renewables california update mid-c 2010

Upload: quetzal2

Post on 06-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Renewables California Update Mid-C 2010

    1/13

    California Update

    14th Annual Mid-C Seminar

    Wenatchee, Washington

    July 19, 2010

  • 8/3/2019 Renewables California Update Mid-C 2010

    2/13

    Disclaimer

    The conclusions and opinions in this presentation are the authors. They do not

    reflect the opinions, conclusions or policy positions of the Western Power TradingForum or its members, Resero Consulting or its clients, WECC or the VGS, or the

    CAISO.

  • 8/3/2019 Renewables California Update Mid-C 2010

    3/13

    Dynamic Transfers

    Topics

    TRECSIndependentTransmission

    SupplyVariability

  • 8/3/2019 Renewables California Update Mid-C 2010

    4/13

    Copyright 2010 Resero Corporation4

    TRECS (Tradable Renewable Energy Credits) Scorecard

    CPUC decision issued on March 11, 2010

    Through 2011, 25% of RPS target could be met with TRECS

    After 2011, no cap on TRECS

    IOU quotas were essentially filled at the time

    Decision was stayed immediately

    TRECS cant be used to meet RPS at all

    CARB issued separate rules that do allow use of TRECS to meet 33% RPS

    Separate initiative underway to broker a compromise (also SB 722)

    60% in-state, 15% dynamic transfer, 25% TRECS

    TRECS

  • 8/3/2019 Renewables California Update Mid-C 2010

    5/13

    Copyright 2010 Resero Corporation5

    Practical Implications of TRECS

    Out-of-state renewable development has limitations

    Availability of dynamic transfer capability (500 MW at COI)

    Ability of BAs to absorb VG (BPAs DSO 216)

    Availability and cost of transmission

    Availability and cost of balancing, firming, shaping

    In-state development has limitations

    Costs of siting, permitting and construction

    Public resistance to new infrastructure

    Availability, quality and suitability of in-state resources

    CPUC decision and SB 722 likely to face challenges under Commerce Clause

    Lends urgency to Joint Initiative, Efficient Dispatch Toolkit, similar efforts

    TRECS

  • 8/3/2019 Renewables California Update Mid-C 2010

    6/13

    Copyright 2010 Resero Corporation6

    aka, Who Can Build What?

    ~ December, 2009

    CAISO proposes to confer right of first refusal to incumbent TOs for renewable

    energy projects in their service territories

    Independent developers complain

    CPUCcomplains

    ~ April, 2009

    CAISO backs off ROFR

    Devil is in the details

    Trans-Bay Cable - $400 million HVDC connecting SF with Pittsburg

    Western Grid Development Proposals

    Independent Transmission

  • 8/3/2019 Renewables California Update Mid-C 2010

    7/13

    Copyright 2010 Resero Corporation7

    Supply Variability

    Indicative ResultsSource: CAISO Renewable Issues Forum 2010: Market and Product Review

  • 8/3/2019 Renewables California Update Mid-C 2010

    8/13

    Copyright 2010 Resero Corporation8

    Supply Variability

    Indicative ResultsSource: CAISO Renewable Issues Forum 2010: Market and Product Review

  • 8/3/2019 Renewables California Update Mid-C 2010

    9/13

    Copyright 2010 Resero Corporation9

    Supply Variability

    Indicative ResultsSource: CAISO Renewable Issues Forum 2010: Market and Product Review

  • 8/3/2019 Renewables California Update Mid-C 2010

    10/13

    Copyright 2010 Resero Corporation10

    Supply Variability

    Indicative ResultsSource: CAISO Renewable Issues Forum 2010: Market and Product Review

  • 8/3/2019 Renewables California Update Mid-C 2010

    11/13

    Copyright 2010 Resero Corporation11

    Supply Variability

    Renewable (VG) Integration Issues

    Managing variability and uncertainty

    Whos responsible: producer, buyer, someone else?

    Where is it done: gen bus, source BA, sink BA?

    What tools are available: dynamic transfer, on-site supplemental resources, firming

    and shaping services, changes in scheduling, etc.?

    Are new grid services needed?

    Ramp product for speed of response

    Load following product for long-duration response

    Should VG pay for its impacts on the grid?

    Should VG be incentivized to bid day-ahead? Should it be required to provide

    flexibility?

    Is compensation for suppliers of flexibility adequate?

  • 8/3/2019 Renewables California Update Mid-C 2010

    12/13

    Copyright 2010 Resero Corporation12

    Supply Variability

    What the Future MightLook Like*

    Slow phase-out of the Day-Ahead/Hour-Ahead Markets

    Continuous delivery of power is incompatible with infrequent, periodic spot markets

    at defined points in time

    VG and Smart Grid require frequent opportunities to update market positions

    Facilitated by transition to more flexible supply and price-responsive demand

    Addition of five minute energy markets, 15 minute scheduling intervals at the interties

    Mitigates the impact of block hour schedules

    Allows VG to do its own balancing

    Automation and technology make it possible

    CPS1 and CPS2 will be replaced by RBC or something else

    Free-flowing interties necessary to maximize VG production Interconnection frequency and local voltages are the real reliability metrics

    * See the disclaimer

  • 8/3/2019 Renewables California Update Mid-C 2010

    13/13

    13

    Thanks!

    Any Questions?

    Contact:

    Jack Ellis

    Resero Consulting

    [email protected]