remediation of the tar ponds and coke ovens sites
TRANSCRIPT
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
REMEDIATION OF THE TAR PONDS
AND COKE OVENS SITES
DESIGN AND CONSTRUCTION OVERSIGHT
SERVICES
ENVIRONMENTAL MANAGEMENT PLAN
97918-GEN-EMP-N-001-R2
Prepared By: Original Signed By Date: 14 June 2010
Stephen Pinto
Environmental Coordinator
AECOM Canada Ltd.
Reviewed By: Original Signed By Date: 14 June 2010
Bruce Noble
Deputy Project Manager
AECOM Canada Ltd.
Approved By: Original Signed By Date: 14 June 2010
Ray Rice
Project Manager
AECOM Canada Ltd.
Approved By: Date: 14 June 2010
Wilfred Kaiser
Environmental Manager
Sydney Tar Ponds Agency
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Revision Summary
Revision Date of Issue Purpose
A 11 January 2007 DRAFT internal review
B 23 January 2007 DRAFT issue for client review
C 17 May 2007 DRAFT issue for client review
D 25 July 2007 Issue for client review
0 15 January 2008 Final for Issue
1 4 August 2009 Re-issue for client review
2 14 June 2010 Re-issue for client review
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Distribution List
Agency Project Manager (12) Sydney Tar Ponds Agency
David Wilson Project Director
Don Shosky Project Director
Shawn Duncan Environmental and Regulatory Lead
Ray Rice Project Manager
Stephen Pinto Environmental Coordinator
Bruce Noble Deputy Project Manager
Dan MacDonald Engineering Manager
Robert Jones Quality Assurance Manager
Andrew McIntosh Regulatory Lead
File Copy CBCL Central Records
File Copy AECOM Library
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
i
97918-GEN-EMP-N-001-R2 14 June 2010
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................................................................. 1
1.1. PROJECT OVERVIEW ..................................................................................................................................... 2
1.2. HISTORICAL BACKGROUND .......................................................................................................................... 2
1.3. PROJECT ENVIRONMENTAL MECHANISM ...................................................................................................... 3
1.4. OBJECTIVES OF THE EMP ............................................................................................................................. 4
1.4.1. Content of the Environmental Management Plan ....................................................................................... 5
1.5. MAINTENANCE OF THE EMP AND CHANGE PROTOCOL DOCUMENT ............................................................. 6
1.6. ENVIRONMENTAL POLICY, GUIDING PRINCIPLES AND COMMITMENT TO MITIGATION ................................. 7
2.0 REMEDIAL MANAGEMENT PLAN ................................................................................................................ 9
2.1. PROJECT DESCRIPTION .................................................................................................................................. 9
2.2. TAR PONDS ................................................................................................................................................. 10
2.3. COKE OVENS .............................................................................................................................................. 10
2.4. ELEMENT DESCRIPTION AND LAYOUT ........................................................................................................ 11
2.4.1. TP6A – Flow Diversion............................................................................................................................. 11
2.4.2. TP6B – Solidification/Stabilization (S/S) and Channel Construction ....................................................... 12
2.4.3. TP6C – Ferry Street Bridge Construction ................................................................................................ 13
2.4.4. TP6D – Construction of Access Roads ..................................................................................................... 13
2.4.5. TP2 – Material Processing Facility .......................................................................................................... 13
2.4.6. TP7 – Tar Ponds Surface Cap .................................................................................................................. 13
2.4.7. CO1 – Coke Oven Brook Connector Sediment Removal and Disposal .................................................... 14
2.4.8. CO2 – Solidification/Stabilization (Tar Cell) ........................................................................................... 14
2.4.9. CO5 – Vertical Cutoff Walls ..................................................................................................................... 15
2.4.10. CO6 – Coke Ovens Surface Cap ............................................................................................................. 15
2.4.11. CO7/CO8 – Coke Oven Brook Water Treatment & Ground Water Collection ...................................... 16
2.5. CONCEPTUAL SITE MODELS ....................................................................................................................... 17
2.6. SEQUENCING OF PROJECT ELEMENTS ......................................................................................................... 17
2.7. PROJECT SCHEDULE AND MILESTONES ....................................................................................................... 19
2.7.1. Project Milestones .................................................................................................................................... 19
3.0 REGULATORY APPROVALS, AUTHORIZATIONS AND PERMITS ...................................................... 19
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
ii
97918-GEN-EMP-N-001-R2 14 June 2010
3.1. FEDERAL GOVERNMENT OF CANADA ......................................................................................................... 20
3.2. PROVINCIAL GOVERNMENT OF NOVA SCOTIA ............................................................................................ 20
3.3. MUNICIPAL GOVERNMENT – CAPE BRETON REGIONAL MUNICIPALITY ..................................................... 21
4.0 ENVIRONMENTAL MANAGEMENT TEAM ORGANIZATION, STRUCTURE AND
RESPONSIBILITIES ................................................................................................................................................ 22
4.1. ORGANIZATION AND STRUCTURE ............................................................................................................... 22
4.2. ENVIRONMENTAL MANAGEMENT COMMITTEE ........................................................................................... 24
4.3. MANAGING PARTNERS ................................................................................................................................ 26
4.4. NOVA SCOTIA DEPARTMENT OF ENVIRONMENT ......................................................................................... 26
4.5. SYDNEY TAR PONDS AGENCY .................................................................................................................... 27
4.5.1. Agency Project Director ........................................................................................................................... 27
4.5.2. Safety, Health and Environmental Coordinator ....................................................................................... 27
4.6. AECOM AND CBCL .................................................................................................................................. 28
4.7. INDEPENDENT ENGINEER ............................................................................................................................ 29
4.8. CONTRACTORS ............................................................................................................................................ 30
4.9. ANALYTICAL LABORATORY ....................................................................................................................... 31
4.10. INDEPENDENT QUALITY ASSURANCE CONSULTANT ................................................................................... 31
5.0 MANAGEMENT PLANS ................................................................................................................................... 32
5.1. WATER MANAGEMENT PLAN ..................................................................................................................... 32
5.1.1. Management of Runoff from Precipitation................................................................................................ 32
5.1.2. Management of Watercourses during Construction ................................................................................. 33
5.1.2.1. Sources of Water ........................................................................................................................................... 33
5.1.2.2. Water Management ....................................................................................................................................... 34
5.1.3. Water Collection and Treatment ............................................................................................................... 34
5.1.3.1. Sources of Water ........................................................................................................................................... 36
5.1.3.2. Permanent Water Treatment (CO8) .............................................................................................................. 37
5.1.3.3. Treatment Processes ...................................................................................................................................... 38
5.1.4. Compliance under the Federal Fisheries Act ........................................................................................... 38
5.1.5. Coke Oven Brook Groundwater Quantity and Discharge Chemistry ....................................................... 40
5.2. TRANSPORTATION MANAGEMENT PLAN ..................................................................................................... 41
5.2.1. Transportation Infrastructure ................................................................................................................... 43
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
iii
97918-GEN-EMP-N-001-R2 14 June 2010
5.2.2. Street Access to the Sydney Tar Ponds and Coke Ovens Sites .................................................................. 44
5.2.3. Study Area Traffic Volumes and Vehicle Collisions ................................................................................. 45
5.2.4. Traffic Generators .................................................................................................................................... 50
5.2.5. Impacts on Transportation Infrastructure ................................................................................................ 52
5.2.6. Environmental Impacts ............................................................................................................................. 52
5.2.7. Contractor Traffic Responsibilities ........................................................................................................... 53
5.2.8. Conclusions and Recommendations .......................................................................................................... 54
5.3. LAND USE AND INSTITUTIONAL LAND CONTROLS ...................................................................................... 55
5.3.1. Land Use Designation ............................................................................................................................... 56
5.3.2. Future Land Use in the North End of Sydney ........................................................................................... 56
5.4. QUALITY ASSURANCE QUALITY CONTROL MEASURES PROGRAM ............................................................. 57
5.4.1. Quality Management Plan ........................................................................................................................ 58
5.4.2. Quality Control Plan ................................................................................................................................. 59
5.4.3. Independent Quality Assurance Plan ........................................................................................................ 60
6.0 ENVIRONMENTAL PROTECTION PLANS ................................................................................................. 61
7.0 MONITORING PLANS ...................................................................................................................................... 63
7.1. BACKGROUND............................................................................................................................................. 63
7.2. CONSTRUCTION/MITIGATION MONITORING ................................................................................................ 64
7.2.1. Purpose and Objective .............................................................................................................................. 64
7.2.2. Real Time Air Monitoring ......................................................................................................................... 65
7.3. AIR MONITORING – NOT IN CONTRACT (NIC) ............................................................................................ 65
7.3.1. Real-time Air Monitoring .......................................................................................................................... 65
7.3.2. Real-time Monitoring ................................................................................................................................ 66
7.3.3. Target Emissions ....................................................................................................................................... 67
7.3.4. Monitoring Duration and Frequency ........................................................................................................ 68
7.3.5. Monitoring Location ................................................................................................................................. 69
7.3.6. Real-time Protocols and Equipment ......................................................................................................... 69
7.3.7. Weather Conditions .................................................................................................................................. 70
7.3.8. Site Action Levels ...................................................................................................................................... 70
7.3.9. PM10 Action Levels and Measures ........................................................................................................... 70
7.3.10. TVOCs Action Levels and Measures ....................................................................................................... 72
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
iv
97918-GEN-EMP-N-001-R2 14 June 2010
7.3.11. Noise Monitoring .................................................................................................................................... 74
7.3.12. Surface Water Monitoring ...................................................................................................................... 76
7.3.13. Short Term Cap Monitoring .................................................................................................................... 78
7.3.14. Visual Inspection ..................................................................................................................................... 79
7.3.15. Environmental Inspection Logs............................................................................................................... 79
7.3.16. Adaptive Management............................................................................................................................. 80
7.4. REGULATORY COMPLIANCE MONITORING.................................................................................................. 81
7.4.1. Battery Point/Sydney Harbour .................................................................................................................. 82
7.4.2. Effluent Discharge .................................................................................................................................... 82
7.4.3. Air Emissions ............................................................................................................................................ 82
7.5. ENVIRONMENTAL EFFECTS MONITORING ................................................................................................... 82
7.5.1. Ambient Air Monitoring ............................................................................................................................ 83
7.5.2. Surface Water Monitoring ........................................................................................................................ 86
7.5.3. Aquatic Monitoring in Sydney Harbour .................................................................................................... 86
7.5.4. Avifauna Monitoring ................................................................................................................................. 87
7.6. LONG TERM MONITORING .......................................................................................................................... 88
7.6.1. Cap Monitoring Plan ................................................................................................................................ 88
7.6.2. Groundwater Monitoring Plan ................................................................................................................. 89
7.7. MONITORING RESULTS REPORTING ............................................................................................................ 90
8.0 CONTINGENCY AND EMERGENCY RESPONSE PLANS ........................................................................ 91
8.1. EMP CONTINGENCY PROTOCOLS ............................................................................................................... 91
8.1.1. Failure to Comply Contingency Plan ....................................................................................................... 91
8.1.2. Fuel and Hazardous Material Spills Contingency Plan ........................................................................... 93
8.1.3. Malfunctions and Accidents Contingency Plan ........................................................................................ 97
8.1.4. Fire Response Contingency Plan .............................................................................................................. 98
8.1.5. Environmental Contingency Plan ........................................................................................................... 100
8.1.6. Restricting Public Access Contingency Plan .......................................................................................... 104
8.1.7. Erosion/Sedimentation to Surface Water Contingency Plan ................................................................... 105
8.1.8. Dewatering Contingency Plan ................................................................................................................ 107
8.1.9. Archaeology and Heritage Resource Contingency Plan ......................................................................... 107
8.1.10. Unexpected Site Conditions Contingency Plan ..................................................................................... 111
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
v
97918-GEN-EMP-N-001-R2 14 June 2010
8.1.11. Cumulative Effects Contingency Plan ................................................................................................... 113
8.1.12. Key Contact List .................................................................................................................................... 115
8.2. CONTINGENCY PLANNING IN DETAILED EPPS .......................................................................................... 115
8.3. IMPLEMENTATION RESPONSIBILITIES ........................................................................................................ 116
9.0 ENVIRONMENTAL AWARENESS TRAINING ......................................................................................... 117
9.1. SPECIFIC ENVIRONMENTAL AWARENESS PROGRAMS ............................................................................... 119
9.1.1. Decontamination ..................................................................................................................................... 119
9.1.2. Spills Response........................................................................................................................................ 120
9.1.3. Fire Response.......................................................................................................................................... 121
9.1.4. Discovery of Unexpected Site Conditions ............................................................................................... 121
9.1.5. Archaeology and Heritage Resources ..................................................................................................... 122
10.0 COMMUNICATION AND REPORTING .................................................................................................... 122
10.1. COMMUNICATION ..................................................................................................................................... 122
10.2. PUBLIC REPORTING PROTOCOL ................................................................................................................. 123
10.2.1. Reporting Results .................................................................................................................................. 124
10.2.1.1. Areas Subject to Public Reporting .............................................................................................................. 124
10.2.1.2. Reporting Guidelines for Monitoring Results ............................................................................................. 126
10.2.1.3. Monitoring Parameters ................................................................................................................................ 127
10.2.1.4. Reporting Frequency ................................................................................................................................... 128
10.2.1.5. Communication Methods ............................................................................................................................ 128
10.3. REPORTING ............................................................................................................................................... 129
10.4. DOCUMENT CONTROL ............................................................................................................................... 130
10.5. ENVIRONMENTAL AUDITS ........................................................................................................................ 130
11.0 REFERENCES ................................................................................................................................................ 132
Tables
Table 1: Operational Discharge Criteria………………………………………………………………….. 35
Table 2: Water Sources and Management .................................................................................................. 36
Table 3: Annual Average Daily Traffic Volumes for Study Area Roads ................................................... 46
Table 4: Seasonal Variation in Average Daily Volumes ............................................................................ 48
Table 5: Five Year (1999 to 2003) Collision Data for Study Area Roads .................................................. 49
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
vi
97918-GEN-EMP-N-001-R2 14 June 2010
Table 6: Estimated Project Vehicle Volumes ............................................................................................. 51
Table 7: Selected Business Industrial Locations, Corridors and Nodes in the CBRM Former and Proposed
Land Uses ................................................................................................................................................... 56
Table 8: Quality Management Metrics from the QMP ............................................................................... 58
Table 9: Summary of Project Real-Time Action Levels PM10 .................................................................. 71
Table 10: Summary of Project Real-Time Action Levels for TVOC ......................................................... 73
Table 11: Summary of Real-Time Action Levels and Action Measures .................................................... 73
Table 12: Spill Report Requirements .......................................................................................................... 96
Table 13: Cumulative Effects, Mitigations Measures and Significance ................................................... 114
Table 14: Monitoring Parameters ............................................................................................................. 127
Table 15: Monitoring Report Frequencies ................................................................................................ 128
Figures
Figure 1: Design Organizational Chart ....................................................................................................... 23
Figure 2: Construction Organizational Chart .............................................................................................. 24
Figure 3: Fish Removal ............................................................................................................................... 40
Figure 4: Access Locations ....................................................................................................................... 475
Figure 5: Major Transportation Access Facilities & Traffic Volumes ....................................................... 47
Figure 6: Baseline Noise Monitoring Locations ......................................................................................... 75
Figure 7: Adaptive Management Procedure ............................................................................................... 81
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
vii
97918-GEN-EMP-N-001-R2 14 June 2010
Appendices
Appendix A Project Site Overview
Appendix B Change Protocol Document
Appendix C Conceptual Site Models
Appendix D Summary Base Project Schedule
Appendix E Quality Assurance Procedure Audits
Appendix F Environmental Inspection Log
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
viii
97918-GEN-EMP-N-001-R2 14 June 2010
Acronyms used in Report
CQCP Contractor Quality Control Plan
AADT Annual Average Daily Traffic
AHASP Assignment Health and Safety Plan
All Tech All Tech Environmental Consultants
AMEC AMEC Earth and Environmental
AMP Air Monitoring Program
ASTM American Society for Testing and Materials
BTEX Benzene, Toluene, Ethylbenzene, Xylene
C&D Construction and Demolition Debris
CAEAL Canadian Association of Environmental Analytical Laboratories
CBCL CBCL Limited
CBRM Cape Breton Regional Municipality
CBRMC Cape Breton Regional Municipality Council
CEAA Canadian Environmental Assessment Act
CEPA Canadian Environmental Protection Act
CO1 Coke Oven Brook Connector Sediment Removal and Disposal
CO2 Tar Cell Solidification/Stabilization
CO5 Vertical Cutoff Walls
CO6 Coke Ovens Surface Cap
CO7/CO8 Coke Oven Water Treatment Plant & Groundwater Collection
COC Chemical of Concern
CPT Cooling Pond Treatment
CQC Contractor Quality Control
CQCP Construction Quality Control Plan
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
ix
97918-GEN-EMP-N-001-R2 14 June 2010
CRA Conestoga Rovers and Associates
CSM Conceptual Site Model
DFO Fisheries and Oceans Canada
EA Environmental Assessment
EEM Environmental Effects Monitoring
EHS Environmental, Health and Safety
EIS Environmental Impact Statement
EM Environmental Monitor
EMC Environmental Management Committee
EMP Environmental Management Plan
EPP Environmental Protection Plan
GAC Granular Activated Carbon
GCL Geosynthetic Clay Liner
GCS Groundwater Collection System
GDC Groundwater Discharge Chemistry
GFP Groundwater Field Program
GNS Government of Nova Scotia
GOC Government of Canada
HASP Health and Safety Plan
HDPE High-Density Polyethylene
IE Independent Engineer
IQAC Independent Quality Assurance Contractor
IQAP Independent Quality Assurance Plan
JDAC Jacques Whitford, Dillon Consulting, ADI Limited and CBCL Limited
JRP Joint Review Panel
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
x
97918-GEN-EMP-N-001-R2 14 June 2010
LTM Long term monitoring
MHASP Master Health and Safety Plan
MOA Memorandum of Agreement
NAPS National Air Pollution Surveillance
NSE Nova Scotia Department of Environment
NSTIR Nova Scotia Department of Transportation and Infrastructure and Renewal
PAH Polycyclic Aromatic Hydrocarbon
PCB Polychlorinated biphenyl
PDO Property Damage Only
PIP Project Implementation Plan
PM Particulate Matter
PMC Project Management Committee
POLs Petroleum, Oils or Lubricants
PPE Personal Protective Equipment
PRP Public Reporting Protocol
PWGSC Public Works and Government Services Canada
QA/QC Quality Assurance/Quality Control
QC Quality Control
QCP Quality Control Plan
QMP Quality Management Plan
RAER Remedial Action Evaluation Report
RFP Request for Proposal
RMP Remedial Management Plan
S/S Solidification/Stabilization
SPAR Sydney Port Access Road
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
xi
97918-GEN-EMP-N-001-R2 14 June 2010
SSP Steel Sheet Piles
Agency Sydney Tar Ponds Agency
TMP Transportation Management Plan
TP2 Material Processing Facility– Construction and Operation
TP6A Flow Diversion
TP6B Solidification/Stabilization (S/S) and Channel Construction
TP6C Construction of Ferry Street Bridge
TP6D Construction of Access Roads
TP7 Tar Ponds Surface Cap
VEC Valuable Ecosystem Components
VOC Volatile Organic Compound
WMP Water Management Plan
WTP Water Treatment Plant
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
xii
97918-GEN-EMP-N-001-R2 14 June 2010
Units used in Report
m3 cubic metres
ppm parts per million
NTU Nephelometric Turbidity Units
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
1
97918-GEN-EMP-N-001-R2 14 June 2010
1.0 INTRODUCTION
The Government of Canada and Province of Nova Scotia have committed to remediate the Sydney Tar
Ponds and Coke Ovens Sites, a project to be managed and implemented by the Sydney Tar Ponds Agency
(The Agency). There are two (2) goals of the remediation effort. First is to reduce the health and
ecological risks to area residents and the environment from existing soil, sediment and water
contamination. Second is to enhance the development potential of the land to drive economic investment
in the Cape Breton Regional Municipality (CBRM). Figure 1 in Appendix A shows the Project site
Overview.
This EMP has been developed and updated to protect the environment during activities associated with
the Remedial Design and Construction Oversight of the Sydney Tar Ponds and Coke Ovens Sites (the
Project), by communicating to all project participants and stakeholders the commitment and efforts to be
undertaken to manage and minimize potential environmental impacts. As the proponent, the Agency is
required to complete an EMP prior to submitting an application for Part V Approval(s) under the
Environmental Act (Government of Nova Scotia [GNS], 1995a) to conduct remediation work. As the
EMP is a living document, it is updated on a routine basis to address situations that may not have been
identified in previous revisions.
The overall objective of the EMP is to provide a comprehensive strategy for ensuring compliance with the
relevant environmental legislation, policies and permitting requirements, to provide a Project
Environmental Management Plan and to ensure that the environment is protected throughout the life of
the Project. This EMP complies with the Nova Scotia Department of Environment‟s (NSE)
Environmental Assessment (EA) Approval Terms and Conditions under Part IV of the Environment Act
(GNS, 1995a).
The document will also promote the implementation of Panel Recommendations as agreed to by
governments.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
2
97918-GEN-EMP-N-001-R2 14 June 2010
1.1. Project Overview
The Agency is the management and implementation Agency, acting under a Memorandum of Agreement
(MOA) between the Government of Canada and the Province of Nova Scotia. The Agency‟s mandate is
to remediate the Sydney Tar Ponds and Coke Ovens Sites in the Cape Breton Regional Municipality.
Detailed definition of the project and related work activities are being developed during the detailed
design engineering phase of the project. This includes a broad range of activities primarily based on
solidification/stabilization (S/S) over an eight (8) year period. The work itself will be performed in
accordance with the Project Description and associated Work and Management Plans developed for the
Agency. Construction activities will be directly contracted to the Agency under the oversight of
AECOM/CBCL (the Consultant). Accordingly, this Project EMP and associated Project Environmental
Protection Plan (EPP) provided under a separate cover, serve as umbrella documents to guide
environmental protection aspects of all relevant site activities during the tenure of the remediation project.
The development and maintenance of environmental management planning initiatives are an integral part
of the scope of work. This includes remedial management plans, air, groundwater and cap monitoring
programs, environmental effects monitoring (EEM) programs and mitigative measures and monitoring
plans; in addition to a Health and Safety Plan (HASP) (submitted under separate cover).
Detailed construction-phase activity specific EPPs, for design engineering and construction activities
alike, will be developed as tasks/activities are fully defined during the design portion of the project and
submitted with the 75%, 95% and 100% design submissions.
1.2. Historical Background
The Tar Ponds and Coke Ovens Sites are a legacy of the steel and coking industries that operated in
Sydney for most of the 20th Century. The former Coke Ovens provided coke for the local steel
manufacturing industry, while the by-products, such as tar and ammonia were used to manufacture
various other commercial products. Historic by-product and waste management practices, including the
storage of tars in tanks and lagoons, disposal of wastewaters to brooks and the adjacent estuary and site
backfilling/land reclamation practices have resulted in significant impacts to soil, surface and
groundwater and sediment at the Site.
Growing understanding of contamination and its impacts, combined with the steel industry‟s financial
difficulties, led to some drastic changes. Efforts to modernize the steel plant were undertaken but failed
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
3
97918-GEN-EMP-N-001-R2 14 June 2010
and the plant subsequently closed, while a series of ongoing site studies and proposed solutions set the
stage for the current cleanup plans. In fact, numerous previous studies have contributed to the
Remediation Plan for the Tar Ponds and Coke Ovens Sites.
The Muggah Creek tidal estuary, otherwise known as North and South Tar Ponds, covers an area of
approximately 34 hectares. This tidal estuary contains over 700,000 tonnes (550,000m3) of Polycyclic
aromatic hydrocarbons (PAH) and metals-contaminated sediments which relate to the adjacent historic
steel mill and Coke Ovens operation. Approximately 5% of the sediments encountered in the Tar Ponds
also contain Polychlorinated biphenyls (PCBs) at concentrations exceeding 50ppm.
The 68 hectare Coke Ovens Site operated from 1901 to 1988. An estimated 560,000 tonnes (280,000m3)
of soil at the Coke Ovens Site has been contaminated with petroleum hydrocarbons, PAHs and metals.
An additional 1,300 tonnes (1,000m3) of PAH-contaminated sediment has been identified in Coke Oven
Brook and connector and 25,000 tonnes (12,500m3) of contaminated soil is located in the in-ground Tar
Cell at the Coke Ovens Sites.
1.3. Project Environmental Mechanism
On May 12, 2004, the Minister of Public Works and Government Services Canada and the Premier of
Nova Scotia signed a MOA to jointly remediate the Tar Ponds and Coke Ovens Sites in Sydney, Nova
Scotia. This Project was subject to an EA pursuant to the Canadian Environmental Assessment Act
(Government of Canada [GOC], 1992a) and provisions of Part IV of the Nova Scotia Environment Act
(GNS, 1995a). A Joint Review Panel was established under the Agreement for the Joint Panel Review
(Canadian Environment Assessment Agency & NSE, 2005) of the Sydney Tar Ponds and Coke Ovens
Sites Remediation Project.
To satisfy the EA, an Environmental Impact Statement (EIS) was prepared by AMEC Earth &
Environmental (AMEC, 2005a) in association with Jacques Whitford Limited and ADI Limited on behalf
of the Agency and submitted to the Joint Review Panel and relevant regulatory authorities for the
Remediation of Sydney Tar Ponds and Coke Ovens Sites.
AECOM completed a preliminary engineering and cost estimation project (“the Pre-design”) as part of
the overall remediation of the Tar Ponds and Coke Ovens Sites. The Pre-design followed on the
publication of the Project Description (AMEC, 2005b) tailored to meet the requirements of the Canadian
Environmental Assessment Act and the Nova Scotia Environment Act (GOC, 1992a; GNS, 1995a). The
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
4
97918-GEN-EMP-N-001-R2 14 June 2010
Project Description (AMEC, 2005b) is an assemblage of remediation options, for each of the Tar Ponds
and Coke Ovens Sites selected from those presented as being acceptable following the earlier Remedial
Action Evaluation Report (RAER) process (CBCL & ENSR, 2003).
Subsequently, in the Fall of 2006 the Agency retained the Consultant to complete the Design and
Construction Oversight Services for Remediation of the Tar Ponds and Coke Ovens Sites. The proposed
Remediation Program will focus on two (2) primary sites, identified as the Coke Ovens (including Coke
Oven Brook Connector running from Victoria Road to the South Tar Pond) and the Tar Ponds (including
both the North and South Tar Ponds). The remedial strategy focuses on the S/S of contaminated materials
within both of the Tar Ponds and Coke Ovens Sites.
1.4. Objectives of the EMP
This EMP will apply to all Project elements, span the life of the Project and provide a framework for the
environmental management of the entire Project. The Project-wide environmental management approach
is defined in the EMP; however, more detailed environmental management provisions will be outlined in
the Project and Detailed EPPs. While the EMP is meant to provide the Project with stable and consistent
environmental guidelines, should changes in scope of the Project occur, or if changing or unexpected
conditions are encountered during construction activities, the EMP will be reviewed and modifications
made to ensure the EMP remains comprehensive. Any revisions to the EMP will be reviewed and issued
in the form of an addenda in accordance with Section 1.5.
The specific objectives of the EMP are to:
Clearly state the environmental protection policies and philosophy to be followed on the Project.
Set the appropriate environmental objectives and framework.
Identify the relevant legislative, regulatory and approval requirements for the Project and review
these requirements for each element to ensure that all approvals and permits are obtained in advance.
Identify applicable mitigation measures and follow-up requirements provided in the EIS document.
Provide a framework for the development of the Project EPP and the element specific Detailed EPPs
during the construction phase of the Project and long term EEM Plans. Detailed construction specific
environmental protection plans will be presented in the element EPPs.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
5
97918-GEN-EMP-N-001-R2 14 June 2010
Establish contingency and response procedures related to the discovery of unexpected site conditions
(i.e.: archaeology artifacts, spills).
With respect to environmental protection, establish clear roles and responsibilities for the engineering
team and Contractor(s), including work accountability and institution of regular reporting protocols.
Ensure that potential environmental problems are anticipated; and, contingency and emergency
response plans for dealing with unplanned events such as spills are developed and implemented.
Ensure safe, rapid and effective response to unexpected and emergency situations.
Establish procedures for the appropriate control and management of materials, vehicles and
equipment, noise, etc.
Require the implementation of environmental awareness training to ensure that all on-site personnel
understand the importance of environmental protection, the causes of environmental damage, proper
environmental protection practices and their obligations to ensuring that the environment is protected.
Establish a compliance monitoring program to verify that the environmental protection measures
outlined in the EMP and associated documents are being properly implemented and maintained.
Establish protocols for activity and long-term specific EEM Programs.
Establish contributory initiatives to federal follow-up monitoring requirements.
Ensure that proper records are maintained and monitor the effectiveness of the EMP.
Establish a process for analyzing the results of inspection and monitoring and review with
management.
Develop and implement an environmental Quality Assurance/Quality Control (QA/QC) Program to
ensure that environmental protection measures are properly implemented.
Establish communication and reporting protocols.
1.4.1. Content of the Environmental Management Plan
With these objectives in mind, the Environmental Management Plan (EMP) addresses the following main
components:
Remedial Management Plan;
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
6
97918-GEN-EMP-N-001-R2 14 June 2010
Regulatory Approvals, Authorizations and Permits;
The Environmental Management Team Organization, Structure and Responsibilities;
Management Plans;
Environmental Protection Plans;
Monitoring Plans;
Contingency and Emergency Response Plans;
Environmental Awareness Training; and
Communication and Reporting.
In addition, the EMP sets standards for the QA/QC requirements necessary to ensure that environmental
quality is achieved throughout all phases of the Project.
Once approved, this EMP and its amendments will be a binding environmental plan for the Project and
along with the EPPs, will set the environmental protection requirements to be incorporated into the
construction contract documents.
1.5. Maintenance of the EMP and Change Protocol Document
The EMP has been designed to reflect the proposed construction activities and identified environmental
conditions at the Site. Over the course of the Project, the scope of work may change, be expanded or
modified to accommodate lessons learned, or be revised to confront unforeseen environmental conditions.
Any of these occurrences could change what guidelines are necessary in the EMP. In such an event, the
EMP will be reviewed to ensure that the EMP adequately addresses these new considerations from an
environmental perspective. If it is determined that the EMP does not address the potential environmental
implications of these changes, an amendment to the EMP will be issued. Any significant revisions to the
EMP will be reviewed by the Agency, Environmental Management Committee (EMC) and NSE as per
the provincial Conditions of Approval. Issuance of the EMP and any amendments will be documented in
the Change Protocol Document found in Appendix B.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
7
97918-GEN-EMP-N-001-R2 14 June 2010
1.6. Environmental Policy, Guiding Principles and Commitment to Mitigation
The Agency is committed to ensuring that the following environmental policies are adhered to:
The Project is constructed in accordance with sound principles of environmental stewardship and
regard for the sustainability of the earth‟s ecosystem.
The Project construction activities are carried out in compliance with existing environmental laws,
regulations, guidelines, practices and procedures.
The Project remedial design and construction activities will conform to best management practices
and industry standards.
The Project construction activities will implement, monitor and maintain the mitigation measures
identified as part of the EA/Joint Panel Review (JPR) Process.
The Project remedial design and construction activities will provide for the protection of human
health and environment.
The EMP is based on the following guiding principles to ensure environmental protection:
Commitment – The Contractor(s), as defined in Section 4.8, will be committed to ensuring that their
operations are conducted in a manner consistent with this EMP and their own Environmental Policies.
The Agency will be accountable for ensuring that all aspects of the EMP are implemented.
Environmental Responsibility – Environmental protection is everyone‟s responsibility. All
construction personnel and staff directly involved in the Project will be informed of this responsibility
and will be trained and given authority to undertake the necessary actions to protect the environment.
To this end, all staff shall be made familiar with the incident reporting and response protocols for
reporting environmental incidents, as laid out in Section 8, Contingency and Emergency Response
Planning. Staff environmental protection initiatives will be recognized by the Agency, while failure
to fulfil environmental protection obligations will not be tolerated.
Continuous Improvement – This EMP is based on a philosophy of continuous improvement of
environmental protection practices through a program of inspection, monitoring and review.
Proactive Communication – Agency, the Consultant and the Contractor(s) are committed to
identifying various means of working proactively with regulatory agencies and the public to address
potential environmental concerns throughout the process, not just when issues arise.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
8
97918-GEN-EMP-N-001-R2 14 June 2010
Integrated Approach – Agency, the Consultant and the Contractor(s) will employ an integrated
management approach so that environmental concerns are integrated into the planning and
implementation phases to avoid or minimize the environmental impacts of construction.
These environmental principles are the cornerstone against which all activities will be tested during
construction.
This EMP confirms that the Agency, the Consultant and the Contractor(s) are committed to mitigating
adverse environmental impacts associated with construction of the Project through the following
principles:
All materials (hazardous and non-hazardous) will be handled so as to protect human health and the
environment.
Activities will be planned and implemented and equipment will be managed and maintained in a
manner that minimizes impacts on the environment.
EPPs will be developed prior to and implemented during construction and post construction. Long
term environmental effects monitoring will be developed and implemented to ensure appropriate
identification of impacts and to enable corrective and mitigative action.
Measures will be put in place and implemented in order to prevent the accidental discharge of
contaminants into soils, surface water and/or groundwater. Any accidental contamination will be
reported by the Owner (Agency) to NSE by contacting the environmental emergencies reporting
centre by telephone at (902) 426-6200 and cleaned up as per Provincial requirements. In the event of
a spill in the estuary/marine environment, the reporting agency is the Canadian Coast Guard Regional
Operations Centre Nova Scotia 1-800-565-1633 (twenty-four (24) hour emergencies).
Hazardous wastes produced will be managed in accordance with applicable laws and regulations.
Erosion control measures will be designed, implemented and maintained to ensure that there is no
increased sediment loading to surface waters and/or sewer systems leaving the Project site. Given the
importance of natural habitats for sustaining plant, animal and aquatic life, the Contractor(s) will be
responsible for implementing control measures to adequately protect natural habitats.
The Contractor(s) will be responsible for carrying out mitigation measures as prescribed and approved by
the Agency including, but not limited to the following:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
9
97918-GEN-EMP-N-001-R2 14 June 2010
Environmentally sensitive designs intended to lessen or eliminate potential adverse effects.
Environmentally responsible and sound construction practices.
Strict adherence to federal, provincial, municipal and other applicable regulations, guidelines,
standards, policies, permits and authorizations and implementation of all mitigation measures
identified through the EA/JPR Process.
Environmental impacts attributable to the Contractor shall be rectified, at the Contractor(s)‟s expense, to
the satisfaction of the Agency and the Consultant, as per the Contract.
2.0 REMEDIAL MANAGEMENT PLAN
The EMP‟s Remedial Management Plan (RMP) lays out the scope of the Sydney Tar Ponds and Coke
Ovens Remediation Project and provides a general overview of the Project components, sequencing and
timelines. The Project involves two (2) distinct areas (Tar Ponds and the Coke Ovens) to undergo
remediation activities. Work in each of these areas is divided into several separate design elements.
These distinct areas are described within the RMP and a brief description of each Project element is
provided. In addition, the RMP sets out the sequencing with which each element is to be completed,
accounting for environmental contamination considerations and what Project elements must be completed
for others to continue. Finally, the RMP outlines the Project Schedule and Key Project Milestones.
2.1. Project Description
The Agency, in conjunction with the Federal and Provincial governments, developed a proposed cleanup
plan for the Project by utilizing numerous engineering and scientific studies and by consulting extensively
with the public since 1996. Through these thorough research methods, a remediation strategy was
developed for the Tar Ponds and Coke Ovens Sites consisting of the following key components:
Controlling surface water and groundwater at the Tar Ponds and Coke Ovens;
Treating in-place selected contaminants;
Containing remaining contaminants;
Site surface restoration ; and
Developing long-term monitoring and maintenance plans.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
10
97918-GEN-EMP-N-001-R2 14 June 2010
The main components that will be involved in implementing the proposed remediation strategies for the
Tar Ponds and Coke Ovens Sites are provided below:
2.2. Tar Ponds
The strategies that will be involved in the remediation efforts of the Sydney Tar Ponds include:
a) Control Water: Watercourse diversion utilizing pump stations and pipelines will redirect surface
water flowing through the Tar Ponds. This will isolate brooks and streams from contaminated Tar
Ponds sediments. Groundwater will be controlled through trenches to be constructed in the Tar Ponds
area.
b) Treat Selected Contaminants In-place: Sediments will be solidified and stabilized in-place with a
binder, such as Portland cement, using excavation, augers or grout injection systems.
c) Contain Residual Contaminants: A containment system will be designed and constructed to reduce
human and ecological exposure to contaminants and to prevent the movement of contaminants off-
site. The containment system will consist of an engineered cap and the installation of low
permeability barrier walls or liners around the perimeter of the Tar Ponds, if required.
d) Site Surface Restoration: The Site surfaces will be restored in a manner compatible with natural
surroundings and future site use(s).
e) Long-term Monitoring and Maintenance Plan: Long-term monitoring and maintenance plans will be
developed for the Site to cover the twenty-five (25) year period following completion of the Project.
As a part of these plans, cap, surface water discharges and groundwater monitoring will be conducted.
As per the MOA, following the twenty-five (25) year period after construction, monitoring becomes
the responsibility of the Federal Government and the Provincial Government of Nova Scotia.
Monitoring of Sydney Harbour will become the responsibility of the Federal Government with the
input of the Agency.
2.3. Coke Ovens
The strategies that will be implemented in the remediation efforts of the Sydney Coke Ovens include:
a) Control Water: Diversion channels and barrier walls will be installed to reroute groundwater and
surface water flowing through the Site. This will facilitate the removal and cleanup of contaminated
materials, prevent contamination of surface water and minimize water treatment requirements.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
11
97918-GEN-EMP-N-001-R2 14 June 2010
b) Treat Selected Contaminants: The Tar Cell materials will be solidified and stabilized ex-situ with a
binder, such as Portland cement, using excavation, augers or grout injection systems.
c) Contain Residual Contaminants: A containment system will be designed and constructed to reduce
human and ecological exposure to contaminants and to prevent the movement of contaminants off-
site. The containment system will consist of low permeability vertical walls installed at various
locations around the perimeter of the Coke Ovens and a soil cover designed to facilitate future site
use(s).
d) Site Surface Restoration: Site surfaces will be restored in a manner compatible with natural
surroundings and future site uses.
e) Long-term Monitoring and Maintenance Plan: Long-term monitoring and maintenance plans will be
developed for the Site to cover the twenty-five (25) year period following completion of the Project.
As a part of these plans, cap, surface water discharges and groundwater monitoring will be conducted.
As per the MOA, following the twenty-five (25) year period after construction, it is the responsibility
of the landowner to investigate changes in site conditions in consultation with regulatory bodies.
2.4. Element Description and Layout
A general conceptual description of each element is provided in this section. Detailed construction and
remediation activities for each element can be found in the individual Detailed EPPs and design
documents prepared specifically for each Project element. Each Detailed EPP also includes a task-focused
RMP to guide the sequencing and construction activities of each task.
2.4.1. TP6A – Flow Diversion
During TP6A activities, flows from Coke oven Brook and Wash Brook are diverted from the Tar Ponds
through the use of temporary pumping stations. This approach allows for S/S work to take place without
the influence of the water from these sources or influence from tidal action through the use of cut-off
walls.
The Flow Diversion includes the following scope:
Inlet and outlet structures for bypass pumping;
Construction and operation of pumping stations;
Pipelines to convey the redirected flow;
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
12
97918-GEN-EMP-N-001-R2 14 June 2010
Cut-off walls to assist with management of groundwater;
Outfall modifications; and
Temporary drainage ditches.
TP6A will be divided into three (3) phases: (I) South Tar Pond, (II) The Narrows and (III) Battery Point.
Upon isolation of each phase, the TP6B Contractor will mobilize to the area and begin the S/S process.
Activities will progress as follows:
Isolate the South Tar Ponds at Ferry Street to allow for control of conditions within the South Tar
Pond;
Isolate work area around Ferry Street and realign the sewer line at Ferry Street;
Install steel sheet piling (SSP) or equivalent along the east bank of the Tar Ponds to act as a barrier to
redirect migration of groundwater from the adjacent SYSCO property;
Pump standing water in the South Tar Pond into the North Tar Pond and provide on-going pore and
maintenance pumping to water treatment facility to keep the South Pond dewatered for construction;
Isolate Ferry Street to North Pond Narrows. Complete pump around of water from Ferry Street to
North Pond downstream of Narrows; and
Isolate the North Pond at Battery Point Barrier; repeat the previous process for the isolated section
from the North Pond narrows to Battery Point Barrier to allow for control of conditions within the
North Tar Pond.
2.4.2. TP6B – Solidification/Stabilization (S/S) and Channel Construction
Solidification, Stabilization and Channel Construction includes the following scope of work:
S/S recipe development;
In-situ S/S treatment of sediment in the North and South Tar Ponds; and
Construction of a new clean channel through the North and South Tar Ponds.
The S/S recipe development includes bench scale and pilot scale work. S/S of sediment involves the in-
situ treatment of the Tar Ponds sediments through mixing of the sediments with other materials which
result in a solidified material having properties that meet or exceed the criteria (strength, permeability and
containment) for the Project. The channel design will permanently convey water from Wash Brook and
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
13
97918-GEN-EMP-N-001-R2 14 June 2010
Coke oven Brook to Sydney Harbour. The channel will take into account the need to accommodate the
numerous outfalls that populate the shorelines of the ponds, as well as considerations for fish passage at
low tide. In addition, the channel will also capture a portion of local overland flows and pressure relief
wells to reduce pressure at the underside of the channel.
2.4.3. TP6C – Ferry Street Bridge Construction
The bridge construction will include the construction of a new bridge structure, widening the channel
opening in the existing causeway and maintaining the existing sanitary sewer that runs along Ferry Street.
2.4.4. TP6D – Construction of Access Roads
The access roads construction element will include creation of access roads for Tar Ponds and Coke
Ovens elements.
2.4.5. TP2 – Material Processing Facility
TP2 is comprised of a Material Processing Facility and includes a contractor‟s compound area. The
processing facility will handle materials excavated from the Tar Ponds that will not be going directly into
an isolated Pond area for S/S treatment. The material will be sorted, classified and returned to the
designated area for S/S (if 200mm or less); and if not acceptable material for the S/S recipe, the material
will be sorted, cleaned and either recycled, sent to a licensed facility or the SYSCO landfill. There will be
a structure and amenities block for all the contractor‟s trailers, personnel vehicles, site vehicles and
lunchroom. There will be utility hookups available for sewer, water, hydro and communications. The
wastewater will be directed to a licensed water treatment plant for treatment.
2.4.6. TP7 – Tar Ponds Surface Cap
Following the S/S treatment of Tar Ponds sediments in TP7, further containment and protection will be
provided by capping the treated sediments.
Element TP7 will involve the following activities:
Excavation and installation of a network of groundwater control trenches through the solidified
sediments and into the underlying till unit;
Installation of an HDPE liner or equivalent between the granular trench backfill and the solidified
sediments, to minimize groundwater contact with the sediment (not to extend into the till zone);
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
14
97918-GEN-EMP-N-001-R2 14 June 2010
Installation of groundwater sampling wells near the channel end of each trench to allow recovery of
groundwater samples in the post-construction period;
Installation of the Surface Cap over the North and South Tar Pond sites, following the S/S treatment
of the sediments, consisting of a GCL Liner bedding, GCL Liner, a drainage layer, a clay/till fill and a
topsoil and vegetative cover; and
Provide a cap interface between the realigned channel and the S/S sediments, which will be
constructed during the capping process.
During the maintenance phase of the project, the cap will be inspected (by Agency or their designee) for
settling by completing a topographic survey. The cap will also be inspected (by Agency or their
designee) on an annual basis for integrity. Maintenance details can be found in the cap maintenance and
monitoring plan provided in the Project EPP.
2.4.7. CO1 – Coke Oven Brook Connector Sediment Removal and Disposal
The upper section of Coke Oven Brook Connector covers the area from the upstream end of the culvert
under Victoria Road and then downstream approximately 400m, to just above the rail bridge crossing of
the Coke Oven Brook Connector. The lower section of Coke Oven Brook Connector includes the area
from the rail culvert above SYSCO Gate No.3 to the South Tar Pond. The total area covers
approximately 900m. This element focuses on the removal of contaminated bottom sediments and the
protection of the Coke Oven Brook Connector from coal tar contamination from the SYSCO Site. During
excavation and removal of contaminated material, connector flow will be temporarily diverted from the
construction area. Removal of the contaminated sediments will be based on visual observations at the
time of excavation but will not exceed 1m based on the Project description (practical limit of GCL and
subsequent 1m of backfill). Following excavation, a GCL liner system will be installed under the brook
to prevent tar from entering the brook. A 1m clean layer of backfill will be applied and covered with a
geotextile and a scour protection layer. A low flow channel will be integrated into the bottom
reconstruction for fish passage. A weir will be installed between SYSCO Gate No.3 and Inglis Street
Culvert to allow for fish passage as this area sees a 1.5m drop.
2.4.8. CO2 – Solidification/Stabilization (Tar Cell)
The contaminated material in the Tar Cell on the Domtar Site will be subjected to S/S treatment as a
means of creating a structurally enhanced, low permeable mass that immobilizes contaminants in place.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
15
97918-GEN-EMP-N-001-R2 14 June 2010
The purpose is to provide increased structural strength for capping and to decrease the mobility of
containments. Method of S/S treatment currently being considered is ex-situ treatment under a temporary
structure to enclose mixing operations and control emissions. In-situ mixing is not viable in the Tar Cell
area due to the large number of buried objects, such as concrete footings and abandoned site services. In
addition, the consistency of the material and need to add additional material to the matrix as defined in the
bench scale work require an ex-situ mixing approach. Construction water will be collected and
transported to a water treatment plant for treatment.
2.4.9. CO5 – Vertical Cutoff Walls
The Coke Ovens Site is located in a 3.5km long, 500m wide east-west trending valley within the Muggah
Creek Watershed. The groundwater flow is generally west-northwest down the valley and off-site to the
west. This groundwater flow regime can result in relatively clean groundwater entering the Site and
contacting contaminated material. In addition, groundwater can migrate off site and degrade groundwater
quality off site. Therefore, vertical cutoff walls have been designed to manage these conditions by
diverting clean groundwater around the Coke Ovens Site. The CO5 element includes the following
activities:
Rough grading and excavation of trenches along the north, west and south sides of the Coke Ovens
Site into the underlying clean till;
Installation of sub-drains on the south side (upgradient) of the southwest cutoff wall directed to the
realigned channels;
Stockpiling of excavated material, until transport to the Tar Ponds for S/S treatment is available;
Backfilling the trench with compacted clay/till bentonite/soil slurry up to within 0.5m of the surface;
Backfilling of the remainder of the trench with 0.3m clean clay and 0.2m of topsoil; and
Removal and storage of any subsurface infrastructure encountered during trench excavation for the
construction of the cutoff wall.
2.4.10. CO6 – Coke Ovens Surface Cap
Capping activities undertaken in this element will extend over a large portion of the Coke Ovens and Tar
Cell Sites to create a barrier to contaminated materials and assist with surface drainage. This is essentially
an earthworks job, with grading and installation of an impermeable liner and a topsoil layer being placed
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
16
97918-GEN-EMP-N-001-R2 14 June 2010
over the Site. Contouring, runoff, reduction of infiltration and vegetation management will be considered
during the detailed design of this element.
The activities that are generally associated with the construction of the Surface Cap include:
Manage the interface of the Surface Cap with Cut-off Walls, Coke Oven Brook Channel and
Realigned Channels;
Remove wooden culvert from the Domtar Site;
Install surface cap over the Coke Ovens Site;
Contour grading layer to ensure proper surface water drainage;
Re-vegetation of surface cap by hydroseeding; and
Initiate short term Cap Monitoring Program.
2.4.11. CO7/CO8 – Coke Oven Brook Water Treatment & Ground Water Collection
Elements CO7/CO8 must be completed prior to completion of element CO1 so that the remediated
section of the Cook Oven Brook Connector is not recontaminated by untreated upstream
flows/discharges. In CO7, new groundwater collection lines will be installed along the west side of the
Domtar Site to collect the groundwater flowing west from the Domtar Site and along the Coke Oven
Brook interceptor line to collect groundwater from the Coke Ovens Site. The groundwater collection
system (the interceptor lines) will flow by gravity into a pump station, which will direct the groundwater
to a raw water equalization tank, feeding the CO8 Coke Oven Water Treatment Plant (WTP). The
construction of CO7 will require coordination with CO8 activities. The groundwater will flow by gravity
via the CO7 interceptor lines into a pump station constructed as part of CO7 which will direct the
groundwater to the CO8 Water Treatment Plant (WTP).
Water treatment requirements for the Coke Ovens Site over a twenty-five (25) year period include the
contaminated groundwater from the groundwater collection system to be installed under the Coke Oven
Brook as part of Element CO7. Expected contaminants of concern include petroleum hydrocarbons,
PAHs and metals. The mass transport and hydrology models, expertise and historical information will be
used to determine contaminant concentrations and flow rates from each area. The collected water will
need to be treated to meet the acute lethality test to be in compliance with the Fisheries Act and NSE.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
17
97918-GEN-EMP-N-001-R2 14 June 2010
The treatment considerations for the Coke Ovens Site by itself and in combination with the Tar Ponds
water treatment requirements, will be reviewed and approved by the regulators.
2.5. Conceptual Site Models
Conceptual Site Models (CSMs) have been prepared to describe, in general terms, how Project activities
may contribute to the release of contaminants of concern, how they may be transported and what
receptors those contaminants may reach. These CSMs provide the framework for the development of
Detailed EPPs and mitigation strategies for each activity. Two (2) site wide CSMs have been developed,
one (1) for the Tar Ponds and one for Coke Ovens, showing the numerous Project elements and receptors
that apply. In addition, a detailed CSM has been developed for each element. The CSMs can be found in
Appendix C.
2.6. Sequencing of Project Elements
The sequencing of construction activities for individual project elements is of great importance for the
Project. Sequencing must allow each element‟s progression to fit within the limitations of other work, as
the commencement and continuation of several major Project activities face physical restrictions for
cleanup due to work that must be completed under separate Project elements. In addition to appropriately
sequencing elements for the purposes of maintaining the overall Project Schedule, the staging of
construction activities must be such that cleaned areas are not re-contaminated by further work.
Ultimately, carefully planned sequencing creates a logical succession of element implementation. The
following paragraphs outline the sequencing of Project elements and construction tasks that must be
completed before the commencement of other remediation activities.
The Cooling Pond Treatment and Pilot Scale activities will be the first element. This includes the S/S
treatment of the Cooling Pond and six (6) cells in both the North and South Tar Ponds to demonstrate the
effectiveness of S/S treatment.
Element TP2 (Material Processing Facility) will begin early in the Project construction sequencing as it
will accept materials from many elements. It will be completed to allow for site controlled egress by
means of a central decontamination facility and will also serve various elements by accepting, sorting and
decontaminating debris, waste and oversize materials. An amenities block will be provided allowing
personnel from various elements to change into “dirty” work clothes in the morning and clean clothing
after work hours, as well as providing shower areas.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
18
97918-GEN-EMP-N-001-R2 14 June 2010
CO5 (Vertical Cutoff Walls) will be one of the first elements to start on the Coke Ovens Site. It consists
of the excavation and installation of cutoff walls on the Site in order to manage the groundwater in the
area and to minimize groundwater contact with the most contaminated areas of the Site project.
CO2 (Tar Cell Solidification/Stabilization) consists of ex-situ solidification/stabilization (S/S) treatment
of the Cell on the Domtar Site. CO2 must be completed prior to the progression of CO6 over the Tar Cell
as the Coke Ovens Surface Cap will cover the entire Domtar Site, including the S/S material in the Tar
Cell area.
TP6D (Construction Access Roads) will be completed prior to the commencement of the TP6A (Flow
Diversion) and CO7/CO8 (Coke Ovens Water Treatment Plant & Ground Water Collection). As the
roads will be used to access work areas for those elements and subsequent elements (e.g. TP6B).
TP6A (Flow Diversion) will commence prior to TP6B (S/S and Channel Construction) in order to isolate
sections prior to S/S treatment. TP6A and TP6B will take an estimated four (4) years to complete during
which element TP6C (Ferry Street Bridge Construction) will commence.
CO8 (Coke Ovens Water Treatment Plant) will be commissioned prior to the completion of CO7
(Groundwater Collection System) in order to treat the contaminated groundwater from the groundwater
collection lines to be installed as part of CO7 activities. CO7 will include the construction of the Coke
Oven Brook groundwater collection line and the collection of the Domtar interceptor trench flow and
direct it to CO8. CO7 is also closely linked to TP2 for the processing and disposal of debris. CO7/CO8
must be completed prior to the initiation of CO1 and the commissioning the TP6B channels.
CO6 (Coke Ovens Surface Cap) consists of installation of the surface cap over the Coke Ovens Site.
CO6 must include proper grading at the interface with CO7. Elements CO5, CO2 and CO7/CO8 must be
completed prior to the progression of CO6 in each of those areas.
The Coke Ovens elements are driven by the need to protect downstream areas from upstream
contaminants. Therefore, to protect the Coke Oven Brook Connector, CO1 (Coke Oven Brook Connector
Sediment Removal and Disposal) will only start after CO7/CO8 are completed.
TP7 (Tar Ponds Surface Cap) will begin following the S/S treatment of the Tar Ponds (TP6B).
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
19
97918-GEN-EMP-N-001-R2 14 June 2010
2.7. Project Schedule and Milestones
The Sydney Tar Ponds Project is anticipated to extend into the year 2014; follow the general sequencing
described in Section 2.6. The Summary Base Project Schedule, outlining the anticipated commencement
and conclusion of the individual Project elements, can be found in Appendix D. As shown in the figure,
Project Management Services will extend throughout the life of the project. Project Management
includes all Project communication procedures, local benefits programs, project guidelines and controls,
the Project HASP and implementation plans, including this EMP. Timelines for design, construction and
initiation of long-term monitoring for element-specific activities have also been predicted and the
timelines of specific tasks under each element can be derived from the Project Schedule as well. Project
Milestones are discussed in Section 2.7.1.
2.7.1. Project Milestones
In order to undertake construction and remediation activities, detailed engineering design plans are
required for the various elements to guide task management decisions. As the Consultant,
AECOM/CBCL has been contracted by the Agency to prepare and submit 75%, 95% and 100% Design
Reports in addition to tender review documents for each element. The 75% and 95% reports along with
the tender review documents are then reviewed by the Agency, regulatory agencies and the Independent
Engineer (IE) for approval before the commencement of active remediation construction works.
3.0 REGULATORY APPROVALS, AUTHORIZATIONS AND PERMITS
The Project is regulated under various federal and provincial legislation as well as related policies and/or
guidelines and industry codes of practice. These requirements, in Canada and Nova Scotia, have evolved
over a number of years to increasingly provide environmental protection and sustainable development and
ensure that environmental implications of projects are considered during the planning phase.
The list provides an overview of the regulatory requirements of the Project. While this is not intended to
be an exhaustive list of pertinent federal and provincial legislation and policies, it does provide an
overview of key regulatory requirements for Project planning and implementation. Depending on the
final scope of work as determined in the detailed design, additional relevant legislative, regulatory and
approval requirements may be necessary and will be identified during completion of the detailed design
elements and associated Detailed EPPs. In addition, regulatory requirements will be reviewed on an on-
going basis to ensure that all approvals and permits are obtained in advance of Project activities. A
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
20
97918-GEN-EMP-N-001-R2 14 June 2010
regulatory permits and approvals binder will be maintained and updated regularly to serve as a reference
document for all Contractors and Consultants during construction activities.
3.1. Federal Government of Canada
FISHERIES ACT: A permit from DFO to collect fish prior to construction activity in waters frequented by
fish will be required to comply with Section 30(1) and Section 32 of the Fisheries Act. This will ensure
fish are not exposed to degraded construction waters as the deposit of a deleterious substance cannot be
permitted as mandated by Section 36(3). This will be accomplished by performing a permitted fish
rescue. This permit will be applied for and obtained by each element‟s Contractor.
TRANSPORTATION OF DANGEROUS GOODS ACT AND REGULATIONS: All waste and/or contaminated
materials transported from the Site must be managed and handled as per the requirements of the
Transportation of Dangerous Goods Act and Regulations (GOC, 1992b).
CANADIAN ENVIRONMENTAL PROTECTION ACT (CEPA): All construction activities must be conducted
within the limitations as set out in the CEPA (GOC, 1999). Pollution control, waste management and
control of toxic substances are just some of the regulations found in this Act that must be followed.
3.2. Provincial Government of Nova Scotia
ENVIRONMENT ACT, ACTIVITIES DESIGNATION REGULATIONS: An Approval under the Activities
Designation Regulations (GNS, 1995b), will be required for specific work conducted at the Site. The list
of permits and approvals will include, but not be limited to, the following for the NSE:
Industrial (Division V);
Water (Division 1) Approval; and
Watercourse alteration permit.
ENVIRONMENT ACT, ENVIRONMENTAL ASSESSMENT REGULATIONS: Approvals under the Environmental
Conditions of Approval (GNS, 2003), will be required for specific work conducted at the Site. The
Minister of Environment must approve the project environmental assessment for the project to proceed.
All additional required permits and approvals must be required before initiating any construction
activities.
ENVIRONMENT ACT, AIR QUALITY REGULATIONS: Adherence to the Air Quality Regulations (GNS,
2005) will be required for any site remediation or construction activities.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
21
97918-GEN-EMP-N-001-R2 14 June 2010
ENVIRONMENT ACT, PETROLEUM MANAGEMENT REGULATIONS: Adherence to the Petroleum
Management Regulations (GNS, 2002) will be required for the storage of fuels or refuelling on-site.
ENVIRONMENT ACT, EMERGENCY SPILLS REGULATIONS: Adherence to the Emergency Spills
Regulations (GNS, 1995d) will be required for the remedial and construction activities on-site and shall
be covered by the Emergency Response and Preparedness Plan and site-specific HASPs.
DANGEROUS GOODS MANAGEMENT AND DANGEROUS GOODS TRANSPORTATION REGULATIONS: All
waste materials and/or dangerous goods stored and/or transported from the Site must be managed and
handled as per the requirements of the Provincial Dangerous Goods Management and Dangerous Goods
Transportation Regulations (GNS, 1995e; GNS, 1989a).
NOVA SCOTIA SPECIAL PLACES PROTECTION ACT: An Archaeological Research Permit from the
Department of Tourism and Culture will be required to conduct archaeological surveys or for any activity
that threatens or disturbs sites declared special places under the Special Places Protection Act (GNS,
1989b).
BEACHES ACT: A clearance under the Beaches Act (GNS, 1989c) from the Department of Natural
Resources will be required for works seaward of the ordinary high water mark such as sampling or
remedial activities that take place between the high and low tide mark of a marine or estuarine
environment.
Specific regulations to be applied to the Project will be determined in consultation with the NSE and
provided in the individual Project element EPPs to provide clear guidance to on-site construction
personnel.
3.3. Municipal Government – Cape Breton Regional Municipality
MUNICIPAL GOVERNMENT ACT: The Municipal Government Act (GNS, 1998) grants power to
municipalities to pass by-laws and to govern. Adherence to the following CBRM permits or by-laws will
be required:
Building By-Law and Permits;
Noise By-Law; and
Sewer Use By-Law.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
22
97918-GEN-EMP-N-001-R2 14 June 2010
4.0 ENVIRONMENTAL MANAGEMENT TEAM ORGANIZATION, STRUCTURE
AND RESPONSIBILITIES
The EMP will be managed and implemented by the Agency and the Consultant to ensure that the
activities associated with the remedial design and construction oversight services are undertaken in a way
that protects and sustains the ecosystem and meets the spirit and letter of all applicable legislated
requirements and commitments. Contractor(s) also share in these environmental responsibilities and shall
be responsible for implementing the applicable components of the EMP.
It is the responsibility of the Agency, the Consultant and the Contractor(s) to develop, coordinate and
implement the environmental protection plans, monitoring, contingency plans, emergency response
components and QA/QC during the design and construction of the Project. All organizations will work
together to ensure that all environmental issues or problems are identified and resolved as quickly and
effectively as possible and the appropriate documentation filed.
The following is an outline of the management structure associated with the Project and the
responsibilities associated with the various positions. As the Project evolves, the management structure
may be altered and responsibilities may be added or taken away from these positions and allocated to
others. In addition, field specific roles and responsibilities shall be outlined in more detailed site-specific
environmental protection plans as they are developed.
4.1. Organization and Structure
Figures 1 and 2 provide an overview on the approvals and implementation paths that will be followed
over the life of the Project in order to carry out the remediation activities in accordance with the
procedures outlined in the EMP. The Project involves many individuals and organizations that will be
responsible for implementing the EMP. Further specifications on the general roles and responsibilities of
those involved in the Project follow in the subsequent Sections.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
23
97918-GEN-EMP-N-001-R2 14 June 2010
Figure 1: Design Organizational Chart
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
24
97918-GEN-EMP-N-001-R2 14 June 2010
Figure 2: Construction Organizational Chart
4.2. Environmental Management Committee
On May 12, 2004, the Minister of Public Works and Government Services Canada and the Premier of
Nova Scotia signed a MOA, which outlined the required agreements pertaining to the Sydney Tar Ponds
and Coke Ovens Remediation Project description, governance, financial accountabilities and EA. To
implement the federal and provincial agreements respecting the Project, a Project Management
Committee (PMC) was convened with authorities described in the cost share agreement. This Project
Management Committee later initiated the creation of the EMC. The purpose of the EMC is to inform the
PMC on all environmental aspects of the Project as they relate to the pre-construction, construction and
operation phases of the Project. In this regard, the EMC is responsible for providing guidance to the
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
25
97918-GEN-EMP-N-001-R2 14 June 2010
Agency during the development and implementation of this EMP. In addition, the EMC will consider
and implement, as appropriate, decisions of the PMC involving non-regulatory environmental issues. The
EMC will continue to operate after Project completion for a period of time to be determined by the PMC.
The EMC serves as a forum for information exchange between federal and provincial regulatory and
expert departments on all matters pertaining to the environmental management of the Project.
Specifically, the EMC is responsible for the following:
Auditing and evaluating the development and implementation of the EMP by the Implementing
Agency, including a critical review of the EMP and component documents.
Preparing a results-based evaluation of the environmental plans during the implementation phase.
The EMC will be expected to provide the Agency with expert advice concerning the effectiveness of
these plans throughout the life of the Project.
Informing the PMC on the Agency‟s progress in meeting EMP requirements.
Coordinating federal and provincial interests respecting the mitigation of adverse environmental
impacts.
Participating in the development and implementation of a (mandatory) follow-up program pursuant to
the CEAA.
Liaising with the IE on environmental issues associated with their oversight role for the Project.
Representatives on the EMC include:
Environment Canada;
Health Canada;
Fisheries and Oceans Canada;
Public Works and Government Services Canada;
Transport Canada;
The Nova Scotia Department of Environment and Labour;
Nova Scotia Department of Health Promotion and Protection;
Nova Scotia Department of Transportation and Infrastructure and Renewal;
Natural Resources Canada;
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
26
97918-GEN-EMP-N-001-R2 14 June 2010
Enterprise Cape Breton Corporation;
IE, Ex-officio; and
Agency, Ex-officio.
4.3. Managing Partners
The Minister of Public Works and Government Services Canada (PWGSC) is the designated federal
management lead on the Project with the responsibility of negotiating agreements and protocols with the
Province of Nova Scotia. Through the MOA signed by the Minister of PWGSC and the Premier of Nova
Scotia, the PWGSC is accountable for the management of federal project funds, including the
development of oversight mechanisms to manage these funds with due diligence. In addition, PWGSC is
responsible on behalf of the Government of Canada for liaison with First Nations, public and stakeholder
groups in respect of the Project, as well as the management of federal reporting, submission and
communication requirements.
The Nova Scotia Department of Transportation and Infrastructure and Renewal (NSTIR) is partnering
with PWGSC under the MOA and is responsible for overseeing the implementation of the Project through
a single purpose entity, the Agency. NSTIR administers provincial funds in respect of the Project and is
party to most federal/provincial agreements ensuing from the MOA. As such, NSTIR is accountable for
the provisions of the MOA on the part of the Province.
In order to implement the federal and provincial agreements respecting the Project, the PWGSC/NSTIR
PMC was convened. The PMC is responsible for:
Ensuring that the Project is implemented in accordance with the MOA and its ancillary Agreements.
Providing leadership in areas including, but not limited to, issues related to First Nations, the
environment, community consultation and regional economic development opportunities.
Ensuring that the Project is carried out in a manner that ensures the protection of the environment.
Assisting in the implementation of the EMP on behalf of both levels of government and associated
regulatory authorities.
4.4. Nova Scotia Department of Environment
As summarized on the Canada News Centre Web Site (GOC, 2007), the NSE will act as the lead agency
for regulatory oversight of the remediation project through the conditions of the Environmental
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
27
97918-GEN-EMP-N-001-R2 14 June 2010
Assessment approval and subsequent approvals required under the Environment Act (GNS, 1995a).
Throughout the Project, it is the responsibility of the NSE to review and evaluate the remediation process,
ensuring that all remediation efforts are falling within regulatory guidelines set for air emissions, waste
disposal, water treatment, etc. The Minister of Environment and Labour will also be responsible for
establishing an independent Remediation Monitoring Oversight Board, which will serve to monitor the
regulatory management of the project. Twenty-five (25) years following the completion of the
construction phase of the Project, Nova Scotia will take ownership of the Sites and will be responsible for
all future maintenance and monitoring thereof.
4.5. Sydney Tar Ponds Agency
The Agency is a provincial special operating agency that has been set in place as the implementing
agency for the Project, pursuant to the MOA signed by the Federal and Provincial governments. The
Agency is to provide balance between government accountability and private sector efficiencies.
The Agency‟s fundamental role is to direct, procure and implement the services needed to complete the
Project while protecting the interests of the partners. The Agency is responsible for ensuring that the
cleanup is conducted in an environmentally sound manner through the design and implementation of
monitoring programs that evaluate air and water quality and other environmental parameters. The
purpose of environmental monitoring is to ensure the environmental integrity of the Project and to protect
the public. In addition, the Agency is accountable in acquiring and adhering to any and all required
permits and approvals for the Project.
4.5.1. Agency Project Director
The Agency Project Director (or their designee) is responsible for the overall implementation of the EMP.
This will include having mechanisms in place to ensure that the safety, health and environmental policies
and procedures are being adhered to by contractors and by staff engaged on the project.
4.5.2. Safety, Health and Environmental Coordinator
The Agency has appointed a Safety, Health and Environmental Coordinator who is responsible for safety,
health and environmental management. The following functions fulfill this responsibility:
Coordinate all safety, health and environmental management functions.
Report on safety, health and environmental matters to the Agency Project Manager.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
28
97918-GEN-EMP-N-001-R2 14 June 2010
Monitor compliance with relevant safety, health and environmental standards.
Ensure all project participants have received the required training and any refresher training programs
throughout the duration of the Project.
Document all training programs and certifications.
Act as a spokesperson on safety, health and environmental issues.
4.6. AECOM and CBCL
In support of the overall Remediation Program for the Sydney Tar Ponds Site, AECOM and CBCL were
retained as the Consultant to conduct the Remedial Design and Construction Oversight of the Sydney Tar
Ponds and Coke Ovens Site. The role of the Consultant includes the development of engineering designs
for the remediation elements defined in the Project Description (AMEC, 2005b) and also the gathering of
information related to hydraulic conductivity and S/S and quantity surveys. Specific responsibilities of the
Consultant include:
The completion and verification of detail design documents.
The preparation and completion of all forms and document identified in the Design Plan.
The management of the Design Agency‟s engineering team and approval of all design drawings and
documents produced (providing professional seal as required).
Ensuring the Design Agency is in compliance with Quality Program and Project Quality Plan.
Reviewing and approving Design Agency quality documents.
Performing all architectural related tasks and documents by preparing design drawings and
documents as identified in the Design Plan.
Performing all civil engineering related tasks and documents by preparing design drawings and
documents as identified in this Design Plan. Provides professional seal, when required.
Performing all structural engineering related tasks and documents by preparing design drawings and
documents as identified in this Design Plan. Provides professional seal, when required.
Performing all mechanical engineering related tasks and documents by preparing design drawings and
documents as identified in this Design Plan. Provides professional seal, when required.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
29
97918-GEN-EMP-N-001-R2 14 June 2010
Performing all electrical engineering related tasks and documents by preparing design drawings and
documents as identified in this Design Plan. Provides professional seal, when required.
Performing all process equipment engineering related tasks and documents by preparing design
drawings and documents as identified in this Design Plan.
Preparing Environmental, Health and Safety (EHS) documents.
Reviewing and approving EHS-related documents.
Verifying EMP/EPPs are implemented.
In addition to these specific tasks, the Consultant is responsible for construction oversight and contract
administration of the project elements and the execution of quality management activities. It is the
responsibility of the Consultant to coordinate, oversee and monitor construction and installation activities
by the Contractor and conduct inspections of the work as required, ensuring quality of each Contract
Work Package according to the provisions established in the Project Independent Quality Assurance Plan
(IQAP) and Quality Control Plan (QCP). The Consultant shall assign full time Site representatives,
assisted by both resident and non-resident engineering staff as required, to oversee the on-site activities.
AECOM is responsible for maintaining records of all Consultant-related activities at the Site including
construction oversight, field inspections, field instructions, shop drawing reviews, photographs, meeting
minutes (as required), correspondence, manuals, test results and other pertinent information. The
Consultant will maintain a copy of these records on-site at all times.
AECOM representatives will attend regular site meetings with the Contractor and will manage all change
processes with the Contractors, including Instructions to Contractor, Requests for Field Change, Notices
of Major Field Change and Field Change Records.
The Agency may identify additional measures over those noted herein at any time during the
implementation of the project elements.
4.7. Independent Engineer
The NSTIR, acting on behalf of the federal and provincial governments, has retained the services of an
independent engineer to act in the capacity of the IE. The role of the IE is to ensure that all design and
remediation activities are conducted in accordance with the conditions of the MOA and its
implementation agreements.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
30
97918-GEN-EMP-N-001-R2 14 June 2010
In this capacity, the IE will act as an unbiased third party monitoring the implementation activities,
schedules and expenditures of the Agency and its contractors and the consultants. The IE will, amongst
other things, review procurement documents, schedules, cost estimates and full computational checks of
designs. It is not the IE‟s role to participate in any direct way in the design, construction, or QA/QC of
the Project; nor is the IE to take on the task of correcting any identified deficiency. Any deficiencies
identified by the IE will be directed to the Agency for consideration and resolution.
4.8. Contractors
All contractors and subcontractors working on the Site will be responsible for implementing, enforcing
and maintaining their activities in accordance with the EMP and associated EPPs for the duration of their
contractual activities at the Site. The Contractor(s) holds specific quality management responsibilities in
the planning, execution and management of the activities involved in each project element. The
Contractor(s) are responsible for the preparation of a Contract Work Package for each project element.
The Contract Work Package is to include a Construction Quality Control Plan (CQCP), which documents
the Contractor‟s processes and quality control (QC) procedures for delivering the quality objectives and
standards established for the project, confirming that the requirements of the Agency and regulatory
agencies are satisfied. Additional details on the Contract Work Package and CQCP is provided in the
Project QCP (provided under separate cover).
The Contractor shall also be required to develop a corrective action plan which ensures identified non
conformances, defects and errors are documented and corrected.
Each contractor and subcontractor responsible for the construction of an element will designate an
Environmental Monitor (EM) to ensure that work is being performed in compliance with the EMP and
EPPs. The contractor/subcontractor will ensure that the EM has appropriate training to comply with the
QC requirements of the contract, including all technical provisions. The Contractor‟s staff must be of
sufficient size and have the qualifications necessary to ensure contract compliance, whether work is
performed by the prime contractor or by subcontractors or vendors. The Contractor shall provide proof of
certification, where applicable.
In addition to the above obligations, the Contractor will allow (but does not require or obligate) the
Agency to do its own tests and inspections through an Independent Quality Assurance Consultant
(IQAC). The Contractor is required to accommodate this testing, allow access to Work and provide the
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
31
97918-GEN-EMP-N-001-R2 14 June 2010
equipment necessary to facilitate inspection. This testing is solely for the benefit of the Agency and does
not relieve the Contractor of its quality control and testing obligations.
The Contractors are required to engage any required specialized inspection/testing agencies for inspecting
and/or testing portions of the work as indicated in the Construction Documents. Cost of such services will
be borne by the Contractor and the contractor shall not employ Inspection agencies or labs utilized by the
IQAC.
4.9. Analytical Laboratory
Where laboratory analysis is required as part of quality control, laboratories shall carry the relevant
certification for the analysis. Laboratories will be authorized to operate in Province of Nova Scotia with
qualifications to meet basic requirements of ASTM E35 and shall be accredited by the Canadian
Association of Environmental Analytical Laboratories (CAEAL). These requirements shall also be
included as part of the Contractor‟s specifications. Laboratories shall be required to notify the
Consultant(s) and Contractor(s) of observed irregularities or deficiencies of Work, equipment or material
and promptly submit written report of each test and inspection to each Consultant, Contractor and the
Agency.
4.10. Independent Quality Assurance Consultant
The IQAC shall be retained by the Agency to hold the responsibility for the implementation of the IQAP.
The IQAC shall verify that the Contractor's activities and Quality Control Programs are in compliance
with the contract plans and specifications and report all findings, whether positive or negative, directly to
the Agency. The IQAC shall establish specific reporting mechanisms with the Agency according to their
contract. If the IQAC discovers, to their discretion, any deficiencies in the implementation of the IQAP,
these deficiencies shall be reported immediately by phone to the Contractor for correction and to the
Agency. With respect to the IQAP, the IQAC will be responsible for communicating any instructions
from the Agency to the relevant Contractor(s) and/or other Project management personnel, via the
Contractor‟s or Project management personnel‟s preferred method of on-site communication.
The IQAC is responsible for all activities necessary to manage, control and document activities involved
in the IQAP. The IQAC responsibility includes ensuring adequate quality assurance services are provided
for work accomplished on and off-site by its organization, sub-consultants, technical laboratories and
suppliers. The work activities will include and conform to the requirements as set forth in the IQAP and
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
32
97918-GEN-EMP-N-001-R2 14 June 2010
the contract documents. The IQAC shall engage independent inspection/testing agencies if the IQAC is
unable to independently carry out required inspections or tests as indicated in the IQAP and the contract
documents.
5.0 MANAGEMENT PLANS
While the purpose of the Project EMP as a whole is to communicate to all project participants and
stakeholders the commitment and efforts related to the prevention, management and minimization of
potential environmental impacts during the implementation of remediation efforts, the purpose of the
following Management Plans is to develop strategies to ensure that the goals of the EMP are met.
Management Plans outline specific areas of concern that are associated with major Project components
and propose mitigative measures and programs that will control associated environmental impacts. The
following plans have been developed in association with Agency and regulatory requirements to outline
the Project-wide control measures associated with site activities. The ultimate responsibility for
implementation and maintenance is held by the Agency.
5.1. Water Management Plan
The implementation of the Project will require the management of runoff during precipitation events and
the removal and, in some cases, treatment of surface and groundwater during construction and post
construction. The purpose of this Water Management Plan (WMP) is therefore to manage surface water
runoff and coordinate the pumping around, collection and/or treatment of water from the multiple project
elements to protect the environment by limiting exposure to potentially hazardous substances. This WMP
will be supplemented by more specific water management, collection and discharge details to be provided
in the Detailed EPPs and design documents prepared for individual project elements. The procedures,
guidelines and provisions outlined in this WMP and those described within the element specific EPPs will
be implemented by the Contractor‟s Site Supervisor and supervised by the Agency.
5.1.1. Management of Runoff from Precipitation
Surface water runoff will be managed by the installation of specific diversion control structures such as
berms or ditches. Surface runoff will be intercepted and re-directed to a desirable collection or discharge
point, as required in each element of the Project. Accumulated water through precipitation will be
decanted during circumstances in which the ground has not been disturbed and collected and treated in
circumstances in which the ground has been disturbed (e.g. trenching activities), S/S treatment occurring
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
33
97918-GEN-EMP-N-001-R2 14 June 2010
in area or the runoff is suspected as contaminated through contact with contaminated material or
equipment.
Specific diversion control measures will be installed prior to and used during construction activities. They
shall not be removed until all areas have been sufficiently stabilized. The removal of control measures
will only be undertaken on the authorization of the Construction Site Supervisor, once environmental
inspections have confirmed that the erosion and sedimentation and contamination control performance
objectives have been met.
5.1.2. Management of Watercourses during Construction
Management of watercourses for each element differs, depending on where the watercourse is located
relative to the other activities occurring on Site.
5.1.2.1. Sources of Water
Many of the project elements involve a temporary (for construction purposes) or permanent change (as
part of the remedial design) in the surface or groundwater flow regime. These include:
TP6A and TP6B: Construction of a new permanent channel and groundwater flow management
within the treated Tar Ponds area. Temporary pump stations will collect surface waters from the
Coke Oven Brook and Wash Brook, divert water around the Tar Ponds in three stages as identified in
Section 2.4.1. Ditches will be constructed along the edges of the Tar Ponds to intercept CBRM
stormwater outfalls and temporarily redirect their water flow to the temporary pump station. The
stormwater outfalls will be permanently redirected to the newly constructed permanent channel.
CO1: Coke Oven Brook will be temporarily diverted around the excavation construction site on a
segment by segment basis using gravity and/or pumps as well as a bypass pipe to allow for
construction in the dry.
CO5: A cut-off wall will be installed below grade to redirect groundwater away from the
contaminated soil within the Coke Ovens Site and also contain the groundwater within the Site. Sub-
drains will be installed on the south side (upgradient side) of the southwest cutoff wall which will be
directed to the realigned channels.
CO7/CO8: A groundwater collection system will be installed at the Coke Ovens Site and Coke Oven
Brook. Fredrick Street and Cagney Brook will have structures removed and the channel filled in as
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
34
97918-GEN-EMP-N-001-R2 14 June 2010
water is no longer flowing at these locations (realigned in 2006). Groundwater collection system and
permanent (twenty-five (25) year) treatment plant. CO7: The Groundwater Collection System (GCS)
will manage the groundwater contamination of the Coke Oven Site. The GCS will be designed to
capture contaminated groundwater and convey it by gravity to a wet well using two existing
interceptor lines and two (2) new groundwater collection lines. The water will be pumped to the
permanent water treatment plant for treatment prior to discharge into Coke Oven Brook.
5.1.2.2. Water Management
In some cases, a simple diversion into the ponded areas will be implemented. In other cases, a pump
around the work construction site will be implemented. Regardless of method and whether it will be a
temporary or permanent removal of surface and/or groundwater, all site-specific requirements identified
in the construction plans, conditions of the DFO work permits and all erosion and sediment control
measures shall be implemented by the Contractor and monitored. Surface and groundwater construction
waters as identified in Section 5.1.3 below, will be collected for treatment and subsequent discharge.
5.1.3. Water Collection and Treatment
Construction water includes any water found within the intrusive work area of the construction zone,
including pore water, precipitation, groundwater infiltration, waste water produced from ongoing,
continuous construction activities, such as decontamination and maintenance pumping. Prior to any
removal, release or discharge from the Site the treated construction water that is intended for discharge
from a temporary water treatment facility to a discharge location must meet the operational and/or
compliance discharge criteria developed by AECOM/CBCL and accepted by NSE. The compliance
discharge criterion is bioassay for acute toxicity based on a ninety-six (96) hour LC50 test. The
operational discharge criteria were developed based on CCME Canadian Water Quality Guidelines for the
Protection of Aquatic Life (CCME FWAL) and include values from the Massachusetts Remediation
General Permit (RGP) guidelines (as noted using “EPA” in the text). The operational discharge criteria
are provided in the following table:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
35
97918-GEN-EMP-N-001-R2 14 June 2010
Table 1: Operational Discharge Criteria
Parameter Freshwater Discharge
Criteria
Marine Discharge
Criteria
Organics
Polycyclic Aromatic Hydrocarbons (PAHs)
EPA (Group I Carcinogenic)
Benzo(a)antharacene - -
Benzo(a)pyrene - -
Benzo(b)fluoranthene - -
Benzo(k)fluoranthene - -
Chrysene - -
Dibenzo(a,h)anthracene - -
Indeno(1,2,3-cd)pyrene - -
SUM 10 10
EPA (Group II Probable Carcinogenic)
Acenaphtene - -
Acenapthylene - -
Anthracene - -
Benzo(g,h,i)perylene - -
Fluoranthene - -
Fluorene - -
Naphthalene 20 20
Phenanthrene - -
Pyrene - -
SUM 100 100
Total Petroleum Hydrocarbons
EPA 5 mg/L 5 mg/L
BTEX
Benzene 5 5
Ethylbenzene - -
Toluene - -
Total BTEX 100 100
Inorganics
Aluminium 100 NC
Arsenic 5 12.5
Cadmium 0.017 0.12
Total Chromium 8.9 56/1.5
Copper 2-4 3.7
Iron 1000 1000
Lead 7 8.5
Mercury 0.026 0.016
Molybdenum 73 NC
Nickel 150 8.2
Selenium 1 71
Silver 0.1 2.2
Zinc 30 85.6
Cyanide 5 NC
TSS
30 mg/L 30 mg/L
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
36
97918-GEN-EMP-N-001-R2 14 June 2010
Parameter Freshwater Discharge
Criteria
Marine Discharge
Criteria
pH (pH units) 6.5-9.0 7-8.7
Misc. Organics
PCBs - -
Phenols 4 NC
All parameters are ug/L unless otherwise indicated
NC = Not Calculated
- = No criteria established
Construction water can also be collected and treated using a licensed water treatment facility, in which
case the discharge criteria would be as per the facilities permit and approval.
5.1.3.1. Sources of Water
Source construction waters for treatment and/or management include:
TP6A & B: Prior to the solidification/stabilization (S/S) treatment of the sediments in the Tar Ponds,
dewatering will be required. Surface water in areas of the Tar Ponds that have not yet been treated
will be decanted from the surface to either the ditches and in turn the pump around system or other
Tar Pond areas not yet remediated. Sediment laden/pore water in the treatment zone will be collected
and treated. The water removed through pore and maintenance pumping during the
solidification/sedimentation process will be treated by a WTP. Table 2 details water management for
TP6A and TP6B activities.
Table 2: Water Sources and Management
Source* Treatment Zone Active Zone Non-Active Zone
Precipitation Collect & Treat Decant Decant (as required)
Upwelling Collect & Treat Decant Decant (as required)
Side Infiltration Collect & Treat Decant Decant (as required)
Standing Water at time of isolation N/A – decanted when
classified as Active Zone Decant No Action
Pore Water Use in mix / Collect & Treat
Excess No Action No Action
Equipment Decontamination Collect & Treat Collect &
Treat Collect & Treat
Dust Control Water Use in mix / Collect & Treat
Excess No Dust Control
Decant (pond area)/ Direct to sediment
capture areas (on land)
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
37
97918-GEN-EMP-N-001-R2 14 June 2010
Perimeter ditch outfall (storm drain) collection Collect & Treat Decant Decant
Pump capability bypass from brooks Collect & Treat Decant Decant
Overland Flow Collect & Treat Decant Decant
Notes:
Collect and treat Water is collected and treated to meet established operational and compliance discharge criteria prior to release.
Decant
Water is conveyed to Non-active zones, energy dissipation structure or areas of perimeter ditch with erosion control measures. Water which is to discharge to Non-active zones following treatment of sediment there, energy dissipation structure or areas of perimeter ditch will be done so in a manner to prevent visual evidence of re-suspension of fines.
Use in mix / collect and treat excess Water is included in the matrix of the S/S mixture; excess water is collected and treated.
No Action No action is taken to collect / treat / or otherwise deal with water.
No Equipment No equipment is present in the area
No Dust Control No dust control is undertaken in the area
TP2: Waste water will be generated from material washing, vehicle decontamination and site
personnel washing. The waste water stream will discharge into a collection chamber within the TP2
Processing Area, after passing through a sediment trap and an oil water separator. The water will be
collected and treated by a licensed WTP. Waste water generated from the washroom facility will be
collected and discharged to the Cape Breton Regional Municipality sewer system.
TP7: Water which has contacted the S/S sediments, despite surface water diversion measures, prior to
capping will be collected for treatment in a WTP.
CO1, CO5, CO7 and CO8: Contaminated water will be collected from the construction site and
equipment decontamination area and will be treated at a WTP. Groundwater infiltration into the
construction work area may be pumped to dissipation ponds located on pre-approved locations on the
Coke Ovens site. Dissipation ponds would be excavated on the Coke Ovens site to hold water until it
either dissipated into the ground or was pumped and treated through a WTP.
Numerous project elements involve the pumping of waste water to treatment facilities, both temporary
and permanent. These elements include:
5.1.3.2. Permanent Water Treatment (CO8)
The permanent water treatment facility will be located on the Coke Ovens Site and will treat
contaminated water collected by the Coke Ovens groundwater collection system as part of element CO7.
Contaminated groundwater will be collected and pumped to the water treatment plant. Initial batch testing
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
38
97918-GEN-EMP-N-001-R2 14 June 2010
will be completed to ensure compliance, followed by continuous discharge with compliance testing. The
permanent WTP and associated delivery systems will be designed and maintained to operate well past a
twenty-five (25) year operating life. Flow rates will be determined by the Consultant, reviewed with NSE
and the Agency and approved by NSE. Preliminary and final estimates of flow velocities shall be
included in the Detailed EPPs.
5.1.3.3. Treatment Processes
It is the treatment process in the permanent WTP (CO8) will consist of an oil water separator to remove
free product, sand/clay filters and/or clarifiers to remove suspended solids, ion exchange to remove metals
and granular activated carbon (GAC) filters to remove organics such as PAHs, BTEX and other
hydrocarbons. If these treatment processes are implemented, exhausted ion exchange resin and GAC
media will be returned to the supplier for regeneration and the exhausted sand filters will be landfilled.
Clarifier sludge will be landfilled. However, treatment and disposal methods will ultimately be
determined by the type of contamination and effluent discharge criteria as approved by NSE. Once
treated, groundwater will be discharged to Coke Oven Brook. Treatment and disposal methods shall be
finalized in the element design documents and reflected in the Detailed EPPs.
5.1.4. Compliance under the Federal Fisheries Act
Appropriate treatment and subsequent compliance testing of waste water the permanent WTP will ensure
that liquid effluent discharges to fresh water are compliant with the pollution prevention requirements of
the Fisheries Act. Chemistry of the treated waste water will be monitored according to NSE‟s Part 5
conditions of approval to verify that treatment continues to meet the standards set.
During barrier and pumping station inlets and outlets construction within the Wash Brook and Coke Oven
Brook and within and along the shoreline of the Tar Ponds, there is the potential to directly injure or kill
fish with machinery (i.e., diversion pumps), or to indirectly injure them through smothering with excess
sediment laden water.
To minimize potential fisheries impacts and water quality impacts during construction of the flow
diversion, all site-specific requirements identified in the construction plans, conditions of the DFO work
permits and procedures in the ESCP procedures shall be followed. In addition, excess material, fuels,
controlled materials and construction debris, shall be stored at the temporary materials storage pad area or
in a designated area on gradients that will not allow a spill to easily enter a watercourse.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
39
97918-GEN-EMP-N-001-R2 14 June 2010
Fish must also not be harmed by the pumping stations themselves. To protect fish from both the suction
force and actually entering the pumps, a hydraulic dissipater and series of mechanical screens will be
installed around the pump intake. These will serve to allow the fish to overcome the flow generated by the
pumps and provide a final barrier to prevent their access to the equipment. Fish barriers also prevent
debris larger than 9mm from entering the pump area.
The scale of impact of pumping fresh water into Sydney Harbour will depend on the volume of water
discharged. Mitigation will include discharging as close to the current opening of Battery Point Barrier as
possible into the first of the three energy dissipation outlet structures to effectively mix the water with
seawater. In addition, energy dispersion and silt control will be designed at the discharge location to
minimize erosion and scour.
All fish management work will be guided by fisheries specialists retained by the Contractor(s) to remove
as many fish from the construction areas as possible. The Contractor(s), under the guidance of a fisheries
specialist, shall follow the subsequent procedure to remove fish from the construction as follows:
1. Place a turbidity curtain along the shoreline;
2. Drag one end of a turbidity curtain loosely along the bottom of the pond to create an area devoid of
fish along one shoreline to the construction position (see Figure 3);
3. By starting at the other end and ensuring a relatively good seal, the Contractor(s) shall gently drag the
opposite side of turbidity curtain along the shoreline to the respective construction location;
4. Once the curtain has been fully deployed, the area between the shore and curtain should be void of
fish; and
5. Fish collected in the turbidity curtain shall be relocated away from any other activity taking place at
the site, either further upstream if relocated within the brooks, or downstream of the barrier or to the
completed channel if within the Tar Ponds.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
40
97918-GEN-EMP-N-001-R2 14 June 2010
Figure 3 – Fish Removal
In case all fish are not captured during the removal phase, when water diversion is taking place, the
Contractor(s) will monitor for fish and remove accordingly. This will require:
a) Screens of adequate mesh size (9mm) installed on or around pumps to prevent the removal of fish by
pumps;
b) A net with a long pole or equivalent equipment to be used to capture and release any remaining fish;
and
c) Routine monitoring of pump inlet areas within the Wash Brook and Coke Oven Brook and upstream
transfer of stranded or crowded fish.
5.1.5. Coke Oven Brook Groundwater Quantity and Discharge Chemistry
A Groundwater Investigation Program (GIP), which included groundwater as surface water, was
completed to verify the discharge quantity and chemistry of Coke Oven Brook. The Program involved
sampling seven (7) brook and underdrain locations under three (3) flow conditions (low, moderate and
high). Full results of the GIP are provided under separate cover in a document entitled Groundwater
Investigation Program dated October 4, 2007, and a summary is provided in element CO7‟s Design
Report Appendix entitled Rational for Groundwater Discharge Chemistry. Based on the findings of the
report, the following conclusions were provided:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
41
97918-GEN-EMP-N-001-R2 14 June 2010
The North and South Underdrains will continue to discharge into Coke Oven Brook (ie., the drainage
swale to be constructed in the current brook channel). This flow will not be collected and treated.
The groundwater collection system will be designed to pump up to 150L/min to the Water Treatment
Plant (CO8). This flow is based on the estimate of long term moderate groundwater discharge to the
Coke Oven Brook Groundwater Collection Line and the Domtar Interceptor Trench. Flow in excess
of 150L/min will be allowed to overflow into the Coke Oven Brook drainage swale, on the basis that
the overflow will be substantially diluted by elevated surface water flow at these times.
The on-site section of Frederick Street Brook will be backfilled as part of CO7 grading activities and
the upstream reach will be re-directed into the North Channel.
The Cagney Brook Underdrain will be exposed and backfilled, as part of CO7 grading activities.
Flow from the North and South Channels will continue to discharge into Coke Oven Brook (ie., the
drainage swale to be constructed along the current brook channel). This flow will not be collected
and treated.
The chemistry of upstream surface water coming onto the CO7 contract boundary via Coke Oven
Brook will be acceptable for inclusion in the Coke Oven Brook drainage swale. This flow will not be
collected and treated.
Runoff from precipitation events, over the Coke Ovens Site and CO6 cap will be flow into Coke
Ovens Brook and will not have been exposed to contaminated materials.
5.2. Transportation Management Plan
The preparatory work, construction activities and post-construction work during remediation of the Tar
Ponds and Coke Ovens Sites will require the use of personal transportation vehicles and the intensive use
of heavy construction vehicles, both on and off-site. The use of transportation machineries will result in
extra traffic to local roadways, noise, diesel and other exhaust emissions and airborne particulate matter
(PM) in the form of dust. As such, the purpose of the Transportation Management Plans (TMP) are to
establish controls that will mitigate these impacts Site-wide and to the surrounding area prior to the
commencement of construction activities. Each element will develop a TMP in order to minimize
transportation impacts, consideration is to be given to providing a comprehensive transportation
management strategy, updated as the project evolves. In addition, the TMP assigns specific responsibility
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
42
97918-GEN-EMP-N-001-R2 14 June 2010
to ensure that these controls are implemented successfully and that all Health and Safety Protocols under
HASP are followed.
The Transportation Management Plan includes reviews and recommendations on:
Infrastructure impacts;
Transportation routes;
Timing/Scheduling;
Dust Management/Air Pollution/Noise;
Safety issues and containment measures; and
Monitoring and reporting.
The TMP includes easily accessible mechanisms and proposed mitigation measures to offset any adverse
impacts to the surrounding road network.
During the Project construction phase, noise and/or air quality impacts (e.g., dust, odour) associated with
construction vehicle movement may temporarily pose a nuisance to the nearby residents and
transportation infrastructure. Existing commercial enterprises, within the Sydney downtown core in
particular, could experience similar temporary nuisances.
The primary concerns regarding the potential adverse effects of the Project on transportation
infrastructure include:
a) Traffic Impact on Adjacent Road Networks: Worker and equipment movement associated with the
Sydney Tar Ponds and Coke Ovens Sites will increase traffic volumes on local road networks and
possibly residential or commercial streets.
b) Safety Impact: Worker and equipment movement associated with the Sydney Tar Ponds and Coke
Ovens Sites may cause traffic congestion or increase collision potential at Study Area intersections.
c) Air Pollution Impact: Preparatory work and intensive use of heavy vehicles during construction will
result in diesel exhaust and airborne PM. Based on prevailing wind directions onsite, proximity to
downwind neighbourhoods and condition of onsite transportation routes (dryness); the Agency
through the use of Provincial government personnel and equipment will ensure dust control measures
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
43
97918-GEN-EMP-N-001-R2 14 June 2010
(e.g. water truck, magnesium chloride) are used as required, which may include their use several
times a day.
d) Noise Impact: During the construction phase, the use of heavy construction vehicles could increase
ambient noise levels attributed to traffic on local roads. As such, the Contractor(s) shall mitigate
noise impacts by implementing noise control measures, as described in Section 5.2.6.
5.2.1. Transportation Infrastructure
The Sydney area is undergoing a transition from industrial land use, dominated by heavy industries (coal
and steel), to commercial land use, dominated by tertiary industries (e.g., services). As a part of this
transition, a 325-acre corridor between the Harbour Side Industrial Park (formerly known as the SYSCO
Business Industrial Park) and Emera Piers and Highway 125 has recently been converted to a
transportation corridor by the CBRM, in anticipation of the remediation of the Coke Ovens Site (AMEC,
2005a). A highway linking the Harbour Side Industrial Park to Highway 125 was also constructed to
facilitate the transformation of the former SYSCO Site into a business/industrial park.
Transportation infrastructure includes existing streets, roads and railroads in the Study Area that may be
used or impacted by the Project.
Access to the east, west and south of the Site can be provided via:
Lingan Road: Access to/from the east & north;
Trunk 28 (Victoria Road): Access to/from the north;
Grand Lake Road: Access to/from the east; and
Highway 125: Access to/from the west & south.
The Project will affect transportation infrastructure during the construction, operation and
decommissioning phases of the Project, which are scheduled to occur between 2006 and 2014. The
impact of the ongoing operation of the Tar Ponds and Coke Ovens Sites beyond 2014 will be minimal and
requires no further assessments.
The streets and roads that will be used by the Project are under the authority of either the CBRM or the
NSTIR. Truck weights and dimensions permitted on streets and roads are regulated by Weights and
Dimensions of Vehicles Regulations of the Nova Scotia Motor Vehicle Act.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
44
97918-GEN-EMP-N-001-R2 14 June 2010
A review of the physical description of the routes, road design, study area traffic volume data and
collision rate statistics, as well as project information, provided by the design engineers, was completed as
part of this task. As engineering details are finalized, a comprehensive transportation management
strategy, including a Traffic Management Plan, will need to be further enhanced and updated as the
Project moves forward.
5.2.2. Street Access to the Sydney Tar Ponds and Coke Ovens Sites
Access to the Sydney Tar Ponds and Coke Ovens Sites is possible via numerous locations. These
locations are shown in Figure 4 (adapted from EIS (AMEC, 2005a) and include:
a) Terminal Road provides Site access from Prince Street just east of the railroad crossing. Left turns are
prohibited for vehicles exiting from Terminal Road to Prince Street.
b) Inglis Street provides a direct connection from Prince Street to the Agency office; however, there is a
slight distance restriction on Prince Street caused by a crest just east of the intersection.
c) Victoria Road at the Cape Breton Street ramps: Ramps and a Victoria Road underpass at Cape Breton
Street allow access; however, ramp widths and available turning radii restrict use by heavy
equipment.
d) Ferry Street currently links George Street to the Sydney Port Access Road (SPAR) via Inglis Street
(east and west shoreline areas) and facilitates sewage rerouting. The dam, located at the end of
Sydney‟s Ferry Street, separates South and North Pond. However, the bridge along Ferry Street will
be closed during the construction phases and the traffic will be rerouted through Prince Street via
George Street.
e) George Street is a collector Street under the jurisdiction of the CBRM providing access from the
South Shoreline Area neighbourhoods/businesses to the west and south via Prince Street and
Highway 125. During the construction phase, George Street will also provide access to/from the north
and east, as a result of the temporary closure of Ferry Street bridge crossing.
f) Sydney Port Access Road:
Vehicles from the Whitney Pier area of Sydney can access the Site at the Lingan Road/SPAR
intersection. This intersection is controlled by traffic signals and rail crossing protection lights and
arms are provided for railroad crossings on Lingan Road and SPAR.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
45
97918-GEN-EMP-N-001-R2 14 June 2010
For the eastern and western areas of CBRM, the Site can be accessed via connections onto the SPAR
from the Highway 125/Grand Lake Road intersection.
g) The Coke Oven Site is accessed from Teak Street at the east end of the Site. Access from Teak Street
is via Welton Street (Trunk #4).
Figure 4: Access Locations
5.2.3. Study Area Traffic Volumes and Vehicle Collisions
In order to determine the extent of possible transportation impacts on the surrounding street system, an
understanding of the current conditions is fundamental. The NSTIR has periodically obtained traffic
counts on the Study Area highway sections using automatic traffic counters. Historical count data
indicates that traffic volume growth rates are between 1.5% and 2.0% per year. Estimated 2005 and
projected 2015 annual average daily traffic (AADT) volumes for Study Area roads are reported in
Table 3.
Access to/from
Whitney Pier Traffic Signals
& Rail Crossing
Access to/from
East/West/South
HIGHWAY 125
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
46
97918-GEN-EMP-N-001-R2 14 June 2010
Table 3: Annual Average Daily Traffic Volumes for Study Area Roads
Road Section
Estimated and Projected AADT Volume
(vehicles per day)
2005 2015 (1)
Lingan Road - 0.5 km east of former Sydney City Limit 2,340 2,600
Lingan Road - 0.5 km west of Trunk 28 2,070 2,300
Lingan Road - 0.5 km east of Trunk 28 2,160 2,400
Trunk 28 - just east of Lingan Road 7,560 8,300
Trunk 4 (Grand Lake Road) - 3 km east of Highway 125 21,600 23,000 (2)
Trunk 4 (Grand Lake Road) - just west of Highway 125 26,700 29,000 (2)
SPAR - just north of Trunk 4 6,600 12,000 (3)
SPAR - north of BURNAC retail site 3,800 6,500 (3)
Highway 125 -just west of Trunk 4/SPAR intersection 18,000 20,000
Highway 125 - between George St. and Alexandra St. 24,000 26,000
Highway 125 - between Frenchvale Rd. And Sydney River 13,800 15,000
Source: (AMEC, 2005a))
NOTES: (1) An annual growth rate of 2.0% has been used, except as indicated in Notes 2 and 3.
(2) An annual growth rate of 1.5% was used for Trunk 4 volumes.
(3) Volumes have been estimated based on proposed retail and site access development on BURNAC retail sites
Recorded traffic volumes along the study area road network are also depicted in Figure 5 (adapted from
EIS (AMEC, 2005a)). In essence, historical traffic volumes provide the basis for comparison to truck and
passenger vehicle estimates associated with construction activities. Similarly, the impact of any increased
use of transportation infrastructure due to construction activities can only be estimated if compared to
existing conditions.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
47
97918-GEN-EMP-N-001-R2 14 June 2010
Figure 5: Major Transportation Access Facilities & Traffic Volumes
SEASONAL VARIATION IN STUDY AREA TRAFFIC VOLUMES
Through the use of permanent counters and vehicle classification stations throughout the Study Area, the
NSTIR is able to derive seasonal traffic volume variations, as indicated in Table 4. Daily volumes tend to
fluctuate from one (1) time of year to another, with volumes typically higher in the summer and lower in
the winter. In addition to the estimated average daily traffic volumes discussed at the beginning of Section
5.2.3, major transportation access facilities are also shown in Figure 5.
2,340/2,600
6,600/7,300
21,600/23,000
3,800/6,500
28,700/29,000 24,000/26,000 (George/Alexandra)
6,600/12,000
18,000/20,000
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
48
97918-GEN-EMP-N-001-R2 14 June 2010
Table 4: Seasonal Variation in Average Daily Volumes
Season Average Daily Volume as a Percent of AADT
Winter (December, January, February, March) 0.82
Spring/Fall (April, May, October, November) 0.96
Summer (June, July, August, September) 1.11
Source: (AMEC, 2005a)
VEHICLE COLLISIONS
Due to a number of uncontrollable variables, such as personal negligence, sudden equipment malfunction
and poor weather conditions, there is an inherent probability that vehicle accidents may occur along
public transportation routes. Collisions on local roads may lead to injury of both workers and members of
the public. As such, protocols shall be put in place to minimize the likelihood of collisions resulting from
mitigable factors, such as routine equipment maintenance and driver training sessions for on-site workers
traveling off-site.
The relative safety of sections of highway within the Study Area has been discerned by comparing
average collision rates within the Study Area to the average collisions rates for all similar highways in the
Province, as shown in Table 5. Collision rates are generally expressed as the number of collisions per
hundred million vehicle kilometres.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
49
97918-GEN-EMP-N-001-R2 14 June 2010
Table 5: Five Year (1999 to 2003) Collision Data for Study Area Roads
Road Section
Number of Collisions by Severity Collision Rates by Severity
PDO1 Injury Fatal Total PDO1 Injury Fatal Total
Trunk 4 (Grand Lake Road) Sections
Trunk 4 - Old Sydney Limit to Hwy 125 24 17 0 41 47.9 33.9 0.0 81.8
Trunk 4 - Hwy 125 to Reserve Mines 178 189 2 369 45.8 48.6 0.5 94.9
Trunk 4 - Combined Rates 46.0 46.9 0.5 93.4
Trunk 28 Sections
Trunk 28 - Dominion to New Waterford 22 18 0 40 19.2 15.7 0.0 34.9
Highway 125 Sections
Highway 125 - Frenchvale to Sydport 9 10 1 20 8.6 9.6 1.0 19.1
Highway 125 - Sydport to Sydney River 50 40 3 93 62.6 50.1 3.8 116.4
Highway 125 - Sydney River to Alexandra St. 21 9 1 31 34.7 14.9 1.7 51.3
Highway 125 - Alexandra St. to George St. 29 17 3 49 27.2 15.9 2.8 46.0
Highway 125 - George St. to Grand Lake Rd. 17 21 1 39 14.8 18.3 0.9 34.0
Highway 125 - Combined Rates 27.0 20.8 1.9 49.8
Provincial 1999 to 2003 Average Collision Rates for Road Classes in the Study Area
100 Series - Two Lanes - Full Access Control (most of Highway 125) 21.9 11.0 0.9 33.8
Trunk Highway - Four Lanes - No Access Control - Not Divided (Trunk 4) 129.7 69.2 0.3 199.3
Trunk Road - Rural (Trunk 28) 46.9 28.4 0.9 76.2
Local or Collector Route - Two Lanes (most of Lingan Road) 59.5 32.8 0.5 92.8
Source: (AMEC, 2005a)
(1) PDO = Property Damage Only
While collision rates for Trunk 4 and Trunk 28 are generally lower than provincial average rates for
similar road classes, collision rates on Highway 125 are higher than the provincial average rates. Property
Damage Only (PDO) collision rates on Highway 125 are about 25% higher than average; however, the
injury and fatal collision rates are about twice the provincial average rates.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
50
97918-GEN-EMP-N-001-R2 14 June 2010
COLLISIONS RESULTING IN SPILLS
Any spills resulting from off-site collisions are anticipated to be localized and minor, due to the nature of
the materials being transported (mostly dry construction materials). Appropriate traffic management
procedures surrounding a spill site shall be implemented at the discretion of local authorities and shall be
abided by the Contractor(s) and personnel involved. The Agency is to be notified immediately and other
regulatory authorities shall be notified by the Agency, as necessary. If a collision involving the spill of
sediments or other controlled substances should occur, the area shall be contained and barricaded until
appropriate decontamination procedures have been undertaken, as developed by the Agency in
association with the Consultant. The remedial activities will be supervised by the Agency and/or the
Consultant. Regulatory authorities could require testing of a spill area following the event, which shall be
supervised by the Agency or their Consultant.
5.2.4. Traffic Generators
The construction activities being undertaken on Sydney Tar Ponds and Coke Ovens Sites, generate higher
levels of traffic than normally observed on local routes. Increased traffic volume is the result of heavy
vehicles associated with construction (large trucks and buses) and personal vehicles (cars, vans, SUVs
and light trucks), which could potentially impact local transportation infrastructure, noise, emissions and
traffic volumes. It has been determined that the primary impact from construction activities with respect
to transportation will be increased traffic volumes from trucks and passenger vehicles on existing roads
(AMEC, 2005a). Historically, the average vehicle classification counts for Grand Lake Road traffic at
eight intersections in the Study Area included 97% passenger type vehicles and 3% heavy vehicles
(AMEC, 2005a). Increased traffic volumes, especially when attributed to heavy construction vehicles,
could impact the length of time required for local commutes and possibly increase the number of
collisions observed.
Table 6 provides a summary of the estimated vehicle volumes, as discussed in the EIS (AMEC, 2005a), in
addition to recent details on both truck and passenger volumes.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
51
97918-GEN-EMP-N-001-R2 14 June 2010
Table 6: Estimated Project Vehicle Volumes
Project Component Activity
Estimated Vehicle
Affected Areas Notes Daily
Volume
Peak
(# per hour)
All project
components Site Worker Access 180 70
Distributed to access streets
and roads
100 workers day time; 25
night time; 1.4 persons per
vehicle
All project
components
Vertical Cutoff Walls
Solidification/
Stabilization
Concrete Trucks 10 2 SPAR and regional roads
from concrete batch plant
5 loaded and 5 empty trucks
per day; assume 20% during
peak hr; 5 days per week
CO6: Coke Ovens
Surface Cap &
TP7: Tar Pond surface
Cap
Capping Material
Trucks 150 15
SPAR and regional roads
from source of capping
material
75 loaded and 75 empty
trucks per day; assume 10%
during peak hr; 350 to 400
days
TP1, TP6, CO1, CO7 Excavated Sediment
Shipping 27 (1) 4
Construction access roads/
shore roads east and west of
the Tar Ponds
TP6: Solidification/
Stabilization Deliveries 5 (1) 1
Distributed to access streets
and roads
TP2: Material
Processing/Constructi
on/Operation
Deliveries 10 1 Distributed to access streets
and roads
(1) assuming 100,000 m
3 demand per year
HEAVY CONSTRUCTION VEHICLES
All major construction and cap materials, including cement, backfill and sediments, will be transported to
and from the Site by highway-licensed tandem, triaxle and tractor trailer trucks, which, especially during
peak periods, can greatly impact transportation infrastructure. For example, the EIS (AMEC, 2005a),
Section 7.10.5, indicates that for the purposes of capping the Sydney Tar Ponds and Coke Ovens Sites,
150 daily truck trips (75 loaded and 75 empty) would be observed daily. An additional ten (10) concrete
trucks per day are also anticipated. While construction vehicles are scheduled to use the SPAR to access
the Project site, the source of capping materials and cement required for solidification activities has not
yet been confirmed; thus, an assessment of potential impacts to other roads cannot be completed at this
time.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
52
97918-GEN-EMP-N-001-R2 14 June 2010
An additional ten (10) concrete trucks per day are also anticipated. The movement of these trucks and
other construction related vehicles during peak traffic flow periods, is a determining factor in potential
adverse effects on transportation infrastructure. While these vehicles are slated to use the SPAR for
accessing the Project site, the source of either the capping materials or the cement required for
solidification activities has not yet been decided, thus making an assessment of impacts on other roads
difficult.
PASSENGER VEHICLES
Based on the projected employment of one hundred (100) daytime workers and twenty-five (25) night
time workers, approximately 180 site worker vehicle trips per day at the Tar Ponds and Coke Ovens Sites
(ninety (90) in each direction) can be anticipated. According to the EIS (AMEC, 2005a), it is anticipated
that passenger vehicle trips would not have any significant effect on existing traffic, as any potential
effects on transportation could be kept to non-significant levels through traffic management.
5.2.5. Impacts on Transportation Infrastructure
The number of construction related vehicles moving during morning and afternoon peak hours on streets
and roads that access the Site, as well as on regional streets and roads, is the most important determining
factor when considering the potential for adverse effects on transportation infrastructure. Construction
activities will include about seventy (70) passenger vehicles and twenty-one (21) truck movements on
access streets and roads to the Tar Ponds and Coke Ovens Sites during the peak hours (Table 5).
The seventy (70) worker vehicles accessing the Tar Ponds and Coke Ovens Sites will disperse to various
site access streets. The twenty-one (21) concrete and capping material trucks will likely use SPAR.
5.2.6. Environmental Impacts
DUST AND AIR POLLUTION
Potential sources of air emissions associated with the Project are identified in Section 7.4.1. However, in
order to contain air pollution effect associated with the transportation aspect of the project, the following
mitigation measures shall be considered:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
53
97918-GEN-EMP-N-001-R2 14 June 2010
Minimizing the distance for transport ;
Applying dust suppressants to the loaded material;
Implementing speed restrictions;
Using completely enclosed or tarped vehicles;
Increasing vehicle maintenance regimes to prevent leaks;
Installing wash stations at site exits to capture particulate before vehicle departure;
Limiting or suspending work during periods of high winds;
Controlling the speed and distance during loading/unloading;
Paved roads: flushing or vacuum sweeping will be conducted, as required; and
Unpaved roads: Usage of a dust suppressant (e.g., water and magnesium cloride) when required
(depending on weather conditions), as applied by Provincial government personnel and equipment.
NOISE POLLUTION
To mitigate the effects of noise associated with large construction vehicles, the following key measures
shall be employed by the Contractor(s) when organizing vehicles to be sent off-site:
Routing shall be reviewed to ensure noise impacts are diverted from residential or small commercial
areas to approved provincial highways, designated industrial areas or construction roads, as
appropriate.
Scheduling shall be such that increased average ambient noise levels resulting from heavy
construction vehicles is limited to daytime hours.
5.2.7. Contractor Traffic Responsibilities
All Contractors must develop and implement their own Traffic Management Plan which provides policies
and procedures that aims to minimize health and safety risks to the general public that are posed by
increased road traffic associated with their element, as well as the safety of their own employees. The
traffic management plan must be accepted by the Agency.
Components of the plan should include, but not be limited to; implementation and enforcement of safety
standards, that may include:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
54
97918-GEN-EMP-N-001-R2 14 June 2010
Collaboration with Agency to promote public awareness of Project activities, such as signage
regarding large trucks and public information regarding traffic patterns and safety issues.
Enforcement of all local and national traffic laws for large vehicles (if any) and/or other safety
standards.
Requiring a valid driver‟s license for all vehicle operators.
Transport during daylight and low-traffic periods as is reasonable and practical.
Transport of dangerous materials during non-peak hours.
Police cars or other warning systems for public when appropriate.
Liaison with Agency to ascertain traffic patterns and sizes of transport vehicles.
Transportation of workers where necessary and/or practicable to minimize undue excessive local
traffic.
Management of road access and temporary road closure issues, including advance notification for
communities and provision of alternative routes.
Scheduling transportation activities that involve increased noise levels (such as unloading of supplies)
that are sensitive to local community quiet times.
Providing additional safety and defensive driving training for vehicle operators.
5.2.8. Conclusions and Recommendations
Based on an evaluation of the construction and operational activities on-site, the following conclusions
and recommendations are provided with respect to Project traffic management:
a) The number of construction related vehicles moving during morning and afternoon peak hrs on streets
and roads that access the Site, as well as on regional streets and roads, is the most important
determining factor when considering the potential for adverse effects on transportation infrastructure.
b) The operation phase is not expected to have a significant adverse impact on transportation
infrastructure.
c) The decommissioning work is not expected to have any significant residual adverse effects on
transportation infrastructure.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
55
97918-GEN-EMP-N-001-R2 14 June 2010
d) There is no follow-up or monitoring recommended with respect to Project effects on transportation
infrastructure.
e) In order to offset/minimize the transportation impacts of the Project, the Agency shall monitor the
implementation of:
Traffic Route Restrictions: To ensure that truck traffic is limited to the provincially maintained
highways and that the Site is being accessed via the SPAR, if possible.
Contractor Traffic Responsibilities: To ensure that Contractors abide by all traffic and
transportation policies and management plans designed for the Project.
The Motor Vehicle Act (GNS, 1989d): To ensure that truck weights and dimensions permitted on
streets and roads are being implemented, as regulated by the Weights and Dimensions of Vehicle
Regulations under the Motor Vehicle Act.
g) All Tech Environmental Consultants (All Tech), the Air Quality Monitoring Consultant, shall monitor
air quality to ensure that appropriate air pollution measures (as discussed in Section 5.2.6) are being
implemented by the Contractor(s). Mitigation measures used to control dust or other air pollution
concerns shall be recorded by the EM as part of the daily Environmental Inspection Log
(Appendix F).
5.3. Land Use and Institutional Land Controls
Given the nature of the remediation works proposed with respect to both the Tar Ponds and Coke Oven
Sites, there is a necessity to ensure that the structural integrity of the implemented works are not
jeopardized by inappropriate future use on any of the Site(s). There exists a recognized need to put in
place the appropriate institutional and regulatory controls that will protect the Sites in perpetuity. This
will involve consideration not only of the future uses proposed for various parts of the remediated lands,
but ultimate land ownership and the determination both of the governance issues involved and the
alternative regulatory mechanisms, e.g., zoning or development agreements, that may be used pursuant to
the Municipal Act and/or common law mechanisms in property law such as covenants. The identification
of appropriate uses for these areas will likely be determined over the balance of 2007 as various studies
are completed and as detailed engineering proceeds. The determination of appropriate land use controls
will be determined in a comparable timeframe.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
56
97918-GEN-EMP-N-001-R2 14 June 2010
5.3.1. Land Use Designation
In the CBRM planning strategy the Coke Ovens Site has a special land-use classification, as the Coke
Ovens Site Reserve Zone. To the east, the land is zoned for purposes of utility
generation/treatment/disposal and is currently characterized by industrial developments including the
municipal waste incinerator; the former municipal landfill site, an abandoned railway line and the balance
is vacant land. To the west of the Coke Ovens Site, the vacant SYSCO Industrial Park Zone connects the
Coke Ovens Site to the Tar Ponds Site. To the north of the Coke Ovens Site, across the SPAR, the land is
zoned for residential (Whitney Pier) and rural purposes. To the south of the Coke Ovens Site, a residential
area and a business corridor zone have developed. There are residences within 1km of the Site.
5.3.2. Future Land Use in the North End of Sydney
The North End of Sydney may change land use by proposition of the CBRM to redevelop the industrial
land along the Tar Ponds. It is expected that the remediation of the Tar Ponds will dominate the area for a
few years, but residents hope that in the future this part of the North End of Sydney will be primarily a
green belt available for public use and enjoyment combined with new housing developments (Cape
Breton Regional Municipality Council [CBRMC], 2005).
Sydney and area is completing a transition from industrial land use, dominated by heavy industries (coal
and steel), to commercial uses dominated by tertiary industries (e.g., services). Within the CBRM, a
number of sites exist that have potential for industrial or other uses. CBRM have proposed future land use
for these sites as shown in Table 7. A description of each proposed site is provided in the CBRM Draft
Secondary Planning Strategy of the North End of Sydney (CBRMC, 2005).
Table 7: Selected Business Industrial Locations, Corridors and Nodes in the CBRM Former and
Proposed Land Uses
Location Size / Value Existing or Former Use Proposed Use
Victoria Junction Coal
Treatment Plant 750 acres Coal treatment complex Regional Market
Sydney Airport (Reserve
Mines) 1,600 acres Airport Businesses
Point Aconi, Boularderie
Island 1,870 acres
Prince Mine & Point Aconi
power generating facility Industry with outside markets
Lingan Industrial
Corridor, New Waterford 1,200 acres Industrial use
Industrial business/regional utility/regional tertiary service
projects with minimal truck traffic
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
57
97918-GEN-EMP-N-001-R2 14 June 2010
Location Size / Value Existing or Former Use Proposed Use
Coxheath/Westmount $7 million
Keltic Drive Business corridor
linking Sydney with Northside
housing regional service,
wholesale and warehousing
distributors
_
Eastern side of Sydney
Gabarus Highway $1 million Business/Industrial _
Glace Bay 370 acres Former Atomic Energy of Canada
Limited site _
Gardiner Mines near
Warbutan Rd. 65 acres DEVCO lands _
Mitchell Ave. & Neville
St. (Dominion) 140 acres DEVCO lands Regional Market
Reserve Mines 40 acres DEVCO lands _
The North End of the Sydney peninsula‟s business/industrial corridor has experienced decay over the past
years because of its location near the SYSCO property. According to the CBRM Draft Secondary
Planning Strategy (CBRMC, 2005), this area could be revitalized subsequent to the dismantling of the
steel mill and the remediation of the associated lands. The remediation of the Tar Ponds, the gradual
revitalization of downtown Sydney‟s waterfront and the demolition of the dry-dock facility, will all
facilitate urban renewal. The efforts of the old Sydney Society involve establishing a complex of
museums in the neighbourhoods located in proximity to downtown Sydney.
Plans are underway to develop an overall trail policy within the CBRM. This would include a green space
system linking the waterfronts and downtowns of the major urban communities with their undeveloped
outlying areas via existing watercourses. According to the CBRM Draft Secondary Planning Strategy
(CBRMC, 2005), the Council will authorize the preparation of a report on a concept of urban open space
for unorganized recreational use.
5.4. Quality Assurance Quality Control Measures Program
The QA/QC Measures Program is designed to ensure that standard procedures are followed throughout
the life of the Project with respect the integrity of work, reporting, analytical testing and other parameters.
The QA/QC Measures Program consists of three independent documents, provided under separate cover,
the Project‟s Quality Management Plan (QMP), the QCP and the IQAP. The QMP addresses the QA/QC
measures that are relevant during the design phase of the Project, as well as sets out the preliminary
guidelines for QA/QC measures to be followed during the construction phase. The QCP and IQAP add
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
58
97918-GEN-EMP-N-001-R2 14 June 2010
more detail to the procedures that shall be put in place during the construction phase of the Project, to
ensure that work quality is ensured through all Project activities. The three plans are summarized as
follows:
5.4.1. Quality Management Plan
The QMP was created to address the assurance requirements outlined in the Agency‟s Request for
Proposal (RFP) document and in the Engineering Agreement for Design and Construction Oversight
Services for Remediation of the Tar Ponds and Coke Oven Sites Project. The goal of the QMP included
the proper identification of quality objectives, the specification of quality-related activities, outlining the
activities necessary to achieve desired levels of quality, prescribing independent verification activities and
devising a system to implement, document and verify needed corrective actions.
The QMP establishes management roles and responsibilities and a process of management review,
including the specification of peer reviewers for each Project element (See Appendix E). This system of
verifying work quality is shown in Table 8:
Table 8: Quality Management Metrics from the QMP
Parameter Measure Metric
AECOM Assignment Health and
Safety Plan
Submission of draft and final
versions. Acceptance by the Agency.
Project Implementation Plan
including Environmental
Management Planning
Submission of draft and final
versions. Acceptance by the Agency.
Project Master Health and Safety
Plan
Submission of draft and final
versions. Acceptance by the Agency.
Design Reports and EPPs 75%, 95% and 100% milestones. 100% Design Reports Delivered in the time
stipulated.
Bid documents in addition to
copies provided with Design
Reports
Available for tender. Delivered in the time stipulated.
Construction Contract Documents Available for Contract placement. Delivered in the time stipulated.
Plain Language Report Draft and Final versions. Delivered in the time stipulated.
Post Construction and Long Term
Monitoring Reports and Bid
Documents
Draft and Final versions. Delivered in the time stipulated.
Local Economic Benefits
Model outputs on design
development and construction
including direct, indirect and induced
LEB‟s.
Monthly/Regular progress reports.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
59
97918-GEN-EMP-N-001-R2 14 June 2010
Parameter Measure Metric
Schedule WBS milestone versus
Actual.
LD dates on design reports.
Construction completion by April 16, 2014.
Design Oversight Conforming to approved QMP.
Completion/closure of QMP process:
● Audits completed.
● Non conformances addressed.
5.4.2. Quality Control Plan
The QCP outlines the scope of the overall Quality Control Program, defines the related roles and
responsibilities of the Agency, Design & Construction Oversight Consultant, the Contractor(s) and the
IQAC. The objective of the QCP describes the quality management process, the quality control measures
including monitoring, inspection and testing, and the corresponding documentation for review by the
Agency. The Agency has outlined that Construction Quality Control involves the monitoring of results to
ensure compliance with relevant quality standards and the objective of the QCP is to document the
approach and procedures used to ensure this conformance with set standards throughout the execution of
the Project. Ultimately, it is the Contractor‟s responsibility to ensure that all products/services conform to
the contractual requirements and to initiate appropriate corrective actions.
Any Contractors who will be constructing the Construction Work Packages for each project element or
providing specialized services are also responsible for the preparation and implementation of Contractor
Quality Control Plans (CQCP) to ensure the quality objectives and standards established for the Project
will be achieved and that the requirements of the Agency and regulatory agencies are satisfied. In addition
to procedures for QC activities during construction, including test methods, location, frequency and
similar requirements, the CQCP shall include:
Contractor‟s quality personnel and organization/structure of QC personnel;
Training qualifications for QC personnel;
Plan for interface with and list of subcontractors and suppliers;
Description of inspection plan and control procedures;
Description of material testing plan and control procedures;
Procedure for corrective action for non conformances;
Contractor‟s data/document management systems for all control documents; and
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
60
97918-GEN-EMP-N-001-R2 14 June 2010
List and description of all records/documents to be maintained.
The QCP also gives direction to the Contractor to develop a clear protocol for confronting non
conformances, which is defined as a project deliverable that does not meet the contract requirements,
established policies or Agency requirements. Documentation procedures are outlined in detail, including:
a) Inspection Data Sheets: identification of various inspection details including type of inspection,
procedures, recorded observations and tests, necessary calculations, personnel involved and results of
inspection activity.
b) Daily Field Reports: to be completed by all field and Contractor Quality Control (CQC) personnel,
such as the EM, when they are on-site within a field book or on standard field data sheets.
c) Progress Reports: summaries to be provided at time intervals established at the pre-construction
meeting that detail the quality characteristics being evaluated during inspections or tests, work
activities, test results and any construction situations, deficiencies, defects and problem resolutions
during the reporting period.
d) Final Documentation: includes a final CQC report for the project element containing all appropriate
documentation, daily reports, sample locations, test results, record drawings, photographic
documentation and any modifications to the design.
5.4.3. Independent Quality Assurance Plan
The IQAP outlines the scope of the independent quality assurance program, defines the responsibilities of
the IQAC and describes the minimum quality assurance monitoring, inspection and testing requirements
to implement the plan. The IQAP plays an important part in fulfilling the requirements and guidelines
established in the overall QMP.
It is the responsibility of the IQAC‟s role to undertake material testing and inspection services during
remediation of the Tar Ponds and Coke Ovens Sites. This includes a variety of tests and inspections to
independently verify element aspects outlined in the detailed design documents during construction. In
the event of non conformance, the IQAC is required to monitor the Contractor‟s Corrective Action Plan,
which ensures identified non conformances, defects and errors are documented and corrected.
The IQAP sets out written documentation tracking requirements during construction of the project
elements. In addition to specifying specific formatting requirements for this documentation, the IQAP
states that the monthly reporting document shall contain:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
61
97918-GEN-EMP-N-001-R2 14 June 2010
A summary of work activities accomplished during the progress reporting period.
Identification of areas or items inspected and/or tested during the reporting period addressed by the
report.
A summary of the quality characteristics being evaluated, with appropriate criteria for each inspected
characteristic.
A summary of inspection and test results, failures and retests.
A summary of construction situations, deficiencies and/or defects occurring during progress reporting
period.
A summary of other problem resolutions and dispositions.
In addition to the monthly reports, it is the responsibility of the IQAC to issue a final report for all details
of the respective project element that fall within their scope of work. As such, the final report is to
contain: all appropriate documentation, daily reports, sample locations, test results, record drawings and
photographic documentation.
6.0 ENVIRONMENTAL PROTECTION PLANS
Project and Detailed EPPs have been developed by the Consultant as part of the overall remedial design
of the Project. EPPs have been designed to contain important field information for Contractors and site
personnel and have been based on a review of the specific environmental conditions of the Project area,
identification of the potential Project-environment interactions, identification of the potential changes to
the existing environment from the proposed construction activities and identification of the necessary
environmental protection measures to avoid/prevent, minimize, or reduce the potential adverse
environmental effects.
The Detailed EPPs are intended to be implemented by the Contractor(s) as per their contract with Agency
and in parallel with the Contractor(s)‟s more specific Contractor‟s Environmental Protection Plan
(CEPP), Assignment Health and Safety Plan (AHASP), Contingency Plans and Emergency Response
Plans. All of these provisions shall be designed to protect the integrity of the environment and the safety
of on-site workers and visitors.
Typical sections of a Detailed EPP include: description of the activity and associated concerns, required
permits and approvals, definition of responsible authority, reporting procedures, documentation
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
62
97918-GEN-EMP-N-001-R2 14 June 2010
requirements and mitigation measures. It is the Contractor‟s responsibility to review and follow the EPPs
and to develop environmental protection measures for any additional construction activities, as necessary.
In the event that an EPP conflicts with Contractor-designed protocols, which have been approved by the
Agency, the Contractor‟s protocols shall be implemented.
The Project EPP includes broad-scoped plans that cover all potential Project activities. Also contained
within the Project EPP are environmental effects monitoring (EEM) plans. Project-wide EPP protocols
have been developed for the following environmental elements:
Erosion and Sediment Control;
Dust, Volatile Organic Compounds (VOCs) and Odour Control;
Product Handling and Storage;
Equipment Maintenance and Fueling;
Building Transportation Infrastructure;
Site Generated Waste Disposal;
Well Decommissioning Environmental Protection Procedure;
Clearing, Grubbing and Refurbishing;
Excavation and Transportation of Sediment;
Archaeology and Heritage Resources;
Restricting Public Access;
Training and Education;
Spill Response;
Dewatering;
Water Management;
Monitoring and Reporting;
Communication and Reporting;
Noise; and
Contingency Plans.
The Detailed EPPs are designed for each Project element and will be included within the 75%, 95% and
100% design reports for each design element.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
63
97918-GEN-EMP-N-001-R2 14 June 2010
7.0 MONITORING PLANS
7.1. Background
As described in the EIS Report (AMEC, 2005a), the Project is to include the implementation of
comprehensive monitoring programs. The objectives of these programs are to:
a) Ensure that the operational requirements and objectives of the remediation works are met;
b) Confirm effectiveness of the mitigation measures proposed in the EIS;
c) Ensure proper implementation of the mitigation measures outlined in the EIS;
d) Determine the need for new mitigation strategies as required to address unanticipated adverse effects
and/or ineffective mitigation;
e) Ensure compliance with regulatory permits, approvals and requirements; and
f) Assist in verifying effects predictions of the EIS.
Although the types of monitoring to address objectives b) to f) were described in the EIS as either
Environmental Compliance Monitoring or Environmental Effects Monitoring, during the more detailed
planning of these programs in this detailed design phase, there is further categorization of monitoring
types into the following areas:
Performance Monitoring, to address a);
Construction/Mitigation Monitoring, to address b), c) and d);
Regulatory Compliance Monitoring, to address b) through e);
Environmental Effects Monitoring, to address f); and
Long Term Monitoring and Follow-up Monitoring, to address f).
Performance monitoring is addressed through Project design and is discussed fully in the Quality
Assurance/Quality Control Plan for the Project.
Construction/mitigation monitoring is focussed on activities within specific elements and is generally
site-specific. This type of monitoring is instantaneous and is intended to identify immediately if
mitigation measures are effective.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
64
97918-GEN-EMP-N-001-R2 14 June 2010
Regulatory compliance monitoring will provide regulators with the information required to determine if
legislation and/or permits are adhered. This monitoring information will be compiled into regular reports
to be disseminated as described in the Reporting Protocol, Section 10.3 of this EMP.
The EEM Program is a tool to determine if effluents are causing effects on ecosystems. Effects are
assessed using regular cyclical monitoring and interpretation phases. Impacts on the same endpoints and
locations are recorded periodically every two (2) to six (6) years, depending on the program, thereby
providing both a spatial characterization of potential effects and a record through time to assess changes
in receiving environments.
The EEM Program for this Project differs from the Long Term Monitoring (LTM), as the EEM can be
discontinued if results show the predictions of the EIS are confirmed prior to the end date of the LTM,
which is twenty-five (25) years.
All monitoring results will be used to facilitate an “adaptive management approach”, to ensure that
corrective action is taken when deficiencies in the Project implementation are identified. The Monitoring
Programs themselves will be subject to re-evaluation and adjustments as Site conditions evolve or the
need to focus on specific operational aspects or issues changes.
The following subsections briefly describe each Monitoring Program, the purpose, objectives and
rationale. Further details for each Program; such as, sample sites, frequencies, methodologies and
inspection protocols are provided in the Project EPP and/or the Detailed EPPs for each element.
7.2. Construction/Mitigation Monitoring
7.2.1. Purpose and Objective
During construction, Contractors shall monitor their construction activities for environmental impacts to
determine whether the impact-minimizing measures developed for the activity are effective. The main
purpose of Construction/Mitigation Monitoring is to identify the source of air and/or water contaminants
before any contaminants impact the receiving environment.
The Conceptual Site Models, as shown in Appendix B, show potential impacts to receptors as a result of
various activities that will occur as part of the Remedial Design for the Project. This information was
used in the development of each Detailed EPP for each element. The Detailed EPPs contain specific
mitigation measures to minimize impacts by identifying potential impacts related to each activity and
providing general and activity specific protective procedures. In addition, these plans provide real time
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
65
97918-GEN-EMP-N-001-R2 14 June 2010
air monitoring, noise and surface water monitoring within the Project site to immediately assess the
effectiveness of the mitigation, thereby providing the information required for immediate action if
measures are ineffective. Various element-specific Contingency Plans are also provided in the Detailed
EPPs.
The objective of the Construction/Monitoring Plans is to provide the necessary information to the
Contractor, so that immediate decisions can be made to ensure mitigation is effective, preventing impacts
to the public and/or the environment. EEM is a tool to determine if predictions made in the EIS are valid;
however, with this type of monitoring there is a time lapse which does not allow immediate response.
Data collected through the EEM Programs for ambient air, surface water, aquatics and avifauna in
addition to the long term monitoring data collected for groundwater will all be used to assess the
effectiveness of mitigative measures for the Project.
7.2.2. Real Time Air Monitoring
The Agency‟s Air Quality Monitoring Consultant (AQMC) is responsible for collecting the real time air
monitoring data and providing this information to the Contractor for each element. This program includes
perimeter monitoring upwind and downwind from each construction activity to identify sources of VOCs
and/or dust. The objective of the Real Time Air Monitoring Program is to protect the general public and
on-site workers from health impacts as a result of remediation activities.
7.3. Air Monitoring – Not in Contract (NIC)
The AQMC is responsible for all ambient and real time air quality monitoring throughout the duration of
all construction activities. Details on ambient air monitoring protocols for the Project are provided in the
Ambient Air Monitoring Plan within the Project EPP. Only Real-time Air Monitoring is discussed as a
construction/mitigative Monitoring Program.
7.3.1. Real-time Air Monitoring
The independent air quality consultant (IAQC) on a contract basis will provide air monitoring services.
The IAQC will collect time weighted (twenty-four (24) hour) ambient air samples at the six (6) existing
monitoring stations to satisfy environmental effects monitoring requirements during remediation. The
IAQC will also carry out real-time continual air monitoring along downwind and upwind fence line
remedial activity sources. Exceedances to real-time action levels will require appropriate corrective action
by the Contractor. The Contractor is responsible for overseeing the implementation of any mitigation
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
66
97918-GEN-EMP-N-001-R2 14 June 2010
measures deemed necessary by the Agency. The Contractor is also responsible for informing the Agency
of any intrusive work that will occur at a specific element in a timely manner, so the IAQC can prepare
for field work.
The Agency will be responsible for the supply of all discrete (twenty-four (24) hour) sampling equipment
including high volume samplers and Summa canisters. The IAQC will be responsible to subcontract all
necessary laboratory facilities required to analyze collected samples with one exception. The Agency
shall contract Environment Canada Air Toxics Section in Ottawa to provide VOC analytical support
including supply of VOC sampling equipment. The IAQC will be responsible for sample collection,
transportation, analyses of samples, data validation, QA/QC, interpretation, reporting and management of
monitoring results.
7.3.2. Real-time Monitoring
The real-time component of the AMP is critical to ensure the remediation work is carried out in a safe
manner without the release of harmful levels of air emissions. The primary objective of real-time
monitoring is to measure air quality, on a continual basis at downwind fence line perimeters. Monitoring
data are compared to approved, short term action levels developed to assist construction managers in
immediately modifying site activities and preventing exceedances of health based compliance criteria.
The real-time work will focus available resources on those contaminants that pose the most significant
health risks during remedial activity. The Real-Time Program has identified a number of target
compounds, or class of compounds, that can be monitored effectively on-site on a continual basis using
portable equipment. The target compounds have been selected based on a set of criteria:
Toxicity or unit risk factor of the particular compound;
Relative concentration of the contaminant present in the buried waste or soil;
The compound‟s volatility or rate at which the compound is emitted to the air;
The location and spatial coverage of the remedial activities; and
Limitations and effectiveness of real-time monitoring equipment in measuring the types of air
emissions typically released to the air by these activities.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
67
97918-GEN-EMP-N-001-R2 14 June 2010
Rapid data turnaround is an important consideration in the selection of real-time monitoring equipment.
Turnaround times are critical when the monitoring data are being compared with short-term action levels
during remediation. A multi-level approach to real-time monitoring will be provided which includes:
Odours and visual (dust) by sensory detection;
Portable, continual reading, gas and aerosol monitors at perimeters; and
Colorimetric gas detection tubes to assess the relative contribution (volatiles) from benzene
emissions.
7.3.3. Target Emissions
Any remediation activity that moves or disturbs soil or waste at the site can potentially result in air
emissions of VOCs, naphthalene, and particulate matter (i.e., dust). Solid or liquid particles (aerosols) can
be released from remedial activity into the ambient air, including contaminated soil particles, heavy metal
particulates and droplets of organic compounds. Control of particulate emissions at the remediation
source will limit concentrations of heavy metals and PAHs/PCBs (as particulate-borne concentrations) in
the ambient air surrounding the Site. The disturbance of waste materials can also release liquid droplets
into the air from volatization of the contaminated waste. Volatile organic compounds and some PAH
compounds with higher volatilities can be released if adequate control measures are not initiated.
Total suspended particulate (TSP) and the PM10 fraction are considered more representative of dust that
can be generated by earthworks. Particulate matter less than 2.5 microns (PM2.5) is typically not
monitored around earthworks, despite its greater potential health impacts. The smaller fraction is
normally emitted by combustion sources. The PM10 fraction is considered more protective of human
health than TSP and has been selected as the most appropriate dust parameter to monitor on a continual,
real-time basis.
VOCs and PAHs are among the most common type of contaminant of concern at remediation sites. Based
on the relative volatility, sediment concentration (in-situ) and toxicity of the compound, each VOC and
PAH was screened to determine which chemicals posed the most significant risks. A group of VOCs,
known as aromatics, include the BTEX compounds (benzene, toluene, ethylbenzene, xylenes), which are
considered to be of key importance due to their volatility and concentration. Benzene and naphthalene is
considered to pose the greatest risk and has been selected as a conservative indication of overall
VOC/PAH impacts. Benzene, due to its higher volatility, will likely be emitted into the ambient air before
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
68
97918-GEN-EMP-N-001-R2 14 June 2010
other VOCs and at potentially higher concentrations than most other VOC species. Benzene is a known
carcinogen with a “severe” toxicity rating.
Real-time monitoring of individual VOC and PAH species is complicated. The current state of technology
can provide continual measurement of VOCs using photoionization detection (PID) instruments. Most of
the portable real-time monitors react with entire classes of compounds and tend to not be specific for a
given compound. PIDs for example are very sensitive to aromatic hydrocarbons (BTEX compounds) but
significantly less sensitive to aliphatic hydrocarbons. In addition, PIDs cannot differentiate between
benzene and toluene if both compounds are present. In some instances, action levels are set based on total
response, as if the instrument readings were due solely to benzene and not other aromatic compounds.
To address PID monitoring limitations, a screening strategy will be employed where total volatiles
(TVOC) will be monitored on a continual basis and compared to established action levels. These levels
have been preset to ensure public protection against benzene and naphthalene exposure at the perimeter.
The established action levels are summarized in Table 9 and Table 10.
In addition to using TVOC emissions as an indication of air impacts due to volatilization, naphthalene is
also considered a target compound, due to its low odour threshold level (450μg/m3) and volatility.
Toxicological studies are ongoing to determine whether exposure to the compound has carcinogenic
effects on humans. Naphthalene, with its low odour threshold and strong characteristic odour
(“mothballs”), will provide an early warning of potential VOC emissions being released into the air from
remedial activity. In the event sustained (ten (10) minute) naphthalene odours are detected by the IAQC,
the Contractor in consultation with the Consultant and the Agency, will assess the situation and determine
the most appropriate corrective action(s).
7.3.4. Monitoring Duration and Frequency
Continual measurements for PM10 and TVOC will be taken downwind and upwind of remedial activity at
fence line perimeters. Fixed monitors will be positioned on stable tripod along exposed downwind
perimeters at the start of each work day. Each monitoring site will measure and record fifteen (15) minute
average concentrations (PM10 and TVOC) on a continual basis throughout the work day. Supporting data
management software package will be utilized to provide ongoing readout of concentrations over preset
averaging periods.
Real-time monitoring will be carried out using hand held instruments with PM10 and TVOC
measurements taken downwind of construction activities at a frequency of two (2) fifteen (15) minute
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
69
97918-GEN-EMP-N-001-R2 14 June 2010
readings per hour. The monitoring frequency for upwind of construction activities will be fifteen (15) one
(1) fifteen (15) minute reading per hour.
Benzene is a known carcinogen with a “severe” toxicity rating. Benzene detection will be initiated when
TVOC levels exceed the established site action levels at the fenceline perimeter, in order to determine the
relative contribution from benzene emissions.
7.3.5. Monitoring Location
All real-time measurements will be performed at predetermined locations, with exact locations selected
prior to start of each work day based on a review of the prevailing wind direction(s), wind speeds, type of
work activity and location of activity (source) in relation to downwind receptors. Fence line monitors,
fixed to tripods, will be positioned along downwind exposed perimeters to ensure adequate coverage and
protection is provided between adjacent neighbourhood(s) and remedial activity(s). The siting of monitors
will primarily be driven by location of remedial work relative to fenceline and wind direction.
Critical fence line perimeters have been identified based on an overall review of planned remedial
activity(s), site features, neighbourhood locations, terrain and meteorological conditions. Screening level
model exercises were used to assess likely air dispersion patterns from the remedial activity(s). Key
perimeters were identified downwind of Tar Pond and Coke Oven remedial sites.
Fixed locations along all downwind perimeters shall be located by the IAQC prior to start of any
scheduled remedial work. Positioning of handheld instruments will require sound judgment and careful
planning.
7.3.6. Real-time Protocols and Equipment
Hand-held instruments used to screen concentrations at the fenceline perimeter will include
photoionization devices (PIDs) for total VOCs and aerosol monitors for dust (PM-10). Real-time
monitoring of TVOCs will be carried out using portable real-time analyzers (photoionization detector),
sensitive to aromatic hydrocarbons like benzene, toluene, ethylbenzene and xylenes. PIDs and aerosol
monitors will be employed to carry out the perimeter monitoring requirements as well. Portable Units will
be mounted on tripods with weatherproof enclosure. Instrumentation shall be capable of logging
minimum, maximum and average concentrations over predetermined time intervals. Units will provide
real-time clock for time and date stamping of events. In addition, benzene concentrations will be screened
at the source using colorimetric gas detection tubes with a minimum detection limit of 0.125ppm
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
70
97918-GEN-EMP-N-001-R2 14 June 2010
(400μg/m3). Benzene detection will be initiated when TVOC levels exceed the established site action
levels.
7.3.7. Weather Conditions
On-site weather stations will be used to collect meteorological data for the current Air Monitoring
Program. The IAQC will collect real-time weather data including wind direction, speed, temperature and
relative humidity. The IAQC will obtain detailed twenty-four (24) hour weather forecasts prior to each
work day from Meteorological Services Canada.
7.3.8. Site Action Levels
Table 4-24 provides a summary of real-time action levels for fence line air monitoring. The site action
levels are based on an approach that considers the budgeting of emissions during the work day. The
budgeting of emissions takes into account shifting wind patterns.
7.3.9. PM10 Action Levels and Measures
PM10 action levels were calculated based on the twenty-four (24) hour average criterion of 50 μg/m3. As
determined by STPA, the action levels and measures previously determined for the Muggah Creek
Remediation Project will be implemented for the EPP. The following summarizes how the action levels
were determined, as outlined in the document, Proposed Air Quality Standards, Muggah Creek
Remediation Project (CRA, 2005).
The purpose of the PM10 emissions budget is to meet a daily average limit of 50 μg/m3 in the community.
As such, it was determined that the sum of the hourly PM10 results for a twenty-four (24) hour period
cannot be above an emissions budget of 1200 ug-hrs/m3 (50 μg/m3 * twenty-four (24) hours = 1200 μg-
hrs/m3). It was assumed that a ten (10) hour work day was required for the remediation activities. The
hourly PM10 concentration during the fourteen (14) hour period without construction activities was
assumed to be 15 μg/m3. As a result, the fourteen (14) hour time period without construction activities
will spend a maximum emissions of 210 μg -hr/m3 (fourteen (14) hours X 15 μg/m3 = 210 μg-hrs/m3).
Therefore, the PM10 emissions budget remaining for the ten (10) hour work day was calculated to be 990
μg-hrs/m3 (1200 – 210 = 990 μg-hrs/m3).
As a result, each hour has a limit for an hourly average of 99 μg/m3 (990 μg/m3 / 10 hours = 99 μg/m3-hr).
Furthermore, it was assumed that the PM10 background concentrations are an average concentration of 33
μg/m3 during the ten (10) hour work day, based on a maximum reading of 33 μg/m3 at the St. Anthony
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
71
97918-GEN-EMP-N-001-R2 14 June 2010
Daniel station in 2004. Accounting for the PM10 background concentration during the ten (10) hour work
day, the remaining PM10 emissions budget for the work day was calculated to be an hourly limit of 66
μg/m3 (99 μg/m3 – 33 μg/m3 = 66 μg/m3). The ten (10)-hour average incremental concentration of 66
μg/m3-hr was then used to develop a fifteen (15) minute action level. The fifteen (15) minute action levels
were calculated for using the reference document titled STB Technical Bulletin No. EES-1, Odour
Impacts – An Overview (Science and Technology Branch, MOE, February 1996). Action levels for each
of the fifteen (15) minute averaging time period was converted as a function of atmospheric stability
class. The derivation used a meteorological classification of E and F, which results in 0.167 for the
stability constant. The fifteen (15) minute action level was calculated to be 155 μg/m3. Table 9 below
summarizes the real-time action levels for PM10.
Table 9: Summary of Project Real-Time Action Levels for PM10
Time Period Action Levels(1)
Fifteen (15) minute action level at fenceline 155 μg/m3
Daily Budget Value (not to be exceeded) 990 μg/m3
Notes: 1 Source: Muggah Creek Remediation Project Sydney, Nova Scotia (Conestoga Rovers & Associates, 2005)
The following action measures will be implemented for the construction elements:
a) In the case where real-time PM10 concentration measure as 2/3 of the allowable maximum of 155
μg/m3, (i.e., 100 μg/m3), the Contractor(s) will be notified that the work activities should be closely
monitored and procedures revised to incorporate mitigative measures. This step is implemented as an
additional safeguard.
b) The “Dust Budget” will be monitored during the day by calculating hourly downwind averages for
each monitoring area, and adding together the hourly averages and adding the estimated background
for the remainder of the work day. When the expended budget to that point plus the remaining hours
in the work day multiplied by the background concentration reaches or exceeds 990 μg/m3, site
activities will be shut down for that day. In addition, when the expended budget to that point plus the
highest reading for that day multiplied by one(1) hour plus the remaining hours in the work day, less
one (1) hour, multiplied by the background concentration exceeds 990 μg/m3, site activities will be
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
72
97918-GEN-EMP-N-001-R2 14 June 2010
terminated for the day. The formula for the calculation of the Daily Dust Budget (as reported in the
CRA letter report titled “Proposed Air Quality Standards, Muggah Creek Remediation Project,
Sydney, Nova Scotia” dated April 20, 2005) is as follows:
990 μg/m3 > (Budget to that point) + (Highest hourly average reading that day x 1 hour) + (33
μg/m3 x remaining work hours). Where remaining hours = 10-((number of hours monitored
before exceedance)+1)
This formula indicates 990 μg/m3 as the total daily “Dust Budget” (CRA, 2005).
7.3.10. TVOCs Action Levels and Measures
TVOCs action levels and measures have been adopted from:
The Proposed Work Management Decision Criteria for Sydney Tar Ponds and Coke Ovens Clean Up
Project (AMEC, 2009); and
The document, “Proposed Air Quality Standards, Muggah Creek Remediation Project” (CRA, 2005).
Currently, there are no jurisdictional air criteria for TVOCs. Therefore, site specific action levels have
been developed for TVOC monitoring results. The action levels use an approach based on budgeting of
emissions. The daily budget value for TVOCs is based on assuming that the volatiles at the fence line are
100% benzene or 100% naphthalene. Thus, a daily budget value of 8 ppm for TVOCs is used assuming
two (2) fifteen (15) minute readings every hour at a downwind fence line location. Furthermore, the real-
time action level for TVOCs over a fifteen (15) minute period has been adopted as 0.66 ppm.
As determined by STPA, the fifteen (15) minute action levels and measures previously developed for the
Muggah Creek Remediation Project will be implemented for the EPP. In addition, the daily budget value
as outlined in the March 2009 report for proposed work management criteria will be implemented. Table
10 below summarizes the action levels.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
73
97918-GEN-EMP-N-001-R2 14 June 2010
Table 10: Summary of Project Real-Time Action Levels for TVOC
Time Period Action Levels
Fifteen (15) minute action level at fenceline 0.66 ppm(1)
Daily Budget Value (not to be exceeded) 8 ppm(2)
Notes:
1 Source: Proposed Air Quality Standards, Muggah Creek Remediation Project, Sydney, Nova Scotia (Conestoga Rovers &
Associates (CRA), 2005)
2 Source: Proposed Work Management Decision Criteria for Sydney Tar Ponds and Coke Ovens Clean Up Project (AMEC, 2009)
The following action measures will be implemented for the construction elements:
When the TVOC action level of 0.66 ppm is exceeded, the IAQC will contact the contractor and
notify them that work activities are to be closely monitored and possibly adjusted. The IAQC will
sample benzene concentrations using a Draeger tube. If measurements continue to increase, a decision
to temporarily halt or shut down remedial operations will be considered. Contractor(s) will be
required to modify their work practices in order to reduce VOC emissions.
The “TVOC Budget” will be monitored during the work day. When the expended budget reaches or
exceeds 8 ppm, site activities will be shut down for that day.
Table 11 outlines the appropriate action levels and associated action measures for the work day.
Table 11: Summary of Real-Time Action Levels and Action Measures
Parameter Action
Level
Monitoring
Location
Averaging
Period
Action Required if Level Exceeded
PM10 100 μg/m3 @downwind
fence line
Fifteen
(15)
Minutes
Site continues to operate. IAQC notifies the
Contractor, AECOM/CBCL and the Agency. The
Contractor will investigate potential source of air
emissions. Visible dust plumes on-site and/or sensory
detection of organic odors shall be an early indicator
that immediate corrective measures may be warranted.
First line of defense measures such as the addition of
water sprays to control airborne dust or changing
activity locations may be implemented. The Contractor
will initiate appropriate measures to correct operations.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
74
97918-GEN-EMP-N-001-R2 14 June 2010
Parameter Action
Level
Monitoring
Location
Averaging
Period
Action Required if Level Exceeded
PM10 155 μg/m3 @ downwind
fence line
Fifteen
(15)
Minutes
The Contractor, AECOM/CBCL and the Agency will
evaluate work practices and determine the appropriate
course of action. Temporary stop work practices will
be evaluated. If the PM10 action level is reached or
exceeded and the exceedances is due to site work
activities, site work will be temporarily suspended
until proper techniques are identified and
implemented. The Contractor is to initiate appropriate
control measures. Work will resume within a short
time period when corrective procedures are
implemented.
TVOC 0.66 ppm @ downwind
fence line
The IAQC will notify the Contractor, AECOM/CBCL
and the Agency. The IAQC will assess Benzene
concentrations using colorimetric gas detection tubes.
The results of the colorimetric tubes will be
communicated to the Agency, the Contractor and
AECOM/CBCL.
• The contractor will closely monitor work and
possibly implement mitigation measures. If
measurements continue to increase, a decision to
temporarily halt or shut down remedial operations will
be considered. Contractor(s) will be required to modify
their work practices in order to reduce VOC emissions.
PM10
990μg-
hrs/m3
@downwind
fence line
Daily
Emissions
Limit
If the daily emissions budget is reached, the IAQC
notifies the contractor, AECOM/CBCL and the
Agency. The contractor terminates site work for the
day. The Contractor, AECOM/CBCL and STPA will
discuss and examine remaining options available to
correct air emission exceedances. A course of action
will be developed for the next day of remedial activity.
TVOC 8ppm
Note: Upwind conditions are to be considered prior to shutting down site work activities. Work activities
are not to be terminated in the event that the action level is exceeded upwind and the downwind
concentrations are less than 10% of the upwind concentrations. The dust budget is to be similarly
managed, that only the background concentration to the budget is added in these situations.
The Contractor should note all air exceedances/incidents on the EIL located.
7.3.11. Noise Monitoring
Noise monitoring will be conducted by each Contractor responsible for each element of the Project to
assess if noise levels are within the Guidelines as described in the Detailed EPPs.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
75
97918-GEN-EMP-N-001-R2 14 June 2010
As part of the Remediation of Sydney Tar Ponds and Coke Ovens Sites Environmental Impact Statement
(EIS), AMEC Earth and Environmental Inc. completed a Noise Monitoring Program1 to establish baseline
noise conditions prior to the commencement of Project activities.
The Noise Monitoring Program included nine (9) locations close to residential receptors around the
Sydney Tar Ponds and Coke Ovens Sites, as indicated on Figure 62. Baseline conditions provide an
indication of noise attributable to factors outside construction, such as vehicular traffic, train movement,
and residential events.
Figure 6: Baseline Noise Monitoring Locations
Once each element‟s construction activities begin, noise monitoring specific to each element will begin.
Noise monitoring will be conducted at three locations along the Project site boundary (e.g., the fence line)
during active construction hours (typically between 0700-1900 hours). Measurements at the Project site
1 AMEC Earth & Environmental (2005). Remediation of Sydney Tar Ponds and Coke Ovens Sites Environmental Impact
Statement, Volume I, s.5, p.38. Sydney, NS: Sydney Tar Ponds Agency. 2 AMEC Earth & Environmental (2005). Noise Monitoring Locations in Sydney [Figure]. Remediation of Sydney Tar Ponds and
Coke Ovens Site Environmental Impact Statement, Volume I. Sydney, NS: Sydney Tar Ponds Agency.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
76
97918-GEN-EMP-N-001-R2 14 June 2010
boundary shall take note of noise generated off-site (e.g., background noise) when considering the total
effects of construction activities.
Noise monitoring levels will be measured at the Project site boundary on a two (2) hour Leq (dBA) basis
during active daytime hours when construction equipment is operational. Once mobilization is complete,
construction noise monitoring will be completed three times per week, at three locations, for the first three
weeks and one per week, thereafter provided there are no noise issues or complaints. Should noise
complaints arise that may be attributed to the activities at the site, an assessment will be completed to
determine whether the noise is attributed to on-site construction activities and to determine compliance
with NSE‟s criteria. As part of the assessment, noise monitoring will be conducted at the nearest
receptors during construction hours. If the noise is attributed to site construction activities, noise
mitigation steps, will be considered to meet the NSE guidelines, within reasonable economic restraints.
All construction activities and equipment operation will comply with the CBRM noise by-law(s) and any
applicable provincial and federal guidelines as stipulated in the Environmental Impact Statement:
Guidelines for the Environmental Assessment of the Sydney Tar Ponds and Coke Ovens Sites Remediation
Project3. NSE has established the following noise criteria under the Guidelines for Environmental Noise
Measurement and Assessment4 document.
a) Leq,2hr < 65 dBA between 0700 to 1900 hours (Days);
b) Leq,2hr < 60 dBA between 1900 to 2300 hours (Evenings); and
c) Leq,2hr < 55 dBA 2300-0700 hours (Nights).
d) In accordance with applicable legislation, the Contractor(s) shall also monitor noise levels in the
construction work area and at the nearest receptors and take appropriate noise mitigation or PPE actions,
as required.
7.3.12. Surface Water Monitoring
Construction/mitigation surface water quality monitoring will be conducted every four (4) hours of active
construction, by the Contractor‟s EM when construction activities are within 30 m of a waterbody.
3 Public Works and Government Services Canada (2005). Environmental Impact Statement Guidelines for the Environmental
Assessment of the Sydney Tar Ponds and Coke Ovens Sites Remediation Project. 4 Nova Scotia Environment (1991). Guidelines for Environmental Noise Measurement and Assessment. Halifax, NS: Author.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
77
97918-GEN-EMP-N-001-R2 14 June 2010
Sample site location and frequency depends on where and what type of activity is being carried out.
Typically the sample sites are upstream, midstream and downstream from the activity and compared
against the upstream background levels. .
Specific monitoring procedures, protocols and reporting requirements are to be consistent with NSE
requirements and standard operating procedures developed for the Groundwater and Surface Water
Sampling Program5.
Surface water monitoring is to be completed by the Contractor‟s EM or designee at a point roughly mid-
depth of the water column near the centre of the channel during flow events. Sample monitoring should
commence with the furthest downstream location and progress upstream to avoid any disturbances to the
sample. Field turbidity is to be monitored using an optical backscatter (OBS) nephelometer with an
underwater sensor and direct surface readout or another instrument having similar capabilities. Prior to
monitoring, all equipment and sampling devices are to be calibrated as per manufacturer‟s
recommendations.
The specific locations of monitoring points will change depending on the active working area. The
location of surface water testing will be determined at the time of testing by the Contractor‟s EM and
documented in the EIL.
The upper level criteria defined as a reportable event for turbidity will be 110% of background, when
background (upstream sample location) is greater than or equal to 80 Nephelometric Turbidity Units
(NTUs). When background is less than 80 NTU, a reportable event will be greater than an increase of 8
NTU above background6.
If an element‟s turbidity monitoring reveals that the upper level criteria have been exceeded, the
construction activities suspected of contributing to the exceedance (e.g., excavation) will be temporarily
halted until levels decrease to an acceptable level. During this time, all efforts will be made to rectify the
cause of the exceedance.
5 Dillon Consulting & ADI Limited, (2004). Groundwater and Surface Water Sampling Program. Sydney, Nova Scotia: Nova
Scotia Department of Transportation and Public Works
6 Canadian Council of Ministers of the Environment (2006). Water Quality Guidelines. Winnipeg: Author.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
78
97918-GEN-EMP-N-001-R2 14 June 2010
The Contractor(s) shall then resume turbidity monitoring at an increased intensity level (hourly) to verify
that the source activity has been abated. Explanatory details documenting the exceedance and any
corrective measures taken will be documented.
7.3.13. Short Term Cap Monitoring
The Construction Phase Surface Cap Monitoring Plan is designed to monitor the state of the cap at both
CO6 and TP7, while construction activities are ongoing. Once construction of the cap has been
completed, the Cap Environmental Effects Monitoring Plan (EEM) found in the Project EPP and
described below in Long Term Cap Monitoring Section will take effect. The purpose of both the short
and long term plans is to study the integrity of the cap.
Short Term Cap Monitoring shall be completed by the Contractor(s) and include:
a) Daily overview inspections by the Contractors‟ Site Supervisor to ensure that grading and material
thicknesses have been constructed according to specifications and to check for any signs of erosion or
other potential cap installation problems. Should cap installation problems be identified, action will
be taken as soon as possible to rectify the situation;
b) The seal of the liner, where applicable, shall be inspected at the manufacturer‟s specified frequency to
meet manufacturer‟s recommended criteria. If manufacturer‟s specifications are not met, appropriate
action will be taken and may include liner replacement, if applicable;
c) Compaction testing shall be completed for the clay fill installation for every 0.3m lift per hectare.
Compaction shall meet 98% standard proctor density and will be measured using a nuclear
densometer by qualified personnel;
d) Detailed weekly inspections and documentation of the status of cap installation will be completed by
the Contractors‟ EM. Documentation shall be submitted to the Agency along with any other EILs for
CO6 and TP7 and shall include, but is not limited to, observations on the following:
Condition of hydroconductivity (impermeable/clay) layer, if applicable;
Evidence of erosion or differential subsidence;
Signs of gullies or rills; and
Germination of vegetation.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
79
97918-GEN-EMP-N-001-R2 14 June 2010
e) If deficiencies are identified during the weekly inspections, appropriate action will be taken to
mitigate potential environmental effects; and
f) Once an area of the cap has been vegetated, monitoring of that cap shall be completed by others in
accordance with the long term cap monitoring plan provided in the Project EPP.
7.3.14. Visual Inspection
The Contractor‟s EM will also be conducting visual inspections every four (4) hours (exception for TP2
Operations and Maintenance, where it will be daily) at each active construction site and once daily during
inclement weather conditions during shut down periods, to ensure maintenance of the mitigative measures
and all environmental issues are addressed. In cases, where an unexpected long term shut down period
occurs, the EM shall inspect the site once weekly as a minimum. Environmental inspection is the primary
tool to ensure that the Contractor is implementing the environmental commitments of the EMP,
identifying where remedial actions may be required and taking the required actions in a timely fashion.
Through the actions of AECOM/CBCL as the Design and Construction Oversight Consultant, the
Contractor‟s compliance with the EMP and the Detailed EPPs will be monitored to ensure that
environmental protection objectives are being achieved in the field.
7.3.15. Environmental Inspection Logs
The Contractor will regularly inspect and evaluate environmental procedures and shall record the status of
each Project activity every four (4) hours in the Environmental Inspection Log (Appendix F). If a
problem or potential problem is identified by the Contractor, the Consultant and the Agency shall be
notified immediately. The Consultant shall oversee that the appropriate mitigative or restorative actions
are taken and shall immediately report the actions taken to the Agency along with a plan for future action.
As the Consultant is responsible for construction oversight, they will review the Contractor logs weekly
to verify environmental site conditions and send a Monthly Summary Report to the Agency. The IQAC
shall also prepare documentation of their activities to the Agency. The IQAC reports are to be reviewed
by the Agency directly and the Agency is to direct any remedial action required to the Consultant. This
procedure has been designed to provide an early detection and solution implementation mechanism for
emerging problems before they become serious or unmanageable.
By undertaking routine inspections and completing Environmental Inspection Logs every four (4) hours
as required in the detailed EPPs, a proactive approach aimed at identifying potential concerns before
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
80
97918-GEN-EMP-N-001-R2 14 June 2010
environmental impacts occur is achieved. In addition, inspections and other mechanisms of direct
reporting, such as telephone or email, serve to ensure that corrective actions occur immediately where
unsafe conditions have been identified. The inspection activities will act as a safeguard to ensure that the
environmental protection measures are functioning effectively.
To determine the ongoing effectiveness of environmental management and mitigation procedures, the
Contractor and IQAC are both required to submit a Monthly Environmental Inspection Report to the
Agency (and to the Consultant from the Contractor) for review. These reports shall also identify actions
needed to remedy situations of environmental concern. If environmental protection measures are
persistently proving to be ineffective at mitigating the impacts of construction activities, a revision to an
existing detailed or Project EPP may be required. Revisions to EPPs shall be subject to the procedures
outlined in the Change Protocol Document (Appendix B). Employees are to be trained in any new
procedures, as per the requirements in Section 9 of this EMP.
This adaptive management process of inspection/monitoring, analysis, review, policy revision and
training will ensure that the EMP is meeting Agency‟s environmental protection commitments.
7.3.16. Adaptive Management
Locations, timing, frequency, parameters and action triggers are provided in the element specific Detailed
EPPs for the Construction/Mitigation Measures Monitoring Programs. Visual observation provides
additional information to determine if protective measures are effective. With information obtained from
analytical and visual data collection, an assessment will be made whether further mitigation or
investigation is required. Steps to be taken by the Contractor and the Agency, or their designate, if
mitigation appears to be ineffective are:
Investigate and determine the source;
Identify and evaluate possible corrective actions;
Implement corrective action; and
Monitor the effectiveness of the corrective action.
Adaptive management involves mitigating and monitoring each activity, assessing effectiveness and if the
mitigation is not effective, reporting the incident to the Agency with further mitigation implemented. If
further mitigation is shown to be ineffective through monitoring results, the Agency must be notified and
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
81
97918-GEN-EMP-N-001-R2 14 June 2010
work is to temporarily cease until the issue is resolved. This process is graphically represented in
Figure 7.
Figure 7: Adaptive Management Procedure
7.4. Regulatory Compliance Monitoring
Various pieces of legislation apply to the Project, in addition to specific conditions of permits, as
provided in Section 3 of this EMP. Monthly compliance monitoring reports shall be submitted by the
Consultant and All Tech to the NSE and other regulators concerning:
Battery Point/Sydney Harbour surface water;
Effluent discharge from element CO8, Coke Oven Water Treatment Plant, to surface water;
Air emissions from element TP2, the Materials Processing Facility;
Air emissions from element CO8, Coke Oven Water Treatment Plant; and,
Other compliance monitoring stipulated by NSE as part of Conditions of Approval.
In the event that analytical test results taken from compliance monitoring locations are found to
unexpectedly exceed provincial or federal limits, these results will be reported immediately to the
Agency, NSE and other regulators, and an investigation of cause will be carried out. Additional details on
compliance monitoring programs are provided in the Project EPP.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
82
97918-GEN-EMP-N-001-R2 14 June 2010
Continuous real-time data will be available as it is generated and provided to the Agency and other
stakeholders, as required. The Air Quality Environmental Effects Monitoring Plan identifies the use of
continuous reading perimeter monitors connected to a central data management system onsite where the
appropriate real-time summary data can be transmitted to the various stakeholders including the general
public.
7.4.1. Battery Point/Sydney Harbour
Turbidity, pH, conductivity, salinity and temperature will be monitored at Battery Point using an
automatic datalogger. Data will be downloaded and analyzed monthly, with the exception of heavy
precipitation events as described in the Compliance Monitoring Section of the Project EPP or if there is a
failure of an erosion control structure. This instrumentation will be the responsibility of the Agency or
their designate. In addition to retrieving and monitoring data at this location, if compliance is not
achieved, an investigation to determine the source is to be initiated by the individual who is tasked (by the
Agency) with the monitoring and maintenance of this datalogger.
Lab analyses of surface water for various parameters will be carried out under the EEM Program.
7.4.2. Effluent Discharge
Effluent discharge criteria in compliance with the Fisheries Act and NSE‟s approval will be the basis for
the design of the WTP (element CO8). Effluent from element CO8 will be monitored for the duration of
operations which is expected to be twenty-five (25) years.
A detailed monitoring plan with timing, frequency, parameters and action triggers will be provided in the
Project EPP.
7.4.3. Air Emissions
Approval from NSE for air emissions from the Materials Processing Facility (element TP2) and the WTP
(element CO7/CO8) will be acquired prior to operation of these facilities. This approval will contain the
levels of emissions allowed for various parameters. These emissions will be monitored as per the
Condition of Approval requirements for each of the two facilities.
7.5. Environmental Effects Monitoring
EEM programs are “early warning” tools to detect negative impacts on the environment and allow for a
review of the impacts and implementation of corrective actions, if they are required. EEM programs are
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
83
97918-GEN-EMP-N-001-R2 14 June 2010
listed in the subsections that follow and are typically carried-out over a period of several years. An
Ecological Risk Assessment of Sydney Harbour will be completed to provide additional information to be
incorporated into the EEM plans.
EEM Programs are to be implemented for:
Ambient Air Monitoring;
Surface Water Monitoring;
Aquatic Monitoring in Sydney Harbour; and
Avifauna Monitoring.
Monitoring methodologies, locations, parameters and frequency of sampling for all EEM Programs are
provided in the Project EPP. In addition, methods to assess, post data collection, the need for each
program to continue will also be provided in the Project EPP.
7.5.1. Ambient Air Monitoring
OBJECTIVES AND RATIONALE
Ambient air monitoring will provide cumulative information for various locations throughout the Project
site. Cumulative information for various locations throughout the Project and within the community will
be collected in accordance with the Environmental Effects Monitoring Plan. Baseline data has been
collected in previous years to characterize the local airshed, onsite and offsite. Air samples will continue
to be collected at the six (6) existing monitoring stations within the community during the Project with
results compared to baseline conditions in the airshed.
The baseline study has been on-going with services provided by All Tech Environmental Consultants.
Local air quality predictions made in the EIS will be confirmed with the data collected under this EEM
Program.
POTENTIAL SOURCES OF AIR EMISSIONS
Possibly of most concern to the public throughout the construction phase of the Project, is the impact of
construction activities on the quality of air in the vicinity of residential and commercial neighbourhoods
surrounding the Tar Ponds and Coke Ovens Sites. As the CSMs indicate, emissions could result in the
creation and inhalation of vapours and particulate matter, both by construction workers and the
surrounding community. To mitigate health concerns associated with air quality, each Project element, as
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
84
97918-GEN-EMP-N-001-R2 14 June 2010
described in Section 2.4, will be monitored for the effectiveness of the mitigation measures during the
construction phase. Potentially air-impacting construction activities include, but are not limited to:
Materials processing and handling;
Transportation operation and maintenance;
Building emissions, construction machinery operation and maintenance;
Soil transport and stockpiling;
Contaminant handling and excavation; and
S/S mixing.
These activities can result in an increase in fugitive dust, diesel emissions and the release of VOCs.
STUDY DESIGN
The study design for ambient air monitoring includes a number of basic steps that parallels EPA guidance
documents for ambient air monitoring around Superfund Sites. Basic steps considered in the study design
include:
Define program goals;
Select target compounds;
Select number and location of monitoring sites;
Select duration and frequency of monitoring;
Select monitoring methods;
Establish data quality objectives;
Establish QA/QC Program;
Establish data management and reporting systems;
Establish compliance criteria and site action levels; and
Establish Community Access Program.
The existing pre-remedial AMP was designed to collect baseline air quality data for a multiple number of
chemical compounds than could be present in the surrounding airshed. The database contains more than
five years of monitoring results for an extensive suite of contaminants (approximately 50 parameters),
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
85
97918-GEN-EMP-N-001-R2 14 June 2010
defining twenty-four (24) hour and annual average concentrations and trends prior to any significant level
of remedial activity occurring on-site. Based on this information and knowledge obtained during the pre-
remedial monitoring work, the AMP has been designed to monitor a number of target compounds using
proven sampling and analytical methods employed during the previous program.
The baseline database has been reviewed and a list of contaminants that were routinely detected during
the baseline study was identified. Factors that affect the magnitude of any health risk posed by a
particular contaminant include; the concentration of the compound in the buried waste or soil, the
compound‟s volatility or the rate at which the compound is emitted to the air, and the toxicity or unit risk
factor of the particular compound. The AMP focuses on available resources on these compounds that
pose the most significant risk during the remediation work.
The AMP includes a fixed network of point samplers located around the perimeter of the Tar Ponds and
Coke Ovens Sites. Generally, the factors that influence the required number and locations of sample
stations include:
The locations of potential on-site emission sources;
The locations of topographic features that affect the dispersion and transport of site emissions;
The variability of local wind patterns;
The location of sensitive receptors; and
The level of confidence needed to ensure that the maximum concentration levels are being monitored.
For determining concentration levels with respect to short-term effects, a fixed network of real time
sampling stations ideally should be located around the perimeter of the Sites, with additional real time
monitors located near working areas on-site and near sensitive receptors.
The AMP includes the appropriate time, duration and frequency of the sampling events. The baseline
program collects twenty-four (24) hour samples on a six (6) day NAPS schedule. Sampling periods
during remedial construction activity will be selected for compatibility with relevant regulatory and site
action level criteria. Compliance with long-term criteria is usually determined using twenty-four (24)
hour sampling periods.
The AMP is designed to ensure that sufficient valid data are collected to achieve the goals of the Program,
which are to protect the workers and public from health impacts and to verify the prediction of the EIS,
that with mitigation, there will be no significant air impacts from the Project.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
86
97918-GEN-EMP-N-001-R2 14 June 2010
7.5.2. Surface Water Monitoring
OBJECTIVES AND RATIONALE
The surface water environmental effects monitoring program will provide data to determine the migration
of any off-site contaminants on to the Project Site and the transport of contaminants in surface water that
have originated on-site and are being carried off-site. The data collected through this program will
confirm the prediction of the EIS that there will be no significant adverse effect of the Project
construction activities to surface waters.
POTENTIAL SOURCES OF POOR WATER QUALITY
As shown on the CSMs for the various elements where construction is to occur near watercourses, there is
a potential for sediment and other contaminants within the water column to be transported downstream
into Sydney Harbour. Road building, bridge construction, steel sheet piling, excavation of sediment from
isolated sections of streams in the project elements, may potentially result in impacts to surface water
quality. Protective procedures and Contingency Plans are provided.
STUDY DESIGNS
The study is designed to collect surface water quality data at the Project boundaries in streams for
parameters known to be contaminants of concern for this Project. Additional sites are to be located
downstream of construction activities.
Surface hydrology monitoring will be carried out in select locations to monitor flows during construction
and post construction. Of special interest is the location of discharge from the WTP (element CO8). A
stage-discharge curve (relationship) will be developed as soon as possible to enable fieldwork to be
conducted in the most efficient manner in future years.
Surface water quality and flow monitoring in the newly constructed channel environments will provide
information to verify the predictions made in the EIS of no significant effects.
7.5.3. Aquatic Monitoring in Sydney Harbour
Marine water, sediment quality and benthic/bivalve monitoring will be conducted at Battery Point within
Sydney Harbour to determine Environmental Effects at this location as a result of Project activities.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
87
97918-GEN-EMP-N-001-R2 14 June 2010
OBJECTIVES AND RATIONALE
A Contaminant Fate Modeling Study was conducted by AMEC as part of the EIS, Volume 7 (AMEC,
2005a) to model the rate of flux of Chemicals of Concern (COCs) prior to, during and post construction.
Flux studies conducted by Jacques Whitford, Dillon Consulting, ADI Limited and CBCL Limited (JDAC)
in (2002a, b) were used as the main basis for selected COCs to conduct this modeling. The Contaminant
Fate Model was run for a sixty (60) year period for each COC. During the first thirty-nine (39) years, the
contaminant flux rate was stable, at the rate that was measured by JDAC (2002a, b). In Year forty (40),
the contaminant flux rate was increased by five (5) times the standard rate to simulate release related to
remedial construction activities. In Years forty-one (41) to sixty (60), the flux rate was decreased by 10%
to simulate remediated conditions. Annual incremental increases in contaminant transport to the Harbour
are presented in the EIS for surface water quality and sediment quality. The EEM program will verify
these predictions.
POTENTIAL RELEASE OF CONTAMINANTS TO SYDNEY HARBOUR
COCs are currently being transported to the Harbour, however the rate of transport – the flux – will
increase during construction due to the remedial construction activities as described in the CSMs.
However, the incremental increase when compared to existing flux rates for various parameters is
predicted to be non-significant.
STUDY DESIGN
This program will confirm predictions made in the EIS. Surface water, sediment, benthic invertebrates
and other indicator or sensitive species may be monitored. The Ecological Risk Assessment will assist to
further define this program.
7.5.4. Avifauna Monitoring
Avifauna habitat survey and breeding bird surveys will provide effects monitoring information to confirm
the predictions of the EIS.
OBJECTIVE AND RATIONALE
Since wetland habitat – the Tar Ponds – will be reduced in size, there was a concern birds would be
negatively impacted. However, the conclusions of the EIS were that birds would not be negatively
impacted since they would habituate in a much cleaner environment post remediation. For this VEC,
construction monitoring is not practical and the EEM program is intended to begin post remediation.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
88
97918-GEN-EMP-N-001-R2 14 June 2010
POTENTIAL PATHWAY OF CONTAMINANTS TO BIRDS
Some species of birds rely on obtaining the majority of their food from the Tar Ponds environment.
However, these species as adults do not spend all their time at the Tar Ponds as there are other habitats
available to them.
COC‟s from the Tar Ponds can enter food eaten by birds by ingestion or absorption. Aquatic species can
retain these contaminants in their organs while continually exposed to COCs or bioaccumulate these
COCs within their tissue. Whatever the mechanism, birds ingest the COCs by mouth as food. These
COCs can impact reproduction, growth and other life history functions.
STUDY DESIGN
The monitoring of the presence of bird and the increase in local bird populations provides some indication
of improved habitat quality. A direct study, such as assessment of contaminants present in chicks, will
provide a very good correlation between contaminants within the organism and contaminants remaining
in the Ponds post remediation, since some species of chicks rely solely on pond organisms for food.
7.6. Long Term Monitoring
Long term monitoring programs include the Cap Monitoring and Maintenance Plan and the Groundwater
Monitoring Plan. Both of these monitoring programs will continue for twenty-five (25) years.
7.6.1. Cap Monitoring Plan
The Cap Monitoring and Maintenance Plan presents specific monitoring procedures and general
maintenance and repair concepts associated with the two (2) caps to be constructed as part of the
Remediation of the Tar Ponds and Coke Ovens Sites. The caps include; the cap over the stabilized Tar
Ponds and the cap over the Coke Ovens Site
The caps are multilayer barriers designed to divert surface water away from certain areas to minimize any
potential transport of contaminants. The simplest consists of a low hydraulic conductivity layer to
minimize infiltration of storm water and a low maintenance layer to provide protection of the low
hydraulic conductivity layer.
The final cover caps are generally multilayer caps. For complex caps the layers may include (from the
bottom up) a grading layer, a low hydraulic conductivity layer (GCL, or low hydraulic conductivity soil),
drainage layer (geocomposite or high hydraulic conductivity soil with geotextile), a protective layer and a
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
89
97918-GEN-EMP-N-001-R2 14 June 2010
vegetative layer (topsoil and vegetation). For simple caps the layers may consist of a low hydraulic
conductivity layer (usually clay) and a protective layer (usually vegetated topsoil).
The objective of the cap is to limit and control the infiltration of storm water into the area below through;
surface drainage, installation of a low permeability layer or a combination of the two.
The objective of the monitoring and maintenance plan is to ensure that the integrity of the cap is not
compromised. Also included is guidance on the documentation of these activities and the reporting
requirements.
Visual inspection methods and frequencies, maintenance to control vegetation, as well as repair activities,
are provided in the Cap Monitoring and Maintenance Plan within the Project EPP. In addition, methods
to monitor the integrity of the monolith are provided.
7.6.2. Groundwater Monitoring Plan
The purpose of the Groundwater Monitoring Plan, as described in the EIS, is to assess and monitor the
following:
TAR PONDS SITE
Modification of groundwater flow field under the SYSCO High Dump and remainder of the eastern
shoreline;
Contaminated groundwater into the new channel;
Leaching of the solidified/stabilized Tar Pond sediments; and
Ensuring that remedial activities designed and implemented for the SYSCO Site do not alter or
negatively impact the remedial designs established for this Project.
COKE OVENS SITE
DNAPL transport pathway under the Coke Oven Brook Connector down to the South Tar Pond,
under Domtar Brook and behind the western cut-off wall;
Impact of modifying the groundwater flow field through installation of the cut-off walls;
The effectiveness of the groundwater collection system; and
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
90
97918-GEN-EMP-N-001-R2 14 June 2010
The effectiveness of the Coke Ovens WTP (CO8) in dealing with contaminated groundwater seeping
from several areas over the Site.
The objective of the Program is to provide on-going monitoring to supplement baseline data and confirm
the predictions in the EIS.
Groundwater monitoring locations for quality and level monitoring have been chosen strategically based
on the presence of existing wells with baseline data and their proximity to element activities. Frequency,
methodologies, sampling sites and parameters to be sampled are provided in the Project EPP.
7.7. Monitoring Results Reporting
An effective monitoring plan must generate accurate, verifiable reports in a timely manner. The data
must be defensible and must meet the criteria established in the QA/QC Plan for accuracy, precision,
completeness and typical representation. Establishing sound data management procedures and objectives
as the plan is being developed can be critical to its effectiveness. Monitoring design focuses on key
elements of data management including data acquisition, reduction, validation and reporting.
Follow-up monitoring is an integral element of the environmental assessment process. Compliance
monitoring data will therefore be provided to the Agency and provincial regulatory agencies, as required.
Monitoring reports will also be made available to federal, provincial, municipal agencies, stakeholder
groups and the general public.
It is important to ensure that the community is kept abreast of monitoring activities and results, as
indicated in the Public Reporting Protocol in Section 10.2. Results are currently and will continue to be
reported on the web. It is anticipated than an appropriate automated data management system established
onsite will be able to report exceedances in air quality within the hour the actual exceedance occurs.
There is a potential for measurements of certain parameters, such as ambient air, to exceed established
protocol standards beyond the boundaries of the Project Site. For instance, benzene, due to its toxicity,
volatility and relative in-situ concentration, is of prime importance during remedial monitoring and shall
have specific compliance criterion to ensure protection of the general public. In the event that ambient air
monitoring returns a result that indicates the public is at risk due to air quality, the public shall be
immediately notified by methods including, but not limited to, televised and radio broadcasts and/or visits
to surrounding neighbourhoods by local authorities. The Agency and provincial regulatory authorities
shall also be notified if ambient air monitoring indicates a threat to public health.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
91
97918-GEN-EMP-N-001-R2 14 June 2010
In regards to reporting a breach or failure of the cap, in order for the Agency to report a cap failure within
twenty-four (24) hours of discovery, the contractor responsible for monitoring the caps shall be required
to provide verbal notification immediately upon discovery and follow up with written notification and
supporting documentation by the end of the work shift or as directed by the Agency.
Additional details on reporting protocols are provided in Sections 4, 10.3 and 10.4 of this EMP.
8.0 CONTINGENCY AND EMERGENCY RESPONSE PLANS
One of the necessary elements in ensuring that the EMP delivers on its commitment to protecting the
environment and public and worker health and safety, is to provide strategic response protocols in the
event of unforeseen issues and emergency events. Although extensive protocols and monitoring systems
have been established to limit the risk of emergency situations, in large multi-faceted remediation projects
there are always unanticipated events that have to be addressed.
To address the potential for unanticipated events, AECOM/CBCL has developed the following site-wide
contingency plans containing protocols to be followed in emergency situations or in the event of other
unforeseen occurrences. These contingency plans are supplemented by the Agency Master Health and
Safety Plan (MHASP) and the Consultant‟s AHASP, both prepared by the Consultant, which contain
specific requirements regarding Emergency Response Planning. In addition, for each individual Project
element, a Contractor‟s AHASP and more task-oriented contingency plans (within the Detailed EPPs)
have been developed. All these plans have to be developed in accordance with the NSE Contingency
Planning Guidelines (NSE, 1990) and/or the Canadian Standard Association‟s (CSA) Emergency
Preparedness and Response for Industry (2003).
The following EMP Contingency Protocols outline Project-wide emergency measures that shall be
followed in the event of unexpected events considered potentially dangerous or hazardous to people or the
environment that could occur given the nature of the Project activities. These protocols shall be used in
conjunction with more specific task-oriented contingency protocols as outlined in the Detailed EPPs.
8.1. EMP Contingency Protocols
8.1.1. Failure to Comply Contingency Plan
All on-site activities are subject to the protocol provisions found in numerous Project documents. While
strong communication and reporting procedures have been put in place to guard against the breach of
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
92
97918-GEN-EMP-N-001-R2 14 June 2010
these protocol documents, it is still possible that protocols could be overlooked during the course of the
Project construction and monitoring activities.
In the event that the Contractor or another responsible party has been found not to be in compliance with
the requirements established in this EMP, the Agency‟s MHASP, the Contractor‟s AHASP, the EPPs, or
other documents pertaining to the environmental integrity of the Site or the protection of workers and the
general public, immediate action will be required.
Any failure to meet established procedural protocols involving a Contractor or their designee will be
reported by the Consultant or IQAC to the Agency. If required, the incident will also be reported to other
appropriate government bodies (e.g. NSE or Fisheries and Oceans Canada (DFO)) by the Agency for
review. In the event of a failure to meet the protocols, the Consultant will issue to the Contractor
disciplinary documentation in the form of either a Request for Action (RFA) or a Non-Compliance Report
(NCR). An RFA is issued when there is risk of breach of the protocols or the breach was minor, while an
NCR is issued when there is a more significant non-compliance. These documents are then responded to
by the Contractor until the issue is resolved.
It is the responsibility of the Agency to develop disciplinary or response measures for particular incidents
should they arise, in conjunction with the Consultant and the EMC. These disciplinary measures could
include, but are not limited to:
a) Written warning from the Agency specifying the specific deficiencies observed in the Contractor‟s or
responsible party‟s environmental protection and management implementation techniques;
b) Requirement for the Contractor‟s EM to increase frequency of environmental testing, obligation to
provide daily monitoring reports directly to the Agency and increased surveillance by the Consultant
and IQAC;
c) Order to revise personnel training protocols to better address environmental protection protocols;
d) Temporary stop work order;
e) Thorough investigation of the qualifications of the Contractor‟s EM, which could lead to dismissal or
a requirement to employ additional EMs; and
f) Contract termination.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
93
97918-GEN-EMP-N-001-R2 14 June 2010
8.1.2. Fuel and Hazardous Material Spills Contingency Plan
This Fuel and Hazardous Material Contingency Plan presents a response system in the event of the release
of petroleum, oils, or lubricants (POLs) or other hazardous liquids on-site. The objectives of the Plan are
to:
Generate awareness of potential spill situations;
Establish protocols to protect persons from danger and adverse health effects;
Ensure everyone is well trained and equipped in the event of a spill;
Minimize impairment to the quality of the natural environment (air, water or land);
Contain the extent of affected area and outline clear spill clean-up procedures;
Control degree of disturbance during the work;
Decrease risk of damage to property; and
Set out what notifications and reporting is required in the event of a spill.
In the event of an incident involving a spill or leak, spills or discharges of pollutants or contaminants
under the control of the Contractor and spills or discharges of pollutants or contaminants that are a result
of the Contractor's operations that cause or are likely to cause adverse effects, shall forthwith be reported
to the Agency by the Consultant according to the provisions outlined in the Agency‟s MHASP. Such
spills or discharges and their adverse effects shall be as defined in the Government of Nova Scotia
Emergency Spill Regulations (GNS, 1995d).
The Contractor‟s EM shall immediately report any unauthorized release of a contaminant listed in
Column 3 of Table 12, in quantities greater than those listed in Column 4, by calling the twenty-four (24)
hour spill reporting number: 1-800-565-1633. Using this number will ensure that both the federal and
provincial governments are made aware of the spill. The guidelines in Table 12 have been established in
the Nova Scotia Emergency Spill Regulations.:
The following information should be recorded in the event of a spill and reported to the twenty-four (24)
hour spill reporting centre:
Location of spill;
Time of observation of spill;
Reported by;
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
94
97918-GEN-EMP-N-001-R2 14 June 2010
Probable (or known) sources of the spill;
Probable (or known) time of the spill;
Nature of material spill;
Probable (or known) volume of spill;
Probable (or known) duration of spill;
Area affected;
Mobility of spill;
Weather, water, or geographic conditions;
Action being taken to contain and/or control the spill;
Personnel at the scene of the spill;
Resources threatened (e.g. water supply, bird colony, fish kills, etc.);
Other agencies contacted; and
Any other pertinent information.
In the event of a spill or leak, the following procedure shall be followed:
a) The activity causing the spill will be stopped. If the spill or leak is minor and the individual who
discovers the spill or leak is aware of the properties of the spilled substance, this individual shall
attempt to stop and contain the leak or spill. Following containment, arrangements for cleanup shall
be made by the Contractor„s Site Supervisor.
b) If the spill or leak is significantly large that it cannot be cleaned, controlled or contained by the
individual who discovers it or if this individual is unaware of the properties of the substance that has
leaked or spilled, that person shall immediately vacate the area and notify the Contractor‟s Site
Supervisor. Visible warnings, such as signs or pylons, shall be positioned surrounding the area of the
spill and all workers shall evacuate the area.
c) The on-site Contractor‟s EM will have the full authority to take appropriate action without
unnecessary delay.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
95
97918-GEN-EMP-N-001-R2 14 June 2010
d) In the event that the spill or leak enters a freshwater body (with or without fish habitat), the
Consultant shall report the incident to the NSE, DFO and Agency and coordinate a cleanup by the
Contractor according to regulatory requirements, as dictated by the indicated regulatory authorities.
e) In the event that the spill or leak enters coastal waters, either directly or through freshwater discharge,
the Consultant shall notify the Canadian Coast Guard, NSE, DFO and Agency. The Contractor‟s Site
Supervisor shall work with the Consultant and the Canadian Coast Guard in coordinating a clean-up.
f) All spills, whether major (as identified in Table 9) or minor shall be documented by the Contractor‟s
EM in an EIL (Appendix F) and submitted to the Consultant forthwith, along with a mitigative
measures program. If the issue is not resolved in a reasonable period of time, as per the mitigative
measures program developed by the Contractor‟s EM, the Consultant shall contact the Agency. The
Consultant shall contact NSE immediately in the event of a major spill as outlined in this section.
g) In the event of a spill, leak or discharge, the Contractor‟s EM shall work with the Consultant and the
authorities (NSE and others, as required) in coordinating a clean-up, which will include the following
actions, where appropriate:
Deploy on-site personnel to contain the spilled material using absorbent material or booms, as
appropriate;
Assess site conditions and environmental impact of various clean-up procedures;
Choose and implement an appropriate clean-up procedure;
Deploy on-site personnel to mobilize pumps and empty drums (or other appropriate storage) to
the spill site;
Apply absorbents as necessary;
Remove any contaminated sediment/soil, as required;
Dispose of all contaminated debris, water, soil, cleaning materials and absorbents generated by
the clean-up operation to approved disposal site; and
Take all necessary precautions to ensure that the incident does not recur.
h) During on-site activities, the following spill response resources shall be available close to potential
sources of fuels and/or hazardous materials in readiness to respond to accidental releases:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
96
97918-GEN-EMP-N-001-R2 14 June 2010
Absorbent materials (e.g., sorbent pads, Sorb-All, vermiculite);
Small hand equipment (e.g. shovels, tool kit, sledgehammer, buckets, tarpaulins, one (1) empty
drum, personal protective equipment (PPE); and
A fire extinguisher.
i) The Contractor„s EM shall follow all procedures outlined in the Agency‟s MHASP, Emergency
Response and any additional protocols outlined in the Contractor‟s AHASP. Work in the area shall
only resume once the spill has been cleaned or contained and the leak stopped.
In the event of personal injury or a near miss involving on-site workers, incidents are to be reported to the
Contractor‟s Site Supervisor, who will submit written documentation of the incident to the Consultant
who will pass the documentation on to the Agency and, if necessary, to NSE, according to the provisions
outlined Agency‟s MHASP. Any additional protocols outlined in the Contractor‟s AHASP shall also be
implemented, as required.
Table 12: Spill Report Requirements
Item
No.
TDGA
Class
Description of Contaminant Amount
Spilled
1. 1 Explosives any amount
2. 2.1 Compressed gas (flammable) 100 L
3. 2.2 Compressed gas (non-corrosive, non-flammable) 100 L
4. 2.3 Compressed gas (toxic) any amount
5. 2.4 Compressed gas (corrosive) any amount
6. 3 Flammable liquids 100 L
7. 4.1 Flammable solids 25 kg
8. 4.2 Spontaneously combustible solids 25 kg
9. 4.3 Water reactant solids 25 kg
10. 5.1 Oxidizing substances 50 L or 50 kg
11. 5.2 Organic peroxides 1 L or 1 kg
12. 6.1 Poisonous substances 5 L or 5 kg
13. 6.2 Infectious substances any amount
14. 7 Radioactive substances any amount
15. 8 Corrosive substances 5 L or 5 kg
16. 9.1
(in part)
Miscellaneous products or substances, excluding PCB mixtures 50 L or 50 kg
17. 9.1
(in part)
PCB mixtures of 50 or more parts per million 0.5 L or 0.5 kg
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97
97918-GEN-EMP-N-001-R2 14 June 2010
Item
No.
TDGA
Class
Description of Contaminant Amount
Spilled
18. 9.2 Environmentally hazardous substances 1 L or 1 kg
19. 9.3 Dangerous wastes 5 L or 5 kg
20. none Asbestos waste as defined in the Asbestos Waste Management Regulations 50 kg
21. none Used oil as defined in the Used Oil Regulations 100 L
22. none Contaminated used oil as defined in the Used Oil Regulations 5 L
23. none A pesticide in concentrated form 5 L or 5 kg
24. none A pesticide [in] diluted form 70 L
25. none Unauthorized sewage discharge into fresh water or sensitive marine water 100 L
26. none Ozone depleting substances as defined in the Ozone Layer Protection Regulations 25 kg
8.1.3. Malfunctions and Accidents Contingency Plan
During the course of the work on the Project, there is a possibility that some of the following
malfunctions and accidents could occur:
a) Failure of heavy construction machinery or remediation equipment resulting in construction delays,
damage to remediation efforts and/or personal injury.
b) Failure of structural components during the course of site remediation activities (e.g. containment cell
breach during dewatering), resulting in construction delays, damage and/or personal injury.
c) Failure of site mitigation controls.
d) Off-site traffic accident resulting in personal injury, damaged equipment/vehicles and/or spillage of
fuel, construction materials or contaminated excavation materials.
e) On-site traffic accident resulting in personal injury, damaged equipment/vehicles and/or spillage of
fuel, construction materials or contaminated excavation materials.
To minimize the risk of the listed potential malfunctions and accidents, all those working on the Project
shall follow the following precautionary procedures:
a) All on-site equipment, machinery and structural components of the construction area are to be
routinely inspected and monitored to ensure proper working order.
b) The Contractor Traffic Management Plan (Section 5.2), will be followed to ensure that proper traffic
safety protocols are set out for all those operating motorized vehicles on or off-site. It is the
responsibility of the Contractor‟s Site Supervisor to ensure that the plan is followed.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
98
97918-GEN-EMP-N-001-R2 14 June 2010
c) Specific Health and Safety Plans shall be completed and followed for all activities on-site, as
specified in the Agency‟s MHASP. These additional Health and Safety Plans shall be contained
within the Contractor‟s AHASP.
In the event of a vehicle or machinery malfunction or collision off-site:
a) The appropriate authorities shall be notified by the Contractor‟s Site Supervisor.
b) Any and all spilled construction materials or contaminant spills shall be dealt with in accordance with
the procedures outlined in Section 8.1.2.
In the event that a malfunction or accident occurs such that those working on or off-site are in the
immediate area are in danger, the following measures, in addition to the provisions established in the
Contractor‟s AHASP, shall be followed:
a) The area shall be immediately evacuated by the Contractor‟s Site Supervisor and appropriate
emergency personnel notified.
b) The Contractor‟s Site Supervisor shall ensure that all those working in the area are accounted for
following evacuation. Any persons missing shall be reported immediately to appropriate emergency
personnel.
c) No one shall re-enter the work area until notified by emergency personnel and the Contractor‟s Site
Supervisor that it is safe to do so.
d) Whether the malfunction and/or accident occur on or off-site, the Contractor‟s Site Supervisor shall
report the incident to the Contractor‟s EM, the Consultant, the Agency and NSE and all appropriate
emergency personnel. The Agency shall inform the regulatory authorities of the reported incident, if
warranted.
e) In the event of personal injury or a near miss involving on-site workers, all incidents are to be
reported to the Agency and NSE by the Contractor‟s Site Supervisor, according to the provisions
outlined in the Agency‟s MHASP. Any additional protocols outlined in the Contractor‟s AHASP
shall also be implemented, as required.
8.1.4. Fire Response Contingency Plan
There exists the potential for fires on all work sites that involve mechanical equipment and fuels;
however, mitigative measures can be taken to minimize the potential for fires at the work site. All
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
99
97918-GEN-EMP-N-001-R2 14 June 2010
precautions necessary shall be taken to prevent fire hazards when working at the Site. These include, but
are not exclusive to:
a) All flammable waste shall be removed on a regular basis and disposed of at an approved disposal site,
according to the Detailed EPPs.
b) All fire equipment on the work site are to be checked on a routine basis, in accordance with local fire
safety regulations, to ensure the equipment is in proper working order at all times.
c) All potential fire hazards are to be identified by the Contractor‟s Site Supervisor prior to beginning
work in an area. If a fire hazard exists, all on-site personnel working in the vicinity are to be property
notified and trained in how to mitigate the risk.
d) A meeting location (i.e. muster point) shall be established by the Contractor‟s Site Supervisor for
each working area, such that in the event of an emergency, on-site workers will know where to
gather.
e) Fire extinguishers shall be available at the work site. Such equipment shall comply with and be
maintained to the manufacturers‟ standards.
f) All workers shall be instructed in fire safety and emergency response protocols, as outlined in
Detailed EPPs and the Contractor‟s AHASP.
In the event that an incident involving fire does occur, the Agency‟s MHASP and Contractor‟s AHASP
shall be consulted. In addition, the following safety protocols shall be followed:
a) In the event of any fire, large or small, on-site personnel shall immediately notify the appropriate Fire
Department. The Contractor‟s Site Supervisor shall also be notified immediately.
b) If and only if, the fire poses no immediate threat to human safety and only after help from the fire
department is on the way, on-site personnel shall take immediate steps to extinguish the fire using the
appropriate fire extinguishing equipment.
c) If the fire cannot be contained, all on-site personnel shall vacate the area. All warnings shall be
delivered in such a way that the safety of vacating workers is not jeopardized.
d) On-site workers who have vacated the area of the fire shall gather at a safe location, identified by the
Contractor‟s Site Supervisor, who will also insure all workers who had been working in that area are
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
100
97918-GEN-EMP-N-001-R2 14 June 2010
accounted for. All missing persons shall be reported to the appropriate Fire Department personnel
upon their arrival to the scene.
e) No worker is to re-enter the vacated area until a safety clearance has been issued by Fire Department
personnel to the Contractor‟s Site Supervisor.
f) All incidents involving fire shall be reported by the Contractor‟s Site Supervisor to the EM, the
Consultant, the Agency, NSE and all appropriate emergency personnel. The Agency shall inform the
regulatory authorities of the reported incident, if warranted.
g) In the event that a fire event leads to a spill of contaminated material, the procedures and reporting
protocol outlined in Section 8.1.2. shall be implemented.
h) In the event of personal injury or a near miss involving on-site workers, all incidents are to be
reported to the Agency by the Contractor‟s Site Supervisor, according to the provisions outlined in
the Agency‟s MHASP. Any additional protocols outlined in the Contractor‟s AHASP shall also be
implemented, as required.
8.1.5. Environmental Contingency Plan
FLOODS
The likelihood of severe flooding that would materially affect the remediation efforts underway at the
Sydney Tar Ponds and Coke Ovens Sites is slim due to the flow regimes of the channels. Element-
specific concerns are outlined in the Detailed EPPs, as each area would be potentially affected by
different flooding types and sources.
All precautions are to be taken to ensure that in the event of severe weather, the integrity of the Project
and the safety of the workers will be maintained. These precautions include:
a) Consideration of the weather forecast for the Site.
b) All equipment and products are to be stored no closer than 30m from any watercourse or shoreline to
prevent shifting and associated environmental consequences in the event of the flooding.
Although flooding, were it to occur, would affect different site areas and Project activities in different
ways, the following general procedures shall be followed in flood conditions:
a) In circumstances where flooding is localized to specific areas, the Contractor‟s Site Supervisor will
instruct site workers to move vehicles and equipment out of low-lying areas prone to flooding for
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
101
97918-GEN-EMP-N-001-R2 14 June 2010
temporary work relocation. The same procedure shall be followed if flooding is expected to dissipate
in the short term.
b) All reasonable measures are to be taken by the Contractor‟s Site Supervisor to protect unfinished
Project elements remaining in the pathway of floodwaters from damage, either through the erection of
temporary flood barricades (e.g. sand bags) or by other means (e.g. tarps).
c) If extreme flooding occurs, all work shall be temporarily stopped. All workers shall vacate
potentially hazardous site areas and meet in a safe area established by the Contractor‟s Site
Supervisor.
d) Following a flooding event, the stability of the shoreline and work areas is to be investigated to
ensure safe working conditions and to assess any environmental impacts or damage to construction
elements. Only after the safety investigation has been completed by the Contractor‟s Site Supervisor
shall work resume in the affected area.
e) Any harmful environmental effects resulting from flooding shall be assessed and a restoration plan
developed, if necessary.
f) All incidents of flooding resulting in harmful environmental effects shall be reported by the
Contractor‟s Site Supervisor to the EM, the Consultant, the Agency, NSE and all appropriate
emergency personnel. The Agency shall inform the regulatory authorities of the reported incident.
SEVERE WEATHER
Severe weather conditions including high winds (when persistent wind gusts exceed 70 km/hr), heavy
rainfall (20mm within a twenty-four (24) hour period rain event), ice storms, lightning strikes and
extreme temperatures could effect on and off-site remediation activities. Impacts could include, but are
not absolutely limited to:
a) High winds could cause more medium and fine-grained particles to become airborne, leading to
difficult working conditions and potential health impacts, especially if contaminated sediments are
lifted.
b) High winds could also lower the stability of tall equipment, which could potentially lead to the
toppling of the equipment. As such, no workers should operate or be in the vicinity of tall equipment
during periods of high winds and the machinery shall be safely reconfigured to minimize height.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
102
97918-GEN-EMP-N-001-R2 14 June 2010
c) Heavy rainfall may result in flooding and a high volume of overland sheet flow with potential effects
on-site work, exposure of contaminated materials and compromised decontamination procedures,
sedimentation and impacts to the aquatic environment.
d) Ice and snowstorms could affect the safety vehicular traffic on and off-site through compromised road
conditions and decreased visibility. Progress on project elements may slow or need to be ceased
entirely if the storm is severe enough.
e) Lightning strikes while operating machinery could affect the safely of on-site workers in the vicinity
of large conductive equipment. All site work shall be temporarily ceased if lightning is present and
all workers shall clear the work area to a safe location.
f) Severe weather may cause a loss of site power, which could affect the integrity of the Project. All site
work shall be temporary ceased and all workers shall meet in a safe location.
g) Extreme heat or cold could place added stress on outside site workers, requiring a greater degree of
worker self-monitoring and the provision of appropriate break areas.
All precautions are to be taken to ensure that in the event of severe weather, the integrity of the Project
and the safety of the workers will be maintained. These precautions include:
a) Ensuring that exposure of incomplete or ongoing structural elements is limited.
b) Designing active areas to include surface water drainage, erosion control swales and holding points.
c) Enclosing areas used for storage of contaminated or hazardous substances or, if not enclosed,
establishing containment structures sufficiently large to manage unusual storm events without
uncontrolled discharge to the environment.
In the event of a severe weather occurrence (excluding temperature), the following procedures shall be
followed:
a) The Contractor‟s Site Supervisor will monitor weather forecasts and shall be responsible for
communicating all severe weather alerts to on-site workers and ensure that proper storm preparation
is undertaken.
b) If the weather event is sudden and no warning was available, all work shall be temporarily, but
immediately, stopped. All workers shall vacate potentially hazardous site areas and meet in an area
established by the Contractor‟s Site Supervisor.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
103
97918-GEN-EMP-N-001-R2 14 June 2010
c) If time allows, all areas under construction are to be covered or otherwise protected against the
impending storm prior to the onset of the severe weather event and the area vacated. Only after site
safety has been insured by appropriate personnel and the status communicated to the Contractor‟s Site
Supervisor shall work resume in the area.
d) Following all severe weather events, a thorough investigation of shoreline integrity and stability and
an assessment of the likelihood of a hazardous spill or leak, shall be conducted by the Contractor.
The findings of this investigation shall be compiled into a report.
e) In the event of personal injury or a near miss involving on-site workers, all incidents are to be
reported to the Agency and NSE by the Contractor‟s Site Supervisor, according to the provisions
outlined in the Agency‟s MHASP. Any additional protocols outlined in the Contractor‟s AHASP
shall also be implemented, as required.
f) In the event that flooding or hazardous spills occur as a result of a sever weather event, all appropriate
contingency plans and relevant guidelines set out for those occurrences shall be followed.
g) In the event of extremes in temperature, all precautions outlined in the Contractor‟s AHASP shall be
followed to protect worker safety and work will continue at an adjusted level. However, if the
Contractor‟s Site Supervisor feels that temperature extremes are such that working conditions are
unsafe regardless of added safety provisions, he or she maintains the right to call a temporary stop-
work order. If this occurs, all appropriate site contacts will be notified and a formal report submitted
to the Agency.
SEISMIC EVENTS
Based on the seismic activity generally experienced in the area of the Sydney Tar Ponds, it is unlikely that
seismic activity will have an adverse effect on Project construction elements and other related activities.
All construction activities and machine operations shall temporarily cease in the event of severe seismic
activities. A safety inspection will be carried out prior to recommencing activities and an incident report
will be filed.
CLIMATE CHANGE
Climate change, otherwise defined as the change in temperature, precipitation and wind speed averaged
over several decades or more, influences the frequency and severity of weather events and sea levels.
While temperatures in Atlantic Canada are expected to increase between 3 and 4°C over the next 100
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
104
97918-GEN-EMP-N-001-R2 14 June 2010
years, influencing both rainfall and storm surges, given the length of construction activities, the effects of
climate change are not expected to have manifested themselves to a degree that adversely effects the
implementation phase of the Sydney Tar Ponds and Coke Ovens Remediation Project. However, any
flooding and/or erosion shall be dealt with according to procedures outlined in Sections 8.1.4 and 8.1.7
and other relevant contingency plans.
8.1.6. Restricting Public Access Contingency Plan
As with any construction site, there exists a potential for vandalism, theft and trespassing on-site during
and/or after construction hours. The potential impacts of unlawful intrusion could include, but are not
limited to:
a) Theft of construction equipment, supplies or confidential information.
b) Damage to site barriers, including chain link fences and locks.
c) Disruption of construction area including tampering with equipment or supplies and general
disturbance of site re-vegetation efforts.
d) Personal injury as a result of trespassing, either to the trespasser or on-site workers.
If a trespasser is seen on-site:
a) The trespasser must be immediately escorted from site and the Contractor‟s Site Supervisor notified.
b) If the trespasser refuses to leave the site, the Contractor‟s Site Supervisor or night watchperson shall
immediately call the appropriate authorities and halt construction activities within the immediate area.
c) Once the trespasser has been cleared from the site, site activities shall resume and a site check shall be
initiated by on-site workers to determine if any damage was done to the site, equipment or site
barriers.
d) All incidents involving trespassing are to be reported by the Contractor‟s Site Supervisor or night
watchperson to the Agency, NSE and emergency personnel, if necessary. The incident shall be kept
on file by the Agency, which shall also insure that the any issues regarding site barriers are addressed,
if necessary.
If signs exist that a trespasser has been on the property (i.e. damage to site barriers, movement of
equipment or supplies, missing supplies or equipment, etc,) but no trespasser is currently on the property,
the following steps shall be taken:
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
105
97918-GEN-EMP-N-001-R2 14 June 2010
a) An attempt shall be made by the Contractor‟s Site Supervisor to determine where the trespasser
gained access to the Site. Appropriate signage shall be posted where suspected trespasser access
occurred.
b) All damaged barriers shall be repaired within forty-eight (48) hours or, if necessary, replaced within
seventy-two (72) hours. If barriers replacement is required, temporary barriers shall be erected. Any
damage locks shall be replaced within twenty-four (24) hours, inclusive of weekends and Statutory
Holidays.
c) On-site workers shall evaluate the condition of their equipment to ensure safe working order.
d) All missing or damaged equipment shall be reported to the Contractor‟s Site Supervisor, who will
then notify the appropriate law enforcement officials. The Contractor‟s Site Supervisor shall then
order replacement parts, supplies or repairs.
e) The night watchperson shall be notified of the intrusion and the suspect area where this intrusion
occurred.
f) If trespassing develops into an ongoing issue, further security measures, such as additional
watchpersons or movement-sensitive lights and/or cameras, shall be considered.
g) Again, all incidents involving trespassing are to be reported by the Contractor‟s Site Supervisor or
night watchperson to the Agency which shall keep the incident on file and insure that the any issues
regarding site barriers are addressed.
In the event of personal injury or a near miss involving either on-site workers or the trespasser(s), the
procedures outlined in the Agency‟s MHASP, Emergency Response shall be followed. Any additional
protocols outlined in the Contractor‟s AHASP shall also be implemented, as required.
8.1.7. Erosion/Sedimentation to Surface Water Contingency Plan
There is a possibility that a structural or equipment malfunction, accident, environmental event or
vandalism in construction areas could compromise the integrity of erosion control measures and/or slope
stability leading to surface water sedimentation and increased turbidity. Response protocols will depend
on the type of contaminants and the comparison of the contaminant level against the site-specific target
limits for surface water. The upper level criteria defined as a reportable event for turbidity will be an
increase by eight (8) Nephelometric Turbidity Units (NTUs) above background (upstream sample
location), when the background is between 8 and 80NTU. If background concentrations are greater than
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
106
97918-GEN-EMP-N-001-R2 14 June 2010
80NTU, then the upper level criteria defined as a reportable event for turbidity, will be 10% above
background (CCME, Water Quality Guidelines, 2006). The upper level criteria defined as a reportable
event for other surface water parameters are outlined in the surface water EEM.
In the event that the Consultant determines that erosion exceeds the provincial and federal
approvals/authorizations and/or the specifications as outlined in this Erosion/Sedimentation Contingency
Plan and the Contract are compromised, the Contractor shall:
a) Temporarily halt activities potentially contributing to the exceedance until levels decrease to an
acceptable level. During this time, all efforts will be made to rectify the cause of the exceedance.
b) Respond by:
Installing silt curtains around active cells and work areas;
Discontinuing or modifying water pumping rates and pre-treatment of discharged water;
Creation/repairing of sediment fences, Rip rap, check dams and/or settling ponds; and,
Repairing silt curtains and land based sediment and erosion control devices, as required.
c) Resume monitoring at the restart of the ceased activity at an increased intensity level (every fifteen
(15) minutes over a sixty (60) minute period) to verify that conditions have been abated.
d) Explanatory details documenting the erosion and any corrective measures taken will be documented
by the Contractor‟s EM in an EIL (Appendix F) and submitted to the Consultant for review.
e) Assess and record sedimentation effects on surrounding wildlife and natural habitats. If
environmental impacts are evident, efforts to restore natural habitats to pre-sedimentation conditions
shall be undertaken by the Agency or its representative. The NSE and other applicable regulatory
bodies shall also be contacted by the Agency in the event that natural habitats have been impacted by
sedimentation.
In addition, explanatory details documenting the exceedance and any corrective measures taken will be
documented by the Contractor‟ EM.
Should the upper level criteria be exceeded post-construction, responses include the evaluation of
potential contaminant sources and possible diversion or treatment.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
107
97918-GEN-EMP-N-001-R2 14 June 2010
A list of contacts will be provided to assist site personnel in carrying out the stop-work process and other
requirements of the Contingency Plan. The list will be available at construction sites and will provide
contact information for internal personnel and external officials.
8.1.8. Dewatering Contingency Plan
Dewatering activities may be required depending on the specific element tasks. Detailed EPPs containing
dewatering contingency plans will be designed specifically for individual Project elements and shall
include:
The conditions in which dewatering activities will cease and the contingency plan will be
implemented.
The procedure to rectify dewatering issues and appropriate reporting protocols.
In the event of flooding, the procedures outlined in Section 8.1.5 should be followed.
8.1.9. Archaeology and Heritage Resource Contingency Plan
The Archaeology and Heritage Resource Contingency Plan sets out the process for preserving and
protecting historical materials uncovered by remediation activities on the Tar Ponds and Coke Ovens
Sites. The Plan‟s guidelines address what needs to be done when artefacts, First Nations and historical
features or skeletal remains are discovered and were developed to:
Prevent the destruction of archaeology and historical resource materials uncovered by construction
activity while maintaining archaeological conditions.
Ensure that artifacts or skeletal remains are properly removed or handled appropriately.
Protect all archaeological and historical discoveries in keeping with provincial regulations and
cultural practices.
Dr. Stephen Davis through Davis Archaeology Consultants was consulted and contingency plans of
Canadian municipal and provincial jurisdictions were reviewed in the development of these guidelines.
Guidelines balance project requirement for timely handling of unexpected discoveries and historic
preservation concerns.
Carrying out the Archaeology and Heritage Resource Contingency Plan will largely depend on the ability
of frontline construction personnel to recognize and value heritage resources. This makes it necessary to
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
108
97918-GEN-EMP-N-001-R2 14 June 2010
promote the nature and value of heritage materials clearly expressing their importance to the heritage of
First Nations and other historic groups within Nova Scotia. This will be done through:
Posting of an archaeology/heritage resource stop work notice at construction sites including
workplace contacts to notify when heritage material is encountered.
Creation of a short heritage awareness presentation for inclusion in the orientation provided for all
Consultant staff, construction workers and Contractor(s).
Inclusion of this Archaeology and Heritage Resource Contingency protocol in the EMP which is an
information resource for the Consultant and Contractor(s).
A list of contacts will be provided to assist site personnel in carrying out the stop-work process and other
requirements of the Contingency Plan. The list will be available at construction sites and will provide
contact information for internal personnel and external officials.
The following summarizes the procedure to be followed if an artifact, First Nations or historical feature is
encountered during construction:
a) Project personnel are directed to stop all work in the immediate area of the discovery and report the
finding to a supervisor. The Contractor will not restart work in the area of a discovery until clearance
has been given by cultural authorities from Heritage Division and First Nations.
b) The Project Manager/designee will instruct the Contractor to flag or fence off the discovery area and
take measures to protect it until it can be assessed by an Archaeologist.
c) The Project Manager/designee will report the discovery to the Manager of Special Places at the
Heritage Division, the Executive Director of the Union of Nova Scotia Indians and Mi‟kmaq Rights
Initiative (contact Roger Lewis). The information provided will include the nature of discovery,
location and how it was discovered.
d) An Archaeologist will be consulted to determine whether the discovery is isolated or completely
disturbed by prior construction activities or a significant archaeological resource requiring further
evaluation and will advise the Project Manager/designee regarding when to restart construction
activities. The Project Manager/designee will consult with provincial and First Nations
representatives with respect to restart requirements.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
109
97918-GEN-EMP-N-001-R2 14 June 2010
e) An archaeological evaluation of the Site, if required, is to be done by the Archaeologist who is
approved by the Heritage Division, the Union of Nova Scotia Indians and Mi‟kmaq Rights Initiative
(contact Roger Lewis); provision of information about the discovery and its archaeological and
historical significance to provincial and First Nations representatives.
f) Documentation of the discovery to include:
Type of discovery – artifact or feature;
Composition – stone, wood, metal, ceramic, glass, etc.;
Location within the area of excavation – map;
Nature of the activity resulting in the discovery;
Time of discovery;
Name of person(s) who discovered the materials;
Extent of the area of discovery;
Measures to protect materials and the Site;
Photographs and profile drawings;
Present location of the material, if moved – storage, museum, university; and
Research questions associated with the discovery.
g) Carry out a plan, with the approval of Nova Scotia Museum and First Nations officials, to recover
historical resources from the archaeological site including removal and final placement.
h) Construction activities to resume upon the completion of the recovery plan and approval from Nova
Scotia Museum and First Nations officials; timely approval is needed to meet construction
requirements.
The discovery of human remains requires protective handling with respect and dignity. In the event that
skeletal remains are uncovered during the course of work, the following procedures shall be followed:
a) Project personnel will stop all work in the immediate area to keep at a minimum the disturbance of
bones and other associated materials; the site will be preserved and protected until burial concerns
have been resolved.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
110
97918-GEN-EMP-N-001-R2 14 June 2010
b) The Project Manager will instruct the contractor to secure the site to make sure that vital data are not
destroyed and exposure to the weather and casual viewing are minimized; all artifacts found in the
burial area are to be considered grave goods and kept with the skeletal remains.
c) The Project Manager will contact the local police and coroner who will determine whether the
remains are human, part of a burial or crime scene; age at death, sex and cultural group to be
determined by a Forensic Anthropologist/Archaeologist who will also determine if any scientific
analysis of skeletal remains or grave goods will be conducted.
d) The Project Manager will inform the Manager of Special Places at the Heritage Division and
Cemeteries Regulations officials in the Heritage Division of the Nova Scotia Ministry of Tourism,
Culture and Heritage about the discovery.
e) If the remains are of Aboriginal peoples, the Project Manager will immediately consult with the
Union of Nova Scotia Indians and Mi‟kmaq Rights Initiative (contact Roger Lewis) to inform them
about the discovery and obtain permission to conduct scientific analysis of skeletal remains and grave
goods, if necessary.
f) Project Manager will inform the representative (religious, historical) of the deceased that are not
Aboriginal about the discovery and obtain permission to conduct scientific analysis of skeletal
remains and grave goods.
g) An Archaeologist shall be engaged to assist in the investigation of the nature and extent of the
discovery of the human skeletal remains and cultural associations; the Archaeologist will consider
bone condition and discoloration, artifacts around the discovery site, knowledge of known
archaeological sites in the area, presence/absence of a coffin, depth of remains, position of body and
presence of grave goods.
h) The Project Manager will obtain a declaration from Cemetery Regulations officials whether the Site
is an Aboriginal people‟s cemetery. A cemetery that is not Aboriginal will require the identification
of a representative of the deceased from the same religious or cultural affiliation. This representative
shall:
Oversee the removal of the remains to a designated resting place; an Aboriginal cemetery, other
existing cemetery or in an area on the Site.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
111
97918-GEN-EMP-N-001-R2 14 June 2010
Negotiate with the Agency the costs of uncovering, removing and re-interning remains with
minimum damage while observing religious and other cultural requirements, processing
documentation and the cost of reburial.
i) Approval must be obtained by the Project Manager to restart construction activities from provincial,
local and relevant cultural authorities.
j) The Project Manager is responsible for the preparation of a report containing information on:
Location of discovery;
Nature of activity resulting in the discovery of the remains;
Time of discovery;
Name of person(s) who discovered the remains;
Measures to protect remains and the site;
Cultural association of the deceased, if available;
Boundaries and maps of the discovery area;
Style and manner of burial;
Description of artifacts;
Archaeological methods;
Local and Aboriginal knowledge; and
Present location of remains and grave goods.
k) A media representative from the Community Liaison Committee for the Project shall handle media
interest and ensure that photographs of skeletal remains are not publicly displayed, as this is
disrespectful to the deceased and offensive to the representatives of the deceased.
8.1.10. Unexpected Site Conditions Contingency Plan
While most conditions within the Project work area are known, it is possible that unanticipated site
conditions could be encountered. Proper management procedures, regarding the discovery of active
pipelines or utilities, or soil and/or groundwater impacts, are required to ensure the safety of on-site
workers.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
112
97918-GEN-EMP-N-001-R2 14 June 2010
ACTIVE PIPELINES AND UTILITIES
It is the responsibility of the Contractor to ensure that any pipelines or utilities on site are located and are
inactive prior to the commencement of construction activities. However, should the Contractor uncover
an active pipeline or utilities during the course of construction activities, or a pipeline containing the
remnants of a suspected hazardous material, the Contractor is to notify the Agency and the Consultant
immediately for the arrangement of proper shut-off and/or removal.
UNANTICIPATED DISCOVERY OF MATERIAL OR SITE AREA CONTAMINATION
To more accurately predict the exact conditions of each construction or activity area, a pre-assessment of
site risk shall be conducted prior to the commencement of construction activities. All workers are to be
trained to recognize potential contaminants and the procedures to follow if unexpected conditions are
encountered.
EMERGENCY PROCEDURE
When responding to unexpected site conditions during construction, the following procedures shall be
followed:
All work in the vicinity of the discovery shall be immediately stopped and the site secured. The
Consultant shall ensure that the Site is secured and that the appropriate response is initiated.
A worst case scenario shall be assumed and personnel shall stay away from the work area. The scene
shall be cordoned off to prevent contact with the pipeline, utilities or hazardous materials, until it is
determined that it is safe to do so.
Sampling of contaminated soil is to be arranged, so that the degree of contamination can be
determined. The soil sample shall be submitted to a laboratory for chemical testing.
The Consultant shall provide the Project Manager with the approach developed for site clean-up. The
Project Manager shall review and approve the approach for clean-up prior to commencing.
The Consultant will implement the approved plan and provide the Project Manager with written
progress reports. A final report, summarizing all activities related to clean-up, shall be prepared by
the Consultant and submitted to the Project Manager and Agency.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
113
97918-GEN-EMP-N-001-R2 14 June 2010
8.1.11. Cumulative Effects Contingency Plan
Cumulative effects may occur when the environmental impact of one Project element or activity
combines with the impact of other past, present and future Project elements and/or other
projects/activities in the area. If it is discovered during the course of environmental effects monitoring
that cumulative impacts associated in whole or in part with the Sydney Tar Ponds and Coke Ovens
Remediation Project are likely to exceed pre-defined definitions of significance as contained by the EIS,
or are likely to occur if the planned procedures are followed, then adaptive management must be
implemented to mitigate these effects. Appropriate response procedures will depend on the type of
exceedances that are witnessed or expected to occur. The EIS identifies four criteria that must be
considered when assessing whether cumulative effects may result from Project activities:
a) The status of another element or activity, whether it is past or existing, certain or planned, or
reasonably foreseeable.
b) The potential for overlap related to timing of the Project and or element activities.
c) The potential for overlap related to the type of effect, whether the impact of the activity is similar to
the Project-related residual effects.
d) The potential for spatial overlap of Valuable Environmental Components (VECs).
e) The EIS explores a number of implemented and planned activities on the Sydney Tar Ponds and Coke
Ovens Remediation Project and the likelihood that interaction between them will lead to cumulative
effects.
Mitigation for cumulative effects tend to be more regionally oriented, rather than spatially associated with
specific Project activities. The EIS has identified the likely cumulative effects and mitigation measures
required to result in minor adverse or beneficial residual effects, as shown in Table 13. The Contractor‟s
Site Supervisor shall be aware of possible cumulative effects as described in the EIS, in addition to
understanding and implementing the appropriate mitigative measures to result in insignificant or
beneficial environmental effects.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
114
97918-GEN-EMP-N-001-R2 14 June 2010
Table 13: Cumulative Effects, Mitigations Measures and Significance
VEC Potential Cumulative Effect Mitigation/Enhancement
Residual
Cumulative
Effect
Significance
1 Groundwater,
Surface
Water, Soil
Quality
Resources
Potential for adverse cumulative effect:
Mounding of groundwater along
western shore of Muggah Creek
channels and groundwater
collection system along SYSCO
property with potential for changes
in local groundwater flow field
Coordination with
remediation designs for
adjacent properties
If required: design
refinements (groundwater
collection system, e.g.,
French drains)
Minor adverse
effect
(localized;
effective
mitigation
available)
Insignificant
Potential for beneficial cumulative
effect:
Overall reduction in contamination
levels in concert with other
remediation projects and
preventative works
No enhancement measures
required/identified
Beneficial
effect
Not
evaluated
2 Marine
Habitat and
Biota
Potential for adverse cumulative effect:
Loss of marine habitat/estuary
habitat
Coordination of habitat
design of new channels
with habitat designs at
Battery Point Cofferdam
Beneficial
effect
Not
Evaluated
Potential for beneficial cumulative
effect:
Overall reduction in contamination
levels in concert with other
remediation projects and
preventative works
No enhancement measures
required/identified
Beneficial
effect
Not
Evaluated
3 Freshwater
Habitat and
Biota
Potential for beneficial cumulative
effects:
Overall reduction of contaminant
levels and exposure of freshwater
biota to CoCs in concert with other
remediation projects and
preventative works
Habitat enhancements
(buffer plantings) along
embankment of new surface
water channels;
Integration of new stream
channels into future
habitat/open space network
Beneficial
effect
Not
evaluated
4 Wildlife/
Vegetation
Potential for adverse cumulative effect:
Loss of habitat and vegetation
communities typical for derelict
sites in urban environments
Re-creation of high-quality
diverse habitat in
remaining/future open
space
Linear habitat along water
courses
Minor adverse
effect (affected
features are
common and
easy to
recreate)
Insignificant
5 Labour and
Economy
Potential for adverse cumulative effect:
Temporary construction-related
employment
Potential for sustained future
economic growth
Maximize use of local
supply and labour markets
Communication with local
economic development
department
Communication with
community at large
Beneficial
effect
Not
evaluated
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
115
97918-GEN-EMP-N-001-R2 14 June 2010
In addition to the long-term potential cumulative effects listed in Table 13, the interaction of several
Project components could impact regional air quality in the short term as well. As such, real time air
monitoring will be implemented to monitor air quality exceedances instantaneously. If results from this
program show an exceedance, as described in the Real Time Monitoring Program (provided in the
Detailed EPPs), an investigation to determine the source shall be immediately initiated by All Tech. If
the source is identified as being generated off-site, All Tech will notify the Agency, who will in turn
notify NSE and the CBRM. Any issues shall be resolved between the various parties without unnecessary
delay to the Project. Any data collected during this time must be documented, analyzed and included
within a written account of the investigation.
8.1.12. Key Contact List
As part of this assignment, it is important that communications occur in an efficient manner. This will
require that contact names and phone numbers of critical personnel and services are readily available at
all times. This is also important for key organizations and/or individuals that may be contacted during
emergency situations and/or regarding regulatory issues. The Emergency Contact List for this project
will be provided under a separate cover and updated on a monthly basis by the Agency‟s designate and
distributed to all affected parties.
8.2. Contingency Planning in Detailed EPPs
Contingency plans shall be included in the Detailed EPPs to address potential risks resulting from specific
element tasks. While the EMP provides an overview of contingency plan procedures, the Detailed EPPs
shall be consulted and kept on hand during site activities in the event of an incident requiring mitigative
action. The Detailed EPP and the Contingency Plans therein are to meet the following requirements:
a) Identify the physical and chemical properties and characteristics of the materials being used; where
they are located in relation to the surrounding area; and how they are stored, handled or transported.
b) Identify the potential concerns/problems or emergency scenarios associated with these construction
activities or release of the material (including both on-site and off-site) to determine what could go
wrong that would lead to an accident or emergency.
c) Develop and implement prevention measures in the construction activities or material use to reduce
the likelihood of an emergency occurring (i.e.; train staff, identify potential issues in current practices
and change them accordingly, etc.).
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
116
97918-GEN-EMP-N-001-R2 14 June 2010
d) Describe roles and responsibilities of key personnel and responders during an emergency.
e) Provide contact lists for emergency resource personnel and equipment.
f) For each potential accident or emergency, develop plans to address the “next steps” should the
prevention measures fail to work or emergency situations arise including measures to be taken to
notify members of the public who may be adversely affected by the emergency.
g) Document and communicate reportable incidents and establish clear callout and notification
procedures for all relevant agencies.
h) Review the Contingency and Emergency Response Plans with Agency and Project Manager to obtain
comment and revise accordingly.
i) Ensure that the Contractor‟s Site Supervisor who is responsible for implementing the finalized
Contingency and Emergency Response Plans is fully versed with all aspects of each plan.
j) Train all on-site personnel with the procedures contained in the Plans and integrate these procedures
into the EPPs for implementation.
k) Revise the Contingency and Emergency Response Plans as required throughout the Project to address
new issues as they arise and update on-site personnel appropriately.
8.3. Implementation Responsibilities
Once the Contingency and Emergency Response Plans have been developed and approved, the
responsibility for implementing them lies with the Contractor and Environmental Consultant. Specific
responsibilities of the Environmental Consultant include:
Reviewing the Contingency Plans and Emergency Response Plans and identifying any issues or
concerns to the Project Manager and providing suggested changes and updates.
Providing advice to construction staff on proper emergency response procedures.
Monitoring the Contractor(s)‟s response to events resulting in the activation of its Contingency Plans
and Emergency Response Plans and reporting to the Project Manager on the effectiveness of the
response.
Initiating actions to correct any response deficiencies identified through the audit process and
bringing this to the attention of the Project Manager.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
117
97918-GEN-EMP-N-001-R2 14 June 2010
Documenting the implementation of the Contingency and Emergency Response Plans in emergency
response records for review by the Agency and the appropriate regulatory agencies.
Specific responsibilities of the Contractor(s) include:
Ensuring that all construction personnel are trained in Contingency Plan Implementation and
Emergency Response Techniques and that they have the appropriate equipment on hand.
Implementing Contingency and Emergency Response Plans when environmental situations, as
described in Section 8.1 of this EMP and in the Detailed EPPs, occur.
Documenting the implementation of the Contingency and Emergency Response Plans for review by
the Consultant, Agency and the appropriate regulatory agencies.
The emergency response records are to be incorporated into the monthly monitoring reports to identify
the response that had to be taken so that changes can be made to the appropriate EPP and the lessons
learned can be applied. For example, in the event of the failure of erosion and sediment control measures,
the results of the emergency response are to be documented in the Monthly Environmental Report, including
the nature of the failure, the preventive measures which could have been implemented to avoid the incident
(if possible), the emergency response measures taken to control the failure, the effectiveness of those
emergency response measures and the extent of the release of sediments.
9.0 ENVIRONMENTAL AWARENESS TRAINING
This section describes the approach to be taken by the Contractor(s) in developing and implementing
environmental awareness training to ensure that all on-site personnel are aware of the environmental
sensitivities associated with their actions; their roles and responsibilities in protecting the environment;
and, the mechanisms available to them to carry out their environmental protection responsibilities.
The Contractor(s)‟s Environmental Awareness Training Program must satisfy the following three main
goals:
a) Educate workers and visitors about the importance of environmental protection. While most
individuals may have some understanding of the importance of environmental protection, many
individuals may not fully understand or appreciate the relationship between their actions and
environmental degradation.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
118
97918-GEN-EMP-N-001-R2 14 June 2010
b) Inform staff and visitors of their responsibilities regarding the environment and provides them with
the necessary educational tools to fulfill these responsibilities.
c) Provide workers with a firm understanding of the environmental sensitivities associated with the
Project and the role they play in protecting the environment, as outlined in this EMP (through
implementation tools such as the EPPs and Contingency and Emergency Response Plans).
The elements the environmental training program must include are:
Identification of the training needs based on the proposed construction activities;
Identification of each component of the training program;
Identification of the means by which employees/visitors will be trained;
Documentation of the information provided during training;
Evaluation of the effectiveness of the training received by each employee or visitor;
The basis for retraining employees/visitors; and
Identification of the means for implementing on-going training.
The Contractor in consultation with the Agency, must approve the training program before construction
starts. Once approved, the Consultant shall be provided with all training records and shall keep track of all
training completed. The Contractor is responsible for ensuring that all on-site personnel have undergone
environmental awareness training before working on the Site. Proof of completion of the training
program must be kept on file by the Consultant. The Consultant shall provide the Agency with training
records, upon request.
The awareness training must include, as a minimum, the following key factors:
The Project overview and timetable.
Overview of the environmental regulatory requirements: Overview of the existing environmental
conditions and sensitivities.
Identification of the construction activities that could negatively affect the environment; the resultant
environmental effects; and the required mitigation measures that must be implemented and
maintained to avoid or minimize these effects (e.g., proper installation and maintenance of erosion
and sediment control procedures).
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
119
97918-GEN-EMP-N-001-R2 14 June 2010
All aspects of the EMP and EPPs (including the roles and responsibilities of staff).
Environmental inspection and QA/QC procedures, roles and responsibilities.
Contingency and Emergency Response Plans.
Documentation and Reporting Procedures.
Refresher seminars are to be held as required to address any shortfalls identified during the QA/QC
program. Construction personnel are to be trained in all Contingency and Emergency Response Plans and
reporting procedures; Site visitors are to be made aware that Contingency and Emergency Response Plans
have been developed for specific potential events.
9.1. Specific Environmental Awareness Programs
As per the requirements of the Agency‟s MHASP, all personnel who are scheduled to perform work on
the Site must complete appropriate training sessions (i.e. orientation, medical surveillance, hazard
assessment and management and PPE) that commensurate with the activities and hazard level to which
the employee may be potentially exposed prior to commencement of activities. Site visitors do not
require such training; however, they may need to be accompanied by Agency personnel, or their
designate. Contractors will submit a training program as part of their AHASP for review and acceptance
by Agency.
The Contractor(s) is responsible for including specific environmental awareness programs for the various
Contingency and Emergency Response Plans in the Environmental Awareness Training of all on-site
personnel. The following sub-sections provide a brief overview of some of the considerations that must
be included in these specific environmental awareness programs.
9.1.1. Decontamination
The Contractor will address decontamination procedures for personnel, equipment and vehicles in the
Contractor‟s AHASP. Standard Operating Procedures for Decontamination shall be developed to
minimize the spread of contamination within different areas of the Site. Contractors are therefore
required to define, maintain and provide a clear delineation for the following contamination control
zones:
Exclusion Zone;
Contamination Reduction Zone; and
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
120
97918-GEN-EMP-N-001-R2 14 June 2010
Support Zone.
Contractors shall provide, as a minimum, the following:
Suitable PPE for decontamination activities;
Suitable containers for storage and disposal of used disposable PPE; and
Potable water and a suitable sanitation facility.
Contractors will be required to enforce the following provisions:
On-site personnel shall wear appropriate PPE at all times when entering or working in the Exclusion
or Contaminant Reduction Zones.
Used disposable PPE shall not be reused and when removed, shall be placed inside appropriate
containers provided for that purpose.
Soiled disposable outerwear shall be removed prior to entering the lunch area and prior to cleansing
hands.
On-site personnel shall thoroughly cleanse their hands and other exposed areas before entering the
smoking or lunch area and before leaving the Site.
All personnel in Level A or B PPE, or Level C depending on work conditions, will change to fresh
clothing after each working period or shift, prior to leaving the Site.
Water generated from washing and showering shall be stored or disposed of in accordance with
applicable regulations and standard practices.
Work boots shall be left at the Site at the end of each workday or cleaned/brushed to remove visible
dirt before leaving the Site. Grossly contaminated boots shall be left at the work site.
9.1.2. Spills Response
All employees of the Contractor(s) and its sub-Contractor(s) must aware of the provisions outlined in
Section 8.1.2 and be trained in proper spill response procedures including:
Spill prevention;
Worker safety and the handling of hazardous liquids;
Potential hazards involved in the Project;
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
121
97918-GEN-EMP-N-001-R2 14 June 2010
What to do when a spill is discovered;
Notification and reporting requirements;
Spill containment;
Emergency evacuation and First Aid;
Environmental regulations and appropriate government agencies; and
Spill cleanup and disposal.
9.1.3. Fire Response
In preparation for the possible event of a fire, all construction staff and sub-contractor(s) staff must be
aware of the provisions outlined in Section 8.1.4 and be trained in the proper fire response, including:
Fire prevention training, including the location and use of on-site fire-fighting equipment;
Explanation of the purpose of the Fire Response Plan and when the plan is triggered; and
Explanation of the roles and responsibilities and accountability for implementing the plan.
If it is anticipated that a fire or discharge thereof, is likely to impact surrounding neighbourhoods (i.e.
through smoke, vapours released), then the affected public shall be notified using emergency broadcasting
and neighbourhood evacuation techniques, such as police patrol. If adjacent work sites are likely to be
impacted by fire, a cease work notice shall be issued and, if necessary, the affected areas shall be
evacuated.
9.1.4. Discovery of Unexpected Site Conditions
All contractor(s) and sub-contractor(s) staff must be trained to respond appropriately in the event of the
discovery of unexpected site conditions, as described in Section 8.1.10, including:
Contaminated Site recognition;
The importance of stopping work and how to secure the site;
The importance of the proper management of contaminated materials;
Notification of appropriate personnel; and
Site clearance before re-starting work.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
122
97918-GEN-EMP-N-001-R2 14 June 2010
9.1.5. Archaeology and Heritage Resources
All employees of the contractor(s) and sub-contractor(s) must be trained in the proper response to the
discovery of archaeology and heritage resources, as outlined in Section 8.1.9, including:
The importance of protecting archaeology and heritage resources;
Recognition of archaeology and heritage resources; and
Procedures for stopping work, notification and work start-up.
10.0 COMMUNICATION AND REPORTING
Additional communication protocols and procedures to those found herein are currently being developed
by communication personnel at various levels of government. As such, this Communication and
Reporting section is subject to revision to reflect updated information as it becomes available.
10.1. Communication
Part of the success of the Project will require clear lines of communication, both within the Project and
externally. A Public Communication Plan is being developed by the Agency to inform public of planned
activity and schedule, to ensure timelines and effectiveness of internal and external communication,
including communications with the community and media, addressing the complexity of issues associated
with the Project.
As an integral part of the Project Team, Agency staff will communicate directly with the other team
members on a regular basis through attendance at project meetings, through telecoms and correspondence
and involvement in key decisions.
The Agency communications team will be provided with current information on Project progress and
issues and with support required to manage communications with stakeholders and interest groups.
The primary contact for this assignment will be between the Consultant‟s Project Manager and the
Agency‟s Project Director. During the start-up phase of the Project, clear communication protocol
between both parties will be established. It is imperative that all communications follow the protocol
established. This protocol will be developed jointly by the Consultant and Agency.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
123
97918-GEN-EMP-N-001-R2 14 June 2010
10.2. Public Reporting Protocol
The Sydney Tar Ponds Remediation Project will have an impact not only on the immediate Project area,
but also the surrounding neighbourhoods. Discharges to air, mitigation efforts regarding surface and
groundwater contamination and an influx of activity due to construction and remediation activities will be
monitored and results must be reported by the Agency to all those potentially impacted by these activities.
The purpose of the Public Reporting Protocol (PRP) is to establish which monitoring results and site
activities will be reported by the Agency, how this reporting will take place and the frequency with which
these reports will be issued. More specifically, the PRP sets out the details of which communication
methods the Agency will use to most effectively report results to individuals who are invested, involved
or interested in the Project or are members of the general public.
This Public Reporting Protocol has been developed to promote the following key principles:
PROTECTING PUBLIC HEALTH AND SAFETY
Health and Safety protocols are continuously implemented during on and off-site Project activities and
have been designed to protect the health and safety of both Project workers and the public. In addition,
resources have been dedicated to ensure that health and safety is integrated with all aspects of mitigation
and monitoring activities. From these mitigation and monitoring activities, the Agency is committed to
providing the public and all stakeholders with timely and useful information regarding the wellness of
their environment and the status of Project activities.
PROMOTING PUBLIC AWARENESS AND PARTICIPATION
The Agency is committed to promoting public awareness of the Project and ensuring that resources are
available to allow individuals to monitor the Project developments that affect them. More than just one-
way sharing of information, the Agency will set up feed-back mechanisms through the reporting mediums
selected that encourage open response and consultation with the community. These efforts will not only
add to the credibility of the Project, but also ensure that the community remains as committed to the
Project as other key Project proponents.
MAINTAINING PUBLIC ACCOUNTABILITY
Public reporting will clearly identify the agencies and companies involved in setting and fulfilling
monitoring requirements. This way, the public will be assured that proper care is being taken in the
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
124
97918-GEN-EMP-N-001-R2 14 June 2010
establishment of monitoring requirements and will have an avenue to follow if any questions arise
involving these requirements.
ENSURING THE EFFECTIVENESS OF MITIGATION MEASURES
Mitigation measures have been developed for each project activity. Commitment to public reporting will
ensure that mitigation measures are properly implemented, as the Project team is accountable not only to
regulatory and proponent agencies through the EMC, but also to the general public and other
stakeholders.
10.2.1. Reporting Results
10.2.1.1. Areas Subject to Public Reporting
The following areas of public interest will be subject to status reporting in accordance with the key
principles outlined in this PRP.
AIR MONITORING
Air monitoring reporting will be required to address the ongoing status of air quality, in addition to any
air quality issues and associated causes, arising from site-related operations. Air monitoring will mostly
be analytically based, but will also address any widespread public concerns or questions regarding air
quality that may be brought forward during the course of a reporting period. The PRP recognizes that air
quality reporting will be especially important to neighbourhoods situated adjacent to areas of project
activities.
NOISE MONITORING
Perimeter noise monitoring will be undertaken on-site whenever construction projects involving large
machinery or equipment is involved. Since excessive noise could become a nuisance to nearby residents,
noise monitoring results will be reported regularly to the public, accompanied by responses to concerns
that have been brought forward by local residents. Reports will also include references to the CBRM
noise by-laws and applicable Provincial and/or Federal guidelines, as verification that the Project
activities are within these limits.
GROUNDWATER MONITORING
Groundwater monitoring reports will be issued to the public that will address both the influence of the
channel on groundwater flow regimes and the status of potential contamination moving from off-site into
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
125
97918-GEN-EMP-N-001-R2 14 June 2010
the new channels. If a potential contaminant has been identified, mitigative measures to prevent negative
environmental affects will also be included in the Public Report.
SURFACE WATER MONITORING
Surface water monitoring results will be issued to confirm plans and activities regarding the cleanup and
stabilization of Site contaminants, in addition to the status of rehabilitation plans regarding water-based
creatures and marine habitats.
WASTE WATER MONITORING
Waste water monitoring will be ongoing, so the public will know the discharge rates and water treatment
processes that are occurring on-site. Information regarding discharge limits will also be available once
accepted by the NSE.
CAP MONITORING
Cap monitoring reports will be made available to all stakeholders, including the public, so that they are
able to understand the long-term capability of the cap to prevent the deterioration of the solidified masses
and potential migration of plant, animal, bacteria or other organisms into the capped area.
TRANSPORTATION MONITORING
Transportation monitoring is important to the public, as transportation of goods, waste, workers and
machinery to Site affects the traffic volumes, noise and air quality of surrounding neighbourhoods. To
assist the public in dealing with traffic issues and the effects of route changes, long-term major changes in
the Site transportation management regime will be reported to the surrounding public with notice. Public
feedback will be encouraged.
ACTIVITY REPORTING
Stakeholders will be made aware of all mitigation measures being implemented for specific Site activities.
In this way, they will be kept aware of what is being completed to monitor environmental effects, which
will then also be reported at the conclusion of the activity.
RESULTS OF SOLIDIFICATION AND STABILIZATION PILOT TEST
Reports monitoring the results from the solidification and stabilization pilot test will be available to the
public when completed.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
126
97918-GEN-EMP-N-001-R2 14 June 2010
EMERGENCY REPORTING
Emergency response and alerts with respect to critical events, official actions and public protection
instructions are imperative. Notification will be issued if danger to the public exists as a result of any
occurrence on or related to Site activities, as determined by the Nova Scotia Ministry of Health.
LOCAL ECONOMIC BENEFITS REPORTING
The Agency is also committed to communicating the local economic benefits that will result to the public
as a result of the remediation work being undertaken at the Sydney Tar Ponds. Evaluations of local
prosperity directly related to Project work will be reported annually.
10.2.1.2. Reporting Guidelines for Monitoring Results
Since monitoring results will need to be seen and understood by a diverse group of stakeholders, the
following reporting guidelines for monitoring results will apply to any information that is released for the
purpose of communicating to the public:
DISTRIBUTION
Information will be distributed widely using various mediums to ensure that both key interest groups and
members of the public that are not represented by organized groups will receive knowledge of relevant
Project events and publicly reported monitoring results.
REPORTING STYLES
By using a number of reporting outlets, as described in subsequent sections of this PRP, easy access to
information by a variety of stakeholders will be maintained. For the purpose of public reporting, detailed
analytical results will be explained in plain text and supplemented with explanatory matrices, maps and
diagrams. Specialized report formats will also be available upon request to those with disabilities.
TWO-WAY COMMUNICATION
Following the PRP key principle to ensure public participation in the Project, reports will be organized
such that public comments on monitoring results are encouraged. The Agency will follow-up on public
responses received.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
127
97918-GEN-EMP-N-001-R2 14 June 2010
ASSOCIATED COMMUNICATIONS GOALS
Along with reporting and keeping stakeholders aware of monitoring results, the overall intent of the PRP
is also to encourage a higher level of public awareness for the various Project components, their possible
effects and how to respond to emergency situations. As such, monitoring reports will also include
references to associated Project activities, the purpose of monitoring and potential effects and emergency
protocols.
10.2.1.3. Monitoring Parameters
There are a number of parameters that will be reported to the public and other stakeholders during the
course of construction and post-construction activities at Sydney. The following table, Table 14,
indicates the parameters that will be monitored during the Project, each further detailed in the Project EPP
and EEMs. The specific parameters that are monitored and reported will depend on the individual
element.
Table 14: Monitoring Parameters
Air Noise Sediments Groundwater Surface Water Marine
PARAMETERS PAH
VOCs including
benzene
Arsenic, manganese,
lead and benzene
Lower Explosive
Limit (LEL)
H2S
PCB
Dioxins/Furans
Particulates:
- PM2.5 , PM 10
(Dust)
- TSP
Wind Velocity and
Direction
Ambient
Noise
PAH
PCB
TOC
Arsenic,
cadmium,
copper,
mercury,
lead and zinc
Grain size
analyses
PAH, TPH,
BTEX
Metals
Inorganic
Chemistry
Water levels
PAH,
TPH/BTEX
Total Metals
General
Chemistry
Field
Turbidity
Flow
Water
PAHs
PCBs
General chemistry
Total metals
Field turbidity
Sediment
Grain size
PAHs
PCBs
Total organic carbon
(TOC)
Arsenic
Cadmium
Copper
Mercury
Lead
Zinc
Toxicity
Biota
PAHs
PCBs
Arsenic
Cadmium
Copper
Mercury
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
128
97918-GEN-EMP-N-001-R2 14 June 2010
Air Noise Sediments Groundwater Surface Water Marine
Lead
Zinc
Benthic
community
composition
10.2.1.4. Reporting Frequency
Different parameters require different reporting frequencies. In addition to three week notification of
transportation route changes and special task-specific reports, such as when pilot test results for
solidification/stabilization are complete, the following monitoring reporting frequencies (Table 15) will
be maintained:
Table 15: Monitoring Report Frequencies
FREQUENCY
Real Time Monthly Quarterly Annually
PA
RA
ME
TE
R
Air
Emergencies
Spills
Fires
Floods
Air
Noise
Surface water
Air
Noise
Groundwater
Sediment
Composite Samples
All monitoring results:
Including: Local
Economic Benefits
10.2.1.5. Communication Methods
Numerous mechanisms and support materials will be used to communicate monitoring results to the
public. These communication methods will include, but may not be excluded to, the following:
INTERNET WEB SITE
Air monitoring and other results will be posted on the Agency‟s Web Site, which will continue to expand
as new reports become available. The Agency Web Site will be reformatted so that it is made accessible
to people. In addition, interested parties will be able to sign up for updates on Project aspects, which will
then be forwarded electronically as they become available.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
129
97918-GEN-EMP-N-001-R2 14 June 2010
NEWSLETTER
The Agency‟s quarterly newsletter will be available to every household and business in Sydney. The
purpose of these newsletters is to report quarterly monitoring results, provide some information on Project
activities and emergency protocols and to follow-up on issues and concerns raised by the public.
COMMUNITY FACILITIES
Hard copies of monitoring reports will be available annually at designated locations (i.e. Agency office)
for public review.
PROJECT FACILITIES
Monitoring results will be available at the Agency‟s office for any interested member of the public.
MEDIA
Summarized results and emergency notifications will be issued using print and radio media to instill
immediate public awareness and encourage public response. News from the Sydney Tar Ponds
Remediation Project will be communicated in a way that is dependent on the purpose of the message; for
instance, an immediate press release will be issued in local, regional and national media channels, as
appropriate, in the event of an emergency.
RESPONSE LINE
An automated telephone response line will be established to allow communication of views and opinions
from the public to the Agency. Public comments will be considered and responses sent when applicable.
MEETINGS
Members of the Agency will be available to meet with local groups upon request to explain monitoring
results and reports and respond to any concerns. In addition to providing immediate guidance on
questions posed at these meetings, all comments will be recorded, considered and responded to in writing,
where appropriate.
10.3. Reporting
Environmental reports will be generated monthly for the duration of the Project. Results of
environmental reports will be reviewed with the Project and Construction Managers to determine what
has worked and what actions need to be taken to remedy any identified environmental problems. This
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
130
97918-GEN-EMP-N-001-R2 14 June 2010
may involve revisions to the existing EPPs, or development of new EPPs as required. The Managers will
then ensure that the appropriate new policies/procedures or EPPs are developed and provided to the
Environmental Consultant or for implementation.
Maintenance of this EMP will be the responsibility of the Project Manager or designate to ensure that the
most current and comprehensive version of this EMP as well as EPPs are available to Project staff,
regulating agency representatives, stakeholders, interested parties and others.
This continuous improvement process of inspection/monitoring, analysis, review, policy revision and
training will ensure that the EMP is meeting Agency‟s environmental protection commitments.
10.4. Document Control
A Quality Management Plan (QMP) was prepared which documents details on the program that will be
implemented to address the specific quality assurance requirements outlined in the Agency‟s Request for
Proposal for Engineering Design and Construction Oversight Services for the Remediation of the Tar
Ponds and Coke Ovens Sites document and in the Engineering Agreement for Design and Construction
Oversight Services for Remediation of the Tar Ponds and Coke Ovens Sites. The QMP consists of a
quality assurance policy, program description, procedures, forms and effective quality control verified by
documented review, testing and inspection.
All documents produced for the Project will be subject to established control procedures as detailed in the
QMP (Appendix E). Documents will be clear, understandable and sufficiently detailed as to purpose,
method, assumptions, design input, references and units such that they may be reviewed and verified
without recourse to the originator. Templates/master copies of key documents will be made available
electronically to all team members and will be updated regularly showing evidence of the revision date or
level. Drawings will be produced electronically and will be based on the Project‟s CAD Document
Production Procedures identified in the Project Implementation Plan (PIP).
10.5. Environmental Audits
To assist in ushering in a consistent and correctly implemented EMP for the Project, an audit function
will be applied to the EMP and associated supporting plans. The audit function will be facilitated through
two existing auditing mechanism: the external QA function and the internal QC Plan.
The internal QC Program will address the implementation of the EMP and associated supporting
documents within the scope of the overall PIP, and will thereby provide an audit function related to
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
131
97918-GEN-EMP-N-001-R2 14 June 2010
overall EMP implementation.
Findings and corrective actions identified through the two audit functions will be addressed as outlined in
the Project‟s Quality Management Plan (QMP), the QCP and the IQAP.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
132
97918-GEN-EMP-N-001-R2 14 June 2010
11.0 REFERENCES
AMEC Earth & Environmental, (2005a). Remediation of Sydney Tar Ponds and Coke Ovens Sites
Environmental Impact Statement. Sydney Tar Ponds Agency.
AMEC Earth & Environmental Limited, (2005b). Remediation of the Sydney Tar Ponds and Coke Ovens
Sites, Project Description. Sydney Tar Ponds Agency.
Canadian Council of Ministers of the Environment, (2006). Water Quality Guidelines. Author.
Canadian Environmental Assessment Agency & Nova Scotia Department of Environment and Labour,
(2005). Agreement Concerning the Establishment of a Joint Review Process for the Sydney Tar
Ponds and Coke Ovens Sites Remediation Project. Author.
Canadian Standards Association, (2003). Emergency Preparedness and Response, CAN/CSA –Z731-03.
Author.
Cape Breton Regional Municipality Council, (2005). Draft Secondary Planning Strategy of the North End
of Sydney. Author.
CBCL Limited & ENSR International (2003). Remedial Action Evaluation Report [RAER]: Tar Ponds
Site. Joint Action Group.
Government of Canada, (2007). Canada's New Government And Nova Scotia Invest $400 Million in the
Environmental Cleanup of Sydney Tar Ponds and Coke Ovens. Canada News Centre. Author.
Retrieved July 2007 from the World Wide Web:
http://news.gc.ca/web/view/en/index.jsp?articleid=271389
Government of Canada, (1999). Canadian Environmental Protection Act, c. 33. Department of Justice
Canada.
Government of Canada, (1992a). Canadian Environmental Assessment Act, c.33. Department of Justice
Canada.
Government of Canada, (1992b). Transportation of Dangerous Goods Act. Transport Canada.
Government of Canada, (1985). Fisheries Act, R.S., c. F-14, s. 1. Department of Justice Canada.
Government of Nova Scotia, (2005). Air Quality Regulations, N.S. Reg. 28/2005. Office of the
Legislative Counsel.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
133
97918-GEN-EMP-N-001-R2 14 June 2010
Government of Nova Scotia, (2002). Petroleum Management Regulations, N.S. Reg. 44/2002. Office of
the Legislative Counsel.
Government of Nova Scotia, (1998). Municipal Government Act, c. 18, s. 1. Office of the Legislative
Counsel.
Government of Nova Scotia, (1997). Water and Wastewater Facility Regulations, N.S. Reg. 83/97.
Office of the Legislative Counsel.
Government of Nova Scotia, (1995a). Environment Act, 1994-95, c. 1, s. 1. Office of the Legislative
Counsel.
Government of Nova Scotia, (1995b). Activities Designation Regulations, N.S. Reg. 47/95. Office of the
Legislative Counsel.
Government of Nova Scotia, (1995c). Environmental Assessment Regulations, N.S. Reg. 26/95. Office
of the Legislative Counsel.
Government of Nova Scotia, (1995d). Emergency Spill Regulations, N.S. Reg. 59/95. Office of the
Legislative Counsel.
Government of Nova Scotia, (1995e). Dangerous Goods Management Regulations. Office of the
Legislative Counsel.
Government of Nova Scotia, (1990). Pollution Prevention Workbook Appendix C: Contingency Plan
Criteria for Releases of Dangerous Goods and Hazardous Wastes. Nova Scotia Department of
Environment and Labour.
Government of Nova Scotia, (1989a). Dangerous Goods Transportation Act, R.S., c. 119, s. 1. Office of
the Legislative Counsel.
Government of Nova Scotia, (1989b). Special Places Protection Act, R.S., c. 438, s. 1. Office of the
Legislative Counsel.
Government of Nova Scotia, (1989c). Beaches Act, R.S., c. 32, s. 1. Office of the Legislative Counsel.
Government of Nova Scotia, (1989d), Motor Vehicle Act, R.S., c. 293, s. 1. Office of the Legislative
Counsel.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
134
97918-GEN-EMP-N-001-R2 14 June 2010
Jacques Whitford, Dillon Consulting, ADI Limited, CBCL Limited, (2002a). Contaminant Loading
Study for Muggah Creek. Report to Nova Scotia Department of Transportation and Public
Works.
Jacques Whitford, Dillon Consulting, ADI Limited, CBCL Limited (2002b). Contaminant Flux from
Muggah Creek to Sydney Harbour. Transportation and Public Works.
Nova Scotia Department of Environment and Labour (2007). Environmental Assessment Approval:
Sydney Tar Ponds and Coke Ovens Sites Remediation Project. Sydney, Nova Scotia: Author.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Appendix A
Project Site Overview
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Appendix B
Change Protocol Document
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
97918-GEN-PROT-N-001-RC.doc 29 October 2008
REMEDIATION OF THE TAR PONDS AND COKE
OVENS SITES
DESIGN AND CONSTRUCTION OVERSIGHT
SERVICES
ENVIRONMENTAL CHANGE PROTOCOL
97918-GEN-PROT-N-001-RC
Prepared by: Original Signed By Date: 29 October 2008
Janice Green
EMP/EPP Coordinator, AECOM
Reviewed by: Original Signed By Date: 29 October 2008
Shawn Duncan
Environmental Lead, AECOM
Approved by: Original Signed By Date: 29 October 2008
David Wilson
Project Director, AECOM
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Revision Summary
Revision Date of Issue Purpose
A 17 May 2007 Initial Issue to Client
B 15 January 2008 Final Issue to Client
C 29 October 2008 Revision Issued to Client
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Distribution List
STPA Project Manager (12) Sydney Tar Ponds Agency
David Wilson Project Director
Don Shosky Project Director
Shawn Duncan Environmental Director
Ray Rice Project Manager
John Fairclough Deputy Project Manager
Dan MacDonald Engineering Manager
Randy Pointkoski Construction OS Contract Admin. Manager
Jim Albury Construction Manager
Bruce Noble Design Coordinator
Robert Jones Quality Assurance Manager
Janice Green Project EMP/EPP Coordinator
File Copy CBCL Central Records
File Copy AECOM Library
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
TABLE OF CONTENTS
1. POLICY...............................................................................................................................................................1
2. PURPOSE............................................................................................................................................................1
3. SCOPE.................................................................................................................................................................1
4. INTERNAL REVIEW CHANGES ...................................................................................................................1
5. SCOPE OF WORK CHANGES........................................................................................................................2
6. APPROVED FOR CONSTRUCTION CHANGES.........................................................................................2
7. ENVIRONMENTAL RELATED CHANGE REQUIREMENTS..................................................................4
8. RESPONSIBILITIES.........................................................................................................................................5
9. REFERENCES....................................................................................................................................................5
i
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
1. POLICY
Environmental management, regulatory requirements or environmental protection measures (Environ-
mental related changes), will be implemented in a controlled manner to ensure that only authorized
changes are made and that the changes are issued to appropriate persons.
Environmental related changes will be fully documented and subject to review, coordination and approval
commensurate with the original design.
Environmental related changes will be described in such a manner as to facilitate incorporation into the
Environmental Management Plan (EMP), the Environmental Effects Monitoring Plan (EEM) and the En-
vironmental Protection Plan (EPP) documents in a timely manner.
2. PURPOSE
The purpose of this procedure is to provide guidelines to ensure environmental related changes are re-
viewed, implemented, checked and approved in a controlled manner.
3. SCOPE
This procedure applies to environmental related changes required by changes to the project scope of work
during the design phase; and, to design changes after the Approved for Construction design documents
have been issued for construction. This procedure also applies to any environmental related changes re-
quired as a result of permanent alterations in environmental protection measures employed resulting in
lessons learned. Any alterations made to the EMP or EPPs with respect to lessons learned, will also be
reflected in associated design documents.
4. INTERNAL REVIEW CHANGES
Changes made to environmental related documents, prior to each milestone peer review, will be consid-
ered as part of the iterative nature of the design process and will not be subject to formal change control.
1
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
5. SCOPE OF WORK CHANGES
Changes to the project scope of work that affect the environmental management, regulatory and protec-
tion requirements, will be documented on the Change Request Form QAF-020 and submitted to the
Environmental Manager for cost estimation and approval.
A record of all Change Requests will be recorded on the Scope Changes Log, QAF-021.
6. APPROVED FOR CONSTRUCTION CHANGES
This procedure applies to environmental related changes implemented after the Approved for
Construction (AFC) design documents for the Remediation of the Tar Ponds and Coke Ovens Sites pro-
ject, have been issued for construction.
All environmental related change requests by Contractors, the Sydney Tar Ponds Agency (the Agency) or
the Independent Engineer, including those for the EMP, EPPs or for terms and conditions of approvals
issues under Part V of the Provincial Environment Act, will be documented in a Request For Field
Change (RFFC) Form (QAF-032) completed by the originator of the change request and will be
submitted to the AECOM Environmental Coordinator, with additional information attached to clearly
describe the required change.
Environmental related change requests will be classified by AECOM Environmental Coordinator as either
minor or major. Major changes are defined as those affecting the results of:
• Remediation of the Sydney Tar Ponds and Coke Ovens Sites Environmental Impact Statement
(EIS) (AMEC, 2005a);
• Terms and Conditions for Environmental Assessment Approval, dated January 23, 2007, (Depart-
ment of Environment and Labour, Province of Nova Scotia);
2
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
• Government of Canada response to the Environmental Assessment Report of the Joint Review
Panel on the Sydney Tar Ponds and Remediation Project, December 2006 (Infrastructure
Renewal);
• Safety, regulatory or permitting requirements.
All other changes will be considered as minor.
Requests for field changes of a minor nature will be reviewed by AECOM Environmental Coordinator or
the Contract Administrator who will confirm the classification, before approval.
When the RFFC has been approved, a Field Change Record (FCR) Form (QAF-034) will be issued by the
AECOM Environmental Coordinator.
For environmental related change requests of a major nature, the Environmental Manager will coordinate
a formal review of the request for change, with the affected Design Leads, to confirm the need for and
implications of the change.
Consideration will be given to the following factors during the environmental related change review
process:
• the reasons and requirements for the changes;
• scope or complexity of change to determine extent of review;
• specific impact on EIS, Provincial Conditions of Approval, Federal Recommendations or Safety,
Regulatory or Permitting requirements;
• approval requirements; and
• assessment of proposed change will be carried out by AECOM and approved by the Agency,
NSE and the Environmental Management Committee (EMC).
3
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
If the need for the change is confirmed, the Environmental Manager will issue a Notice of Major Field
Change (NOMFC) Form (QAF-033) for authorization by the Project Manager of the implementation of
the change.
While the decision to approve major environment-related changes to the EMP or EPPs ultimately rests
with the NSE, these changes may also require approval from any or all of the following project
participants:
• The Agency Project Manager
• Independent Engineer (IE)
• EMC
When the required major change has been developed, a Field Change Record (FCR) Form (QAF-034)
will be issued by the AECOM Environmental Coordinator for acceptance by NSE, the Agency, IE and
EMC, so that necessary modifications to the project scope and budget can be executed and work
necessary to make the required change can proceed.
7. ENVIRONMENTAL RELATED CHANGE REQUIREMENTS
Environmental related change documents will be developed, as required, and coordinated with affected
interfaces, checked, approved, issued, distributed and controlled, to the same degree as the original
document.
When an environmental related change is approved, other than by revision to the affected documents,
measures will be established to incorporate the change into these documents where such incorporation is
appropriate.
Where an environmental related change is necessary because of an improved design, the design process
and verification procedures will be reviewed and modified, as required, as outlined in the Quality
Management Plan.
4
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Remediation of the Tar Ponds and Coke Ovens Sites Design and Construction Oversight Services
Environmental Change Protocol
All documentation produced during the environmental related change process will be signed and dated, as
a record of the formal Quality Assurance process for ultimate retention in the project files. New revised
documents will be clearly named such that the revision number can be found within the document file
name.
8. RESPONSIBILITIES
The Environmental Manager is responsible for reviewing, classifying and responding to all Change
Requests and Requests For Field Changes, coordinating a formal review of requests for major environ-
mental related changes, with the affected Design Leads, to confirm the need for and implications of the
change, issuing a Notice of Major Field Change when the need for the major change has been confirmed
and issuing a Field Change Record when the change has been completed.
The Project Manager or Deputy Project Manager is responsible for coordinating necessary approvals from
other project participants and authorizing major design changes.
The Project Administrator is responsible for retention of environmental related change records in the
project file and maintaining a change log that indicates the status and disposition of requested changes.
The Quality Assurance Manager is responsible for monitoring the environmental related change process
to ensure quality requirements are met.
9. REFERENCES
A QAF-020 Environmental Related Scope Change Request
B QAF-021 Environmental Related Scope Change Log
C QAF-032 Request for Field Change Form
D QAF-033 Notice of Major Field Change Form
E QAF-034 Field Change Record Form
5
97918-GEN-PROT-N-001-RC.doc 29 October 2008
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Appendix C
Conceptual Site Models
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Appendix D
Summary Base Project Schedule
Activity ID Activity Name Start Finish
TP2 Materials Handling FacilityTP2 Materials Handling Facility 23-Jul-07 A 15-Sep-09
Confirm Design Basis & Complete Detailed DesignConfirm Design Basis & Complete Detailed Design 23-Jul-07 A 19-Jun-08 A
TP2DD0270 Submit 95% Design Report 23-Jul-07 A
TP2DD0320 Submit 100% Design Report 26-Sep-07 A
TP2DD0420 Submit Bid Documents to Regulatory Agencies 20-Feb-08 A 28-Apr-08 A
TP2DD0460 Prepare Addenda as Required and Tendering 09-Apr-08 A 06-May-08 A
TP2DD0480 STPA Review Period and Contract Award 05-Jun-08 A 19-Jun-08 A
Contract Administration & Construction OversightContract Administration & Construction Oversight 19-Jun-08 A 15-Sep-09
TP2 Materials Handling Facility OperationsTP2 Materials Handling Facility Operations 16-Apr-09 A 13-Mar-14
Operations DesignOperations Design 16-Apr-09 A 07-Aug-09
TP2OD0020 Submit 75% Design 16-Apr-09 A
TP2OD0040 Submit 100% Design 27-May-09 A
TP2OD0050 Prepare Addenda as Required and Tendering 25-Jun-09 23-Jul-09
TP2OD0070 STPA Review Period and Contract Award 24-Jul-09 07-Aug-09
OperationsOperations 07-Aug-09 13-Mar-14
TP6 (A)Pump AroundTP6 (A)Pump Around 17-Jun-08 A 17-Sep-12
Part "A" Flow DiversionPart "A" Flow Diversion 17-Jun-08 A 04-Mar-09 A
TP6DD0360 Submit 100% Design & Tender Documents (Flow Diversion) 17-Jun-08 A
TP6DD0400 Submit Bid Documents to Regulatory Agencies (Flow Diversion) 25-Sep-08 A 02-Dec-08 A
TP6DD0430 Prepare Addenda as Required and Tendering (Flow Diversion) 10-Oct-08 A 21-Jan-09 A
TP6DD0450 STPA Review Period and Contract Award (Flow Diversion) 12-Feb-09 A 04-Mar-09 A
Part "A" Contract Administration & Construction Oversight (Flow Diversion)Part "A" Contract Administration & Construction Oversight (Flow Diversion) 04-Mar-09 A 17-Sep-12
TP6 (B)Solidification, Stabilization & Channel ConstructionTP6 (B)Solidification, Stabilization & Channel Construction 02-Sep-08 A 09-Aug-13
Part "B" Approve Treatability (NSE) Portion of Work is on TP6 (S/S)Part "B" Approve Treatability (NSE) Portion of Work is on TP6 (S/S) 02-Sep-08 A 25-Jun-09
TP6DD0660 Submit 100% Design & Tender Documents (S/S) 02-Sep-08 A
TP6DD0800 Submit Bid Documents to Regulatory Agencies (S/S) 30-Jan-09 A 02-Apr-09 A
TP6DD0830 Prepare Addenda as Required and Tendering (S/S) 19-Dec-08 A 05-May-09 A
TP6DD0850 STPA Review Period and Contract Award (S/S) 28-May-09 A 25-Jun-09
Part "B" Contract Administration & Construction Oversight (S/S)Part "B" Contract Administration & Construction Oversight (S/S) 25-Jun-09 09-Aug-13
TP6 (C) Ferry Street BridgeTP6 (C) Ferry Street Bridge 08-May-09 A 12-Jan-12
Part "C" Ferry Street Bridge (Preliminary Dates)Part "C" Ferry Street Bridge (Preliminary Dates) 08-May-09 A 25-Jun-09
TP6CDD0270 Submit 95% Design Report 08-May-09 A
TP6CDD0320 Submit 100% Design Report 25-Jun-09
Ferry Street Bridge Abutments (C-1)Ferry Street Bridge Abutments (C-1) 06-Jul-09 16-Sep-09
TP6C1DD0460 Prepare Addenda as Required and Tendering 06-Jul-09 04-Aug-09
TP6C1DD0480 STPA Review Period and Contract Award 25-Aug-09 16-Sep-09
Part "C" Contract Administration & Construction Oversight (F.S. Bridge C-1)Part "C" Contract Administration & Construction Oversight (F.S. Bridge C-1) 16-Sep-09 03-Feb-10
Ferry Street Bridge Superstructure (C-2)Ferry Street Bridge Superstructure (C-2) 26-Apr-11 13-Jul-11
TP62CDD0570 Prepare Addenda as Required and Tendering 26-Apr-11 31-May-11
TP6C2DD0590 STPA Review Period and Contract Award 22-Jun-11 13-Jul-11
Part "C" Contract Administration & Construction Oversight (F.S. Bridge C-2)Part "C" Contract Administration & Construction Oversight (F.S. Bridge C-2) 13-Jul-11 12-Jan-12
TP6 (D) Construction RoadsTP6 (D) Construction Roads 07-Nov-08 A 30-Jul-09
Construction Roads (Approved)Construction Roads (Approved) 07-Nov-08 A 20-Jan-09 A
TP6DDD1010 Prepare Addenda as Required and Tendering 07-Nov-08 A 05-Dec-08 A
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1Q2
2007 2008 2009 2010 2011 2012 2013 2014 2015
Design and Construction Oversight Services
Remediation of the Tar Ponds and Coke Ovens Site
Project No. 97918
95% &100% Design Report Submittals with Approval,
Tender, Contract & Construction Periods
25-Jun-09
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Page 1 of 2
PRELIMINARYTASK filter: PIP 95%100% part 5 tender contract a.
© Primavera Systems, Inc.
Activity ID Activity Name Start Finish
TP6DDD1030 STPA Review Period and Contract Award 31-Dec-08 A 20-Jan-09 A
Contract Administration & Construction OversightContract Administration & Construction Oversight 20-Jan-09 A 30-Jul-09
TP7 Tar Ponds Surface CapTP7 Tar Ponds Surface Cap 17-Jun-08 A 31-Oct-13
Confirm Design Basis & Complete Detailed DesignConfirm Design Basis & Complete Detailed Design 17-Jun-08 A 17-Dec-09
TP7DD0270 Submit 95% Design Report 17-Jun-08 A
TP7DD0320 Submit 100% Design Report 03-Sep-08 A
TP7DD0420 Submit Bid Documents to Regulatory Agencies 25-Jun-09 01-Sep-09
TP7DD0460 Prepare Addenda as Required and Tendering 23-Sep-09 04-Nov-09
TP7DD0480 STPA Review Period and Contract Award 26-Nov-09 17-Dec-09
Contract Administration & Construction OversightContract Administration & Construction Oversight 17-Dec-09 31-Oct-13
CO1 Coke Ovens Bk Connector Sediment Removal & DisposalCO1 Coke Ovens Bk Connector Sediment Removal & Disposal 15-May-09 A 10-Sep-10
Confirm Design Basis & Complete Detailed DesignConfirm Design Basis & Complete Detailed Design 15-May-09 A 11-Dec-09
CO1DD0326 Submit 75% Design Report (Lower Reaches) 15-May-09 A
CO1DD0382 Submit 100% Design Report (Lower Reaches) 09-Jul-09
CO1DD0420 Submit Bid Documents to Regulatory Agencies 17-Jul-09 23-Sep-09
CO1DD0460 Prepare Addenda as Required and Tendering 30-Sep-09 29-Oct-09
CO1DD0480 STPA Review Period and Contract Award 20-Nov-09 11-Dec-09
Contract Administration & Construction OversightContract Administration & Construction Oversight 10-Dec-09 10-Sep-10
CO5 Vertical Cut-off WallsCO5 Vertical Cut-off Walls 11-Oct-07 A 17-Jul-09
Confirm Design Basis & Complete Detailed DesignConfirm Design Basis & Complete Detailed Design 11-Oct-07 A 11-Aug-08 A
CO5DD0270 Submit 95% Design Report 11-Oct-07 A
CO5DD0320 Submit 100% Design Report 18-Apr-08 A
CO5DD0420 Submit Bid Documents to Regulatory Agencies 25-Apr-08 A 28-Jun-08 A
CO5DD0460 Prepare Addenda as Required and Tendering 25-Apr-08 A 23-May-08 A
CO5DD0480 STPA Review Period and Contract Award 05-Aug-08 A 11-Aug-08 A
Contract Administration & Construction OversightContract Administration & Construction Oversight 11-Aug-08 A 17-Jul-09
CO6 Coke Ovens Surface CapCO6 Coke Ovens Surface Cap 01-Nov-07 A 29-Jun-11
Confirm Design Basis & Complete Detailed DesignConfirm Design Basis & Complete Detailed Design 01-Nov-07 A 14-Sep-09
CO6DD0270 Submit 95% Design Report 01-Nov-07 A
CO6DD0320 Submit 100% Design Report 06-Aug-08 A
CO6DD0420 Submit Bid Documents to Regulatory Agencies 14-Aug-08 A 21-Oct-08 A
CO6DD0460 Prepare Addenda as Required and Tendering 25-Jun-09 30-Jul-09
CO6DD0480 STPA Review Period and Contract Award 24-Aug-09 14-Sep-09
Contract Administration & Construction Oversight (Part A)Contract Administration & Construction Oversight (Part A) 14-Sep-09 29-Jun-11
CO7/CO8 COWTP & GWCSCO7/CO8 COWTP & GWCS 11-Jan-08 A 20-May-10
Confirm Design Basis & Complete Detailed DesignConfirm Design Basis & Complete Detailed Design 11-Jan-08 A 25-Jun-09
CO7/CO8DD0420 Submit Bid Documents to Regulatory Agencies 15-May-08 A 22-Jul-08 A
CO7/CO8DD0460 Prepare Addenda as Required and Tendering 26-Mar-09 A 13-May-09 A
CO7/CO8DD0480 STPA Review Period and Contract Award 05-Jun-09 A 25-Jun-09
CO7DD0270 Submit 95% Design Report 11-Jan-08 A
CO7DD0320 Submit 100% Design Report 13-May-08 A
Contract Administration & Construction OversightContract Administration & Construction Oversight 25-Jun-09 20-May-10
CO7/CO8 COWTP & GWCS OperationsCO7/CO8 COWTP & GWCS Operations 21-May-10 04-Mar-14
Operations (Not in Contract)Operations (Not in Contract) 21-May-10 04-Mar-14
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1Q2
2007 2008 2009 2010 2011 2012 2013 2014 2015
Design and Construction Oversight Services
Remediation of the Tar Ponds and Coke Ovens Site
Project No. 97918
95% &100% Design Report Submittals with Approval,
Tender, Contract & Construction Periods
25-Jun-09
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Page 2 of 2
PRELIMINARYTASK filter: PIP 95%100% part 5 tender contract a.
© Primavera Systems, Inc.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Appendix E
Quality Assurance Procedure Audits
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Audit Procedure
97918-GEN-QAP-Q-004-RB 15 January 2008
REMEDIATION OF THE TAR PONDS AND COKE OVENS SITES
DESIGN AND CONSTRUCTION OVERSIGHT SERVICES
QUALITY ASSURANCE PROCEDURE
AUDITS
97918-GEN-QAP-Q-004-RB
Prepared By: Original Signed By Date: 15 January 2008 Karen Wilson Project Quality Coordinator
Reviewed By: Original Signed By Date: 15 January 2008 Robert Jones Quality Manager, Earth Tech
Approved By: Original Signed By Date: 15 January 2008 David Wilson Project Director, Earth Tech
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Audit Procedure
97918-GEN-QAP-Q-004-RB 15 January 2008
Revision Summary
Revision Date of Issue Purpose A 18 October 2006 Initial draft for client review B 15 January 2008 General update
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Audit Procedure
i
97918-GEN-QAP-Q-004-RB 15 January 2008
Table of Contents
1.0 PURPOSE ......................................................................................................................................................1
2.0 SCOPE ...........................................................................................................................................................1
3.0 AUDIT PROTOCOL ....................................................................................................................................1
4.0 RESPONSIBILITIES ...................................................................................................................................2
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Audit Procedure
1
97918-GEN-QAP-Q-004-RB 15 January 2008
1.0 PURPOSE
The purpose of this procedure is to establish requirements for planning and conducting internal
audits and reporting of audit results. Internal audits of the Design Quality Assurance Program
shall be conducted to ensure compliance with the program requirements described in the Quality
Management Plan (QMP) and to evaluate effectiveness of the program.
2.0 SCOPE
This procedure applies to activities affecting quality during the design phase of the Remediation
of the Tar Ponds Coke Ovens Sites project.
3.0 AUDIT PROTOCOL
An audit plan will be developed and documented by the Quality Manager (QM) for each audit
identifying the following:
• Scope of audit
• Activities to be audited
• Applicable documents
• Objective evidence to be reviewed
• Audit schedule
Activities and program elements selected for the audit will be evaluated in terms of specified
requirements.
Objective evidence will be selected and examined to a depth necessary to determine effective
implementation of activities.
Internal audits will be scheduled to provide coverage of and coordination with, ongoing quality
assurance program activities at appropriate intervals during project implementation.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Audit Procedure
2
97918-GEN-QAP-Q-004-RB 15 January 2008
Nonconformances relative to program requirements will be documented as audit findings and
addressed as outlined in QMP Section 8.3.2: Nonconformances.
Appropriate corrective action will be taken by the responsible manager to address each
nonconformance identified and documented in the Nonconformance Report.
An audit report documenting the results of the audit will be prepared, signed and issued by the
QM. The report will provide a description of the audit scope and a summary of the results,
including a statement on the effectiveness of the quality assurance program. The audit report will
be distributed to ET/CBCL Project Lead and STPA’s Project Lead.
The audit report may include observations and concerns of the QM which will be discussed with
the ET/CBCL Project Lead and appropriately addressed at his/her discretion.
Follow-up reviews or surveillances will be performed by the QM to verify the implementation
and effectiveness of corrective actions taken to address nonconformances.
4.0 RESPONSIBILITIES
The Quality Manager is responsible for planning and conducting the audits, for preparing the
audit reports and for necessary follow-up activities.
The Project Lead, Deputy Project Manager, Design Manager, Design Coordinators and Design
Leads are responsible for providing the QM access to the records & documents to be examined
and for taking prompt corrective action, as required, to resolve audit findings.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
97918-GEN-QAP-Q-001-RE 15 January 2008
REMEDIATION OF THE TAR PONDS AND COKE OVENS SITES
DESIGN AND CONSTRUCTION OVERSIGHT SERVICES
QUALITY ASSURANCE PROCEDURE
DOCUMENTATION CONTROL 97918-GEN-QAP-Q-001 RE
Prepared By: Original Signed By Date: 15 January 2008 Karen Wilson Project Quality Coordinator Reviewed By: Original Signed By Date: 15 January 2008 Robert Jones Quality Manager Approved By: Original Signed By Date: 15 January 2008 David Wilson Project Director, Earth Tech
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
97918-GEN-QAP-Q-001-RE 15 January 2008
Revision Summary Revision Date of Issue Purpose
A 18 October 2006 Initial draft for review B 08 December 2006 Discipline code revised, E-mail filing procedure revised and
document delivery formats added. C 10 January 2007 Table II extended. Specification format & identification. Document control file.
D 1 March 2007 Table II extended, e-mail filing revised. E 15 January 2008 General update, all sections.
Notes:
1. This Procedure is an uncontrolled document and it is the reader’s responsibility to confirm
that this copy is the latest revision.
2. Revision letters will be used (e.g., A, B, C, etc.) until a quality document is issued for tender.
Upon issue for tender, this document will become Revision 0 and subsequent revisions will
be indicated with numbers.
Design & Construction Oversight Services Documentation Control Procedure
i
i
97918-GEN-QAP-Q-001-RE 16 January 2008
Table of Contents
1.0 PURPOSE ......................................................................................................................................................1
2.0 SCOPE ...........................................................................................................................................................1 2.1 PROJECT COMMUNICATIONS .......................................................................................................................1 2.2 DESIGN DOCUMENTATION ..........................................................................................................................1
3.0 PROJECT E-MAILS ....................................................................................................................................2 E-MAILS CAN BE CONSIDERED EITHER “NON-ESSENTIAL” OR “PROJECT RELATED”....................................................2 3.1 E-MAIL IDENTIFICATION..............................................................................................................................2 3.2 INTERNAL E-MAIL FILING...........................................................................................................................2 3.3 EXTERNAL E-MAIL FILING..........................................................................................................................3 3.4 RECORDS.....................................................................................................................................................3
4.0 DOCUMENTATION ....................................................................................................................................3 4.1 COMMUNICATIONS DOCUMENT IDENTIFICATION ........................................................................................3 4.2 DESIGN DOCUMENT IDENTIFICATION..........................................................................................................4 4.3 DOCUMENT MANAGEMENT.........................................................................................................................8 4.4 DESIGN DOCUMENT FORMATTING ..............................................................................................................9 4.5 DESIGN DOCUMENT CHECKS AND APPROVALS...........................................................................................9 4.6 DESIGN VERIFICATION ..............................................................................................................................10 4.7 DESIGN DOCUMENT DISTRIBUTION...........................................................................................................10 4.8 DOCUMENT DELIVERY FORMATS..............................................................................................................10 4.9 DESIGN CHANGES .....................................................................................................................................12 4.10 DESIGN DOCUMENT REVISIONS AND OBSOLETENESS ...............................................................................13 4.11 DESIGN DOCUMENT CONTROL CENTRE ....................................................................................................13 4.12 DOCUMENT RETENTION ............................................................................................................................14
5.0 RESPONSIBILITIES .................................................................................................................................14
List of Tables
TABLE I: PROJECT ELEMENT CODES..............................................................................................................................6 TABLE II: DOCUMENT TYPE CODES...............................................................................................................................7 TABLE III: DISCIPLINE CODES .......................................................................................................................................8
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
1
1
97918-GEN-QAP-Q-001-RE 15 January 2008
1.0 PURPOSE
The purpose of this procedure is to provide clear guidance regarding the control and tracking of
project communications documents and design documentation relating to the Remediation of the
Tar Ponds and Coke Ovens Sites. Design documents are to be appropriately documented,
distributed and retained in a controlled manner and project tem members trained on the procedure
to ensure understanding and compliance.
2.0 SCOPE
2.1 Project Communications
Project communications documents include, but are not limited to the following:
• Emails • Memos • Letters • Facsimiles • Transmittals • Meeting Minutes • Documentation of Verbal Conversations
2.2 Design Documentation
This procedure is applicable to the suite of design documentation to be created, so the design can
be related to the design requirements; and, the construction oversight and commissioning phases
can be effectively implemented by the responsible organizations.
Applicable documents include, but are not limited to, the following:
• Project Implementation Plan • Quality Management Plan • Risk Management Plan • Health & Safety Plan • Environmental Protection Plan • Communications Plan • Design Requirements • Design Drawings and Sketches • Design Reports
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
2
2
97918-GEN-QAP-Q-001-RE 15 January 2008
• Design Analyses and Calculations • Technical Specifications • Submissions for Licensing Purposes • Purchasing Requirements • Project Element Level Requirements • Commissioning Requirements • Operating and Maintenance Requirements
3.0 PROJECT E-MAILS
E-mails can be considered either “non-essential” or “project related”.
Non-essential e-mails are those for which the content is not considered necessary for future
reference or long term record purposes.
Project related e-mails are those that may have contractual implications, such as design memo’s,
scope, cost, approvals or meeting minutes. These must be adequately titled to facilitate correct
filing and retrieval.
3.1 E-mail Identification
Date (year xxxx month xx day xx)–(project number)–(element number)–(subject)
Example: 2008 01 27 97918 CO8 Scope of work
3.2 Internal E-Mail Filing
All project related e-mails that have contractual implications are to be filed on the network.
E-mails are to be filed under file folder:
97918 \ 04a \4a.1 Emails \ (element #) the e-mails will be filed by date order.
The e-mails can be filed either by copying to (cc):
Or, alternatively, you can file directly using the following path:
97918 \ 04a General-Correspondence \ 4a.1 Email \ (element #)
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
3
3
97918-GEN-QAP-Q-001-RE 15 January 2008
The email can be saved by:
1. upon opening your email, do a “SAVE AS”
2. locate the path (shown above)
3. Ensure that the “SAVE AS TYPE” is selected to “Outlook Message Format” - your
email will automatically have the extension “.msg”.
If the e-mail has attachments, it should be indicated if these are intended for filing or not by including a
note addressed to Central Filing.
3.3 External E-Mail Filing
Copy any relevant e-mails using the above format to:
3.4 Records
A hard copy of all project related e-mails that have contractual implications should be sent to
the Central Filing System. The hard copy should have the Project Number with its file directory
extension at the top right corner in order to assist the Central Filer in placing the document in the
appropriate file.
Attachments to e-mails that are intended for filing at the Sydney Office should be indicated as
such in an instruction to the filer.
4.0 DOCUMENTATION
4.1 Communications Document Identification
Each communications document, with the exception of email messages, should be identified with
the Project Number, File Number, name of owner/originator, revision level (if applicable) and the
date.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
4
4
97918-GEN-QAP-Q-001-RE 15 January 2008
4.2 Design Document Identification
Design documentation excluding drawings and technical specifications is to be uniquely
identified in the following manner:
[ET Project number] - [Project element] - [document type] - [discipline code] – [sequential
number] – [revision]
Example: 97918-TP1-REP-C-001-RA
Revisions are to be identified with a two letter revision code: RA, RB, RC, etc.
Documents to be issued for tender are to be identified alpha-numerically as R0 upon issue for
tender and subsequent revisions are to be numbered sequentially: R1, R2, R3, etc.
Dates of document production, issue and revision are to be clearly identified on each document.
4.2.1 Drawings identification:
[ET PN] - [project element*] – DWG - [discipline*] - [three digit sequential # as defined by the
project CAD Coordinator] – [revision]
Refer to the “Remediation of the Tar Ponds and Coke Ovens Sites CAD Standard Manual”.
Revisions are to be identified with a two letter revision code: RA, RB, RC, etc.
Drawings are to be identified alpha-numerically as RO upon issue for tender and subsequent
revisions are to be numbered sequentially: R1, R2, R3, etc.
4.2.2 Technical Specification Format and Editing:
The technical specification sections will be based on National Master Specifications (NMS);
amended to suit Project requirements.
The Sydney Design Centre will be responsible for specification editing using the NMS Edit Pro
word processing software.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
5
5
97918-GEN-QAP-Q-001-RE 15 January 2008
The NMS specification sections can be obtained from the Sydney Design Centre or by email
[email protected] c.c. [email protected]. The Design Centre will send the requested
specification sections electronically or by fax. The sections can be sent in PDF, NMS Edit Pro or
MSWord files and can be marked up by pen and faxed in or by using Track Changes in MSWord.
If the specification sections are changed in NMS Edit Pro they must be sent by the section only
and not in a created project, sections would have to be extracted as the main Project (SPP) file
will be held at the Sydney Design Centre.
Specification Identification:
[Project number] - [project element] - [document type]-[Six digit Section #] - [revision]
Example: 97918-TP7-TS-03 41 00-RA
Revisions are to be identified with a two letter revision code: RA, RB, RC, etc. Specifications are
to be identified alpha-numerically as R0 upon issue for tender and subsequent revisions are to be
numbered sequentially: R1, R2, R3, etc.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
6
6
97918-GEN-QAP-Q-001-RE 15 January 2008
The codes for the project elements are listed in the following table:
Table I: Project Element Codes
Project Element
Element Description TP1 Coke Ovens Wash Brook Channels
TP2 Material Processing Facility
TP6 Solidification/Stabilization
TP1/TP6 Alternative Pump Around Design
TP7 Tar Ponds Surface Cap
CO1 Coke Oven Brook Connector Sediment Removal & Disposal
CO2 Tar Cell Solidification/Stabilization
CO5 Vertical Cut-off Walls
CO6 Coke Ovens Surface Cap
CO7 Coke Oven Brook Sediment Removal & Groundwater Collection System
CO8 Coke Oven Water Treatment Plant
CO9 On-Site Engineered Landfill
TC1 Temporary Construction Water Treatment
TC2 Operations Contract No 1
GEN General (Common Services, etc.)
CP Cooling Pond
CPT Cooling Pond Treatment
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
7
7
97918-GEN-QAP-Q-001-RE 15 January 2008
The codes for the document types are listed in the following table:
Table II: Document Type Codes
Code Document Type Code Document Type AHASP Assignment Health & Safety Plan HG Hydro Geology AUD Audit Document LIST Listing AQ Air Quality MHSP Master Health & Safety Plan BOM Bill of Materials MTM Maintenance Manual CAD Cad Manual NCR Nonconformance Report CAL Calculations OPM Operations Manual CSP Client Satisfaction Plan PIP Project Implementation Plan COD Contract Document PLR Plain Language Report CN Change Notice PROT Protocol CO Change Order QAP Quality Assurance Procedure CP Commissioning Plan QAF Quality Assurance Form CPT Cooling Pond Treatment QMP Quality Management Plan CMP Construction Management Plan QAQC Quality Assurance/Quality Control COMM Communications Plan REP Report DD Design Description RFI Request for Information DM Design Manual RFQ Request for Quotation DR Design Report SCH Schedule DRC Document Review & Comment SKT Sketch DRQ Design Requirements TS Technical Specification DRD Design Review Document WBS Work Breakdown Structure DWG Drawing WP Work Plan EMP Environmental Management Plan GWIP Groundwater Investigation Programs EPP Environmental Protection Plan FDP Field Demonstration Plan FORMS Forms Directory
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
8
8
97918-GEN-QAP-Q-001-RE 15 January 2008
The codes for the disciplines are listed in the following table:
Table III: Discipline Codes
Code Discipline A Architectural B Geotechnical C Civil E Electrical F Fire Protection G General H Hazardous Material I Instrumentation (I&C) L Landscape M Mechanical (Includes Plumbing & HVAC) N Environmental P Process Q Quality S Structural T Telecommunications V Survey/Mapping
4.3 Document Management
The forms listed in the Forms Directory (97918-GEN-QAF-Q-000) define the format and
presentation of certain documents referenced in this procedure.
Before any formal documents are submitted externally to the Agency or others, they should be
proof read, reviewed for content and approved.
Meeting minutes or notes are to be prepared and distributed to all project team members within
five days. This is required in order to allow for the prompt response to action items. Meeting
action items will be logged and tracked in a Meeting Action Item Log in the Project File Folder.
Key elements from important verbal communications, including telephone conversations, should
be logged by recording them in an email or a memo.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
9
9
97918-GEN-QAP-Q-001-RE 15 January 2008
4.4 Design Document Formatting
Each design document is to be prepared and managed in accordance with Earth Tech’s practices
or the Agency’s specified requirements.
Design drawings are to be stored electronically in AutoCAD (2000) format and printed in
accordance with the “Remediation of the Tar Ponds and Coke Ovens Sites CAD Standard
Manual”.
Reports and Manuals are to have a Revision Record page (Summary) Page within the document.
Manual calculations are to be documented on standard calculation sheets, with a cover sheet
containing dates and signatures of the original designer, reviewer and approver.
Calculations or other design analysis documents are to be identified by subject, originator,
reviewer and date for ease of access; and, are to include:
• objective of the calculation or design analysis
• identification of design inputs on which it is based
• identification of data or information from other sources used in calculation
• identification of assumptions and indication of those that must be verified as design
proceeds
• identification of computer software programs used in the calculation
• documentation of review and approval
4.5 Design Document Checks and Approvals
Design documents are to be subject to on-going quality checks by the design team members for
adequacy, completeness and correctness prior to approval by the appropriate manager and issue.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
10
10
97918-GEN-QAP-Q-001-RE 15 January 2008
The signatures or initials of design document reviewers and approvers with dates are to be
documented at the beginning of the document for reports and in the title block for drawings. An
Engineer’s Seal is to be applied to the master drawing copy.
4.6 Design Verification
Verification of design work through a formal Design Review process is to be carried out in
accordance with procedure 97918-GEN-Q-QAP-002, prior to submission of key deliverables at
75% and 95% milestones.
4.7 Design Document Distribution
The issue and distribution of design documents to the Agency and other external organizations, is
to be carried out in accordance with a distribution list.
Design documents issued to external organizations are to have a Transmittal Form attached with a
description of the contents or changes made since the previous issue. A copy of each Transmittal
Form should be filed in the Project File Folder 05 Transmittals.
4.8 Document Delivery Formats
Draft and final reports are to be delivered in both hard and electronic copies.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
11
11
97918-GEN-QAP-Q-001-RE 15 January 2008
Hard Copies
Deliverable Number of Copies
Consultant’s Assignment Health & Safety Plan 20
Project Implementation Plan 20
Project Master Health and Safety Plan 20
75% Design Report 20
95% Design Report 20
100% Design Report 20
Bid Documents in addition to copies provided with Design Reports 30
Construction Contract Documents 5
Draft Plain Language Report 20
Final Plain Language Report 100
Draft Post Construction and Long Term Monitoring Reports and Bid Documents 20
Final Post Construction and Long Term Monitoring Reports and Bid Documents 30
Electronic Copies
All electronic reports shall be submitted to the Agency on properly labeled compact discs. Two copies of
the CD’s shall be submitted. Electronic files over 10MB in size must be submitted in two versions. The
first version as one file of the entire report while the second report version contains the entire report but is
broken into component files limited in size between 5 and 10 MB. All electronic files submitted to the
Agency shall be according to the file labeling directives, which shall be available on request.
Electronic copies of reports shall be provided according to the following specifications:
1) Reports to be in Adobe Portable Document Format (PDF).
2) All reports, drawings, spreadsheets, etc., can be developed separately in their native
programs such as MS Word, MS Excel, GINT, AutoCAD, etc., provided the software is
compatible with Adobe (see specific requirements for figures and drawings).
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
12
12
97918-GEN-QAP-Q-001-RE 15 January 2008
3) Images, drawings, etc., shall be ‘printed’ as PDF where possible and inserted into the
final PDF report document.
4) No security, password, encryption, etc., is to be enabled.
5) The PDF file created must be a ‘smart’ document supporting searching, bookmarks and
hyperlinks to aid in document navigation.
6) Hyper linking of the original Table of Contents (TOC) within the Word document to its
subsections is allowed and desired, but not required.
7) All Table of Contents, Table of Figures, section headers, etc., within MS Word (or other
word processing software) are to be formatted using TOC, TOC1, or Header, Headings 1,
etc., so that they are bookmarked automatically by Adobe during conversion.
8) Appendices titles are to be formatted as TOC or Header, Heading 1, etc., so that they are
book marked automatically by Adobe during conversion.
9) Default PDF conversion settings are to be used from within MS Word etc., with the
exception that Bookmarks are to be enabled for TOC, TOC1, etc., where used.
10) All fonts must be embedded in the PDF document.
Documents needed for inclusion in reports that are only available in hardcopy are to be scanned
and converted to PDF for insertion into the final report document, taking careful attention to
minimize the size of the scanned PDF while ensuring its legibility.
Double-sided printing is preferred, as is not less than 11-point Seriffed font and 1.5 line spacing.
4.9 Design Changes
Design changes required by project scope changes and design changes following the issue of
design documents, are to be carried out in accordance with the Design Review procedure (97918-
GEN-QAP-Q-002).
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
13
13
97918-GEN-QAP-Q-001-RE 15 January 2008
4.10 Design Document Revisions and Obsoleteness
Revisions to documents which do not alter the intent, objective or quality requirements expressed
by the document, are to be considered minor and not subject to the requirements of this
procedure. Minor changes which can be made or authorized by the preparer of the document
include: typographical errors, punctuation, editorial corrections and inconsistencies.
Revisions to documents, other than those defined above as minor, are to be controlled by the
same or equivalent measures used to control the original document, including the same
authorization level as the original document.
A Revision Record (Summary) Page indicating the revision level, date and changes since the last
revision, should be attached to all revised reports and manuals.
Revision letters will be used (e.g., A, B, C, etc.) until a document is considered “Final” or is
issued for tender. Upon finalization or issue for tender, the document will become Revision 0 and
subsequent revisions will be indicated with numbers
No liquid white outs, correction tape or mark-ups to hard copies are to be used to revise design
documents, revisions are to be made to soft copies only.
Obsolete documents should be marked as “Obsolete”, or “Superseded” to preclude inadvertent
use and adverse effects on quality.
4.11 Design Document Control Centre
The design document control center is to be located at Earth Tech’s Sydney Design Centre, where
current copies of the documents can be made available to the project team on request. Project
team leaders are to obtain their most recent document for editing purposes from the ET Sydney
Design Center, ensuring document control is adhered to at all times.
Hard copies of current design documents are to be maintained in the Project Master File by the
Document Controller(s).
Electronic copies of design documents are to be maintained in folders in the Project File.
Remediation of the Tar Ponds & Coke Ovens Sites Design & Construction Oversight Services
Documentation Control Procedure
14
14
97918-GEN-QAP-Q-001-RE 15 January 2008
4.12 Document Retention
Refer to Canada East Office Operating Procedure SOP-01 Control of Records for project storage
and retention.
5.0 RESPONSIBILITIES
The Project Lead, supported by the Deputy Project Manager, the Design Manager and the Design
Coordinators, has both the responsibility and authority for ensuring the documentation control
system is implemented and maintained in accordance with the requirements of this procedure.
The Document Controllers are responsible for document tracking and management by means of
logs of transmitted and received project communications documents and by maintaining the
Design Document Control Centre.
The Quality Manager is responsible for establishing the quality requirements, developing
procedures for the documentation control system and for monitoring the program to ensure it is
functioning to its intended extent. The Quality Manager will be the point of contact for inquiries
and matters regarding quality measures as they relate to documentation control.
All members of the project team have the responsibility for ensuring that project communications
documents and design documentation are prepared, identified, reviewed, approved, filed,
distributed, revised and retained in accordance with the requirements of this procedure.
Page 1 of 2
Form No. QAF – 003 Project Name: Remediation of the Tar Ponds & Coke Ovens Sites
Records Retention Schedule
Storage Categories: Category: A Central Records, Departments, Libraries & Regional Centers Category: B Central On site Storage and/or Off Site Storage Note: (Expressed in years and P = Permanent storage)
Record Type
Listing Code
Record Type/Description Cat. A Storage
Cat. BStorage
Present Total
Retention
Total RetentionRequiredBy Law
Comments
A. Accounts
2 7 9 varies to P
*Requires a more detailed breakdown of this Record Type. Note as part of Corporate Records, some records are kept permanently
B. Field Books
1 29 30 P
C. Computer Printout
1 9 10
D. Drawings (P&R)
5 P P P
E. Contract Documents • Signed • Blank Records Copy
5 5
P -
P 5
P
F. Correspondence: • Files • Files (Microfilmed) • Microfilm Copies
1 1 1
29 4
29
30 5
30
30
Depending on the Correspondence if they relate to a contractual agreement they may be deemed necessary for Permanent storage as are contracts and other agreements
G. Misc. Administration
1 29 30
H. Design Calculations
1 29 30 30
I. Cost Estimates
1 29 30 30
J. Soil Reports
1 P P P
K. Shop Drawings
1 29 30
L. Library
1 29 30
Page 2 of 2
Record Type
Listing Code
Record Type Description
Cat. A Storage
Cat. B Storage
Present Total
Retention
Total Retention Required
By Law
Comments
M. Survey Data
1 29 30
N. S Drawings
1 29 30
O. Engineering Agreement
1 P P P
P. Personnel Records
1 P varies to P
Some records such as accident reports should be Permanent
Q. Quantities
1 29 30
R. Reports (including Sub-consultants reports)
5 P P
S. Site Administration
1 29 30
T. Proposals (P&R)
5 10 15
U. Curriculum Vitae
- - -
V. Photographs
1 P P
W. Work Files
1 29 30
X. Y. Corporate Records
1 P P P
Z. Spare Copies of Publications
Computer Records:
• Tape (Mainframe & Network)
• Diskettes -CADD • Diskettes - REPORTS
1
10 10
9 - -
10
10 10
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Appendix F
Environmental Inspection Log
L:\work\97000\97918\19-Pplans\19-Project Plans\GEN\Quality\Forms Page 1 of 2
Form No: 97918-QAF-070 R3
Remediation of the Tar Ponds and Coke Ovens Sites
Design and Construction Oversight Services
Remediation of the Sydney Tar Ponds and Coke Ovens Sites
Environmental Inspection Log (EIL)
Design Element:
Date: (D/M/Y):
Time (24 hrs):
Weather Conditions:
Daily Construction Activities:
EIL Completed by (printed name and signature): EM Name EM Signature
EIL Reviewed by (DE name, signature, date, time): DE Name DE Signature DD/MM/YYYY, 24:00
DAILY CHECKLIST ITEM: DESCRIPTION ACCEPTABLE NOT
ACCEPTABLE1
NOT
APPLICABLE
Comment #
(See P.2)
1. Sediment Control Structures:
Hay
Silt Fences
Dissipation Measures
Silt Curtains
Oil Absorbent Boom
Other:
2. Stabilization Areas
3. Noise Control Measures
4. Dust Control Measures
5. Air Emission Control Measures
6. Materials, Product & Equip. Storage
7. Fueling and Maintenance Area
8. Waste Disposal/Debris
9. Access Roads
10. Dewatering
Hoses
Connections
11. Decontamination Areas (ONCE DAILY)
Workers
Equipment/Vehicles
12. Barriers for Disposal, Storage &
Work Areas (ONCE DAILY)
13. Other Specific EM Activities:
Type:
Type:
Type:
14. Field Sampling:
Type:
1 Criteria for Acceptable and Not Acceptable for each checklist item is given on Pages 3 to 6.
Where a checklist item is not acceptable, comments must be provided below detailing: the nature of the concern; the extent of any environmental impacts;
the remediation measures undertaken; the requirement for any further remediation measures; if notification of a regulatory body was required, and if so, the
response; any recommendations for improvements/follow-up; and any other relevant information.
L:\work\97000\97918\19-Pplans\19-Project Plans\GEN\Quality\Forms Page 2 of 2
Form No: 97918-QAF-070 R3
Remediation of the Tar Ponds and Coke Ovens Sites
Design and Construction Oversight Services
Remediation of the Sydney Tar Ponds and Coke Ovens Sites Environmental Inspection Log (EIL)
Design Element:
Date: (D/M/Y):
Time (24 hrs):
WEEKLY CHECKLIST ITEM: DESCRIPTION ACCEPTABLE NOT
ACCEPTABLE1
NOT
APPLICABLE Comment #
1. Above Ground Storage Tanks:
Tank
Pipe
Valve
Pump
Other Tank Equipment
2. Compressive Gas Storage
Data
Comments/Observations
(Comment #, Comment, Date, Time, Initials) If additional space is required, please attach a separate page.
Time: Surface Water Monitoring Results (NTU)
Location Notes/Observations
Time: Sound Monitoring Results (dBA)
Location Average Notes/Observations
____________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
___________________________
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
Criteria to Determine if Mitigation Effectiveness is Acceptable or Non-acceptable
1. Sediment Control Structures:
a. Acceptable: If instantaneous Turbidity readings are within 8 Nephelometric Turbidity
Units (NTUs) above background (upstream sample location), if background
concentrations are less than 80NTU. If background is greater than 80NTU and samples
are within 10% of background levels on downstream side of the structure, the structure is
deemed to be functioning as intended. During visual inspection, if the sediment control
structures are intact with no gaps, tears, slumping or weathering of the materials and no
noticeable impacts in the receiving water “downstream” of the sediment control
structures.
b. Not Acceptable: If instantaneous Turbidity readings are greater than 8NTU if background
is less than 80NTU, or if readings are greater than 10% of background levels on
downstream side of the structure, the structure is deemed to be not functioning as
intended. During visual inspection, if the sediment control structures are not intact with
gaps, tears, slumping or weathering of the materials and noticeable impacts in the
receiving water “downstream” of the sediment control structures.
2. Stabilization Areas:
a. Acceptable: During visual inspection, if there is no apparent sloughing banks or erosional
processes occurring in an area of disturbance created by the Project.
b. Not Acceptable: During visual inspection, if there is sloughing banks or erosional
processes occurring in an area of disturbance created by the Project.
3. Noise Control Measures:
a. Acceptable: If noise measurements (based on two hour averages) are within the following
limits:
Leq < 65dBA between 0700 to 1900hrs
Leq < 60dBA between 1900 to 2300hrs
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
b. Not Acceptable: If noise measurements (based on two hour averages) are not within the
above limits.
4. Dust, VOCs and Odour Control Measures:
a. Acceptable: During visual inspection, dust, VOCs and odours are controlled during
grading, excavation and construction activities. The exposed surfaces, stock piles or
stored materials are covered with water, foam or tarps, as required. The vehicles used for
excavation or transportation of materials are completely enclosed or with retractable load
covers, the haul unit seals are in good working order, hoses and connections on
equipment are free of leaks or drips.
b. Not Acceptable: During visual inspection, dust, VOCs and odours are not controlled
during grading, excavation and construction activities. The exposed surfaces, stock piles
or stored materials are not covered with water, foam or tarps. The vehicles used for
excavation or transportation of materials are not completely enclosed or with retractable
load covers, the haul unit seals are not in good working order, hoses and connections on
equipment have leaks or drips.
5. Particulate Control Measures:
a. Acceptable: If measurement by Air Monitoring Consultant at fenceline at downwind
averaged over 15 minutes does not exceed 100 g/m3
or if measurement at fenceline at
downwind averaged over 10 hours does not exceed 990 g/m3.
b. Not Acceptable: If measurement by Air Monitoring Consultant at fenceline at downwind
averaged over 15 minutes exceeds 100 g/m3 or
if measurement at fenceline at downwind
averaged over 10 hours exceeds 990 g/m3.
6. Air Emission Control Measures:
a. Acceptable: If measurement by Air Monitoring Consultant halfway between fence line
and source(s) is less than or equal to: 2ppm averaged over 15 minutes; or, with the
exception of benzene and naphthalene, five exceedances to the 15 minute averaging
period over the workday averaged over 10 hours; or 2.5ppm for benzene and naphthalene
(as confirmed by Draeger –Tubes or olfactory means) averaged over one hour.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
b. Not Acceptable: If measurement by Air Monitoring Consultant at halfway between fence
line and source(s) is greater than: 2ppm averaged over 15 minutes; or with the exception
of benzene and naphthalene, five exceedances to the 15 minute averaging period over the
workday averaged over 10 hours; or 2.5ppm for benzene and naphthalene (as confirmed
by Draeger –Tubes or olfactory means) averaged over one hour.
7. Product Storage:
a. Acceptable: All potentially hazardous products are stored in a pre-designated, safe and
secure product storage area at the worksite, in accordance with provincial legislation; all
products shall be properly labelled according to WHMIS; any spilled products are
contained and the area cleaned.
b. Not Acceptable: Any potentially hazardous products are not stored in a pre-designated,
safe and secure product storage area at the worksite, in accordance with provincial
legislation; or any products are not properly labelled according to WHMIS; or any spilled
products are not contained; or the area has not been cleaned after a spill.
8. Fuelling and Maintenance Area:
a. Acceptable: Area is clean, well organized. All potentially hazardous products are stored
in a pre-designated, safe and secure product storage area within the construction area, in
accordance with provincial legislation. All products are properly labelled according to
Workplace Hazardous Materials Information System (WHMIS). Material Safety Data
Sheets (MSDS) are on site with the relevant product.
b. Not Acceptable: Area is not clean, unorganized and any of the above noted safeguards
are missing.
9. Waste Disposal/Debris:
a. Acceptable: Project site is free from any waste/debris whether it be benign solid waste or
hazardous waste other than wastes stored in designated bins/areas.
b. Non Acceptable: Project site contains waste/debris whether it is benign solid waste or
hazardous waste, is not destined for immediate disposal and requires appropriate
disposal.
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
10. Dewatering:
a. Acceptable: Fish have been removed prior to dewatering; fish screens are installed in
pumps; and the dewatered cells are maintained during construction.
b. Not Acceptable: Fish have not been removed prior to dewatering; fish screens are not
installed; or the dewatered cells are not maintained during construction.
11. Environmental Monitoring Activities:
Air Quality (Responsibility of the Air Monitoring Consultant)
a. Acceptable: Monitoring instruments are regularly calibrated. Data is collected and
recorded hourly. During times periodically when there is a potential for increased
emissions, real time monitoring shows compliance with previously established limits as
identified above in items 5 and 6.
b. Not Acceptable: Monitoring instruments are not regularly calibrated. Data is not collected
or not recorded hourly. During times periodically when there is a potential for increased
emissions, real time monitoring shows exceedances of limits as shown in numbers 5 and
6 above.
Surface water
a. Acceptable: Monitoring instruments are regularly calibrated. Data is collected and
recorded hourly. Periodically, during times when there is a potential for increased
sediment loading (e.g. excavation), real time monitoring shows no exceedances of limits
as described in Item 1.
b. Non Acceptable: Monitoring instruments are not regularly calibrated or data is not
collected and recorded hourly. Periodically, during times when there is a potential for
increased sediment loading (e.g. excavation), real time monitoring shows exceedances of
limits as described in Item 1.
Groundwater
a. Acceptable: If a contaminant of concern in groundwater does not have an upward trend
after the fourth sample for three consecutive samples using the Mann-Kendall trend
Remediation of the Tar Ponds & Coke Ovens Sites
Design and Construction Oversight Services
Environmental Management Plan
97918-GEN-EMP-N-001-R2 14 June 2010
analysis; this approach will use the entire available time series of data (within the
numerical constraints of the test).
b. Not Acceptable: When an upward trend after the fourth sample for three consecutive
samples using the Mann-Kendall trend analysis is identified; again, this approach will use
the entire available time series of data (within the numerical constraints of the test).
12. Access Roads
a. Acceptable: Upon visual inspection, the access roads are dust suppressed, free of debris
or unnecessary materials with no spills. If applicable, the silt fences appear to be working
and are being maintained along toe of slope (along banks) and drainage ditches appear to
be working to direct flow away from waterways.
b. Non Acceptable: Upon visual inspection, the access roads are not dust suppressed, have
debris or unnecessary materials with spills. If applicable, the silt fences appear not to be
working or to not be maintained along toe of slope (along banks) and drainage ditches
appear not to be working to direct flow away from waterways.