renovation and modernization of lignite fired … and modernization of lignite fired power plant ......
TRANSCRIPT
1 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Renovation and Modernization of Lignite fired Power Plant Boxberg
Guenter HeimannVattenfall Europe Generation AG, BU Lignite
Confidentiality - None (C1)
4th EU South Africa Coal and Clean Coal Working Group Meeting
Johannesburg, 5-6 Nov 2012
Confidentiality - None (C1)
2 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Table of contents
Results3
The USC Units Box Q + R3
Outlook3
Renovation & Modernization Program of Boxberg Power plant
2
Vattenfall in brief1
3 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Vattenfall in brief
Confidentiality - None (C1)
4 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Vattenfall: a leading European energy company
• Vattenfall is one of Europe's largest generators of electricity and largest producer of heat
• Operations were conducted in Sweden, the Netherlands, Germany, Finland, Denmark, Poland,Belgium, France and the UK with up to 7.8 millions of electricity costumers
• Electricity: generation, transmission and distribution• Heat: production, transmission and distribution• Gas: transmission und distribution • Energy trading and lignite mining• Consulting and contracting activities in the energy sectors• approximately 38,000 employees• The parent company, Vattenfall AB, is 100 %
owned by the Swedish state
Confidentiality - None (C1)
5 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Vattenfall structure
Organisation since 1st January 2011
Board of Directors
Staff Functions
BU R&D Projects
BU Engineering BU Nuclear
BU Lignite BU Asset Optimisation Continental
BU Asset Optimisation Nordic
BU Trading
BU Operations
BU Hydro
BU Thermal andHeat
BU Thermal Projects
Chief Financial Officer
BD ProductionBD Asset
Optimisation and Trading
BU Customer Service
BD Distributionand Sales
BU Sales B2C
BU Sales B2B
BD Asset Development
BU OnshoreWind Projects
BD Renewables
BU OffshoreWind Projects
BU Generation Wind
BU Nuclear & Hydro Power Projects
BU Project Governance& Improvement
BU Heat
BU Distribution
BU EnergyRelated Services
BU Biomass
Chief Executive Officer
Confidentiality - None (C1)
6 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Vattenfall‘s electricity generation 2011
34,5
42,5
85
3,4
1,3
0
20
40
60
80
100
120
140
160
180
2011
Elec
trici
ty P
rodu
ctio
n [T
Wh]
Biomass / WasteWindFossilNuclearHydro
166.7 TWh
Source: Year End Report 2011
89.7 %
52,913 TWh
56.9 million t
59,367 kt
Key figures 2011
Availability Lignite:
Power generation Lignite:
CO2 absolute:
Coal quantity:
Confidentiality - None (C1)
7 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Power plants of BU Lignite Mining & Generation
power plant Jänschwaldecapacity: 6 * 500 MWinitial start-up: 1981-1989efficiency: 36 %
power plant Boxberg blocks N/Pcapacity: 2 * 500 MWinitial start-up: 1979/1980efficiency: 36 %
power plant Schwarze Pumpecapacity: 2 * 800 MWinitial start-up: 1997/1998efficiency: 41 %
power plant Lippendorfcapacity: 2 * 920 MW (50 % share) initial start-up: 1999/2000efficiency: 43 %
power plant Boxberg block Qcapacity: 900 MWinitial start-up: 2000efficiency: 43 %
500 MW units
800/900 MW units
+ 675 MWBoxberg unit R
3,420 MW
4,000 MW
7,420 MW8,095 MW
gross capacity
800/900 units
500 MW units
Lignite power plants
new build
Confidentiality - None (C1)
8 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Further Coal PP of Vattenfall Group
Hard Coal PPMoorburg (GE)2 x 820 MWelunder Construction
Hard Coal PPBuggenum (NL)240 MWel
Hard Coal PPHemweg (NL)630 MWel
Hard Coal PPFynsvaerket (DK)409 MWel
Hard Coal PPAmagervaerket (DK)319 MWel
Hard Coal PPNordjyllandsvaerket (DK)660 MWel
Hard Coal PPReuter West (GE)560 MWel
Hard Coal PPTiefstack (GE)320 MWel
Installed Capacity based on Hard Coal > 5.000 MW
Confidentiality - None (C1)
9 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Overview on Vattenfall’s lignite assets
3
4
3
2
2
Flexibility[%-PN/min]
800/900 MW
class(supercritical boilers)
500 MW
class
2000
2000
1997 / 98
1981-88
1978 / 79
commissioning
547°C260 bar41.2 %2 x 800 MWSchwarze
Pumpe
554°C267 bar42.8 %933 MWLippendorf
unit R
545°C266.4 bar42.4 %907 MWBoxberg unit Q
535°C163 bar35.5 %6 x 500 MWJänschwalde
535°C163 bar35.0 %2 x 500 MWBoxberg
units N/P
Life steam parameter
Net efficiency
Gross capacityPower plant
Confidentiality - None (C1)
10 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
0%10%20%30%40%50%60%70%80%90%
100%
unplanned downtime 2,8 3 4,4 5,6 2,9 3,5
planned downtime 8,5 3,6 8,4 8,8 10,3 6,9
availability for work 88,7 93,4 87,2 85,6 86,7 89,5
2006 2007 2008 2009 2010 2011
Development of availability of lignite assets
11 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Renovation & Modernization of Boxberg Power Plant
Confidentiality - None (C1)
12 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
2575 MW
unit R 675 MWas of 2012
Start-up modules I / II / III / IV
Confidentiality - None (C1)
13 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Aerial view Boxberg site
Old 210 MW unitsdecommissioned
Unit N+P2 x 500 MWel
Unit Q900 MWel
Unit R675 MWel
Confidentiality - None (C1)
14 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Boxberg N + P – Technical Key Parameter
N: 240,000P: 237,000Operating hours
2 x 500 MWGross Output el
540 °CIntermediate steam temperature
125 MJ/s
35 %
530 °C
163 bar
2x815 t/h per unit
8.7 – 9.1 MJ/kg
560 t/h per unit
District heating
Net efficiency
Live steam temperature
Live steam pressure
Live steam quantity
Caloric value lignite
Raw coal output
Confidentiality - None (C1)
15 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Power Plant Boxberg – Technical Parameter
>1,400 100,000N: 240,000P: 237,000Operating hours
675 MW900 MW2 x 500 MWGross Output el
610 °C578 °C540 °CIntermediate steam temperature
Unit RUnit QUnit N and P
150 MJ/s
42 %
541 °C
258 bar
2 422 t/h
8.7 – 9.1 MJ/kg
890 t/h
125 MJ/s
35 %
530 °C
163 bar
2x815 t/h per unit
8.7 – 9.1 MJ/kg
560 t/h per unit
-District heating
43.7 %Net efficiency
600 °CLive steam temperature
285 barLive steam pressure
1710 t/hLive steam quantity
8.0 – 9.2 MJ/kgCaloric value lignite
612 t/hRaw coal output
Confidentiality - None (C1)
16 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
500 MW Renovation & Modernization Program
IPhase
1991 - 1996
IIPhase
2002 - 2006
IIIPhase
2006 - 2014
„B500“
Confidentiality - None (C1)
17 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Modernization Phase I (1991-1996) 500 MW Units
Respective actions:- Modernization of the steam generator- Retrofit of the low pressure turbines- Installation of flue gas desulphurization plants (FGD)- Modernization of the electro filter- Change of the control system
I
Confidentiality - None (C1)
18 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Modernization of the steam boiler
Objective: compliance of all limit values and increase of the efficiency
- Reduction of NOx emission1. Conversion of the burner as low-NOx-burner2. Retrofit of over-fire-air-nozzles for a better
CO-burnout3. Reduction of the combustion air surplus
- Increase of the efficiency1. Increase of the controlled air content from 55 %
to > 85 %2. Decline of the exhaust temperature3. Reduction of the unburnt in slag and fly ash
Results:
- Δηboiler ≈ + 4.2 – 5.8 % pointsΔηunit, net ≈ + 1.5 – 2.2 % points
I
Confidentiality - None (C1)
19 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
boiler
e-filter
coal
ash
>5000 mgSO2/Nm3
SO2 air
Flow chart
GS 1,4 %
condensator
cooling water-pump
New construction of flue gas desulphurization plant
absorber
water H2O
air O2
CaSO4
gypsyum
Flue gas SO2
Clean gas
cleaned fluegas /
limestone CaCO3
Flue
gas
with
> 50
00 m
g SO
2/ N
m3
water steamf
SO2 ≤
5%
max
. 400
mg/
Nm
3
Objective: Capture of SO2 of the flue gasconstruction of the FGD each boiler with flue gas dissipation in den cooling towercombining flue gas duct of e-filter over FGD to the cooling towerrenovation of the cooling tower with optimization of the installations
Result:- Unit auxiliary power requirements: + 2 % pointsΔηunit, net ≈ - 0.7 % points
I
Confidentiality - None (C1)
20 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Retrofit of LP Turbine
Target: Increase in EfficiencyMeasures:
Replacement of LP rotor and inner casing to achieve
- Flow improvement- performance increase- Elimination of Erosion
Results: - ΔηND-Turbine up to + 7 %-PunkteΔηBlock, netto + 1,5 - 1,9 %-Punkte
I
Confidentiality - None (C1)
21 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Modernization of ESP
Target: reduction of dust emissionIncrease of precipitation by
- replacing & optimizing the installed equipment- Optimizing the performance of electrodes- Reducing pressure loss
Avoiding operation below acid dew point by- Reducing ration of leak air- Improving insulation
I
Pre
Cle
anin
g Zo
ne
Flue GasInlet
Dry AshM
iddl
eC
lean
ing
Zone
Seco
ndar
yC
lean
ing
Zone
Flue Gasoutlet
Confidentiality - None (C1)
22 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Replacement of Control System
Legal and technical Requirements:-NOx-low Operation of the Steam boiler-Optimization E-Filter Control-Integration FGD into I&C systems-Grid control
Due to the existing I&C Ursarmar 4000 was obsolete as well as the unavailability of spare parts the exchange to processor-based I&C system was required!
Results:-Conformity with environmental and economic requirements
-Higher level of automation and simplified operation
-Common control room for two units with one operator for each unit
I
Confidentiality - None (C1)
23 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Modernization phase II (2002-2006) 500MW units
Retrofit to reach incineration of secondary fuels
Modernization of the control system
Retrofit of the HD turbines
II
Confidentiality - None (C1)
24 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Example: Retrofit HP-turbines 500MW Unit N+P
Before
- Fixed pressure operation- Equal pressure turbine blades (8 stages)- Central drilling at rotor- High maintenance expense – opening once in 4
years necessary- Efficiency: ηHP-turbine = 76 – 79 %
After
- Still fixed pressure operation- Optimised 3-D reaction pressure blades
(16 stages) pre-twisted with integral shroud bands
- Opening only once in 100,000 operating hours
- Efficiency: ηHP-turbine ≈ 89 %
∑ 3.5 mill. EUR each turbine
II
Confidentiality - None (C1)
25 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
• Integration of the required measures into the revision cycle of 4/8 years during the period of time from 2008 to 2014
• Maintenance of the known characteristics of the 500-MW-equipment
• Basis of the project are the maintenance projects planned in medium-term planning
• Realisation of provable economic measures only
• Project period from 2008 to 2014
Project goals
• Maintenance of the technical safety and an availability of at least 90 %• Further operation of the eight 500-MW-units on the site of Jänschwalde by 2029
and of Boxberg by 2031
Modernization Phase 3 - B500 Retrofit Program
Fundamentals
Avoidance of additional downtime
Technical innovations result in improvements
III
Confidentiality - None (C1)
26 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
B500 Program
Project Study
• Inspection/assessment of the 500-MW-units at the Jänschwalde and BoxbergPower Plants within the framework of a Study in the years 2005/ 2006
• This Study included the cost finding of the determined scope of the project
Requests to suppliers for information offers as far as the required measures in 01/2006 are concerned
Approval of the project
• In December 2006 the project was approved by Vattenfall Board based on econmical evaluations.
• This value scope corresponded to the cost estimate determined within the framework of the study.
Integration of the measures into the Revision Plan 2008-2014
III
Confidentiality - None (C1)
27 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
B500 Measures at the 500MW units at Boxberg
• Replacement HZÜ (reheater) steam pipe at units N+P
• Replacement/Recoiling unit transformer at units N+P
• Replacement SPAT (feed water power turbine)
(4 TSP (turbo feed pump)- power turbines)
• Replacement of automation system until 2014
• Replacement of electrical feed pumps
• Coil end stabilisation generator at units N+P
• Waste water treatment for service water
• Raw water supply, new section
• Auxiliary cooling and service water pipes
• Replacement of 10-kV-engines
III
Confidentiality - None (C1)
28 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Planned Modification 2013/14 - IP Retrofit 500 MW
Scope of supply:• New IP Rotor with 3D Reaction Type
Blading• New IP Inner Casing and Blade
Carriers with 3D Reaction Type Blading• Gland Casing seals and Coupling Parts• Installation and Alignment into the
existing Outer Casing
expected results:• Power increase of > 6,3 MW (green)• Reduce of Heat Consumption
of > 90 kJ/kWh• Save more than 45.000 t/CO2 per Year• Reducing Overhaul Costs• Improving Reliability and Availability
for the remaining Life Time
III
Confidentiality - None (C1)
29 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Renovation & Modernization Program 500 MW Units
Results
I
Confidentiality - None (C1)
30 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Overview of Main Measures of Modernization Program from 1990-2014
• Replacement of the heat recovery adjunct except ECO and HD1 (high pressure) and improvement of the control
• Conversion of the firing system • Conversion of the ignition oil supply
towards light fuel oil• REA retrofitting
• Partial replacement of E-technology
• Rewiring of 650 km cable
• Modernisation of the cooling tower – installation of high perfomance frigistors
• Installation of Taprogge facility• Replacement of sealed bearings
• Complete replacement of control and communication technology
• Introduction of workstations• Increased levels of automatisation• New 1000 MW – unit control room
• HD- Retrofit• Replacement of MD
(medium pressure)-rotor
• Replacement of automation system
• Raw water supply • Waste water treatment
• Auxiliary cooling water and service water
Legend : black Improvements during the 1990ies purple extension of operation B500
ESPTSP
Confidentiality - None (C1)
31 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Results of Retrofits of 500 MW Turbines
95
70
75
80
85
90
HD MD ND
Efficiency [%]
Before Modernization After ModernizationBFPT
- 680 kJ/kWhElectrical Power
+ 52 MW
Heat Consumption
G
535MW
Δ = + 3,4Δ = + 11Δ = + 10 / 13
Δ = + 7,6
Main Steam Turbine Set BFPT’s
Confidentiality - None (C1)
32 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Results of the modernization till 2006
φφØ Operating performanceComparison 1989 and 2005
Net efficiencyComparison 1989 and 2005
II
Confidentiality - None (C1)
33 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Results of the modernization till 2006
boiler e-filterFlue gas
desulphurization plant
Dust
II
34 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
The USC UnitsBoxQ and R
Confidentiality - None (C1)
35 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Boxberg Q – Technical Key Parameter
100,000Operating hours
900 MWGross Output el
578 °CIntermediate steam temperature
150 MJ/s
42 %
541 °C
258 bar
2 422 t/h
8.7 – 9.1 MJ/kg
890 t/h
District heating
Net efficiency
Live steam temperature
Live steam pressure
Live steam quantity
Caloric value lignite
Raw coal output
Confidentiality - None (C1)
36 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
L&C Steinmüller / Babcock Lentjes
Type: forced flow
580 °CIntermediate steam temperature =
8Number of mills =
545 °CLive steam temperature =
58 barIntermediate steam temperature =
266 barLive steam pressure =
581 kg/sIntermediate steamquantity =
673 kg/sLive steam - quantity =
Cleaning plants
Water lance blowers 16 piecesRetractable soot blowers 84 piecesLance blowers 42 pieces
Unit Q – Steam Boiler 2,422 t/h
Confidentiality - None (C1)
37 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
9StagesFeedwater Preheating
290°CFeedwater - Boiler Inlet Temperature
46.1%Unit Efficiency brutto
640MWPower Output net
35MWAux Power
closed loop, cooling tower-Cooling system
4.5mill t/aFuel Consumption
33mbarLP- Exhaust Pressure
Operation Mode - Base LoadFuel - LignitePower Output brutto MW 675
Unit Efficiency net % 43.7
Live Steam °C / bar 600 / 286Intermediate Steam °C / bar 610 / 50
spec CO2-Emission g/kWhnet 924
Boxberg R – Technical Key Parameter
38 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
4. Outlook
Confidentiality - None (C1)
39 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Coal had a share of 43.5 % ofGermanys electricity production in 2011
Electricity generation in Germany 2011
Overall electricity production (gross): 614.5 TWhOverall installed capacity: 167,820 MW
Source: BDEW 03/2012
Share of energy sources in %
3.16.1
3.2
5.2
7.6
13.7
17.6
18.6
24.9lignitehard coalnucleargaswindbiomasshydroPVother
Confidentiality - None (C1)
40 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Growth of wind and solar capacity in Germany
Source: Prognos, base scenario 2010A, September 2011
27,2 2946
6376 79
18,46,1
6565
63
52
2516,51,80,1
0
20
40
60
80
100
120
140
160
2000 2005 2010 2011 2020 2030 2040 2050
Inst
alle
d C
apac
ity [G
W]
Wind (total) Solar
Prognosis
The increasing share of discontinuous generated electricity fromrenewable plants with feed-in priority requires a significantly higher
controllability of conventional power plants.
Confidentiality - None (C1)
41 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Development perspective
• challenges today and in the futureSecurity of supply
Economic efficiencyEnvironmental compatibility
Flexibility
• this means the meaningful use of all different types of production
regenerative ↔ coal ↔ gas
• massive expansion of the electricity grid and development of the storage techno-logy
(Lignite) power plants are an indispensable part of the German
electricity supply in the technical and economic view
42 | 4th EU - South Africa Coal & Clean Coal Working Group Meeting | 2012-11-05
Thank you for your attention!