report and recommendations on operation & …
TRANSCRIPT
Docket:
Exhibit Number
Commissioner
Administrative Law Judge
Public Advocates Office
Witness
:
:
:
:
:
A.21-01-003
Cal Adv - ____
Martha Guzman Aceves
Daphne Lee
Andrew Sweeney
REPORT AND RECOMMENDATIONS
ON
OPERATION & MAINTENANCE EXPENSE
Application 21-01-003
San Francisco, California
May 25, 2021
This page intentionally left blank
iii
MEMORANDUM
The Public Advocates Office at the California Public Utilities Commission (Cal 1
Advocates) examined requests and data presented by San Jose Water Company (SJWC) 2
in Application (A.) 21-01-003 (Application) to provide the California Public Utilities 3
Commission (Commission) with recommendations that represent the interests of SJWC’s 4
customers for safe and reliable service at the lowest cost. This Report is prepared by 5
Andrew Sweeney. Ting-Pong Yuen is Cal Advocates’ project lead for this proceeding. 6
Mukunda Dawadi is the oversight Program and Project Supervisor, and Angela Wuerth is 7
the legal counsel. 8
Although every effort was made to comprehensively review, analyze, and provide 9
the Commission with recommendations on each ratemaking and policy aspect of the 10
requests presented in the Application, the absence from Cal Advocates’ testimony of any 11
particular issue does not constitute its endorsement or acceptance of the underlying 12
request, or the methodology or policy position supporting the request. 13
iv
This page intentionally left blank
v
TABLE OF CONTENTS
Memorandum ...................................................................................................................... iii
Table of Contents ................................................................................................................. v
Executive Summary ............................................................................................................ vi
Operation and Maintenance Expense .................................................................................. 1
I. Introduction ............................................................................................................... 1
II. Summary of Recommendations ................................................................................ 2
III. Discussion ................................................................................................................. 3
A. Purchased Water Potable, Purchased Water Recycled, Pump Tax Expense, and
Purchased Power Expenses ......................................................................................... 3
B. Purchased Materials/Services ................................................................................. 8
C. Expenses for Water Treatment, Water Quality and Distribution ......................... 14
D. Maintenance Expenses.......................................................................................... 18
IV. Conclusion ............................................................................................................... 19
Attachment 1-1: Statement of Qualifications – Andrew Sweeney ................................ 20
Attachment 1-2: Valley Water 2021-2022 PROPOSED WATER CHARGES ............ 22
Attachment 1-3: SJW Group 2020 Sustainability Report ............................................. 26
vi
EXECUTIVE SUMMARY
This Report provides the Public Advocates Office at the California Public Utilities 1
Commission (Cal Advocates) analyses and recommendations regarding San Jose Water 2
Company’s (SJWC) Test Year (TY) 2022 Operation and Maintenance (O&M) Expense. 3
The Commission should authorize an O&M Expense budget of $220,784,505, which is 4
greater than SJWC’s request of $207,830,874.1 For TY 2022, the Commission should 5
authorize the following specific O&M Expense budgets: 6
1. $110,926,899, $3,662,614 and $56,762,808 respectively for Purchased Water 7
Potable, Purchased Water Recycled and Pump Taxes. SJWC’s forecasts of 8
$100,373,135,23 $3,210,0504 , and $50,979,4695 are not accurate, are likely to be 9
“trued-up,” and should not be used to set the budget for this O&M category. 10
2. $5,592,801 for Purchased Power Expense. SJWC’s forecast of $7,422,5146 is not 11
accurate and should not be used to set the budget for this O&M category. 12
3. $10,421,700 for Purchased Materials/Services Expense (sans water treatment and 13
water quality expenses). SJWC’s forecast of $11,981,3007 is not accurate and 14
should not be used to set the budget for this O&M category. 15
1 A.21-01-003, SJWC Exhibit F, WP 8-02 at cell L40. In the 45-day update the total O&M Expense was
$210,014,158.
2 Cal Advocates’ recommendations are based on SJWC’s application figures. Any differences in SJWC’s
application figures and SJWC’s 45-day update are footnoted.
3 A.21-01-003, SJWC Exhibit F, WP 8-07, at cell D18. SJWC’ s 45-day update estimated $101,304,987.
4 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell D39. This is SJWC’s
application figure; the 45-day update gave a figure of $3,662,614.
5 .21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell D26. This is SJWC’s application
figure; the 45-day update gave a figure of $52,029,418.
6 A.21-01-003, SJWC Exhibit F, WP 8-06 at cell L31. In the 45-day update the total O&M Expense was
$7,654,428.
7 A.21-01-003, SJWC Exhibit F, WP 8-15 at cell K27+K28. In the 45-day update SJWC estimated
$11,770,300.
vii
4. $1,457,854 for Water Treatment and Water Quality Expense. SJWC’s forecast of 1
$1,512,9588 is not accurate and should be used to set the budget for this O&M 2
category. 3
5. $17,157,908 for Maintenance Expense. SJWC’s forecast of $16,988,3429 is not 4
accurate and should not be used to set the budget for this O&M category. 5
8 A.21-01-003, SJWC Exhibit F, WP 8-15 at cell K29+K30. In the 45-day update SJWC estimated
$1,457,854.
9 A.21-01-003, SJWC Exhibit F, WP 8-02 at cell L38. In the 45-day update the total Maintenance
Expense was $17,883,488.
1
OPERATION AND MAINTENANCE EXPENSE
I. Introduction 1
This report contains (Cal Advocates) recommended San Jose Water Company’s 2
(SJWC) Test-Year (TY) 2022 Operation and Maintenance (O&M) Expenses budget.10 3
SJWC requests a TY 2022 budget of $207,830,87411 12 in combined O&M Expenses with 4
$190,842,53213 for operational expenses and $16,988,34214 for maintenance expenses, 5
which is approximately 3.78%15 higher than authorized by the Commission for 2019.16 6
The Operations Expenses include (1) water source of supply costs such as purchased 7
water and pump taxes, (2) costs related to pumping such as purchased power, (3) costs 8
related to water treatment, and water quality, such as chemical costs, (4) costs related to 9
water transmission and distribution such as transportation, and (5) costs related to 10
customer accounts such as purchased services – materials & supplies, and conservation – 11
material and supplies. Maintenance Expenses are also split into the same sub-categories. 12
10 Numerous company witnesses support SJWC requests in A.21-01-003, SJWC Exhibit E, Results of
Operations Report [hereinafter A.21-01-003, SJWC Exhibit E], and in Exhibit F, GRC Workpapers
[hereinafter A.21-01-003 SJWC Exhibit F]. A.21-01-003, SJWC Exhibit E, Chapters 8 and 16 pertain to
SJWC’s requests for O&M expenses.
11 A.21-01-003, SJWC Exhibit E, CH-8, “Operations and Maintenance Expenses” p.8-8 Table 8-B.
12 A.21-01-003, SJWC Exhibit F, WP 8-02, at cell L64. In the 45-day update the total O&M Expense was
$210,154,263.
13 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-01, at cell L57. In the 45-day update
SJWC requested $192,130,670.
14 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-02, at cell L38. In the 45-day update
SJWC requested $17,883,488.
15 A.21-01-003 SJWC Exhibit F, WP8-02, at cell H40/L40 (Authorized TY 2019 expenses =
$200,261,000). (TY 2022 proposed O&M expenses = $207,830,874). ($207,830,874/200,261,000) =
1.0378 = 3.78%.
16 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-02, at cell H40.
2
The Commission should adopt a TY 2022 total budget of $220,784,05517 for O&M 1
Expenses because SJWC underestimates its forecasted O&M Expenses by $12,953,181.18 2
II. Summary of Recommendations 3
For TY 2022, the Commission should authorize the following specific O&M Expense 4
budgets: 5
• Purchased Water Potable, Purchased Water Recycled, and Pump Tax budgets of 6
$110,926,899, $3,662,614 and $56,762,808 respectively for SJWC’s TY 2022, 7
and reject SJWC’s forecasts of $100,373, 135, $3,210,050 and $50,979,469. 8
• A Purchased Power budget of $5,592,801for SJWC’s TY 2022, and reject SJWC’s 9
forecast of $7,422,514. 10
• For TY 2022 O&M Purchased Services & Materials Expenses (without water 11
treatment and water quality expenses), a budget of $10,421,700, and reject 12
SJWC’s estimate of $11,981,300. 13
• A budget of $1,457,854 for Water Treatment and Water Quality Expenses and 14
reject SJWC’s TY 2022 forecast of $1,512,958. 15
• For TY 2022 Maintenance Expenses, a budget of $17,157,908 rather than SJWC’s 16
estimate of $16,988,342. 17
The table below shows a category by category breakdown of the expenses discussed 18
in this testimony, along with the aggregate difference between SJWC’s and Public 19
Advocates’ O&M Expenses Budgets. 20
17 Cal Advocates’ recommendations are based on SJWC’s application figures. Any differences in SJWC’s
application figures and SJWC’s 45-day update are footnoted.
18 Public Advocates Recommended Total Budget – SJWC Recommended Total Budget =
($220,784,055– $207,830,874) = $12,953,181.
3
Table 1-1: Itemized O&M Expenses Budget
SJWC Request Public Advocates
Recommendation Difference
Purchased Water Potable $100,373,135 $110,926,899 $10,553,764
Purchased Water Recycled $3,210,050 $3,662,614 $452,564
Pump Tax $50,979,469 $56,762,808 $5,783,339
Purchased Power $7,422,514 $5,592,801 ($1,829,713)
Total Purchased Materials & Services $11,981,300 $10,421,700 ($1,559,600)
Water Treatment and Water Quality
Expenses
Regulatory Expenses $319,338 $234,961 ($84,377)
“Other” Operating Expenses $499,60619 $443,505 ($56,101)
Total Water Treatment and Water
Quality Expenses $1,512,958 $1,457,854 (55,104)
Maintenance Expenses $16,988,342 $17,157,908 $169,566
Total Operations & Maintenance
Expenses $207,830,874 $220,784,055 $12,953,181
III. Discussion 1
A. Purchased Water Potable, Purchased Water Recycled, Pump Tax 2
Expense, and Purchased Power Expenses 3
It is important to remember that, in this GRC, the Commission is not setting the 4
amount that SJWC is allowed to spend; instead, it is setting the budget that SJWC is 5
allowed to recover from its customers. As a result of its incremental cost balancing 6
account, between this GRC and the next, SJWC can file to correct or "true-up" certain 7
expenses, namely Purchased Water, Pump Taxes, and Purchased Power, to correct for 8
19 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-01, at cell (L18+L35+L42+L52) 45-day
update 2022 figure was $499,000.
4
variances between forecasted and actual costs. In addition to reducing SJWC’S 1
forecasting risk, “Trueing up” can lead to reduced customer transparency when costs are 2
forecasted too low in a GRC and rates are increased following the GRC to recover the 3
difference between forecasted and actual costs. 4
Taking the issue of “trueing up” into account, the Commission should adopt a 5
Potable Purchased Water Expense of $110,926,899; Recycled Purchased Water Expense 6
of $3,662,614; Pump Tax Expense of $56,762,808; and Purchased Power Expense of 7
$5,592,801 for TY 2022. SJWC's annual forecasts do not account for likely cost 8
increases in purchased water and pump tax expenses. SJWC provides a less accurate, 9
lower forecast of purchased water. SJWC determined the portion of SJWC’s customer 10
bills tied to pump taxes using the current rate. However, Santa Clara Valley Water 11
(Valley Water) has adopted new water charges, effective July 1, 2021. Valley water 12
plans to increase the potable purchased water cost to $1,61420 per acre-foot from $1,474 13
per acre-foot, and the pump taxes to $1,49921 per acre-foot from $1,374 per acre-foot. 14
Purchased water costs are expenses that can be reasonably forecasted and, as such, 15
should be accurately reflected in the expense budget established in this GRC. SJWC’s 16
proposed O&M Expenses do not account for Valley Water’s price increase. SJWC 17
seeking to later recover costs incurred due to expense increases that could have been 18
reasonably forecasted in the GRC decreases customer transparency, hindering customers’ 19
understanding of utility-proposed rate increases included in the GRC application. This 20
results in customers experiencing more rate changes (and surprise billing) between 21
GRCs. 22
20 Attachment 1-2: https://www.valleywater.org/your-water/current-water-charges/your-water/current-
water-charges/2021-22-proposed-water-charges. “2021-2022 Proposed Water Charges”
21 Attachment 1-2: https://www.valleywater.org/your-water/current-water-charges/your-water/current-
water-charges/2021-22-proposed-water-charges. “2021-2022 Proposed Water Charges”
5
1. Purchased Water Potable 1
The Commission should increase SJWC’s Potable Purchased Water Expense 2
budget to $110,926,899 from $100,373,13522 for TY 2022. SJWC estimates a Purchased 3
Potable Water Expense of $100,373,135 based on the existing 2021 pump tax rate of 4
$1,474 per acre-foot ($4,524 per million gallons (MG)),23 which became effective 5
beginning on July 1, 2019.24 SJWC’s estimates do not account for the upcoming increase 6
in potable water price by Valley Water, the wholesaler from which SJWC buys treated 7
potable water. Valley Water is going to increase the potable (treated) water price to 8
$1,614 per acre-foot ($4,953 per MG) for zone W-2 (North County) on July 1, 2021.25 26 9
SJWC requests that any price changes by Valley Water be incorporated into the 10
purchased water expenses determined in this GRC.27 Therefore, the Commission should 11
authorize SJWC a purchased water price of $1,614 per acre-foot. Any other differences 12
between Cal Advocates’ recommended potable purchased water amounts and SJWC’s 13
requested amounts for TY 2022 are due to the differences in estimated volumes of water 14
as discussed in the Direct Testimony of Cal Advocates’ witness Mr. Ting-Pong Yuen. 15
2. Purchased Water Recycled 16
The Commission should adopt $3,662,614 as the budget for the Purchased Water 17
Recycled Expense for TY 2022. SJWC estimates its TY 2022 Purchased Water Recycled 18
Expense of $3,210,05028 based on 2021 purchased water recycled price of $1,269 per 19
22 A.21-01-003, SJWC Exhibit F, WP 8-01, at cell K27. SJWC’ s 45-day update estimated $101,304,987.
23 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell C16.
24 A.21-01-003, Exhibit E – RO Report Public Version, p. 8-2.
25 Attachment 1-2: https://www.valleywater.org/your-water/current-water-charges/your-water/current-
water-charges/2021-22-proposed-water-charges. “2021-2022 Proposed Water Charges”
26 Attachment 1-2: The final charge adopted by SJWC was $1,499/CCF for Purchased Water Potable.
27 A.21-01-003, Exhibit E – RO Report Public Version, p. 8-2.
28 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell D39. This is SJWC’s
application figure; the 45-day update gave a figure of $3,662,614.
6
acre-foot ($3,894 per MG),29 which became effective from July 1, 2019,30 and the water 1
quantity (824 MG31). After reviewing Recycled Purchased Water Expenses, past 2
recorded costs, and SJWC’s cost estimation methodology, a budget of $3,662,614 should 3
be adopted for the TY 2022 Recycled Purchased Water Expense to account for the 4
greater estimated volume of Recycled Purchased Water consumed. 5
3. Pump Taxes 6
The Commission should adopt $56,762,808 as the budget for Pump Tax Expense 7
for TY 2022. SJWC estimates a Pump Tax Expense of $50,979,46932 based on the 8
existing 2021 pump tax assessment of $1,374 per acre-foot ($4,217/MG),33 which 9
became effective on July 1, 2019.34 Valley Water charges SJWC a fixed pump tax 10
charge for groundwater extraction from wells. Valley Water will increase the pump tax 11
charge to $1,499 per acre-foot ($4,600/MG) for the 2021-22 fiscal year for zone W-2 12
(North County). 35 36 Assuming SJWC’s estimated quantities of extracted well water for 13
TY 2022 are unchanged, the pump tax expenses total $56,762,808, which is $5,783,33937 14
more than what SJWC proposed.38 SJWC requests that any changes by Valley Water be 15
29 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell C37.
30 A.21-01-003, Exhibit E – RO Report Public Version, p. 8-2.
31 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell D36. This is SJWC’s
application figure; the 45-day update gave a figure of 940MG.
32 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell D26. This is SJWC’s
application figure; the 45-day update gave a figure of $52,029,418.
33 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-07, at cell C24.
34 A.21-01-003, Exhibit E – RO Report Public Version, p. 8-2.
35 Attachment 1-2: https://www.valleywater.org/your-water/current-water-charges/your-water/current-
water-charges/2021-22-proposed-water-charges. “2021-2022 Proposed Water Charges”
36 Attachment 1-2: The final charge adopted by SJWC was $1,614/CCF for Purchased Water Potable.
37 ($56,762,808 – $50,979,469) = $5,783,339
38 2022: ($4,600 per MG * 12,339MG) = $56,762,808: ($4,217 per MG * 12,090MG) = $50,979,469.
7
incorporated into Pump Tax Expenses determined in this GRC.39 Since Valley Water 1
will increase the pump tax assessment from $1,374 per acre-foot to $1,499 per acre-foot 2
on July 1, 2021, the Commission should use the pump tax charge of $1,499 per acre-foot 3
to set the SJWC’s budget for Pump Tax Expense. Any other differences between Cal 4
Advocates’ recommended pump tax amounts and SJWC’s requested pump tax amounts 5
for TY 2022 are due to the differences in estimated volumes of water. These are 6
discussed in the Direct Testimony of Cal Advocates’ witness Mr. Ting-Pong Yuen. 7
4. Purchased Power 8
The Commission should adopt a TY 2022 budget of $5,592,801 for Purchased 9
Power Cost. SJWC’s proposed budget of $7,422,51440 is less accurate because it is based 10
on a forecast that assumes a single-year increase will become a trend. SJWC estimates 11
the total cost of purchased power by multiplying the 2020 cost per kWh by the total 12
number of kWh used.41 There are some issues with SJWC’s estimated total number of 13
kWh. SJWC’s estimate relies on the assumption42 that the higher kWh per KCCF43 14
ratio44 (0.8066 in 2020 vs. the 2016-2020 5-year average of 0.598445)46 will persist 15
through the next GRC despite the absence of historical precedent beyond 2020. Basing 16
future expenses solely on the 2020 figure would result in a high estimate of total energy 17
consumption. This method would, in turn, result in unwarranted customer bill increases 18
to cover purchased power costs. Therefore, the Commission should use the 2016-2020 19
39 A.21-01-003, Exhibit E – RO Report Public Version, p. 8-2.
40 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-06, at cell M31/N31. The 45-day update
was $7,654,400 for 2022.
41 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-06, at cell J23.
42 The version of CH-08, Tab WP8-06 listed in the application used the 2020 $/ kWh figure (0.1822)
rather than the 2016-2020 average $/ kWh (0.18283).
43 A KCCF is equal to 1,000 CCF. A CCF is 100 cubic feet (748 gallons) of water.
44 A higher kWh/KCCF ratio means more electricity will be expended to extract a set amount of water.
45 These are the application figures; the 45-day update figures were 0.8058 and 0.62518, respectively.
46 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-06, at cell F17-J17.
8
average kWh/KCCF ratio to calculate the total estimated kWh used, and from there, 1
estimate the total purchased power cost. Based on the updated total purchased power 2
cost, the Commission should authorize a TY 2022 budget of $5,592,801 for Purchased 3
Power Expenses. 4
B. Purchased Materials/Services 5
1. Total Purchased Materials/Services 6
The Commission should adopt a TY 2022 budget of $10,421,700 for Purchased 7
Material &Services Expense (without water treatment and water quality expenses). This 8
figure is more accurate than SJWC’s proposed budget of $11,981,300.47 SJWC forecasts 9
Purchased Material &Services Expense by subtracting water treatment costs from the 10
2018-2020 inflation-adjusted average operations and maintenance costs and then adding 11
the two. SJWC then adds any additional Purchased Materials & Services expenses that it 12
predicts will be incurred. The Commission’s Rate Case Plan for Class-A water utilities 13
instructs the utilities to present a five-year inflation-adjusted average.48 D.07-05-062 at p. 14
A.24, Footnote 7, states: 15
“In addition to any other methodology the utility may wish to use, the 16
utility shall also present, in its workpapers, an inflation adjusted simple 17
five-year average for all administrative and O&M expenses.” 18
Given the annual variance of SJWC’s historical Purchased Materials & Services 19
expenses, five years of data are necessary to ascertain increasing or decreasing trends in 20
expenditure levels. Where there is no clear trend, or a cyclic trend, in prices across all 21
five years, the Commission should adopt a five-year inflation-adjusted average49 to 22
47 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15. In cell K32, SJWC forecasts
$13,494,258 ($11,981,300 absent water treatment and quality costs). In 45-day updated workpapers,
SJWC updated the forecasted numbers for 2022 with $13,370,154 ($11,912,300 absent water treatment
and quality costs).
48 D.07-05-062 at p, A.24, Footnote 7.
49 D.04-06-018. States that, for test year expenses, a utility must present “an inflation-adjusted simple
five-year average for all administrative, Operational and Maintenance Expenses” in addition to any other
9
smooth out the year-to-year variations in expenditures. SJWC follows the Commission’s 1
rule in forecasting water treatment & water quality expenses and calculates those costs50 2
using five years (2016-2020) of historical data. However, the utility then disregards that 3
rule and presents a forecast of its Purchased Materials & Services expenses calculated 4
using a three-year (2018-2020) inflation-adjusted average.51 Replacing the three-year 5
inflation-adjusted average with a five-year inflation-adjusted average and removing the 6
additional expenses as discussed in the subsequent section results in a TY 2022 budget of 7
$10,421,700 for the Purchased Materials & Services Expense. 8
Table 1-2: Total O&M Purchased Materials & Services (Public Advocates Recommendation)
2021 2022
Total Purchased Services (5-year inflation-adjusted average) $9,931 $10,179
Additions to Purchased Materials & Services $0 $242.7
Water Treatment and Water Quality Operations $1,269 $1,301
Water Treatment and Water Quality Maintenance $153 $157
Total O&M Purchased Materials & Services $11,353 $11,880
Total O&M Purchased Materials & Services – Treatment Costs $9,931 $10,421.7
2. Additional Expenses in Test Year 2022 9
The Commission should authorize a TY 2022 budget of $242,70052 for the 10
additional O&M Purchased Materials & Services Expense (Additional Expense). When 11
estimating Additional Expense, the Commission should exclude $1,031,60053 54 of 12
method used p.7. I have chosen to use this stated average so that all expenses both within SJWC and
across other water utilities for later comparison can be fairly compared.
50 A.21-01-003, Exhibit F, Workpaper CH-08, tab WP 8-15, at cell I17, I22.
51 A.21-01-003, Exhibit F, Workpaper CH-08, tab WP 8-15, at cell I18, I23.
52 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15a, at cell D13.
53 Additional Purchased Materials & Services $1,274,300 – Analytical Costs $242,700 = $1,031,600.
54 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15a, at cell D22 – cell D13.
10
proposed O&M Purchased Materials & Services including $162,600 for Monetvina Plant 1
Maintenance, $500,000 for Well Rehabilitation, $200,000 for SJWC’s Sustainability, 2
Environmental Management System, $160,000 for Amazon Cloud Hosting, and $318,000 3
of operations security expenses.55 SJWC’s forecast and budget for Additional Expense, 4
shown in Table 1-3 below, shows items that are double-counted or not supported by the 5
specific plans or programs. SJWC’s forecast adds each of these expenses to the inflation-6
adjusted average total purchased services56 cost and then multiplying the combined sum 7
by the inflation factor to estimate the cost of the purchased services57 for the following 8
year. They are separate from the inflation-adjusted average purchased services figure58 9
and not used to calculate that figure for the following year. They are, however, included 10
in the total O&M Purchased Materials & Services figure given in the previous 11
paragraph.59 12
Table 1-3: Additional Expenses Proposed in SJWC’s Purchased Materials & Services
SJWC Proposed
2022
Cal Advocates’
Recommended 2022
Operations Security Expense $ 9,000 0
Analytical Costs $242,700 $242,700
Montevina Plant Maintenance $162,600 0
Well Rehabilitation $500,000 0
Sustainability-Environmental
Management System
$200,000 0
Amazon Cloud Hosting $160,000 0
Subtotal $1,274,300 $242,700
Operations Security Expense60 $309,000 0
Total $1,583,300 $242,700
55 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15, at Cell K27. In Cell K27, SJWC
adds $309,000 on top of escalated 5-year average of recorded cost.
56 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15, at cell K32.
57 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15, at cell L27.
58 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15, at cell K27.
59 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15, at cell J32, K32.
60 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15(a), cell K27. In cell K27, SJWC adds
$309,000 on top of the escalated 5-year average of recorded cost.
11
Among the Additional Expenses, the operations security budget of $318,00061 was 1
approved and integrated into the overall Purchased materials & services expense in the 2
2019 GRC.62 SJWC also included in its forecast an additional expense for Oracle 3
Utilities Customer Care and Billings (CC&B) Cloud Hosting63 that had already been 4
incurred in the 2019 GRC. SJWC also included it in its overall Purchased Materials & 5
Services Expense forecast.64 The transition year 2018 and TY2019 Total Purchased 6
Materials & Services Expense projected in the previous GRC,65 including the additional 7
expenses, are very similar to the 2019 expense66 given in the current GRC. This indicates 8
that the Additional Expenses67 were from those years were included in the previous 9
GRC’s total purchased services expense, and therefore were already included in the five-10
year average that determines the TY 2022 Total Purchased Materials & Services 11
Expense. The $160,000 Amazon Cloud Hosting budget, an equivalent service, includes 12
costs that were already included in the CC&B Cloud Hosting budget that must therefore 13
be removed from the Additional Expense forecast and budget. SJWC’s proposed 14
additional costs for Montevina Plant Maintenance, Well Rehabilitation, and 15
Sustainability-Environmental Management System, as shown below in Table 1-1. They 16
are not supported by any documentation showing how the listed budgets were determined 17
or how they are, specifically, going to be utilized. 18
In estimating the Purchased Service Expense budget, $318,000 of Additional 19
Expense tied to operations security should be excluded. As shown in Table 1-1, this 20
61 A.18-01-004, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15a, at cell C12, D12.
62 A.18-01-004, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15, at cell J32, K32.
63 A.18-01-004, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15a, at cell D16
64 A.21-01-003 SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15, at cell F25, G25.
65 A.18-01-004, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15, at Cell J32, K32.
66 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15, at Cell F25, G25.
67 A.18-01-004, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15(a), at Cell C22, D22.
12
amount is composed of $9,00068 and $309,00069 of expenses related to operations 1
security. The $160,000 expense tied to Amazon Cloud Hosting should also be excluded 2
from the forecast because the Commission had already authorized $338,300 for CC&B 3
cloud hosting, an equivalent expense, in its previous GRC. SJWC estimates the total 4
O&M Purchased Materials & Services by taking the 2018-2020 average of the previous 5
year’s inflation-adjusted recorded expenses and adding the Additional Expenses listed in 6
Table 1-1 above. SJWC’s past recorded Purchased Materials & Services costs include 7
the Commission authorized Operations Security Expenses and Cloud Hosting Service 8
cost in the last GRC. As stated previously, estimating Purchased Materials & Services 9
cost by taking the average of the recorded costs, which includes similar expenses from 10
the past, and adding an additional purchased and material services cost without 11
supporting documentation will double the Operations Security cost and Cloud Hosting 12
cost because it will allow SJWC to recover a cost twice for the same additional expenses, 13
unnecessarily inflating customer bills. Therefore, the Commission should exclude 14
$318,000 of Operations Security Expense and $160,000 of Amazon Cloud Hosting cost 15
from the TY 2022 forecast and budget for Purchased Materials & Services. 16
The Commission should exclude $162,600 for Montevina Plant Maintenance costs 17
in the Purchased Materials & Services Expenses forecast and budget because SJWC did 18
not provide support for these costs. Although SJWC mentions that it has “retained 19
vendors to perform the maintenance tasks that the (Montevina) Water Treatment Plant 20
Operators cannot routinely perform,” the estimated annual Montevina Plant Maintenance 21
Expense costs appear excessive. The estimated 2021-23 cost is more than 75 times the 22
2015-17 pre-upgrade amount,70 and nearly 9 times the projected 2020 value. 23
Additionally, this cost is not supported by documentation demonstrating the need for 24
68 A.18-01-004, SJWC Exhibit F, Workpaper CH-08, Tab WP8-15(a), at Column D.
69 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15, at Cell K27.
70 A.21-01-003, SJWC Exhibit E, p. 16-8, 2015-2017 pre-upgrade average cost = $2,111, 2019 cost =
$377,283, 2020 cost = $18,949, 2018-2020 average cost = $164,660. Estimated 2021-2023 cost =
$162,549.
13
such a substantial increase in the maintenance budget or indicating how that budget will 1
be spent. Hence, the Commission should exclude $162,600 of Montevina Plant 2
Maintenance cost from the TY 2022 Purchased Materials & Services forecast and budget. 3
The Commission should exclude $500,000 for Well Rehabilitation from the 4
Purchased Materials & Services Expenses forecast and budget because SJWC did not 5
provide support for these costs. According to Exhibit E of SJWC’s GRC Application,71 6
SJWC is planning on rehabilitating, on average, two of its rotary wells per year for an 7
estimated average annual cost of $500,000, or $250,000 per well. Well rehabilitation is a 8
yearly expense that SJWC should have anticipated for the 31 wells72 it acquired and 9
included in its overall Maintenance Expenses estimate, rather than listing it under 10
Additional Expenses. As it stands, SJWC has provided no supporting documentation 11
concerning the initial costs for the well repair equipment, variations in the cost of 12
maintaining individual wells, or any historical precedent to support the requested amount. 13
Given this lack of supporting documentation, the Commission should exclude $500,000 14
from the Purchased Materials & Services Expense forecast and budget. 15
The Commission should exclude $200,000 for Sustainability-Environmental 16
Management System costs from the Purchased Materials & Services expense forecast and 17
budget because SJWC does not support these costs. SJWC does not provide a project 18
plan or detailed budget. It also does not provide concrete goals for greenhouse gas 19
(GHG) emissions reductions, water conservation, or any other sustainability goal it plans 20
to meet after implementing the environmental management system (ISO 14001). Instead, 21
SWJC only provides a list of elements that the Sustainability-Environmental 22
Management System will contain and goals the system sets out to fulfill.73 The system’s 23
goals include compliance with environmental regulations, efficient use of water 24
resources, setting targets for the reduction of GHGs, and enhancing the environmental 25
71 A.21-01-003, SJWC Exhibit E, p. 16-9.
72 A.21-01-003, SJWC Exhibit E, p. 16-9.
73 A.21-01-003, SJWC Exhibit E, p. 16-10/11.
14
performance of the group’s suppliers.74 SJWC projects $200,000 in expenses, with no 1
detailed breakdown or supporting documents apart from the 2020 sustainability report, 2
and states that a dedicated staff with the mission of implementing the system will be 3
necessary. The 2020 Sustainability Report lists the same goals75 given in Exhibit E of 4
SJWC’s GRC Application and listed earlier in this paragraph. Furthermore, it is unclear 5
why SJWC cannot use existing resources to implement this system. The Sustainability-6
Environmental Management System costs are unsupported and unreasonable. 7
C. Expenses for Water Treatment, Water Quality and Distribution 8
This section contains O&M expenses related to water treatment, water quality, and 9
distribution. These expenses include Transportation, Regulatory, and Conservation 10
Expenses, Chemical costs, and “Other” Operating Expenses. Each of the previously 11
mentioned expenses should be estimated using an appropriate multi-year average rather 12
than the inflation-adjusted 2020 values used by SJWC. A multi-year average of these 13
costs will better account for their variability. 14
a. Transportation Expenses 15
SJWC requests a budget of $4,287,80076 for O&M Transportation Expenses, with 16
fuel costs accounting for $570,05277 of the total for TY 202278, respectively. 17
Transportation Expenses are primarily driven by labor, depreciation, and fuel, with fuel 18
being the focus of this testimony. Cal Advocates reviewed California fuel price market 19
74 A.21-01-003, SJWC Exhibit E, p. 16-10.
75 https://www.sjwater.com/sites/default/files/2020-12/SJW_Report_Layout_100320_Web_FINAL.pdf.
P.37
76 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-18, at cell K23. This figure comes from
SJWC’s application. SJWC’s 45-day update figure is $4,303,900.
77 This number is the total fuel cost multiplied by the proportion of O&M Transportation Expenses versus
Total Transportation Expenses = $644,836*($4,287,800/$4,846,922) = $570,052
78 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-18, at cell K16. This figure comes from
SJWC’s application. The 45-day update figure is $477,103 = 531,081*(4,303,900/4,790,828).
15
data and verified the 3% annual fuel price increase SJWC used to calculate its fuel, and 1
by extension, overall transportation expenses as reasonable.79 Any non-fuel-related 2
differences between Cal Advocates’ recommended amounts and SJWC’s requested 3
amounts for Transportation Expenses are discussed in the Testimony of Cal Advocates 4
witness, Mr. Ting-Pong Yuen. 5
b. Water Quality Regulatory Expenses 6
The Commission should reduce SJWC’s requested TY 2022 budget for Water 7
Quality Regulatory Expenses to $234,961 from $319,338.80 SJWC estimated its 2022 8
Water Quality Regulatory Expenses by multiplying the 2021 value by the weighted 9
inflation adjustment factor and the 5-year average customer growth after calculating the 10
2021 value from the 2020 recorded cost using the same method. SJWC’s method ignores 11
the substantial variation in Regulatory Expenses over time. If the most recent year’s 12
Water Quality Regulatory Expenses were higher than average, this could lead to an 13
excessively high forecast of regulatory expenses and higher customer bills. As shown in 14
Figure 1-1 below, the last five years of recorded annual Regulatory Expense data show 15
that the expenses are cyclic in nature, with the expenses in each post GRC year (2017 and 16
2020) averaging close to three times those of the other years.81 Estimating Regulatory 17
Expenses for the next GRC solely on the expenses incurred in the year following the 18
previous GRC, 2020 in this case, with the highest recorded expenses among three years 19
would result in SJWC collecting $982,37382 from customers from 2022 to 2024, over 20
79 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-18 cell I41.
80 D.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-23 cell J21. This figure comes from
SJWC’s application; the 45-day update was $367,094.
81 D.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-23: Post GRC average =
(349,700+306,643)/2 = $328,171.5, Other Year Average = (57,720 +161,894 +176,250)/3 = $131,995 5-
year average = $210,441.
82 D.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-23 at cell J21, K21, L21.
16
37%83 more than is needed. To capture the three-year cyclic nature of Water Quality 1
Regulatory Expenses, the Commission should use the inflation-adjusted 2018-2020 2
average84 rather than just the 2020 recorded expenses to calculate a reasonable 3
Regulatory Expenses budget. 4
Graph 1-4: Cyclic Expenses in Regulatory Fees
c. Chemical Costs 5
SJWC requests a TY 2022 budget for estimated Chemical Expenses of $547,303.85 6
After reviewing SJWC’s prior years’ recorded costs and SJWC’s methods for calculating 7
chemical costs in its work papers, SJWC’s estimated chemical cost and requested budget 8
for TY 2022 is reasonable. 9
d. Conservation Expenses 10
SJWC requests a TY 2022 budget of $1,495,95486 for estimated Conservation 11
Expenses. After reviewing SJWC’s historical Conservation Expenses, and the methods 12
83 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-23, at cell J21, K21, L21.
($319,338+$327,605+$335,430)/($234,961+$238,720+$242,540) = $982,373/$716,221 = 1.3716
84 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-23, at cell F21, G21, H21.
85 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-23, at cell J13. The 45-day update value
is the same as the value listed in the application = $547,303.
86 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-01, at cell L51. This is updated to
$1,362,095 in the 45-day update
-
50,000.00
100,000.00
150,000.00
200,000.00
250,000.00
300,000.00
350,000.00
400,000.00
2016 2017 2018 2019 2020
RegulatoryFees
17
SJWC uses to calculate conservation costs in its work papers, SJWC’s estimated 1
Conservation Expenses for TY 2022 are reasonable. Moving forward, however, SJWC 2
should provide more detailed information in the GRC application concerning its ongoing 3
conservation programs, such as the potential water savings generated by Commercial, 4
Industrial, Institutional (CII)87 audits, or how many in-person educational events are 5
conducted, and what information is distributed. 6
e. “Other” Operating Expenses 7
The Commission should authorize a TY 2022 budget of $443,505 for “Other” 8
Operating Expenses. This figure is lower than the $499,60688 proposed by SJWC. The 9
operating expenses SJWC labels as “Other” are spread across all four of the five 10
categories of expenses listed in the executive summary (Source of Supply, Water 11
Treatment and Quality, Transmission and Distribution, and Customer Accounts). SJWC 12
calculated various categories of “Other” Expenses by multiplying the recorded 2020 13
expense amount by the weighted inflation adjustment factor and the 5-year average 14
customer growth.89 90 However, this methodology is not appropriate for the “Other” 15
Expenses, as it does not account for the year-to-year fluctuations in their rate of increase. 16
Therefore as the “Other” Operating Expenses do not increase consistently, they should be 17
calculated using a 2016-2020 inflation-adjusted average. 18
87 A.21-01-003, SJWC Exhibit E, p.258 (18-4).
88 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-02, at cell (L18+L35+L42+L52) 45-day
update TY 2022 figure was $498,374.
89 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP8-01, at cell K18. Example: $158,000
(rounded) (2021 Source of Supply “Other”) = ($155,864 (2020 value)*1.016 (Weighted Inflation))*1 (5-
yr average customer growth). The resulting value is multiplied by the next year’s weighted inflation and
5-year average customer growth to get the TY 2022 value = 162,000 (rounded).
90 A.07-05-062, Appendix A, page A-20, item 7 states that “Escalation year expenses may also be
increased by the most recent 5-year average customer growth…” It does not mention transition or test
years.
18
D. Maintenance Expenses 1
The Commission should authorize a TY 2022 budget of $17,157,908 for estimated 2
Maintenance Expenses. This amount is lower than the $16,988,342 proposed by SJWC.91 3
SJWC calculates each expense for maintenance-related purchased services using a 4
percentage (source of supply = 2.96%, pumping = 10.28%, water treatment + 5
transmission/distribution = 86.75%) of SJWC’s total 2020 purchased services 6
maintenance budget.92 SJWC calculates the percentage allocations of the total purchased 7
services budget for operations and maintenance93 using a 2018-2020 average.94 The TY 8
2022 “Transportation” and “Other” Maintenance Expenses tied to water transmission & 9
distribution are calculated by multiplying the recorded 2020 amount by the weighted 10
inflation factor and projected customer growth to generate the 2021 cost estimate. The 11
process is then repeated to estimate the rate case cycle years. This method wrongly 12
assumes that the most recent year’s expense represents the average or typical level of 13
annual expense SJWC is likely to incur during the next rate case cycle. Estimating future 14
Maintenance Expenses using only the most recent year’s expense could disadvantage 15
customers if the most recent year’s expenses were higher than average, increasing 16
customer bills. Given that the expenses that comprise overall maintenance costs fluctuate 17
from year to year, a more suitable method for calculating Maintenance Expenses is to use 18
the 2016-2020 average as the base figure when the year-to-year values trend up and down 19
rather than steadily increasing. 20
91 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-02, at cell L38. This is the value listed
in the application; the 45-day update expense was $17,883,488.
92 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15, at cell F51,F52,F54. These are the
application values, the 45-day update values were 2.57%, 16.76%, 80.67%.
93 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-02, at cell I51 and I52.
94 A.21-01-003, SJWC Exhibit F, Workpaper CH-08, Tab WP 8-15, at cell K27.
19
IV. Conclusion 1
The Commission should authorize a TY 2022 budget of $220,784,055 for estimated 2
O&M Expense. This amount represents a more accurate budget than SJWC’s requested 3
budget of $207,830,874. The Commission should authorize the following TY 2022 4
budgets for the following categories of O&M Expense: 5
• $110,926,899, $3,662,614 and $56,762,808 respectively for Purchased Water 6
Potable, Purchased Water Recycled and Pump Tax expenses. 7
• $5,592,801 for Purchased Power. 8
• $10,421,700 for Purchased Materials & Services Expenses (sans water treatment/ 9
quality expenses) 10
• $1,457,854 for Water Treatment and Water Quality Expenses. 11
• $17,157,908 for Maintenance Expenses. 12
13
[END OF THE REPORT] 14
20
ATTACHMENT 1-1: STATEMENT OF
QUALIFICATIONS – ANDREW SWEENEY
21
Q1. Please state your name, business address, and position with the California Public 1
Utilities Commission (“Commission”). 2
A1. My name is Andrew Sweeney, and my business address is 505 Van Ness Avenue, 3
San Francisco, California 94102. I am a Public Utilities Regulatory Analyst I in 4
the Water Branch of the Public Advocates Office. 5
Q2 By whom are you employed and in what capacity? 6
A2. I am currently employed by the California Public Utilities Commission Public 7
Advocates Office as a Public Utilities Regulatory Analyst I in the Rates & 8
Revenue Section. 9
Q3. Please summarize your educational background and professional experience. 10
A3. I graduated from the University of California San Diego with a Bachelor of 11
Science in Environmental Systems and a Minor in Business. I later graduated from 12
the Rady School of Management with a Masters of Finance. Before joining the 13
Public Advocates Office, I worked as a corporate governance research associate 14
for Glass Lewis & Co. and as an Accounting Clerk for several companies. In my 15
time at the Public Advocates Office, I have analyzed bill arrearages for Class A 16
water utilities. I have written testimony for East Pasadena Water Company and 17
Warring Water Service’s proposed mergers with California-American Water. 18
Q4. What is your responsibility in this proceeding? 19
A4. Writing testimony analyzing the utility’s Operations and Maintenance Expenses. 20
Q5. Does this conclude your prepared direct testimony? 21
A5. Yes, it does.22
22
ATTACHMENT 1-2: VALLEY WATER 2021-2022
PROPOSED WATER CHARGES
23
24
25
26
ATTACHMENT 1-3: SJW GROUP 2020
SUSTAINABILITY REPORT
27