remedial action report -...
TRANSCRIPT
98-102 STEUBEN STREET
BROOKLYN, NEW YORK
Remedial Action Report
NYC VCP Project Number 15CVCP090K
E-Designation Project Number 15EH-N053K
Prepared For:
Clinton Hill Development II LLC
152 West 57th Street, 60th Floor
New York, NY 11205
(212) 649-9700
Prepared By:
Carlin-Simpson & Associates
61 Main Street
Sayreville, NJ 08872
732-432-5757
JUNE 2017
98-102 Steuben Street
Remedial Action Report
May 2017
2
REMEDIAL ACTION REPORT
TABLE OF CONTENTS
LIST OF ACRONYMS ...................................................................................................... 5
CERTIFICATION .............................................................................................................. 6
EXECUTIVE SUMMARY ................................................................................................. 7
REMEDIAL ACTION REPORT ........................................................................................ 16
1.0 SITE BACKGROUND ........................................................................................... 16
1.1 SITE LOCATION AND BACKGROUND ................................................ 16
1.2 REDEVELOPMENT PLAN ....................................................................... 16
1.3 DESCRIPTION OF SURROUNDING PROPERTY ................................. 17
1.4 SUMMARY OF PAST SITE USES AND AREAS OF CONCERN ......... 17
1.5 SUMMARY OF WORK PERFORMED UNDER THE REMEDIAL
INVESTIGATION ...................................................................................... 19
1.6 SUMMARY OF FINDINGS OF REMEDIAL INVESTIGATION ........... 19
2.0 DESCRIPTION OF REMEDIAL ACTIONS ......................................................... 21
3.0 COMPLIANCE WITH REMEDIAL ACTION WORK PLAN ............................. 25
3.1 CONSTRUCTION HEALTH & SAFETY PLAN ..................................... 25
3.2 COMMUNITY AIR MONITORING PLAN.............................................. 25
3.3 SOIL/MATERIALS MANAGEMENT PLAN........................................... 25
3.4 STORM-WATER POLLUTION PREVENTION ...................................... 25
3.5 DEVIATIONS FROM THE REMEDIAL ACTION WORK PLAN ......... 25
4.0 REMEDIAL PROGRAM ....................................................................................... 27
4.1 PROJECT ORGANIZATION .................................................................... 27
4.2 SITE CONTROLS ...................................................................................... 27
4.3 MATERIALS EXCAVATION AND REMOVAL ACTION .................... 30
4.4 MATERIALS DISPOSAL .......................................................................... 32
4.5 BACKFILL IMPORT ................................................................................. 34
98-102 Steuben Street
Remedial Action Report
May 2017
3
5.0 ENGINEERING CONTROLS ............................................................................... 36
6.0 INSTITUTIONAL CONTROLS ............................................................................ 38
7.0 SITE MANAGEMENT PLAN ............................................................................... 39
8.0 SUSTAINABILITY REPORT ............................................................................... 40
FIGURES
Figure 1: Site Location Map
Figure 2: Site Boundary Map
Figure 3: Development Plan
Figure 4: Map of End-Point Sample Locations
Figure 5: Map Showing Location and Approximate Depth of Excavations
Figure 6: Map of Soil Reuse and Backfill Placement Locations
Figure 7: As-Built Plan of Vapor Barrier System & SSDS System
Figure 8: SSDS System Riser Diagram
TABLES
Table 1: Summary of End-Point Analytical Results
Table 1A: Summary of End-Point Analytical Results
Table 2: List of SCOs
Table 3: Disposal Quantities and Disposal Facilities
Table 4: Backfill Quantities and Sources
98-102 Steuben Street
Remedial Action Report
May 2017
4
APPENDICES
Appendix A: Remedial Investigation Report
Appendix B: Remedial Action Work Plan & Stipulation List
Appendix C: Daily Reports to OER
Appendix D: Photographs of Remedial Action
Appendix E: Community Air Monitoring Plan Results
Appendix F: Disposal Facility Documentation and Approval Letters
Appendix G: Shipping and Disposal Manifests
Appendix H: Disposal Characterization Sample Laboratory Testing Results
Appendix I: End-point Sample Analytical Laboratory Data Reports
Appendix J: Documentation for Vapor Barrier System
Appendix K: Imported Backfill Laboratory Analytical Data Reports
98-102 Steuben Street
Remedial Action Report
May 2017
5
LIST OF ACRONYMS
Acronym Definition
CAMP Community Air Monitoring Plan
DER-10 NYS DEC Division of Environmental Remediation Technical
Guidance Manual 10
EC Engineering Control
HASP Health and Safety Plan
IC Institutional Control
NYC VCP New York City Voluntary Cleanup Program
NYC DEP New York City Department of Environmental Protection
NYC DOHMH New York City Department of Health and Mental Hygiene
NYC OER New York City Office of Environmental Remediation
NYS DEC New York State Department of Environmental Conservation
ORC Oxygen Release Compound
PID Photoionization Detector
QA/QC Quality Assurance/Quality Control
QEP Qualified Environmental Professional
RAR Remedial Action Report
RAWP Remedial Action Work Plan
RCA Recycled Concrete Aggregate
SCG Standards, Criteria and Guidance
SCO Soil Cleanup Objective
SMMP Soil/Materials Management Plan
SMP Site Management Plan
SVOCs Semi-Volatile Organic Compounds
UST Underground Storage Tank
VOCs Volatile Organic Compounds
98-102 Steuben Street
Remedial Action Report
May 2017
6
CERTIFICATION
I, Robert B. Simpson, P.E., certify the following:
• I am currently a registered professional engineer licensed by the State of New York.
• I performed professional engineering services and had primary direct responsibility for
implementation of the remedial program for the 98-102 Steuben Street site, site number
15CVCP090K.
• I have reviewed this document, to which my signature and seal are affixed.
• The vapor barrier constructed during this remedial action was designed by me or a person under my
direct supervision and achieves the goals established in the Remedial Action Work Plan for this site.
• The passive SSDS, and vapor barrier constructed during this remedial action were designed by me
or a person under my direct supervision and achieve the goals established in the Remedial Action
Work Plan for this site.
The vapor barrier and passive SSDS constructed during this remedial action were professionally
observed by me or by a person under my direct supervision are accurately reflected in the text and
drawings for as-built design reported in this Remedial Action Report.
• The OER-approved Remedial Action Work Plan dated March 2015 and Stipulations in a letter dated
15 April 2015 were implemented and that all requirements in those documents have been
substantively complied with. I certify that contaminated soil, fill, liquid or other material from the
property was taken to facilities licensed to accept this material in full compliance with applicable
laws and regulations.
Name
Robert B. Simpson, P.E.
PE License Number
081840
Date
6/21/17
Signature
I, Meredith R. Anke, certify the following:
• I am a Qualified Environmental Professional. I had primary direct responsibility for implementation of the
remedial program for 98-102 Steuben Street site, site number 15CVCP090K.
• The OER-approved Remedial Action Work Plan dated March 2015 and Stipulations in a letter dated 15
April 2015 were implemented and that all requirements in those documents have been substantively
complied with. I certify that contaminated soil, fill, liquid or other material from the property was taken
to facilities licensed to accept this material in full compliance with applicable laws and regulations.
QEP Name
Meredith R. Anke Date
6/21/17 QEP Signature
98-102 Steuben Street
Remedial Action Report
May 2017
7
EXECUTIVE SUMMARY
Clinton Hill Development II LLC has enrolled in the New York City Voluntary
Cleanup Program (NYC VCP) to investigate and remediate a property located at 98-102
Steuben Street in the Clinton Hill section of Brooklyn, New York. A Remedial
Investigation (RI) was performed to compile and evaluate data and information necessary
to develop a Remedial Action Work Plan (RAWP). A remedial action was performed
pursuant to the OER-approved RAWP in a manner that has rendered the Site protective of
public health and the environment consistent with the proposed use of the property. This
RAR describes the remedial action performed under the RAWP. The remedial action
described in this document provides for the protection of public health and the
environment and complies with applicable environmental standards, criteria and guidance
and applicable laws and regulations.
Site Location and Background
The Site is located at 98-102 Steuben Street in the Clinton Hill section in Brooklyn,
New York and is identified as Block 1893 and Lot 47 on the New York City Tax Map.
The Site Location Map is shown in Figure 1. The Site is 7,500-square feet and is bounded
by Steuben Street to the east, residential properties to the south, and multi-family
residential properties to the north and west. The Site Boundary Map is shown in Figure 2.
Prior to development, the Site was vacant but had been used for residential use and storage.
The site previously contained two residential two-story buildings with basements. There
was also a yard to the west of the buildings, undeveloped space in the northern portion of
the property, and a small dilapidated structure in the northwest corner of the Site.
Summary of Redevelopment Plan
The Site is 7,500-square feet in total area. The former Site buildings were demolished
in order to re-develop the property. The development of the Site consists of a new 8-story
multi-family residential building with a full cellar. The building has 39 residential units
and is approximately 4,500 square feet in area. The structure is situated in the eastern
portion (front) of the property. An excavation depth ranging from approximately 14 to 20
98-102 Steuben Street
Remedial Action Report
May 2017
8
feet was required in the building area. This depth was deeper than anticipated in the RAWP
but was required due to the thickness of the mat foundation system and the existing
foundation conditions of the adjacent buildings to the north and south of the Site.
There is also an open space area in the western portion of the site (rear yard),
approximately 3,000 square feet in area, with tiered retaining walls and landscaping plants
along the western property line. The area between the building and the retaining walls
consists of a concrete paver patio. The entire rear yard area was excavated to a depth of
approximately 10 feet below grade, which corresponds to the building cellar elevation.
This excavation was as anticipated in the RAWP but the retaining wall layout was revised
from the plan included in the RAWP.
A map showing the building location, basement location, and open space location is
shown in the Development Plan in Figure 3.
Summary of Description of Surrounding Property
The area surrounding the Site consists of residential and commercial properties. To the
immediate north of the Site is a 7-story multi-family residential building that was
completed in 2014. To the west is another 7-story multi-family residential building on
Grand Avenue. To the east is Steuben Street followed by commercial buildings. To the
south of the Site are three (3) 4-story residential buildings followed by commercial
properties along Myrtle Avenue.
Summary of Past Site Uses and Areas of Concern
At the time of a Phase I Environmental Site Assessment (ESA) in February 2014, the
northern Site building and the first floor of the southern Site building were being used for
storage. The second floor of the southern building was occupied by residential tenants.
The exterior of the site was also being used for storage.
According to the Phase I ESA Report, the southern portion of the Site had been
occupied with a two-story structure since 1887. The two-story structure had been primarily
occupied by residential tenants from 1887 to 2007 with the exception of a brief period
from 1969 to 1977 when it was occupied by an office. From 2007 to 2014, the two-story
98-102 Steuben Street
Remedial Action Report
May 2017
9
structure had been occupied by both residential and commercial tenants. A varying level
lumber shed was located to the west of the structure from 1915 to 1938 and a single-story
shed was located to the west from 1938 to 1969.
The Phase I ESA Report also indicated that the northern portion of the Site had been
occupied with a two-story structure since 1887. The two-story structure had been occupied
by both residential and commercial tenants from 1887 to 2014. Commercial tenants
including offices, a storage company, a coal company, and a setting controls company had
occupied the northern portion of the site from 1934 to 2014. A stable was located to the
north and west of this structure from 1887 to 1904 and a lumber storage building was
located to the north from 1904 to 1938. Additionally, a lumber shed was located to the
west of the structure from 1915 to 1938. In the period from 1938 to 1969, a contractor’s
storage facility was located to the north of the structure. From 1977 to 2007, a single-story
auto repair facility was located in the northwest portion of the Site.
Based on the Phase I Environmental Site Assessment (ESA) that was performed by
Environmental Business Consultants (EBC) in February 2014, the areas of concern
(AOCs) identified for this site were as follows:
1. There was a 275-gallon heating oil aboveground storage tank (AST) (installation
date unknown) in the basement of 102 Steuben Street located on the southern
portion of the Site. The heating oil fill pipe and vent pipe for the AST in the
basement were observed on the east side of the Site. The AST was connected to a
boiler. The oil supply line from the AST to the boiler was buried and was most
likely repaired at some point as holes in the concrete indicated. Surficial staining
was noted on top of the AST and on the concrete floor in the area of the boiler. The
presence of the staining represents a recognized environmental concern as it is
indicative of a release of heating oil from the oil supply line which may have
impacted the subsurface at the Site.
2. Based on a review of historical records, a single-story commercial building used for
auto repair operations was located on the northwest portion of the Site from
approximately 1977 to circa 2007. Auto repair facilities typically store and utilize
98-102 Steuben Street
Remedial Action Report
May 2017
10
solvents and petroleum products on-site including oil, waste oil, antifreeze, battery
acid, grease, antifreeze, and solvent parts washers. The former occupancy of the
auto repair facility on the northwest side of the Site represents a recognized
environmental condition.
Summary of the Work Performed under the Remedial Investigation
The scope of work for the RI was developed in response to the planned development
project and took into consideration the AOCs listed above. An investigation of soil, soil
vapor, and groundwater was performed to characterize the entire Site for potential
environmental contamination from historic on-site uses, operations, etc. As part of this
investigation, Carlin-Simpson & Associates performed the following scope of work:
1. Installed 7 soil borings across the entire project Site, and collected 12 soil samples
for chemical analysis from the soil borings to evaluate soil quality;
2. Installed 3 groundwater monitoring wells throughout the Site to establish
groundwater flow and collected 3 groundwater samples for chemical analysis to
evaluate groundwater quality;
In addition, Environmental Maintenance Contractors, Inc. (EMC) performed the
following scope of work:
1. Installed 4 soil vapor probes across the project Site and collected 4 samples for
chemical analysis.
Summary of Findings of Remedial Investigation
1. Elevation of the property ranges from approximately 42 to 44 feet.
2. Depth to groundwater ranges from 37.5 to 38.4 feet at the Site.
3. Groundwater flow is generally from south to north beneath the Site.
4. Depth to bedrock is greater than 102 feet at the Site.
5. The stratigraphy of the site, from the surface down, consists of 2 to 5 feet of
existing fill material (Class 7) that is underlain by medium dense to dense Sand,
Silty Sand, or Sandy Silt, with trace to little Gravel (Class 3a or 3b).
98-102 Steuben Street
Remedial Action Report
May 2017
11
6. Twelve soil/fill samples collected during the investigations were compared to New
York State Department of Environmental Conservation (NYSDEC) Part 375, Table
375-6.8 Unrestricted Use and Restricted Residential Use Soil Cleanup Objectives
(SCOs). The samples results showed that VOCs, pesticides, and PCBs were not
detected in any of soil samples. Several SVOCs including benzo(a)anthracene
(max. of 6.8 mg/kg), benzo(a)pyrene (max. of 5.4 mg/kg), benzo(b)fluoranthene
(max 6.8 mg/kg), benzo(k)fluoranthene (max 2.6 mg/kg), chrysene (max 7.3
mg/kg), dibenz(a,h)anthracene (max 1.4 mg/kg), and indeno(1,2,3-c,d)pyrene (max
5.1 mg/kg), were detected above Restricted Residential Use SCOs in four shallow
(0 to 2’) samples. The detected SVOCs are all in a class of compounds known as
polycyclic aromatic hydrocarbons (PAHs). Metals including arsenic (max of 32.9
mg.kg), barium (max of 646 mg/kg), cadmium (max 3.7 mg/kg), copper (max 550
mg/kg), lead (max of 1580 mg/kg), and mercury (max 1.5 mg/kg) exceeded
Restricted Residential Use SCOs in one or more shallow soil samples. Nickel,
silver, and zinc also exceeded Unrestricted Use SCOs. Only iron exceeded
Restricted Residential Use SCOs in deeper soil samples. The data indicates that the
PAHs and metals, which are typical constituents of historic fill material, are
widespread in the upper 2 to 5 feet across the site at varying concentrations.
7. Three groundwater samples collected during the investigations were compared to
the NYSDEC Technical and Operational Guidance Series (TOGS) 1.1.1 Ambient
Water Quality Standards (GQS) for Class GA (drinking water). Groundwater
samples collected during the RI showed that SVOCs, pesticides, and PCBs were
not detected in groundwater. Three VOCs including chloroform, tetrachloroethene
(PCE), and trichloroethene were detected in groundwater samples. Only PCE at 28
ug/L exceeded its GQS in one of three groundwater samples. Several metals were
identified in groundwater, but only sodium exceeded its GQS. The RI data
indicates that there is no widespread impact to the groundwater below the Site as a
result of the historic fill material or the identified AOCs. Based on the Groundwater
Flow Map, the PCE appears to be from an unknown upgradient source to the south
of the Site.
98-102 Steuben Street
Remedial Action Report
May 2017
12
8. Four soil vapor samples collected during the 2014 RI were compared Table 3.1 Air
Guideline Values derived by the NYSDOH located in the New York State
Department of Health (NYSDOH) Final Guidance for Evaluating Soil Vapor
Intrusion. Soil vapor samples showed moderate levels of petroleum related and
chlorinated VOCs in all soil vapor samples. Most contaminant concentrations were
below 20 ug/m3 except for 2,2,4-trimethylpentane (max of 8,100 ug/m3), acetone
(max of 210 ug/m3), cyclohexane (max of 950 ug/m3), and hexane (max of 2,800
ug/m3). Petroleum related compounds (BTEX) were detected at a maximum
concentration of 169 ug/m3. Chlorinated VOC, tetrachloroethylene (PCE) was
detected in all four samples at a maximum concentration of 26 μg/m3.
Trichlorethylene (TCE) was detected in three samples at a maximum concentration
of 1.3 μg/m3. Carbon tetrachloride was not detected in any samples. The TCE and
PCE concentrations are below the monitoring level ranges established within the
State NYS DOH soil vapor guidance matrix.
Appendix A includes the RIR
Summary of the Remedial Action
The Remedial Action achieved protection of public health and the environment for the
intended use of the property. The Remedial Action achieved all of the Remedial Action
Objectives established for the project; addressed applicable standards, criteria, and
guidance; reduced mobility, toxicity and volume of contaminants; was cost effective and
implementable; and used standard methods that are well established in the industry. The
remedial action is effective in the short-term and long-term.
A summary of the milestones achieved in the Remedial Action is as follows: A
Remedial Investigation (RI) was performed from December 2014 to January 2015. A RI
Report dated February 2015 was prepared to evaluate data and information necessary to
develop a Remedial Action Work Plan (RAWP). A Site Contact List was established. A
draft RAWP was prepared and released with a Fact Sheet on March 10, 2015 for a 30-day
public comment period. The RAWP and Stipulation List dated April 15, 2015 was
approved by the New York City Office of Environmental Remediation (OER) on April 23,
98-102 Steuben Street
Remedial Action Report
May 2017
13
2015. A Pre-Construction Meeting was held on May 20, 2015. The remedial action was
begun in May 2015 and completed in April 2017. Appendix B contains the RAWP.
The remedial action consisted of the following tasks:
1. Prepared a Community Protection Statement and implemented a Citizen
Participation Plan.
2. Mobilized site security and equipment; completed utility mark outs; and marked
and staked excavation areas.
3. Performed Waste Characterization Study prior to excavation activities. Nine waste
characterization soil samples were collected in February and September 2015.
Waste characterization samples were collected at a frequency dictated by disposal
facility(s).
4. Performed a Community Air Monitoring Program for particulates and volatile
organic carbon compounds.
5. Selected NYSDEC Part 375 Track 1 Soil Cleanup Objectives (SCOs).
6. The following excavations were performed: soil on the site was removed to depths
ranging from 14 to 20 feet from grade beneath the area of the new building and to
a depth of 10 feet below grade in the open space rear yard area. A total of 3,377
cubic yards of soil/fill was excavated and removed from the property.
7. Excavated 2,935.30 tons (~1,980 cubic yards) of non-hazardous soil/fill (historic
fill) and transported it to Coplay Aggregates, 5101 West Coplay Road, Whitehall,
PA; excavated 1,856.07 tons (~1,240 cubic yards) of clean soil and transported to
Vanbro Corporation, 1900 South Avenue, Staten Island, NY; excavated
approximately 286 tons (191 cubic yards) of clean soil and transported to Con-
Strux, 702 Grand Blvd., Westbury, NY.
8. Screened excavated soil/fill during intrusive work for indications of contamination
by visual means, odor, and monitoring with a PID.
9. Conducted materials management of excavated materials including temporarily
stockpiling and segregating in accordance with defined material types and to
prevent co-mingling of contaminated material and non-contaminated materials.
98-102 Steuben Street
Remedial Action Report
May 2017
14
10. Appropriately segregated excavated media onsite prior to disposal. Transported
and disposed all soil/fill material at permitted facilities in accordance with all
applicable laws and regulations for handling, transporting, and disposing, and the
RAWP.
11. Collected and analyzed 9 end-point samples to determine attainment of SCOs.
Track 1 SCOs were achieved.
12. As part of development, constructed an engineered Composite Cover System
consisting of a 36-inch thick mat foundation in the building area; retaining walls
and up to 10 feet of clean soil fill behind the walls in the rear yard; and concrete
pavers on virgin soil in the rear yard. The contractors for the Composite Cover
System construction were Red Hook Construction Group (building) and ECI
Contracting LLC (rear yard).
13. Installed a Vapor Barrier System that consisted of a 20-mil polyethylene vapor
barrier liner (VaporBlock Plus 20 by Raven Industries, Inc.) beneath the building
slab and along the below-grade foundation walls”. The contractor for the Vapor
Barrier System construction was Red Hook Construction Group.
14. Installed a passive Sub-Slab Depressurization System consisting of one loop of 4-
inch diameter slotted high density polyethylene (HDPE) pipe with one 4-inch
diameter cast iron vent riser pipe vented above the roof of the building. The
contractor for the Passive Sub-Slab Depressurization System construction was Red
Hook Construction Group.
15. Performed all activities required for the Remedial Action, including permitting
requirements and pretreatment requirements, in compliance with applicable laws
and regulations.
16. Implemented storm-water pollution prevention measures in compliance with
applicable laws and regulations.
17. Imported soil to be used for backfill and cover in compliance with the Remedial
Action Work Plan and in accordance with applicable laws and regulations.
18. Submitted daily reports during construction oversight activities. Daily reports were
submitted from May 27, 2015 to April 8, 2017.
19. Submitted a Sustainability Report.
98-102 Steuben Street
Remedial Action Report
May 2017
15
20. Submitted an RAR that describes the Remedial Action; certifies that the remedial
requirements defined in the RAWP have been achieved; defines the Site
boundaries; and lists any changes from the RAWP.
98-102 Steuben Street
Remedial Action Report
May 2017
16
REMEDIAL ACTION REPORT
1.0 SITE BACKGROUND
Clinton Hill Development II LLC has enrolled in the New York City Voluntary
Cleanup Program (NYC VCP) to investigate and remediate a property located at 98-102
Steuben Street in the Clinton Hill section of Brooklyn, New York. The boundary of the
property subject to this Remedial Action is shown in Figure 2 and includes, in its entirety,
Brooklyn Block 1893 and Lot 47. The Remedial Action was performed pursuant to the
OER-approved RAWP in a manner that has rendered the property protective of public
health and the environment consistent with its intended use. This RAR describes the
Remedial Action performed under the RAWP. The remedial action described in this
document provides for the protection of public health and the environment and complies
with applicable environmental standards, criteria and guidance (SCGs) and applicable laws
and regulations.
1.1 SITE LOCATION AND BACKGROUND
The Site is located at 98-102 Steuben Street in the Clinton Hill section in Brooklyn,
New York and is identified as Block 1893 and Lot 47 on the New York City Tax Map.
The Site Location Map is shown in Figure 1. The Site is 7,500-square feet and is bounded
by Steuben Street to the east, residential properties to the south, and multi-family
residential properties to the north and west. The Site Boundary Map is shown in Figure 2.
Prior to development, the Site was vacant but had been used for residential use and storage.
The site previously contained two residential two-story buildings with basements. There
was also a yard to the west of the buildings, undeveloped space in the northern portion of
the property, and a small dilapidated structure in the northwest corner of the Site.
1.2 REDEVELOPMENT PLAN
The Site is 7,500-square feet in total area. The former Site buildings were demolished
in order to re-develop the property. The development of the Site consists of a new 8-story
multi-family residential building with a full cellar. The building has 39 residential units
and is approximately 4,500 square feet in area. The structure is situated in the eastern
98-102 Steuben Street
Remedial Action Report
May 2017
17
portion (front) of the property. An excavation depth ranging from approximately 14 to 20
feet was required in the building area. This depth was deeper than anticipated in the RAWP
but was required due to the thickness of the mat foundation system and the existing
foundation conditions of the adjacent buildings to the north and south of the Site.
There is also an open space area in the western portion of the site (rear yard),
approximately 3,000 square feet in area, with tiered retaining walls and landscaping plants
along the western property line. The area between the building and the retaining walls
consists of a concrete paver patio. The entire rear yard area was excavated to a depth of
approximately 10 feet below grade, which corresponds to the building cellar elevation.
This excavation was as anticipated in the RAWP but the retaining wall layout was revised
from the plan included in the RAWP.
A map showing the building location, basement location and open space location is
shown in the Development Plan in Figure 3.
1.3 DESCRIPTION OF SURROUNDING PROPERTY
The area surrounding the Site consists of residential and commercial properties. To the
immediate north of the Site is a 7-story multi-family residential building that was
completed in 2014. To the west is another 7-story multi-family residential building on
Grand Avenue. To the east is Steuben Street followed by commercial buildings. To the
south of the Site are three (3) 4-story residential buildings followed by commercial
properties along Myrtle Avenue.
1.4 SUMMARY OF PAST SITE USES AND AREAS OF CONCERN
At the time of a Phase I Environmental Site Assessment (ESA) in February 2014, the
northern Site building and the first floor of the southern Site building were being used for
storage. The second floor of the southern building was occupied by residential tenants.
The exterior of the site was also being used for storage.
According to the Phase I ESA Report, the southern portion of the Site had been
occupied with a two-story structure since 1887. The two-story structure had been primarily
occupied by residential tenants from 1887 to 2007 with the exception of a brief period
98-102 Steuben Street
Remedial Action Report
May 2017
18
from 1969 to 1977 when it was occupied by an office. From 2007 to 2014, the two-story
structure had been occupied by both residential and commercial tenants. A varying level
lumber shed was located to the west of the structure from 1915 to 1938 and a single-story
shed was located to the west from 1938 to 1969.
The Phase I ESA Report also indicated that the northern portion of the Site had been
occupied with a two-story structure since 1887. The two-story structure had been occupied
by both residential and commercial tenants from 1887 to 2014. Commercial tenants
including offices, a storage company, a coal company, and a setting controls company had
occupied the northern portion of the site from 1934 to 2014. A stable was located to the
north and west of this structure from 1887 to 1904 and a lumber storage building was
located to the north from 1904 to 1938. Additionally, a lumber shed was located to the
west of the structure from 1915 to 1938. In the period from 1938 to 1969, a contractor’s
storage facility was located to the north of the structure. From 1977 to 2007, a single-story
auto repair facility was located in the northwest portion of the Site.
Based on the Phase I Environmental Site Assessment (ESA) that was performed by
Environmental Business Consultants (EBC) in February 2014, the areas of concern
(AOCs) identified for this site were as follows:
1. There was a 275-gallon heating oil aboveground storage tank (AST) (installation
date unknown) in the basement of 102 Steuben Street located on the southern
portion of the Site. The heating oil fill pipe and vent pipe for the AST in the
basement were observed on the east side of the Site. The AST was connected to a
boiler. The oil supply line from the AST to the boiler was buried and was most
likely repaired at some point as holes in the concrete indicated. Surficial staining
was noted on top of the AST and on the concrete floor in the area of the boiler. The
presence of the staining represents a recognized environmental concern as it is
indicative of a release of heating oil from the oil supply line which may have
impacted the subsurface at the Site.
2. Based on a review of historical records, a single-story commercial building used for
auto repair operations was located on the northwest portion of the Site from
98-102 Steuben Street
Remedial Action Report
May 2017
19
approximately 1977 to circa 2007. Auto repair facilities typically store and utilize
solvents and petroleum products on-site including oil, waste oil, antifreeze, battery
acid, grease, antifreeze, and solvent parts washers. The former occupancy of the
auto repair facility on the northwest side of the Site represents a recognized
environmental condition.
1.5 SUMMARY OF WORK PERFORMED UNDER THE REMEDIAL
INVESTIGATION
The scope of work for the RI was developed in response to the planned development
project and took into consideration the AOCs listed above. An investigation of soil, soil
vapor, and groundwater was performed to characterize the entire Site for potential
environmental contamination from historic on-site uses, operations, etc. As part of this
investigation, Carlin-Simpson & Associates performed the following scope of work:
1. Installed 7 soil borings across the entire project Site, and collected 12 soil samples
for chemical analysis from the soil borings to evaluate soil quality;
2. Installed 3 groundwater monitoring wells throughout the Site to establish
groundwater flow and collected 3 groundwater samples for chemical analysis to
evaluate groundwater quality;
In addition, Environmental Maintenance Contractors, Inc. (EMC) performed the
following scope of work:
1. Installed 4 soil vapor probes across the project Site and collected 4 samples for
chemical analysis.
1.6 SUMMARY OF FINDINGS OF REMEDIAL INVESTIGATION
1. Elevation of the property ranges from approximately 42 to 44 feet.
2. Depth to groundwater ranges from 37.5 to 38.4 feet at the Site.
3. Groundwater flow is generally from south to north beneath the Site.
4. Depth to bedrock is greater than 102 feet at the Site.
98-102 Steuben Street
Remedial Action Report
May 2017
20
5. The stratigraphy of the site, from the surface down, consists of 2 to 5 feet of
existing fill material (Class 7) that is underlain by medium dense to dense Sand,
Silty Sand, or Sandy Silt, with trace to little Gravel (Class 3a or 3b).
6. Twelve soil/fill samples collected during the investigations were compared to New
York State Department of Environmental Conservation (NYSDEC) Part 375, Table
375-6.8 Unrestricted Use (Track 1) and Restricted Residential Use (Track 2) Soil
Cleanup Objectives (SCOs). The samples results showed that VOCs, pesticides,
and PCBs were not detected in any of soil samples. Several SVOCs including
benzo(a)anthracene (max. of 6.8 mg/kg), benzo(a)pyrene (max. of 5.4 mg/kg),
benzo(b)fluoranthene (max 6.8 mg/kg), benzo(k)fluoranthene (max 2.6 mg/kg),
chrysene (max 7.3 mg/kg), dibenz(a,h)anthracene (max 1.4 mg/kg), and
indeno(1,2,3-c,d)pyrene (max 5.1 mg/kg), were detected above Restricted
Residential Use SCOs in four shallow (0 to 2’) samples. The detected SVOCs are
all in a class of compounds known as polycyclic aromatic hydrocarbons (PAHs).
Metals including arsenic (max of 32.9 mg.kg), barium (max of 646 mg/kg),
cadmium (max 3.7 mg/kg), copper (max 550 mg/kg), lead (max of 1580 mg/kg),
and mercury (max 1.5 mg/kg) exceeded Restricted Residential Use SCOs in one or
more shallow soil samples. Nickel, silver, and zinc also exceeded Unrestricted Use
SCOs. Only iron exceeded Restricted Residential Use SCOs in deeper soil samples.
The data indicates that the PAHs and metals, which are typical constituents of
historic fill material, are widespread in the upper 2 to 5 feet across the site at
varying concentrations.
7. Three groundwater samples collected during the investigations were compared to
the NYSDEC Technical and Operational Guidance Series (TOGS) 1.1.1 Ambient
Water Quality Standards (GQS) for Class GA (drinking water). Groundwater
samples collected during the RI showed that SVOCs, pesticides, and PCBs were
not detected in groundwater. Three VOCs including chloroform, tetrachloroethene
(PCE), and trichloroethene were detected in groundwater samples. Only PCE at 28
ug/L exceeded its GQS in one of three groundwater samples. Several metals were
identified in groundwater, but only sodium exceeded its GQS. The RI data
98-102 Steuben Street
Remedial Action Report
May 2017
21
indicates that there is no widespread impact to the groundwater below the Site as a
result of the historic fill material or the identified AOCs. Based on the Groundwater
Flow Map, the PCE appears to be from an unknown upgradient source to the south
of the Site.
8. Four soil vapor samples collected during the 2014 RI were compared Table 3.1 Air
Guideline Values derived by the NYSDOH located in the New York State
Department of Health (NYSDOH) Final Guidance for Evaluating Soil Vapor
Intrusion. Soil vapor samples showed moderate levels of petroleum related and
chlorinated VOCs in all soil vapor samples. Most contaminant concentrations were
below 20 ug/m3 except for 2,2,4-trimethylpentane (max of 8,100 ug/m3), acetone
(max of 210 ug/m3), cyclohexane (max of 950 ug/m3), and hexane (max of 2,800
ug/m3). Petroleum related compounds (BTEX) were detected at a maximum
concentration of 169 ug/m3. Chlorinated VOC, tetrachloroethylene (PCE) was
detected in all four samples at a maximum concentration of 26 μg/m3.
Trichlorethylene (TCE) was detected in three samples at a maximum concentration
of 1.3 μg/m3. Carbon tetrachloride was not detected in any samples. The TCE and
PCE concentrations are below the monitoring level ranges established within the
State NYS DOH soil vapor guidance matrix.
Appendix A includes the RIR.
98-102 Steuben Street
Remedial Action Report
May 2017
22
2.0 DESCRIPTION OF REMEDIAL ACTIONS
The Remedial Action was performed in accordance with an OER-approved Remedial
Action Work Plan and achieved the Remedial Action Objectives established for the
project. The Remedial Action was evaluated in an alternatives analysis and was determined
to be protective of human health and the environment, compliant with standards, criteria,
and guidelines (SCGs), effective in the short-term, effective in the long-term, capable of
attaining appropriate levels of reduction of toxicity, mobility, or volume of contaminated
material, implementable, cost effective, acceptable to the community, consistent with land
uses, and sustainable.
A summary of the milestones achieved in the Remedial Action is as follows: A
Remedial Investigation (RI) was performed from December 2014 to January 2015. A RI
Report dated February 2015 was prepared to evaluate data and information necessary to
develop a Remedial Action Work Plan (RAWP). A Site Contact List was established. A
RAWP was prepared and released with a Fact Sheet on March 10, 2015 for a 30-day public
comment period. The RAWP and Stipulation List dated April 15, 2015 was approved by
the New York City Office of Environmental Remediation (OER) on April 23, 2015. A Pre-
Construction meeting was held on May 20, 2015. The remedial action was begun on May
27, 2015 and completed on April 8, 2017. Appendix B includes the RAWP.
The remedial action consisted of the following tasks:
1. Prepared a Community Protection Statement and implemented a Citizen
Participation Plan.
2. Mobilized site security and equipment; completed utility mark outs; and marked
and staked excavation areas.
3. Performed Waste Characterization Study prior to excavation activities. Nine waste
characterization soil samples were collected in February and September 2015.
Waste characterization samples were collected at a frequency dictated by disposal
facility(s).
4. Performed a Community Air Monitoring Program for particulates and volatile
organic carbon compounds.
98-102 Steuben Street
Remedial Action Report
May 2017
23
5. Selected NYSDEC Part 375 Track 1 Soil Cleanup Objectives (SCOs).
6. The following excavations were performed: soil on the site was removed to depths
ranging from 14 to 20 feet from grade beneath the area of the new building and to
a depth of 10 feet below grade in the open space rear yard area. A total of 3,377
cubic yards of soil/fill was excavated and removed from the property.
7. Excavated 2,935.30 tons (~1,980 cubic yards) of non-hazardous soil/fill (historic
fill) and transported it to Coplay Aggregates, 5101 West Coplay Road, Whitehall,
PA; excavated 1,856.07 tons (~1,240 cubic yards) of clean soil and transported to
Vanbro Corporation, 1900 South Avenue, Staten Island, NY; excavated
approximately 286 tons (191 cubic yards) of clean soil and transported to Con-
Strux, 702 Grand Blvd., Westbury, NY.
8. Screened excavated soil/fill during intrusive work for indications of contamination
by visual means, odor, and monitoring with a PID.
9. Conducted materials management of excavated materials including temporarily
stockpiling and segregating in accordance with defined material types and to
prevent co-mingling of contaminated material and non-contaminated materials.
10. Appropriately segregated excavated media onsite prior to disposal. Transported
and disposed all soil/fill material at permitted facilities in accordance with all
applicable laws and regulations for handling, transporting, and disposing, and the
RAWP.
11. Collected and analyzed 9 end-point samples to determine attainment of SCOs.
Track 1 SCOs were achieved.
12. As part of development, constructed an engineered Composite Cover System
consisting of a 36-inch thick mat foundation in the building area; retaining walls
and up to 10 feet of clean soil fill behind the walls in the rear yard; and concrete
pavers on virgin soil in the rear yard. The contractors for the Composite Cover
System construction were Red Hook Construction Group (building) and ECI
Contracting LLC (rear yard).
13. Installed a Vapor Barrier System that consisted of a 20-mil polyethylene vapor
barrier liner (VaporBlock Plus 20 by Raven Industries, Inc.) beneath the building
98-102 Steuben Street
Remedial Action Report
May 2017
24
slab and along the below-grade foundation walls”. The contractor for the Vapor
Barrier System construction was Red Hook Construction Group.
14. Installed a passive Sub-Slab Depressurization System consisting of one loop of 4-
inch diameter slotted high density polyethylene (HDPE) pipe with one 4-inch
diameter cast iron vent riser pipe vented above the roof of the building. The
contractor for the Passive Sub-Slab Depressurization System construction was Red
Hook Construction Group.
15. Performed all activities required for the Remedial Action, including permitting
requirements and pretreatment requirements, in compliance with applicable laws
and regulations.
16. Implemented storm-water pollution prevention measures in compliance with
applicable laws and regulations.
17. Imported soil to be used for backfill and cover in compliance with the Remedial
Action Work Plan and in accordance with applicable laws and regulations.
18. Submitted daily reports during construction oversight activities. Daily reports were
submitted from May 27, 2015 to April 8, 2017.
19. Submitted a Sustainability Report.
20. Submitted an RAR that describes the Remedial Action; certifies that the remedial
requirements defined in the RAWP have been achieved; defines the Site
boundaries; and lists any changes from the RAWP.
98-102 Steuben Street
Remedial Action Report
May 2017
25
3.0 COMPLIANCE WITH REMEDIAL ACTION WORK PLAN
3.1 CONSTRUCTION HEALTH & SAFETY PLAN
The remedial construction activities performed under this program were in compliance
with the Construction Health and Safety Plan and applicable laws and regulations. The Site
Safety Coordinator was Meredith R. Anke, P.E.
3.2 COMMUNITY AIR MONITORING PLAN
The Community Air Monitoring Plan provided for the collection and analysis of air
samples during remedial construction activities to ensure proper protections were
employed to protect workers and the neighboring community. Monitoring was performed
from May 27, 2015 to April 8, 2017 in compliance with the Community Air Monitoring
Plan in the approved RAWP. The results of Community Air Monitoring are shown in
Appendix E.
3.3 SOIL/MATERIALS MANAGEMENT PLAN
The Soil/Materials Management Plan provided detailed plans for managing all
soil/materials that were disturbed at the Site, including excavation, handling, storage,
transport and disposal. It also included a series of controls to assure effective, nuisance-
free remedial activity in compliance with applicable laws and regulations. Remedial
construction activities performed under this program were in compliance with the SMMP
in the approved RAWP.
3.4 STORM-WATER POLLUTION PREVENTION
Storm water pollution prevention included physical methods and processes to control
and/or divert surface water flows and to limit the potential for erosion and migration of
Site soils, via wind or water. Remedial construction activities performed under this
program were in full compliance with methods and processes defined in the RAWP for
storm water prevention and applicable laws and regulations.
3.5 DEVIATIONS FROM THE REMEDIAL ACTION WORK PLAN
The following are the deviations from the Remedial Action Work Plan:
98-102 Steuben Street
Remedial Action Report
May 2017
26
1. At the time the RAWP was prepared, the construction plans were still being
developed. It was anticipated that the new building would have a 5-inch thick
concrete floor slab. The building was actually constructed with a 36-inch thick
reinforced concrete mat foundation.
2. An excavation depth of 10 feet was anticipated for the building area but an actual
excavation depth ranging from approximately 14 to 20 feet was required due to the
thickness of the mat foundation system and the existing foundation conditions of
the adjacent building to the north of the Site. This resulted in additional excavation
and disposal of clean native soil.
3. RCA, natural crushed stone, and quarry mason sand were imported to the site for
construction of the retaining walls in the rear yard of the property. Since these
materials were imported from properly registered facilities and since laboratory
analytical results confirmed that the quarry mason sand met the NYSDEC
Unrestricted Use SCOs, OER was not notified of the import of these materials.
4. During the construction of the rear yard retaining walls in November 2016, excess
native soil that had been stockpiled in the area was removed from the site. The
waste characterization results, the required profile information, and the OER
Historical Fill Notification Form were submitted to Con-Strux Recycled
Aggregates who subsequently issued an acceptance letter for their facility dated
November 10, 2016. However, we inadvertently neglected to obtain approval from
OER for the disposal of the additional clean native soil.
98-102 Steuben Street
Remedial Action Report
May 2017
27
4.0 REMEDIAL PROGRAM
4.1 PROJECT ORGANIZATION
Principal personnel who participated in the remedial action include Meredith R. Anke,
who is the Project Manager for Carlin-Simpson & Associates, Ryan Sullivan, who is the
Project Manager for Clinton Hill Development II LLC, Matthew Raices, who is the
Construction Director for Clinton Hill Development II LLC, and Gregory Johnson, who is
the Construction Manager from The J Companies, LLC. The Professional Engineer (PE)
and Qualified Environmental Professionals (QEP) for this project are Robert B. Simpson,
P.E. and Meredith R. Anke, respectively.
4.2 SITE CONTROLS
Site Preparation
Mobilization was conducted as necessary for each phase of work at the Site.
Mobilization included field personnel orientation, equipment mobilization,
marking/staking sampling locations and utility mark-outs. Each field team member
attended an orientation meeting to become familiar with the general operation of the Site,
health and safety requirements, and field procedures. Initial mobilization for the remedial
action occurred in May 2015.
On June 5, 2015, Environmental Maintenance Contractors (EMC) removed a 275-
gallon aboveground storage tank (AST) from the basement of one of the existing site
buildings. The steel tank was disposed of as scrap metal at Scrap King Flushing Inc. A
copy of the disposal receipt is attached in Appendix G of this report.
Demolition of the two previous site buildings occurred in July and August 2015 and
was performed by Northeast Service Interiors, LLC.
The presence of utilities and easements on the Site was investigated prior to the
performance of invasive work by contacting the One-Call System (811). All invasive
activities were performed in compliance with applicable laws and regulations to assure
safety. Utility companies and other responsible authorities were contacted to locate and
mark the locations.
98-102 Steuben Street
Remedial Action Report
May 2017
28
All permits or government approvals required for construction were obtained prior to
the start of the remedial action.
An OER Project Notice was erected at the project entrance and was in place during all
phases of the Remedial Action.
Soil Screening
Visual, olfactory and PID soil screening and assessment was performed under the
supervision of a Qualified Environmental Professional during all remedial and
development excavations. Soil screening was performed during all invasive work
performed during the remedy and development phase. No visual/olfactory evidence of
petroleum contamination was identified in the site excavations.
Stockpile Management
The majority of the historic fill material was loaded directly onto trucks to eliminate
the need for stockpiling. Some temporary stockpiling of historic fill was performed during
the excavation of footings and heel blocks and at the start of construction before disposal
facility approvals were obtained. Segregation of this excavated material was not required
since it was all treated as historic fill or as comingled historic fill. These temporary
stockpiles were covered with 8-mil poly-sheeting to prevent dust. To eliminate the need for
material segregation, virgin soil was not excavated in any portion of the site until the
historic fill had been completely removed from that area. Where a virgin soil stockpile
remained for an extended period in the rear of the property, the stockpile was covered with
8-mil poly-sheeting to prevent dust. Temporary virgin soil stockpiles were also covered
with 8-mil poly-sheeting, as needed, to prevent dust. Imported materials were temporarily
stockpiled in the rear of the property prior to their use in the retaining wall construction.
All temporary stockpile activities were compliant with applicable laws and regulations.
Soil stockpile areas were appropriately graded to control run-off in accordance with
applicable laws and regulations.
Truck Inspection
Before exiting the site, trucks were inspected for evidence of contaminated soil on the
undercarriage, body, and wheels. Soil and debris were removed, as necessary. Trucks on
98-102 Steuben Street
Remedial Action Report
May 2017
29
the property were restricted to the driveway area in the northeast portion of the site. Given
the limited size of the site, a stone tracking pad was not used for this project. Trucks
leaving the site did not track soil and fill from the site into the surrounding community.
Site Security
Site access was controlled by gated entrances to the fenced property.
Nuisance Controls
All invasive work during the remedial action was conducted in accordance with the
Odor, Dust, and Nuisance Control section of the RAWP. Air quality was monitored by on-
site personnel and equipment stationed at the downwind perimeter of the work area and
upwind of the work area. Work was halted whenever dust was detected and dust
suppression was performed whenever necessary by wetting dry surfaces. The contractors
were responsible for limiting all noise levels to a minimum and conformed to the New
York City noise control standards. Nuisance odors were not identified during the remedial
action. No dust or odor complaints were reported during the development.
Reporting
Daily reports providing a general summary of activities for each day of active
remedial work were emailed to the OER Project Manager. The reports included the
following:
• Project number and statement of the activities and an update of progress made
and locations of work performed;
• End-point samples collected;
• Quantities of material imported and exported from the Site;
• A summary of CAMP excursions, if any;
• Photographs of notable Site conditions and activities.
All daily reports are included in Appendix C. Digital photographs of the Remedial
Action are included in Appendix D.
98-102 Steuben Street
Remedial Action Report
May 2017
30
4.3 MATERIALS EXCAVATION AND REMOVAL ACTION
Soil/Fill Excavation and Removal
Existing soil was excavated from the limits of the entire site. This included excavation
in the 4,500 square foot building area to depths ranging from 14 to 20 feet and excavation
in the 3,000 square foot rear yard area to an approximate depth of 10 feet. A map showing
the approximate locations where excavations were performed and approximate thickness of
excavated material is shown in Figure 5. A total of 3,377 cubic yards of soil/fill were
excavated and removed from the property during the Removal Action. Materials removed
from the property under this Removal Action is generally classified as follows: historic fill
material, 2,935.30 tons (~1,980 cubic yards). The quantity of native soil removed from the
property is 2,142.07 tons (~1,431 cubic yards). The quantity of native soil recycled using
the NYC Clean Soil Bank is 0 cubic yards. The Removal Action was performed under the
oversight of Meredith R. Anke for the project.
The historic fill material was excavated and removed from the eastern portion (front)
of the Site first where the building would be constructed. During the RI, the historic fill
was found to range from approximately 2 feet to 5 feet in thickness. The excavation and
removal of the historic fill included the upper 1 foot to 2 feet of the underlying clean soil to
ensure that all historic fill had been removed. In addition, any material that had been
inadvertently mixed with the historic fill during the excavation, staging, and loading
operations was treated as historic fill material for disposal purposes. The historic fill
material was transported to Coplay Aggregates in Whitehall, Pennsylvania.
Once the historic fill was removed from an area, the underlying native soil was
excavated to the required subgrade elevations. The native soil generally consisted of
medium dense to dense Sand, Silty Sand, or Sandy Silt, with trace to little Gravel. Clean
native soil was transported to the Vanbro facility in Staten Island, New York.
Approximately 250 cubic yards of the excavated native soil was stockpiled in the
western portion of the Site (rear yard) from December 2015 until November 2016 for the
purpose of constructing retaining walls at a later date. In the RAWP, it was anticipated that
approximately 50 cubic yards of excavated native soil would be required for this purpose.
98-102 Steuben Street
Remedial Action Report
May 2017
31
In November 2016, approximately 191 cubic yards of the previously stockpiled material
was removed from the site and transported to the Con-Strux facility in Westbury, New
York. The remaining onsite native soil (approximately 60 cubic yards) and some imported
materials were placed as backfill for the new retaining walls in March and April 2017.
A map showing the approximate source location of reused soil and the location of
placement of reused soil is shown in Figure 6.
Soil Cleanup Objectives
The SCOs for this Remedial Action are Track 1 Unrestricted Use SCOs.
End Point Sample Results
The SCOs for this project were achieved.
Following excavation to the required subgrade elevations, Carlin-Simpson &
Associates collected nine endpoint soil samples. The samples were collected at depths
ranging from 10 to 14 feet below grade. Endpoint samples were not collected at deeper
intervals since only a small area at the north side of the building sloped down to a depth of
20 feet to meet the elevation of the adjacent building foundation. The locations of the
endpoint soil samples are shown on Figure 4. Dedicated disposable sampling equipment
was used to collect the samples eliminating the need for field equipment (rinsate) blanks.
Each of the soil samples was placed into laboratory-provided glass jars and sealed
with Teflon lined lids to provide a hermetic seal. The samples were then placed in plastic
coolers and delivered directly to Test America Inc. in Edison, New Jersey (NYDOH ELAP
Certification No. 11452) under proper chain-of-custody procedures for the required
analysis. Each of the soil samples was analytically tested in accordance with USEPA
methodologies for the following analysis:
• Volatile organic compounds by EPA Method 8260;
• Semi-volatile organic compounds by EPA Method 8270;
• Target Analyte List metals; and
• Pesticides/PCBs by EPA Method 8081/8082.
98-102 Steuben Street
Remedial Action Report
May 2017
32
As shown in Table 1, no VOCs, SVOCs, Pesticides, PCBs, or Metals were detected
above the Unrestricted Use SCOs, with the exception of the following slight exceedances:
• 4,4’-DDT at 0.0094 ppm in PE-A1
• Lead at 63.1 ppm in PE-A2
• Mercury at 0.27 ppm in PE-A2
• 4,4’-DDT at 0.0086 ppm in PE-C1
To verify the end-point sampling results for samples PE-A1 and PE-A2, the locations
were re-sampled on December 7, 2016. The samples were collected in close proximity to
the original sample locations and at the same subgrade elevation. Sample PE-A1* was only
analyzed for Pesticides and sample PE-A2* was only analyzed for Metals. The results are
summarized in Table 1A. As shown in Table 1A, no Pesticides were detected in sample
PE-A1* and no Metals were detected above the Unrestricted Use SCOs in sample PE-A2*.
Based on the end-point analytical results, the slight pesticide and metals exceedances
at samples PE-A1 and PE-A2 are isolated and not indicative of on-site contamination.
Furthermore, the detected pesticide and metals concentrations at samples PE-A1, PE-A2,
and PE-C1 are all well below the Residential Use SCOs and are, therefore, still protective
of public health and the environment.
A map of end-point sample locations is shown in Figure 4. A tabular summary of end-
point sampling results compared to SCOs is included in Table 1 and Table 1A. Full
laboratory reports are included in Appendix I.
4.4 MATERIALS DISPOSAL
Waste characterization sampling of the historic fill and the underlying virgin soil was
performed in February 2015 and September 2015. In February 2015, Carlin-Simpson &
Associates performed nine geoprobe borings at the Site for the purpose of collecting waste
characterization soil samples. Historic fill was encountered to depths ranging from 2 to 5
feet below grade. Waste characterization samples in the historic fill consisted of the
following:
98-102 Steuben Street
Remedial Action Report
May 2017
33
• Three discrete soil/fill samples from three geoprobe locations for laboratory
analytical testing for VOCs.
• Three 4-point composite samples from nine geoprobe locations for laboratory
analytical testing for SVOCs, PCBs, Metals, and TCLP Metals.
The virgin soil on the Site generally consists of medium dense brown Sand, Silty
Sand, or Sandy Silt, with trace to little Gravel. Waste characterization samples in the virgin
soil consisted of the following:
• One 5-point composite sample from five geoprobe locations for laboratory
analytical testing for VOCs, SVOCs, Pesticides, Herbicides, PCBs, Petroleum
Hydrocarbons, Metals, Cyanide, and Organic Content.
• Two discrete soil samples from two locations for laboratory analytical testing
for VOCs.
The number of waste characterization samples and the required laboratory analysis
were dictated by the disposal facilities.
The laboratory analytical results and the required profile information along with the
OER Historical Fill Notification Form was submitted to Coplay Aggregates (historic fill)
and to Vanbro Corporation (virgin soil). Material Solution Services issued an acceptance
letter for the Coplay Aggregates facility dated August 10, 2015 and TRC Engineers issued
an acceptance letter for the Vanbro facility dated September 10, 2015.
The laboratory analytical results, the required profile information, and the OER
Historical Fill Notification Form was also later submitted to Con-Strux Recycled
Aggregate for additional virgin soil to be removed from the Site in 2016. Con-Strux issued
an acceptance letter for their facility dated November 10, 2016.
Disposal facility documentation, including the OER Historical Fill Notification Form
and acceptance letters, and OER correspondence is included in Appendix F and the waste
characterization analytical results are included in Appendix H.
From August 26, 2015 to October 30, 2015, a total of 2,935.30 tons (~1,980 cubic
yards) of historic fill was removed from the entire limits of the Site and loaded into dump
98-102 Steuben Street
Remedial Action Report
May 2017
34
trucks for transport to Coplay Aggregates in Whitehall, PA.
From October 6, 2015 to November 16, 2015, a total of 1,856.07 tons (or
approximately 1,240 cubic yards) of native soil was removed from the entire limits of the
Site and loaded into dump trucks for transport to Vanbro Corporation in Staten Island, NY.
From November 2, 2016 to November 9, 2016, approximately 191 cubic yards of
native soil was removed from the rear portion of the Site and loaded into dump trucks for
transport to Con-Strux Recycled Aggregates in Westbury, NY.
The type, quantity, and disposal location of each material removed and disposed off-
Site is presented below:
Disposal Location/Address Type of Material Quantity
Coplay Aggregates
5101 West Coplay Road
Whitehall, PA
Non-Hazardous
Soil/Fill
2,935.30 tons
(~1,980 cubic yards)
Vanbro Corporation
1900 South Avenue
Staten Island, NY
Clean Soil 1,856.07 tons
(~1,240 cubic yards)
Con-Strux
702 Grand Blvd.
Westbury, NY
Clean Soil ~286 tons
(191 cubic yards)
Disposal facility documentation, including the OER Historical Fill Notification Form
and facility acceptance letters, is included in Appendix F. Manifests are included in
Appendix G. Waste characterization laboratory reports are presented in Appendix H. A
summary table of the material disposal quantities is included in Table 3.
4.5 BACKFILL IMPORT
Materials were imported to the Site for construction of tiered retaining walls in the
rear yard. These materials consisted of the following:
98-102 Steuben Street
Remedial Action Report
May 2017
35
• Two loads (32 cubic yards) of RCA was imported on November 10, 2016 and
November 11, 2016 from Con-Strux for the retaining wall leveling pad.
• One load (7 cubic yards) of natural crushed stone was imported on December
8, 2016 from Con-Strux for retaining wall drainage.
• 1,400 50-pound bags (35 tons) of 3/4-inch natural crushed blue stone was
imported from March 22, 2017 to April 7, 2017 from GC Warehouse LLC for
retaining wall drainage and for landscaping behind retaining walls.
• Four loads (95.91 tons) of quarry mason sand was imported from March 29,
2017 to April 6, 2017 from Diamond Sand & Gravel / Earth Efficient for
retaining wall backfill.
Truck tickets were reviewed for all imported materials to ensure that the correct
materials were being received and that they were from the approved facilities. The
imported material was also visually inspected for compliance. Photographs of the import
tickets are included in Appendix D. Since the imported materials consisted of RCA, natural
crushed stone, and quarry mason sand from properly registered facilities, OER was not
notified of the import of these materials.
All soil imported to the property (quarry mason sand from Diamond Sand & Gravel /
Earth Efficient) met the Unrestricted Use SCOs. A table of all sources of backfill with
quantities for each source is shown in Table 4. A table summarizing chemical analytical
results for backfill is included in Appendix K. The laboratory report for imported soil is
included in Appendix K. A map showing backfill placement locations at the Site is shown
in Figure 6.
98-102 Steuben Street
Remedial Action Report
May 2017
36
5.0 ENGINEERING CONTROLS
A Track 1 Remedial Action was achieved and Engineering Controls are not required.
However, as part of construction, several protective systems were installed. These are:
(1) Composite Cover System;
(2) Vapor Barrier System;
(3) Passive Sub-Slab Depressurization System.
Composite Cover System
As part of development, an engineered Composite Cover System has been built at the
site. This Composite Cover System is comprised of a 36-inch thick reinforced concrete mat
foundation in the building area; retaining walls and up to 10 feet clean soil fill behind the
retaining walls in the rear yard; and concrete pavers on the virgin soil in the rear yard
between the building and the retaining walls. The contractors for the Composite Cover
System construction were Red Hook Construction Group (building) and ECI Contracting
LLC (rear yard).
Figure 3 (Development Plan) shows a map of the location of each Composite Cover
System type built at the Site. Photographs of construction of the Composite Cover System
are included in Appendix D.
Vapor Barrier System
As part of the development, a Vapor Barrier System has been built at the site. This
Vapor Barrier System consists of a 20-mil polyethylene vapor barrier liner (VaporBlock
Plus 20 by Raven Industries, Inc.) beneath the building slab and along the below-grade
foundation walls. The vapor barrier and all seals and welds were installed in accordance
with the manufacturer’s recommendations and specifications. Specifically, seams/joints
were overlapped a minimum of 6 inches and sealed with VaporBond Plus 4-inch tape.
Penetrations were sealed using fabricated pipe boots, overlapping seams, and VaporBond
Plus 4-inch tape. The professional engineer for the Vapor Barrier System was Robert B.
Simpson, P.E. The contractor for the Vapor Barrier System construction was Red Hook
Construction Group.
98-102 Steuben Street
Remedial Action Report
May 2017
37
Figure 7 shows the Vapor Barrier System as-built at the Site. Photographs of
installation of the Vapor Barrier System are included in Appendix D. A copy of
manufacturer’s specifications for the Vapor Barrier System is included in Appendix J.
Passive Sub-Slab Depressurization System
Exposure to soil vapor is prevented by a passive Sub-Slab Depressurization System
(SSDS) that has been built on the Site. This SSDS consists of one loop of 4-inch diameter
slotted high density polyethylene (HDPE) pipe with one 4-inch diameter cast iron vent
riser pipe vented above the roof of the building. No blowers, gauges, or alarms were
installed as part of the system.
The design engineer for the passive SSDS is Ronen Sharon, P.E. of Sharon
Engineering P.C. The contractor for construction of the Passive SSDS was Red Hook
Construction Group. Figure 7 shows the as-built location for the Passive SSDS installed in
this Remedial Action and includes the location and layout of sub-slab vapor collection
piping and the riser vent pipe. Figure 8 shows the SSDS Vent Riser Diagram. Photographs
showing the installation of the Passive SSDS are shown in Appendix D.
98-102 Steuben Street
Remedial Action Report
May 2017
38
6.0 INSTITUTIONAL CONTROLS
A Track 1 Remedial Action was achieved and Institutional Controls are not
required.
98-102 Steuben Street
Remedial Action Report
May 2017
39
7.0 SITE MANAGEMENT PLAN
A Track 1 Remedial Action was achieved and Site Management is not required.
98-102 Steuben Street
Remedial Action Report
May 2017
40
8.0 SUSTAINABILITY REPORT
This Remedial Action provided for sustainable remediation and redevelopment
through a variety of means that are defined in this Sustainability Report.
Reuse of Clean, Recyclable Materials and Conservation of Natural Resources. Reuse
of clean, recyclable materials reduces consumption of non-renewable virgin resources and
can provide energy savings and greenhouse gas reduction since these materials can be
locally-derived.
Conservation of non-renewable resources was achieved by reusing onsite soil and using
RCA during the redevelopment of the site. An estimate of the quantity of recycled material
reused on this project is 100 cubic yards of onsite soil and 32 cubic yards of RCA.
Conversion to Clean Fuels. Use of clean fuel improves NYC’s air quality by reducing
harmful emissions. Natural gas is utilized as the principal fuel in the new building.
Paperless Brownfield Cleanup Program. Clinton Hill Development II LLC participated
in OER’s paperless Voluntary Cleanup Program. Under this program, submission of
electronic documents replaced submission of hard copies for the review of project
documents, communications and milestone reports. A best estimate of the mass (pounds)
of paper saved under this plan is 50 pounds.
Low-Energy Project Management Program. Clinton Hill Development II LLC
participated in OER’s low-energy project management program. Under this program,
whenever possible, meetings were held using remote communication technologies, such as
videoconferencing and teleconferencing to reduce energy consumption and traffic
congestion associated with personal transportation. A gross estimate of the number of
miles of personal transportation that was conserved in this process is 300 miles.
DRAWING TITLE
CHECKED BY
SCALE DATE
PROJECT #
DRAWING #
100-102 Steuben StreetBrooklyn, NY 11205
OWNER
abarchitekten
# DATE DESCRIPTION
89
67
34
12
5
10
ISSUES/REVISIONS
86 Walker St 4th Fl New York NY 10013T 212.334.1232 F 212.334.4520
www.abarchitekten.com
The General Contractor shall check and verify alldimensions and report all errors and omissionsto the Architect. Do not scale measurementsfrom the drawings. This drawing shall not beused for construction purposes unless signed bythe consultants. This drawing is copyrighted andit is the sole property of AB Architekten. Anyreproduction or other use of this drawing withoutconsent of the Architect is prohibited.
OF 21
AB
2.26.15
DATE DESCRIPTION
STRUCTURAL / MECHANICAL ENGINEER
3.12.156.6.17
1112131415
OER SUBMISSIONINSTALLATION REPORT
AS-BUILT
A-200.00
CELLAR PLAN
1
1/4 " = 1'-0"
DRAWING TITLE
CHECKED BY
SCALE DATE
PROJECT #
DRAWING #
100-102 Steuben StreetBrooklyn, NY 11205
OWNER
abarchitekten
# DATE DESCRIPTION
89
67
34
12
5
10
ISSUES/REVISIONS
86 Walker St 4th Fl New York NY 10013T 212.334.1232 F 212.334.4520
www.abarchitekten.com
The General Contractor shall check and verify alldimensions and report all errors and omissionsto the Architect. Do not scale measurementsfrom the drawings. This drawing shall not beused for construction purposes unless signed bythe consultants. This drawing is copyrighted andit is the sole property of AB Architekten. Anyreproduction or other use of this drawing withoutconsent of the Architect is prohibited.
OF 21
AB
2.26.15
DATE DESCRIPTION
STRUCTURAL / MECHANICAL ENGINEER
3.12.156.6.17
1112131415
OER SUBMISSIONINSTALLATION REPORT
AS-BUILT
AS INDICATED
A-210.00
REAR YARD PLAN
11
DRAWING TITLE
CHECKED BY
SCALE DATE
PROJECT #
DRAWING #
100-102 Steuben StreetBrooklyn, NY 11205
OWNER
abarchitekten
# DATE DESCRIPTION
89
67
34
12
5
10
ISSUES/REVISIONS
86 Walker St 4th Fl New York NY 10013T 212.334.1232 F 212.334.4520
www.abarchitekten.com
The General Contractor shall check and verify alldimensions and report all errors and omissionsto the Architect. Do not scale measurementsfrom the drawings. This drawing shall not beused for construction purposes unless signed bythe consultants. This drawing is copyrighted andit is the sole property of AB Architekten. Anyreproduction or other use of this drawing withoutconsent of the Architect is prohibited.
OF 21
AB
2.26.15
DATE DESCRIPTION
STRUCTURAL / MECHANICAL ENGINEER
3.12.156.6.17
1112131415
OER SUBMISSIONINSTALLATION REPORT
AS-BUILT
3/16" = 1'-0"
A-301.00
SECTION
12
PROFESSIONAL ENGINEERROBERT B. SIMPSON, P.E.
FIG -7
1" = 10'
RBS
14-131A
MRA
98-102 STEUBEN STREETBROOKLYN, NEW YORK
05.01.17
CARLIN-SIMPSON AND ASSOCIATES61 Main StreetSayreville, NJ 08872
Consulting Geotechnical andEnvironmental Engineers
MAP OF LOCATION OF VAPOR BARRIERSYSTEM AND SSDS SYSTEM
GENERAL NOTES:
1. GENERAL LAYOUT WAS OBTAINED FROM A DRAWING THATWAS PREPARED BY SHARON ENGINEERING PC, ENTITLED"FOUNDATION PLAN", DATED 4/14/2015, DRAWING NO.FO-100.00.
2. RISER PIPE LOCATION WAS OBTAINED FROM A DRAWINGPREPARED BY AB ARCHITEKTEN, ENTITLED "CELLAR PLAN",DATED 9/9/2015, DRAWING NO. A-200.00.
Table 1 - Summary of End-Point Analytical Results
Sample No. NYSDEC
Unrestricted Use SCO
PE-A1 PE-A2 PE-A3 PE-B1 PE-B2 PE-B3 PE-C1 PE-C2 PE-C3
Sample Date mg/kg 11/10/16 11/10/16 11/10/16 10/20/15 10/20/15 11/10/15 10/20/15 10/20/15 11/10/15
Sample Depth -- 10 ft 10 ft 10 ft 14 ft 14 ft 14 ft 14 ft 14 ft 14 ft
Volatile Organic Compounds (VOCs by 8260C, mg/kg)
1,1,1-Trichloroethane 0.68 ND ND ND ND ND ND ND ND ND
1,1,2,2-Tetrachloroethane - ND ND ND ND ND ND ND ND ND
1,1,2-Trichloroethane - ND ND ND ND ND ND ND ND ND
1,1-Dichloroethane 0.27 ND ND ND ND ND ND ND ND ND
1,1-Dichloroethene 0.33 ND ND ND ND ND ND ND ND ND
1,2,3-Trichlorobenzene - ND ND ND ND ND ND ND ND ND
1,2,4-Trichlorobenzene - ND ND ND ND ND ND ND ND ND
1,2-Dibromo-3-Chloropropane - ND ND ND ND ND ND ND ND ND
1,2-Dibromoethane - ND ND ND ND ND ND ND ND ND
1,2-Dichlorobenzene 1.1 ND ND ND ND ND ND ND ND ND
1,2-Dichloroethane 0.02 ND ND ND ND ND ND ND ND ND
1,2-Dichloropropane - ND ND ND ND ND ND ND ND ND
1,3-Dichlorobenzene 2.4 ND ND ND ND ND ND ND ND ND
1,4-Dichlorobenzene 1.8 ND ND ND ND ND ND ND ND ND
1,4-Dioxane 0.1 ND ND ND ND ND ND ND ND ND
2-Butanone 0.12 ND ND ND ND ND ND ND ND ND
2-Hexanone - ND ND ND ND ND ND ND ND ND
4-Methyl-2-pentanone - ND ND ND ND ND ND ND ND ND
Acetone 0.05 ND ND ND ND ND ND ND ND ND
Benzene 0.06 ND ND ND ND ND ND ND ND ND
Bromochloromethane - ND ND ND ND ND ND ND ND ND
Bromodichloromethane - ND ND ND ND ND ND ND ND ND
Bromoform - ND ND ND ND ND ND ND ND ND
Bromomethane - ND ND ND ND ND ND ND ND ND
Carbon disulfide - ND ND ND ND ND ND ND ND ND
Carbon tetrachloride 0.76 ND ND ND ND ND ND ND ND ND
Chlorobenzene 1.1 ND ND ND ND ND ND ND ND ND
Chloroethane - ND ND ND ND ND ND ND ND ND
Table 1 - Summary of End-Point Analytical Results
Sample No. NYSDEC
Unrestricted Use SCO
PE-A1 PE-A2 PE-A3 PE-B1 PE-B2 PE-B3 PE-C1 PE-C2 PE-C3
Sample Date mg/kg 11/10/16 11/10/16 11/10/16 10/20/15 10/20/15 11/10/15 10/20/15 10/20/15 11/10/15
Sample Depth -- 10 ft 10 ft 10 ft 14 ft 14 ft 14 ft 14 ft 14 ft 14 ft
Chloroform 0.37 ND ND ND ND ND ND ND ND ND
Chloromethane - ND ND ND ND ND ND ND ND ND
cis-1,2-Dichloroethene 0.25 ND ND ND ND ND ND ND ND ND
cis-1,3-Dichloropropene - ND ND ND ND ND ND ND ND ND
Cyclohexane - ND ND ND ND ND ND ND ND ND
Dibromochloromethane - ND ND ND ND ND ND ND ND ND
Dichlorodifluoromethane - ND ND ND ND ND ND ND ND ND
Ethylbenzene 1 ND ND ND ND ND ND ND ND ND
Freon TF - ND ND ND ND ND ND ND ND ND
Isopropylbenzene - ND ND ND ND ND ND ND ND ND
m&p-Xylene 0.26 ND ND ND ND ND ND ND ND ND
Methyl acetate - ND ND ND ND ND ND ND ND ND
Methylcyclohexane - ND ND ND ND ND ND ND ND ND
Methylene Chloride 0.05 0.00057(J) 0.00044(J) 0.00052(J) ND ND ND ND ND ND
MTBE 0.93 ND ND ND ND ND ND ND ND ND
o-Xylene 0.26 ND ND ND ND ND ND ND ND ND
Styrene - ND ND ND ND ND ND ND ND ND
Tetrachloroethene 1.3 ND ND ND ND ND ND ND ND ND
Toluene 0.7 ND ND ND ND ND ND ND ND ND
trans-1,2-Dichloroethene 0.19 ND ND ND ND ND ND ND ND ND
trans-1,3-Dichloropropene - ND ND ND ND ND ND ND ND ND
Trichloroethene 0.47 ND ND ND ND ND ND ND ND ND
Trichlorofluoromethane - ND ND ND ND ND ND ND ND ND
Vinyl chloride 0.02 ND ND ND ND ND ND ND ND ND
Total Estimated VOC TICs - ND ND ND ND ND ND ND ND ND
Semi-Volatile Organic Compounds (SVOCs by 8270D, mg/kg)
1,2,4-Trichlorobenzene - ND ND ND ND ND ND ND ND ND
1,2-Dichlorobenzene 1.1 ND ND ND ND ND ND ND ND ND
1,3-Dichlorobenzene 2.4 ND ND ND ND ND ND ND ND ND
Table 1 - Summary of End-Point Analytical Results
Sample No. NYSDEC
Unrestricted Use SCO
PE-A1 PE-A2 PE-A3 PE-B1 PE-B2 PE-B3 PE-C1 PE-C2 PE-C3
Sample Date mg/kg 11/10/16 11/10/16 11/10/16 10/20/15 10/20/15 11/10/15 10/20/15 10/20/15 11/10/15
Sample Depth -- 10 ft 10 ft 10 ft 14 ft 14 ft 14 ft 14 ft 14 ft 14 ft
1,4-Dichlorobenzene 1.8 ND ND ND ND ND ND ND ND ND
2,4,5-Trichlorophenol - ND ND ND ND ND ND ND ND ND
2,4,6-Trichlorophenol - ND ND ND ND ND ND ND ND ND
2,4-Dichlorophenol - ND ND ND ND ND ND ND ND ND
2,4-Dimethylphenol - ND ND ND ND ND ND ND ND ND
2,4-Dinitrophenol - ND ND ND ND ND ND ND ND ND
2,4-Dinitrotoluene - ND ND ND ND ND ND ND ND ND
2,6-Dinitrotoluene - ND ND ND ND ND ND ND ND ND
2-Chloronaphthalene - ND ND ND ND ND ND ND ND ND
2-Chlorophenol - ND ND ND ND ND ND ND ND ND
2-Methylnaphthalene - 0.012(J) 0.015(J) 0.011(J) ND ND ND ND ND ND
2-Methylphenol 0.33 ND ND ND ND ND ND ND ND ND
2-Nitroaniline - ND ND ND ND ND ND ND ND ND
2-Nitrophenol - ND ND ND ND ND ND ND ND ND
3,3'-Dichlorobenzidine - ND ND ND ND ND ND ND ND ND
3-Nitroaniline - ND ND ND ND ND ND ND ND ND
4,6-Dinitro-2-methylphenol - ND ND ND ND ND ND ND ND ND
4-Bromophenyl phenyl ether - ND ND ND ND ND ND ND ND ND
4-Chloro-3-methylphenol - ND ND ND ND ND ND ND ND ND
4-Chloroaniline - ND ND ND ND ND ND ND ND ND
4-Chlorophenyl phenyl ether - ND ND ND ND ND ND ND ND ND
4-Methylphenol 0.33 ND ND ND ND ND ND ND ND ND
4-Nitroaniline - ND ND ND ND ND ND ND ND ND
4-Nitrophenol - ND ND ND ND ND ND ND ND ND
Acenaphthene 20 0.011(J) 0.018(J) ND ND ND ND ND ND ND
Acenaphthylene 100 ND ND ND ND ND ND ND ND ND
Anthracene 100 ND 0.051(J) ND ND ND ND ND ND ND
Benzo[a]anthracene 1 0.058 0.12 ND ND ND 0.043 0.044 ND 0.056
Benzo[a]pyrene 1 0.049 0.10 0.015(J) ND ND 0.034 0.028(J) ND 0.049
Table 1 - Summary of End-Point Analytical Results
Sample No. NYSDEC
Unrestricted Use SCO
PE-A1 PE-A2 PE-A3 PE-B1 PE-B2 PE-B3 PE-C1 PE-C2 PE-C3
Sample Date mg/kg 11/10/16 11/10/16 11/10/16 10/20/15 10/20/15 11/10/15 10/20/15 10/20/15 11/10/15
Sample Depth -- 10 ft 10 ft 10 ft 14 ft 14 ft 14 ft 14 ft 14 ft 14 ft
Benzo[b]fluoranthene 1 0.065 0.13 0.030(J) ND ND 0.040 0.041 ND 0.064
Benzo[g,h,i]perylene 100 0.024(J) 0.050(J) ND ND ND 0.023(J) ND ND 0.042(J)
Benzo[k]fluoranthene 0.8 0.037 0.065 ND ND ND 0.022(J) ND ND 0.027(J)
Bis (2-chloroisopropyl) ether - ND ND ND ND ND ND ND ND ND
Bis(2-chloroethoxy) methane - ND ND ND ND ND ND ND ND ND
Bis(2-chloroethyl) ether - ND ND ND ND ND ND ND ND ND
Bis(2-ethylhexyl) phthalate - ND ND ND ND ND 0.020(J) ND ND ND
Butyl benzyl phthalate - ND ND ND ND ND ND ND ND ND
Carbazole - 0.0094(J) 0.019(J) ND ND ND ND ND ND ND
Chrysene 1 0.060(J) 0.12(J) 0.019(J) ND ND 0.047(J) 0.038(J) ND 0.063(J)
Dibenz(a,h)anthracene 0.33 ND ND ND ND ND ND ND ND ND
Dibenzofuran 7 ND 0.017(J) ND ND ND ND ND ND ND
Diethyl phthalate - ND ND ND ND ND ND ND ND ND
Dimethyl phthalate - ND ND ND ND ND ND ND ND ND
Di-n-butyl phthalate - 0.029(J) 0.039(J) 0.012(J) ND ND ND ND ND ND
Di-n-octyl phthalate - ND ND ND ND ND ND ND ND ND
Fluoranthene 100 0.12(J) 0.30(J) 0.038(J) ND ND 0.078(J) 0.092(J) ND 0.10(J)
Fluorene 30 0.011(J) 0.025(J) ND ND ND ND ND ND ND
Hexachlorobenzene 0.33 ND ND ND ND ND ND ND ND ND
Hexachlorobutadiene - ND ND ND ND ND ND ND ND ND
Hexachlorocyclopentadiene - ND ND ND ND ND ND ND ND ND
Hexachloroethane - ND ND ND ND ND ND ND ND ND
Indeno[1,2,3-cd]pyrene 0.5 0.026(J) 0.066 ND ND ND 0.024(J) ND ND 0.043
Isophorone - ND ND ND ND ND ND ND ND ND
Naphthalene 12 0.0092(J) 0.015(J) ND ND ND ND ND ND ND
Nitrobenzene - ND ND ND ND ND ND ND ND ND
N-Nitrosodi-n-propylamine - ND ND ND ND ND ND ND ND ND
N-Nitrosodiphenylamine - ND ND ND ND ND ND ND ND ND
Pentachlorophenol 0.8 ND ND ND ND ND ND ND ND ND
Table 1 - Summary of End-Point Analytical Results
Sample No. NYSDEC
Unrestricted Use SCO
PE-A1 PE-A2 PE-A3 PE-B1 PE-B2 PE-B3 PE-C1 PE-C2 PE-C3
Sample Date mg/kg 11/10/16 11/10/16 11/10/16 10/20/15 10/20/15 11/10/15 10/20/15 10/20/15 11/10/15
Sample Depth -- 10 ft 10 ft 10 ft 14 ft 14 ft 14 ft 14 ft 14 ft 14 ft
Phenanthrene 100 0.086(J) 0.21(J) 0.029(J) ND ND 0.054(J) 0.047(J) ND 0.066(J)
Phenol 0.33 ND ND ND ND ND ND ND ND ND
Pyrene 100 0.10(J) 0.23(J) 0.031(J) ND ND 0.086(J) 0.064(J) ND 0.098(J)
Total Estimated SVOC TICs - 1.3 2.65 3.12 ND ND ND ND ND ND
Pesticides (Pesticides by 8081B, mg/kg)
4,4'-DDD 0.0033 ND ND ND ND ND ND ND ND ND
4,4'-DDE 0.0033 ND ND ND ND ND ND 0.0021(J) ND ND
4,4'-DDT 0.0033 0.0094 ND ND ND ND ND 0.0086 ND ND
Aldrin 0.005 ND ND ND ND ND ND ND ND ND
alpha-BHC 0.02 ND ND ND ND ND ND ND ND ND
beta-BHC 0.036 ND ND ND ND ND ND ND ND ND
Chlordane 0.094 ND ND ND ND ND ND ND ND ND
delta-BHC 0.04 ND ND ND ND ND ND ND ND ND
Dieldrin 0.005 ND ND ND ND ND ND ND ND ND
Endosulfan I 2.4 ND ND ND ND ND ND ND ND ND
Endosulfan II 2.4 ND ND ND ND ND ND ND ND ND
Endosulfan sulfate 2.4 ND ND ND ND ND ND ND ND ND
Endrin 0.014 ND ND ND ND ND ND ND ND ND
Endrin aldehyde - ND ND ND ND ND ND ND ND ND
Endrin ketone - ND ND ND ND ND ND ND ND ND
gamma-BHC (Lindane) 0.1 ND ND ND ND ND ND ND ND ND
Heptachlor 0.042 ND ND ND ND ND ND ND ND ND
Heptachlor epoxide - ND ND ND ND ND ND ND ND ND
Methoxychlor - ND ND ND ND ND ND ND ND ND
Toxaphene - ND ND ND ND ND ND ND ND ND
Polychlorinated Biphenyls (PCBs by 8082A, mg/kg)
Total PCBs 0.1 ND ND ND ND ND ND ND ND ND
TAL Metals (Metals by 6010C, mg/kg)
Aluminum - 5290 6490 8660 5500 3650 3410 4170 3790 4610
Table 1 - Summary of End-Point Analytical Results
Sample No. NYSDEC
Unrestricted Use SCO
PE-A1 PE-A2 PE-A3 PE-B1 PE-B2 PE-B3 PE-C1 PE-C2 PE-C3
Sample Date mg/kg 11/10/16 11/10/16 11/10/16 10/20/15 10/20/15 11/10/15 10/20/15 10/20/15 11/10/15
Sample Depth -- 10 ft 10 ft 10 ft 14 ft 14 ft 14 ft 14 ft 14 ft 14 ft
Antimony - ND ND ND ND ND ND ND ND ND
Arsenic 13 1.5(J) 2.6(J) 2.8 1.2(J) ND 1.4(J) 1.1(J) ND 2.5(J)
Barium 350 41.2 53.5 82.0 44.3 26.6(J) 32.2(J) 36.1 31.1(J) 40.5(J)
Beryllium 7.2 ND 0.40 0.45 ND 0.33(J) ND 0.35 0.34 ND
Cadmium 2.5 ND ND ND ND ND ND ND ND ND
Calcium - 1450 1370 602(J) 1090 671(J) 732(J) 2350 1210 2100
Chromium 30 14.0 16.8 15.7 17.9 10.9 8.2 13.1 12.1 12.2
Cobalt - 6.0(J) 6.1(J) 9.4 6.5(J) 3.9(J) 3.1(J) 5.3(J) 4.1(J) 5.3(J)
Copper 50 13.9 15.6 16.0 11.3 7.9 7.2 11.3 10.6 14.1
Iron - 16300 20000 16800 20200 14700 10600 20200 19900 16200
Lead 63 35.3 63.1 26.8 8.1 5.6 7.8 14.4 8.8 40.7
Magnesium - 2080 2120 2280 2510 1610 1340 2560 1810 1980
Manganese 1600 328 365 451 350 232 197 376 386 306
Nickel 30 13.4 14.3 17.4 15.1 9.4 8.3 12.6 10.8 11.4
Potassium - 888 1060 1030 1290 974 888(J) 961 781(J) 926(J)
Selenium 3.9 ND ND ND 1.2(J) ND ND ND ND ND
Silver 2 ND ND ND ND ND ND ND ND ND
Sodium - ND ND ND ND ND ND ND ND ND
Thallium - ND ND ND ND ND ND ND ND ND
Tin - 1.4(J) 2.3(J) ND ND 1.3(J) 1.4(J) 1.4(J) 1.3(J) 2.0(J)
Vanadium - 18.8 21.8 20.9 23.7 15.8 11.6 18.8 18.6 18.2
Zinc 109 41.0 46.5 36.4 42.1 24.1 21.4 36.4 29.0 36.9
Mercury (Mercury by 7471B, mg/kg)
Mercury 0.18 0.13 0.27 0.036 0.024 ND 0.028 0.015(J) ND 0.081
Cyanide (Cyanide by 9012B, mg/kg)
Cyanide, Total 27 0.041(J) 0.044(J) 0.050(J) ND 0.019(J) 0.024(J) ND ND 0.035(J)
Notes
ND – Not Detected
J – Estimated Concentration Below the Detection Limit
Table 1A - Summary of End-Point Analytical Results
Sample No. NYSDEC
Unrestricted Use SCO
PE-A1*
Sample Date mg/kg 12/7/16
Sample Depth -- 10 ft
Pesticides (Pesticides by 8081B, mg/kg)
4,4'-DDD 0.0033 ND
4,4'-DDE 0.0033 ND
4,4'-DDT 0.0033 ND
Aldrin 0.005 ND
alpha-BHC 0.02 ND
beta-BHC 0.036 ND
Chlordane 0.094 ND
delta-BHC 0.04 ND
Dieldrin 0.005 ND
Endosulfan I 2.4 ND
Endosulfan II 2.4 ND
Endosulfan sulfate 2.4 ND
Endrin 0.014 ND
Endrin aldehyde - ND
Endrin ketone - ND
gamma-BHC (Lindane) 0.1 ND
Heptachlor 0.042 ND
Heptachlor epoxide - ND
Methoxychlor - ND
Toxaphene - ND
Sample No. NYSDEC
Unrestricted Use SCO
PE-A2*
Sample Date mg/kg 12/7/16
Sample Depth -- 10 ft
TAL Metals (Metals by 6010C, mg/kg)
Aluminum - 2300
Antimony - ND
Arsenic 13 ND
Barium 350 21.1(J)
Beryllium 7.2 ND
Cadmium 2.5 ND
Calcium - 2670
Chromium 30 7.5
Cobalt - 5.0(J)
Copper 50 17.1
Iron - 12000
Lead 63 6.4
Magnesium - 1270
Manganese 1600 175
Nickel 30 10.5
Potassium - 586(J)
Selenium 3.9 ND
Silver 2 ND
Sodium - 65.0(J)
Thallium - ND
Tin - 1.8(J)
Vanadium - 12.1
Zinc 109 24.9
Mercury (Mercury by 7471B, mg/kg)
Mercury 0.18 ND
Table 2 - List of SCOs
Metals Pesticides/PCBs
Arsenic 13 2,4,5-TP Acid (Silvex) 3.8
Barium 350 4,4'-DDE 0.0033
Beryllium 7.2 4,4'-DDT 0.0033
Cadmium 2.5 4,4'-DDD 0.0033
Chromium, hexavalent 1 Aldrin 0.005
Chromium, trivalent 30 alpha-BHC 0.02
Copper 50 beta-BHC 0.036
Total Cyanide 27 Chlordane (alpha) 0.094
Lead 63 delta-BHC 0.04
Manganese 1,600 Dibenzofuran 7
Total Mercury 0.18 Dieldrin 0.005
Nickel 30 Endosulfan I 2.4
Selenium 3.9 Endosulfan II 2.4
Silver 2 Endosulfan sulfate 2.4
Zinc 109 Endrin 0.014
Heptachlor 0.042
Lindane 0.1
Volatile Organic Compounds (VOCs) Polychlorinated biphenyls 0.1
1,1,1-Trichloroethane 0.68
1,1-Dichloroethane 0.27
1,1-Dichloroethene 0.33 Semi-Volatile Organic Compounds (SVOCs)
1,2-Dichlorobenzene 1.1 Acenaphthene 20
1,2-Dichloroethane 0.02 Acenapthylene 100
cis-1,2-Dichloroethene 0.25 Anthracene 100
trans-1,2-Dichloroethene 0.19 Benz(a)anthracene 1
1,3-Dichlorobenzene 2.4 Benzo(a)pyrene 1
1,4-Dichlorobenzene 1.9 Benzo(b)fluoranthene 1
1,4-Dioxane 0.1 Benzo(g,h,i)perylene 100
Acetone 0.05 Benzo(k)fluoranthene 0.8
Benzene 0.06 Chrysene 1
n-Butylbenzene 12 Dibenz(a,h)anthracene 0.33
Carbon tetrachloride 0.76 Fluoranthene 100
Chlorobenzene 1.1 Fluorene 30
Chloroform 0.37 Indeno(1,2,3-cd)pyrene 0.5
Ethylbenzene 1 m-Cresol 0.33
Hexachlorobenzene 0.33 Naphthalene 12
Methyl ethyl ketone 0.12 o-Cresol 0.33
MTBE 0.93 p-Cresol 0.33
Methylene chloride 0.05 Pentachlorophenol 0.8
n-Propylbenzene 3.9 Phenanthrene 100
sec-Butylbenzene 11 Phenol 0.33
tert-Butylbenzene 5.9 Pyrene 100
Tetrachloroethene 1.3
Toluene 0.7
Trichloroethene 0.47
1,2,4-Trimethylbenzene 3.6
1,3,5- Trimethylbenzene 8.4
Vinyl chloride 0.02
Xylene (mixed) 0.26
Table 3 - Disposal Quantities and Disposal Facilities
Disposal Location/Address
Date Number of
Trucks Estimated
Quantity (cyds) Manifest
Quantify (tons)
Coplay Aggregates 5101 West Coplay Road
Whitehall, PA
(Non-Hazardous Historic Fill)
August 26, 2015 14 260 392.40
September 2, 2015 5 100 141.69
September 16, 2015 11 220 338.32
September 17, 2015 13 260 374.18
September 21, 2015 10 200 289.37
September 22, 2015 11 220 326.24
October 8, 2015 4 80 122.73
October 9, 2015 4 80 130.11
October 12, 2015 4 80 118.62
October 13, 2015 5 100 157.63
October 15, 2015 4 80 116.02
October 16, 2015 4 80 113.78
October 19, 2015 3 60 91.92
October 22, 2015 3 60 87.70
October 23, 2015 4 80 114.13
October 30, 2015 1 20 20.46
Coplay Aggregates Totals -- 100 trucks 1,980 cyds 2,935.30 tons
Disposal Location/Address
Date Number of
Trucks Estimated
Quantity (cyds) Manifest
Quantity (tons)
Vanbro Corporation 1900 South Avenue Staten Island, NY
(Clean Native Soil)
October 6, 2015 6 120 183.95
October 7, 2015 9 180 276.51
October 15, 2015 4 80 119.19
October 16, 2015 4 80 124.29
October 19, 2015 9 180 273.81
October 29, 2015 4 80 129.79
October 30, 2015 6 120 188.21
November 9, 2015 3 60 86.40
November 10, 2015 8 180 240.86
November 16, 2015 8 160 233.06
Vanbro Corporation Totals -- 61 trucks 1,240 cyds 1,856.07 tons
Disposal Location/Address
Date Number of
Trucks Estimated
Quantity (cyds) Manifest
Quantity (cyds)
Con-Strux 702 Grand Blvd. Westbury, NY
(Clean Native Soil)
November 3, 2016 1 20 11
November 4, 2016 1 22 16
November 8, 2016 2 55 34
November 9, 2016 7 60 96
November 14, 2016 1 -- 18
November 26, 2016 1 -- 16
Con-Strux Totals -- 13 trucks 157 cyds 191 cyds
Table 4 - Backfill Quantities and Sources
Source Location/Address
Material Description
Date Number of Loads Estimated
Quantity (cyds)
Con-Strux 702 Grand Blvd. Westbury, NY
Recycled Concrete Aggregate (RCA)
November 10, 2016 1 16
November 11, 2016 1 16
-- -- --
-- -- --
Con-Strux RCA Totals -- 2 loads 32 cyds
Source Location/Address
Material Description
Date Number of Loads Estimated
Quantity (cyds)
Con-Strux 702 Grand Blvd. Westbury, NY
Natural Crushed Stone
December 8, 2016 1 7
-- -- --
-- -- --
-- -- --
Con-Strux Crushed Stone Totals -- 1 load 7 cyds
Source Location/Address
Material Description
Date Number of Bags Estimated
Quantity (tons)
GC Warehouse LLC 515 South 4th Avenue
Mt. Vernon, NY
Natural 3/4” Crushed Blue
Stone
March 22, 2017 400 10
March 28, 2017 500 12.5
April 7, 2017 500 12.5
-- -- --
GC Crushed Stone Totals -- 1,400 bags 35 tons
Source Location/Address
Material Description
Date Number of Loads Estimated
Quantity (tons)
Diamond Sand & Gravel 33 Demarest Road
Sparta, NJ
Quarry Mason Sand
March 29, 2017 1 23.66
March 31, 2017 1 25.56
April 4, 2017 1 23.85
April 6, 2017 1 22.84
Diamond Quarry Sand Totals -- 4 loads 95.91 tons