead body
management conducted with no of RCY
- Observation, FGD - Primary data, participants list, photo
- Y&V
Co-curriculum activities - expansion upto 40%, ToT, Youth Leadership Workshop/ update 70% ToT for teacher, leadership workshop, RCRC basic, DM, SAR
- 70% expansion of co-curricular activities - Conducted ToT on Youth Leadership, RCRC Basic, DM, SAR - Conducted ToT for teachers on Youth Leadership, RCRC Basic,
DM, SAR
- Observation, FGD
- Primary data, ToT report, annual report, participant list
- Y&V
National Volunteer Camp at 3 Divisions - Organized yearly youth camp
- Review
- Camp report - Y&V
Assessment and implementation of OCAC - Organized OCAC for BDRCS - No of initiatives taken against OCAC recommendation
- Review
- Office order, participant list - P&D
Midterm evaluation led by PMER for all ongoing projects - No of evaluation supported by PMER
- - PMER
Misuse of emblem campaign - No of awareness raising orientation/campaign/workshop
conducted by Information Department
- Review
- Report/participant list/videos/photos
- IR
Gender sensitization through programs
- No of gender sensitization activities conducted by the programmes
- KII with department focal, - Project/programme
document
- OD
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
70
DRM INTERVENTIONS:
Type Activity/ setting of indicators (proposed) Methodology of Monitoring Source and Means of Verification
(MoV)
Detp./prog/proj
Prep
ared
ness
Early warning/ strengthen the warning system - Received early warning from BMD - Conducted regular coordination meeting
between CPP and BMD - Early warning equipments are functional - Conducted training and refreshers on early
warning system
- Document review - Observation - FGD
- Meeting minutes/schedule - Training report/register/money
receipt
Response , CPP Training Dept / DRM, CCA Project
Community mobilisation / Community mobilisation through training volunteers and effective networking
- No of community consultation, awareness raising session conducted
- No of Mock Drill conducted - No of training conducted with volunteers - No of meeting conducted with CBOs - Community people participated in
preparedness activity
- Document review - Observation
- Videos of mock drill - Register - Participant list - Reports
DRM Dept – CBDRR Prog., CCA project, UDRR, V2R & IFRC
NDRT / Formulate NDRT (2 teams) / I NDRT - 3 NDRT teams formed - No of training conducted with NDRT
members - NDRT members deployed in response
- Review
- Participant list - ToR & office order
- Response department
UDRT / Formulate UDRT (20 teams at Branch level)
- 30 UDRT teams formed - No of training conducted with UDRT
members - UDRT members deployed in response
- Review
- Participant list
- ToR & office order
- DRM – CBDRR, CCA,
UDRR, V2R and IFRC
CDRT/ Formulate CDRT - as per programme req. - No of CDRT teams formed - No of training conducted with CDRT
members - CDRT members deployed in response
- Review
- Participant list - ToR & office order
- DRM – CBDRR, CCA, UDRR, V2R and IFRC
NDRWT/ Formulate NDRWT (2 teams) - 2 NDRWT teams formed - No of training conducted with NDRWT
members - NDRWT members deployed in response
- Review
- Participant list - ToR & office order
- DRM – CBDRR, CCA, UDRR, V2R and IFRC
Community resilience through programmes - No of awareness raising campaign conducted
- Document review
- Report - Photo
- DRM – CBDRR, CCA, UDRR, V2R and IFRC
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
71
- Provided IG training to the community - Provided IG support for livelihood
- Beneficiary list - Participant list
Revise ASO and get approval - Conducted ASO revision workshop - Approved ASO by proper authority
- Document review
- Participant list - Document
-
Formulating contingency and response plan - Formulated contingency and response plan
- Document review - Document -
SOP formation and approval - Formulated SOP - Approved SOP
- Document review
- Participant list - Document
- Response, DRM
Em
erg
en
cy r
esp
on
se
Developing Regional/Domestic contingency plan/ review existing plan - Conducted workshop to formulate contingency
plan in regional/domestic level in 2011 - Conducted workshop to review existing plan
- Document review - Contingency plan - Workshop participant list
- Response, DRM
Search & Rescue/capacity building on S&R - No of search & Rescue training conducted - No of participant covered - % of trained volunteers deployed in S&R
operation
- Survey - Observation
- Participant list - Training schedule - Deployment record
- Training department, Y&V Department DRM
FA - First Aid/ Scaling up of First Aid service - No of people covered through First Aid services - No of First Aid training conducted - No of First Aid kits purchased
- Document review - Participant list - Training schedule - Register
- Training department, Health, Y&V Department
- DRM
PHiE / Strengthening PHiE Health Department
WASH/ Introduce WASH and integrate in future programme planning - Included WASH interventions in
programme/project planning - No of awareness raising sessions conducted on
WASH - No of safe water source installed or repaired - No of sanitation system installed or repaired
- Survey - Observation
- Participants list - Project reports
DRM, Response, IFRC
Relief Management/ Enhanced capacity in Relief Management -construct new warehouse, introduce better techniques in management etc. - No of training conducted on Relief Management - Formulated standard beneficiary selection criteria
for relief distribution - No of new ware house established in strategic
location - Established complaint mechanism in relief
management
- Survey - Observation
- Training schedule - Participants list - Project reports - Received box/list
- Response Department, Training Department , DRM
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
72
- No of reports prepared on relief distribution - No of workshop conducted
Restoring Family Link/ Strengthen RFL activities - No of family received RFL service - No of volunteers trained on RFL - No of volunteers deployed in response - No of RC message exchanged in and abroad
- Observation - Training schedule - Participants list - Record - Register
- Tracing, IR Department
HEALTH INTERVENTIONS:
Activity/ setting of indicators (proposed) Methodology of Monitoring
Source and Means of Verification (MoV)
General Health (MCH centres - expansion by 7 new centres)/ expansion of 3 centres - Established 8 new MCH centers - No of ANC, PNC, delivery conducted - No of beneficiaries covered by counselling session - No of child and maternal covered EPI session conducted at MCH centres - No of pathology services (various tests) provided - Patient satisfaction measurement (%)
Health department, Blood and MCH
General Health – strengthening of existing MCH and blood centres - Renovated MCH and blood centres - Organized capacity building training
Safe Blood services/ establish 2 more centres / establish 2 more centres - Established 3 new blood centres - No of blood collection sessions organized for blood collection - No of blood bags collected - No of blood bags supplied - % of retention of blood donors
PHiE: Road safety/ cover 2 new high way/ cover 2 new high way - No of volunteer trained on First Aid and Counselling - Project covered 3 new road - No of First Aid service provided by the volunteers - No of parent referred - No of service providing posts established
PHiE: Emergency Health - No of volunteer trained on CBHFA and hand wash - No of awareness raising session conducted with the beneficiary - No of services provided - Increase of knowledge on CBHFA and basic hygiene
Hospitals - No of patients consulted (outdoor)
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
73
- No of indoor patients consulted - Renovated hospital cabin and wards - No of surgery undertaken - No of delivery conducted , - Patient satisfaction measurement (%), - Fund flow (increased / decreased), - No of hospital managed locally
Health education - No of group discussion conducted with the beneficiaries
HIV Programme - No of counselling session conducted at the community level - Increased knowledge of beneficiaries on HIV issues (% from baseline data)
5.2: Qualitative indicators and checklist of FGD, KII and Interview
Indicator (Qualitative) Implementing
authority
Data Collection
Method/
Respondent
Checklist Place, Timeline & Budget
% of volunteers
and unit officials have Knowledge on SAR, FA, RFL and Dead Body Management
OD & DM FGD with
volunteers and
Unit Officials.
FGD Checklist: Have you received any training on SAR/ FA/ RFL/ DBM? What are the objectives and overall impression about the
trainings? What have you learned? Did you know the issues before receiving training? How many of you got refresher course? When did you receive last
training? How many of you utilized the knowledge in emergency / in need? How many of you never had the chance to utilize the training
knowledge? Have you ever deployed in any emergency? Which of the above skills/ knowledge you have utilized during
your deployment? Do you utilize the knowledge any other way apart from
deployment in emergency? Do you have any success story to share? Have you faced any Challenges? Any recommendation on further improvement of training qualities
- Cox’s Bazar, Khulna, Barguna, Kurigram, Natore, Sylhet
By June 15~30, 2014 Participants: 10-12 volunteers and staff in each event Duration: 45 minutes (approx.)
% of recipient
applied acquired knowledge and skills at real field
OD & DM FGD with
volunteers
% of Movement members knows 7 Fundamental Principles
NHQ / Unit FGD with UEC
members, Staffs,
volunteers
FGD Checklist Did you receive any orientation on RCRC basic? How many FPs are there in RCRC Movement and what are they? Do you apply them in your work? give an example Have you ever disseminated the FPs and how?
- Cox’s Bazar, Khulna,
Kurigram, Natore, By June 15~30, 2014
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
74
Do you have any suggestion to further promote FPs? Participants: 8-10 UEC member, volunteer and staff Duration: 45 minutes
% of CPP volunteers informed and disseminated early
warning messages–
CPP FGD with RCY &
CPP volunteers
FGD Checklist
What do you know about CPP?
What do you mean by early warning system and its importance?
How many volunteers are there for early warning message
dissemination?
Do you have any training in early warning system?
What is your basic learning?
What do you know about evacuation drill?
How early warning dissemination system works in your area?
(signal receive and dissemination)
Where people can take shelter?
Any challenges that you have faced in disseminating early
warning signal?
Do you have any suggestion for further improvement of early
warning system of BDRCS or CPP?
Cox’s Bazar, Khulna,
Participants: 10-12
volunteers (CPP)
Duration: 45 minutes
% of community
people have basic knowledge on WASH
CDI FGD with
beneficiary
FGD Checklist
Did you attend any awareness session on WASH conducted by
BDRCS?
What is your basic learning on WASH from the session?
How do you practice it in your daily life?
Do you know 5 critical times of hand wash?
Any other basic hygiene practices that you follow?
What is sanitary latrine?
Do you use sanitary latrine?
Why using sanitary latrine is important?
How to maintain sanitary latrine?
What are the Drinking water sources in your locality?
What are the main water-borne diseases?
What is the status of your community regarding diarrhoea
disease in compare to past.
- Community Development
Initiative (CDI) Programme (Rangpur)
Participants: 10-12 community people Duration: 30 minutes
Enhanced capacity in Relief Management
Response KII with IFRC and
BDRCS/
FGD with relevant
KII Checklist What are the implications of SOP on preparedness, response and
recovery? Is there any contingency plan in place for response?
- KII/FGD at NHQ - (IFRC- Mr. Adith Shah
Durjoy - BDRCS-Mr. Matiur, Belal
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
75
officials
What are the Beneficiary selection criteria? What is you perception on standardization and accuracy for
beneficiary selection? How many training, meeting, workshop, lessons learned
workshop conducted on relief management? What are the implications of those training, meeting, workshop,
lessons learned workshop? How the relief management system works in BDRCS and are you
satisfied with it? Does BDRCS maintain DP Stock? And is it sufficient? How is the maintenance and warehousing system of BDRCS? What are the challenges that you faced in relief management
during 2011~2013? Do you want to share any best practices? Do you have any recommendation to strengthen BDRCS relief
management system?
and Farook) By June 15, 2014
% of NDRT, CDRT, UDRT, NDWRT members contributed towards disaster response
Response and
other Relevant
Department
FGD with NDRT,
CDRT, UDRT,
NWDRT members
FGD checklist:
Why you are with RCRC Movement?
What type of training you have received?
What is the basic learning from the training?
What are the main roles of NDRT/ CDRT/ UDRT/ NWDRT
members?
Have you ever deployed in any emergency?
What skills you utilized during response/ deployment?
Level of satisfaction about the services you are providing.
Any challenges that you have faced during deployment?
Do you have any stories to share?
Do you have any recommendation for efficient service delivery?
(NDRT & NDWRT will be conducted at NHQ BDRCS)
(UDRT will be done at Cox’s Bazar, Khulna, Kurigram
Enhanced capacity on RFL activities
Tracing (RFL) KII with RFL
director and ICRC
focal point
KII Checklist What are the key areas that RFL address? What have you done in 2011-2013? What are the initiatives that you have taken for effective RFL
service delivery (during 2011-13)? Have you organized any training/ workshop/ meeting/ orientation
on RFL for volunteers? Do Units have any capacity on RFL activities? What are they? How they are Utilizing the knowledge? How do you collaborate with BDRCS in regard to RFL services?
(ICRC) How do you collaborate within BDRCS Departments, ICRC and
other organization on RFL? (BDRCS)
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
76
What is your plan for further strengthening of FRL service? (BDRCS & ICRC)
Any story you want to share? What are the main challenges in RFL? Do you have any recommendation?
No of Units received and utilized financial
support for renovation and construction as per estimated budget
Selected Unit Observation
method to be
followed and KII
with ULO of
selected Unit
KII Checklist:
What is the amount and source of financial support?
How the money was utilized? (maintaining quality of renovation
and construction)
What are the implications of construction and renovation work?
Is there any scope for further development?
Any challenges that you have faced?
Cox’s Bazar, Khulna,
Barguna, Kurigram, Natore, Sylhet
(TBD in discussion with Unit
Affairs Department & P&D)
% of reporting focal acquired basic knowledge on reporting
All Department at
NHQ
FGD with
reporting focal
FGD Checklist:
Have you received any orientation on reporting?
What is the basic learning from orientation?
How and where are you utilizing the learning?
What is the current reporting process and system in your Dept?
What is the utilization of those reports?
What types of report you are preparing?
What are the challenges in reporting?
Do you have any recommendation?
- NHQ, BDRCS
By 15 June, 2014
% of Unit officials/
volunteers utilized ICT knowledge in day to day work
Selected Unit FGD with Unit
Officials and
Volunteers
FGD Checklist Have you received any ICT orientation/ training? What are the basic learning from orientation/ training? How are you utilization the learning in day to day work? How about the email correspondence? Any challenges that you have faced? Do you have any recommendation?
Cox’s Bazar, Khulna, Barguna, Kurigram, - Jessore - Rangpur
To be merged in the FGD with reporting focal
No of initiatives taken against OCAC recommendation
P&D, IFRC OD
Focal
KII with P&D
Director, FO and
IFRC OD Focal
KII Checklist
What is OCAC?
Is OCAC conducted?
What are the measures taken to conduct OCAC?
Who were the participants to conduct the exercise?
What were the challenges in conducting OCAC?
What are the main recommended areas in OCAC findings report?
What is your plan for implementing OCAC recommendation?
NHQ, BDRCS
#11 June, 2014 at 9:30
% of community
people aware
IR & Communication
FGD with
community
FGD Checklist How do you perceive Red Crescent? (May show the logo if they
- Cox’s Bazar, Khulna,
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
77
about RCRC emblem
Dept (Emblem campaign)
(Pharmacy,
Hospital, Clinic)
people
(KII with Thana Health Officer)
recognize) Have you received any orientation/ campaign on RCRC emblem? What was the main learning? How the learning is utilized? Did BDRCS share any IEC materials? Have you ever disseminated the message of RCRC emblem
campaign? What is your opinion about not misusing the RC emblem? Do you have any suggestions or feedback on the emblem
campaign?
Dhaka ()
No of measures taken for maximum rent collection and BDRCS property recovery
Estate KII with Estate
Director
KII Checklist What are the areas that Estate Department deal with? What are the sources of rent collection? Comparison between plan and achievement of rent collection
(2011-13) What are the measures taken for collecting arrear rents? What are the measures taken for recovering Society’s properties? Does BDRCS have Real Estate and Asset Management Policy? What are the main challenges in this regard? Do you have any recommendation?
- NHQ, BDRCS
% of patient satisfied with the services of existing Health Care system
Health (Document
review/interview
of patients)
<Secondary data
may be collected
from patient
satisfaction
measurement
report by Health
Dept>
Observe the MCH
Question - Interview individuals/ patients
What type of health services the MCH delivering?
What type of services you have received?
What do you think about doctors’ consultation?
Any pathological test that you have undergone?
Were you satisfied with the quality of pathological test?
Are you satisfied with the services in terms of cost?
Is there any complain mechanism established in the MCH centres?
Have you ever complained and response received accordingly?
How was the behaviour of MCH staff?
Normal-delivery patient
What do you think about the service quality?
How was the behaviour of MCH staff?
How was the referral service?
Service provider’s interview What are the measures taken to maximize patient satisfaction
and providing quality service?
Cox’s Bazar, Khulna, Kurigram, - Secondary data in Health
Department - Primary data from the
interview with MCH patients (1/2 patients)
% of community Health FGD with FGD Checklist MCH project has an inbuilt
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
78
people informed about CBHFA and Basic Hygiene
volunteers/
community people
Have you received any orientation from RC Volunteers on FA and Basic Hygiene?
What are the main issues of basic hygiene? How many of you know about that? How many of you know about First Aid issues? What have you learned about First Aid? How many of you utilize in your daily life? Do you have any suggestion?
system to disseminate HIV message to the community. - Khulna MCH, Satkhira,
Jessore
% of beneficiary aware about HIV issues
Health FGD with
community people
FGD Checklist Any orientation/ awareness session conducted by RC HIV project
staff? What have you learned about HIV AIDS? Describe 3 reasons of transmitting HIV /AIDS Describe 3 reasons of preventing HIV /AIDS Is there any arrangement of counselling session for HIV affected
patient?
MCH project has an inbuilt system to disseminate HIV message to the community.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
79
5.3: Questionnaire for general understanding of SP 2011-15
Applicable for National Society (Bangladesh Red Crescent Society)
01
Have you heard about SP 2011-15, BDRCS? 1. Yes
2. No
02 What you think SP 2011-15 is?
1. It’s a Human Resource document 2. It’s a DRM document
3. It’s a Health document 4. It’s the Strategic Development Plan of
BDRCS
03 Were you involved in developing the SP 2011-15 of the BDRCS? 1. Yes
2. No
3.1 If yes, to what extend did you participate?
1. Active 2. Partial 3. Only at the beginning of this process 4. Just
attended a meeting
04 To which division of SP 2011-15, did you provide your institutions inputs?
1. Organizational Development 2. Disaster Management 3.
Health
05 In which part of the SP you provided support?
1. Narrative writing 2. Objective setting 3. 4 Year PoA 4. All of the
mentioned issues
06 Did you review your input before finalization of the document?
1. Yes, I reviewed my input 2. No, I wasn’t able to do that 3. I didn’t get any
opportunity
08 Did you receive any orientation on the SP 2011-15? 1. Yes 2. No
09 Did you formulate 4 Years Development Plan for your Department? 1. Yes
2. No
9.1 If yes, did you address SP 2011-15 in your 4 Year Development plan? 1.
Yes 2. No
9.2 If yes, how? 1. Development objective is aligned with SP Objective
2. Activities are aligned with SP objective 3. Both of these
10 Are you implementing your Development Plan as per SP? 1. Yes
2. No
11 Do you have a hard copy of SP 2011-15? 1. Yes
2. No
12 Do you have any comments regarding SP/SP Implementation in BDRCS?
1.
2.
3.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
80
Applicable for PNSs, ICRC and IFRC (supporting BDRCS)
01 Have you heard about SP 2011-15, BDRCS? 1. Yes 2. No
02 What you think SP 2011-15 is?
1. It’s a Human Resource document 2. It’s a DRM document
3. It’s a Health document 4. It’s the Strategic Development Plan of
BDRCS
03 Were you involved in developing the SP 2011-15 of the BDRCS? 1. Yes
2. No
3.1 If yes, to what extent did you participate?
1. Active 2. Partial 3. Only at the beginning of this process 4. Just attended
in a meeting
04 To which division of SP 2011-15, did you provide your institutions inputs?
1. Organizational Development 2. Disaster Management 3.
Health
05 In which part in the SP, were you supported?
1. Narrative writing 2. Objective setting 3. 4 years PoA 4. All of the
mentioned issues
06 Did you review your input before finalizing the document?
1. Yes, I reviewed my input 2. No, I wasn’t able to do that 3. I didn’t get any
opportunity
08 Did you receive any orientation on the SP 2011-15? 1. Yes 2. No
09 In case of providing support to BDRCS, do you consider SP 2011-15 in
programme/project proposals 1. Yes 2. No
9.1
If yes, what do you usually check in programme/project proposal?
1. Whether the overall objective aligned with SP or not 2. Whether the plan is
aligned with 4 Years Development plan 3. Both of
these
10 Do you have a hard copy of SP 2011-15? 1. Yes 2. No
11 Do you have any comments regarding SP/SP Implementation in BDRCS?
1.
2.
3.
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
81
5.4: Secondary data collection tool
Sl. No.
Indicator statement
Unit measuremen
t
As per SP 2011 As per SP 2012 As per SP June 2013 (June 2013)
% of achievement
Average % of achi.
Beneficiary Coverage
Total benefic
iary Plan Achi.
People reached
Plan Achi.
People reached
Plan Achi.
People reache
d
2011
2012
2013
2011 2012 2013
M F M F M F
1
2
3
4
5
6
7
8
9
10
11
12
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
82
5.5 List of reporting focal persons
Sl. No.
Name of person Designation Department/Programme/Project Email address Cell No
1 Khandaker A. K. M. Iqbal DD PMER Section [email protected] 01715703327
2 Rezina Halim DD Unit Affairs [email protected] 01811458508
3 Bashir Ahmed DD Cyclone Preparedness Programme [email protected] 01927667504
4 Md. Jiaul Ahasan DD Training [email protected] 01711261470
5 Sayma Ferdowsy DD Youth and Volunteers [email protected] 01678089188
6 Sultana Nelofar Banu DD Fund Raising [email protected] 01912475775
7 Joynal Abedin DD Estate [email protected] 01811458511
8 Abdul Karim AD Health [email protected] 01811458519
9 Mizanur Rahman AD Urban Disaster Risk Reduction [email protected] 01716433091
10 Khonduker Enayetullah Akram AD Communication and IR [email protected] 01716760599
11 Farzana Akther JAD Human Resource [email protected] 01817617363
12 Fazlur Rahman Khan JAD Health [email protected] 01715002461
13 Halima Tarafader JAD Administration [email protected] 01811458548
14 Abul Kalam Azad JAD Health [email protected] 01190509497
15 Ripan Das ICT Officer ICT Section [email protected] 01717187274
16 Mst. Reksona Khatun Finance Officer Finance [email protected] 01811458544
17 Mohammad Keramot Ali Field Coordinator Community Development Initiative [email protected] 01714019064
18 Md. Kamrul Hasan Sr. PMER Officer CCA, CBDRR [email protected] 01815298341
19 Modasher Ahmed project manager Vulnerability 2 Resilience [email protected] 01716674119
20 A K M Mohsin Asst Director Tracing [email protected] 01811458528
21 Md. Emranul Hassan Field Officer Planning & Development [email protected] 01916754444
22 Farook Rahman Field Officer Disaster Response [email protected] 01740945846
Report on Midterm Progress Review of SP 2011-15 | PMER Section, BDRCS
83
5.6 Pictures: captures during workshop, meeting, and data collection
From upper left, Picture’s Description
From upper left to right, workshop on midterm
progress review, meeting with reporting focal
person, FGD with volunteers, FGD with project
beneficiary, FGD with disaster response personnel,
visit of MCH center, discussion on emblem and KII
with ULO.