report of the rpii visit to bnfl sellafieldthe sellafield mox plant. the tribunal in the case issued...
TRANSCRIPT
Report of the RPII Visit to BNFL Sellafield
P.A. ColganD. PollardC. HoneC. McMahonA.T. McGarry
RPII 05/01
Report of the RPII Visit to BNFL Sellafield
Report of the RPII Visit to BNFL Sellafield
P.A. ColganD. PollardC. HoneC. McMahonA.T. McGarry
April 2005
Report of the RPII Visit to BNFL Sellafield
Contents
1. Introduction 1
2. Summary of Operations at BNFL Sellafield 2
2.1 Introduction 2
2.2 Reprocessing at BNFL Sellafield 2
2.3 The Magnox Operating Plan (MOP) 4
3. Site Visits 6
3.1 The Magnox Fuel Storage Pond and Decanning Facility 6
3.2 The Solid Active Waste Storage Facility 7
3.3 The Medium Active Concentrate (MAC) Storage Tanks 7
3.4 The Highly Active Liquor Evaporation and Storage (HALES) Plant 8
3.5 The Waste Vitrification Facility 9
3.6 The Thermal Oxide Reprocessing Plant (THORP) 10
4. Emergency Planning Arrangements at BNFL Sellafield 11
4.1 The BNFL Sellafield Reference Accident 11
4.2 Structure of Emergency Response 11
4.3 The Sellafield District Control Centre (DCC) 12
4.4 Security Issues post 9/11 12
5. Conclusions 13
5.1 Plant Operations 13
5.2 Radioactive Discharges 14
5.3 Emergency Preparedness 14
5.4 Terrorist Threats 15
6. References 16
ANNEX 1 17
ANNEX 2 21
ANNEX 3 28
Report of the RPII Visit to BNFL Sellafield 1
1. Introduction
In 2002 the Irish Government initiated international legal
proceedings against the United Kingdom (UK) under the United
Nations Convention on the Law of the Sea (UNCLOS) in relation to
the Sellafield MOX Plant. The Tribunal in the case issued an Order
on 24 June 2003 after hearing an application by Ireland for
Provisional Measures. The Provisional Measures Award
recommended inter alia that Ireland and the UK enter into
dialogue to improve cooperation and consultation between the
two Governments.
As part of this process the Irish Government expressed an
interest in further visits to BNFL Sellafield by officials of the
Radiological Protection Institute of Ireland (RPII). A previous fact-
finding visit had taken place in February 2000. Written proposals
for a visit were presented to the UK in January 2004. In their
response to the proposals, the UK invited the RPII, together with
relevant officials from the Department of the Environment,
Heritage and Local Government, to a background briefing at the
headquarters of the Health and Safety Executive in Bootle in
advance of a visit to BNFL Sellafield.
The background briefing, conducted over two-and-a-half days,
was comprehensive and contributed significantly to understanding
the regulatory approach by both the Health and Safety Executive’s
Nuclear Installations Inspectorate (NII) and the Environment
Agency (EA) and the regulatory regime currently in place at BNFL
Sellafield. The briefing also addressed the current principal
regulatory issues at BNFL Sellafield including details of a revised
Discharge Authorisation to be issued by the Environment Agency
to take effect in October 2004 and the considerations
underpinning the current regulatory obligations imposed by the
NII on the BNFL Sellafield site in relation to the reduction of the
Highly Active Liquor (HAL) stocks to buffer stock levels by 2015.
Five members of staff of the RPII visited BNFL Sellafield over the
period 23-24 September 2004. The purpose of the visit was to see at
first-hand a small number of on-site facilities of particular interest and
concern to Ireland and to explore the changing nature of operations
at the site. Issues of security were outside the scope of the visit.
The facilities included as part of the visit were:
• The redundant Magnox Fuel Storage Pond and Decanning
Facility;
• The Solid Active Waste Storage Facility;
• The Medium Active Concentrate (MAC) Storage Tanks;
• The Highly Active Liquor Evaporation and Storage (HALES)
Plant;
• The Waste Vitrification Facility (WVF); and
• The Thermal Oxide Reprocessing Plant (THORP).
Throughout the visit representatives of BNFL, the NII and the EA
accompanied the RPII delegation. The RPII met key BNFL
personnel in each of the areas visited as well as representatives of
the main worker unions.
On the second day of the visit the RPII discussed on-site and off-
site emergency arrangements with staff of BNFL Sellafield and the
emergency planning officer of Cumbria County Council
responsible for the BNFL Sellafield site.
A summary of the regulatory activities of the NII and of the EA can
be found in Annexes 1 and 2 respectively. General information on
emergency response planning and procedures in the UK can be
found in Annex 3.
Report of the RPII Visit to BNFL Sellafield2
2. Summary of Operations at BNFL Sellafield
2.1 IntroductionBNFL Sellafield is a 700-acre nuclear site in Cumbria in the North
West of England. The site is located close to the Irish Sea and at its
closest point (Clogher Head, Co. Louth) is approximately 112
miles from the Irish coastline.
In the late 1940s work commenced at the site on the construction
of two nuclear ‘piles’ for the production of plutonium for military
use. These are commonly referred to as the Windscale piles.
Electricity production commenced at the site in 1956 when the first
of four Calder Hall nuclear reactors came into operation. The last of
these closed down in March 2003. Sellafield was also the site of an
experimental reactor, the Windscale Advanced Gas-cooled Reactor
(WAGR), which is being decommissioned presently.
Today the main activities at BNFL Sellafield include the storage and
reprocessing of spent nuclear fuel1, the storage of plutonium and
uranium, the fabrication of mixed oxide (MOX) fuel and
decommissioning activities.
Previous non-commercial operations that have ceased have
resulted in large amounts of radioactive waste being stored in
various buildings around the BNFL Sellafield site. These are often
referred to as ‘legacy wastes’2. The clean-up3 of these facilities
represents a major challenge that has begun to be addressed and
will be the primary focus of future activities at BNFL Sellafield once
commercial reprocessing operations come to an end.
2.2 Reprocessing at BNFL SellafieldAfter being removed from a nuclear reactor, the spent nuclear fuel
still contains approximately 96% uranium. The remainder consists
of plutonium (1%) and a number of other highly radioactive
materials collectively called fission products. Spent fuel is highly
radioactive and generates a large amount of heat; it therefore
needs to be managed very carefully to protect both man and the
environment. One way of managing spent nuclear fuel is by
separating it into its constituent parts. This is called reprocessing.
Reprocessing was first developed to provide plutonium for military
purposes. Plutonium can also be used in a modern reactor design
called a fast breeder reactor but there is currently little interest in
developing this type of reactor. One further use for plutonium is in
the manufacture of mixed oxide (MOX) fuels for burning in some
commercial nuclear reactors. The majority of UK nuclear reactors
are not suited to the burning of MOX fuel. UK nuclear reactor sites
are shown in Figure 1.
There are two reprocessing plants on the BNFL Sellafield site. One
of these, the Magnox reprocessing plant, reprocesses spent fuel
from Magnox reactors. Magnox technology was developed in the
UK and is principally confined to the UK. The Thermal Oxide
Reprocessing Plant (THORP), which came into full operation in
1995, reprocesses uranium oxide fuel used in several different
types of nuclear reactors in the UK, Europe and Japan. Figure 2
shows the various steps in the reprocessing of spent nuclear fuel
through THORP.
Following delivery to the BNFL Sellafield site for reprocessing, the
spent fuel is stored in cooling ponds, often for several years, in
order to allow some of the heat to dissipate and the amount of
radioactivity present to reduce by natural decay. The spent fuel is
then chopped into small pieces and dissolved in hot nitric acid4.
The casing is segregated and stored as intermediate-level
radioactive waste. A solvent is then added that separates out the
uranium and plutonium for purification and storage. What remains
is high or medium-level radioactive waste in concentrated liquid
nitric acid.
1 Conventional nuclear fuel consists of a mixture of uranium-235 and uranium-238.This is used in a nuclear reactor to produce energy. ‘Spent nuclear fuel’ is nuclearfuel that has been removed from a nuclear reactor. Spent nuclear fuel containsuranium-235, uranium-238, plutonium and a number of highly radioactivematerials collectively referred to as ‘fission products’.
2 In the 2002 UK White Paper on managing the nuclear legacy (DTI, 2002), ‘legacywastes’ are defined in the following terms• those nuclear sites and facilities now operated by the United Kingdom Atomic
Energy Authority (UKAEA) and British Nuclear Fuels plc (BNFL), which weredeveloped in the 1940s, 50s and 60s to support the Government’s researchprogrammes, and the wastes, materials and spent fuel produced by thoseprogrammes; and
• the Magnox fleet of nuclear power stations designed and built in the 1960s and70s and now operated on the Government’s behalf by BNFL, plant and facilitiesat Sellafield used for the reprocessing of Magnox fuel and all associated wastesand materials.
3 ‘clean-up’ is defined as the decontamination and decommissioning of a nuclearlicensed site.
4 The casing of Magnox fuel is removed before the fuel is dissolved. In the case ofoxide fuels processed through THORP, the fuel and its casing are chopped intosmall pieces. The nitric acid dissolves the fuel but not the casing, which is thensegregated for storage as intermediate-level waste.
Report of the RPII Visit to BNFL Sellafield 3
Figure 1Location of BNFL Sellafield and UK Nuclear Reactor Sites
Torness
Hunterston A & B
Chapelcross
HartlepoolSellafield/2Calder Hall
Heysham I & II
Sizewell A & B
Bradwell
Dungeness A & BHinkley Point A & B
Oldbury
Berkeley
Trawsfynydd
Wylfa
Report of the RPII Visit to BNFL Sellafield4
Reprocessing generates large amounts of radioactivity for which
there is no end use. This waste material is classified according to its
radioactive content as high-, intermediate- or low-level waste. High-
level liquid radioactive wastes are stored in the Highly Active
Storage Tanks (HASTs) before being incorporated into glass blocks
(a process known as vitrification) for long-term storage.
Intermediate-level radioactive waste is stored on-site at BNFL
Sellafield while low-level radioactive waste produced at BNFL
Sellafield is disposed of at a nearby waste repository called Drigg.
Reprocessing also gives rise to liquid radioactive discharges into the
Irish Sea and gaseous radioactive discharges to the environment.
These discharges are classified as low-level radioactive wastes.
Reprocessing at BNFL Sellafield evolved into a commercial activity
in the 1980s, providing uranium and plutonium for reuse in the
manufacture of nuclear fuel. However, given the current low world
price for uranium it is cheaper to mine and mill fresh uranium than
to re-use uranium recovered during reprocessing. In the absence
of a fast breeder reactor programme the only alternative to long-
term storage or disposal of plutonium is the manufacture of MOX
fuel in the Sellafield MOX Plant. The plutonium is mixed with
uranium and the MOX fuel can be used in certain nuclear reactors
to generate electricity. There are currently no plans to produce
MOX fuel from the UK’s own plutonium stocks but some contracts
do exist with BNFL’s overseas customers for the conversion of
their plutonium into MOX fuel for burning in nuclear reactors in
their own countries.
On 1 April 2005 a new Nuclear Decommissioning Authority (NDA)
takes over responsibility for the management of all legacy wastes
at designated sites (NDA, 2004) as well as current and future
decommissioning programmes in the UK. The NDA also assumes
responsibility for the commercial activities on the BNFL Sellafield
site, namely the reprocessing operations at THORP and the
manufacture of MOX fuel.
2.3 The Magnox Operating Plan (MOP)The UK’s nuclear power programme, announced in 1955, called
for 5,000 megawatts of generating capacity through the
construction of a series of Magnox reactors across the country.
The fuel used in Magnox nuclear reactors consists of natural
uranium encased in magnesium alloy. When stored underwater,
Magnox spent fuel undergoes corrosion, initially of the
magnesium alloy cladding and subsequently of the uranium metal
within. Dry storage has also been considered but is not a proven
long-term management option, although interim storage of
Figure 2Reprocessing of Spent Nuclear Fuel through THORP
Fuel2Assemblies
Shipm
ent of Spent2
Reactor Fuel
Pluto
nium2
Oxide Liquid2
Discharges
Uranium2
Oxide
Liquid2Discharges
THORP2Storage Pond
Solid2Waste Store
Plutonium2Store
Uranium2Store
IRISH2SEA
Discharges to2Air & Sea
Discharges of2Gases to Air
High-Level2Waste Storage2
TanksReactor
Liquid2WasteTHORP EARPSpent2
Reactor Fuel
Report of the RPII Visit to BNFL Sellafield 5
Magnox spent fuel does take place at the Wylfa nuclear power
plant. According to the UK Radioactive Waste Management
Advisory Committee “even if dry stored…[Magnox spent
fuel]…would need to be in a carefully controlled environment and
would not be in line with the concept of passivity. If a policy of
deep disposal were ultimately pursued, the fuel would also then
subsequently have to be suitably conditioned, given that it would
still be reactive in a geological environment. Currently, no
industrial-scale process exists to do this, other than reprocessing
itself. It is therefore rational to continue to reprocess the [Magnox]
spent fuel” (RWMAC, 2000). Thus the UK’s policy for managing
Magnox spent fuel is based primarily on the reactivity of the fuel
and the fuel cladding, which in turn makes it unsuitable for
ultimate disposal unless it is reprocessed.
The only Magnox stations still operating are in the UK, where they
produce approximately 8% of the UK’s electricity. Previously, Magnox
power stations operated at Latina in Italy and Tokai Mura in Japan.
In May 2000 BNFL announced the planned closure dates for its
remaining Magnox reactors. Following a number of safety-related
incidents at both Calder Hall and Chapelcross, the closure dates
for these reactors were brought forward as their continued
operation could not be justified economically. The UK Strategy for
Radioactive Discharges 2010-2020 (DEFRA, 2002) also brought
forward the closure dates for Oldbury and Wylfa (previously 2013
and 2016/2021 respectively).
The most up-to-date timetable for closure, defuelling and
decommissioning of the Magnox stations is given in Table 1.
The Magnox Operating Plan (MOP) places priority on the
reprocessing of Magnox spent nuclear fuel. OSPAR Contracting
Parties, including the UK, undertook in 1998 to reduce radioactive
discharges so that, by 2020, the additional concentrations in the
marine environment above historic levels, arising from such
discharges, are close to zero (OSPAR, 1998). This goal is to be
achieved through progressive and substantial reductions in
radioactive discharges.
The Magnox reprocessing plant is due to cease operation by the
end of 2012. This date is consistent with the closure date for the
final Magnox station (Wylfa) in 2010 and the NII specification to
reduce HAL volumes in the HASTs by 2015 (HSE, 2000a). To
achieve the 2012 operational deadline requires approximately
eight years of good operation of all plants – including the liquid
effluent treatment plants - linked to the Waste Vitrification Facility.
Procedures are in place to monitor the implementation of the MOP
so that steps can be taken if problems arise. If the HAST
specification is not complied with, then the NII has the authority to
close the Magnox stations at an earlier date or to constrain the
operation of THORP so as to give priority to Magnox reprocessing.
Restricting the operation of THORP would still allow the 2015
specification to be met but would extend the time period over
which THORP reprocessing would take place.
Table 1Current Status of UK Magnox Reactors
Station Commissioned Current Status
Berkeley 1962 closed 1989 – being decommissioned
Hunterston A 1964 closed 1989 – being decommissioned
Trawsfynydd 1965 closed 1991 – being decommissioned
Hinkley Point A 1965 closed 2000 – being defuelled
Bradwell 1962 closed 2002 – being defuelled
Calder Hall 1956 closed 2003 – awaiting defuelling (2005)
Chapelcross 1958 closed 2004 – awaiting defuelling (2005)
Dungeness A 1965 to close 2006
Sizewell A 1966 to close 2006
Oldbury 1967 to close 2008
Wylfa 1971 to close 2010
Report of the RPII Visit to BNFL Sellafield6
3. Site Visits
3.1 The Magnox Fuel Storage Pond and Decanning FacilityThe Magnox Fuel Storage Pond and Decanning Facility came into
operation in 1959. Its principal role was to receive and store
irradiated spent fuel from Magnox reactors and to remove the fuel
cladding (a process called ‘decanning’) prior to the fuel being
reprocessed. Initially a wet decanning process was used but later a
dry decanning facility was added. A new Magnox Fuel Handling
Plant was commissioned in 1986 and a phased handover to the
new plant took place in the early 1990s.
The Magnox spent fuel is stored underwater in a pond that is
exposed to the open air. The pond is approximately 60 m in length
and 12 m in width. The casing of Magnox fuel is subject to corrosion
and this limits the amount of time for which it can be stored
underwater to approximately one year. Around 1974 a reprocessing
shutdown led to the accumulation of spent Magnox fuel in the
storage ponds; this started to corrode and leak, making it almost
impossible, with the technology available at the time, to recover and
reprocess the contents. Over the years this has resulted in the
accumulation of highly radioactive spent fuel in the form of sludge
on the bottom of the storage ponds, which by the mid 1980s meant
that it was no longer feasible to operate the plant reliably. This
sludge contains uranium, plutonium and a range of fission products.
Around this time the ponds were also used to store other
radioactively contaminated material generated in the plant. This
includes material such as iron bars, pumps, solid material
contaminated as a result of routine operations, etc. The total
inventory of contaminated material and its radioactive content is
not accurately known and this adds to the complexity of the
clean-up operations.
The NII regards the clean-up of this facility as one of the major on-
site priorities and it has specified a date of August 2010 by which
90% of the sludge in the tanks must be removed. A further
specification requires that at least 80% of the total volume of all
sludges originating from operations prior to 1 August 2000 and
which have been accumulated as radioactive waste shall be stored
in a passive form by 2020. Material retrieved from the ponds will
be classified as intermediate-level waste i.e. it will be encased in
concrete, placed in metal drums and stored on the BNFL Sellafield
site. BNFL has put in place a project team with an annual budget
of £150 million to decommission the facility. While considerable
advances have been made in improving the building condition,
developing contingency plans and retrieving some of the wastes,
there are many unknowns and unforeseen problems arise on a
regular basis (Travis, 2003).
The dose rates inside the plant present a major constraint on
working times and mean that much of the work has to be done
remotely. Dose rates along the south wall of the pond, for example,
are as high as 1 Sievert per hour in places. This compares with the
annual dose limit for a radiation worker of 0.02 Sievert. On-going
work is necessary to upgrade basic safety facilities and to stabilise
and make safe the structures in order that the decommissioning
work can continue. These factors greatly increase the technical
complexity of the decommissioning operations.
After the NDA takes over responsibility for clean-up operations at
several UK sites, including BNFL Sellafield, in April 2005, it will
have available to it an annual budget of £1.2 billion for each of the
first three years of its operation. While the NDA is free to set its
own priorities for the clean-up of the UK’s nuclear sites, there is
confidence that the current clean-up and decommissioning
programme for this plant will continue.
The water in the pond serves the dual purpose of cooling the
pond contents while also acting as a shield to reduce radiation
doses to workers. These waters are routinely transferred to the
Site Ion Exchange Effluent Plant (SIXEP), where they are treated to
remove radionuclides prior to discharge, and replaced by fresh
uncontaminated water. As part of the new EA Discharge
Authorisation for BNFL Sellafield, which came into force on 1
October 2004, BNFL is required to estimate the actual discharges
from all of its major operations. The clean-up and
decommissioning of the Magnox Fuel Storage Pond and
Decanning Facility is regarded as one such major operation.
Estimated discharges for current operations must be submitted to
the EA on an annual basis with the first such submission required
at the end of June 2006.
Report of the RPII Visit to BNFL Sellafield 7
3.2 The Solid Active Waste Storage FacilityThe Solid Active Waste Storage Facility was commissioned in 1952
for the dry storage of intermediate-level waste, principally the casings
that had been removed from spent fuel. The facility is a reinforced
concrete structure sub-divided into a number of compartments,
normally referred to as ‘silos’. Routine tipping of waste into these
silos ceased in 1966. However small quantities of miscellaneous
beta/gamma wastes were placed in the silos up to 1969.
In addressing the on-going maintenance and eventual
decommissioning of the facility there are two principal issues. The
first is the potential for a fire and/or explosion from Magnox
casings stored in a dry environment. This risk was previously
evaluated by BNFL and considered unacceptable with the result
that the building is now maintained in an argon-rich environment.
Argon is an inert gas that significantly reduces the risks of fire from
dry storage of fuel cladding. To ensure an uninterruptible argon
supply, back-up safety systems have been installed and are
regularly tested. The second issue is the very high radiation levels
present. These are due to a combination of, the small amounts of
spent fuel that remained attached to the casing at the time of
mechanical separation, irradiation products and the miscellaneous
beta/gamma emitters referred to above.
Waste material from the facility is classified as intermediate-level
waste. As with the sludges and other waste materials arising from
the clean-up operations at the Magnox Fuel Storage Pond and
Decanning Facility, this waste will be retrieved, packaged and
stored on-site in metal drums. However the timescale for these
activities has yet to be established.
3.3 The Medium Active Concentrate (MAC) Storage Tanks The MAC storage tanks were built in the late 1940s and are used
to store liquid wastes generated by Magnox reprocessing before
being sent to the Enhanced Actinide Removal Plant (EARP). In
EARP, chemical treatment of the wastes removes much of the
strontium-90, caesium-137, americium-241 and plutonium prior to
discharge to the Irish Sea. Since March 2004, the chemical
tetraphenylphosphonium bromide (TPP) has been added to MAC
as it passes through EARP and this removes the bulk of the
technetium-99 present in this waste stream, resulting in a
significant reduction in discharges of technetium-99 into the Irish
Sea. Current and future arisings of MAC are diverted directly to
the HALES building where they are added to high-level
radioactive wastes prior to vitrification.
The NII has expressed its “…concern about the prolonged use of
..[the tanks].. to store MAC because of the age of the tanks (built
in the late 1940s) and the deteriorating condition of the building
structure”5. Specifically the NII cited that the roof of the building
could collapse, damaging the tanks and leading to a release of
radioactivity to the environment. The NII is satisfied that the tanks
are structurally sound up to 2006. The current discharge strategy
will see the tanks emptied by this date and this will further reduce
the overall hazard on the site. Over the past year approximately
65% of the stored MAC has been removed from the tanks.
The BNFL Sellafield discharge authorisation issued by the EA will
allow the contents of the MAC storage tanks to be emptied within
the timescale acceptable to the NII. At present the EA is
considering a request from BNFL to accelerate the treatment and
discharge of MAC. If this proceeds, the on-site hazard will be
reduced more quickly than is presently foreseen. MAC is normally
stored for a period of three years in order to allow the ruthenium-
106 content to reduce by radioactive decay. A change to the
present timetable will reduce the storage time to less than three
years and this will result in a small increase in the quantity of this
radionuclide discharged to the Irish Sea6.
Ruthenium-106 is not presently detected in the Irish marine
environment and it is unlikely that the small increased discharges
resulting from the earlier emptying of the MAC storage tanks will
change that. However, in future years BNFL Sellafield is likely to
handle spent fuels which have spent longer times in the reactor and
which are stored for shorter periods prior to reprocessing. These two
factors could potentially further increase the discharges of ruthenium-
106 to the Irish marine environment if no abatement is applied.
5 Letter to Rt. Hon. Margaret Beckett, M.P. from Laurence Williams, NII ChiefInspector dated 13th January 2003.
6 Ruthenium-106 has a half-life of approximately one year and therefore prolongedstorage can significantly reduce the amount present. EARP does not removeruthenium-106 from MAC prior to discharge.
Report of the RPII Visit to BNFL Sellafield8
3.4 The Highly Active Liquor Evaporationand Storage (HALES) Plant The HALES Plant contains over 90% of the on-site radioactivity in
the form of waste and is where the Highly Active Storage Tanks
(HASTs) are located. The HASTs contain high-level liquid
radioactive wastes, commonly referred to as Highly Active Liquors
(HAL), awaiting vitrification.
On arrival, waste streams sent to the HALES plant are evaporated
to reduce the volume of material that has to be managed. There
are two evaporation plants – one for Magnox wastes and one for
THORP wastes – and a third (back-up) evaporator has recently
been recomissioned. The volume reduction achieved by
evaporation is typically a factor of 125. The waste is then
transferred to one of the HASTs and different tanks are used for
Magnox and THORP wastes.
There are 21 HASTs, all of which are located in the HALES
building. The first eight HASTs were commissioned in 1955 and
brought into active use between 1955 and 1970 as the volume of
waste produced increased. Each of these has a working volume of
70 cubic metres. The remaining 13 HASTs were built during the
1970s and 1980s and each has a working volume of 145 cubic
metres. For safety reasons, a policy of keeping one tank empty for
every three in use has always been maintained in the event that
one of the other HASTs needs to be emptied at short notice.
The HASTs are housed in thick reinforced concrete cells. Because
of the very significant heat generating capacity of the waste (up to
several kilowatts per cubic metre) the tanks require continuous
cooling to prevent evaporation and, ultimately in the case of those
tanks with the larger radioactive inventories, boiling and release to
atmosphere of their contents.
For safety reasons the HASTs are also segregated into ‘cells’ to
provide isolation from the other tanks. The first eight tanks were
installed two per cell while the remaining 13 tanks were installed
one per cell.
Most of the waste stored in the HASTs consists of long-lived
radioactive materials. The most important of these is caesium-137,
which accounts for about 10% of the total inventory. The next
most important radionuclides (in terms of quantity stored) are
strontium-90, caesium-134 and ruthenium-106. Because the
stored wastes are derived from reprocessing, much of the
plutonium has already been removed and only trace amounts are
present in the HASTs.
RPII staff previously examined safety documentation relating to
the HASTs, the Continued Operation Safety Report (COSR) over a
two-week period in February 2000 (Turvey and Hone, 2000). The
main conclusions of that examination were that the risk of damage
from a severe earthquake had not been fully analysed and that,
while the probability of an accident leading to a significant release
of radioactivity was low it could be reduced further through the
implementation of certain measures including, in particular,
increasing the level of independence of the cooling water
supplies. These issues were discussed with appropriate personnel
during the course of the site visit.
The RPII team was advised that the safety case relating to severe
earthquake damage, much of which would also apply to a terrorist
attack involving the intentional crashing of a heavy aircraft into the
building, has been completed and that the NII accepts that no
further structural modifications are required. The team were also
advised that the level of independence of the different cooling
water supplies has been increased since the February 2000 visit.
The issue of the detection of ‘spikes’ or ‘hot-spots’ of activity in the
cooling jacket in HAST 13 as referred to in the RPII Annual Report
and Accounts 2003 was discussed in detail. At the time of our visit
we were advised that, while the source of the contamination had not
been fully identified, it was believed to have originated from cross
contamination from cooling water in an internal cooling coil. (The
cooling coils and cooling jackets share a common water supply).
Minor cracks in internal cooling coils do occur from time to time and
while the pressure in the cooling coils is kept higher than the
pressure of the HAL to prevent HAL entering a damaged cooling
coil, some transfer of radioactivity through mixing is a possibility.
Report of the RPII Visit to BNFL Sellafield 9
The Institute was subsequently advised by the NII that the spike in
activity in the cooling jacket in HAST 13 is now believed to be due to
a microscopic fissure in the tank wall, as a result of stress corrosion of
the steel, which has allowed nanolitre quantities of HAL to leak out.
While there are no immediate safety concerns, further studies are
being conducted by BNFL and the NII is monitoring this work and
considering the implications for storage of HAL. This incident is
clearly of greater significance than if the activity in the spike was due
to cross contamination resulting from a leaking internal cooling coil
and provides further evidence that the long-term storage of high-
level radioactive waste in liquid form is not sustainable.
The NII recently advised the Institute that a small activity spike, at
too low a level to characterise, has been detected in HAST 12. An
enhanced surveillance programme has been put in place to
monitor this HAST. The activity spikes in both HASTs are under
active investigation by both BNFL and the NII. The NII has
acknowledged that these events are “a safety concern, as well as
potentially an additional constraint on the efficiency of operations”
(HSE, 2005).
The NII has specified that BNFL must reduce the volume of HAL
stored in the HASTs to a ‘buffer’ volume of 200 m3 by 2015. The
NII believes that this requirement is necessary to reduce overall
hazard at the BNFL Sellafield site (HSE, 2001). In specifying this
requirement, the NII has taken into account the need to reduce
the volume of stored HAL as quickly as possible while still
ensuring that the stocks of spent fuel currently in storage on site
and awaiting reprocessing are dealt with in a timely manner. The
NII believes that the current arrangements are the best solution for
dealing with the many hazards that are present on the site.
The current volume of HAL in the HASTs is approximately 1400 m3.
To meet the NII requirements, this volume must be reduced by 35 m3
per year for the next number of years and this is currently being
achieved. Once THORP and Magnox reprocessing end in 2010
and 2012 respectively there will be a significant reduction in the
volume of HAL generated and this will allow the rate of volume
reduction in the HASTs to be increased.
The NII is on record as saying that, if there are indications that
these deadlines will not be met, it will use its regulatory powers to
instruct BNFL to cease temporarily the reprocessing of oxide spent
nuclear fuel through THORP. This is consistent with the Magnox
Operating Plan (MOP), which places priority on the reprocessing
of Magnox spent nuclear fuel. This is discussed in greater detail in
Section 2.3.
3.5 The Waste Vitrification Facility In the early years of Magnox reprocessing research was carried
out into the treatment and long-term management of the HAL
stored in the HASTs. However, it was subsequently decided to
invest in a vitrification process developed in France and in 1990 a
Waste Vitrification Facility (WVF) came into operation. This facility
encapsulates the HAL in glass blocks for long-term storage. The
WVF had two vitrification lines but these failed to operate at full
capacity due to operational difficulties associated in part with the
very high temperatures of the materials passing through the plant.
In January 2002 the commissioning of a third vitrification line
commenced and this came into full operation in July 2004.
There are many factors to consider when dealing with the
vitrification and storage of HAL: it is highly radioactive; it contains
acids that are corrosive in nature; it generates considerable
amounts of heat and it contains different mixes of radionuclides
depending on whether it originated from Magnox or THORP
reprocessing. The process of vitrification involves the blending of
wastes from the different HASTs in order to minimise the number
of glass blocks that have to be produced and maximising the
amount of radioactivity in each, while at the same time taking
account of the chemical nature of the different liquors. Following
blending, the waste is sent by pipe to the WVF.
On arrival at the WVF, the HAL is passed through a calciner to
transform it into powder form. Glass-making substances are added
and the material is heated and melted to form a viscous liquid that
is then poured into stainless steel containers. The glass cools and
solidifies, thereby binding the radioactivity into a structure that is
chemically inert and shows long-term resistance to leakage.
The stainless steel containers are transferred to a shielded storage
area that has the capacity for 8,000 containers. Presently the store
is less than half full. BNFL’s current overseas contracts will
generate approximately 3,000 containers and from 2007 onwards
these will be returned to the customer by ship. BNFL’s
reprocessing contracts with its UK customers are expected to
generate considerably less than 8,000 containers.
Report of the RPII Visit to BNFL Sellafield10
No decision has been made on the long-term storage or disposal
of high-level radioactive waste in the UK. However, the UK
recently established an independent body, the Committee on
Radioactive Waste Management (CoRWM) to review the available
options and to provide its recommendations to Ministers by July
2006. The current inventory of radioactive waste at BNFL Sellafield
is given in Table 2.
Table 2Current Inventory of Radioactive Waste
at BNFL Sellafield1
Radioactive Waste Form Volume (m3)
High Level Waste
HASTs (liquid)2 1400
Vitrified Waste (solid)3 745
Intermediate Level Waste4 75,400
Low Level Waste5 1 x 106
1 based on April 2001 values given in DEFRA (2001).
2 value as of end December 2004.
3 it is estimated that the total volume of vitrified waste generated from current
reprocessing contracts will be 1510 m3, of which approximately 400 m3 belongs to
BNFL’s overseas customers (CoRWM, 2004).
4 the majority, but not all, of this waste originates at BNFL Sellafield.
5 low-level radioactive waste produced at BNFL Sellafield is disposed of at Drigg,
approximately 6 km south of the BNFL Sellafield site. This disposal is controlled
through authorisations issued by both the NII and the EA.
Efficient operation of the WVF is the key to volume reduction of
HAL in the HASTs. If the vitrification throughput is reduced, this in
turn limits the allowable production of HAL (as the volume in the
HASTs must decrease rather than increase) and could impact
significantly on THORP reprocessing. This is also discussed in
some detail in Section 2.3. For this reason considerable effort is
being put into upgrading the first two vitrification lines in an effort
to process the volume of HAL in storage in the HASTs at a faster
rate than that specified by the NII.
Neither the operations in the Waste Vitrification Facility or HALES
give rise to liquid discharges to the environment. All such waste
streams are recycled to the evaporators in the HALES building.
3.6 The Thermal Oxide Reprocessing Plant(THORP)In March 1977 BNFL applied to Cumbria County Council for
approval to construct THORP. Following a public inquiry, THORP
was approved in 1978 and subsequently built at a total cost of
£2.8 billion. Commissioning of THORP commenced in 1994 and
the plant came into full operation in early 1995.
The reasons for Magnox and THORP reprocessing are
fundamentally different. Originally Magnox reprocessing was
undertaken to produce plutonium for the UK’s nuclear weapons
programme. At present, the reprocessing of Magnox spent fuel is
seen as the best management option for a material that is reactive
and unstable when stored under water or in open air for prolonged
periods. Conversely, THORP reprocessing was set up as a
commercial venture to provide operators in the UK and abroad
with a spent fuel management route and/or to extract reusable
uranium and plutonium from their spent uranium oxide fuel.
THORP reprocesses spent fuel used in several different types of
nuclear reactor including advanced gas cooled reactors and light
water reactors. In terms of tonnage, THORP’s main customer is
Japan, followed by British Energy. Its principal European customer
is Germany but contracts also exist with utilities in Switzerland,
Italy, Spain, Sweden and the Netherlands.
THORP is in stark contrast to the older plants visited. It is clearly
more modern and has a greater degree of automation. The
aerial and liquid discharges from THORP are also less than those
from Magnox reprocessing for the same throughput of spent
fuel. The mix of radionuclides discharged and their relative
percentages are also different from those discharged as a result
of Magnox reprocessing.
The future planned throughput of spent fuel through THORP
would result in all existing reprocessing contracts being completed
by 2010. However, additional reprocessing contracts may be
entered into, but only with the consent of the UK Government.
Presently, any requests for approval of such contracts are made by
BNFL to the UK Government, its sole shareholder. As of 1 April
2005 these submissions, should any arise in respect of new
contracts, will be made by the NDA.
Report of the RPII Visit to BNFL Sellafield 11
4. Emergency Planning Arrangements at BNFL Sellafield4.1 The BNFL Sellafield Reference AccidentAll nuclear sites in the UK are required by law to define a
bounding reference accident scenario for the purposes of off-site
emergency planning. The reference accident must be based on
the concept of the worst credible accident, which is reasonably
foreseeable at the site, taking into account all of the facilities on
the site (see Annex 3). The NII must approve the reference
accident for each nuclear site and this is then used as the basis for
deciding the size of the Detailed Emergency Planning Zone
(DEPZ). Within the DEPZ detailed plans must be prepared for the
implementation of applicable off-site countermeasures.
Formerly the reference accident for the BNFL Sellafield site was
based on the Calder Hall reactors. Since the closure of these
reactors in 2003, the reference accident has been based on a leak
into the coolant circuit in one of the Highly Active Storage Tanks
(HASTs) leading to an environmental release via one of the HAST
cooling towers. While precise information on the reference
accident source term or amount of radioactivity likely to be
released is not made publicly available by the UK authorities for
security reasons, it is possible, on the basis of the size of the DEPZ
to make a crude estimate of the size of the source term. This was
found to be equivalent to a small percentage of the inventory for
one of the older HASTs or less that 1% for one of the newer
HASTs, based on the HAST inventories previously reported by the
RPII (Turvey and Hone, 2000).
While the hypothetical release is somewhat smaller for the HASTs
than was the case for the reference accident based on the Calder
Hall reactors, the difference is small and the NII decided to leave the
size of the DEPZ unchanged at 2 km. However, since the current
reference accident does not involve any release of iodine-131 and
since there is no longer a source of iodine-131 at BNFL Sellafield,
the distribution of stable iodine tablets as a countermeasure for the
site is no longer warranted and has been discontinued.
The decision to implement a particular countermeasure (such as
sheltering or the administration of stable iodine) in a given set of
circumstances is generally based on consideration of the benefits
(in terms of reduction in radiation exposure) and the risks
(disruption to normal living) associated with the countermeasure.
In order to assist decision makers radiation doses known as an
Emergency Reference Level (ERL) have been defined in advance,
at which the benefits are likely to outweigh the detriment
associated with implementing the countermeasure.
4.2 Structure of Emergency ResponseThe emergency planning infrastructure in place on the BNFL
Sellafield site includes a site emergency response centre equipped
with the necessary communications infrastructure and access to
site monitoring systems and other response resources. This centre
is at all times manned by the BNFL Sellafield duty site supervisor.
The key facilities of the emergency response centre are duplicated
at a second facility on the site remote from the first. The site
emergency response centre manages all communications between
the site and outside agencies such as the NII, DTI and the local
authority. In addition to the site emergency response centre there
is a network of 12 local response centres located around the BNFL
Sellafield site for the management of emergencies at facility level.
All of the local response centres are identically equipped and are
used regularly for drills and response training.
There are three classifications of emergency for the BNFL
Sellafield site, namely a facility emergency, a site emergency and a
nuclear emergency.
• A facility emergency is defined as an emergency confined to a
single facility and which does not have implications for the
wider site. The response to a facility emergency is managed by
the facility management from a local response coordination
centre;
• A site emergency is defined as an emergency, which affects
more than a single facility but does not have any off-site
implications. The site management manages the response to a
site emergency. Coordination of the initial response is the
responsibility of the duty site supervisor. The site response is
managed from the site emergency control centre, where a site
response coordination team is assembled. Management of the
response at a facility level, however, continues to be the
responsibility of the management for the affected facilities;
and
• A nuclear emergency is defined as an emergency with off-site
consequences. The on-site response is coordinated from the
site emergency control centre while the off-site response is
coordinated from the off-site facility (OSF), which in the BNFL
Sellafield emergency plan is referred to as the District Control
Centre (DCC).
Report of the RPII Visit to BNFL Sellafield12
The site emergency planning officer has responsibility for on-site
planning and coordination with the local authority, Cumbria
County Council. A detailed programme of exercises and
emergency response training is in place for coordination teams,
fire fighters, monitoring teams, etc.
4.3 The Sellafield District Control Centre (DCC)The Sellafield DCC is a purpose-built facility located
approximately 10 km from the BNFL Sellafield site. This facility is
managed by Cumbria County Council but is resourced by BNFL.
The BNFL Sellafield emergency plan envisages that in the event
of an emergency each of the agencies with responsibility for off-
site measures would send a representative to the DCC for the
purpose of coordinating the interagency response. Each agency is
allocated a room with basic IT and communications facilities and a
central area is designated for coordination group meetings. An IT
based information management system is used so that all groups
are kept up to date with developments. A media briefing centre
has been established at a Whitehaven school located
approximately 4 miles from the DCC. The key DCC facilities are
duplicated at a second site.
4.4 Security Issues post 9/11As indicated in the Introduction, discussion of security measures
was not included in this visit. However, since the RPII last visited
the BNFL Sellafield site in 2000, it was evident that a number of
security enhancements have been introduced. Some of the more
obvious manifestations of this enhanced security include:
• The upgrade of fire fighting facilities to deal with the impact of
a major air crash on the site. This has included the
procurement of two airport foam fire tenders and associated
equipment and training;
• The introduction of enhanced perimeter security including
anti-ramming barriers at gates and the use of an increased
number of armed guards;
• The introduction of physical barriers and access restrictions
around individual facilities;
• The construction of heavy barriers around more vulnerable
facilities; and
• The introduction of increased security for visitors to the site.
Report of the RPII Visit to BNFL Sellafield 13
5. Conclusions
5.1 Plant OperationsBNFL Sellafield is an extensive and complex site and there are
several significant hazards present on it. These include, but are not
limited to, the liquid radioactive wastes stored in the Highly Active
Storage Tanks (HASTs), the spent nuclear fuel in storage awaiting
reprocessing and the legacy wastes present in a number of
facilities across the site. The approach being adopted by the
nuclear regulator, the Health and Safety Executive’s Nuclear
Installations Inspectorate (NII), to reduce overall hazard at the site
is to address hazards in parallel. Thus reprocessing and the
management of legacy wastes are continuing while at the same
time the volume of liquid radioactive waste in storage in the
HASTs is being progressively reduced.
The NII requires BNFL to prioritise the reprocessing of Magnox
fuels over oxide fuels. This is because of the instability of Magnox
fuel, particularly under wet storage conditions. If the timetable set
by the NII for completing Magnox reprocessing is interrupted, the
reprocessing of oxide fuels through THORP will be delayed,
thereby extending the lifetime of that plant. The option of further
reprocessing contracts for THORP has not been ruled out but such
a decision is no longer in the hands of BNFL and can only be taken
by the UK Government.
The schedule for the completion of the current reprocessing
contracts is 2010 for oxide fuels and 2012 for Magnox fuels. These
dates are linked to the planned closure programme for Magnox
reactors and the existing reprocessing contracts that BNFL has
entered into with both its UK and overseas customers.
Compliance with these deadlines will require ongoing reliable
throughput of both fuel types at the rates that are only now being
achieved. On the basis of information supplied to the Institute, it is
difficult to see how this can be achieved without also increasing
some radioactive discharges to the environment.
While reprocessing continues, the NII has also stipulated that the
volume of liquid waste stored in the HASTs is to be progressively
reduced at an annual rate of 35 m3 up to 2010 and at a faster rate
thereafter. By July 2015 the volume stored must be reduced to 200 m3
or less. The content of the HASTs currently represents over 90% of
the inventory of radioactivity in the form of waste on the BNFL
Sellafield site.
The recent identification of ‘spikes’ or ‘hot-spots’ of activity in
HASTs 12 and 13 is a matter of concern. While the leaks involve
minute volumes of liquid and have not resulted in a release of
radioactivity to the environment, they do call into question the
long-term integrity of the tanks and underline that the storage of
high-level radioactive waste in liquid form is not sustainable.
The vitrification plant plays a key role in the ability of BNFL Sellafield
to meet its targets over the next few years. If this plant fails to meet
programme requirements, the volume of radioactive waste in
storage in the HASTs can only be controlled by reducing
reprocessing, which in turn means that the 2010 and 2012 deadlines
will be at risk. A possible option would be to close down the
remaining Magnox stations prematurely but as time passes this
would have a progressively smaller impact on the volume of fuel to
be reprocessed. This is because the amount of Magnox fuel already
in reactors or in storage awaiting reprocessing greatly exceeds the
amount of new fuel that will be placed in reactors between now and
the end of the Magnox generating programme in 2010.
At present the major challenge at the BNFL Sellafield site is the
management of legacy wastes. Already the clean-up and
decommissioning of the Magnox Fuel Storage Pond and
Decanning Facility is a significant technical and engineering
challenge with anticipated expenditure up to 2020 of the order of
£150 million per year. The extent to which these operations will
give rise to radioactive discharges has not yet been quantified and
it is too early to say whether future discharges will be greater or
less than those attributable to reprocessing. The UK has indicated
that it will be reviewing its Discharge Strategy (DEFRA, 2002) to
take account of the management of legacy wastes.
Once reprocessing comes to an end and the legacy wastes have
been treated, decommissioning of the BNFL Sellafield site will be
the main on-site activity. The extent of the challenges facing BNFL
and its UK regulators should not be underestimated.
Decommissioning, by its nature, is a slow process that extends
over several decades and current estimates are that
decommissioning and final site remediation of BNFL Sellafield will
not be completed until about 2150 (i.e. 150 years from now).
Ensuring that the resources necessary to support this work are
maintained over this timescale will clearly be a significant
challenge. Decommissioning will also give rise to as yet
unspecified radioactive discharges.
Report of the RPII Visit to BNFL Sellafield14
Responsibility for the management of legacy wastes passes to the
Nuclear Decommissioning Authority (NDA) on 1 April 2005. The
NDA will also assume responsibility for the commercial operations
at BNFL Sellafield and the income generated will be used to fund
clean-up operations. In the Institute’s opinion, this dual
responsibility is not ideal and could result in a situation where
additional reprocessing contracts with overseas customers are
entered into to generate income that would otherwise need to be
provided by central Government. The detail of the way in which
the NDA will operate, and the nature of its working relationship
with the NII and the EA, is still evolving. Both regulatory agencies
have confirmed that the protection of workers, the public and the
environment will continue to be their priorities.
5.2 Radioactive DischargesThe new Discharge Authorisation issued by the Environment
Agency (EA) and which came into effect in October 2004 adopts
an integrated approach to the control of discharges and emissions
from BNFL Sellafield as well as requiring more comprehensive
reporting by BNFL. While the new Discharge Authorisation
reduces the discharge limits for a number of radionuclides, there is
still considerable headroom available to BNFL i.e. the authorised
discharge is still considerably greater than the current rate of
discharge. The new Discharge Authorisation therefore does not
guarantee a reduction in discharges and can be used by BNFL
Sellafield to accommodate any increase in discharges arising from
the increased reprocessing of spent fuel previously mentioned.
The introduction of a new abatement technique involving the
addition of the chemical tetraphenylphosphonium bromide (TPP)
prior to the discharge of Medium Active Concentrate (MAC) has
been highly successful in removing technetium-99 from liquid
discharges, thereby allowing technetium-99 to be stored in solid
form. The technetium-99 site discharge limit has been decreased
from 90 terabecquerels (TBq) to 20 TBq per year. It is anticipated
that all MAC currently in storage will be processed before the end
of 2006 and indications are that this deadline will be met. As all
new significant arisings of technetium-99 generated by Magnox
reprocessing are now being diverted directly to vitrification, it is
expected that a further reduction in the technetium-99 discharge
authorisation (to 10 TBq per year) will come into operation in early
2007, at the latest. The TPP procedure has already significantly
reduced discharges of technetium-99 from the BNFL Sellafield site
into the Irish Sea. This initiative will assist the UK in meeting its
OSPAR obligations.
5.3 Emergency PreparednessEmergency preparedness arrangements are in place to deal with
incidents and accidents affecting the Sellafield site and the
surrounding area. These are regularly tested and comply with the
Radiation (Emergency Preparedness and Public Information)
Regulations, 2001 (REPPIR).
A reference accident, defined as the worst credible accident that is
reasonably foreseeable at the site, has been detailed and
approved by the NII. The exact details of the reference accident
were not made available to the Institute for security reasons.
However, the Institute was informed that the BNFL Sellafield off-
site emergency plan provides for a detailed emergency planning
zone (DEPZ) out to 2 km from the site boundary, within which
detailed plans must be prepared for evacuation of the population.
Using this information, the Institute was able to estimate the
source term for the accident and to make an assessment of the
potential consequences for Ireland of an accident at BNFL
Sellafield consistent with a 2 km DEPZ.
The assessment assumes that the wind direction was such that
radioactivity released to the atmosphere at Sellafield is carried
directly across Ireland. It shows that the potential contamination
levels in Ireland that could result from such an accident are orders
of magnitude below that at which the implementation of
“immediate countermeasures” such as evacuation or sheltering
would be warranted in Ireland. However, regarding foodstuffs
countermeasures, the assessment undertaken demonstrates that
the BNFL Sellafield reference accident could result in levels of
contamination in the food chain that would require intervention
from the Irish authorities. The changing situation at BNFL
Sellafield, as well as other UK nuclear sites, is monitored on an
ongoing basis by the RPII. Advice in relation to emergency
preparedness arrangements, including the implementation of
countermeasures, is updated as necessary.
From an Irish perspective it is vital that, in the event of an
emergency, procedures are in place to provide Irish authorities
with adequate information in real time. Notification arrangements
have been tested in a recent bilateral exercise and have been
Report of the RPII Visit to BNFL Sellafield 15
shown to work well. In December 2004, an Agreement was signed
on behalf of the Governments of Ireland and the UK which
ensures both countries will cooperate fully in the event of a
significant nuclear incident. The Agreement provides for rapid
exchange of information between the parties and for the regular
testing of these arrangement. The UK has also recently facilitated
direct access for Ireland to its RIMNET (Radioactive Incident
Monitoring Network) system. RIMNET comprises 92 monitoring
sites located around the UK and the network supplies routine
hourly readings and raises an alert if any abnormal increases in the
level of radioactivity are noted. Access to this system is on a real
time basis and is managed in Ireland by the RPII. The RPII
considers that access to RIMNET is useful and welcomes the
initiative from the UK to make it available.
5.4 Terrorist ThreatsNuclear fuel reprocessing by its nature gives rise to the generation
of large inventories of radioactive material, much of which is in a
readily dispersible physical form. Nuclear reprocessing plants such
as BNFL Sellafield, therefore, include a number of facilities holding
inventories of readily dispersible radioactive materials likely to
constitute potential terrorist targets.
The HASTs have long been identified as an issue of particular
concern in Ireland given their radioactive inventory and the fact
that the waste is stored as a liquid. Since the events of 11
September 2001, greater consideration has been given to the
possibility of a HAST failure caused by a malicious incident. The
NII has repeatedly assured the Institute that it is satisfied that the
HASTs have a very high level of protection both in terms of
engineered safety systems and physical security. However, for
security reasons, it is not possible for the NII to share detailed
information with the Institute to allow it to make its own
assessment of the likely consequences for Ireland of a terrorist
attack on the HASTs.
There is a well-established and internationally accepted framework
for accessing the safety of nuclear installations with respect to
“accidental” failures. This framework includes clearly understood
methodologies for assessing risk of failure and places a heavy
dependence on peer review to assess the adequacy of safety
arrangements. The situation with regard to emergencies resulting
from malicious or terrorist incidents is significantly different. Here
there is no widely accepted and transparent methodology for
assessing risks or consequences of an event resulting from a
terrorist attack. Furthermore, the necessity to protect information
from falling into the wrong hands means that such security
systems are not subject to public peer review. The scope and
extent of the terrorist threat assessments undertaken for BNFL
Sellafield are not known. No information on any such assessment
is available in the public domain.
In accordance with International Atomic Energy Agency (IAEA)
guidance7, States should develop a Design Basis Threat (DBT)
from an evaluation of the threat of unauthorised removal of
nuclear material and of sabotage of nuclear material and nuclear
facilities. In the UK the DBT is drawn up by the Office for Civil
Nuclear Security (OCNS). The design basis threat sets out the
forms of possible attack against which nuclear sites should protect
themselves. Measures taken by operators in relation to the design
basis threat are subject to regulatory scrutiny but details of the
measures and of their scrutiny by regulators are classified.
While accepting fully the need to protect sensitive information
about plant security, the lack of an established framework for
assessing the adequacy of threat assessments and security
arrangements remains a significant concern.
7 The Physical Protection of Nuclear Material and Nuclear Facilities,INFCIRC/225/Rev.4
Report of the RPII Visit to BNFL Sellafield16
6. References
CoRWM (2004) Preliminary Report on the Inventory. CoRWM
Document 542. Committee on Radioactive Waste Management.
www.corwm.org.uk/PDF/Inventory.pdf
DEFRA (2001) Managing Radioactive Waste Safely. Proposals for
developing a policy for managing solid radioactive waste in the
UK. Department for Environment, Food and Rural Affairs.
www.defra.gov.uk/environment/consult/radwaste/default.htm
DEFRA (2002) UK Strategy for Radioactive Discharges, 2001-
2020. Department for Environment, Food and Rural Affairs.
www.defra.gov.uk/environment
/radioactivity/discharge/strategy/index.htm
DTI (2002) Managing the Nuclear Legacy. A Strategy for Action.
Department of Trade and Industry.
www.dti.gov.uk/nuclearcleanup/pdfs/whitepaper.pdf
DTI (2004) Civil Nuclear Emergency Planning Consolidated
Guidance. Department of Trade and Industry.
www.dti.gov.uk/energy/nuclear/safety/neplg_guide.shtml
HSE (1990) Outline Emergency Planning for Licensed Nuclear
Power Stations. Health and Safety Executive.
HSE (2000a) The Storage of Liquid High-level Waste at BNFL
Sellafield: A Report by HM Nuclear Installations Inspectorate.
Health and Safety Executive. www.hse.gov.uk/nsd/bnfl.pdf
HSE (2000b) HSE Team Inspection of the Control and Supervision
of Operations at BNFL’s Sellafield Site. Health and Safety
Executive. www.hse.gov.uk/nsd/team.htm
HSE (2001) The Storage of Liquid High-level Waste at BNFL
Sellafield: Addendum to February 2000 Report. Health and Safety
Executive. www.hse.gov.uk/nsd/bnfl2.pdf
HSE (2002) A Guide to the Radiation (Emergency Preparedness
and Public Information) Regulations 2001. Health and Safety
Executive. www.hse.gov.uk/radiation/ionising/reppir.htm
HSE (2005) HMNII’s 2004 Biennial Review of the Storage of Liquid
High Level Waste at Sellafield. Annex to Sellafield and Drigg LLC
Report for Oct-Dec 2004. Health and Safety Executive.
www.hse.gov.uk/nsd/llc/2004/sella4.htm
NDA (2004) NDA Annual Plan. Draft for Consultation. Document
URN04/2009. Nuclear Decommissioning Authority.
www.nda.gov.uk
NRPB (1997) Application of Emergency Reference Levels of Dose
in Emergency Planning and Response. Documents of the NRPB,
Vol. 8, No 1. National Radiological Protection Board.
OSPAR (1998) OSPAR Strategy with regard to Radioactive
Substances. The Convention for the Protection of the Marine
Environment of the North-East Atlantic (OSPAR Convention).
www.ospar.org
RSA (1993) Radioactive Substances Act (c. 12). ISBN
0105412937. The Stationary Office Ltd., London.
www.hmso.gov.uk/acts/acts1993/Ukpga_19930012_en_1.htm
RWMAC (2000) RWMAC’s Advice to Ministers on the
Radioactive Waste Implications of Reprocessing. Radioactive
Waste Management Advisory Committee.
www.defra.gov.uk/rwmac/reports/reprocess/index.htm
Travis, M. (2003) Decommissioning a Spent Fuel Storage Pond
and Decanning Facility. Nuclear Engineer 44(2) p. 55-57.
Turvey, F.J. and Hone, C. (2000) Storage of Liquid High-Level
Waste at Sellafield. An Examination of Safety Documentation.
Radiological Protection Institute of Ireland. www.rpii.ie/reports
Report of the RPII Visit to BNFL Sellafield 17
Annex 1Regulation of Activities at BNFL Sellafield by the Health and Safety Executive’s Nuclear Installations Inspectorate
A1.1 IntroductionThe Nuclear Installations Inspectorate (NII), which forms part of
the UK Health and Safety Executive (HSE), licenses the BNFL
Sellafield site, in common with other UK nuclear installations,
under the Nuclear Installations Act, 1965 (as amended). The
parent Government Department to HSE is the Department of
Work and Pensions but this Department has no role in the
promotion of nuclear energy.
The licensed site includes all the territory and buildings within the
perimeter fence and the licence covers all activities at BNFL
Sellafield involving nuclear and radioactive materials, other than
discharges to the environment which are regulated by the
Environment Agency (EA).
There is a Memorandum of Understanding in place between the
NII and EA as close liaison between these two regulators is
essential if there is to be a coherent approach to radiation
protection of workers and the general public.
The HSE publishes reports of all NII examinations of activities at its
licensed sites as well as quarterly reports for local liaison committees
and quarterly reports of incidents at nuclear installations.
A1.2 Licensing SystemUnlike the licensing systems in many countries where licenses are
valid for a fixed period and where applications for renewal must
be supported by evidence that the licensee remains fit to hold a
licence, in the UK licences for nuclear sites remain in force until all
activities covered by the licence cease and all facilities on the site
have been decommissioned. The continued acceptability of the
practices in which the licensee is engaged is reviewed at specified
intervals, e.g. biennially, quinquennially and, particularly
thoroughly, every ten years.
The review system is applied most rigorously to nuclear power
plants which incorporate life limiting components, for example the
steel reactor pressure vessel in early Magnox reactors which
degrades over time due to neutron embrittlement. However they
are also applied at BNFL Sellafield and other nuclear sites. For
example in the case of Sellafield, considerable work has been
done by BNFL to satisfy the NII that the integrity of the concrete
biological shields on the HASTs and of the stainless steel of the
HASTs themselves, can be guaranteed for the remaining lifetime
of the HASTs. As discussed below, the NII has a number of legal
instruments at its disposal to force licensees to suspend or modify
practices which are covered by the licence.
A1.3 Licence ConditionsThere are 36 standard conditions attached to each licence. The
conditions, which are the same for all nuclear sites, are general
rather than prescriptive in nature. They refer, for example to
making adequate arrangements for bringing and storing nuclear
material on the site (condition 4). The arrangements made by the
licensee must be submitted to the NII for approval.
Of particular interest is condition 36 on the Control of
Organisational Change. This condition obliges the licensee to
make and implement adequate arrangements to control any
change to its organisational structure which may affect safety and
to submit these arrangements to the NII for approval before
implementing them. This condition was introduced in answer to
NII concerns that staffing structures at a number of nuclear
facilities, including in particular Sellafield, were being allowed to
change in a manner which was potentially deleterious to safety. It
was introduced in the summer of 1999 and came into full force in
April 2000, i.e. shortly after the Team Inspection of February 2000,
referred to in section A1.7.
Authorisations permitting change are issued in the form of a
Licence Instrument.
A1.4 Safety CasesThe licensee must prepare Safety Cases for operations on the site
and, where required, submit them to NII for its assessment. Safety
Cases are assessed against the NII’s Safety Assessment Principles
(SAPs) that, in turn, make use of a concept known as Tolerability of
Risk (ToR). This concept postulates three levels of risks. These are
risks that are broadly speaking intolerable, risks that, while
tolerable, should be reduced further if it is practicable to do so
(the As Low As Reasonably Practicable, or ALARP, principle) and
risks that are so trivial that expenditure on reducing them further
would not be justified. The SAPs also refer to probability of
occurrence. For example an accident scenario with very severe
consequences may be considered tolerable if the licensee can
Report of the RPII Visit to BNFL Sellafield18
satisfy the NII that the probability of occurrence is extremely low,
i.e. typically less than one in a million per year.
The Safety Case must also satisfy the NII that all plant and component
failures, which could impinge on safety, have been considered and
that the Probabilistic Safety Assessment, which is used to calculate
risks, is based on realistic estimates of plant and component failures
and on the significance of these failures for safety.
The Safety Case of most direct relevance to the RPII visit is the
Continued Operation Safety Report (COSR) for the HASTs. This
report, which was the subject of an examination by RPII officials, is
discussed in section 3.4.
A1.5 Alterations to the SiteSignificant alterations to the licensed site require prior approval by
the NII. These include in particular:
• The construction of new plant;
• Any modifications to the design of plant under construction
which may affect safety;
• The commissioning of new plant and processes; and
• The restarting of operations, which have been suspended or
shutdown for any reason.
In the case of major projects each step of the project requires a
separate authorisation in the form of a Licensing Instrument.
A1.6 EnforcementThe NII makes use of a number of controls derived from licence
conditions. These include giving Consents, Approvals and
Directions. The licence conditions also provide for the use of
Agreements, Notifications and Specifications. These generally act
as enforcement tools in the non-prescriptive nuclear regulatory
regime. NII inspectors may also use their enforcement powers
under the Health and Safety at Work Act, 1974 (HSWA) to issue
Improvement Notices and, in the case of imminent danger,
Prohibition Notices.
Agreements, notifications, and specifications are all legally
binding communications between the NII and the licensee. They
either allow the licensee to carry out an activity or require some
form of action to be taken. To administer these requests/
authorisations, NII has produced a standard form of letter known
as a licence instrument.
NII may bring prosecutions for breaches of HSWA or licence
conditions. NII’s powers are summarised below.
A1.6.1 ConsentsA Consent is required before the licensee can carry out any activity
which is specifically identified in the licence. For example, consent
is required before a reactor is allowed to be started up again
following its periodic shutdown. Before being granted a Consent
the licensee must satisfy the NII that their proposed action is safe
and that all procedures necessary for control are in place.
A1.6.2 ApprovalsAn Approval is used to freeze a licensee’s arrangements. If the NII
so specifies the licensee is required to submit its arrangements and
cannot carry them out until the NII has given its approval. Once
approved, the procedures cannot be changed without the NII’s
agreement, and the procedure itself must be carried out as
specified; failure to do so would infringe the licence condition and
would be an offence. For example, for nuclear power stations the
NII has approved operating rules important to safety in order to
ensure that licensees cannot change these without seeking the
NII’s agreement to the change.
A1.6.3 DirectionsA Direction is issued by the NII when it requires the licensee to
take a particular action. For example, licence condition 31(1) gives
the power to Direct a licensee to shut down any plant, operation
or process. Such a Direction would relate to a matter of major or
immediate safety importance and has been used rarely.
Report of the RPII Visit to BNFL Sellafield 19
A1.6.4 AgreementsAn Agreement issued by the NII allows a licensee, in accordance
with its own arrangements, to proceed with an agreed course of
action. For example licence condition 22 requires a licensee to have
adequate arrangements to control modifications to safety related
plant. Such arrangements will often state that for modifications
which, if inadequately conceived or implemented, there could be
serious nuclear safety implications, the modification cannot be
carried out without the agreement of the NII. Hence, the licensee
submits a Safety Case justifying the modification and does not
proceed until the NII has written agreeing to this proposal.
A1.6.5 NotificationThe standard licence gives the NII powers to request the
submission of information by notifying the licensee of the
requirement. For example in licence condition 21(8) the licensee
shall, if notified by the NII, submit a Safety Case and shall not
commence operation of the relevant plant or process without the
consent of the NII.
A1.6.6 SpecificationThe standard licence gives the NII discretionary controls with
regard to a licensee’s arrangements and these are implemented
through Specifications. For example, under licence condition
23(2), if the NII so specifies, the licensee is required to refer
operating rules to its nuclear safety committee for consideration.
A1.7 Inspections and ReportsThe NII operates a comprehensive inspection programme. A site
inspector, who is responsible for coordinating inspections, is
designated to each nuclear site. In the case of BNFL Sellafield
some 500 days of inspectors’ time per year are assigned.
In addition to routine inspections, the NII carries out inspections
focused on particular activities at BNFL Sellafield. In September
1999 the NII carried out a team examination of the control and
supervision of operations on the site. This identified shortcomings
pertaining to safety in management systems, organisational
structures, inadequate resources and independent audits. The
report of this visit (HSE, 2000b), published in February 2000,
included 28 recommendations to address these issues. These have
now been closed out to the satisfaction of the NII.
Another NII report of particular relevance to the visit is the
February 2000 report on the storage of liquid high-level waste
(HSE, 2000a). This is a comprehensive review of safety issues
relating to the storage of HLW at BNFL Sellafield. The report
focuses on the integrity of the cooling systems which are required
to prevent the contents of the tanks from boiling and the need to
reduce the stored contents through vitrification. The report
includes 22 recommendations relating to these issues. It should be
noted that the main issues of concern referred to in the NII report
are the same as those highlighted in the RPII report already
referred to in section 3.4.
Report of the RPII Visit to BNFL Sellafield20
In August 2001 NII published an addendum to the February report
which found that all 22 recommendations had essentially been
closed out by January 2001, subject to an ongoing programme of
work. This ongoing programme of work included, in particular,
making the plant more resistant to severe seismic events and by
implication certain forms of terrorist attacks.
A1.8 Implications of BNFL Restructuring for theRegulatory ProcessBNFL is in the process of restructuring in readiness for the
commencement of the Nuclear Decommissioning Authority (NDA)
operation on 1 April 2005. One of the implications is that BNFL, as
presently constituted, will be restructured to form separate
companies that will tender to provide decommissioning services of
one kind or another. The NII will need to be satisfied that the
restructured entity is a viable licensee in terms of its ability to
comply with the NII’s safety requirements.
The NII is also expected to insist that, in order to ensure a
coherent approach to site safety, certain activities involving the
clean-up of legacy wastes and commercial activities i.e. the
reprocessing of spent fuel in THORP and the production of MOX
fuel be carried out under one licence.
BNFL is currently providing the NII with a suite of documents
justifying the proposed change. If, following a perusal of these
documents and a number of inspections to assess readiness for
the proposed changes, NII is satisfied with the planned
restructuring, a licence Instrument will be issued on the 31 March
2005 allowing the restructuring to take place.
A1.9 NII In-house ProceduresThe NII has an ongoing in-house programme of self-assessment
and benchmarking. This includes, in particular, providing the
Nuclear Safety Advisory Committee of the UK Health and Safety
Commission with the terms of reference for a review study of its
SAPs. It also benchmarks its SAPs and Technical Assessment
Guides (TAGs) against the IAEA Safety Standards, Fundamentals,
Requirements and Guides and has a programme to revise them
where the need for revision is indicated.
Report of the RPII Visit to BNFL Sellafield 21
Annex 2Regulation of Activities at BNFL Sellafield by the Environment Agency
A2.1 IntroductionThe Environment Agency regulates the disposal of radioactive
waste to land, sea and air from all nuclear sites in England and
Wales (including the BNFL Sellafield site) by means of
authorisations issued under the Radioactive Substances Acts,
1993. The Environment Agency consults the NII on matters
affecting the exposure of workers and the risk of accidents, in
accordance with NII’s role as a statutory consultee. The nuclear
regulatory work of the Environment Agency (EA) is funded partly
by grant-in-aid and partly by direct charging. In total, forty EA staff
are assigned to nuclear regulation, of which 19 are site inspectors.
On average, site inspectors spend 40% of their time on site. The
EA’s nuclear site regulators are structured into two teams, North
and South. The EA’s Radioactive Substances Regulation (RSR)
Process Group defines how regulatory policy, as set out by the EA
RSR Policy Team, is implemented by the site regulators.
The EA’s regulatory regime covers policy, process and operations
with regard to discharges from the BNFL Sellafield site and it
operates within a legal and policy framework, governed by:
• The Environment Act, 1995;
• The Radioactive Substances Act, 1993 (RSA, 93);
• Government objectives for the EA;
• The UK Strategy for Radioactive Discharges, 2001-2020
(DEFRA, 2002);
• EU directives and international commitments;
• Memoranda of Understanding with the Nuclear Installations
Inspectorate, the Food Standards Agency, the Scottish
Environment Protection Agency and the Nuclear
Decommissioning Authority (currently being drafted); and
• Sector Plan: The EA is setting up partnerships with different
industry sectors to set out what measures it is introducing on
the environment and what its objectives are to reduce
environmental impacts.
The Radioactive Substances Act states that UK Government
Ministers have the right to intervene in EA decisions. The EA
sends all its decisions to Ministers so that they may decide
whether or not to use their powers of intervention.
The EA issues Certificates of Authorisation, under the provisions of
section 13 of the RSA 93, which permit the disposal of specified
radioactive wastes from a specified site, subject to limitations and
conditions. The BNFL Sellafield Certificate of Authorisation
comprises a signed certificate together with nine schedules.
Schedule 1 contains general conditions that are applicable to all
authorised waste types. Schedule 2 specifies the categories of
radioactive waste and the disposal routes that are authorised.
Schedules 3 to 8 include limitations and conditions on the
radionuclides in the waste and the physical nature of the waste
streams. Schedule 9 specifies information to be supplied by the
licensee, in this case BNFL plc, and improvements to be carried out.
The main practices to which the BNFL Sellafield certificate
relates are:
• Reprocessing of Magnox spent fuel;
• Reprocessing of oxide spent fuel (THORP);
• Processing of historic liquid wastes;
• Solid waste storage/retrieval;
• Decommissioning of redundant plant;
• (Decommissioning of) Calder Hall nuclear power station; and
• Research and development.
A2.2 New Certificate of Authorisation for Radioactive Discharges from the BNFL Sellafield SiteIn 1999 the UK Government asked the Environment Agency to
carry out a review of the authorisations at the BNFL Sellafield site.
Following a consultation period, a draft document outlining the
EA’s decisions was published in August 2002. The document was
submitted to the Secretary of State for Health and the Secretary of
State for Environment, Food and Rural Affairs. This decision
document was revised in 2004 to reflect both consultation and the
fact that there had been some major developments since the
decisions were first issued (most notably, the closure of the Calder
Hall reactors). A separate ‘fast track’ review of the regulation of
technetium-99 liquid discharges into the sea from BNFL Sellafield
was also undertaken. The steps involved in these reviews are
outlined in Table 1.
Report of the RPII Visit to BNFL Sellafield22
The EA’s stated objectives of the reviews were to ensure that
prescribed limits and conditions are appropriate, that disposal
represents the Best Practicable Environmental Option (BPEO), that
Best Practicable Means (BPM) are used to minimise waste
discharges and that radiation doses to the public are kept ‘As Low
As Reasonably Achievable’ (ALARA) and remain within the legal
limits and constraints. In developing the new authorisation, the EA
carried out an examination of the existing framework of discharge
limits and the numerical values of individual limits, to assess
whether or not any changes were appropriate for the future
regulation of waste discharges from the site.
The main features of the new authorisation are:
• A new integrated authorisation to replace the six previous
authorisations.
• Updated discharge limits: Reductions in the ‘headroom’ (i.e.
gaps between the expected/typical discharges and the
discharge limits authorised) and reductions in 14 site limits for
discharge to air and 8 site limits for discharge to sea.
• Removal of two aerial discharge limits (argon-41 and sulphur-
35) as a result of the shut-down of the Calder Hall reactors.
• More limits on discharges from individual plants as well as
from the site as a whole.
• Introduction of throughput related limits for Magnox and
THORP.
• Introduction of new conditions requiring BPEO/BPM8 to be
used to control discharges. In addition, a programme of
process and environmental improvements and research are
outlined in the authorisation.
• New conditions requiring BNFL to have management systems,
organisational structures and resources to achieve compliance
with the authorisation.
Table 1Timeline of Review and Issue of BNFL Sellafield Discharge Authorisations
Date New (Main) Authorisation Technetium-99 Authorisation
July 2000 Scope and Methodology published
after public comment
November 2000 Consultation on Technetium-99 proposals
July 2001 Consultation on proposals
September 2001 Proposed Decision on Technetium-99
August 2002 Proposed decision
December 2002 Ministers’ Decision
July 2003 MAC diversion
March 2004 Ministers’ consent to proceed
April 2004 TPP implemented
August 2004 Authorisation issued (following update and
consultation with HSE/NII and FSA)
October 2004 Authorisation came into force
8 BPEO: Best Practicable Environmental Option – the best option for disposal ofradioactive waste (based on environmental impact)BPM: Best Practicable Means - minimising of discharges once the BPEO route hasbeen chosen (“optimisation”)
Report of the RPII Visit to BNFL Sellafield 23
A2.3 An Integrated Authorisation for Regulating Radioactive Waste Disposals fromBNFL SellafieldThe EA is introducing integrated certificates of authorisation for
the disposal of radioactive waste from nuclear sites. In contrast to
previous certificates of authorisation, which related to disposal
either to land, water or air, an integrated certificate of authorisation
specifies the general conditions that apply to all disposal routes. It
also specifies the limitations and conditions that apply to individual
disposal routes. One of the EA’s stated aims is improved alignment
with the approach to regulating the discharge of other pollutants.
Prior to the issuing of the new authorisation in October 2004,
there were six authorisations covering the BNFL Sellafield site:
• Discharges to air
• Discharges to sea
• Incineration of oil
• Disposal of solid LLW to Drigg
• Disposal of LLW to BNFL Sellafield
• Transfer of waste from BNFL Sellafield to other BNFL and
UKAEA sites
Under the new authorisation issued, these six authorisations have
been integrated into a single (multi-media) authorisation which
includes: standard general conditions which are consistent across
the nuclear industry including the use of BPEO/BPM; new
conditions covering the management, organisation and resources
of BNFL; a revised framework of discharge limits; and a number of
proposed discharge reduction schemes.
A2.3.1 Limits and Advisory Levels in the New AuthorisationThe current authorisations require BNFL to submit annual reports
to the Agency on the progress that has been made in research
and development for achieving a continuing reduction in
radioactive discharges.
The previous BNFL Sellafield authorisations contained the
following range of limits and advisory/notification levels:
a. 12 month rolling (annual) limits for site discharges;
b. Annual limits for plants or groups of plants (i.e. schedules
containing limits for groups of stacks);
c. Additional components to annual limits for a small number of
specific plants;
d. Short-term limits (monthly, weekly and daily);
e. Plant throughput limits for THORP aerial and liquid discharges;
f. Calendar year limits for solid waste disposals to Drigg;
g. Radionuclide concentration limits for on site solid waste
disposals; and
h. Quarterly notification levels for aerial and liquid discharges.
In the new authorisation, the following changes were introduced:
a. Site annual discharge limits will be expanded to cover all
radionuclide discharges, which meet defined criteria9.
b. Annual discharge limits set at a plant level, rather than group
of plants, wherever practicable and where plant radionuclide
discharges meet the defined criteria.
c. The additional components to limits, which allowed increased
discharges in the event of prolonged plant outage, were
removed, wherever deemed practicable.
d. New plant limits were introduced (i.e., controls on discharges
from individual plants as well as from the overall site).
e. Weekly limits and advisory levels replaced a range of short-
term limits (daily and weekly).
f. Throughput related limits now apply to the Magnox
Reprocessing Plant as well as to THORP and they apply to any
period of 12 consecutive months rather than a calendar year.
g. New limits have been introduced to regulate the transfer of
radioactive waste between BNFL Sellafield and other
nuclear sites.
h. New limits have been introduced to allow the extended use of
on-site solid waste disposal facilities and the previous
provision for in-situ burial of waste on the BNFL Sellafield site
and its associated limits has been revoked.
i. Quarterly notification levels now apply to any 3 month period
rather than a calendar year quarter and are set at 25% of all site
and plant annual discharge limits.
9 The dose to the most exposed group from the established worst case sitedischarges exceeds 1 microsievert (µSv) per year OR the collective dose (world-wide truncated at 500 years) from the established worst case site dischargesexceeds 0.1 manSv per year of discharge OR the quantity of the established worstcase site discharge exceeds 1 gigabecquerel per year (for gaseous discharges) or 1
terabecquerel per year (for aqueous discharges) OR the half-life of theradionuclide exceeds 10 years and the radionuclide is concentrated inenvironmental materials by a factor greater than 1000 OR the discharge will beused as plant performance or process control indicator or for effective regulatorycontrol and enforcement.
Report of the RPII Visit to BNFL Sellafield24
The EA applies the following principles in setting the annual limits
on discharges:
• The limits will be based on the minimum level of discharge the
EA judges that the operator needs to make in order to operate
the plant;
• The limits will provide necessary headroom based on
fluctuations and/or trends in the level of discharge from year
to year, which the Agency judges are an inherent characteristic
of the design of a plant and its operation; and
• The objective is that there should be no unnecessary
headroom when the limits are set.
The previous and new annual limits for discharges to sea and air
are summarised in Table 2.
A2.3.2 Radionuclide-specific Site Disposal LimitsTechnetium-99: Following the implementation of technetium-99
abatement involving addition of the chemical
tetraphenylphosphonium bromide (TPP) in the Enhanced Actinide
Removal Plant, the technetium-99 site limit has been decreased
from 90 terabecquerels (TBq) per year to 20 TBq per year. This
will be further reduced, to 10 TBq per year, once the waste in the
MAC storage tanks has been processed.
Table 2Annual Limits for Discharge from the BNFL Sellafield Site
Radionuclide or
Group of Radionuclides Sea Pipelines (TBq) Aerial (TBq x 10-3)
Previous Limits From October 2004 Previous Limits From October 2004
Tritium (H-3) 30,000 20,000 1,500,000 1,100,000
Carbon-14 21.0 21.0 7300 3300
Cobalt-60 13.0 3.6 0.92 n/a
Strontium-90 48.0 48.0 9.4 0.71
Sulphur-35 n/a n/a 210 n/a
Argon-41 n/a n/a 3,700,000 n/a
Krypton-85 n/a n/a 590,000,000 440,000,000
Zirconium-95 + Niobium-95 9.0 3.8 Not specified Not specified
Technetium-99 90.0 20.0 Not specified Not specified
Ruthenium-106 63.0 63.0 56.0 28.0
Antimony-125 Not specified Not specified 5.0 2.3
Iodine-129 2.0 2.0 70.0 70.0
Iodine-131 Not specified Not specified 55.0 55.0
Caesium-134 6.6 1.6 Not specified Not specified
Caesium-137 75.0 34 18.0 5.8
Cerium-144 8.0 4.0 Not specified Not specified
Neptunium-237 Not specified 1.0 Not specified Not specified
Plutonium (Alpha) 0.7 0.7 1.2 0.19
Plutonium-241 27.0 25.0 17.0 3.0
Americium-241 0.3 0.3 0.74 0.12
Curium-243+244 Not specified 0.069 n/a n/a
Total Alpha 1.0 1.0 2.5 0.88
Total Beta 400 220 340 42.0
Uranium (in kg) 2000 2000 Not specified Not specified
Report of the RPII Visit to BNFL Sellafield 25
Antimony-125: The proposed new site limit for the radionuclide
antimony-125 in liquid discharges has been deferred pending
more information from BNFL. The discharge of antimony-125 will
remain limited by the site limit, and a new plant limit, on total beta
activity and will be subject to the requirements to minimise
discharges through the application of BPM and to a specific
requirement to carry out a programme of work. The introduction
of a site limit for antimony-125 in liquid discharges will be
reviewed before the end of 2007.
Argon-41 and Sulphur-35: The plant and site limits for aerial
discharges of argon-41 and sulphur-35 have been removed in
response to the shut-down of the Calder Hall Power Station.
Liquid discharges of Carbon-14, Strontium-90,
Ruthenium-106, Iodine-129, Plutonium (alpha),
Americium-241, Total Alpha and uranium: The aqueous
discharge limits remain unchanged. In all these cases, BNFL’s
stated business requirements exceed the current limits. The EA
has reviewed BNFL’s estimates of future discharges in the
context of BNFL’s future business plans and considers there is no
scope for reduction in these limits at the current time. With the
exception of carbon-14, the major future source of the aqueous
discharges of these radionuclides is predicted to be the
processing of medium active liquid wastes (medium active
concentrate for strontium-90 and salt evaporator concentrate for
ruthenium-106) and decommissioning work (for the alpha
emitting radionuclides).
Carbon-14: Magnox reprocessing and the storage plant for high
level liquid waste are predicted to be the major future source of
carbon-14 liquid discharges. The installation of a new caustic
scrubber in 2001 to remove carbon-14 from aerial discharges from
the high level waste storage plant has diverted the majority of
carbon-14 from aerial to liquid discharges, resulting in higher
liquid discharges of carbon-14.
Liquid discharges of Hydrogen-3 (Tritium), Cobalt-60,
Zirconium-95/Niobium-95, Caesium-134, Caesium-137,
Cerium-144, Plutonium-241 and Total Beta: The past
performance of the SIXEP plant in removing caesium from liquid
discharges and the reduction in the processing of medium active
concentrate are two of the main reasons why the discharge limits
for these radionuclides have been introduced.
Aerial discharges of Hydrogen-3 (Tritium), Carbon-14,
Krypton-85, and Argon-41: Magnox reprocessing is the
major source of aerial discharges of tritium. The EA considers
that there is scope for a reduction in the current effective site
limit whilst still allowing for a maximum Magnox reprocessing
fuel throughput of 1600 metric tonnes in any 12 month period
and allowing for the possibility of reprocessing higher burn-up
Magnox fuel towards the end of the Magnox reprocessing plant
lifetime. The main source of krypton-85 discharges is the
THORP reprocessing plant. The EA proposed reduction in the
limit, which would still allow for a maximum THORP
reprocessing fuel throughput of 1200 te in any 12-month period
and for the programmed reprocessing of higher burn-up oxide
fuel over the next 7 years.
A2.3.3 Annual Plant Discharge LimitsThe EA has investigated whether it would be practicable for BNFL
to monitor individual plant waste streams and has required BNFL
to provide information including the costs of installing new
monitoring equipment10. Following the investigation, the EA has
decided to require BNFL to report separately the discharges for
each of the main activities on the site. Where appropriate
monitoring arrangements are not in place, discharges will be
estimated indirectly using knowledge of actual operations and
actual discharges where they are measured. In such cases the
assessment methodology must be approved by the EA. This new
reporting procedure comes into operation in June 2006.
Limits are proposed for the individual major discharge stacks across
the BNFL Sellafield site and for the major effluent treatment plants
on the BNFL Sellafield site. While plant limits were previously
specified for aerial discharges from individual stacks, or groups of
stacks11, aqueous plant limits are a new feature of the authorisation.
The sum of the plant limits does not equal the relevant site limits.
This is because site limits are based on the sum of the worst-case
plant discharges, but the plant limits are based on the individual
worst-case plant discharge plus an operating margin.
10 DETR draft Statutory Guidance states: “Monitoring requirements should beframed in such a way as to allow the discharges from each plant, or otherappropriate individual sources for large plant, to be identified separately, and notmerely as aggregated discharge levels”.
11 previously known as schedule limits.
Report of the RPII Visit to BNFL Sellafield26
A2.3.4 BPEO/BPM RequirementsThe authorisation requires BNFL to demonstrate that the best
practicable environmental option has been adopted for the
disposal of all principal waste streams. The demonstration of BPEO
will be a pre-requisite for any waste management strategy that
involves dilution and dispersal of radionuclides in the
environment, where concentration and containment of waste
would be a feasible alternative.
The application of Best Practicable Means (BPM) involves the use of
a level of management and engineering control to minimise as far as
practicable the release of radioactivity to the environment. It takes
account of a range of factors including cost effectiveness,
technological status, operational safety and social and
environmental factors. Under the BPM conditions in the
authorisation, BNFL should take into account a range of factors
including the benefit, cost effectiveness, technological status,
operational safety and social and environmental factors, when
deciding on a waste disposal route or method. In its assessment of
the waste management techniques used at BNFL Sellafield, the EA
takes account of best industry practice and experience in other
countries.
The outcomes of the EA review of its assessment of waste
management techniques in light of BPM/BPEO are summarised
below:
Hydrogen-3 (Tritium): The EA considers that BNFL’s current
practices for disposing of tritium from BNFL Sellafield represent
BPEO. The Agency considers therefore that current practice of
caustic scrubbing of process extract ventilation streams in the
Magnox Reprocessing Plant is consistent with the use of BPM for
minimising tritium discharges to atmosphere. The EA also considers
that caustic scrubbing and chilled water dehumidification of
process extract ventilation streams in THORP is consistent with the
use of BPM for tritium discharge minimisation.
Carbon-14: The EA considers that the current operation of the
carbon-14 (barium carbonate) removal plant in THORP that
results in the radionuclide being trapped in a solid waste-form
and subsequently encapsulated in cement represents BPEO.
However, it remains to be convinced that the current design and
operation of the plant is consistent with the use of BPM for
minimising discharges.
Cobalt-60: The EA considers that the use of an ion exchange pre-
coat on an existing particulate filter in the THORP fuel pond, if
current plant trials are proven to be successful, would represent
BPEO for disposing of cobalt-60 in a solid waste and BPM for
minimising discharges to sea.
Caesium-137: The EA considers that BNFL’s current practice of
converting greater than 99% of caesium-137 in spent fuel into a
solid waste form and storing it to await disposal is consistent with
BPEO. The EA considers that further reductions in caesium-137
discharges to sea could be achieved by routing B27 pond purge
water to SIXEP. The Agency proposes to require BNFL to
implement this abatement option, where reasonably practicable,
rather than discharge the pond purge water via SETP to sea.
Strontium-90: The EA considers that BNFL’s current practice of
converting greater than 99% of strontium-90 in spent fuel into a
solid waste form and storing it to await disposal is consistent with
BPEO. The EA has, however, put forward proposals resulting from
the technetium-99 review that, if implemented, would divert
strontium-90 in future arisings of MAC to vitrification and hence
avoid its discharge to sea. A programme of work is also required,
under Schedule 9, to improve the understanding of the sources of
strontium-90 (and antimony-125) in aqueous discharges from SIXEP.
Iodine-129: The EA considers that the disposal to sea of 90% of
iodine-129 in waste streams arising from spent fuel reprocessing at
BNFL Sellafield is at present consistent with BPEO. However,
around 6% of the iodine-129 discharged to the environment from
BNFL Sellafield is presently in aerial discharges and THORP is the
main source of such discharges. The EA considers iodine–129
discharges may be further reduced by the addition of non-
radioactive iodine to the fuel dissolution process in THORP. The
Agency therefore requires BNFL to provide a programme for
implementing the addition of iodic acid to the fuel dissolution
process in THORP to abate iodine discharges or justify why it is
inappropriate to do so.
Actinides: The EA considers that BNFL’s current practice of
converting greater than 99.9% of plutonium and other actinides
present in waste streams into a solid waste form and storing them
pending final disposal is consistent with BPEO/BPM for disposing
of the radionuclides.
Report of the RPII Visit to BNFL Sellafield 27
A2.3.5 Abatement TechnologiesBNFL’s research and development programme for the abatement
of discharges was reviewed by the EA. The outcome of the review
was that BNFL is required through improvement conditions
(Schedule 9) in the authorisations, to implement further research
and development in specific areas. If the waste reduction schemes
are found to be technically feasible, BNFL is also required to
provide EA with detailed cost/benefit analyses. BNFL may then be
required to introduce measures to improve waste management
arrangements where research and development and the cost-
benefit analysis show the scheme to be effective. Currently, a
number of discharge reduction schemes are being explored.
These include:
1. Ion-exchange to abate cobalt-60 from THORP;
2. The use of iodic acid to reduce iodine-129 gaseous discharges
(this would result in a diversion of iodine-129 to liquid
discharges if implemented);
3. Minimisation of nitrogen-14 fuel impurities which would
reduce carbon-14 discharges;
4. Diversion of borehole 68 groundwater to SIXEP which would
reduce caesium-137 discharges; and
5. Development of a krypton-85 cryogenic abatement plant
(work on this will depend on plans to continue operating
THORP beyond 2016).
Report of the RPII Visit to BNFL Sellafield28
Annex 3Emergency Planning in the UK
A3.1 REPPIRThe Radiation (Emergency Preparedness and Public Information)
Regulations 2001 (REPPIR) implement in Great Britain the articles
on intervention in cases of radiological emergency in Council
Directive 96/29/Euratom (known as the Basic Safety Standards
Directive) and also certain articles of Council Directive
89/618/Euratom (known as the Public Information Directive).
REPPIR establish a framework for radiological protection through
emergency preparedness for radiation accidents with the potential
to affect members of the public, which occur either at fixed
premises or during specified transport operations. The REPPIR
public information provisions require that the public are:
• properly informed and prepared, in advance, about what to do
in the unlikely event of a radiological emergency occurring;
and
• provided with information if a radiation emergency actually
occurs.
The Health and Safety Executive has produced guidance on these
regulations (HSE, 2002).
REPPIR place legal duties on operators of premises where work
with ionising radiation is carried out, transport carriers who convey
radioactive material, local authorities and employers of people
who intervene in a radiation emergency. REPPIR do not replace
existing nuclear site license conditions but operators of licensed
sites who comply with those conditions will satisfy the equivalent
provisions in REPPIR.
A radiation emergency for the purposes of these regulations is an
event that is likely to result in any member of the public receiving
an effective dose of 5 millisievert (mSv) or more during the year
immediately following the emergency. Operators of premises and
transport carriers need to determine whether the regulations will
apply through identification of the quantities of radionuclides or
fissile material used or transported which are then compared with
threshold amounts set out in the Regulations. If the threshold
amounts are exceeded, there may be the potential for a radiation
emergency, and so the Regulations will apply.
The main responsibilities which REPPIR places on operators of
premises and transport carriers who handle or transport radioactive
substances in excess of the threshold quantities, are to:
• carry out an assessment to demonstrate that all hazards that
could cause a radiation accident have been identified and the
risks to employees and others have been evaluated;
• take all reasonably practicable steps to prevent a radiation
accident and limit the consequences of any that do occur; and
• send a report of the assessment to the NII which should
include certain specified information and show whether a
radiation emergency is reasonably foreseeable.
If the assessment concludes that a radiation emergency is
reasonably foreseeable, then operators and carriers must also:
• prepare an emergency plan;
• supply information to the local authority to enable an off-site
emergency plan to be prepared;
• review and test the emergency plan to identify its
effectiveness and ensure it remains up to date;
• implement the emergency plan if a radiation emergency
occurs, or if an event occurs that could lead to a radiation
emergency;
• notify the NII of dose levels for employees who may receive
emergency exposures; and
• provide information to members of the public about what to
do in the event of a radiation emergency.
Report of the RPII Visit to BNFL Sellafield 29
A3.2 UK Framework for Emergency Planningand Response at Civil Nuclear SitesThe Department of Trade and Industry (DTI) has a lead role in
bringing together a wide range of organisations with interests in
off-site civil nuclear emergency planning through the Nuclear
Emergency Planning Liaison Group (NEPLG). This group has
prepared guidelines based on REPPIR for arrangements for
nuclear emergency planning, which are set out in the handbook
“Civil Nuclear Emergency Planning Consolidated Guidance” (DTI,
2004). The handbook covers planning and testing of off-site
emergency preparedness and consolidates all NEPLG guidance
into a single document for general reference by planners and
practitioners concerned with emergency response at civil nuclear
sites. The key aspects of the NEPLG guidance set out in the
handbook are described below.
A3.2.1 Responsibility for Emergency Planning Responsibility for the on-site emergency plan lies with the site
operator, transport emergency plans are the responsibility of the
carrier and off-site plans are the responsibility of the local
authority. Each has the duty to ensure that plans are prepared and
are adequate and fit for purpose. All organisations with a role in
responding to a reasonably foreseeable emergency must be
involved, as appropriate, in the preparation of emergency plans.
The site operator or transport carrier is required to fully resource
all emergency plans. Licence conditions and the Radiation
(Emergency Preparedness and Public Information) Regulations
2001 require nuclear operators and local authorities to ensure on-
site and off-site emergency arrangements are in place.
A3.2.2 Role of the Local AuthorityUnder REPPIR the local authority has responsibility for
preparation, review, revision, testing and implementation of an off-
site plan for any premises in respect of which the operator’s risk
assessment shows that a radiation emergency is reasonably
foreseeable. In addition, the local authority is required to prepare
arrangements to supply information to members of the public in
the event of a radiation emergency actually occurring, regardless
of how it may occur. These arrangements are intended to cover
events such as fallen nuclear-powered satellites, transport
accidents or incidents occurring overseas that may also affect
Great Britain, as well as from premises subject to REPPIR. Local
authorities may also be involved in the dissemination of prior
information to the public from operators and carriers.
It is only since 2002, that off-site planning has been a legal
responsibility on local authorities. Prior to the 2001 Regulations,
local authority participation was on a voluntary basis. There is no
requirement under REPPIR for local authorities to prepare
emergency plans for transport.
A3.2.3 Preparation of Off-site Emergency PlansOff-site emergency plans should provide for rapid and effective
action for accidents that can be reasonably foreseen. Such plans
should be capable of being extended should less likely and more
serious accidents occur. For each licensed site the operator must
define a reference accident upon which detailed off-site
emergency planning can be based. The reference accident must be
based on the concept of the worst credible accident, which is
reasonably foreseeable at that site, taking into account all of the
facilities on the site. Underlying REPPIR is the general principle that
planning must be proportionate and must be related to the risk of
an event occurring and hence planning should not be based on
worst case scenarios, which take no account of the probability of an
event occurring. For each site, a reference accident is defined and
this is the bounding scenario for all facilities on that site.
The operator must, before commencing operations on a site,
submit to the NII for approval details of the reference accident. If
this is accepted by NII it then forms the basis for deciding the size
of the Detailed Emergency Planning Zone (DEPZ) within which
detailed plans must be prepared for implementation of each
applicable countermeasure. It is the role of the NII to determine the
size of the DEPZ for evacuation, sheltering and administration of
stable iodine, where these are applicable. The size of the DEPZ is
generally determined with reference to computer model
predictions of the distances at which the avertable dose would
exceed the National Radiological Protection Board (NRPB)
Emergency Reference Levels (ERLs) (NRPB, 1997). The NII will
then inform the local authority in whose functional area the site is
located the countermeasures for which it must prepare detailed
implementation plans for and the size of the DEPZ for each of those
countermeasures.
Report of the RPII Visit to BNFL Sellafield30
The off-site plan should bring together the emergency
arrangements of all the agencies with a role to play in the
intervention of a radiation emergency occurring at the premises.
The plan provides a framework for a multi-agency response. These
agencies would normally include the police, fire services,
ambulance service, director of public health, County Council,
Borough Council, Government Technical Adviser (GTA), NII,
NRPB, FSA, EA, water utility, DTI and DEFRA.
As part of the off-site emergency plan, the local authority must
designate an off-site facility (OSF) from which the emergency
response is managed and coordinated. Locally the OSF is known
by different titles such as local emergency centre, off-site centre or
district control centre. This is a strategic centre, where during the
emergency phase the activities of all responding organisations are
coordinated. In as far as practicable each of responding
organisations will have a representative at the OSF during the
emergency phase. This representative will normally have a support
team in place and will have access to the necessary
communication facilities.
A3.2.4 Role of PoliceThe police are tasked with chairing the coordinating group
meetings, which involve a representative drawn from all of the key
organisations with a role in the response and where decisions are
made on actions to protect the public. This group meets at the off-
site centre and is normally chaired by a local police assistant chief
constable. The police are also tasked with arranging for
information and advice to be passed on to the public via the media
briefing centre.
A3.2.5 Role of the GTACentral Government is represented at the off site centre by the
GTA, who is appointed by the Secretary of State for Trade and
Industry or the Scottish Ministers. The role of the GTA is to
provide independent and authoritative advice to the police and
other authorities handling the off-site response on the measures
they should take to deal with the emergency. It is also the role of
the GTA to provide an authoritative response to the media on
behalf of Government at local media briefings.
A3.2.6 Role of the NIIThe NII is expected to respond to a range of unplanned nuclear
events on or off nuclear sites. The NII’s regulatory role is primarily
that of witnessing, monitoring and recording the operator’s
responses to the event. On-site the operator is responsible for
taking corrective actions in an emergency. It is not part of the NII’s
responsibility to determine what action should be taken; however,
under certain circumstances the NII may offer advice. It is
considered most unlikely that the NII would contemplate the use
of enforcement powers during an emergency and if this were to
happen it would only be done under very unusual circumstances
and with the authority of the Chief Inspector.
A3.2.7 ExtendibilityGeneral non-site-specific contingency plans of local authorities
exist to deal with a range of civil emergencies from industrial
accidents to natural disasters such as flooding. In considering
whether, and to what extent, these need to be enhanced to deal
with emergencies at nuclear sites larger than the reference
accident the NEPLG guidance states that “….a balance needs to be
struck between ensuring that plans are sufficiently extensive to
cope with serious emergencies, and avoiding a waste of resources
that could occur through over-planning for most improbable
emergencies.” NEPLG guidance specifies that emergency plans
should provide the basis for dealing with radiation emergencies
that are not reasonably foreseeable through the concept of
extendibility, whereby arrangements made for the DEPZ can be
extended over a greater area.
Responsibility for determining the extent and nature of
extendibility planning around a civil nuclear site rests with the local
authority and other relevant emergency response organisations in
consultation with the site operator. NEPLG, however, recommends
that planners take account of the hypothetical extended release
scenario, as set out by the NII (HSE, 1990). This scenario requires
consideration of sheltering and administration of stable iodine
tablets out to approximately 15 km and evacuation out to 4 km.
Report of the RPII Visit to BNFL Sellafield 31
A3.2.8 ExercisesThree levels of exercise are required by the NII. Level 1
exercises involve a scenario requiring only an on-site response
and must be conducted every year at each site. Level 2
exercises test off-site response and must be conducted at each
site every 3 years. Typically there are twelve level 2 exercises
per year in the UK. Level 3 exercises are intended to test
national arrangements and each year one level 2 exercise is
designated as the annual level 3 exercise.
A3.2.9 Response to Far-field ImpactsThe framework for coordinated action to mitigate any impact from
a nuclear accident beyond 40 km from the site is the Department
for Environment, Food & Rural Affairs (DEFRA) plan for “Response
to Radiological Emergencies”. This general contingency plan was
published in 1988 to deal with the consequences for the UK of
overseas nuclear accidents. However, these measures would also
apply to far field impacts from an accident taking place in the UK.
Emergency planning guidance has also been issued by the
Department of Trade and Industry (DTI, 2004).
Report of the RPII Visit to BNFL Sellafield32
designed and produced by dcoy design - www.dcoy.ie
Cover photograph courtesy of BNFL