report of frequency control in power system with renewable resources

Upload: shahrzad474

Post on 10-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    1/28

    UNIVERSITY OF BRITISH COLUMBIA

    DEPARTMENT OF ELECTRICAL AND COMPUTER ENGINEERING

    Frequency Control in Power Systemwith Renewable Resources

    EECE 561 Final Report

    Alternative Energy Sources

    Instructor: Dr. William G. Dunford

    Author: Shahrzad Rostamirad

    7/26/2010

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    2/28

    TABLE OF CONTENTS

    TABLE OF CONTENTS....................................................................................................................... 2

    LIST OF ILLUSTRATIONS................................................................................................................... 31. INTRODUCTION ....................................................................................................................... 4

    2. BASICS OF FREQUENCY CONTROL AND PROTECTION ............................................................. 5

    2.1 FREQUENCY AND POWER BALANCE ................................................................................ 5

    2.2 FREQUENCY CONTROL MECHANISM ............................................................................... 8

    2.2.1 SPEED GOVERNOR .................................................................................................... 8

    2.2.2 AUTOMATIC GENERATION CONTROL ..................................................................... 10

    2.3 UNDERFREQUENCY PRIMARY PROTECTION .................................................................. 123. DYNAMIC FREQUENCY CONTROL .......................................................................................... 14

    3.1 DEMAND MATCHING: LOAD FOLLOWING ..................................................................... 14

    3.2 DEMAND MATCHING: FREQUENCY RESPONSE.............................................................. 17

    3.3 CURRENT STANDARDS ON RE FREQUENCY RESPONSE .................................................. 18

    3.3.1 GRID CONNECTION POLICIES .................................................................................. 18

    3.3.2 ISLANDING POLICIES ............................................................................................... 19

    4. FUTURE OF FREQUENCY PROTECTION IN POWER SYSTEM .................................................. 204.1 FRQUENCY RESPONSE CAPABILITIES OF RE ................................................................... 21

    4.2 VARIABLITY OF RE ........................................................................................................... 22

    4.3 VIRTUAL POWER PLANT ................................................................................................. 23

    5. CONCLUSION ......................................................................................................................... 26

    6. REFERENCES ........................................................................................................................... 27

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    3/28

    LIST OF ILLUSTRATIONS

    Figure 1: Equivalent circuit of a synchronous generator [2] .......................................................... 5

    Figure 2: Phasor diagram of synchronous generator [2] ................................................................ 5

    Figure 3: Change in phasor diagram when electrical real power increases ................................... 7

    Figure 4: The frequency versus power curve of a generator [2] .................................................... 8

    Figure 5: Governor speed-power characteristics of two generator units 1 and 2 [5] .................... 9

    Figure 6: Governor frequency-power characteristics for different speed references [5] ............ 10

    Figure 7: Demand curve of England and Wales [4] ...................................................................... 15

    Figure 8: Ontario demand curve at July 20th [12] ........................................................................ 16

    Figure 9: Electricity Generation of Canada in 1999 ...................................................................... 16

    Figure 10: Timescale of frequency response [4] ........................................................................... 17

    Figure 11: Anticipatory - stage 1 of Combined Power Plant operation [19] ................................ 24

    Figure 12: Fine Tuning - stage 2 of Combined Power Plant operation [19] ................................. 24

    Table 1: 59.1 Hz Load Shedding Plan as required by WECC [9] .................................................... 12

    Table 2: Abnormal frequency minimum performance [15] ......................................................... 18

    Table 3: Distributed generation and storage elements of the Combined Power Plant [19] ........ 23

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    4/28

    1. INTRODUCTIONIn North America, the current issues with developing Renewable Energy (RE) problem is not the

    methods of power generation because the technology, equipment and methods are all

    available. The problem is, in fact, mechanism of sharing the generated electrical power.

    According to Small-Scale RE Systems, Grid-Connection and Net Metering: Overview of Canadianexperience in 2003, two obstacles that prevent widespread deployment of RE are identified as:

    [1]

    1- Inconsistency in policies and standards2- Reluctance of utilities to share the lines

    While many technical and safety factors need to be considered prior to integration of a

    generator to the system such as operating voltage, frequency, substation grounding and

    insulation, this report sheds some light on one major concern which is the frequency response

    of the system after the introduction of RE resources.

    Statements, such as distributed generators free ride on the transmission grid operator or the

    regulatory body to maintain system frequency or REs endanger reliability and stability of the

    grid, are heard every day. However, the question is whether they are accurate and what can be

    done to improve the system. [2]

    The first chapter of the report, which provides technical background on the system frequency

    and its control mechanism, in fact clarifies the meaning of the above stereotypical statement.

    The second chapter introduces the demand matching concept and its timelines in which

    generators need to respond to load variations. Furthermore, it summarizes two majorstandards, one is local and the other is international, on integration requirements of RE

    generators. The third chapter illustrates the capabilities of different renewable energy

    resources to sustain system frequency control and the concept of Virtual Power Plant to further

    expand their potential limits.

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    5/28

    2. BASICS OF FREQUENCY CONTROL AND PROTECTIONIn a conventional power system, it is the synchronous generator that converts mechanical

    power of water or steam to AC electrical power. This part of the report reviews the operation of

    synchronous generator and auxiliary control such as governor as they affect frequency of the

    system. This chapter also illustrates the function of automatic generation control (AGC) toreturn the frequency of the system back to normal.

    2.1 FREQUENCY AND POWER BALANCEA synchronous generator circuit is consisted of two subsystems of rotor (or field) and stator (or

    armature) winding. Rotor circuit, a coil fed by a DC source, is attached to prime mover and

    rotates it. This rotation induces AC voltages of EA on the armature circuit, which is connected to

    the power grid via terminal voltage (VT). The equivalent circuit of synchronous generators is

    shown below. [2]

    Figure 1: Equivalent circuit of a synchronous generator [2]

    The phasor representation of the synchronous generator stator circuit is simplified in the

    following graph (assuming inductive load and lagging power factor).

    Figure 2: Phasor diagram of synchronous generator [2]

    EA

    RA

    jXA

    LF

    RF

    VF VT

    EA

    VT

    jXIA

    RAIA

    jXAIA

    a

    P

    a Q

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    6/28

    The electrical output power (both active and reactive) of a generator, which is the amount of

    power consumed by the load, determines the armature current and terminal voltage of the

    generator [2]:

    Se= Pe + jQe = 3 VT IA*

    On the other hand, mechanical power depends on the torque of the prime mover (Tm), which is

    the product of force applied by the source of energy (water or steam) times the radius of prime

    mover. Power is related to torque by T = P x .

    Since both electrical and mechanical torques try to accelerate the rotor but in the opposite

    direction, the accelerating torque (or power) of a generator could be written as the product of

    the rotor mass moment of inertia (J) and acceleration of rotor angle () [3]:

    To better understand the connection between rotor angle, synchronous frequency and

    frequency of the system, it is important to further discuss rotor angle. The above rotor angle

    (), which is the angle of the rotor with respect to an arbitrary stationary axis, could be

    represented as a relative angle () versus a reference axis which rotates at the synchronous

    speed (e.g. 60 Hz) of:

    By combining the above two formulas and considering that angular speed is the rate of change

    of the angle, the following equation is concluded:

    The above formula, swing equation, shows when electrical power increases, the frequency of

    the system will drop until the electrical power returns to its initial value or governor adjusts the

    mechanical power (this is explained in the next section) to be equal to electrical power [3]. The

    amount of change in frequency also depends on angular momentum of the generator,,,

    which is related to rotors resistance to changes to rotation [3].

    Another way of illustrating the relation between frequency and real power is to use phasor

    diagram of stator. First of all, the internal voltage of a synchronous generator (EA), which is

    induced by revolution ofrotors flux (), changes with the speed of the machine:

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    7/28

    When the speed of the rotor drops, the induced voltage, , decreases. Due to drop in

    frequency, the armature reactance (Xl) decreases. The terminal voltage is assumed to remain

    constant; the armature current increases more significantly (as well as its angle) due to increase

    in electrical output power. The following figure shows the phasor diagram of a generator after a

    sudden increase in electrical power which led to drop in frequency (rotor speed).

    Figure 3: Change in phasor diagram when electrical real power increases

    In summary, a boost in load real power demand forces the electrical output power of the

    feeding synchronous generator to increase. According to their mass moment of inertia,

    generators speed (frequency) will initially drop to meet the extra demand. However, after that,

    governor will sense the change and adjust the mechanical power to match electrical power

    which was not discussed in this part of the report [4]. In the next section the functions of speed

    governor as well as Automatic Generation Control (AGC) in maintaining the speed of the system

    are discussed.

    VT

    EA1

    EA2

    jXIA1

    jXIA2

    a

    P1

    a

    P2

    Cause Result

    Pe P1 < P2

    EA2 < EA1

    XA2 < XA1

    IA1 < IA2

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    8/28

    2.2 FREQUENCY CONTROL MECHANISMLoad of the power system is constantly changing and the primary responsibility of the electric

    grid is to fulfill the consumers demand at all time. As discussed in the previous section, if the

    mechanical power does not match electrical demand of the consumer (either higher or lower),

    the frequency starts to deviate; excess variation of frequency is harmful to customer load, thegenerators and in the severe cases it will lead to instability.

    2.2.1 SPEED GOVERNORIn order to arrest the frequency change, most synchronous generators are equipped with speed

    governor, which automatically adjusts output power of the prime mover accordingly. The speed

    sensor of governor detects the change in system frequency and sends a signal which activates a

    control mechanism to adjust the valves of prime mover that allows more or less flow (e.g.

    water and steam). For example, when a decrease in system frequency occurs due to increase in

    demand, the governor senses the change and opens the gates of prime mover to allow more

    fuel to flow. As a result, the mechanical output of the prime mover increases and governor

    stops the frequency from further decreasing. [5]

    The amount of change in frequency that will cause the governor to move the valves of prime

    mover from close to entirely open condition is called Speed droop. The following graph shows

    the frequency versus output power characteristics of a synchronous generator with governor

    control. The slope of the graph represents the speed droop of the system. [5][2]

    Figure 4: The frequency versus power curve of a generator [2]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    9/28

    Since there is usually more than one generator connected to the power system, it is important

    to understand how output power of each prime mover changes with frequency change. The

    amount of change in output of different generators depends on the speed droop (or slope of

    frequency-power curve) of that generator. The following figure shows the frequency-power

    characteristics of different generators connected to the same grid; unit 1 and 2 generators havespeed droops of 5% and 2% respectively and are operating at the equilibrium system frequency

    of 100% and power output of 50%. To examine the response of each generator, the load is

    increased by 35%; as a result of that, frequency of the system begins to drop. As frequency

    decreases, governor of each generator gradually increases the output power according to the

    frequency. At the frequency of 99.5%, the cumulative extra generation of both generators is

    equal to 35%. Unit 1 and 2 generate additional power of 10% and 25% due to their differing

    speed droop. The new frequency of the system is 99.5%. [5]

    Figure 5: Governor speed-power characteristics of two generator units 1 and 2 [5]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    10/28

    2.2.2 AUTOMATIC GENERATION CONTROLAs the preceding example and figure illustrated, the governor only stops frequency from

    changing and does not return the frequency back to normal; this is the job of Automatic

    Generation Control (AGC). The AGC (at dispatch center) or in some cases the plant control

    operator send a speed reference signal to modify the speed settings of the governor control

    mechanism to allow more flow through prime mover. In other words, the speed reference

    signals parallel-shift the droop characteristics of governor as per following figure. [5][3]

    Figure 6: Governor frequency-power characteristics for different speed references [5]

    It is important to note that for governor and AGC control to be effective in adjusting the mains

    frequency, the generators or at least some of them need to operate below their maximum

    output.

    So far, this report has illustrated the change in frequency when generation and demand of the

    system do not match; furthermore, the function of speed governor and AGS system in restoring

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    11/28

    system frequency by adjusting generation was explained. However, in todays power system,

    where generators might be operating very close to their rated power and there is little reserve

    available, it is more difficult to correct underfrequency problems. Since the generation level

    cannot be raised any further, the only way to restore the system frequency back to normal is by

    disconnecting some loads. Load shedding which is the primary protection againstunderfrequency is the subject of the next section and will be described in full details. [6]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    12/28

    2.3 UNDERFREQUENCY PRIMARY PROTECTIONIf generation and customer load do not match and governor and AGC do not manage to restore

    the balance, the frequency will continue to drop. Major decline in system frequency will

    damage generating equipment and transmissionfacilities, endanger reliability of the

    interconnected systems and lead to total system collapse. This is why power utilities hasadopted underfrequency load shedding (UFLS) programs. [7]

    Load shedding schemes are designed to disconnect enough customers to restore the balance

    and correct the frequency. Since the frequency drop is a measure of severity of system

    overload, automatic UFLS relays disconnect blocks ofnon critical load (excluding emergency

    services and Olympic venues!) as the frequency drops. [6]

    Western Electricity Coordinating Council (WECC), which coordinates and promotes reliability in

    western interconnection, requires all the involved utilities to implement 59.1 Hz Plan as a

    minimum standard. Following table illustrates 59.1 Hz plan as required by WECC. [9]

    Even though exact balance between demand and supply is not always possible, the major

    power utilities such as UK keep the frequency within the permissible range of 0.6 Hz (59.4-

    60.6 Hz) at 95% of the time. WECC requires utilities to shed at least 5.3% of load within 14

    cycles since frequency reaches 59.1 Hz. If frequency continues to decay, the next blocks of load

    should be disconnected. [4][9]

    Table 1: 59.1 Hz Load Shedding Plan as required by WECC [9]

    Load Shedding Block % of Customer Load

    Dropped

    Pickup (Hz) Tripping Time (Cycle)

    1 5.3 59.1 14

    2 5.9 58.9 14

    3 6.5 58.7 14

    4 6.7 58.5 14

    5 6.7 58.3 14

    Most standard entities including Western Electricity Coordinating Council require all pre-

    determined load shedding blocks, one or more distribution feeders, to trip before the

    frequency reaches 57 Hz. Besides major damages to turbine, this frequency level will impair the

    auxiliary equipment of the plant which will cause the output power to fall. Thus, protective

    devices will trip the generators out instantaneously. This will worsen the generation/demand

    mismatch and the system will collapse in minutes. Due to the possibility of cascading outage,

    interties are allowed to disconnect even before the frequency reaches 57 Hz and isolate the

    problematic region. [7][8]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    13/28

    Another way of regulating demand, which is similar to load shedding but more voluntarily, to

    meet generation level by power utilities is Load Curtailment. Due to prior agreement between

    the utility and (usually industrial or commercial) customer, the electricity is offered at a lower

    rate but the customer is required to disconnect all or some of its load upon the utilitys request.

    Depending on the severity of generation shortfall and their agreement, load curtailment takesdifferent forms; for example, the amount of notification time and load might be different. In

    some cases, a remotely controlled switch at the connection point of customer to grid might be

    installed for faster response and more control. [10]

    This chapter illustrated the problem of abnormal frequency in bulk electric system, the

    importance of maintaining the frequency within the normal range via speed governor,

    automatic generation control, load shedding and load curtailment schemes. Next chapter

    discusses the dynamic frequency control mechanism and the related standards and policies

    under which renewable energy resources can integrate with the grid.

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    14/28

    3. DYNAMIC FREQUENCY CONTROLAs discussed in previous section, power utilities try to design and operate the power system

    such that its frequency remains within narrow range of 59.4 Hz to 60.6 Hz. This is because,

    beside the reliability risk that significant drop in frequency impose on the grid (cascading

    outage for example), the abnormal frequency has different negative impacts on customersload and electrical power equipments.

    Because speed of motor determines to the system frequency, it must remain constant for

    customers motors that drive a device for example pump of washing machine and conveyor of

    assembly line. Change in System frequency also affects electronic devices that use mains

    frequency to time different processes. Similar to auxiliary equipment of generation plant,

    equipment of electric power grid is not immune from damages caused by abnormal frequency.

    Transformers for examples may be overloaded due to significant drifts of frequency. [4]

    To ensure the system frequency within the normal range, the study of system operation (ordemand matching) was traditionally divided into two timescales. One timescale, which is called

    frequency response, captures the changes over seconds to minute. The second timescale is

    for variations from ten minutes to hours and is called load following. This is the responsibility

    of the operators of the system to ensure there is enough generating capacity to meet the

    varying demand via generation scheduling and reserve during load following and frequency

    response timescales respectively. [4]

    3.1 DEMAND MATCHING: LOAD FOLLOWINGThis section describes the load following timescale. According to the Energy Dictionary, the

    definition of load following is the practice of power utilities in communicating the demand

    requirements with generation facilities to produce neither too little nor too much power and

    meet the moment by moment demand of the system.

    Over the years, utilities have developed accurate load forecasting methods which modify

    demand patterns of previous years, months and days based on factors such as weather

    condition. The demand variations are also watched in real time to find the trend for the

    following hours and minutes to come. Accordingly to the expected demand, economic and

    technical considerations, operators schedule different generators to match hour-to-hour and

    daily variations of load. [4]

    Varieties of generators both conventional and renewable have different characteristics which,

    in fact, define their functions in the power system. One of these characteristics based on which

    power utilities put the generators to work is their flexibility to change their output power; this

    is called load following capability. Although customer demand changes throughout the day,

    there is a portion of this load that is always present and is referred to as the base load. Thus

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    15/28

    inflexible generators, which are not capable of load following, operate at their maximum

    output power to supply the base load. The more flexible ones will meet the changing demand

    especially during peak hours. These two types of generators are called base load power plant

    and loadfollowing power plant. [4][11]

    In order to represent the contribution of different generators to meet the aggregate load, the

    demand curve (consumers demand over a period of time) is divided into multiple layers. The

    following figure demonstrates the demand of curve of England and Wales power system and

    the share of various generators in meeting the demand. [4]

    Figure 7: Demand curve of England and Wales [4]

    Inflexible generators of nuclear and natural gas which take multiple hours to reach full output

    from cold are placed at the bottom layers of the demand curve to supply base load. Coal

    generators, however, are more flexible and can change their output power from zero to full

    capacity in minutes; coal generation along with hydroelectric and renewable is put at the top

    layers as the load following power plants.

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    16/28

    Figure 8: Ontario demand curve at July 20th [12]

    Just for the comparison, a typical demand curve of Ontario (preceding figure) as well as

    distribution of electricity resources in Canada (following figure) are given in this section. Similar

    to the UK demand curve, the Ontario daily demand curve can be layered based on the pie

    diagram of Canada electricity generation. In that case, the demand curve for Canada would be

    very similar with a difference that hydroelectric will be at the top supplying most of demand,

    close to 60%. This allows the grid to take on more variations in demand since hydroelectric is

    the most flexible among the conventional generations. On the other hand, fossil Fuel and

    nuclear plants operate as the base load generating plants based on economical factors. [4][13]

    Figure 9: Electricity Generation of Canada in 1999

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    17/28

    3.2 DEMAND MATCHING: FREQUENCY RESPONSEIn addition to load following timescale, demand could change suddenly and substantially and

    the power grid must be able to response fairly quickly in matters of seconds to minute. This

    response which is referred to as the frequency response divides into two sections: 1.

    Continuous service; 2. Occasional service.

    During continuous service timescale, modest frequency change, inertia and governor of

    generators maintain the frequency. Inertia, which is based on Newtons First Law of Motion, is

    the tendency of an object in motion (e.g. rotating turbine) to resist acceleration.

    The occasional service or reserve timescale, which is for incidents of significant frequency

    excursions, is divided to primary and secondary subcategories. Primary reserve requires very

    fast generators that can increase their output within 10 seconds from incident and maintain

    that for 20 seconds. For secondary reserve, generators are not as fast and response after 30

    seconds but they must maintain their response for longer time of 30 minutes. Occasionalservice is performed by AGC system. [4]

    Figure 10: Timescale of frequency response [4]

    Depending on the characteristics of different generators, they are planned to participate in

    frequency response actions. By assigning different droop ratio to each generator, operatorsdictate the contribution of each generator. Traditionally, partly loaded hydro, pumped storage

    and flexible coal generator were used for fast response. Next chapter will discuss the

    capabilities of renewable energy (RE) resources to participate in load following and frequency

    response actions. But first, in the next section, the policies and local standards that these new

    electricity resources need to follow to participate in demand matching function. [4][13]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    18/28

    3.3 CURRENT STANDARDS ON RE FREQUENCY RESPONSEWhile the previous section discussed the demand matching process from frequency response

    to load following, this section summarizes some of the standards and policies about frequency

    control for transmission and distribution connected generators.

    3.3.1 GRID CONNECTION POLICIESPolicy of BC Hydro, which also complies with IEEE 1547 standard on Distributed Generation

    Interconnection, regarding speed governor is that all generator rated above 1.0 MVA need a

    speed governor or have a similar performance to hydraulic and steam turbine-generator units.

    Generators smaller than 1 MVA are discounted from the above criterion because they have

    little impact on system operation. These governors must operate at droop of 5% or in the case

    of smaller generators (< 69kV), they should be able to operate at isochronous as well. For

    power generators (PG) to regulate system frequency and improve stability of the grid, BC Hydro

    requires the unstrained operation for all speed governors. [15][16]

    As described in previous chapter, droop of 5% means 5% drop in frequency is necessary to

    move turbine control valve from fully close to fully open. In Isochronous, which is zero droop,

    governor keeps the frequency constant regardless of power required by load (as long as it is

    within generation capabilities of the generator). Isochronous setting is desirable for islanding

    situation but not grid connected condition. That is because small fluctuations in system

    frequency will cause major changes in output power of that generator. [5]

    Table 2: Abnormal frequency minimum performance [15]

    Underfrequency Limit (Hz) Overfrequency Limit (Hz) Minimum Time

    60.0-59.5 60.0-60.5 Continuous

    59.4-58.5 60.6-61.5 3 minutes

    58.4-57.9 61.6-61.7 30 seconds

    57.8-57.4 7.5 seconds

    57.3-56.9 45 cycles

    56.8-56.5 7.2 cycles

    Less than 56.4 Greater than 61.7 Instantaneous

    Power system disturbances cause frequency oscillations which may be temporary and damp

    out after a short time. Power generators (PG) (and customer loads) are protected againstextended off nominal frequencies via under/over-frequency relays. In power generators that

    are connected to the grid through power electronic convertors, the protection function of their

    internal microprocessor can be programmed instead of external relays. However, they and

    abnormal frequency relays need to be set up such that they do not trip the generator

    prematurely before upstream protection or load shedding relays. As discussed previously,

    sudden changes in feeder loading may lead to voltage phase-angle swings which could trip PGs

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    19/28

    if their abnormal frequency relays do not have sufficient time delays. For extensive off-nominal

    frequency situation, these power generators are not allowed to trip out earlier than specified in

    the preceding. [15][16][17]

    In addition to continuous frequency response, large generation plant (> 69 kV) may be required

    to connect to automatic generation control (AGC) system of the dispatching centre to

    participate in wholesale transmission services. Due to local consideration even smaller

    generators may be mandated to be dispatchable. [16]

    3.3.2 ISLANDING POLICIESFollowing operation of a circuit breaker, power system divides into groups of isolated loads and

    generators; this situation is called islanding and generators that continue supplying the local

    load are called islanded. Without getting into details about different methods of detecting

    islanding situation, one of the major methods is by measuring frequency deviation; this method

    relies on the high probability of unbalance between generation and demand of island. IEEE1547 standard claims that problem with unplanned/unintentional islanding is that it expose line

    crew to live lines that workers may believe to be de-energized or it will delay the restoration

    time as the crew trying to ensure islanding of the generator is not a problem. This seems to be a

    minor issue since line crew deal with this problems everyday and communication between

    operators of the distributed generation plant and the control centre of the grid (or accurate

    documentation about location of isolating breakers) should solve the issue. However BC hydro

    has other concerns such as possibility ofdamage to customers load due to abnormal

    frequency and voltage, voltage flicker, increased harmonic generation or miscoordination of

    protection devices ifa fault happens during islanding. Thus BC Hydro requires the powergenerators to automatically disconnect from system when islanding occurs. This is because

    after an islanding condition, load and generation become unbalanced; in the case of induction

    generator for example, overvoltage and/or overfrequency may occur due to resonance

    between generator inductance and self-excitation capacitor or sudden drop in load which leads

    to decrease in slip. However, they allow the generators to continue their operation if their

    control (e.g. governor) managed to establish a new equilibrium (balanced load situation) in

    the island. For more details about considerations of the utility and generation plant in

    operation in islanding situation, please refer to reference 15 about BC Hydro Distribution Power

    Generator Islanding Guidelines. [15][16][17][18]

    In summary, power generators, including renewable energy resources, are allowed by BC Hydro

    to operate in islanding condition as long as sufficient coordination and analysis with the utility

    has been done and the islanded generator managed to maintain frequency and voltage within

    the limit during the islanding situation.

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    20/28

    4. FUTURE OF FREQUENCY PROTECTION IN POWER SYSTEMTo fulfill the essential objective of the electric system in meeting the growing electricity

    demand while respecting international agreements on minimizing environmental impacts of

    electricity generation, the form of electric system is changing from centralized generation

    sourced from fossil and nuclear fuel to more distributed generations from Renewable Energy(RE) resources. The portion of electrical power generated by renewable energy resources is

    identified as penetration: [4]

    [Instantaneous or average] penetration =

    The current average penetration of RE resources in the World is 11%. This number, however, is

    guaranteed to incline due to increasing capacity of renewable power; for example, the World

    capacity of wind power has been growing at 30% over the last ten years. With all the

    international pressure for replacement of fossil fuel based generation with renewable, many

    believes that by the end of this century, the main supplier of electricity will be RE resources.

    With increasing penetration ratio of renewable energy resources, many are anxious to know

    the impact of these newly integrated resources on the power grid and on its main responsibility

    of the continuous power balance. [4]

    As discussed in previous chapter, in order for a generator to participate in dynamic frequency

    control it must be flexible and predictable. For frequency response period, the generator must

    be able to response within few seconds from when demand fluctuates. For load following

    timeline though, the generator needs to maintain its output for up to 20 minutes which means

    its source of energy needs to be predictable. As a result, this chapter discusses the frequencyresponse capability and variability of different RE resources.

    Demand matching capabilities of RE resources could potentially play an important role in parts

    of the World with dominating inflexible generation units and even in Canada, as the World

    leader of hydroelectricity with fast frequency control. For example, during low demand days of

    year when very few conventional units are supplying the grid to provide adequate levels of

    response and reserve, the connected RE resources such as wind and solar might be highly

    available to supply variable load. [4][13]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    21/28

    4.1 FRQUENCY RESPONSE CAPABILITIES OF REEarly technologies of wind power were based on simple fixed speed induction generators with

    little control over dynamic performance. Similar to conventional generation plants, the kinetic

    energy stored in rotor inertia and turbine will assist in maintaining mains frequency by slowing

    down as long as it remains within their operating limits. [4][14]

    Wind power technologies have progressed significantly, over the recent years, because of the

    development of variable speed wind turbines with significant control technologies. Although

    these wind turbines are usually programmed to maximize their power production due to

    economical consideration, they are able to provide frequency response via output power

    control mechanism. Besides primary and secondary service timelines, the variable speed wind

    technologies can contribute to continuous service (high frequency response) by providing

    greater inertial energy than conventional plant of the same size. [4][14]

    Due to low energy density, energy consumption and cost of transportations of biomass, biofuelgenerating plants are relatively very small and low efficient. Although biofuel plants are

    theoretically capable of continuous and occasional frequency response, they are practically too

    inefficient and small that are almost always operated at their full capacity to supply base load.

    [4]

    Small and medium sized hydrogenation plants without major storage capacity are considered

    intermittent. Due to relatively high opportunity cost associated with spilling water, governor

    control equipment and real time monitoring, they currently do not participate in frequency

    regulation services. However, small or medium hydro scheme based on synchronous generator

    are perfectly capable of continuous and occasional frequency response as long as economical

    constraints allow. [14]

    Although large photovoltaic panels do not have any mechanical inertia, due to their electronic

    interface to grids, they can response very fast. Because of their relatively high efficiency and

    predictability, they are likely to be partly loaded for continuous and occasional frequency

    response. [4]

    Although large tidal scheme have many advantages such as high-predictability, due to their high

    capital cost there are not commercialized yet. Besides economical constraints, tidal power is

    available in few places in the World for only few hours a day. Thus, partly loaded tidal schemes

    to participate in frequency control are unlikely. [4]

    In summary, currently all RE power plants are fully load due to high initial cost of these

    technologies, many of them are expected to be partly-loaded and take part in frequency

    regulation in future.

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    22/28

    4.2 VARIABLITY OF REAnother argument against usage of renewables for load following purposes is their variability.

    Although variation level of a renewable resource is location specific and needs to be studied

    individually, this section will try to shed some light on this problem by providing some general

    information about RE variation. [4]

    Small hydroelectric unit without storage varies very little in minute by minute basis but

    substantially over hourly, daily and time of the year due to sudden rainfall. Although minute by

    minute changes might affect the capability of a small hydroelectric in load following (not so

    much on fast frequency response), having multiple small hydroelectric units which are

    geographically dispersed will smooth out the changes. [4]

    Since radiation and temperature impacts the output of photovoltaic panels, their output vary

    hourly and even minute by minute due to clouds. However, similar to small hydroelectric

    change in PV systems is rather slow and their geographical spread will alleviate the short-rangechanges. [4]

    Speed of Wind is continuously changing annually, seasonally, with passing weather (synoptic),

    daily and second by second (turbulence) among which synoptic has the most effect on speed

    variation. However, its variation which takes multiple days is slow enough for the operators of

    power system. Although turbulences can have significant impact on wind speed, their

    aggregation decreases the problem. [4]

    Although wind over the surface of water is the source of wave power and its variation is very

    similar to wind power, the change in electrical output of wave power is slow due to itsconversion process. Output of biomass, which is a storable fuel, does not vary over time. Both

    biomass and wave power (to some extend) are considered predictable. [4]

    With the advanced technologies in weather forecast, the output power of all the renewable

    energy resources is predictable to varying degrees. As discussed earlier aggregation of many

    renewable energy units (of the same type or different types) will help smooth their variation

    and their integration into power system. Thus, with high penetration of renewable resources in

    future, they will contribute to frequency control services of the grid more.

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    23/28

    4.3 VIRTUAL POWER PLANTDue to concerns over variability and unpredictability of renewable energy based generators,

    they are penalized in electricity wholesale markets for example by reducing their market value.

    In response to this market distrust, the concept of Virtual Power Plant was introduced

    recently by the Institute for Solar Energy Supply Technology of the University of Kassel inGermany. [4]

    The pioneer project on Virtual Power Plant (VPP), which is a cluster of distributed generators

    operated together by a central control mechanism, is the Combined Power Plant which is

    carried out by the University of Kassel with cooperation of many companies in renewable

    energy sector. The objective of this project was not only to illustrate the reliability of RE

    generation but to prove that full electricity supply from renewable sources is possible. [19]

    With constantly varying RE generation and demand, it seems very difficult to maintain the

    reliability of a system that is fully supplied by renewable resources. However, as discussed inprevious section, the combination of renewable energy sources balances out their fluctuations.

    The Combined Power Plant, which links and runs 36 RE resources around Germany (table 3), is

    as reliable as a conventional large-scale power station. [20]

    Table 3: Distributed generation and storage elements of the Combined Power Plant [19]

    RE Type Numbers Total Capacity

    Wind Turbines 11 12.6 MW

    Solar Power Plants 20 5.5 MW

    Biogas (CHP) units 4 4.0 MW

    Pumped Storage 1 1.06 MW for 80 Hours

    The central control unit operates in two steps of anticipatory control and fine tuning. In

    anticipatory step, the central control is provided by load profile or demand forecast as well as

    forecast of wind strength and hours of sun. According to this information, central control

    decides how much wind turbines and solar modules can generate at each instant and its surplus

    and shortage against demand. Then, control unit plans how to spread and balance out these

    shortages and surpluses using biogas CHP and pump storage (figure 11). [20]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    24/28

    Figure 11: Anticipatory - stage 1 of Combined Power Plant operation [19]

    During the real time operation, despite accurate weather forecast, there are small deviations inactual generation and demand which will be handled by fine tuning mechanism. As following

    figure illustrates, the central control unit of Combined Power Plant constantly receives

    information on output of each RE generation and storage plants and commands an increase in

    their output as necessary. [20]

    Figure 12: Fine Tuning - stage 2 of Combined Power Plant operation [19]

    Virtual Power Plant works on the principle that aggregate of the small RE generation plants

    perform more reliably such that it makes a power system with 100% perturbation of renewable

    energy sources possible.

    However, the concept of Virtual Power Plant (VPP) is not adopted by power utilities and still in

    research phase. One of the most-talked-about issues with VPP is that depending on the

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    25/28

    circumstances of the geographical location and its local resources, the generators that take part

    in the cluster may have to be geographically dispersed; this jeopardizes the existing

    requirements for local control of power and voltage. This topic is in fact the topic of many

    ongoing research projects. [4]

    One of the components of VPP is the energy storage element, which refills and drains during

    low and high demand periods. Although pumped hydro and biogas, which are rather

    conventional storage technologies, was used in the Combined Power Plant project, electrical

    storage takes many different forms: large hydro, compressed air, hydrogen, batteries, flywheel,

    super capacitors and heat/cold store. However, economical feasibility of storage devices is

    doubtful due to high capital cost, high operation and maintenance costs and low efficiency of

    these devices. Inexpensive efficient storage devices are also the topic of ongoing research

    projects. [4]

    Other major VPP projects include FENIX, Flexible Electricity Network to Integrate the eXpectedenergy revolution, FortZED and Xcel Energys SmartGridCity. FENIX is European collaborative

    project that focuses on integrating wholesale electricity generation from wind farms and co-

    generation. FortZED and Xcel Energy s SmartGridCity are taking place in Colorado and dispatch

    the aggregate of RE resources as one big generation plant and optimize the system via demand

    management techniques. [22]

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    26/28

    5. CONCLUSIONCurrent issues preventing the full implementation of Renewable Energy (RE) resources are not

    their technologies but concerns over their integration with existing power grid. Because the

    main responsibilities of the electrical power grid is to balance demand and supply of electricity

    and thus preservation of the mains frequency, the objective of this report was the frequencyregulation and RE resources.

    The first chapter of the report explained how power imbalance effects speed of generators and

    system frequency. Higher generation than demand increases the frequency and vice versa. It

    also described the function of speed governor, which is stopping frequency variations,

    Automatic Generation Control, which is restoring frequency back to normal, and load shedding

    mechanism as the primary protection against underfrequency.

    The second chapter re-emphasised the importance of maintaining frequency via demand

    matching. It also divided load matching mechanism to two timelines of frequency responsewithin seconds to ten minutes and load following within ten minutes to hours of the incident.

    Based on the flexibility and availability of generators, they are assigned to contribute to the

    actions of one or both these timelines. At the end, IEEE 1547 and BC Hydro standards for

    frequency controls of integrated generators in grid connected and islanded situations were

    discussed.

    The third chapter explained the penetration of RE resources is growing such that at the end of

    the century they might become the dominant source of electricity. All RE resources are

    technically capable of fast frequency response but some vary and are unpredictable. Their

    aggregate smooth out fluctuations and is used with the help of central control in a so called

    Virtual Power Plant (VPP). VPP is not without problems and is still in research phase.

    To sustain and fulfill the main responsibility of electric power system in balancing demand and

    generation, renewable energy resources are green and competent candidate. By resolving

    problems such as unpredictability and continuous variation, the power grid will be fed only

    from renewable energy resources.

  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    27/28

    6. REFERENCES

    1. S. Henderson, J. Bell, Small-scale Renewable Energy Systems, Grid-connection and NetMetering: An Overview of the Canadian Experience in 2003, Abri Sustainable Design and

    Consulting

    2. S.J. Chapman, Electric Machinery Fundamentals, 4th Ed., McGraw-Hill, 20053. J. Grainger and W.D. Stevenson Jr., Power systems analysis, McGraw-Hill International

    Editions, 1994

    4. L. Freris and D. Infield, Renewable Energy in Power Systems, John Wiley & Sons, 20085. H. D. Vu and J. C. Agee, WECC Tutorial on Speed Governors, WECC Control Work Group,

    February 1998

    http://www.wecc.biz/library/WECC%20Documents/Documents%20for%20Generators/

    Governor%20Tutorial.pdf

    6. D. Reimert, Protective Relaying for Power Generation Systems, CRC Press, 20067. Western Electricity Coordinating Council: Reliability Criteria, 2005

    http://www.wecc.biz/Standards/WECC%20Criteria/WECC%20Reliability%20Criteria.pdf

    8. P. Kundur, Power System Stability and Control, McGraw-Hill, 19949. S. Mavis, et al., WECC Coordinated Off-Nominal Frequency Load Shedding and

    Restoration Requirements, 1997

    http://www.usea.org/Programs/EUPP/Jordan_Transmission/third_nepco_program_apri

    l_2010/documents/WECC_ONF_Report_July_2005.pdf

    10.Application Note #3: Load Curtailment/Demand Responsehttp://obvius.com/pdfs/AN_Demand_response.pdf

    11.Load Following Power Plant,http://en.wikipedia.org/wiki/Load_following_power_plant12.Ontario Demand and Market Prices,

    http://www.ieso.ca/imoweb/siteShared/demand_price.asp

    13.S. Pneumaticos, G. Mercier, Renewable Energy in Canada Status Report 200214.Ancillary Service Provision from Distributed Generation, DTI report, UK, 2004

    http://www.ensg.gov.uk/assets/dgcg00030.pdf

    http://www.wecc.biz/library/WECC%20Documents/Documents%20for%20Generators/Governor%20Tutorial.pdfhttp://www.wecc.biz/library/WECC%20Documents/Documents%20for%20Generators/Governor%20Tutorial.pdfhttp://www.wecc.biz/library/WECC%20Documents/Documents%20for%20Generators/Governor%20Tutorial.pdfhttp://www.wecc.biz/Standards/WECC%20Criteria/WECC%20Reliability%20Criteria.pdfhttp://www.wecc.biz/Standards/WECC%20Criteria/WECC%20Reliability%20Criteria.pdfhttp://www.usea.org/Programs/EUPP/Jordan_Transmission/third_nepco_program_april_2010/documents/WECC_ONF_Report_July_2005.pdfhttp://www.usea.org/Programs/EUPP/Jordan_Transmission/third_nepco_program_april_2010/documents/WECC_ONF_Report_July_2005.pdfhttp://www.usea.org/Programs/EUPP/Jordan_Transmission/third_nepco_program_april_2010/documents/WECC_ONF_Report_July_2005.pdfhttp://obvius.com/pdfs/AN_Demand_response.pdfhttp://obvius.com/pdfs/AN_Demand_response.pdfhttp://en.wikipedia.org/wiki/Load_following_power_planthttp://en.wikipedia.org/wiki/Load_following_power_planthttp://en.wikipedia.org/wiki/Load_following_power_planthttp://www.ieso.ca/imoweb/siteShared/demand_price.asphttp://www.ieso.ca/imoweb/siteShared/demand_price.asphttp://www.ensg.gov.uk/assets/dgcg00030.pdfhttp://www.ensg.gov.uk/assets/dgcg00030.pdfhttp://www.ensg.gov.uk/assets/dgcg00030.pdfhttp://www.ieso.ca/imoweb/siteShared/demand_price.asphttp://en.wikipedia.org/wiki/Load_following_power_planthttp://obvius.com/pdfs/AN_Demand_response.pdfhttp://www.usea.org/Programs/EUPP/Jordan_Transmission/third_nepco_program_april_2010/documents/WECC_ONF_Report_July_2005.pdfhttp://www.usea.org/Programs/EUPP/Jordan_Transmission/third_nepco_program_april_2010/documents/WECC_ONF_Report_July_2005.pdfhttp://www.wecc.biz/Standards/WECC%20Criteria/WECC%20Reliability%20Criteria.pdfhttp://www.wecc.biz/library/WECC%20Documents/Documents%20for%20Generators/Governor%20Tutorial.pdfhttp://www.wecc.biz/library/WECC%20Documents/Documents%20for%20Generators/Governor%20Tutorial.pdf
  • 8/8/2019 Report of Frequency Control in Power System With Renewable Resources

    28/28

    15.BC Hydro 35 kV and Below Interconnection Requirements for Power Generators, 2010http://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution

    _interconnection_requirements.Par.0001.File.DIR_May_2010.pdf

    16.BCTC 69 kV to 500 kV Interconnection Requirements for Power Generators, 2006http://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-

    6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec0

    6.pdf

    17.Application Guide for Distributed Generation Interconnection: 2006 Update, The NRECAGuide to IEEE 1547, 2006

    http://www.nreca.org/Documents/PublicPolicy/DGApplicationGuide-Final.pdf

    18.BC Hydro DISTRIBUTION POWER GENERATOR ISLANDING GUIDELINES, 2006http://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution

    _power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_genera

    tion_islanding_june_2006.pdf

    19. The Combined Power Plant: The First Stage in Providing 100 % Power from RenewableEnergy, 2008http://www.solarserver.com/solarmagazin/anlagejanuar2008_e.html

    20.Deutschland Hat Unendlich Viel Energie, Windenergie Wasserkraft SonnenenergieBioenergie Erdwarmehttp://www.kombikraftwerk.de/fileadmin/downloads/Background_Information_Combi

    ned_power_plant.pdf

    21.R. Belhomme, et. al., Case Studies on the Integration of Renewable Energy Sources intoPower System,http://www.iset.uni-kassel.de/abt/FB-

    I/publication/case_studies_nov2005.pdf

    22.P. Asmus, Working Definition of a Virtual Power Plant, 2010http://www.pikeresearch.com/blog/what-is-the-working-definition-of-a-virtual-power-plant

    http://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_interconnection_requirements.Par.0001.File.DIR_May_2010.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_interconnection_requirements.Par.0001.File.DIR_May_2010.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_interconnection_requirements.Par.0001.File.DIR_May_2010.pdfhttp://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec06.pdfhttp://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec06.pdfhttp://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec06.pdfhttp://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec06.pdfhttp://www.nreca.org/Documents/PublicPolicy/DGApplicationGuide-Final.pdfhttp://www.nreca.org/Documents/PublicPolicy/DGApplicationGuide-Final.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_generation_islanding_june_2006.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_generation_islanding_june_2006.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_generation_islanding_june_2006.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_generation_islanding_june_2006.pdfhttp://www.solarserver.com/solarmagazin/anlagejanuar2008_e.htmlhttp://www.solarserver.com/solarmagazin/anlagejanuar2008_e.htmlhttp://www.solarserver.com/solarmagazin/anlagejanuar2008_e.htmlhttp://www.kombikraftwerk.de/fileadmin/downloads/Background_Information_Combined_power_plant.pdfhttp://www.kombikraftwerk.de/fileadmin/downloads/Background_Information_Combined_power_plant.pdfhttp://www.kombikraftwerk.de/fileadmin/downloads/Background_Information_Combined_power_plant.pdfhttp://www.iset.uni-kassel.de/abt/FB-I/publication/case_studies_nov2005.pdfhttp://www.iset.uni-kassel.de/abt/FB-I/publication/case_studies_nov2005.pdfhttp://www.iset.uni-kassel.de/abt/FB-I/publication/case_studies_nov2005.pdfhttp://www.iset.uni-kassel.de/abt/FB-I/publication/case_studies_nov2005.pdfhttp://www.pikeresearch.com/blog/what-is-the-working-definition-of-a-virtual-power-planthttp://www.pikeresearch.com/blog/what-is-the-working-definition-of-a-virtual-power-planthttp://www.pikeresearch.com/blog/what-is-the-working-definition-of-a-virtual-power-planthttp://www.pikeresearch.com/blog/what-is-the-working-definition-of-a-virtual-power-planthttp://www.pikeresearch.com/blog/what-is-the-working-definition-of-a-virtual-power-planthttp://www.iset.uni-kassel.de/abt/FB-I/publication/case_studies_nov2005.pdfhttp://www.iset.uni-kassel.de/abt/FB-I/publication/case_studies_nov2005.pdfhttp://www.kombikraftwerk.de/fileadmin/downloads/Background_Information_Combined_power_plant.pdfhttp://www.kombikraftwerk.de/fileadmin/downloads/Background_Information_Combined_power_plant.pdfhttp://www.solarserver.com/solarmagazin/anlagejanuar2008_e.htmlhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_generation_islanding_june_2006.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_generation_islanding_june_2006.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_power_generation_islanding_june_2006.Par.0001.File.info_distribution_power_generation_islanding_june_2006.pdfhttp://www.nreca.org/Documents/PublicPolicy/DGApplicationGuide-Final.pdfhttp://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec06.pdfhttp://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec06.pdfhttp://transmission.bchydro.com/NR/rdonlyres/8FA9A050-8973-4E78-821F-6B6524189D79/0/69kVto500kVInterconnectionRequirementsforPowerGeneratorsDec06.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_interconnection_requirements.Par.0001.File.DIR_May_2010.pdfhttp://www.bchydro.com/etc/medialib/internet/documents/info/pdf/info_distribution_interconnection_requirements.Par.0001.File.DIR_May_2010.pdf