renewable energy guideline on small hydropower project ... · the re guideline aims to document the...
TRANSCRIPT
-
E-Guidebook, 1st EditionSeptember 2016
Renewable Energy Guideline on
Small Hydropower Project Development in Malaysia
Up to 30 MW
Implemented by:
-
Disclaimers
RE-Guidelines for Small Hydropower development in Malaysia are developed by Renewable Energy Support Programme for ASEAN (ASEAN-RESP), a jointly implemented project by
ASEAN Centre for Energy *ACE) and GIZ. ASEAN-RESP is a regional project implemented on behalf of Federal Ministry for Economic Cooperation and Development (BMZ).
Highest effort has been given to ensure and maintain accuracy of the Guidelines. Regulations and procedures for RE project development in Malaysia are complex, include numerous
actors and are likely to be changed or updated over time. It is therefore not possible to cover all aspects and eventualities of RE project development with these Guidelines. Highest
efforts have been made to maintain the accuracy of existing processes however, GIZ and its implementing partners cannot be held responsible for any error and misuse of the
Guidelines. The Guidelines shall not, in any case, replace or be used instead of existing laws, regulations and official guidelines issued by the relevant authorities in Malaysia.
Imprint
Authors
Ir. Shan Suleiman, Khairunisa Shan (SSM Associates, Malaysia)
International Consultants
Jan Benjamin Spitzley (Eclareon, Germany), Dr. Matthias Eichelbrönner (E.Quadrat, Germany)
Editors
Ms. Azah Ahmad (SEDA), Arne Schweinfurth, Thachatat Kuvarakul, Dr Anant Shukla, Ms. Maria-José Poddey
Design & Layout
Thachatat Kuvarakul, Stephanus Widjanarko, Intan Cinditiara (GIZ)
Publisher
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH in a joint initiative of:
Sustainable Energy Development Authority Malaysia (SEDA)
Renewable Energy Support Programme for ASEAN (ASEAN-RESP)
ASEAN Centre for Energy (ACE) under Renewable Energy Support Programme for ASEAN (ASEAN-RESP)
Kuala Lumpur, September 2016
www.ssmassociates.com.my
www.eclareon.com
www.equadrat-gmbh.de
-
Overall OverallTOC
><
Foreword
Page 1/4>
2011 was a transformative year for the development of renewable energy in Malaysia
with the passing of the Renewable Energy Act [Act 725] and the Sustainable Energy
Development Authority Act 2011 [Act 726]. This in turn ushered in the establishment of
the Sustainable Energy Development Authority (SEDA) Malaysia.
As a statutory body under the direct supervision of the Ministry of Energy, Green
Technology and Water Malaysia, SEDA operates under 5 strategic thrusts as meted out
in the National Renewable Energy Policy and Action Plan (2010) and is primarily
responsible for sustaining the renewable energy agenda in the country. The core
function of SEDA concerns the implementation of the Feed-in Tariff (FiT) mechanism as
a means to foster growth in the nation’s renewable energy (RE) market.
SEDA recognises the potential of small hydro and thus includes it as one of the
resources under the FiT portfolio. The strength of small hydro lies in the maturity of the
technology, and as the cost of harnessing said technology is marginal, small hydro has
the potential to provide electricity at a very reasonable rate. Moreover, small hydro is a
clean form of electricity generation, and being small means minimising one’s ecological
footprint. Not only that, hydro systems also possess a high capacity factor, as well as
the potential to help balance the energy market.
Sustainable Energy Development Authority (SEDA)
Malaysia
Ms. Catherine Ridu
Chief Executive OfficerSEDA Malaysia
-
Overall OverallTOC
><
Foreword
In order for the small hydro market to grow, it is important to develop soft infrastructure
such as human capital to support the industry. In this regard, SEDA is also responsible for
providing a conducive environment as a means to support sustainable development of the
small hydro industry; this includes providing competency development training for small
hydro industry players. SEDA also holds workshops and dialogue sessions for its
stakeholders to ensure transparency on the administrative procedures that uphold the
good governance practiced at SEDA Malaysia.
As such, SEDA Malaysia supports the ASEAN Centre for Energy (ACE) and Deutsche
Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH in their joint effort to develop
this Renewable Energy Guideline on Small Hydropower Project Development in Malaysia
up to 30 MW.
As Malaysia is one of the active members supporting the ASEAN RE agenda, we hope
that this guideline will help deepen the talent pool regarding the development of small
hydro systems both in Malaysia and around the ASEAN region. We hope this guideline
will be beneficial to all potential developers and investors aspiring to develop small
hydropower projects in Malaysia.
Ms. Catherine Ridu,Chief Executive Officer, SEDA
Page 2/4
-
Overall OverallTOC
><
Foreword
Page 3/4
Dr. Sanjayan Velautham
Principal Advisor ASEAN-RESP, GIZ
Malaysia, as one of the front runners in terms of renewable energy (RE) technology implementation
in ASEAN, aspires to achieve targets laid down in the ASEAN Plan of Action for Energy
Cooperation (APAEC) 2016 – 2025, i.e. 23 % share of RE by the year 2025 in ASEAN Energy Mix.
In addition to promote increased share of RE in total energy mix, Malaysia aims to reduce
greenhouse gas emissions by 45% of GDP until 2030, based on the levels of 2005.
Malaysia incorporated RE as early as 1980 with the introduction of Solar Photovoltaic System for
rural electrification. After 21 years, RE was formally adapted in April 2001 under the Five Fuel
Policy with the 8th Malaysia Plan. In 2011, Malaysia established the National Renewable Energy
Policy and Action Plan (NREPAP), which enabled acts viz. Renewable Energy Act 2011 and the
Sustainable Energy Development Act 2011. This resulted in the introduction of Feed-in Tariff (FiT)
and other measures to promote the use of RE.
Successively, Malaysia introduced various financial incentives and strategies such as the FiT
mechanism, Green Technology Financing Scheme (GTFS), Facilitation Fund from TERAJU,
UKAS/PPCU and Pioneer Status/Investment Tax Allowance among others.
The Renewable Energy Support Programme for ASEAN (ASEAN-RESP) - a jointly implemented
programme by the ASEAN Centre for Energy (ACE) and the Deutsche Gesellschaft für
Internationale Zusammenarbeit (GIZ) GmbH on behalf of the Federal Ministry for Economic
Cooperation and Development (BMZ) - is actively supporting ASEAN Member States (AMS)
through various measures. These measures include capacity building, training and Focus Group
Discussions with stakeholders and actors in both the region and worldwide. One such activity is to
streamline the procedures for permitting/approving projects in AMS. In this direction, the
Sustainable Energy Development Authority (SEDA) of Malaysia and ASEAN-RESP have
developed this RE Guideline on Small Hydropower (SHP) Project Development in Malaysia. This
guideline presents an overview of steps involved in the implementation of SHP projects.
>
Executive DirectorASEAN Centre for Energy
Maria-José Poddey
Joint Co-operation on ASEAN-RESP
-
Overall OverallTOC
><
Foreword
Page 4/4
Dr. Sanjayan Velautham
The RE Guideline aims to document the existing permits and steps involved in the implementation
of SHP projects in Malaysia in an easy-to-use and concise format. The Guideline provides an
overview of the various steps involved and approval required from concerned departments or
authorities. The RE Guideline provides a means to improve, strengthen and further the
development of SHP in Malaysia. The RE Guideline intends to support the deployment of installed
capacity from presently 18.30 MW to 261.84 MW by 2019 under the FiT mechanism. An overview
of the procedures and steps involved will result in the increase of RE share in the total energy mix,
improved energy security, self-dependence on energy, as well as job creation in the ASEAN
region.
We are grateful to the Ministry of Energy, Green Technology and Water (KeTTHA), Malaysia and
SEDA for their insights and active engagement in the review and development of this Guideline.
We hope that this publication will help increase the understanding of the various permits and
procedures required for SHP project development in Malaysia, thus motivating various
stakeholders to be involved in SHP projects.
>
Ms. Maria-José Poddey
Principal Advisor ASEAN-RESP, GIZ
Executive DirectorASEAN Centre for Energy
-
Table of Contents
Small HydroPower (SHP)
in Malaysia
Page 8
Small Hydropower in
Malaysia
Potential of small hydropower for
electricity generation; framework for small
hydropower project development in
Malaysia; related regulations; market
condition …
How to use the Guideline
Page 205
List of Abbreviations
Page 203
Procedures: Step-by-step
Small Hydropower (SHP) in Malaysia
Page
15
Foreword
Page 3 & 5
About the
guidelines
Page 11
Procedure: Step-by-step
Small Hydropower in Malaysia
The process for developing a small hydropower plant in
Malaysia may be found in the Gantt’s chart and flow chart.
-
><
OverallOverallTOC
Small Hydropower in Malaysia
Malaysia has considerable hydropower potential. There are around 150 river systems
in Peninsular Malaysia alone and approximately 50 systems in Sabah and Sarawak.
The total potential of small hydropower currently stands at 116.6 MW. As of 2012,
there are 58 small-scale hydropower plants in Malaysia. TNB Energy Services (TNB-
ES), a subsidiary of TNB, operates 30 small hydropower plants[1].
As of October 2014, the installed capacity of commissioned small hydropower plants
under the Feed-in Tariff scheme stood at 11.7 MW, resulting in the power generation
of around 73 GWh in 2013. However, based on the number of applications awaiting
approval the total installed capacity may reach as high as 209 MW in 2017[2]. Also of
note: the majority of the hydropower sites currently in use are located in the eastern
part of Malaysia.
In recent years the Malaysian government has sought to promote RE across the
nation. The concept and idea of a Feed-in Tariff (FiT) was proposed by the Malaysia
Building Integrated Photovoltaic (MBIPV note 1) Project as a potential policy to promote
the Malaysia RE Sector in 2004. In pursuit of said policy, extensive studies were
conducted, consultation workshops held and joint co-operation initiated with
international partners to draft a policy along with supporting mechanisms that best fit
Malaysia’s needs.
Background information
[1]: UNIDO: Small Hydropower World (www.smallhydroworld.org); [2]: SEDA 2014
Note 1: Malaysia Building Integrated Photovoltaic (MBIPV) Project was a joint initiative between the Government of Malaysia, the United Nations Development Program (UNDP) and Global Environment Facility to promote a nationwide and sustainable solar PV market in Malaysia. MBIPV was active from 2006 to 2010.
Page 3/5Malaysia Power Sector Small Hydropower
http://www.smallhydroworld.org/
-
><
OverallOverallTOC
Small Hydropower in Malaysia
The National Renewable Energy Policy and Action Plan (NREPAP) was proposed in
2009 and adopted in April 2010. The NREPAP consists of five objectives:
To increase RE relevance in the national energy mix
To facilitate growth of RE sector
To ensure reasonable cost of RE
To conserve the environment
To enhance awareness on RE
Not long after, FiT was incorporated into the 10th Malaysia Plan in June 2010 and
later into the National Budget of 2011 for the first time. The RE sector gained a strong
foothold in 2011 when the Renewable Energy Act (Act 725) was passed. It
establishes the framework for RE project development under a FiT scheme. The
Sustainable Energy Development Authority (SEDA) was also established by the
SEDA Act (Act 726). SEDA is a special regulatory body under the Ministry of Energy,
Green Technology, and Water who administrate and manage the implementation of
the FiT mechanism under the RE Act.
Background information
Page 4/5
-
><
OverallOverallTOC
Small Hydropower in Malaysia
The Feed-in Tariff for small hydropower projects is between sen 24, sen 25 and sen
26 (~ cent 5.88 US to cent 6.37 US), depending on the installed capacity. The FiT
duration meanwhile is 21 years. There is no digression rate (0%) for small
hydropower plants.
Background information
Page 5/5
Installed capacityFIT rate
(per kWh)
Up to and including 2MW 26 sen(US 6.37 cent)
Above 2MW and up to and
including 10MW25 sen
(US 6.12 cent)
Above 10 MW and up to
30 MW24 sen
(US 5.88 cent)
-
Overall OverallTOC
><
About the Guidelines
In recent years, ASEAN Member States (AMS) have made a considerable effort to tap into the vast reserves of renewable energy
(RE) in the region. Several countries introduced feed-in-tariffs (FIT) or regulations for RE, as well as other supportive policies, for
example tax and customs exemptions or tax holidays.
Despite those efforts and some promising developments, a large scale market for RE applications has not yet been established in
the region. In particular, complex administrative procedures, a lack of transparency in the project cycle and permitting procedures as
well as insufficient access to financial resources are but some of the obstacles preventing an effective market and satisfactory
industry development.
The ASEAN RE Guidelines were developed to facilitate increased private sector activity and investment in the RE sector of the
ASEAN region. Since the confidence of project developers and investors is a prerequisite to boost region-wide RE deployment, the
provision of transparent project development and permit procedures is indispensable.
To this end, the Renewable Energy Support Programme for ASEAN (ASEAN-RESP), jointly implemented by the ASEAN Centre for
Energy (ACE) and Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH, is devleoping a comprehensive, easy-to-
access and regularly updated online tool which includes complete information on ideal RE project development cycles in the
respective AMS. The ASEAN RE Guidelines:
highlight administrative procedures including requirements for project developers and/or investors;
list legal and regulatory provisions as well as necessary permits;
identify country-specific challenges for project development; and
Provide information on how to obtain financial closure.
The ASEAN RE Guidelines are designed as best as possible to meet the needs of project developers and potential investors, as well
as promote transparency and clarity in the RE projects’ pathway. The Guidelines explain in detail the various procedures and help
identify the risks associated with each step so that proper mitigation measures can be designed and put in place.
Page 1/4
ASEAN RE Guidelines This Guideline
>
Small Hydropower Project Development in Malaysia
-
Overall OverallTOC
><
About the Guidelines
The ASEAN RE Guidelines were developed for different technologies and several ASEAN Member States. To promote RE
development, as a precondition a clear legal framework must exist, along with minimum market readiness. The ASEAN-RESP is
working closely with relevant organisations and projects in the respective member states in order to ensure quality, completeness
and accuracy of data.
A series of four ASEAN RE Guidelines have been developed and published in four ASEAN Member States: Indonesia, Malaysia, the
Philippines, and Vietnam.
Page 2/4
Indonesia
• Biomass/biogas
• Mini hydropower (up to 10 MW)
• Solar PV
Philippines
• Solar PV (small & large)
Vietnam
• Biomass
Malaysia
• Solar PV (small & large)
• Small hydropower (up to 30 MW)
ASEAN RE Guidelines This Guideline
Small Hydropower Project Development in Malaysia
-
Overall OverallTOC
><
About the Guidelines
This guideline is one of three publications in the Malaysia series of the ASEAN RE Guidelines initiative. The other guidebooks in the
series are (1) small solar PV project development and (2) large solar PV project development. They are scheduled to be published in
2016.
The Renewable Energy Support Programme for ASEAN (ASEAN-RESP) identified regional and international consultants for the
development of the RE-Guidelines. This guideline (“Small Hydropower Project Development in Malaysia”) was developed
together with regional consultant SSM Associates Sdn Bhd and in close co-operation with Sustainable Energy Development
Authority (SEDA) Malaysia. The guidelines were reviewed by international consultants Eclareon GmbH and E.Quadrat GmbH, to
ensure that the locally-prepared content can be easily understood by foreign investors / developers.
The primary target groups of the guideline include project developers and investors who are interested in conducting studies of small
hydropower projects in Malaysia to determine the financial feasibility. It is also useful to bankers and policy makers. The objective of
these guidelines is to provide an overview of the processes; they were not written from the perspective of engineering, procurement,
and construction (EPC), engineering consultant, or equipment suppliers.
This particular guideline covers only grid-connected small hydropower projects with a capacity of up to 30 MW. Development of an
off-grid project is subject to different procedures and different technical details. That said, the procedures outlined in these guidelines
are for projects that seek to obtain a FiT as stipulated by the Renewable Energy Act 2011.
Based on the regulatory framework and different governing system, development of small hydropower projects in Sarawak need to
follow different laws and regulations; the procedures are also different. This guidebook covers the legal and regulatory framework in
the Peninsular Malaysia or Sabah areas only.
Page 3/4
ASEAN RE Guidelines This Guideline
Small Hydropower Project Development in Malaysia
-
Overall OverallTOC
><
About the Guidelines
The guideline covers only grid-connected small hydropower projects with a capacity of up to 30 MW. Development of an off-grid
project is subject to different procedures and different technical details. The procedure outlined is for projects seeking to obtain a FiT
as stipulated under the Renewable Energy Act 2011.
Based on the regulatory framework and different governing system, development of small hydropower projects in Sarawak need to
follow different laws and regulations; the procedures are also different. This guidebook covers the legal and regulatory framework in
the Peninsular Malaysia or Sabah areas only.
Small Hydropower Project Development in Malaysia
Page 4/4
On-grid Off-grid
10 – 30
MW Above 30 MWCapacity
RE Project
Type
Included in the Guideline Excluded from the Guideline
ASEAN RE Guidelines This Guideline
2 - 10
MW
Location Sabah and
Labuan
Peninsular
MalaysiaSarawak
RE projects larger than 30 MW are
possible but need special approval
from the Ministry of Energy, Green
Technology, and Water (KeTTHA)
Sarawak is a state in Malaysia with a
higher level of autonomy. Therefore,
the laws and regulations differ from the
federal ones.
Up to 2
MW
-
Overall OverallTOC
Construction and Installation
Note: The bar length on the Gantt's chart is not to scale. It should be used for qualitative comparison only.
Planning and Development
Financial
Closure
Operation and
Maintenance
Step 1
Step 7
Step 11
Step 2
Step 5
Step 8
Step 3
Site Selection / Evaluation
Support Mechanisms
Administrative Authorisation
Financing
Procurement and Construction
Testing and
Commissioning
Power Purchase Agreement
Step 9
Step 4
Operation & Maintenance
Electricity Production License
Step 6 Corporate Fiscal/Legal
Page 1/3 ><
Procedures: Step-by-Step
Gantt’s Chart Flow Chart Description
Small Hydropower Project Development in Malaysia
-
Overall OverallTOC
Procedures: Step-by-StepSmall Hydropower Project Development in Malaysia
Site Selection
/ Evaluation
Step 1
Support
Mechanisms
Step 11
Step 2
Administrative Authorisation
Procurement and Construction
Step 7
Testing &
Commissioning
Step 8
Power
Purchase
Agreement
Step 3
Operation
and
Maintenance
Step 9
Corporate
Fiscal / Legal
Step 6
Gantt’s Chart Flow Chart Description
Construction and InstallationPlanning and DevelopmentOperation and
Maintenance
Financial
Closure
Electricity
Production
License
Step 4
Step 5
Financing
Page 2/3 ><
Gantt’s Chart Flow Chart Description
-
Overall OverallTOC
><
Procedures: Step-by-Step
To develop a small hydropower project in Malaysia, project developers must first identify and select a suitable
site for building a small hydropower plant.
Concurrently, permission for grid connection must be obtained.
Typically, project developers establish a special purpose company (SPC) to develop, construct and operate a
small hydropower plant. The establishment of such a company must be done from the outset.
Several permits must be obtained from the government and relevant authorities.
A provisional license must be obtained from the Energy Commission, allowing a project developer to generate
electricity in Malaysia.
Financing must be secured from banks or financial institutions.
After the financial closure, procurement and construction may then proceed.
After completing construction of a small hydropower power plant, inspection and testing must then be
conducted.
After COD, operations at the small hydropower plant may commence.
Gantt’s Chart Flow Chart Description
Page 3/3
Small Hydropower Project Development in Malaysia
-
Overall OverallTOC Step Step
Step 1 | Site Selection / Evaluation
1-3
Appointment of
Technical Expert1-1
SSL (Gantt’s chart)
1-2
Detailed survey
Preliminary Survey and Preparation of Feasibility Study (FS)
Gantt’s Chart Flow Chart More Details…
Conditional sub-step
Mandatory sub-step
2-2
2-1 Power System Study (PSS)
Connection Confirmation Check (CCC)
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
Appointment of
Technical Expert
1-1
Preliminary Survey
and Preparation of
Feasibility Study (FS)
1-2
SSL (Flow Chart)
Detailed Survey
1-3
Gantt’s Chart Flow Chart More Details… 2-2
2-1 Power System Study (PSS)
Connection Confirmation Check (CCC)
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
>
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
DESCRIPTION
1-1
Appointment of Technical Expert
According to the regulatory framework of Malaysia, a professional engineer must prepare the project feasibility study (FS), along
with the supporting documents to be submitted to the Sustainability Energy Development Authority (SEDA). Therefore, as the first
step, the project developer/investor shall appoint a technical expert (who is legally able to provide professional engineering services)
to carry out the aforementioned activities.
Typically, a technical expert will be involved in the two stages of project development.
.
Description Documents Fee/Duration Regulations Page 1/7>
Pre-PPA Stage Post-PPA Stage
This is from inception of the project until a power
purchase agreement (PPA) is signed. The
responsibilities of a technical expert include the
following:
Preparation of the FS (Refer to Sub-step 1-2)
Assist the developer in preparing PPA document
Activities relating to Post-PPA or implementation
stage (explained separately in Sub-step 7-1).
Typically, the tasks of technical experts include the
following:
Detailed design of system
Tendering
Supervision of the supply and installation of
equipment and facility
Supervision of the testing and commissioning of
equipment and facility
The same technical consultant may be contracted for both stages.
Alternatively, different consultants may be contracted separately for
each stage. In the latter case, the developer must ensure complete
transfer of information.
References Challenges
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
DESCRIPTION
1-1
Appointment of Technical Expert
This sub-step details interactions between two businesses; there is no regulation governing the exact procedure. Typically, the
applied procedure to appoint a technical consultant could be as follows:
Project developer requests proposals from one or more potential consultants. A request for proposal (RFP) must be prepared.
Consultants submit their proposals. Typically, a proposal from the potential consultant consists of the following information:
Technical proposal - covering the scope and duties to be carried out by the consultant
Financial proposal - indicating the service cost and reimbursable costs
Project developer evaluates and compares the received proposals. A face-to-face negotiation may be arranged, allowing
detailed discussion on deliverables, timeframe, service costs, negotiation on scope of works and terms & conditions.
The developer makes a decision and notifies the winning consultant through a letter of appointment.
Contract between project developer and consultant is signed.
Description Documents Fee/Duration Regulations References Page 2/7Challenges
-
REQUIRED DOCUMENTS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Appointment of Technical Expert
1-1
Page 3/7
Only one document is required for this stage: a request for
proposal (RFP). There is no uniform template for a request
for proposal document. Typically, it should consist of the
following:
Project background
Location of the project, possible RE technology
Scope of work and responsibilities of the consultant
Contract timeframe including crucial milestones
The contract duration is typically made until the signing of the
Renewable Energy Power Purchase Agreement (REPPA). In case
the developer/investor plans to use the same consultant for the post-
PPA phase, the consultant will be involve until the commissioning
and handling over of the completed installation to the
developer/investor
List of deliverables
Performance guarantee and warranty period
Description Documents Fee/Duration Regulations
Scope and responsibilities of the developer
This is to indicate what is excluded from the consultant’s scope and
covered by project developer.
Additional terms and conditions (T&C)
The project developer is required to share additional standard terms
and conditions with the hired consultant.
References Challenges
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
Appointment of Technical Expert
1-1
Page 4/7Description Documents Fee/Duration Regulations
The fee for Feasibility Study can be found in Sub-step 1-
2. The professional fee for post-PPA activities ranges
from 1.5% to 2.5% of the capital expenditure (CAPEX)
As this sub-step is an interaction between the developer
and consultant, there is no specific timeframe for
finalising the contract.
However, expediting the contract finalisation will keep
project costs to a minimum and serve to limit any
unforeseen cost escalation.
References Challenges
-
RELATED LAWS AND REGULATIONS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
§
Appointment of Technical Expert
1-1
Page 5/7
Regulation No. Name
Act
No. 138 Year 1967
Registration of Engineer Act
This act describes the role of Professional Engineer. According to this act, the feasibility study (FS) is deemed
“Professional engineering services” and must be performed by a registered professional engineer only.
Description Documents Fee/Duration Regulations References Challenges
-
REFERENCE DOCUMENTS / SOURCES
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Appointment of Technical Expert
1-1
Page 6/7
Document name Description
SEDA Guidelines Guidelines and Determination of the Sustainable Energy Development Authority, Malaysia
This guideline can be downloaded from the official website of SEDA
Description Documents Fee/Duration Regulations References Challenges
-
CHALLENGES AND RISKS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Appointment of Technical Expert
1-1
Page 7/7
Risk Details
Poor consultation services Engaging inexperienced consultants can lead to poor implementation of the scheme and
improper project planning.
Sunk cost Improper site selection may lead to negative results, e.g., the initial site identified cannot be
developed due to later findings, resulting in the need for the evaluation of more project sites.
This will ultimately inflate sunk costs.
Poor suppliers Unscrupulous suppliers and contractors may try to undermine the authority of and working
arrangement with the consultant. The developer therefore must make clear the scope of work
and deliverables with the consultant as well as the relationship with the suppliers and
contractors. Regular checks must also be conducted to maintain the quality of work and ensure
timely implementation of deliverables/activities.
Description Documents Fee/Duration Regulations >References Challenges
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
DESCRIPTION RELATED AUTHORITIES
Preliminary Survey and Preparation of Feasibility Study (FS)
1-2
Page 1/7
Note 1: The submission of the FS to SEDA is done
during the Feed-in approval holder (FiAH)
application (described in Sub-step 3-2)
This sub-step outlines the processes for conducting a feasibility study (FS) for the
project. This must be done by the contracted consultant (Sub-step 1-1). The FS is to
be carried out to check whether the development of a small hydropower (SHP) project
is technically feasible and economically viable. The FS must be submitted to the
Sustainable Energy Development Agency (SEDA), Malaysia as a part of required
documents for the feed-in Approval Holder (FiAH) application (Sub-step 2-2) as
required by the SEDA Guidelines. The FS will be required by various Financial
Institutes as a basic document for financial closure.
In Malaysia, the Registration of Engineer Act (Act 138) considers the preparation of a
feasibility study (FS) as a “professional engineering service”. Therefore, it must be
performed by a registered professional engineer only.
Typically, a preliminary survey at the site must be performed in this sub-step as well.
This is to ensure that the actual site conditions are suitable for project development.
The project developer shall perform a desktop study and a preliminary site survey.
They will form the basis of the input needed for the feasibility study (FS).
Federal level Sustainable Energy
Development Agency (SEDA)1
– Review and evaluate the FS
State
government
-
Local
government
Local government office –Should be informed about the
survey
Description Documents Fee/Duration >Regulations References Challenges
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
DESCRIPTION
The scope of the preliminary survey should cover the following aspects, at minimum:
Check potential locations, accessibility and availability of:
Water intake
Waterway route
Powerhouse
Transmission route
Power injection point
Electricity demand and load patterns
General geological makeup / features of the site
Collecting other necessary input which will be necessary for the Power System Study (PSS) to be conducted later (see Sub-step
1-3)
A more detailed survey must also be completed but can be executed at a later stage (see Sub-step 1-4)
Preliminary Survey and Preparation of Feasibility Study (FS)
1-2
Page 2/7Description Documents Fee/Duration Regulations References Challenges
-
REFERENCE DOCUMENTS / SOURCES
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Preliminary Survey and Preparation of Feasibility Study (FS)
1-2
Page 3/7Description Documents Fee/Duration
Technical Analysis
The technical analysis aspect of the FS should consist of the
following information / data as a minimum requirement:
Project description
A brief description of the project objective and intended output /
results.
Hydrology data of proposed project site
i.e. rainfall statistics, water discharge, flow duration curve, etc.
Geological assessment of the project site
Assessment of geological information and its impact on the operation
of the project and end user.
Installed capacity [kW or MW] and estimated power
generation [GWh] from the proposed project
Conceptual design
i.e. intake, waterway, powerhouse, electromechanical equipment,
transmission, interconnection facilities, etc.
Economic Analysis
The economic analysis, a vital component of the FS, should
consist of the following basic information / data:
Basic economic analysis, methodology and approaches
Cash flow calculation
Internal rate of return (IRR) analysis
For debt financing, IRR should be more than 10%. For equity
financing, IRR should be more than 12%.
Payback period calculation
For debt financing, expected payback period should be around 8
years. For equity financing, expected payback period should be
around 7 years.
Debt service coverage ratio (DSCR) calculation
DSCR should be kept above 1.3 at all times
Regulations References Challenges
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
Preliminary Survey and Preparation of Feasibility Study (FS)
1-2
Page 4/7Description Documents Fee/Duration
The service cost for FS preparation and finalisation
(including associated preliminary site survey) depends
on proposed project location, project size, etc.
Typical ranges are:
Lower end RM 100,000
(~ USD 24,000)
Higher end RM 300,000
(~ USD 72,000)
Conduction and finalisation of the FS may take around 3
months. However, the duration of the Feasibility Study
depends on a variety of factors, including but not limited
to: viz. project size, technology opted, location, social
factors, etc.
Regulations References Challenges
-
RELATED LAWS AND REGULATIONS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
§
Preliminary Survey and Preparation of Feasibility Study (FS)
1-2
Page 5/7
§
Regulation No. Name
Act
No. 138 Year 1967
Registration of Engineer Act
This act describes the role of Professional Engineer. According to this act, the feasibility study (FS) is considered as
“Professional Engineering Services” and must be performed by a registered professional engineer only.
Description Documents Fee/Duration Regulations References Challenges
-
REFERENCE DOCUMENTS / SOURCES
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Preliminary Survey and Preparation of Feasibility Study (FS)
1-2
Page 6/7Description Documents Fee/Duration
Document name Description
SEDA Guideline Guidelines and Determination of the Sustainable Energy Development Authority Malaysia
This guideline can be downloaded from the SEDA website (www.seda.gov.my)
FiT Application form Feed-in Tariff (FiT) application form
This guideline can be downloaded from the SEDA website (www.seda.gov.my)
Regulations References Challenges
http://www.seda.gov.my/http://www.seda.gov.my/
-
CHALLENGES AND RISKS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Preliminary Survey and Preparation of Feasibility Study (FS)
1-2
Page 7/7Description Documents Fee/Duration >Regulations References Challenges
Risk Details
Poor FS Incomplete data and inexperienced consultants can lead to poorly prepared FS and
subsequently a refusal of proposal by banks.
Sunk Cost There is a risk of sunk cost for FS, third party soil survey costs to the project developer in case
it turns out CAPEX is too high for realisation.
Change of PSS Delays in completing the FS report due to various unforeseen challenges may affect the
completion of the Power System Study (PSS). Thus, investors are encouraged to engage a
PSS consultant at the earliest opportunity to ensure the power evacuation and required findings
can be determined to complete the FS in a timely manner.
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
DESCRIPTION RELATED AUTHORITIES
Preparation of Power System Study (PSS)
1-3
Page 1/7
Federal level None
State
government The respective distribution
licensee (DL) – Review the application, nominate a PSS
consultant.Local
government
Description Documents Fee/Duration >Regulations References Challenges
After the project has been determined, the project developer must conduct a
Power System Study (PSS). The purpose of the PSS is to identify the feasible
interconnection options for the proposed development of the off-taker’s electricity
grid. It sets the technical and safety requirements for the interconnection and
operation of the RE power plant.
The PSS indicates the stability and load demand/absorption of the nearest viable
grid injection point. Load flow and a short circuit analysis are included as parts of
the study to ensure that the proposed scheme operation is within the limits set by
the electricity transmission/grid code.
According to Technical and Operation Rules (P.U.(A) 120) of the Renewable
Energy Act 2011, the PSS is required for projects with an installed capacity of 425
kW and above. Upon receiving approval by the respective Distribution Licensee
(DL), the Power System Study (PSS) is valid for one year. It can be extended by
another year upon approval from SEDA. The extension requires additional
payment of fees to the relevant authority. The PSS is a pre-requisite for an
application for Feed-in Approval Holder (Sub step 2-2).
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
DESCRIPTION
1-3
Page 2/7
Preparation of Power System Study (PSS)
The procedure to be followed for the sub-step Power Step Study is as follows:
1. The applicant submits application to respective DL; e.g., for areas which fall under TNB’s authority, the application shall be
submitted to the TNB Renewable Energy unit (RE TNB)
2. RE TNB (or DL) reviews completeness of the documents submitted and checks for the following:
a. Documentation is in order and proper: RE TNB (or DL) issues order to developer for payment of application fee
b. Developer pays required fees and submits proof of payment to TNB RE (or DL)
c. RE TNB (or DL) after verifying payment details, nominates PSS consultant
d. PSS consultant conducts Power System Study and submits report
e. The Power System Study is one of the main steps for ensuring the success of project development, and due care is required
for the success of the plant.
Description Documents Fee/Duration Regulations >References Challenges
-
REQUIRED DOCUMENTS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Preparation of Power System Study (PSS)
1-3
Page 3/7Description Documents Fee/Duration Regulations
The study focuses on the site conditions for a power system
and its demand and supply has two major requirements. The
following documents are to be prepared:
Scheme location and plan
Information on placing equipment and related plan
Proposed equipment configuration
Configuration of equipment to be installed along with their
configuration
Equipment parameters/characteristics
Various parameters of equipment which allow for making decisions of
the installed capacity and operation characteristics
Other technical and site information
Further to the above three aspects, any information which is relevant
to future development of project development may be stated at this
stage
References Challenges
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
Preparation of Power System Study (PSS)
1-3
Page 4/7
Note: The cost and duration data are based on market survey and an interview with project developer.
Description Documents Fee/Duration Regulations
The fees for the grant of a license are regulated by
SEDA, Malaysia and are fixed. The fees are charged
according to the size of the plant as given below:
Above 425 kW and up to 1 MW
(including 1 MW capacity)
RM 20,000
(~ USD 4660)
Above 1 MW and up to 10 MW
(including 10 MW capacity)
RM 40,000
(~ USD 9320)
Conducting a Power System Study (PSS) usually takes
around 2-3 months. However, several factors can
influence the length of duration, e.g., the project size,
applied technology, equipment availability in market,
location, etc.
References Challenges
-
RELATED LAWS AND REGULATIONS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
§
Preparation of Power System Study (PSS)
1-3
Page 5/7
Detailed Survey
Regulation No. Name
Legal Reference:
PU (A) 120 RE
Electricity Supply Act 1990
P. U. (A) 120 RE (Technical and Operational Requirements) Rules 2014 of RE Act
2011 (Act)
Official Reference: TNB Transmission Grid Code
TNB Distribution Grid Code
TNB Technical Guidebook for the Inter-connection of Generation of Distribution
Network
Description Documents Fee/Duration Regulations References Challenges
-
REFERENCE DOCUMENTS / SOURCES
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
1-3
Page 6/7Description Documents Fee/Duration Regulations References Challenges
Preparation of Power System Study (PSS)
-
CHALLENGES AND RISKS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Preparation of Power System Study (PSS)
1-3
Page 7/7
Challenges Recommendation
Validity of Power System
Study is limited
An assessment of situation and next steps is recommended to complete formalities related to
PSS.
Delays in performing PSS
may result in reanalysing
PSS
A pre-check of the situation and next steps is useful in ensuring timely submission of PSS.
Timely submission of PSS will enable timely interconnection of conditions and in identifying
location for the project.
Description Documents Fee/Duration Regulations >References Challenges
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
DESCRIPTION
1-4
Page 1/5
Detailed Survey
The project developer must contract a licensed land surveyor to perform a detailed survey at the selected project site. In Malaysia,
only a licensed land surveyor may conduct the survey. The purpose of this survey is to identify the topography and contours of the
project site; this enables the project developer to identify potential locations for the facility and components. Identification of
boundaries of the site location, establishment of a profile of the surrounding area, and demarcation survey are parts of sub-step 1-3.
This survey aims to help in the development of a plan for the land acquisition process (Sub-step 2-4)
There is no regulation governing the procedure in this sub-step. It is up to the developer to select a suitable approach to arriving at
an agreement with a land surveyor. Typically, the procedures in identifying and contracting a land surveyor are as follows:
The project developer prepares the Terms of Reference (TOR) to define the scope of work and sends it to potential surveyors.
Interested surveyors submit a quotation to the project developer/investor. The quotation typically consists of the following:
Financial proposal
Detailed scope of work
The project developer compares the quotations received and selects suitable surveyor for the survey work. To officially appoint
identified surveyor, a letter of award shall be prepared and signed for documentation purposes.
Description Documents Fee/Duration Regulations Challenges >
-
REQUIRED DOCUMENTS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Detailed Survey
1-4
Page 2/5Description Documents Fee/Duration Regulations Challenges
The only document required for this stage is the Request for
Proposal (RFP). There is no uniform template for RFP
document. Typically, it should consist of the following:
Project background
Location of the project, possible RE technology
Scope of works and responsibilities of the consultant
Detailed tasks and expected results from the survey must be
communicated.
Contract timeframe including crucial milestones
Project deadlines and milestones must be communicated.
List of deliverables
Reports and necessary drawings, documents must be clearly
mentioned.
Other terms and conditions (T&C)
Additional terms and conditions necessary for a successful survey.
-
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
Detailed Survey
1-4
Page 3/5
Note: The cost and duration data are based on market survey and an interview with project developer.
Description Documents Fee/Duration Regulations Challenges
The service cost for conducting a detailed survey is not
regulated. This is based on the agreement and
negotiations between two private businesses. It depends
on a project’s size, the location to be surveyed, and
many other factors.
Typically, a project developer can expect the cost to be
between:
Lower range RM 250,000
(~ USD 60,000)
Higher range RM 400,000
(~ USD 95,050)
Conducting a detailed site survey usually takes around
2-4 months. However, several factors can influence the
actual duration and may lengthen or shorten it, e.g.,
project size, applied technology, location, etc.
-
RELATED LAWS AND REGULATIONS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
§
Detailed Survey
1-4
Page 4/5
Detailed Survey
Regulation No. Name
ACT 486 Land Acquisition Act
National Land Code
Description Documents Fee/Duration Regulations Challenges
-
CHALLENGES AND RISKS
Step 1 | Site Selection / Evaluation
Overall OverallTOC Step Step
><
Sub-step
Detailed Survey
1-4
Page 5/5
Challenges Recommendation
Small hydro sites are usually
located in remote areas and/or
dense jungles. Thus the working
environment can be very
challenging and tough. This can in
turn lead to delays.
It is imperative to have experienced licensed surveyors who possess sufficient
manpower. It is also a good idea to engage them early on in the implementation process.
The project site and access to said site must be well informed for necessary planning and
co-ordination.
Local communities in some areas
may object to the surveyor
carrying out surveys.
Engage with the local communities early on. Preferably, initial site visits can be co-
ordinated on by respective local officials. Joint briefing and presentations on the benefits
of the project and work to be carried out may also be shared with the affected
people/local communities.
Conflicting interests in land rights
or instances where land sought
cannot be acquired.
To avoid such situations, a thorough check must be conducted during the initial phases of
the Feasibility Study.
Description Documents Fee/Duration Regulations Challenges >
-
Step 2 | Administrative Authorisation
FCSSL
CFL
ADM
EPL
GCP
PCN
PPA
OPM
GCC
FIN
CFL
Overall OverallTOC Step Step
State Economic Planning Unit (EPU) Consent
Applying for Feed-in Account Holder
Local Authority Approval
Land Acquisition Process for Government/State Land
2-1
2-2
2-3
2-4
ADM (Gantt’s Chart)
Gantt’s Chart Flow Chart More Details…
Conditional sub-step
Mandatory sub-step
2-5Water Right Agreement
-
Step 2 | Administrative Authorisation
FC
Overall OverallTOC Step Step
State Economic
Planning Unit (EPU)
Consent
Local Authority
Approval
Water Right
Agreement (WRA)
2-1 2-2
Land Acquisition Process
for Government/State Land
2-3
ADM (Flow Chart)
Gantt’s Chart Flow Chart More Details…
2-4
Applying for Feed-in
Account Holder
2-5
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
>
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Contd …….
Land Acquisition Process for Government/State Land:
Land acquisition approval is usually given by the state authority as it is unlikely for the Central/Federal Government to own land in
rural or remote areas. Applications must be submitted to the relevant state authority; the review of documents is performed by the
district government. Final approval and compensation values are given and determined by the State Executive Committee (EXCO).
Water Rights Agreement:
The water rights agreement (WRA) related to the payable water royalty and the environment/land use protection obligation of the
state. It is a legally binding document between the state and the project developer.
Step Description Page 2/2
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
DESCRIPTION RELATED AUTHORITIES
Sub-step
2-1
State Economic Planning Unit (EPU) Consent
Page 1/6
This sub-step is for obtaining state consent for the right to develop a small
hydropower project. As river and water rights are under the jurisdiction of the state,
such consent is required when applying for feed-in approval holder (FiAH) with SEDA
(see Sub-step 2-2).
This step is usually performed in parallel with the Water Right Agreement (WRA)
(Sub-step 2-5). However, in some states, the WRA will be issued as part of the EPU
consent.
According to the Act, the procedures are as follows:
Project developer submits the filled-out forms and all supporting documents to
the State EPU
Joint site visit is to be conducted at the project site
The developer delivers presentation to the development committee (chaired by
State EPU chief)
…
Federal level (none)
State level State Economic Planning Unit
(State EPU) – Evaluate the application, conduct a site visit,
issue a consent letter
Local Level (none)
Description Documents Fee/Duration Regulations Challenges >
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
DESCRIPTION
Sub-step
2-1
…
The State EPU sources comments and principal approval from the competent state technical departments
The State EPU issues a consent letter with conditional approval terms
In some states, the water rights agreement/terms are also given along with the EPU consent (Sub-step 2-5)
State Economic Planning Unit (EPU) Consent
Page 2/6Description Documents Fee/Duration Regulations Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-1
State Economic Planning Unit (EPU) Consent
Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.
The developer must check with the EPU office in the respective state for the exact list.
Page 2/6Description Documents Fee/Duration Regulations
Filled-out application form
The form can be obtained from the relevant state EPU office
Layout plan of the project scheme
Project description / feasibility study (FS) including:
preliminary technical parameters
economic analysis
(refer to Sub-step 1-2)
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
2-1
State Economic Planning Unit (EPU) Consent
Note: Indicated fee in USD is only approximate based on the currency conversion of USD 1 = PHP 3.27 (as of October 2014)
Page 3/6Description Documents Fee/Duration Regulations
The processing fee is calculated per location. It varies
from state-to-state (in some states, there is no fee).
Lower end No fee
Higher end RM 10,000
(~ USD 2,500)
Typically, this sub-step can take around 3 - 12 months.
The exact processing time depends on the state and the
completeness of the documents being submitted.
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-1
Page 4/6Description Documents Fee/Duration Regulations
Regulation No. Name
Act 172
(1976)
Town and Country Panning Act (1976)
State Economic Planning Unit (EPU) Consent
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
CHALLENGES AND RISKS
2-1
State Economic Planning Unit (EPU) Consent
Page 6/6Description Documents Fee/Duration Regulations >Challenges
Risk Details
Rejection from the State EPU The State EPU may reject applications at this stage after the developer has already invested
considerable time and money in conducting a preliminary study, e.g., feasibility study (FS), site
visit, PSS, etc.
Challenges Details Recommendation
Time-consuming
Procedure
The process of obtaining Economic Planning Unit
(EPU) consent may take longer than expected due to
unexpected issues, e.g., conflicts of interest among
several parties aiming to use the same project site for
different purposes (agriculture, mining, etc.)
Project developer should frequently meet
and discuss with the State EPU offices to
expedite approval / consent. It is
recommended that the developer assign a
dedicated team/persons to handle this
issue.
To follow-up on this challenge a dedicated
team may be assigned.
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
DESCRIPTION RELATED AUTHORITIES
Sub-step
2-2
Apply for Feed-in-Account Holder (FiAH)
Page 1/7
This sub-step is on obtaining a Feed-in-Account. An individual who is a citizen of
Malaysia or a company which is majority-owned by a Malaysian or owned outright by
a Malaysian citizen can apply for a Feed-in approval certificate. The approved Feed-
in certificate can be obtained from SEDA.
The application for a Feed-in-Account can be applied for online by providing the
required information and also by submitting a hard copy of the filled-out form.
Required fees must be paid along with the application form.
Valid proof of payment for a FiAH certificate can be obtained from SEDA, provided
the application has been approved.
The final decision on approval is subject to available quota for FiT.
Holder of a Feed-in certificate is eligible to sell Renewable Energy at the Feed-in-
Tariff (FiT) rate as stipulated by SEDA as set out in the RE Act 2011.
Federal level Sustainable Energy
Development Authority
(SEDA), Malaysia
State level (none)
Local Level (none)
Description Documents Fee/Duration Regulations Challenges >
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-2
Apply for Feed-in-Account Holder (FiAH)
Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.
The developer must check with the EPU office in the respective state for the exact list.
Page 2/7Description Documents Fee/Duration Regulations
Profile Registration Document
The latest audited accounts of the applicant
The memorandum and articles of applicant’s association
Form 8 (Certificate of Incorporation of Public Company) or
Form 9 (Certificate of Incorporation of Private Company) in connection with the Applicant under the Companies Act 1965
All Forms 24 (Return of Allotment of Shares) lodged by the applicant with the Registrar of Companies under the Companies Act 1965
The latest Form 49 (Return giving particulars in Register of Directors, Managers and Secretaries and change of particulars) lodged by the
applicant with the Registrar of Companies and a written confirmation from the company’s secretary on the current shareholding of the applicant
A Share-holding/Ownership Structure Diagram; detailing the shareholding percentages of each ultimate shareholder in the company
Copy of the MyKad of each individual shareholder in the company; or, a certified copy of Form 24 and 49 of each shareholder (if the
shareholder is a company) by the company’s secretary and confirmation letter from the company’s secretary confirming the list of shareholders
Certified copies of Form 24 and 49 of the company(s) where each ultimate shareholder has a shareholding percentage, direct or indirect
An extract of the company’s board resolution authorising the applying person to make present an application on behalf of the applicant and to
execute and submit all document in relation thereto
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-2
Apply for Feed-in-Account Holder (FiAH)
Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.
The developer must check with the EPU office in the respective state for the exact list.
Page 3/7Description Documents Fee/Duration Regulations
Profile of the applicant together with CVs of the Project management team
Submit hard copy of the Feed-in-Approval form and supporting documents:
Application Form
Declaration Form
Summary of the application according to template from SEDA
Certified Feasibility Study (by Professional Engineer)
Power System Study report and letter of approval from RE TNB/DL
List of FiA held by the applicant, both past and present
Documents supporting ownership of the site of EPU consent letter (Step 2-1)
Certificate of registration of each qualified person with the Board of Engineers, Malaysia as a Professional Engineer (Electrical)
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-2
Apply for Feed-in-Account Holder (FiAH)
Note: The exact list of required documents can be different from state-to-state. The list provided in this guidebook is only typical documents usually requested by state EPU office.
The developer must check with the EPU office in the respective state for the exact list.
Page 4/7Description Documents Fee/Duration Regulations
Projects requiring loan from bank or financiers are to be supported by the following documents:
Financing agreement with the entity(ies) that will provide or has provided financing to the applicant for the
project, or
Letter of intent/offer letter(s)/financing term sheet(s) from the entity(ies) that will be or has/have provided
financing to the applicant for the project
For self-financed projects, relevant documents confirming the financial capacity (e.g., bank account statement showing credit balance of at
least equivalent to the total capital cost of the RE installation)
For all cases, the applicant must show proof of funds of at least 5% of the capital expenditure in the form of liquid assets
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
2-2
Apply for Feed-in-Account Holder (FiAH)
Note: Indicated fee in USD is only approximate based on the currency conversion of USD 1 = PHP 3.27 (as of October 2014)
Page 5/7Description Documents Fee/Duration Regulations
The processing fee is decided by SEDA and must be
paid to SEDA Malaysia
Processing Fees with each
submission
RM 1000
Earnest Money
Issued in the form of bankers cheque (RM
100/MW) and payable to SEDA. The
earnest money is reimbursable within 21
days upon issuance of result/s
RM 100 per MW
Typically, this sub-step can take around 2 weeks. The
exact processing time depends on the completeness of
the application form and supporting documents.
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
RELATED LAWS AND REGULATIONS§
2-2
Local Authority Approval
Page 6/7Description Documents Fee/Duration Regulations
Regulation No. Name
Act 725 Renewable Energy Act (Act 725)
Act 726 SEDA Act (Act 726)
Apply for Feed-in-Account Holder (FiAH)
Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
CHALLENGES AND RISKS
2-2
Apply for Feed-in-Account Holder (FiAH)
Page 7/7Description Documents Fee/Duration Regulations >Challenges
Risk Details
Rejection from the SEDA SEDA may reject applications for FiAH due to non-submission of all documents. At this stage the
developer may have already invested considerable time and money in performing a preliminary study,
e.g., feasibility study (FS), site visit, PSS, etc.
Challenges Details Recommendation
Application rejected Application may be rejected due to non-conformity to
document requirements
A thorough check must be conducted
when preparing the application form
Large number of applications received by SEDA Timely application for FiAH along with
proper documentation
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
DESCRIPTION
Sub-step
2-3
This section describes the procedure for obtaining approval from the local authority(ies) for the physical construction of the power
plant. This approval is usually referred to as Development Order (DO). It grants planning permission with or without conditions for
any development specified in the order;
As this sub-step is about obtaining a permit from the local government, the exact procedure may differ slightly from state-to-state
(province). Some states have one-stop service agencies to handle the applications and permits.
In such cases, the project developer must submit an application to the State Department of Town and Country Planning. This
department serves as an One Stop Centre (OSC). It will co-ordinate with other involved agencies and departments to obtain all
relevant approval for remaining comments. In case any comment is provided, the developer must revise the document accordingly
and resubmit.
However, in states where one-stop service has not yet been implemented, the project developer must approach each individual
local authority in order to obtain the necessary approval.
Local Authority Approval
Page 1/7Description Documents Fee/Duration Regulations References Challenges >
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
RELATED AUTHORITIES
2-3
Local Authority Approval
Note:
Page 2/7
Central level (None)
Provincial level State Department of Town and Country Planning – Receive the application and supporting documents, co-ordinate with various agency to obtain their approval or comments (in case one-stop service system has already been implemented)
Other relevant authorities at the state level – Review the application, grant approval or comments
State Department of Environment (DOE)
State Mineral and Geosciences Department
State Department of Forestry
Local level Other relevant authorities in the local level – Review the application, grant approval or comments Land and Mining District Office
District Office (DO)
Public Work Department (PWD)
Drainage and Irrigation Department (DID)
Tenaga Nasional Berhad (TNB)
Indah Water Konsortium (IWK) - (Sewarage)
District Water Board Office
District/Town Council
Fire and Rescue Department
Description Documents Fee/Duration Regulations References Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-3
Local Authority Approval
Page 3/7Description Documents Fee/Duration Regulations References Challenges
The exact list of documents differ from state-to-state. All
drawings, plans, and reports must be properly endorsed by
registered professional engineers. Typically, the project
developer is requested to submit the following documents:
Filled-out submission forms
Layout plan
Contour plan for the project site
Proposed power plant development report or a
Feasibility Study report
Refer to Sub-step 1-2
Drainage report based on the Storm Water Management
Manual (MSMA) of DID
Hydraulic and Hydrology report
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
2-3
Local Authority Approval
Note: Generally for small hydropower plant, the processing would sum up to be between RM 1500 and RM 2000 (~ USD 470 – USD 625) in total.
Page 4/7Description Documents Fee/Duration Regulations References Challenges
The processing fee is regulated by each state
individually. However, the developer can estimate the
fee based on the following:
Typically, the fee is calculated
from the project area
It is a one-off payment, for small
hydropower schemes this ranges
between RM 1500- RM 2000 (USD
350 – USD 450)
RM 0.10 per m2
(~ USD 0.03 per m2)
As there are several relevant permits needed for this
sub-step, it is difficult to determine an exact timeframe.
Typically, the entire process takes around 3 - 6 months.
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
RELATED LAWS AND REGULATIONS§
2-3
Local Authority Approval
Local Authority Approval
Page 5/7Description Documents Fee/Duration Regulations References Challenges
Regulation No. Name
Act 172 (1976) Town and Country Panning Act
Act 138 (1967) Registration of Engineers Act
Uniform by-laws as notified from time to time and location specifics
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-3
Local Authority Approval
Page 6/7
Document Name Description
Standard forms Based on the state/province or local authority
Guidelines Based on the state/province or local authority
Description Documents Fee/Duration Regulations References Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
CHALLENGES AND RISKS
2-3
Local Authority Approval
Local Authority Approval
Page 7/7Description Documents Fee/Duration Regulations References Challenges >
Risk Details
Rejection from the
authority
Certain agencies may reject the small hydropower project, leading to additional delays. There is a
risk of sunk cost as a feasibility study and site survey may have already been performed.
Challenges Details Recommendation
Coordination with related
authority
Some agencies may give comments and
responses based on the normal urban
building requirement which may not be
applicable for SHP development
The project developer must engage with relevant
departments, through their technical consultants or
engineers, as early as possible. Some dedicated
presentations and discussions coupled with site
visits may be needed to facilitate the process.
Long lead time Long lead times during the approval process.
There is no clearly defined deadline on the
processing time for all authorities involved.
It is recommended to start the process early and
hold frequent meetings, communicate regularly and
hold follow-up discussions.
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
DESCRIPTION RELATED AUTHORITIES
Sub-step
2-4
Land Acquisition Process for Government/State Land
Page 1/7
Land acquisition approval is usually given by the state authority as it is unlikely for the
Central/Federal Government to own land in rural or remote areas. Thus, applications
must be submitted to the state authority. A review of the documents submitted is then
performed by the district government. Final approval and compensation values are
given and determined by the State Executive Committee (EXCO).
The applied procedure is as follows:
The project developer submits the demarcation/land acquisition plans (LAP) to
the state authorities using the standard application form(s)
Review of the plans performed by district offices. Comments and/or approval
will be submitted to the developer.
The developer reviews and amends drawings/plans based on comments
The revised documents are tabled at the EXCO meetings and approval given
with compensation values
Contd..
Related Authority
Central level (none)
Provincial
government
State Land/ Mining Office and
Forest Department
Local
government
District Land Office and Forest
Department
Description Documents Fee/Duration Regulations References Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
DESCRIPTION
Sub-step
2-4
…
The state authorities such as the Land/Mining office or the Forest Department notify the developer on the compensation
values
If the developer is not satisfied with the compensation amount, he/she can appeal to the EXCO
Land Acquisition Process for Government/State Land
Page 2/7Description Documents Fee/Duration Regulations References Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-4
Page 3/7
Land Acquisition Process for Government/State Land
The exact list of documents required differs from state-to-
state. Typically, the project developer is requested to submit
the following documents:
Filled-out application form(s)
Demarcation plans or land acquisition plans (LAP)
Description Documents Fee/Duration Regulations References Challenges
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
2-4
Land Acquisition Process for Government/State Land
Note 1: There may be additional fees for joint site visits for tagging and identifying forest trees/logs for compensation estimation.
Page 4/7Description Documents Fee/Duration Regulations References Challenges
The processing fee is regulated by each state
individually. However, the developer can expect the fee
to range between the following:
Lower endnote1 RM 1,500
(~ USD 412)
Higher endnote1 RM 5,000
(~ USD 1,374)
As several permits are relevant, it is difficult to determine
the specific time needed for this sub-step. Typically, the
entire process takes around 6 - 18 months
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
RELATED LAWS AND REGULATIONS§
2-4
Land Acquisition Process for Government/State Land
Land Acquisition Process for Government/State Land
Page 5/7Description Documents Fee/Duration Regulations References Challenges
Regulation No. Name
Act 486 (1992) Land Acquisition Act (Act 486)
- National Land Code
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REFERENCE DOCUMENTS / SOURCES
2-4
Land Acquisition Process for Government/State Land
Page 6/7Description Documents Fee/Duration Regulations References Challenges
Standard application forms
This form must be obtained directly from the state authorities
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
CHALLENGES AND RISKS
2-4
Land Acquisition Process for Government/State Land
Page 7/7Description Documents Fee/Duration Regulations References Challenges
Risk Details
Unable to acquire the land The state may reject the project in this stage after considerable efforts have already been invested.
Challenges Details Recommendation
Time-consuming
procedure
This sub-step requires the most time, apart
from the construction period
To obtain approval as soon as possible, early
submission is imperative. It is recommended to
assign a dedicated team to handle and engage
various authorities and offices from the outset to
ensure a speedy process
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
DESCRIPTION RELATED AUTHORITIES
Sub-step
2-5
Water Rights Agreement (WRA)
Page 1/3
A water rights agreement (WRA) is a legally binding document between the state and
the project developer pertaining to the payable water royalty and the
environment/land use protection obligation of the state. Sometimes, the WRA is given
when the state principal approvals are obtained (Sub-step 2-1).
The WRA is usually part of the state EPU approval for small hydro. However, in some
states, the WRA is to be performed separately but in parallel with the obtaining
process for the state EPU consent.
Description Regulations Challenges
Federal level (none)
State level State Economic Planning Unit
(State EPU) – Evaluate the application and grant the WRA
Local level (none)
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
2-5
Water Rights Agreement (WRA)
Page 2/3Description Regulations Challenges
Regulation No. Name
Act 171 (1976) Local Government Act (Act 171)
- Various state By-laws
-
Step 2 | Administrative Authorisation
Overall OverallTOC Step Step
><
Sub-step
CHALLENGES AND RISKS
2-5
Water Rights Agreement (WRA)
Page 3/3Description Regulations Challenges
Challenges Details Recommendation
High fee The initial royalty rates may be a bit high and may
affect the economic viability of the scheme. The
comparative rate is set independently by each state
where SEDA does not play a role in regulating.
The developer is to appeal and negotiate
on the rate to ensure fair returns for both
parties
-
Step 3 | Power Purchase Agreement
FCSSL
CFL
ADM
EPL
GCP
PCN
PPA
OPM
GCC
FIN
CFL
Overall OverallTOC Step Step
Renewable Energy Power Purchase Agreement (REPPA)
PPA (Gantt’s Chart)
3-1
Gantt’s Chart Flow Chart More Details…
-
Step 3 | Power Purchase Agreement
FC
Overall OverallTOC Step Step
Renewable Energy
Power Purchase
Agreement (REPPA)
3-1
PPA (Flow Chart)
Gantt’s Chart Flow Chart More Details…
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
>
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
><
DESCRIPTION RELATED AUTHORITIES
Sub-step
3-1
Renewable Energy Power Purchase Agreement (REPPA)
Page 1/7
This sub-step covers the procedures for obtaining a signed Renewable Energy
Power Purchase Agreement (REPPA) from the Distribution License (DL).
The REPPA for small hydropower installations with a capacity up to 10 MW is
different from the REPPA for small hydropower installations with a capacity above
10 MW. REPPA for SHP on a larger scale (10 – 30 MW) has 2 critical differences
from the REPPA for SHP installations smaller than 10 MW. These are:
A delayed implementation of the SHP project without an approved extension
of time for COD will face liquidated damage (RM 1,000 or ~ USD 306) from
the off-taker (the DL). The liquidated damage depends on the duration of
delay and may be as high as 70% of the declared energy generation.
A SHP installation generating less than 70% of the declared average annual
energy (AAE) in the REPPA will be charged a penalty (the calculated formula
is given in the REPPA, also see note) The penalty may amount to a sum,
equivalent to up to 70% of the declared energy generation.
Note: The determination penalty is regulated. The
calculation formula is given in the REPPA. It is: LD =
DC x [ (0.7 x DAA) – MRE ] x 1000, where LD is the
sum in RM payable by the Feed-in Approval Holder
to the Distribution Licensee, DC is the prevailing
displaced cost (in RM/kWh), DAA = the Declared
Annual Availability (in MWh) of such Contract Year,
and MRE = the aggregate Metered Renewable
Energy (in MWh) generated by the Renewable
Energy Installation for every hour of each day
Description Documents Fee/Duration Regulations References Challenges
Central
government
SEDA
Provincial
government
(none)
Local
government
(none)
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
><
DESCRIPTION
Sub-step
3-1
Renewable Energy Power Purchase Agreement (REPPA)
Page 2/7
The applied procedures are as follows:
The project developer submits the documents to the respective DL
The DL reviews the completeness of the submitted documents
The developer and the DL jointly sign the Renewable Energy PPA (REPPA)
Description Documents Fee/Duration Regulations References Challenges
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
><
Sub-step
REQUIRED DOCUMENTS
3-1
Renewable Energy Power Purchase Agreement (REPPA)
Page 3/7Description Documents Fee/Duration Regulations References Challenges
Filled-out REPPA document
Form HP 1 – for small hydropower plant up to 10 MW
Form HP 2 – for small hydropower plant above 10
MW and up to 30 MW.
3 sets of REPPA are required. The standard form of REPPA can be
downloaded from the official website of the Sustainable Energy
Development Authority (SEDA) at www.seda.gov.my
FiAH certification
Refer to Sub-step 2-2
Supporting documents as appendices of REPPA
Description of the SHP plant
Description of interconnection facilities and the
connection point
Description of communication facilities
The list of appendices are according to the REPPA standard list
http://www.seda.gov.my/
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
><
Sub-step
FEES / COST DURATION
3-1
Renewable Energy Power Purchase Agreement (REPPA)
Page 4/7Description Documents Fee/Duration Regulations References Challenges
There is no fee for this sub-step This sub-step usually takes around 2 to 3 months
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
><
Sub-step
RELATED LAWS AND REGULATIONS§
3-1
Renewable Energy Power Purchase Agreement (REPPA)
Page 5/7
Regulation No. Name
Act 725 (2011) Renewable Energy Act (Act 725)
Act 726 (2011) Sustainable Energy Development Authority (SEDA) Act (726)
Description Documents Fee/Duration Regulations References Challenges
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
><
Sub-step
REFERENCE DOCUMENTS / SOURCES
3-1
Renewable Energy Power Purchase Agreement (REPPA)
Page 6/7Description Documents Fee/Duration Regulations References Challenges
Guidelines and Determination of the Sustainable Energy Development Authority Malaysia
This guideline is known as “SEDA Guidelines”. It can be downloaded from the SEDA website (www.seda.gov.my)
Official REPPA form (Form HP 1)
Form HP 1 is for small hydropower plants of up to 10 MW. It can be downloaded from the SEDA website (www.seda.gov.my)
Official REPPA form (Form HP 2)
Form HP 2 is for small hydropower plants above 10 MW and up to 30 MW. It can be downloaded from the SEDA website (www.seda.gov.my)
http://www.seda.gov.my/http://www.seda.gov.my/http://www.seda.gov.my/
-
Step 3 | Power Purchase Agreement
Overall OverallTOC Step Step
><
Sub-step
CHALLENGES AND RISKS
3-1
Renewable Energy Power Purchase Agreement (REPPA)
Page 7/7Descr