renewable energy intermittent integration to java … · 2019-10-11 · gitet saguling - cibinong 0...
TRANSCRIPT
PT. PLN (Persero) UIP2B
RENEWABLE ENERGY INTERMITTENTINTEGRATION TO JAVA BALI SYSTEM
E HARIYADI– GM PLN P2B10 Oktober 2019
GENERATION READINESSup to SEPTEMBER 2019
01
www.pln.co.id | 03
JAVA BALI SYSTEM OPERATION EVALUATIONEXECUTIVE SUMMARY up to August 2019
Energy Production
Cumulative : 126.560 GWh, 96,15 % based on Annual Planning (ROT), Oil Fueled 0,017%
Growth : 3,28%
Generation Availability (EAF)
Cumulative : System 86,98%, Coal Fired Power Plant 86,59%
Cumulative Load Factor : 78,73%
Peak Load 201927.563 MWThursday, 26-09-201918.00
www.pln.co.id | 06
JAVA BALI SYSTEM NIGHT PEAK LOAD TREND2013 – Sept 2019
2013 2014 2015 2016 2017 2018 2019
Peak Load 22.567 23.900 24.258 25.051 25.665 27.070 27.563
Growth 6,26% 5,91% 1,50% 3,27% 2,45% 5,47% 1,82%
0,00%
1,00%
2,00%
3,00%
4,00%
5,00%
6,00%
7,00%
-
5.000
10.000
15.000
20.000
25.000
30.000
MW
www.pln.co.id | 06
JAVA BALI SYSTEM DAY PEAK LOAD TREND2013 – Sept 2019
2013 2014 2015 2016 2017 2018 2019
Day Load 21.731 22.915 23.449 24.134 25.001 26.435 26.767
Growth 7,55% 5,45% 2,33% 2,92% 3,59% 5,74% 1,26%
0,00%
1,00%
2,00%
3,00%
4,00%
5,00%
6,00%
7,00%
8,00%
-
5.000
10.000
15.000
20.000
25.000
30.000
MW
www.pln.co.id | 33
NIGHT LOAD FLOW26 SEPTEMBER 2019 18:00; 27.563 MW
79 MW 975 MW
253 MW
-53 MW
438 MW
301 MW
UP2B JBR - UP2B JKB MW UP2B JTD - UP2B JBR MW UP2B JTM - UP2B JTD MW
GI CIANJUR - LEMBUR SITU -251 GI BREBES - PLTU CEP -171 GI BOJONEGORO - CEPU 4
GI CIANJUR - BOGOR BARU -1 GI MAJENANG - BANJAR -9 GI NGAWI - SRAGEN 0
GI SUKATANI - BEKASI -21 GITET PEMALANG - MANDIRANCAN 677 PLTU PACITAN - NGUNTORONADI 260
GI TAMBUN - PONDOK KELAPA -77 GITET KESUGIHAN - TASIKMALAYA 478 GITET KEDIRI - PEDAN 253
GITET MUARATAWAR - CIBINONG -4 975 GITET KRIAN - UNGARAN -53
GITET SAGULING - CIBINONG -181 GITET NGIMBANG - UNGARAN -27
GITET MUARATAWAR - CAWANG 424 438
GITET TASIKMALAYA - DEPOK 192
79 UP2B JTM - UP2B BLI MW
GI BANYUWANGI - GILIMANUK 301
301
www.pln.co.id | 35
DAY LOAD FLOW26 SEPTEMBER 2018 14:00; 26.767 MW
698 MW
427 MW
1 MW
716 MW
254 MW
1603 MW
UP2B JBR - UP2B JKB MW UP2B JTD - UP2B JBR MW UP2B JTM - UP2B JTD MW
GI CIANJUR - LEMBUR SITU -254 GI BREBES - PLTU CEP -141 GI BOJONEGORO - CEPU 4
GI CIANJUR - BOGOR BARU 0 GI MAJENANG - BANJAR -17 GI NGAWI - SRAGEN 0
GI SUKATANI - BEKASI -25 GITET PEMALANG - MANDIRANCAN 1,014 PLTU PACITAN - NGUNTORONADI 276
GI TAMBUN - PONDOK KELAPA -78 GITET KESUGIHAN - TASIKMALAYA 747 GITET KEDIRI - PEDAN 427
GITET MUARATAWAR - CIBINONG -63 1,603 GITET KRIAN - UNGARAN 1
GITET SAGULING - CIBINONG 0 GITET NGIMBANG - UNGARAN 7
GITET MUARATAWAR - CAWANG 548 716
GITET TASIKMALAYA - DEPOK 570
698 UP2B JTM - UP2B BLI MW
GI BANYUWANGI - GILIMANUK 254
254
www.pln.co.id | 06
THE JAVA BALI SYSTEM ENERGY PRODUCTION2013 – August. 2018
2013 2014 2015 2016 2017 2018Jan - Agst
2019
energy 156.398 164.167 165.993 175.094 179.250 187.605 126.560
growth 7,19% 4,97% 1,11% 5,48% 2,37% 4,66% 3,38%
0,00%
1,00%
2,00%
3,00%
4,00%
5,00%
6,00%
7,00%
8,00%
50.000
70.000
90.000
110.000
130.000
150.000
170.000
190.000
210.000M
WH
www.pln.co.id | 06
THE JAVA BALI SYSTEM LOAD FACTOR2013 – August 2019
2013 2014 2015 2016 2017 2018Jan - Aug
2019
LF 79,10% 78,40% 79,30% 79,60% 79,80% 79,13% 78,73%
77,50%
78,00%
78,50%
79,00%
79,50%
80,00%
www.pln.co.id | 19
GENERATION ENERGY PRODUCTIONJan – August 2019
Data Source : P2B Annual Planning & Settlement Department
Hydro3,52%
Geothermal4,95%
Coal70,38%
Gas13,84%
LNG6,92%
CNG0,37%
MFO0,01%
HSD0,01%
Kontribusi Energi
JAVA BALI SYSTEM OPERATION
02
www.pln.co.id |
System Operation Criteria
ECONOMIC
QUALITYRELIABLE
Reliability/security:
System ability to withstand unplanned condition without any power outage
Quality:
System ability to keep all constrain to meet the electricity quality
Economic:
Power system optimization without violation in reliability and quality
www.pln.co.id |
System Reliability
1. Reliability Criteria : maintain reserve margin at minimum 30%Reserve Margin 26 September 2019 :RM=(Nett Capacity-Peak Load)/Peak Load= (34.997 – 27.563)/ 27.563 = 27%
2. Normal System Operation Criteria : Normal Criteria is Spinning Reserve fulfilled at least as same as the biggest unit size of power plant in Java Bali system. (Grid Code OC 2.2) In Java Bali = 815 MW
3. Alert Condition Criteria : maintain System Reserve at least as twice as the biggest unit size. (1630 MW)
4. Defense Scheme Protection : Manual Load Shedding (f<49,5 Hz)UFR (48,4 < f < 49,0 Hz, in 7 steps)Islanding Mode (48,1 < f < 48,3 Hz)Over Generation SheddingOver Load Shedding
5. Grid Limitation / Constraint :network configuration (building sub-system)
www.pln.co.id |
SUB SYSTEM SUPPLY CONDITIONNIGHT PEAK LOAD 27.563 MW26 SEPTEMBER 2019 ,18.00 WIB
Besok Pagi
www.pln.co.id |
Service Quality
1.Voltage Stability (Grid Code OC 4.0) :150 kV and 66 kV system : +5% and -10%500 kV system : +/- 5%
How to keep voltage stability :- Reactive power management (generation side and compensation)- Transmission operation management
2. Frequency Stability (Grid Code OC 3.0) : 49.80 – 50.20 Hz (99% achieved in August-September 2019)Load Frequency Control ( approx ± 311 MW * )Governor Free Mode ( 72,9% power plants participate per October 2019)
*
www.pln.co.id |
Economic Operation of Java Bali System
System Constraint :1. Stability (System Inertia)2. Primary energy Take or Pay Contract and Pipe Line Pack limitation (gas,
geothermal)3. Transmission congestion 3. Long distance power transfer (voltage stability)4. Losses
Power Plant Constraint :1. Power plant mode of operation (base load, load follower or peaker)2. Availibility condition of power plant (FOR, derating)3. Minimum technical loading
Economic Dispatch :1. Hydro thermal coordination2. Merit order
www.pln.co.id | 16
LOADSTACKING & COMPOSITION26 Sept 2019
Sumber Data : Data Aplikasi Rapsodi P2B
-
3.000
6.000
9.000
12.000
15.000
18.000
21.000
24.000
27.000
00:3
0
02:3
0
04:3
0
06:3
0
08:3
0
10:3
0
12:3
0
14:3
0
16:3
0
18:3
0
20:3
0
22:3
0
ROR Geothermal Coal GAS LNG CNG HSD MFO Hydro
27563
Hydro0,45%
Geothermal8,11%
Coal50,79%
Gas28,28%
LNG11,16%
CNG1,21%
MFO0,00%
HSD0,00%
Cost Contribution
Hydro2,06% Geothermal
4,40%
Coal70,47%
Gas17,09%
LNG5,44%
CNG0,54%
MFO0,00%
HSD0,00%
Energy Contribution
www.pln.co.id |
MUST RUN GENERATION
Besok Pagi
Future of Java Bali System
03
www.pln.co.id |
Load Balance of Java Bali System 2018-2027
Additional 26.764 MWCommitted : 20.685 MW
2027
PLN 59%
IPP 41%
Generation:
Source:RUPTL 2018-2027
Projected Fuelmix04
www.pln.co.id |
Java Bali System Fuelmix
Source:RUPTL 2018-2027
Future Transmission & Substation
05
www.pln.co.id |
Transmissions & Substations
Transmissions : 18,600 kms
Substations: 94,400 MVA
Source:RUPTL 2018-2027
www.pln.co.id |
Java Bali System Expansion
25
*) COD Pembangkit Berdasarkan RUPTL 2017-20263
CRATA
CBATUBKASI
CIBNG
CWANG
GNDUL
UJBRG
MDCAN
BDSLN
RWALO
PEDAN
UNGAR
TASIK
KDIRI
AMPEL
GRSIK
SBBRT
DEPOK
PITON
SBSLNNGBNG
BTANG
KMBNG
BNGIL
NTSRI
SRLYAMTWAR
IDMYU
CKLNG
MKRNGDKSBI
PRIOK
CLGON
TJATI B
GRATI
WARU
SKTNI
TMBUN
~~~
~
~~
35 68 9
12 14
1817
1516 19
721
23
24
11
BLRJA
DLTMSLGKNG
25
~
TJWAR
CKUPA
LNTAR
UBRUGTBLRK
~ 26
~22
RMBNG
CWGBR
1
XBOGOR
2
1310
20
TWLAN
~~
WTDDL
~
~4
27~
1. PLTU Jawa-9 & Jawa 10 2x1000 MW (2023/2024)2. PLTU Banten 1x660 MW (2026)3. PLTU Jawa-7 2x991 MW (2020)4. PLTU Jawa-5 1x1000 MW (2022)5. PLTU Lontar Exp #4 1x315 MW (2019)6. PLTGU Muara Karang 500 MW (2019)7. PLTDG/MG Senayan 100 MW (2019)8. PLTGU Jawa-2 800 MW (2018/2019)9. PLTGU Muara Tawar Add-on Blok 2,3,4 650 MW (2019)
19. PLTU Jawa Tengah (PPP) 2x950 MW (2020)20. PLTGU Jawa-Bali 1 779 MW (2020)21. PLTU Jawa-4 2x1000 MW (2021)22. Grindulu PS 1000 MW (2025)23. PLTGU Jawa-3 800 MW (2021)24. PLTGU Grati 450 MW (2018)25. PLTGU Grati Add-on Blok 2 183 MW (2019)26. PLTGU Madura 450 MW (2023)27. PLTU/GU/MG Bali 135 MW (2022)
10. PLTGU Jawa-1 2x880 MW (2022/2023)11. Upper Cisokan PS 4x260 MW (2024/2025)12. PLTA Rajamandala 47 MW (2019) 13. PLTU Indramayu #4 1000 MW (2026)14. PLTA Jatigede 2x55 MW (2019)15. PLTU Jawa-1 1x924 MW (2022)16. PLTU Jawa-3 2x660 MW (2024/2025)17. PLTA Matenggeng PS 4x225 MW (2025)18. PLTU Jawa-8 1x945 MW (2020)
GITET 500 kV
LEGENDA
SUTET 500 kV
Pembangkit
Rencana GITET 500 kV
Rencana SUTET 500 kV
Rencana Pembangkit~
Source:RUPTL 2018-2027
Loadflow 2020-2023
06
www.pln.co.id |
Night Load Flow 500 kV 2020 (19.00 WIB)
www.pln.co.id |
Night Load Flow 500 kV 2021 (19.00 WIB)
www.pln.co.id |
Night Load Flow 500 kV 2022 (19.00 WIB)
www.pln.co.id |
Night Load Flow 500 kV 2023 (19.00 WIB)
Subsystem Configuration 2020-2023
07
www.pln.co.id |
Subsystem Evolution
2018 :11 Subsistem
2023 :22 Subsistem
2023 :10 Subsistem
2018 :5 Subsistem
2023 :9 Subsistem
2023 :1 Subsistem
2018 :7 Subsistem
2018 :3 Subsistem
2023 :7 Subsistem
2018 :1 Subsistem
UP2B JKB
UP2B JBR
UP2B JTD
UP2B JTM
UP2B BALI
2018 :27 Subsistem
2023 :49 Subsistem
SUBSISTEM JAWA BALI
www.pln.co.id |
Area Power Balance 2020 (19.00 WIB)
121378977
UP2B JAKARTA & BANTEN
932
249
UP2B BALI6809
4348
UP2B JATIM
44123944
UP2B JAWA TENGAH & DIY
62724681
UP2B JAWA BARAT
Cadangan Operasi (MW)
Mampu Pasok = Beban Puncak + Cadangan Operasi
Beban Puncak (MW)
www.pln.co.id |
Area Power Balance 2021 (19.00 WIB)
987
194
UP2B BALI7191
4770
UP2B JATIM
46664491
UP2B JAWA TENGAH & DIY
66745080
UP2B JAWA BARAT
1309810416
UP2B JAKARTA & BANTEN
Cadangan Operasi (MW)
Mampu Pasok = Beban Puncak + Cadangan Operasi
Beban Puncak (MW)
www.pln.co.id |
Area Power Balance 2022 (19.00 WIB)
1045257
UP2B BALI
Mampu Pasok = Beban Puncak + Cadangan Operasi
75974414
UP2B JATIM
49404312
UP2B JAWA TENGAH & DIY
70234779
UP2B JAWA BARAT
1354510585
UP2B JAKARTA & BANTEN
Cadangan Operasi (MW)Beban Puncak (MW)
www.pln.co.id |
Area Power Balance 2023 (19.00 WIB)
1103
199
UP2B BALI
73916018
UP2B JATIM
49695082
UP2B JAWA TENGAH & DIY
7271
4532
UP2B JAWA BARAT
1381411116
UP2B JAKARTA & BANTEN
Cadangan Operasi (MW)
Mampu Pasok = Beban Puncak + Cadangan Operasi
Beban Puncak (MW)
www.pln.co.id |
Subsistems Load Balance 2021(Night Peak Load)
Mampu Pasok = Beban Puncak + Cadangan Operasi
359441
Suralaya 1&2 - Cilegon 3
APB DKI JAKARTA & BANTEN
1000898
Cilegon IBT 1&2 – PLTU Labuan
305495
Balaraja IBT 3&4
400400
Balaraja IBT 1&2
362438
Lengkong IBT 1&2
355445
Gandul IBT 1&2
383417
Kembangan IBT 1&2
223
577
Gandul IBT 3&4
14881294
Priok IBT 1&2 – Cawang IBT 1
395405
Cawang IBT 2&3
425375
Depok IBT 1&2
420380
Bekasi IBT 2&4
658542
Bekasi IBT 1&3 – Cibinong IBT 3
592542
Cibinong IBT 1&2 – PLTP Salak
734443
Cibatu IBT 1&2
376424
Cibatu IBT 3&4
632771
Bandung Selatan IBT 1&2
587376
Cirata IBT 1&2
419
855
Tasikmalaya IBT 1&2 -Mandirancan IBT 3
613
196
Ujung Berung IBT 1&2
679850
Ungaran IBT 1&2
364
1679
Ungaran IBT 3&4 - Tanjung Jati IBT 3
442358
Pedan IBT 1&2
580734
Kesugihan IBT 1&2
665
387
Pedan IBT 3&4
833549
Ngimbang IBT 1&2
547
253
Krian IBT 1&2
436364
Krian IBT 3&4
705
407
Kediri IBT 1&2
271
529
Kediri IBT 3&4
14381399
Paiton - Grati IBT 1&2
APB JAWA BARAT APB JAWA TENGAH & DIY APB JAWA TIMUR
Cadangan Operasi (MW)Beban Puncak (MW)
251
549
Cikupa IBT 1&2
215
585
Durikosambi IBT 1&2
305495
Durikosambi IBT 3&4
768920
Ubrug IBT 1&2 – PLTU Pelabuhan Ratu
457343
Tambun IBT 1&2
647
154
Deltamas IBT 1&2
469332
Cibatu Baru II IBT 1&2
279
612
Cikalong IBT 1&2
13771300
Mandirancan IBT 1&2 - Cirata IBT 3
892832
Ungaran IBT 3 - Tanjung Jati IBT 1&2
385443
Tuntang IBT 1&2
283517
Batang IBT 1&2
598453
Kesugihan IBT 3&4
16621028
Gresik IBT 1&2 - Waru IBT 1&2
587
217
Bangil 1&2
APB BALI
884956
Lontar IBT 1&2 – PLTU Lontar
782
1727
Muarakarang
249
552
Cikupa IBT 3&4
230
570
Muaratawar IBT 1&2
217
583
Bogor X IBT 1&2
1138
521
Bali
www.pln.co.id |
Subsistems Load Balance 2023(Night Peak Load)
Mampu Pasok = Beban Puncak + Cadangan Operasi
398402
Suralaya 1&2 - Cilegon 3
APB DKI JAKARTA & BANTEN
1169
729
Cilegon IBT 1&2 – PLTU Labuan
393407
Balaraja IBT 3&4
335
465
Balaraja IBT 1&2
438362
Lengkong IBT 1&2
452
348
Gandul IBT 1&2
307
493
Kembangan IBT 1&2
418382
Gandul IBT 3&4
13351447
Priok IBT 1&2 – Cawang IBT 1
436365
Cawang IBT 2&3
481319
Depok IBT 1&2
476324
Bekasi IBT 2&4
739461
Bekasi IBT 1&3 – Cibinong IBT 3
633502
Cibinong IBT 1&2 – PLTP Salak
745432
Cibatu IBT 1&2
510
290
Cibatu IBT 3&4
825578
Bandung Selatan IBT 1&2
786
176
Cirata IBT 1&2
486788
Tasikmalaya IBT 1&2 -Mandirancan IBT 3
483
326
Ujung Berung IBT 1&2
670859
Ungaran IBT 1&2
303
1741
Ungaran IBT 3&4 - Tanjung Jati IBT 3
486314
Pedan IBT 1&2
551762
Kesugihan IBT 1&2
607445
Pedan IBT 3&4
744637
Ngimbang IBT 1&2
673
127
Krian IBT 1&2
382418
Krian IBT 3&4
868
294
Kediri IBT 1&2
375425
Kediri IBT 3&4
14771409
Paiton - Grati IBT 1&2
APB JAWA BARAT APB JAWA TENGAH & DIY APB JAWA TIMUR
Cadangan Operasi (MW)Beban Puncak (MW)
387413
Cikupa IBT 1&2
381419
Durikosambi IBT 1&2
308
492
Durikosambi IBT 3&4
938760
Ubrug IBT 1&2 –PLTU Pelabuhan
Ratu
546
254
Tambun IBT 1&2
527
273
Deltamas IBT 1&2
495305
Cibatu Baru II IBT 1&2
260
632
Cikalong IBT 1&2
15601116
Mandirancan IBT 1&2 - Cirata IBT 3
820905
Tanjung Jati IBT 1&2
415414
Tuntang IBT 1&2
276524
Batang IBT 1&2
574486
Kesugihan IBT 3&4
16591391
Gresik IBT 1&2 - Waru IBT 1&2
664
141
Bangil 1&2
APB BALI
978861
Lontar IBT 1&2 – PLTU Lontar
10591449
Muarakarang
302498
Cikupa IBT 3&4
298502
Muaratawar IBT 1&2
252
549
Bogor X IBT 1&2
1215
444
Bali
402398
Cililitan IBT 1&2
Java Bali System Future Challenge
08
www.pln.co.id |
Technology influence of Java Bali Power System Operation
• Modern Power Control• Automatic Generation Control
• Wide Area Monitoring System
• Weather Forecast/Monitoring
• Substation Automation System (SAS)
• Flexible AC Transmission System (FACTS)
• HVDC (High Voltage DC)
• IoT (Internet of Things)
• Disaster Management
www.pln.co.id |
Business Model of Java Bali Power System Operation
• Modern Power System• Power Market
• Renewable Energy
• Distributed Generation
• Artificial Intelligence of power system
• Electric Vehicle (EV)
• Smart Grid
THE INFLUENCE OF INTERMITTENT RENEWABLE POWER PLANTS
09
www.pln.co.id |
Background
1. 35000 MW project is to support economic growth as main infrastructure
2. Nationwide energy mix from renewable energy is targeted at 23% at 2025.
(25% in electricity utility)
3. Renewable Energy technology has been commercially mature
4. Government target in lowering average system cost (BPP)
www.pln.co.id |
Scope
1. Capacity of intermittent renewable power plant which can be operated in Java Bali system and still keep maintaining reliability/security, quality and economic aspects.
2. Power system operation considering intermittent power plant integration.
www.pln.co.id |
Defect to Frequency
One characteristic of Wind Power Plant is lowestcertainty of energy availability compared to othertype of power plant thus variation of its load willaffect system frequency
Solar power plant load is extremely fluctuated(full load to no load in seconds) thus willsignificantly affect frequency quality.
Sumber :SMA German, 2017
Solar PV
Household
Wind Generation
www.pln.co.id |
Renewable Energy – Constraint System
Types or renewable energy power plant:
− Planned control / dispatchable (hydro/PLTA, geothermal/PLTP)
− Unplanned control / intermittent / non-dispatchable(solar/PLTS, wind/PLTB), which need to be backed-up by system with:
• Load Frequency Control 200 MW
• Spinning reserve (1 biggest unit – 813 MW) with response rate at 5 MW per minute
• Standby reserve (2 x spinning reserve – 1.626 MW), with responsetime around 30 minutes
• Peaker (Gas Turbin/PLTG open cycle with response time 10 minutes)
www.pln.co.id |
Renewable Energy – Grid Constraint
• In sub-system, capacity of intermittent units is limited by capability of inter-bus transformer (IBT) with residual capacity equal with capacity of intermittent unit
• Grid capability of sub system should be maintain its reliability as N-1 therefore adding intermittent unit will be limited to N-1 of grid
• Thus, intermittent unit can only be connected to 150kV or 20kV grid and not to 500kV grid
Example :
• Pedan Subsistem : could only accommodate maximum 200MW (PPA Wind/PLTB Samas 70 MW)
• Cirata Subsistem : maximum 100 MW
• Bali Subsistem : maximum 50 MW
• Madura Island (Krian Subsistem 1,2) : maximum 10 MW
• Intermittent unit could not provide adequate reactive power thus can not be transmitted in long distance
• Capacity of intermittent unit can be allowed if system reserve is ready
www.pln.co.id |
Intermittency
- Intermittent units are non-dispatchable,
- Operation depends on energy source availability which is uncontrollable,
- Intermittent power plant penetration to power system will affect :
▪ Quality of frequency and voltage
▪ Economic aspect
▪ System stability
www.pln.co.id |
Stability
One characteristic of Intermittent unit is not having inertia thuspenetration to grid will lower system inertia
Impact on non intermittent unit trip when intermittent unit is inoperation is higher than when intermittent unit is not inoperation.
Intermittent unit needs energy storage as pumped storage orbattery
www.pln.co.id |
Economic Aspect
- Because of Intermittent Unit impact on system frequency, itneed to be prepared a Special Reserve (Special SpinningReserve) to maintain system reliability.
- Special reserve comes from thermal unit with very fast ramprate (Gas/PLTG and Diesel/PLTD) which has very highoperation cost.
- Consequently with this special reserve, average cost ofoperation will increase
www.pln.co.id |
Solar Energy Potential
www.pln.co.id |
Wind Power Plant Potentioal
Sumber : windprospecting
www.pln.co.id |
Intermittent Power Plant Proposal Proposed (MoU FS)Type of Power Plant P Nominal (MW) Rencana Lokasi
Solar Power Plant (PLTS) 100 GI (Substation) 150 kV Negara, Bali
Solar Power Plant (PLTS) 100 GI 150 kV Amplapura, Bali
Solar Power Plant (PLTS) 100 GI 150 kV Kubu, Bali
Solar Power Plant (PLTS) 100 GI 150 kV Cirata
Solar Power Plant (PLTS) 600 (150) (Switching Station Line Harapan Indah – Kandang Sapi)
Solar Power Plant (PLTS) 500 Scaterred in Java Bali
Wind Power Plant (PLTB) 70 GI 150 kV Wates, Samas
Wind Power Plant (PLTB) 250 Sukabumi
Wind Power Plant (PLTB) 20 P. Nusa Penida/Nusa Lembongan/Nusa Ceningan
Wind Power Plant (PLTB) 150 Garut
Wind Power Plant (PLTB) 103 Lebak
Wind Power Plant (PLTB) 102 Ciemas, Sukabumi
Hybrid PLTS dan PLTB 220 Tegal
Hybrid PLTS dan PLTB 140 Tuban
PLTS & PLTD/MG (Hybrid) Madura Isolasi
PLTS & PLTD/MG (Hybrid) Gili Ketapang
PLTS & PLTD/MG (Hybrid) Bawean
PLTS & PLTD/MG (Hybrid) Karimun, Jawa Tengah
TOTAL 2.555
www.pln.co.id |
Fast response and flexible power plant to compensate RE Intermittent
Load
& N
et L
oad
(M
W)
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
14,000
16,000
18,000
20,000
22,000
24,000
26,000
28,000
30,000
32,000
34,000
Load, Wind & Solar Profiles --- Base ScenarioJanuary 2020
Net_Load Load Wind Total Solar
Win
d &
So
lar
(MW
)
6,700 MW in
3-hours
7,000 MW in
3-hours
12,700 MW
in 3-hours
Net Load = Load - Wind - Solar
www.pln.co.id |
Defect to Voltage
Voltage from Wind Power Plantdepends on wind speed, thus it isunpredictable
The entry of PV Power Plant into grid couldmake voltage range variate higher thanwithout penetration of PV Power plant
Sumber : - ELP and Power Grid International
- Researchgate 2016
www.pln.co.id |
Voltage Regulator
According to voltage characteristic at intermittent power plant, itwill be needed voltage regulator (Volt-VAR Control). Volt-VARcontrol will act as profile voltage buffer and supportingelectromechanical voltage regulator.
Sumber : ELP and Power Grid International
1. Downward ramping capability
Thermal resources operating to serve loads at night must be
ramped downward and potentially shut down to make room
for a significant influx of solar energy after the sun rises.
2. Minimum generation flexibility
Overgeneration may occur during hours with high renewable
production even if thermal resources and imports are reduced
to their minimum levels. A system with more flexibility to
reduce thermal generation will incur less overgeneration.
3. Upward ramping capability
Thermal resources must ramp quickly from minimum levels during daytime hours and new units may be required to start to meet high net peak demand occurring shortly after sundown.
4. Peaking capability
The system will need enough resources to meet the highest net-loads with sufficient reliability
Power plant characteristic to compensate Intermittent RE Power Plant
www.pln.co.id |
60 MW
Back Up Unit
Because of renewable power plant intermittency, fast response powerplants (Gas Fired Power Plant/PLTG or Diesel Fired Power Plant/PLTD) areneeded as a back up when the load of RE power plant is decreasing
PLTS Unit Back Up
TML
60 MW
www.pln.co.id |
Example Duck Curve in California regarding withIntermittent Renewable penetration
www.pln.co.id |
Maximum capacity in one time
Maximum capacity of Intermittent Units are limited by:
1. Ramp up/ down ability of thermal power plant
2. Thermal power plant technical minimum load + regulator power plant
3. Start up/down speed of thermal power plant
4. Capacity of power plant which can act as frequency regulator
Power Plant Ramp Rate
Coal Fired Steam Power Plant (PLTU) 1 – 5 MW/minutes
Gas Fired Steam Power Plant (PLTGU) 5 – 8 MW/minutes
Gas Fired Power Plant (PLTG) 15 – 20 MW/minutes
Hydro Power Plant (PLTA) 20 – 50 MW/minutes
www.pln.co.id |
Quota of acceptable Intermittent Power Plant capacity to be integrated to Java Bali System
Phase YearLoad(MW)
RMQuota (MW)
Constraint
∆ Avera
ge Cost
Prasyarat
1 2018 – 2020 30.792 36% 200 LFC ≈ LFC
2 2020 – 2022 34.581 38% 1000Spinning reserve,
Must Run unit+
+ AGC, WeatherMonitoring System, Fast Response (10 minutes full load) and flexible
3 2022 – 2024 38.150 44% 3000Peaker power plant
capacity≈
+ Pump Storage Upper Cisokan, Storage System, FSRU/CNG Terminal
4 > 2024 44.518 30%20%Peak Load
USC CFSPP TML, Fast Response Unit
- + Power Market
Listrik untuk Kehidupan yang Lebih Baik
TERIMA KASIHTHANK YOU