renewable grid integration assessment · thailand grid integration project overview ... •provide...

21
1 © OECD/IEA 2018 IEA Renewable Grid Integration Assessment Overview of Thailand Case study Peerapat Vithayasrichareon, Energy Analyst – System Integration of Renewables Grid integration of variable renewable energy, ACEF Asia Clean Energy Forum 2018, Manila, 5 June 2018

Upload: ngoduong

Post on 09-Sep-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

1 © OECD/IEA 2018

IEA

Renewable Grid Integration AssessmentOverview of Thailand Case study

Peerapat Vithayasrichareon, Energy Analyst – System Integration of Renewables

Grid integration of variable renewable energy, ACEF

Asia Clean Energy Forum 2018, Manila, 5 June 2018

2 © OECD/IEA 2018

IEA System Integration of Renewables analysis at a glance

• Over 10 years of grid integration work at the IEA

- Grid Integration of Variable Renewables (GIVAR) Programme

- Use of proprietary and external modelling tools for techno-economic grid integration assessment

- Global expert network via IEA Technology Collaboration Programmes and GIVAR Advisory Group

- Part of delivering the IEA modernisation strategy

Technical Progress & Tracking

2011 2017

Framework, Technology,

Economics

2014 2016 2017

Policy Implementation

3 © OECD/IEA 2018

Thailand grid integration project overview

• Thailand’s Ministry of Energy (MOEN) has officially requested the IEA to provide support on

the study of the impact of variable renewable energy (VRE) and mitigation strategies under

the project “Thailand grid renewable integration assessment”.

• It aims to assist the main stakeholders through workshops, discussions/meetings, detailed

study and analysis

- Energy policy and planning

- System operators – transmission and distribution levels

- Energy regulatory commission

4 © OECD/IEA 2018

Objectives of the project

• Support the reliable and cost-effective uptake of RE generation in Thailand

- Identifying barriers to renewable deployment and integration challenges as well as

proposing possible options in addressing these challenges;

• Provide support by sharing international and regional best practices in

integrating renewables

- Drawing upon the IEA’s network of international experts;

• Conduct quantitative and qualitative analysis on the impact and value of

renewables in the power system;

• Facilitate national and international dialogue through capacity building

workshops and trainings.

5 © OECD/IEA 2018

• VRE phase assessment

for existing system

• Qualitative assessment

of suitability of existing

grid codes for VRE

Analysis components of the project

Each work stream provides insights and recommended actions for Thailand Grid Renewable Integration

1. Existing

power system

context

2. Grid impact

assessment

3. Distributed

solar PV

4. Power sector

planning and

VRE system

costs

• Analysing options to

accommodate RE

integration

• Contractual and

technical flexibility

• Technical potential of

rooftop PV in Thailand

• Economic impacts of PV

• Recommendations and

action priorities

• Assessment of power

sector planning in

Thailand

• System cost and cost

benefit analysis

6 © OECD/IEA 2018

Future power system scenario assumptions for 2036

• Detailed 30-minute power system model

• Validation scenario

- Based on the 2016 system

- Provides a baseline for comparison

• Core scenarios in 2036

- Base scenario (Power Development Plan)

- Assumed higher shares of wind/solar to assess possible integration challenges

• Operational and contractual flexibility option scenarios

- Gas and power purchase contract,

- power plant operational characteristics,

- DSM, EV, storage

Core

ScenarioDescription

Annual

shares

Current (2016)For validation, 3GW solar

and 600 MW wind~3%

Base case (2036)

PDP 2015 target of 6 GW solar and 3 GW wind

6%

RE1 (2036) 12 GW solar, 5 GW wind 12%

RE2 (2036) 17 GW solar, 6 GW wind 15%

RE2 scenario (2036)

•Site selection based on

– Resource potential

– proximity to

transmission

– other considerations

7 © OECD/IEA 2018

Modelling used for the analysis

• Thailand power system model built in the PLEXOS

- 30-min demand data, for 7 regions

- Dispatchable generator operating parameters:

- Ramp rates, min/max gen, heat rates, min up/down times

- Hydro energy constraints with seasonality

- Transmission 230 and 500 kV

- 30-min wind & solar generation

0

5

10

15

20

25

Jan

Feb

Mar

Apr

May Jun

Jul

Aug

Sep Oct

No

vD

ec

VRE Share (%) Base Case

Solar Wind Annual Average (VRE)

0

5

10

15

20

25

Jan

Feb

Mar

Apr

May Jun

Jul

Aug

Sep Oct

No

vD

ec

RE1 Case

0

5

10

15

20

25

Jan

Feb

Mar

Apr

May Jun

Jul

Aug

Sep Oct

No

vD

ec

RE2 Case

8 © OECD/IEA 2018

Detailed analysis of wind, solar output reveals complementarity

There is a high contribution of solar towards a midday peak demand while the wind profile generally

ramps up during the late evening

0

5 000

10 000

15 000

20 000

25 000

30 000

0

10 000

20 000

30 000

40 000

50 000

60 000

VRE Generation (MW)Load (MW)

Wind (CAC) Wind (NAC) Wind (NEC) Wind (SAC)

Solar (CAC) Solar (MAC) Solar (NAC) Solar (NEC)

Solar (SAC) Load Net Load

9 © OECD/IEA 2018

Generation pattern during minimum load period

The system can meet demand reliably during the most challenging weeks, but this requires flexible

operations of including steep ramping and cycling of coal plants.

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

Generation/Load (MW)

Base

Nuclear Coal Biomass and waste Other gas

CCGT GT (diesel) CCGT (OC mode) Hydro

Solar Wind Load Net Load

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

RE1

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

RE2

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

Generation/Load (MW)

Base

Nuclear Coal Biomass and waste Other gas

CCGT GT (diesel) CCGT (OC mode) Hydro

Solar Wind Load Net Load

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

RE1

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

RE2

10 © OECD/IEA 2018

Impact on dispatch of reduced minimum generation

Reduced minimum generation of power plants allows increased deloading of thermal generation

(mostly coal but also other gas) while it is still available to increase output as net demand increases

RE2 core scenario

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

Generation/Load (MW) RE2

Nuclear Coal Biomass and waste Other gas

CCGT Hydro Solar Wind

CCGT (OC mode) GT (diesel) VRE curtailment Load

Net load

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

RE2 + Plant Flexibility

RE2 low minimum generation

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

Generation/Load (MW) RE2

Nuclear Coal Biomass and waste Other gas

CCGT Hydro Solar Wind

CCGT (OC mode) GT (diesel) VRE curtailment Load

Net load

0

5 000

10 000

15 000

20 000

25 000

30 000

31 Dec00:00

31 Dec06:00

31 Dec12:00

31 Dec18:00

RE2 + Plant Flexibility

11 © OECD/IEA 2018

Demand Side Response from Electric Vehicles

Demand response can shift load to periods of abundant supply,

while reducing demand during evening hours.

30 000

35 000

40 000

45 000

50 000

55 000

60 000

14 May00:00

14 May12:00

15 May00:00

15 May12:00

16 May00:00

16 May12:00

Load (MW)

RE2 RE2 with EVs

0

500

1 000

1 500

2 000

2 500

3 000

0

10 000

20 000

30 000

40 000

50 000

60 000

15 May00:00

15 May06:00

15 May12:00

15 May18:00

EV Load (MW)Generation/Load

(MW)

FUEL OIL NUCLEAR COAL GAS

DIESEL HYDRO BIOMASS_WASTE WIND

SOLAR Load EV Load Price (THB/MWh)

0

1 500

3 000

4 500

6 000

7 500

9 000

0

10 000

20 000

30 000

40 000

50 000

60 000

15 May00:00

15 May06:00

15 May12:00

15 May18:00

Price (THB/MWh)Generation/Load (MW)

12 © OECD/IEA 2018

Cost benefits of additional flexibility options

Additional flexibility options allow for further cost savings when integrating higher shares of

renewables, with fuel cost savings due to additional plant flexibility having the biggest impact

-0.2

0

0.2

0.4

0.6

0.8

1

1.2

1.4

RE2 with PlantFlexibility

RE2 with 800MW battery

RE2 withFlexible EV

charging

RE2 withFlexible

IndustrialLoads

RE2 withPumped

Storage Hydro

RE2 with allFlexibility

Options (except400MWbattery)

Total savings per cost component (%

of operating costs)

Fuel Cost Ramp Cost Start & Shutdown Cost Import Hydro Cost VO&M Cost Total

13 © OECD/IEA 2018

Key findings – operational, economic and institutional aspects

• Grid impact assessment

- Much more ambitious solar and wind energy targets are possible from the operational aspect.

- Net ramping requirements increase with higher shares of VRE generation

- Power purchase and gas supply contracts limit currently available flexibility

- DSM, EV and storage and reduced min generation are cost-effective flexibility options

• Distributed PV

- Roof-top availability is no relevant constraint to uptake of distributed solar PV

- Electricity tariff reform is required to ensure a long-term, sustainable uptake of distributed PV

• Power system planning and system cost assessment

- Move towards more integrated planning will be beneficial

- Flexibility options can improve system integration and reduce system costs

14 © OECD/IEA 2018

www.iea.orgIEA

[email protected]

15 © OECD/IEA 2018

1) Existing power system context

• Grid integration

context

• Grid connection

codes

• Renewable

energy control

centre

• VRE phase assessment

for Thailand

• Qualitative assessment

of suitability of existing

codes for VRE

• Role, best practices

and Thailand context

for implementation of

RE control centre

The Thai electricity system is flexible technically, but institutional and contractual constraints limit

mobilising this flexibility

Items Approaches

16 © OECD/IEA 2018

Thailand’s future electricity system has sufficient flexibility options to accommodate a reasonable share

of VRE generation, but some required advanced planning to provide benefits.

Grid Impact Assessment

• VRE Impacts on

system operation

• Flexibility options

to accommodate

VRE integration

• VRE integration

phase assessment

for 2036

• Detailed 30-minute power system model

• Scenario analysis of flexibility options (power plant, DSM, EV, storage)

• Assessment of modelling results in the context of integration phases

Items Approaches

17 © OECD/IEA 2018

Available roof-top area is no relevant constraint for distributed PV, but changes to tariff structures are

needed to ensure that costs and benefits are shared fairly

3) Distributed solar PV

• Technical potential

of rooftop PV in

Thailand

• Economic impacts

of PV

• Recommendations

and action

priorities

Items Approaches

• Measurement of

rooftop area and

generation estimates

• Evaluation of the impact

on the utilities

• Cost benefit analysis for

setting purchasing tariff

18 © OECD/IEA 2018

Planning processes show room for improvement. Solar PV and wind can reduce customer bills, but only

if their cost in Thailand is reduced to international benchmark levels.

4) Power sector planning and VRE system costs

• Assessment of

power sector

planning in

Thailand

• System cost and

cost benefit

analysis

• Detailed qualitative

assessment of the PDP

process

• Quantitative analysis of

the system costs of VRE

in the context of the

future Thailand system

Items Approaches

19 © OECD/IEA 2018

Effect of renewable generation on conventional generation

As shares of VRE increase, it predominantly displaces CCGT generation.

0%

20%

40%

60%

80%

100%

Base RE1 RE2

Generation share

SOLAR WIND CCGTTHERMAL GAS OPEN-CYCLE MODE NUCLEARDIESEL HYDRO COALCHP BIOMASS WASTE

20 © OECD/IEA 2018

Maximum 3-hour ramping

The highest 3-hour ramps vary from a maximum of 39% of daily peak load in the Base to 62% in RE2

0

10

20

30

40

50

60

70

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

3-hour ramps (% daily net peak

load)

Base RE1 RE2

21 © OECD/IEA 2018

Cost benefits of flexible gas supply contracts

Inflexible long term gas contracts can potentially prevent significant fuel cost savings (up to ~14% in

the RE2 scenario), though it is slightly offset by higher cycling costs

-202468

10121416

RE1 RE2

Total savings per cost component

(% of operating costs)

Fuel Cost Import Hydro Cost Ramp CostStart & Shutdown Cost VO&M Cost Total % additional cost