renewable energy guideline on small hydropower project ... · the re guideline aims to document the...

214
E-Guidebook, 1 st Edition September 2016 Renewable Energy Guideline on Small Hydropower Project Development in Malaysia Up to 30 MW Implemented by:

Upload: others

Post on 24-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

  • E-Guidebook, 1st EditionSeptember 2016

    Renewable Energy Guideline on

    Small Hydropower Project Development in Malaysia

    Up to 30 MW

    Implemented by:

  • Disclaimers

    RE-Guidelines for Small Hydropower development in Malaysia are developed by Renewable Energy Support Programme for ASEAN (ASEAN-RESP), a jointly implemented project by

    ASEAN Centre for Energy *ACE) and GIZ. ASEAN-RESP is a regional project implemented on behalf of Federal Ministry for Economic Cooperation and Development (BMZ).

    Highest effort has been given to ensure and maintain accuracy of the Guidelines. Regulations and procedures for RE project development in Malaysia are complex, include numerous

    actors and are likely to be changed or updated over time. It is therefore not possible to cover all aspects and eventualities of RE project development with these Guidelines. Highest

    efforts have been made to maintain the accuracy of existing processes however, GIZ and its implementing partners cannot be held responsible for any error and misuse of the

    Guidelines. The Guidelines shall not, in any case, replace or be used instead of existing laws, regulations and official guidelines issued by the relevant authorities in Malaysia.

    Imprint

    Authors

    Ir. Shan Suleiman, Khairunisa Shan (SSM Associates, Malaysia)

    International Consultants

    Jan Benjamin Spitzley (Eclareon, Germany), Dr. Matthias Eichelbrönner (E.Quadrat, Germany)

    Editors

    Ms. Azah Ahmad (SEDA), Arne Schweinfurth, Thachatat Kuvarakul, Dr Anant Shukla, Ms. Maria-José Poddey

    Design & Layout

    Thachatat Kuvarakul, Stephanus Widjanarko, Intan Cinditiara (GIZ)

    Publisher

    Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH in a joint initiative of:

    Sustainable Energy Development Authority Malaysia (SEDA)

    Renewable Energy Support Programme for ASEAN (ASEAN-RESP)

    ASEAN Centre for Energy (ACE) under Renewable Energy Support Programme for ASEAN (ASEAN-RESP)

    Kuala Lumpur, September 2016

    www.ssmassociates.com.my

    www.eclareon.com

    www.equadrat-gmbh.de

  • Overall OverallTOC

    ><

    Foreword

    Page 1/4>

    2011 was a transformative year for the development of renewable energy in Malaysia

    with the passing of the Renewable Energy Act [Act 725] and the Sustainable Energy

    Development Authority Act 2011 [Act 726]. This in turn ushered in the establishment of

    the Sustainable Energy Development Authority (SEDA) Malaysia.

    As a statutory body under the direct supervision of the Ministry of Energy, Green

    Technology and Water Malaysia, SEDA operates under 5 strategic thrusts as meted out

    in the National Renewable Energy Policy and Action Plan (2010) and is primarily

    responsible for sustaining the renewable energy agenda in the country. The core

    function of SEDA concerns the implementation of the Feed-in Tariff (FiT) mechanism as

    a means to foster growth in the nation’s renewable energy (RE) market.

    SEDA recognises the potential of small hydro and thus includes it as one of the

    resources under the FiT portfolio. The strength of small hydro lies in the maturity of the

    technology, and as the cost of harnessing said technology is marginal, small hydro has

    the potential to provide electricity at a very reasonable rate. Moreover, small hydro is a

    clean form of electricity generation, and being small means minimising one’s ecological

    footprint. Not only that, hydro systems also possess a high capacity factor, as well as

    the potential to help balance the energy market.

    Sustainable Energy Development Authority (SEDA)

    Malaysia

    Ms. Catherine Ridu

    Chief Executive OfficerSEDA Malaysia

  • Overall OverallTOC

    ><

    Foreword

    In order for the small hydro market to grow, it is important to develop soft infrastructure

    such as human capital to support the industry. In this regard, SEDA is also responsible for

    providing a conducive environment as a means to support sustainable development of the

    small hydro industry; this includes providing competency development training for small

    hydro industry players. SEDA also holds workshops and dialogue sessions for its

    stakeholders to ensure transparency on the administrative procedures that uphold the

    good governance practiced at SEDA Malaysia.

    As such, SEDA Malaysia supports the ASEAN Centre for Energy (ACE) and Deutsche

    Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH in their joint effort to develop

    this Renewable Energy Guideline on Small Hydropower Project Development in Malaysia

    up to 30 MW.

    As Malaysia is one of the active members supporting the ASEAN RE agenda, we hope

    that this guideline will help deepen the talent pool regarding the development of small

    hydro systems both in Malaysia and around the ASEAN region. We hope this guideline

    will be beneficial to all potential developers and investors aspiring to develop small

    hydropower projects in Malaysia.

    Ms. Catherine Ridu,Chief Executive Officer, SEDA

    Page 2/4

  • Overall OverallTOC

    ><

    Foreword

    Page 3/4

    Dr. Sanjayan Velautham

    Principal Advisor ASEAN-RESP, GIZ

    Malaysia, as one of the front runners in terms of renewable energy (RE) technology implementation

    in ASEAN, aspires to achieve targets laid down in the ASEAN Plan of Action for Energy

    Cooperation (APAEC) 2016 – 2025, i.e. 23 % share of RE by the year 2025 in ASEAN Energy Mix.

    In addition to promote increased share of RE in total energy mix, Malaysia aims to reduce

    greenhouse gas emissions by 45% of GDP until 2030, based on the levels of 2005.

    Malaysia incorporated RE as early as 1980 with the introduction of Solar Photovoltaic System for

    rural electrification. After 21 years, RE was formally adapted in April 2001 under the Five Fuel

    Policy with the 8th Malaysia Plan. In 2011, Malaysia established the National Renewable Energy

    Policy and Action Plan (NREPAP), which enabled acts viz. Renewable Energy Act 2011 and the

    Sustainable Energy Development Act 2011. This resulted in the introduction of Feed-in Tariff (FiT)

    and other measures to promote the use of RE.

    Successively, Malaysia introduced various financial incentives and strategies such as the FiT

    mechanism, Green Technology Financing Scheme (GTFS), Facilitation Fund from TERAJU,

    UKAS/PPCU and Pioneer Status/Investment Tax Allowance among others.

    The Renewable Energy Support Programme for ASEAN (ASEAN-RESP) - a jointly implemented

    programme by the ASEAN Centre for Energy (ACE) and the Deutsche Gesellschaft für

    Internationale Zusammenarbeit (GIZ) GmbH on behalf of the Federal Ministry for Economic

    Cooperation and Development (BMZ) - is actively supporting ASEAN Member States (AMS)

    through various measures. These measures include capacity building, training and Focus Group

    Discussions with stakeholders and actors in both the region and worldwide. One such activity is to

    streamline the procedures for permitting/approving projects in AMS. In this direction, the

    Sustainable Energy Development Authority (SEDA) of Malaysia and ASEAN-RESP have

    developed this RE Guideline on Small Hydropower (SHP) Project Development in Malaysia. This

    guideline presents an overview of steps involved in the implementation of SHP projects.

    >

    Executive DirectorASEAN Centre for Energy

    Maria-José Poddey

    Joint Co-operation on ASEAN-RESP

  • Overall OverallTOC

    ><

    Foreword

    Page 4/4

    Dr. Sanjayan Velautham

    The RE Guideline aims to document the existing permits and steps involved in the implementation

    of SHP projects in Malaysia in an easy-to-use and concise format. The Guideline provides an

    overview of the various steps involved and approval required from concerned departments or

    authorities. The RE Guideline provides a means to improve, strengthen and further the

    development of SHP in Malaysia. The RE Guideline intends to support the deployment of installed

    capacity from presently 18.30 MW to 261.84 MW by 2019 under the FiT mechanism. An overview

    of the procedures and steps involved will result in the increase of RE share in the total energy mix,

    improved energy security, self-dependence on energy, as well as job creation in the ASEAN

    region.

    We are grateful to the Ministry of Energy, Green Technology and Water (KeTTHA), Malaysia and

    SEDA for their insights and active engagement in the review and development of this Guideline.

    We hope that this publication will help increase the understanding of the various permits and

    procedures required for SHP project development in Malaysia, thus motivating various

    stakeholders to be involved in SHP projects.

    >

    Ms. Maria-José Poddey

    Principal Advisor ASEAN-RESP, GIZ

    Executive DirectorASEAN Centre for Energy

  • Table of Contents

    Small HydroPower (SHP)

    in Malaysia

    Page 8

    Small Hydropower in

    Malaysia

    Potential of small hydropower for

    electricity generation; framework for small

    hydropower project development in

    Malaysia; related regulations; market

    condition …

    How to use the Guideline

    Page 205

    List of Abbreviations

    Page 203

    Procedures: Step-by-step

    Small Hydropower (SHP) in Malaysia

    Page

    15

    Foreword

    Page 3 & 5

    About the

    guidelines

    Page 11

    Procedure: Step-by-step

    Small Hydropower in Malaysia

    The process for developing a small hydropower plant in

    Malaysia may be found in the Gantt’s chart and flow chart.

  • ><

    OverallOverallTOC

    Small Hydropower in Malaysia

    Malaysia has considerable hydropower potential. There are around 150 river systems

    in Peninsular Malaysia alone and approximately 50 systems in Sabah and Sarawak.

    The total potential of small hydropower currently stands at 116.6 MW. As of 2012,

    there are 58 small-scale hydropower plants in Malaysia. TNB Energy Services (TNB-

    ES), a subsidiary of TNB, operates 30 small hydropower plants[1].

    As of October 2014, the installed capacity of commissioned small hydropower plants

    under the Feed-in Tariff scheme stood at 11.7 MW, resulting in the power generation

    of around 73 GWh in 2013. However, based on the number of applications awaiting

    approval the total installed capacity may reach as high as 209 MW in 2017[2]. Also of

    note: the majority of the hydropower sites currently in use are located in the eastern

    part of Malaysia.

    In recent years the Malaysian government has sought to promote RE across the

    nation. The concept and idea of a Feed-in Tariff (FiT) was proposed by the Malaysia

    Building Integrated Photovoltaic (MBIPV note 1) Project as a potential policy to promote

    the Malaysia RE Sector in 2004. In pursuit of said policy, extensive studies were

    conducted, consultation workshops held and joint co-operation initiated with

    international partners to draft a policy along with supporting mechanisms that best fit

    Malaysia’s needs.

    Background information

    [1]: UNIDO: Small Hydropower World (www.smallhydroworld.org); [2]: SEDA 2014

    Note 1: Malaysia Building Integrated Photovoltaic (MBIPV) Project was a joint initiative between the Government of Malaysia, the United Nations Development Program (UNDP) and Global Environment Facility to promote a nationwide and sustainable solar PV market in Malaysia. MBIPV was active from 2006 to 2010.

    Page 3/5Malaysia Power Sector Small Hydropower

    http://www.smallhydroworld.org/

  • ><

    OverallOverallTOC

    Small Hydropower in Malaysia

    The National Renewable Energy Policy and Action Plan (NREPAP) was proposed in

    2009 and adopted in April 2010. The NREPAP consists of five objectives:

    To increase RE relevance in the national energy mix

    To facilitate growth of RE sector

    To ensure reasonable cost of RE

    To conserve the environment

    To enhance awareness on RE

    Not long after, FiT was incorporated into the 10th Malaysia Plan in June 2010 and

    later into the National Budget of 2011 for the first time. The RE sector gained a strong

    foothold in 2011 when the Renewable Energy Act (Act 725) was passed. It

    establishes the framework for RE project development under a FiT scheme. The

    Sustainable Energy Development Authority (SEDA) was also established by the

    SEDA Act (Act 726). SEDA is a special regulatory body under the Ministry of Energy,

    Green Technology, and Water who administrate and manage the implementation of

    the FiT mechanism under the RE Act.

    Background information

    Page 4/5

  • ><

    OverallOverallTOC

    Small Hydropower in Malaysia

    The Feed-in Tariff for small hydropower projects is between sen 24, sen 25 and sen

    26 (~ cent 5.88 US to cent 6.37 US), depending on the installed capacity. The FiT

    duration meanwhile is 21 years. There is no digression rate (0%) for small

    hydropower plants.

    Background information

    Page 5/5

    Installed capacityFIT rate

    (per kWh)

    Up to and including 2MW 26 sen(US 6.37 cent)

    Above 2MW and up to and

    including 10MW25 sen

    (US 6.12 cent)

    Above 10 MW and up to

    30 MW24 sen

    (US 5.88 cent)

  • Overall OverallTOC

    ><

    About the Guidelines

    In recent years, ASEAN Member States (AMS) have made a considerable effort to tap into the vast reserves of renewable energy

    (RE) in the region. Several countries introduced feed-in-tariffs (FIT) or regulations for RE, as well as other supportive policies, for

    example tax and customs exemptions or tax holidays.

    Despite those efforts and some promising developments, a large scale market for RE applications has not yet been established in

    the region. In particular, complex administrative procedures, a lack of transparency in the project cycle and permitting procedures as

    well as insufficient access to financial resources are but some of the obstacles preventing an effective market and satisfactory

    industry development.

    The ASEAN RE Guidelines were developed to facilitate increased private sector activity and investment in the RE sector of the

    ASEAN region. Since the confidence of project developers and investors is a prerequisite to boost region-wide RE deployment, the

    provision of transparent project development and permit procedures is indispensable.

    To this end, the Renewable Energy Support Programme for ASEAN (ASEAN-RESP), jointly implemented by the ASEAN Centre for

    Energy (ACE) and Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH, is devleoping a comprehensive, easy-to-

    access and regularly updated online tool which includes complete information on ideal RE project development cycles in the

    respective AMS. The ASEAN RE Guidelines:

    highlight administrative procedures including requirements for project developers and/or investors;

    list legal and regulatory provisions as well as necessary permits;

    identify country-specific challenges for project development; and

    Provide information on how to obtain financial closure.

    The ASEAN RE Guidelines are designed as best as possible to meet the needs of project developers and potential investors, as well

    as promote transparency and clarity in the RE projects’ pathway. The Guidelines explain in detail the various procedures and help

    identify the risks associated with each step so that proper mitigation measures can be designed and put in place.

    Page 1/4

    ASEAN RE Guidelines This Guideline

    >

    Small Hydropower Project Development in Malaysia

  • Overall OverallTOC

    ><

    About the Guidelines

    The ASEAN RE Guidelines were developed for different technologies and several ASEAN Member States. To promote RE

    development, as a precondition a clear legal framework must exist, along with minimum market readiness. The ASEAN-RESP is

    working closely with relevant organisations and projects in the respective member states in order to ensure quality, completeness

    and accuracy of data.

    A series of four ASEAN RE Guidelines have been developed and published in four ASEAN Member States: Indonesia, Malaysia, the

    Philippines, and Vietnam.

    Page 2/4

    Indonesia

    • Biomass/biogas

    • Mini hydropower (up to 10 MW)

    • Solar PV

    Philippines

    • Solar PV (small & large)

    Vietnam

    • Biomass

    Malaysia

    • Solar PV (small & large)

    • Small hydropower (up to 30 MW)

    ASEAN RE Guidelines This Guideline

    Small Hydropower Project Development in Malaysia

  • Overall OverallTOC

    ><

    About the Guidelines

    This guideline is one of three publications in the Malaysia series of the ASEAN RE Guidelines initiative. The other guidebooks in the

    series are (1) small solar PV project development and (2) large solar PV project development. They are scheduled to be published in

    2016.

    The Renewable Energy Support Programme for ASEAN (ASEAN-RESP) identified regional and international consultants for the

    development of the RE-Guidelines. This guideline (“Small Hydropower Project Development in Malaysia”) was developed

    together with regional consultant SSM Associates Sdn Bhd and in close co-operation with Sustainable Energy Development

    Authority (SEDA) Malaysia. The guidelines were reviewed by international consultants Eclareon GmbH and E.Quadrat GmbH, to

    ensure that the locally-prepared content can be easily understood by foreign investors / developers.

    The primary target groups of the guideline include project developers and investors who are interested in conducting studies of small

    hydropower projects in Malaysia to determine the financial feasibility. It is also useful to bankers and policy makers. The objective of

    these guidelines is to provide an overview of the processes; they were not written from the perspective of engineering, procurement,

    and construction (EPC), engineering consultant, or equipment suppliers.

    This particular guideline covers only grid-connected small hydropower projects with a capacity of up to 30 MW. Development of an

    off-grid project is subject to different procedures and different technical details. That said, the procedures outlined in these guidelines

    are for projects that seek to obtain a FiT as stipulated by the Renewable Energy Act 2011.

    Based on the regulatory framework and different governing system, development of small hydropower projects in Sarawak need to

    follow different laws and regulations; the procedures are also different. This guidebook covers the legal and regulatory framework in

    the Peninsular Malaysia or Sabah areas only.

    Page 3/4

    ASEAN RE Guidelines This Guideline

    Small Hydropower Project Development in Malaysia

  • Overall OverallTOC

    ><

    About the Guidelines

    The guideline covers only grid-connected small hydropower projects with a capacity of up to 30 MW. Development of an off-grid

    project is subject to different procedures and different technical details. The procedure outlined is for projects seeking to obtain a FiT

    as stipulated under the Renewable Energy Act 2011.

    Based on the regulatory framework and different governing system, development of small hydropower projects in Sarawak need to

    follow different laws and regulations; the procedures are also different. This guidebook covers the legal and regulatory framework in

    the Peninsular Malaysia or Sabah areas only.

    Small Hydropower Project Development in Malaysia

    Page 4/4

    On-grid Off-grid

    10 – 30

    MW Above 30 MWCapacity

    RE Project

    Type

    Included in the Guideline Excluded from the Guideline

    ASEAN RE Guidelines This Guideline

    2 - 10

    MW

    Location Sabah and

    Labuan

    Peninsular

    MalaysiaSarawak

    RE projects larger than 30 MW are

    possible but need special approval

    from the Ministry of Energy, Green

    Technology, and Water (KeTTHA)

    Sarawak is a state in Malaysia with a

    higher level of autonomy. Therefore,

    the laws and regulations differ from the

    federal ones.

    Up to 2

    MW

  • Overall OverallTOC

    Construction and Installation

    Note: The bar length on the Gantt's chart is not to scale. It should be used for qualitative comparison only.

    Planning and Development

    Financial

    Closure

    Operation and

    Maintenance

    Step 1

    Step 7

    Step 11

    Step 2

    Step 5

    Step 8

    Step 3

    Site Selection / Evaluation

    Support Mechanisms

    Administrative Authorisation

    Financing

    Procurement and Construction

    Testing and

    Commissioning

    Power Purchase Agreement

    Step 9

    Step 4

    Operation & Maintenance

    Electricity Production License

    Step 6 Corporate Fiscal/Legal

    Page 1/3 ><

    Procedures: Step-by-Step

    Gantt’s Chart Flow Chart Description

    Small Hydropower Project Development in Malaysia

  • Overall OverallTOC

    Procedures: Step-by-StepSmall Hydropower Project Development in Malaysia

    Site Selection

    / Evaluation

    Step 1

    Support

    Mechanisms

    Step 11

    Step 2

    Administrative Authorisation

    Procurement and Construction

    Step 7

    Testing &

    Commissioning

    Step 8

    Power

    Purchase

    Agreement

    Step 3

    Operation

    and

    Maintenance

    Step 9

    Corporate

    Fiscal / Legal

    Step 6

    Gantt’s Chart Flow Chart Description

    Construction and InstallationPlanning and DevelopmentOperation and

    Maintenance

    Financial

    Closure

    Electricity

    Production

    License

    Step 4

    Step 5

    Financing

    Page 2/3 ><

    Gantt’s Chart Flow Chart Description

  • Overall OverallTOC

    ><

    Procedures: Step-by-Step

    To develop a small hydropower project in Malaysia, project developers must first identify and select a suitable

    site for building a small hydropower plant.

    Concurrently, permission for grid connection must be obtained.

    Typically, project developers establish a special purpose company (SPC) to develop, construct and operate a

    small hydropower plant. The establishment of such a company must be done from the outset.

    Several permits must be obtained from the government and relevant authorities.

    A provisional license must be obtained from the Energy Commission, allowing a project developer to generate

    electricity in Malaysia.

    Financing must be secured from banks or financial institutions.

    After the financial closure, procurement and construction may then proceed.

    After completing construction of a small hydropower power plant, inspection and testing must then be

    conducted.

    After COD, operations at the small hydropower plant may commence.

    Gantt’s Chart Flow Chart Description

    Page 3/3

    Small Hydropower Project Development in Malaysia

  • Overall OverallTOC Step Step

    Step 1 | Site Selection / Evaluation

    1-3

    Appointment of

    Technical Expert1-1

    SSL (Gantt’s chart)

    1-2

    Detailed survey

    Preliminary Survey and Preparation of Feasibility Study (FS)

    Gantt’s Chart Flow Chart More Details…

    Conditional sub-step

    Mandatory sub-step

    2-2

    2-1 Power System Study (PSS)

    Connection Confirmation Check (CCC)

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    Appointment of

    Technical Expert

    1-1

    Preliminary Survey

    and Preparation of

    Feasibility Study (FS)

    1-2

    SSL (Flow Chart)

    Detailed Survey

    1-3

    Gantt’s Chart Flow Chart More Details… 2-2

    2-1 Power System Study (PSS)

    Connection Confirmation Check (CCC)

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    >

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    DESCRIPTION

    1-1

    Appointment of Technical Expert

    According to the regulatory framework of Malaysia, a professional engineer must prepare the project feasibility study (FS), along

    with the supporting documents to be submitted to the Sustainability Energy Development Authority (SEDA). Therefore, as the first

    step, the project developer/investor shall appoint a technical expert (who is legally able to provide professional engineering services)

    to carry out the aforementioned activities.

    Typically, a technical expert will be involved in the two stages of project development.

    .

    Description Documents Fee/Duration Regulations Page 1/7>

    Pre-PPA Stage Post-PPA Stage

    This is from inception of the project until a power

    purchase agreement (PPA) is signed. The

    responsibilities of a technical expert include the

    following:

    Preparation of the FS (Refer to Sub-step 1-2)

    Assist the developer in preparing PPA document

    Activities relating to Post-PPA or implementation

    stage (explained separately in Sub-step 7-1).

    Typically, the tasks of technical experts include the

    following:

    Detailed design of system

    Tendering

    Supervision of the supply and installation of

    equipment and facility

    Supervision of the testing and commissioning of

    equipment and facility

    The same technical consultant may be contracted for both stages.

    Alternatively, different consultants may be contracted separately for

    each stage. In the latter case, the developer must ensure complete

    transfer of information.

    References Challenges

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    DESCRIPTION

    1-1

    Appointment of Technical Expert

    This sub-step details interactions between two businesses; there is no regulation governing the exact procedure. Typically, the

    applied procedure to appoint a technical consultant could be as follows:

    Project developer requests proposals from one or more potential consultants. A request for proposal (RFP) must be prepared.

    Consultants submit their proposals. Typically, a proposal from the potential consultant consists of the following information:

    Technical proposal - covering the scope and duties to be carried out by the consultant

    Financial proposal - indicating the service cost and reimbursable costs

    Project developer evaluates and compares the received proposals. A face-to-face negotiation may be arranged, allowing

    detailed discussion on deliverables, timeframe, service costs, negotiation on scope of works and terms & conditions.

    The developer makes a decision and notifies the winning consultant through a letter of appointment.

    Contract between project developer and consultant is signed.

    Description Documents Fee/Duration Regulations References Page 2/7Challenges

  • REQUIRED DOCUMENTS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Appointment of Technical Expert

    1-1

    Page 3/7

    Only one document is required for this stage: a request for

    proposal (RFP). There is no uniform template for a request

    for proposal document. Typically, it should consist of the

    following:

    Project background

    Location of the project, possible RE technology

    Scope of work and responsibilities of the consultant

    Contract timeframe including crucial milestones

    The contract duration is typically made until the signing of the

    Renewable Energy Power Purchase Agreement (REPPA). In case

    the developer/investor plans to use the same consultant for the post-

    PPA phase, the consultant will be involve until the commissioning

    and handling over of the completed installation to the

    developer/investor

    List of deliverables

    Performance guarantee and warranty period

    Description Documents Fee/Duration Regulations

    Scope and responsibilities of the developer

    This is to indicate what is excluded from the consultant’s scope and

    covered by project developer.

    Additional terms and conditions (T&C)

    The project developer is required to share additional standard terms

    and conditions with the hired consultant.

    References Challenges

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    Appointment of Technical Expert

    1-1

    Page 4/7Description Documents Fee/Duration Regulations

    The fee for Feasibility Study can be found in Sub-step 1-

    2. The professional fee for post-PPA activities ranges

    from 1.5% to 2.5% of the capital expenditure (CAPEX)

    As this sub-step is an interaction between the developer

    and consultant, there is no specific timeframe for

    finalising the contract.

    However, expediting the contract finalisation will keep

    project costs to a minimum and serve to limit any

    unforeseen cost escalation.

    References Challenges

  • RELATED LAWS AND REGULATIONS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    §

    Appointment of Technical Expert

    1-1

    Page 5/7

    Regulation No. Name

    Act

    No. 138 Year 1967

    Registration of Engineer Act

    This act describes the role of Professional Engineer. According to this act, the feasibility study (FS) is deemed

    “Professional engineering services” and must be performed by a registered professional engineer only.

    Description Documents Fee/Duration Regulations References Challenges

  • REFERENCE DOCUMENTS / SOURCES

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Appointment of Technical Expert

    1-1

    Page 6/7

    Document name Description

    SEDA Guidelines Guidelines and Determination of the Sustainable Energy Development Authority, Malaysia

    This guideline can be downloaded from the official website of SEDA

    Description Documents Fee/Duration Regulations References Challenges

  • CHALLENGES AND RISKS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Appointment of Technical Expert

    1-1

    Page 7/7

    Risk Details

    Poor consultation services Engaging inexperienced consultants can lead to poor implementation of the scheme and

    improper project planning.

    Sunk cost Improper site selection may lead to negative results, e.g., the initial site identified cannot be

    developed due to later findings, resulting in the need for the evaluation of more project sites.

    This will ultimately inflate sunk costs.

    Poor suppliers Unscrupulous suppliers and contractors may try to undermine the authority of and working

    arrangement with the consultant. The developer therefore must make clear the scope of work

    and deliverables with the consultant as well as the relationship with the suppliers and

    contractors. Regular checks must also be conducted to maintain the quality of work and ensure

    timely implementation of deliverables/activities.

    Description Documents Fee/Duration Regulations >References Challenges

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    DESCRIPTION RELATED AUTHORITIES

    Preliminary Survey and Preparation of Feasibility Study (FS)

    1-2

    Page 1/7

    Note 1: The submission of the FS to SEDA is done

    during the Feed-in approval holder (FiAH)

    application (described in Sub-step 3-2)

    This sub-step outlines the processes for conducting a feasibility study (FS) for the

    project. This must be done by the contracted consultant (Sub-step 1-1). The FS is to

    be carried out to check whether the development of a small hydropower (SHP) project

    is technically feasible and economically viable. The FS must be submitted to the

    Sustainable Energy Development Agency (SEDA), Malaysia as a part of required

    documents for the feed-in Approval Holder (FiAH) application (Sub-step 2-2) as

    required by the SEDA Guidelines. The FS will be required by various Financial

    Institutes as a basic document for financial closure.

    In Malaysia, the Registration of Engineer Act (Act 138) considers the preparation of a

    feasibility study (FS) as a “professional engineering service”. Therefore, it must be

    performed by a registered professional engineer only.

    Typically, a preliminary survey at the site must be performed in this sub-step as well.

    This is to ensure that the actual site conditions are suitable for project development.

    The project developer shall perform a desktop study and a preliminary site survey.

    They will form the basis of the input needed for the feasibility study (FS).

    Federal level Sustainable Energy

    Development Agency (SEDA)1

    – Review and evaluate the FS

    State

    government

    -

    Local

    government

    Local government office –Should be informed about the

    survey

    Description Documents Fee/Duration >Regulations References Challenges

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    DESCRIPTION

    The scope of the preliminary survey should cover the following aspects, at minimum:

    Check potential locations, accessibility and availability of:

    Water intake

    Waterway route

    Powerhouse

    Transmission route

    Power injection point

    Electricity demand and load patterns

    General geological makeup / features of the site

    Collecting other necessary input which will be necessary for the Power System Study (PSS) to be conducted later (see Sub-step

    1-3)

    A more detailed survey must also be completed but can be executed at a later stage (see Sub-step 1-4)

    Preliminary Survey and Preparation of Feasibility Study (FS)

    1-2

    Page 2/7Description Documents Fee/Duration Regulations References Challenges

  • REFERENCE DOCUMENTS / SOURCES

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Preliminary Survey and Preparation of Feasibility Study (FS)

    1-2

    Page 3/7Description Documents Fee/Duration

    Technical Analysis

    The technical analysis aspect of the FS should consist of the

    following information / data as a minimum requirement:

    Project description

    A brief description of the project objective and intended output /

    results.

    Hydrology data of proposed project site

    i.e. rainfall statistics, water discharge, flow duration curve, etc.

    Geological assessment of the project site

    Assessment of geological information and its impact on the operation

    of the project and end user.

    Installed capacity [kW or MW] and estimated power

    generation [GWh] from the proposed project

    Conceptual design

    i.e. intake, waterway, powerhouse, electromechanical equipment,

    transmission, interconnection facilities, etc.

    Economic Analysis

    The economic analysis, a vital component of the FS, should

    consist of the following basic information / data:

    Basic economic analysis, methodology and approaches

    Cash flow calculation

    Internal rate of return (IRR) analysis

    For debt financing, IRR should be more than 10%. For equity

    financing, IRR should be more than 12%.

    Payback period calculation

    For debt financing, expected payback period should be around 8

    years. For equity financing, expected payback period should be

    around 7 years.

    Debt service coverage ratio (DSCR) calculation

    DSCR should be kept above 1.3 at all times

    Regulations References Challenges

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    Preliminary Survey and Preparation of Feasibility Study (FS)

    1-2

    Page 4/7Description Documents Fee/Duration

    The service cost for FS preparation and finalisation

    (including associated preliminary site survey) depends

    on proposed project location, project size, etc.

    Typical ranges are:

    Lower end RM 100,000

    (~ USD 24,000)

    Higher end RM 300,000

    (~ USD 72,000)

    Conduction and finalisation of the FS may take around 3

    months. However, the duration of the Feasibility Study

    depends on a variety of factors, including but not limited

    to: viz. project size, technology opted, location, social

    factors, etc.

    Regulations References Challenges

  • RELATED LAWS AND REGULATIONS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    §

    Preliminary Survey and Preparation of Feasibility Study (FS)

    1-2

    Page 5/7

    §

    Regulation No. Name

    Act

    No. 138 Year 1967

    Registration of Engineer Act

    This act describes the role of Professional Engineer. According to this act, the feasibility study (FS) is considered as

    “Professional Engineering Services” and must be performed by a registered professional engineer only.

    Description Documents Fee/Duration Regulations References Challenges

  • REFERENCE DOCUMENTS / SOURCES

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Preliminary Survey and Preparation of Feasibility Study (FS)

    1-2

    Page 6/7Description Documents Fee/Duration

    Document name Description

    SEDA Guideline Guidelines and Determination of the Sustainable Energy Development Authority Malaysia

    This guideline can be downloaded from the SEDA website (www.seda.gov.my)

    FiT Application form Feed-in Tariff (FiT) application form

    This guideline can be downloaded from the SEDA website (www.seda.gov.my)

    Regulations References Challenges

    http://www.seda.gov.my/http://www.seda.gov.my/

  • CHALLENGES AND RISKS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Preliminary Survey and Preparation of Feasibility Study (FS)

    1-2

    Page 7/7Description Documents Fee/Duration >Regulations References Challenges

    Risk Details

    Poor FS Incomplete data and inexperienced consultants can lead to poorly prepared FS and

    subsequently a refusal of proposal by banks.

    Sunk Cost There is a risk of sunk cost for FS, third party soil survey costs to the project developer in case

    it turns out CAPEX is too high for realisation.

    Change of PSS Delays in completing the FS report due to various unforeseen challenges may affect the

    completion of the Power System Study (PSS). Thus, investors are encouraged to engage a

    PSS consultant at the earliest opportunity to ensure the power evacuation and required findings

    can be determined to complete the FS in a timely manner.

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    DESCRIPTION RELATED AUTHORITIES

    Preparation of Power System Study (PSS)

    1-3

    Page 1/7

    Federal level None

    State

    government The respective distribution

    licensee (DL) – Review the application, nominate a PSS

    consultant.Local

    government

    Description Documents Fee/Duration >Regulations References Challenges

    After the project has been determined, the project developer must conduct a

    Power System Study (PSS). The purpose of the PSS is to identify the feasible

    interconnection options for the proposed development of the off-taker’s electricity

    grid. It sets the technical and safety requirements for the interconnection and

    operation of the RE power plant.

    The PSS indicates the stability and load demand/absorption of the nearest viable

    grid injection point. Load flow and a short circuit analysis are included as parts of

    the study to ensure that the proposed scheme operation is within the limits set by

    the electricity transmission/grid code.

    According to Technical and Operation Rules (P.U.(A) 120) of the Renewable

    Energy Act 2011, the PSS is required for projects with an installed capacity of 425

    kW and above. Upon receiving approval by the respective Distribution Licensee

    (DL), the Power System Study (PSS) is valid for one year. It can be extended by

    another year upon approval from SEDA. The extension requires additional

    payment of fees to the relevant authority. The PSS is a pre-requisite for an

    application for Feed-in Approval Holder (Sub step 2-2).

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    DESCRIPTION

    1-3

    Page 2/7

    Preparation of Power System Study (PSS)

    The procedure to be followed for the sub-step Power Step Study is as follows:

    1. The applicant submits application to respective DL; e.g., for areas which fall under TNB’s authority, the application shall be

    submitted to the TNB Renewable Energy unit (RE TNB)

    2. RE TNB (or DL) reviews completeness of the documents submitted and checks for the following:

    a. Documentation is in order and proper: RE TNB (or DL) issues order to developer for payment of application fee

    b. Developer pays required fees and submits proof of payment to TNB RE (or DL)

    c. RE TNB (or DL) after verifying payment details, nominates PSS consultant

    d. PSS consultant conducts Power System Study and submits report

    e. The Power System Study is one of the main steps for ensuring the success of project development, and due care is required

    for the success of the plant.

    Description Documents Fee/Duration Regulations >References Challenges

  • REQUIRED DOCUMENTS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Preparation of Power System Study (PSS)

    1-3

    Page 3/7Description Documents Fee/Duration Regulations

    The study focuses on the site conditions for a power system

    and its demand and supply has two major requirements. The

    following documents are to be prepared:

    Scheme location and plan

    Information on placing equipment and related plan

    Proposed equipment configuration

    Configuration of equipment to be installed along with their

    configuration

    Equipment parameters/characteristics

    Various parameters of equipment which allow for making decisions of

    the installed capacity and operation characteristics

    Other technical and site information

    Further to the above three aspects, any information which is relevant

    to future development of project development may be stated at this

    stage

    References Challenges

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    Preparation of Power System Study (PSS)

    1-3

    Page 4/7

    Note: The cost and duration data are based on market survey and an interview with project developer.

    Description Documents Fee/Duration Regulations

    The fees for the grant of a license are regulated by

    SEDA, Malaysia and are fixed. The fees are charged

    according to the size of the plant as given below:

    Above 425 kW and up to 1 MW

    (including 1 MW capacity)

    RM 20,000

    (~ USD 4660)

    Above 1 MW and up to 10 MW

    (including 10 MW capacity)

    RM 40,000

    (~ USD 9320)

    Conducting a Power System Study (PSS) usually takes

    around 2-3 months. However, several factors can

    influence the length of duration, e.g., the project size,

    applied technology, equipment availability in market,

    location, etc.

    References Challenges

  • RELATED LAWS AND REGULATIONS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    §

    Preparation of Power System Study (PSS)

    1-3

    Page 5/7

    Detailed Survey

    Regulation No. Name

    Legal Reference:

    PU (A) 120 RE

    Electricity Supply Act 1990

    P. U. (A) 120 RE (Technical and Operational Requirements) Rules 2014 of RE Act

    2011 (Act)

    Official Reference: TNB Transmission Grid Code

    TNB Distribution Grid Code

    TNB Technical Guidebook for the Inter-connection of Generation of Distribution

    Network

    Description Documents Fee/Duration Regulations References Challenges

  • REFERENCE DOCUMENTS / SOURCES

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    1-3

    Page 6/7Description Documents Fee/Duration Regulations References Challenges

    Preparation of Power System Study (PSS)

  • CHALLENGES AND RISKS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Preparation of Power System Study (PSS)

    1-3

    Page 7/7

    Challenges Recommendation

    Validity of Power System

    Study is limited

    An assessment of situation and next steps is recommended to complete formalities related to

    PSS.

    Delays in performing PSS

    may result in reanalysing

    PSS

    A pre-check of the situation and next steps is useful in ensuring timely submission of PSS.

    Timely submission of PSS will enable timely interconnection of conditions and in identifying

    location for the project.

    Description Documents Fee/Duration Regulations >References Challenges

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    DESCRIPTION

    1-4

    Page 1/5

    Detailed Survey

    The project developer must contract a licensed land surveyor to perform a detailed survey at the selected project site. In Malaysia,

    only a licensed land surveyor may conduct the survey. The purpose of this survey is to identify the topography and contours of the

    project site; this enables the project developer to identify potential locations for the facility and components. Identification of

    boundaries of the site location, establishment of a profile of the surrounding area, and demarcation survey are parts of sub-step 1-3.

    This survey aims to help in the development of a plan for the land acquisition process (Sub-step 2-4)

    There is no regulation governing the procedure in this sub-step. It is up to the developer to select a suitable approach to arriving at

    an agreement with a land surveyor. Typically, the procedures in identifying and contracting a land surveyor are as follows:

    The project developer prepares the Terms of Reference (TOR) to define the scope of work and sends it to potential surveyors.

    Interested surveyors submit a quotation to the project developer/investor. The quotation typically consists of the following:

    Financial proposal

    Detailed scope of work

    The project developer compares the quotations received and selects suitable surveyor for the survey work. To officially appoint

    identified surveyor, a letter of award shall be prepared and signed for documentation purposes.

    Description Documents Fee/Duration Regulations Challenges >

  • REQUIRED DOCUMENTS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Detailed Survey

    1-4

    Page 2/5Description Documents Fee/Duration Regulations Challenges

    The only document required for this stage is the Request for

    Proposal (RFP). There is no uniform template for RFP

    document. Typically, it should consist of the following:

    Project background

    Location of the project, possible RE technology

    Scope of works and responsibilities of the consultant

    Detailed tasks and expected results from the survey must be

    communicated.

    Contract timeframe including crucial milestones

    Project deadlines and milestones must be communicated.

    List of deliverables

    Reports and necessary drawings, documents must be clearly

    mentioned.

    Other terms and conditions (T&C)

    Additional terms and conditions necessary for a successful survey.

  • Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    Detailed Survey

    1-4

    Page 3/5

    Note: The cost and duration data are based on market survey and an interview with project developer.

    Description Documents Fee/Duration Regulations Challenges

    The service cost for conducting a detailed survey is not

    regulated. This is based on the agreement and

    negotiations between two private businesses. It depends

    on a project’s size, the location to be surveyed, and

    many other factors.

    Typically, a project developer can expect the cost to be

    between:

    Lower range RM 250,000

    (~ USD 60,000)

    Higher range RM 400,000

    (~ USD 95,050)

    Conducting a detailed site survey usually takes around

    2-4 months. However, several factors can influence the

    actual duration and may lengthen or shorten it, e.g.,

    project size, applied technology, location, etc.

  • RELATED LAWS AND REGULATIONS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    §

    Detailed Survey

    1-4

    Page 4/5

    Detailed Survey

    Regulation No. Name

    ACT 486 Land Acquisition Act

    National Land Code

    Description Documents Fee/Duration Regulations Challenges

  • CHALLENGES AND RISKS

    Step 1 | Site Selection / Evaluation

    Overall OverallTOC Step Step

    ><

    Sub-step

    Detailed Survey

    1-4

    Page 5/5

    Challenges Recommendation

    Small hydro sites are usually

    located in remote areas and/or

    dense jungles. Thus the working

    environment can be very

    challenging and tough. This can in

    turn lead to delays.

    It is imperative to have experienced licensed surveyors who possess sufficient

    manpower. It is also a good idea to engage them early on in the implementation process.

    The project site and access to said site must be well informed for necessary planning and

    co-ordination.

    Local communities in some areas

    may object to the surveyor

    carrying out surveys.

    Engage with the local communities early on. Preferably, initial site visits can be co-

    ordinated on by respective local officials. Joint briefing and presentations on the benefits

    of the project and work to be carried out may also be shared with the affected

    people/local communities.

    Conflicting interests in land rights

    or instances where land sought

    cannot be acquired.

    To avoid such situations, a thorough check must be conducted during the initial phases of

    the Feasibility Study.

    Description Documents Fee/Duration Regulations Challenges >

  • Step 2 | Administrative Authorisation

    FCSSL

    CFL

    ADM

    EPL

    GCP

    PCN

    PPA

    OPM

    GCC

    FIN

    CFL

    Overall OverallTOC Step Step

    State Economic Planning Unit (EPU) Consent

    Applying for Feed-in Account Holder

    Local Authority Approval

    Land Acquisition Process for Government/State Land

    2-1

    2-2

    2-3

    2-4

    ADM (Gantt’s Chart)

    Gantt’s Chart Flow Chart More Details…

    Conditional sub-step

    Mandatory sub-step

    2-5Water Right Agreement

  • Step 2 | Administrative Authorisation

    FC

    Overall OverallTOC Step Step

    State Economic

    Planning Unit (EPU)

    Consent

    Local Authority

    Approval

    Water Right

    Agreement (WRA)

    2-1 2-2

    Land Acquisition Process

    for Government/State Land

    2-3

    ADM (Flow Chart)

    Gantt’s Chart Flow Chart More Details…

    2-4

    Applying for Feed-in

    Account Holder

    2-5

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    >

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Contd …….

    Land Acquisition Process for Government/State Land:

    Land acquisition approval is usually given by the state authority as it is unlikely for the Central/Federal Government to own land in

    rural or remote areas. Applications must be submitted to the relevant state authority; the review of documents is performed by the

    district government. Final approval and compensation values are given and determined by the State Executive Committee (EXCO).

    Water Rights Agreement:

    The water rights agreement (WRA) related to the payable water royalty and the environment/land use protection obligation of the

    state. It is a legally binding document between the state and the project developer.

    Step Description Page 2/2

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    DESCRIPTION RELATED AUTHORITIES

    Sub-step

    2-1

    State Economic Planning Unit (EPU) Consent

    Page 1/6

    This sub-step is for obtaining state consent for the right to develop a small

    hydropower project. As river and water rights are under the jurisdiction of the state,

    such consent is required when applying for feed-in approval holder (FiAH) with SEDA

    (see Sub-step 2-2).

    This step is usually performed in parallel with the Water Right Agreement (WRA)

    (Sub-step 2-5). However, in some states, the WRA will be issued as part of the EPU

    consent.

    According to the Act, the procedures are as follows:

    Project developer submits the filled-out forms and all supporting documents to

    the State EPU

    Joint site visit is to be conducted at the project site

    The developer delivers presentation to the development committee (chaired by

    State EPU chief)

    Federal level (none)

    State level State Economic Planning Unit

    (State EPU) – Evaluate the application, conduct a site visit,

    issue a consent letter

    Local Level (none)

    Description Documents Fee/Duration Regulations Challenges >

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    DESCRIPTION

    Sub-step

    2-1

    The State EPU sources comments and principal approval from the competent state technical departments

    The State EPU issues a consent letter with conditional approval terms

    In some states, the water rights agreement/terms are also given along with the EPU consent (Sub-step 2-5)

    State Economic Planning Unit (EPU) Consent

    Page 2/6Description Documents Fee/Duration Regulations Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-1

    State Economic Planning Unit (EPU) Consent

    Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.

    The developer must check with the EPU office in the respective state for the exact list.

    Page 2/6Description Documents Fee/Duration Regulations

    Filled-out application form

    The form can be obtained from the relevant state EPU office

    Layout plan of the project scheme

    Project description / feasibility study (FS) including:

    preliminary technical parameters

    economic analysis

    (refer to Sub-step 1-2)

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    2-1

    State Economic Planning Unit (EPU) Consent

    Note: Indicated fee in USD is only approximate based on the currency conversion of USD 1 = PHP 3.27 (as of October 2014)

    Page 3/6Description Documents Fee/Duration Regulations

    The processing fee is calculated per location. It varies

    from state-to-state (in some states, there is no fee).

    Lower end No fee

    Higher end RM 10,000

    (~ USD 2,500)

    Typically, this sub-step can take around 3 - 12 months.

    The exact processing time depends on the state and the

    completeness of the documents being submitted.

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-1

    Page 4/6Description Documents Fee/Duration Regulations

    Regulation No. Name

    Act 172

    (1976)

    Town and Country Panning Act (1976)

    State Economic Planning Unit (EPU) Consent

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    CHALLENGES AND RISKS

    2-1

    State Economic Planning Unit (EPU) Consent

    Page 6/6Description Documents Fee/Duration Regulations >Challenges

    Risk Details

    Rejection from the State EPU The State EPU may reject applications at this stage after the developer has already invested

    considerable time and money in conducting a preliminary study, e.g., feasibility study (FS), site

    visit, PSS, etc.

    Challenges Details Recommendation

    Time-consuming

    Procedure

    The process of obtaining Economic Planning Unit

    (EPU) consent may take longer than expected due to

    unexpected issues, e.g., conflicts of interest among

    several parties aiming to use the same project site for

    different purposes (agriculture, mining, etc.)

    Project developer should frequently meet

    and discuss with the State EPU offices to

    expedite approval / consent. It is

    recommended that the developer assign a

    dedicated team/persons to handle this

    issue.

    To follow-up on this challenge a dedicated

    team may be assigned.

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    DESCRIPTION RELATED AUTHORITIES

    Sub-step

    2-2

    Apply for Feed-in-Account Holder (FiAH)

    Page 1/7

    This sub-step is on obtaining a Feed-in-Account. An individual who is a citizen of

    Malaysia or a company which is majority-owned by a Malaysian or owned outright by

    a Malaysian citizen can apply for a Feed-in approval certificate. The approved Feed-

    in certificate can be obtained from SEDA.

    The application for a Feed-in-Account can be applied for online by providing the

    required information and also by submitting a hard copy of the filled-out form.

    Required fees must be paid along with the application form.

    Valid proof of payment for a FiAH certificate can be obtained from SEDA, provided

    the application has been approved.

    The final decision on approval is subject to available quota for FiT.

    Holder of a Feed-in certificate is eligible to sell Renewable Energy at the Feed-in-

    Tariff (FiT) rate as stipulated by SEDA as set out in the RE Act 2011.

    Federal level Sustainable Energy

    Development Authority

    (SEDA), Malaysia

    State level (none)

    Local Level (none)

    Description Documents Fee/Duration Regulations Challenges >

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-2

    Apply for Feed-in-Account Holder (FiAH)

    Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.

    The developer must check with the EPU office in the respective state for the exact list.

    Page 2/7Description Documents Fee/Duration Regulations

    Profile Registration Document

    The latest audited accounts of the applicant

    The memorandum and articles of applicant’s association

    Form 8 (Certificate of Incorporation of Public Company) or

    Form 9 (Certificate of Incorporation of Private Company) in connection with the Applicant under the Companies Act 1965

    All Forms 24 (Return of Allotment of Shares) lodged by the applicant with the Registrar of Companies under the Companies Act 1965

    The latest Form 49 (Return giving particulars in Register of Directors, Managers and Secretaries and change of particulars) lodged by the

    applicant with the Registrar of Companies and a written confirmation from the company’s secretary on the current shareholding of the applicant

    A Share-holding/Ownership Structure Diagram; detailing the shareholding percentages of each ultimate shareholder in the company

    Copy of the MyKad of each individual shareholder in the company; or, a certified copy of Form 24 and 49 of each shareholder (if the

    shareholder is a company) by the company’s secretary and confirmation letter from the company’s secretary confirming the list of shareholders

    Certified copies of Form 24 and 49 of the company(s) where each ultimate shareholder has a shareholding percentage, direct or indirect

    An extract of the company’s board resolution authorising the applying person to make present an application on behalf of the applicant and to

    execute and submit all document in relation thereto

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-2

    Apply for Feed-in-Account Holder (FiAH)

    Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.

    The developer must check with the EPU office in the respective state for the exact list.

    Page 3/7Description Documents Fee/Duration Regulations

    Profile of the applicant together with CVs of the Project management team

    Submit hard copy of the Feed-in-Approval form and supporting documents:

    Application Form

    Declaration Form

    Summary of the application according to template from SEDA

    Certified Feasibility Study (by Professional Engineer)

    Power System Study report and letter of approval from RE TNB/DL

    List of FiA held by the applicant, both past and present

    Documents supporting ownership of the site of EPU consent letter (Step 2-1)

    Certificate of registration of each qualified person with the Board of Engineers, Malaysia as a Professional Engineer (Electrical)

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-2

    Apply for Feed-in-Account Holder (FiAH)

    Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.

    The developer must check with the EPU office in the respective state for the exact list.

    Page 4/7Description Documents Fee/Duration Regulations

    Projects requiring loan from bank or financiers are to be supported by the following documents:

    Financing agreement with the entity(ies) that will provide or has provided financing to the applicant for the

    project, or

    Letter of intent/offer letter(s)/financing term sheet(s) from the entity(ies) that will be or has/have provided

    financing to the applicant for the project

    For self-financed projects, relevant documents confirming the financial capacity (e.g., bank account statement showing credit balance of at

    least equivalent to the total capital cost of the RE installation)

    For all cases, the applicant must show proof of funds of at least 5% of the capital expenditure in the form of liquid assets

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    2-2

    Apply for Feed-in-Account Holder (FiAH)

    Note: Indicated fee in USD is only approximate based on the currency conversion of USD 1 = PHP 3.27 (as of October 2014)

    Page 5/7Description Documents Fee/Duration Regulations

    The processing fee is decided by SEDA and must be

    paid to SEDA Malaysia

    Processing Fees with each

    submission

    RM 1000

    Earnest Money

    Issued in the form of bankers cheque (RM

    100/MW) and payable to SEDA. The

    earnest money is reimbursable within 21

    days upon issuance of result/s

    RM 100 per MW

    Typically, this sub-step can take around 2 weeks. The

    exact processing time depends on the completeness of

    the application form and supporting documents.

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    RELATED LAWS AND REGULATIONS§

    2-2

    Local Authority Approval

    Page 6/7Description Documents Fee/Duration Regulations

    Regulation No. Name

    Act 725 Renewable Energy Act (Act 725)

    Act 726 SEDA Act (Act 726)

    Apply for Feed-in-Account Holder (FiAH)

    Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    CHALLENGES AND RISKS

    2-2

    Apply for Feed-in-Account Holder (FiAH)

    Page 7/7Description Documents Fee/Duration Regulations >Challenges

    Risk Details

    Rejection from the SEDA SEDA may reject applications for FiAH due to non-submission of all documents. At this stage the

    developer may have already invested considerable time and money in performing a preliminary study,

    e.g., feasibility study (FS), site visit, PSS, etc.

    Challenges Details Recommendation

    Application rejected Application may be rejected due to non-conformity to

    document requirements

    A thorough check must be conducted

    when preparing the application form

    Large number of applications received by SEDA Timely application for FiAH along with

    proper documentation

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    DESCRIPTION

    Sub-step

    2-3

    This section describes the procedure for obtaining approval from the local authority(ies) for the physical construction of the power

    plant. This approval is usually referred to as Development Order (DO). It grants planning permission with or without conditions for

    any development specified in the order;

    As this sub-step is about obtaining a permit from the local government, the exact procedure may differ slightly from state-to-state

    (province). Some states have one-stop service agencies to handle the applications and permits.

    In such cases, the project developer must submit an application to the State Department of Town and Country Planning. This

    department serves as an One Stop Centre (OSC). It will co-ordinate with other involved agencies and departments to obtain all

    relevant approval for remaining comments. In case any comment is provided, the developer must revise the document accordingly

    and resubmit.

    However, in states where one-stop service has not yet been implemented, the project developer must approach each individual

    local authority in order to obtain the necessary approval.

    Local Authority Approval

    Page 1/7Description Documents Fee/Duration Regulations References Challenges >

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    RELATED AUTHORITIES

    2-3

    Local Authority Approval

    Note:

    Page 2/7

    Central level (None)

    Provincial level State Department of Town and Country Planning – Receive the application and supporting documents, co-ordinate with various agency to obtain their approval or comments (in case one-stop service system has already been implemented)

    Other relevant authorities at the state level – Review the application, grant approval or comments

    State Department of Environment (DOE)

    State Mineral and Geosciences Department

    State Department of Forestry

    Local level Other relevant authorities in the local level – Review the application, grant approval or comments Land and Mining District Office

    District Office (DO)

    Public Work Department (PWD)

    Drainage and Irrigation Department (DID)

    Tenaga Nasional Berhad (TNB)

    Indah Water Konsortium (IWK) - (Sewarage)

    District Water Board Office

    District/Town Council

    Fire and Rescue Department

    Description Documents Fee/Duration Regulations References Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-3

    Local Authority Approval

    Page 3/7Description Documents Fee/Duration Regulations References Challenges

    The exact list of documents differ from state-to-state. All

    drawings, plans, and reports must be properly endorsed by

    registered professional engineers. Typically, the project

    developer is requested to submit the following documents:

    Filled-out submission forms

    Layout plan

    Contour plan for the project site

    Proposed power plant development report or a

    Feasibility Study report

    Refer to Sub-step 1-2

    Drainage report based on the Storm Water Management

    Manual (MSMA) of DID

    Hydraulic and Hydrology report

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    2-3

    Local Authority Approval

    Note: Generally for small hydropower plant, the processing would sum up to be between RM 1500 and RM 2000 (~ USD 470 – USD 625) in total.

    Page 4/7Description Documents Fee/Duration Regulations References Challenges

    The processing fee is regulated by each state

    individually. However, the developer can estimate the

    fee based on the following:

    Typically, the fee is calculated

    from the project area

    It is a one-off payment, for small

    hydropower schemes this ranges

    between RM 1500- RM 2000 (USD

    350 – USD 450)

    RM 0.10 per m2

    (~ USD 0.03 per m2)

    As there are several relevant permits needed for this

    sub-step, it is difficult to determine an exact timeframe.

    Typically, the entire process takes around 3 - 6 months.

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    RELATED LAWS AND REGULATIONS§

    2-3

    Local Authority Approval

    Local Authority Approval

    Page 5/7Description Documents Fee/Duration Regulations References Challenges

    Regulation No. Name

    Act 172 (1976) Town and Country Panning Act

    Act 138 (1967) Registration of Engineers Act

    Uniform by-laws as notified from time to time and location specifics

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-3

    Local Authority Approval

    Page 6/7

    Document Name Description

    Standard forms Based on the state/province or local authority

    Guidelines Based on the state/province or local authority

    Description Documents Fee/Duration Regulations References Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    CHALLENGES AND RISKS

    2-3

    Local Authority Approval

    Local Authority Approval

    Page 7/7Description Documents Fee/Duration Regulations References Challenges >

    Risk Details

    Rejection from the

    authority

    Certain agencies may reject the small hydropower project, leading to additional delays. There is a

    risk of sunk cost as a feasibility study and site survey may have already been performed.

    Challenges Details Recommendation

    Coordination with related

    authority

    Some agencies may give comments and

    responses based on the normal urban

    building requirement which may not be

    applicable for SHP development

    The project developer must engage with relevant

    departments, through their technical consultants or

    engineers, as early as possible. Some dedicated

    presentations and discussions coupled with site

    visits may be needed to facilitate the process.

    Long lead time Long lead times during the approval process.

    There is no clearly defined deadline on the

    processing time for all authorities involved.

    It is recommended to start the process early and

    hold frequent meetings, communicate regularly and

    hold follow-up discussions.

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    DESCRIPTION RELATED AUTHORITIES

    Sub-step

    2-4

    Land Acquisition Process for Government/State Land

    Page 1/7

    Land acquisition approval is usually given by the state authority as it is unlikely for the

    Central/Federal Government to own land in rural or remote areas. Thus, applications

    must be submitted to the state authority. A review of the documents submitted is then

    performed by the district government. Final approval and compensation values are

    given and determined by the State Executive Committee (EXCO).

    The applied procedure is as follows:

    The project developer submits the demarcation/land acquisition plans (LAP) to

    the state authorities using the standard application form(s)

    Review of the plans performed by district offices. Comments and/or approval

    will be submitted to the developer.

    The developer reviews and amends drawings/plans based on comments

    The revised documents are tabled at the EXCO meetings and approval given

    with compensation values

    Contd..

    Related Authority

    Central level (none)

    Provincial

    government

    State Land/ Mining Office and

    Forest Department

    Local

    government

    District Land Office and Forest

    Department

    Description Documents Fee/Duration Regulations References Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    DESCRIPTION

    Sub-step

    2-4

    The state authorities such as the Land/Mining office or the Forest Department notify the developer on the compensation

    values

    If the developer is not satisfied with the compensation amount, he/she can appeal to the EXCO

    Land Acquisition Process for Government/State Land

    Page 2/7Description Documents Fee/Duration Regulations References Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-4

    Page 3/7

    Land Acquisition Process for Government/State Land

    The exact list of documents required differs from state-to-

    state. Typically, the project developer is requested to submit

    the following documents:

    Filled-out application form(s)

    Demarcation plans or land acquisition plans (LAP)

    Description Documents Fee/Duration Regulations References Challenges

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    2-4

    Land Acquisition Process for Government/State Land

    Note 1: There may be additional fees for joint site visits for tagging and identifying forest trees/logs for compensation estimation.

    Page 4/7Description Documents Fee/Duration Regulations References Challenges

    The processing fee is regulated by each state

    individually. However, the developer can expect the fee

    to range between the following:

    Lower endnote1 RM 1,500

    (~ USD 412)

    Higher endnote1 RM 5,000

    (~ USD 1,374)

    As several permits are relevant, it is difficult to determine

    the specific time needed for this sub-step. Typically, the

    entire process takes around 6 - 18 months

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    RELATED LAWS AND REGULATIONS§

    2-4

    Land Acquisition Process for Government/State Land

    Land Acquisition Process for Government/State Land

    Page 5/7Description Documents Fee/Duration Regulations References Challenges

    Regulation No. Name

    Act 486 (1992) Land Acquisition Act (Act 486)

    - National Land Code

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REFERENCE DOCUMENTS / SOURCES

    2-4

    Land Acquisition Process for Government/State Land

    Page 6/7Description Documents Fee/Duration Regulations References Challenges

    Standard application forms

    This form must be obtained directly from the state authorities

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    CHALLENGES AND RISKS

    2-4

    Land Acquisition Process for Government/State Land

    Page 7/7Description Documents Fee/Duration Regulations References Challenges

    Risk Details

    Unable to acquire the land The state may reject the project in this stage after considerable efforts have already been invested.

    Challenges Details Recommendation

    Time-consuming

    procedure

    This sub-step requires the most time, apart

    from the construction period

    To obtain approval as soon as possible, early

    submission is imperative. It is recommended to

    assign a dedicated team to handle and engage

    various authorities and offices from the outset to

    ensure a speedy process

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    DESCRIPTION RELATED AUTHORITIES

    Sub-step

    2-5

    Water Rights Agreement (WRA)

    Page 1/3

    A water rights agreement (WRA) is a legally binding document between the state and

    the project developer pertaining to the payable water royalty and the

    environment/land use protection obligation of the state. Sometimes, the WRA is given

    when the state principal approvals are obtained (Sub-step 2-1).

    The WRA is usually part of the state EPU approval for small hydro. However, in some

    states, the WRA is to be performed separately but in parallel with the obtaining

    process for the state EPU consent.

    Description Regulations Challenges

    Federal level (none)

    State level State Economic Planning Unit

    (State EPU) – Evaluate the application and grant the WRA

    Local level (none)

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    2-5

    Water Rights Agreement (WRA)

    Page 2/3Description Regulations Challenges

    Regulation No. Name

    Act 171 (1976) Local Government Act (Act 171)

    - Various state By-laws

  • Step 2 | Administrative Authorisation

    Overall OverallTOC Step Step

    ><

    Sub-step

    CHALLENGES AND RISKS

    2-5

    Water Rights Agreement (WRA)

    Page 3/3Description Regulations Challenges

    Challenges Details Recommendation

    High fee The initial royalty rates may be a bit high and may

    affect the economic viability of the scheme. The

    comparative rate is set independently by each state

    where SEDA does not play a role in regulating.

    The developer is to appeal and negotiate

    on the rate to ensure fair returns for both

    parties

  • Step 3 | Power Purchase Agreement

    FCSSL

    CFL

    ADM

    EPL

    GCP

    PCN

    PPA

    OPM

    GCC

    FIN

    CFL

    Overall OverallTOC Step Step

    Renewable Energy Power Purchase Agreement (REPPA)

    PPA (Gantt’s Chart)

    3-1

    Gantt’s Chart Flow Chart More Details…

  • Step 3 | Power Purchase Agreement

    FC

    Overall OverallTOC Step Step

    Renewable Energy

    Power Purchase

    Agreement (REPPA)

    3-1

    PPA (Flow Chart)

    Gantt’s Chart Flow Chart More Details…

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    >

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    ><

    DESCRIPTION RELATED AUTHORITIES

    Sub-step

    3-1

    Renewable Energy Power Purchase Agreement (REPPA)

    Page 1/7

    This sub-step covers the procedures for obtaining a signed Renewable Energy

    Power Purchase Agreement (REPPA) from the Distribution License (DL).

    The REPPA for small hydropower installations with a capacity up to 10 MW is

    different from the REPPA for small hydropower installations with a capacity above

    10 MW. REPPA for SHP on a larger scale (10 – 30 MW) has 2 critical differences

    from the REPPA for SHP installations smaller than 10 MW. These are:

    A delayed implementation of the SHP project without an approved extension

    of time for COD will face liquidated damage (RM 1,000 or ~ USD 306) from

    the off-taker (the DL). The liquidated damage depends on the duration of

    delay and may be as high as 70% of the declared energy generation.

    A SHP installation generating less than 70% of the declared average annual

    energy (AAE) in the REPPA will be charged a penalty (the calculated formula

    is given in the REPPA, also see note) The penalty may amount to a sum,

    equivalent to up to 70% of the declared energy generation.

    Note: The determination penalty is regulated. The

    calculation formula is given in the REPPA. It is: LD =

    DC x [ (0.7 x DAA) – MRE ] x 1000, where LD is the

    sum in RM payable by the Feed-in Approval Holder

    to the Distribution Licensee, DC is the prevailing

    displaced cost (in RM/kWh), DAA = the Declared

    Annual Availability (in MWh) of such Contract Year,

    and MRE = the aggregate Metered Renewable

    Energy (in MWh) generated by the Renewable

    Energy Installation for every hour of each day

    Description Documents Fee/Duration Regulations References Challenges

    Central

    government

    SEDA

    Provincial

    government

    (none)

    Local

    government

    (none)

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    ><

    DESCRIPTION

    Sub-step

    3-1

    Renewable Energy Power Purchase Agreement (REPPA)

    Page 2/7

    The applied procedures are as follows:

    The project developer submits the documents to the respective DL

    The DL reviews the completeness of the submitted documents

    The developer and the DL jointly sign the Renewable Energy PPA (REPPA)

    Description Documents Fee/Duration Regulations References Challenges

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    ><

    Sub-step

    REQUIRED DOCUMENTS

    3-1

    Renewable Energy Power Purchase Agreement (REPPA)

    Page 3/7Description Documents Fee/Duration Regulations References Challenges

    Filled-out REPPA document

    Form HP 1 – for small hydropower plant up to 10 MW

    Form HP 2 – for small hydropower plant above 10

    MW and up to 30 MW.

    3 sets of REPPA are required. The standard form of REPPA can be

    downloaded from the official website of the Sustainable Energy

    Development Authority (SEDA) at www.seda.gov.my

    FiAH certification

    Refer to Sub-step 2-2

    Supporting documents as appendices of REPPA

    Description of the SHP plant

    Description of interconnection facilities and the

    connection point

    Description of communication facilities

    The list of appendices are according to the REPPA standard list

    http://www.seda.gov.my/

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    ><

    Sub-step

    FEES / COST DURATION

    3-1

    Renewable Energy Power Purchase Agreement (REPPA)

    Page 4/7Description Documents Fee/Duration Regulations References Challenges

    There is no fee for this sub-step This sub-step usually takes around 2 to 3 months

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    ><

    Sub-step

    RELATED LAWS AND REGULATIONS§

    3-1

    Renewable Energy Power Purchase Agreement (REPPA)

    Page 5/7

    Regulation No. Name

    Act 725 (2011) Renewable Energy Act (Act 725)

    Act 726 (2011) Sustainable Energy Development Authority (SEDA) Act (726)

    Description Documents Fee/Duration Regulations References Challenges

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    ><

    Sub-step

    REFERENCE DOCUMENTS / SOURCES

    3-1

    Renewable Energy Power Purchase Agreement (REPPA)

    Page 6/7Description Documents Fee/Duration Regulations References Challenges

    Guidelines and Determination of the Sustainable Energy Development Authority Malaysia

    This guideline is known as “SEDA Guidelines”. It can be downloaded from the SEDA website (www.seda.gov.my)

    Official REPPA form (Form HP 1)

    Form HP 1 is for small hydropower plants of up to 10 MW. It can be downloaded from the SEDA website (www.seda.gov.my)

    Official REPPA form (Form HP 2)

    Form HP 2 is for small hydropower plants above 10 MW and up to 30 MW. It can be downloaded from the SEDA website (www.seda.gov.my)

    http://www.seda.gov.my/http://www.seda.gov.my/http://www.seda.gov.my/

  • Step 3 | Power Purchase Agreement

    Overall OverallTOC Step Step

    ><

    Sub-step

    CHALLENGES AND RISKS

    3-1

    Renewable Energy Power Purchase Agreement (REPPA)

    Page 7/7Descr