report lekhgaon goat 31aug14

2
Page/of 1/1 Janpriya Bahu-Udesya Sahakari Sangstha (JBUSS), located in Lekhgaon, Surkhet is approximately twenty km from Birendranagar is an applicant to the W2 VCF. The submitted business plan lacked consensus in the construction and renovation of the goat shed. JBUSS had initially submitted their BP on the renovation of the goat shed. At a later stage they had requested on the re-submission of their BP with construction of the goat shed instead of its renovation. On the 31 st August’14, a PMU team comprising of Harimadan Adhikari (AEC), and Abhijit Bhattacharya (SNV) visited Lekhgaon for a situation analysis for the appropriateness to the HVAP grant support on the construction or/and renovation of the goat shed to the individual HHs. Inspection of the goat shed was randomly done among seven HH as mentioned below; 1. Harikala Pulami 2. Gopisara Pulami 3. Minu Sijali 4. Lalisara Reshmi (stone wall) 5. Kaghisara reshmi 6. Tulsi Pulami (stone wall) 7. Dil Maya Shernet The following observations were made; The existing goat sheds was well constructed with thatched roof ventilation with a good plinth height supported with wooden planks walls and bamboo floor. Two shed were constructed with stones and mud. Most sheds had an extended balcony to stall feed the goats. The goats were a cross breed of khari and jamuna pari and productive in goat rearing The existing sheds were insufficient to accommodate incremental growth of the goat herd size. Bamboo and labour is commonly available but wood is scare. Sufficient availability of fodder and forage on individually owned land. On the discussion and further clarity on the consequences of misappropriation and incompletion of the shed in terms of HVAP parameters the following member volunteered construct new shed to comply by the HVAP norms and conditions; 1. Dil Maya Shernet 2. Ramaba Devi Pulami 3. Ramaba Kumari Pulami 4. Damba Kumari Shernet 5. Ranjana Pulami 6. Lalisara Gaha 7. Lalisara Reshmi 8. Bipana Gaha 9. Joshuda Pulami 10. Uma Pulami 11. Kalpana Pulami 12. Mani Kumari Gaha 13. Chandra Sijalii 14. Laxmi Shernet 15. Kaghisara reshmi 16. Minu Sijali 17. Parbati Gaha Recommendations In consideration to the field observation and the HVAP goat VC intervention strategy the following recommendations can be considered. New construction to be provided to the volunteered and selected members only and renovation to the other members New construction to accommodate both the existing and incremental goats. HVAP Support can be provided on the materials not easily available like skilled labour, wood & stones for walls, roof materials, materials for concrete ground floor slopes and building materials like nails, latches etc. Bamboo and labour is easily available and can be used at very low cost among the community. Their BP shall reflects the total goat herd size of 10-15 goats at the end of third year for each HH HVAP support of Nrs 30,000/- and Nrs. 15,000/- on new construction and renovation respectively of goat shed can be provided to each HH based on the above can be considered. Release of grant funds can be controlled by the periodical monitoring and review. Field Verification – Goat VC: Lekhgaon, Surkhet Janpriya Bahu-Udesya Sahakari Sangstha (JBUSS), 31 th August 2014

Upload: abhijit-bhattacharya

Post on 10-Dec-2015

213 views

Category:

Documents


1 download

DESCRIPTION

Goat Farming in Surkhet

TRANSCRIPT

Page 1: Report Lekhgaon Goat 31Aug14

Page/of 1/1

Janpriya Bahu-Udesya Sahakari Sangstha (JBUSS), located in Lekhgaon,

Surkhet is approximately twenty km from Birendranagar is an applicant to

the W2 VCF. The submitted business plan lacked consensus in the construction and renovation of

the goat shed. JBUSS had initially submitted their BP on the renovation of the goat shed. At a later

stage they had requested on the re-submission of their BP with construction of the goat shed

instead of its renovation. On the 31st August’14, a PMU team comprising of Harimadan Adhikari (AEC),

and Abhijit Bhattacharya (SNV) visited Lekhgaon for a situation analysis for the appropriateness to the

HVAP grant support on the construction or/and renovation of the goat shed to the individual HHs.

Inspection of the goat shed was randomly done among seven HH as mentioned below;

1. Harikala Pulami

2. Gopisara Pulami

3. Minu Sijali

4. Lalisara Reshmi (stone wall)

5. Kaghisara reshmi

6. Tulsi Pulami (stone wall)

7. Dil Maya Shernet

The following observations were made;

The existing goat sheds was well constructed with thatched roof ventilation with a good

plinth height supported with wooden planks walls and bamboo floor. Two shed were

constructed with stones and mud.

Most sheds had an extended balcony to stall feed the goats.

The goats were a cross breed of khari and jamuna pari and productive in goat rearing

The existing sheds were insufficient to accommodate incremental growth of the goat herd

size.

Bamboo and labour is commonly available but wood is scare.

Sufficient availability of fodder and forage on individually owned land.

On the discussion and further clarity on the consequences of misappropriation and

incompletion of the shed in terms of HVAP parameters the following member volunteered

construct new shed to comply by the HVAP norms and conditions;

1. Dil Maya Shernet

2. Ramaba Devi Pulami

3. Ramaba Kumari Pulami

4. Damba Kumari Shernet

5. Ranjana Pulami

6. Lalisara Gaha

7. Lalisara Reshmi

8. Bipana Gaha

9. Joshuda Pulami

10. Uma Pulami

11. Kalpana Pulami

12. Mani Kumari Gaha

13. Chandra Sijalii

14. Laxmi Shernet

15. Kaghisara reshmi

16. Minu Sijali

17. Parbati Gaha

Recommendations

In consideration to the field observation and the HVAP goat VC intervention strategy the following

recommendations can be considered.

New construction to be provided to the volunteered and selected members only and renovation

to the other members

New construction to accommodate both the existing and incremental goats.

HVAP Support can be provided on the materials not easily available like skilled labour, wood &

stones for walls, roof materials, materials for concrete ground floor slopes and building

materials like nails, latches etc. Bamboo and labour is easily available and can be used at very

low cost among the community.

Their BP shall reflects the total goat herd size of 10-15 goats at the end of third year for each

HH

HVAP support of Nrs 30,000/- and Nrs. 15,000/- on new construction and renovation

respectively of goat shed can be provided to each HH based on the above can be considered.

Release of grant funds can be controlled by the periodical monitoring and review.

Field Verification – Goat VC: Lekhgaon, Surkhet

Janpriya Bahu-Udesya Sahakari Sangstha (JBUSS), 31th August 2014

Page 2: Report Lekhgaon Goat 31Aug14

Page/of 2/2

Collage