Release User Group Agenda January 6th, 2015 10:00 a.m.–11:00 a.m. (Pacific Time)
Web Conference Information Conference Call Information
URL: https://www.connectmeeting.att.com
Meeting Number: 8665282256
Access Code: 5251941
Domestic Call In: (866) 528-2256
International Call In: (216) 706-7052
Access Code: 5251941
Page 2
Release User Group Agenda January 6th, 2015 10:00 a.m. – 11:00 a.m. (Pacific Time)
Time Topic Facilitator
10:00 – 10:05 Agenda & ISO Roll call Janet Morris
10:05 – 11:00 Release Plan Adrian Chiosea
Jeremy Malekos
John Huetter
Roxann Hall
Kelly Alga
John Williams
Christopher McIntosh
Eureka Cullado
Indu Nambiar
LuAnn Rivera
Yinka Ajede
Elli Johnston
Raja Iyengar
Early 2015 Deployments
• February 3, 2015
• Outage Management System Replacement (OMS)
– Tariff section 9 changes effective
• Many to Many: SCP Availability Calculations
• Independent efforts
• Flexible Resource Adequacy Criteria and Must Offer Obligation (FRAC-MOO)
• Commitment Costs Enhancements
• Enabling Demand Response
• Pay for Performance Year 1 design changes
Page 3
Release Plan – 2015 • Spring 2015 – Maintenance Release
• No major functional changes
• Enhancements or other changes required for summer operations
• Minor design changes resulting from the Fall 2014 release
• Other system maintenance as needed
• Many to Many Substitution/App Consolidation
• Convergence Bidding at the Interties
• Circular Scheduling removed (manual process remains)
• Fall 2015 (tentative)
• Energy Imbalance Market (EIM) 2015 / EIM Year 1 Enhancements
• Contingency Modeling Enhancements
• RIMS functional enhancements
• OMAR replacement project
• ADS User Interface Replacement and Web Service Standardization
• Capacity Procurement Mechanism Replacement
• Reliability Services Initiative - tentative based on policy phase
• Flexible Ramping Product – tentative based on policy phase
• Subject to further release planning:
• Expanding Metering and Telemetry Options Phase 2
• BAL-003 Compliance (Frequency Response) – moved to Fall 2016
• Load Granularity Refinements
• Pricing enhancements
• Subset of Hours (to follow Reliability Service Initiative)
• Acceptable Use Policy - Analyzing to identify next services to enforce
Page 4
The ISO offers comprehensive training programs
Date Training
January 15 Welcome to the ISO (webinar)
February 10 Introduction to ISO Markets (in person)
February 11, 12 ISO Market Transactions (in person)
March 17 Settlements 101 (in person)
March 18 Settlements 201 (in person)
Page 5
Training calendar - http://www.caiso.com/participate/Pages/Training/default.aspx
Contact us - [email protected]
2015 Release Schedule
http://www.caiso.com/Documents/ReleaseSchedule.pdf Page 6
Market Simulation Plans
ISO is hosting twice weekly Market Simulation calls, presentations can be found
here -
http://www.caiso.com/Pages/documentsbygroup.aspx?GroupID=D0DE8446-
C30C-46CE-80B9-6413B6381B64
January OASIS Release
• OASIS Technical documentation -
http://www.caiso.com/Pages/documentsbygroup.aspx?G
roupID=A177DAEA-91F8-41ED-A85F-B49BE3392393
Page 8
Market GUI Report Name API Single Zip Query API Group Zip Query
Major Version=3 Minor Version=v20150101
Day-Ahead Scheduling Point/Tie Combination Locational
Marginal Prices PRC_SPTIE_LMP DAM_SPTIE_LMP_GRP
Fifteen-Minute
(RTPD/15-minute) FMM Scheduling Point/Tie Combination
Locational Marginal Prices PRC_SPTIE_LMP RTPD_SPTIE_LMP_GRP
Real-Time Dispatch
(RTD/5-minute) Interval Scheduling Point/Tie Combination
Locational Marginal Prices PRC_SPTIE_LMP RTD_SPTIE_LMP_GRP
Real-Time Contingency
Dispatch
Contingency Dispatch Scheduling Point/Tie
Combination Locational Marginal Prices PRC_CD_SPTIE_LMP n/a
The scheduling point/tie combination LMPs are related to the fall release 2014 Full Network Model expansion initiative.
Fall 2014 – Outage Management System (OMS)
Milestone Details/Date Status
Application Software Changes
OMS: New OMS replaces SLLIC and current OMS (transmission) with a
single outage management system. Application Programming Interfaces
(APIs) will be modified to support new data structures and functionality, and a
new user interface will be provided.
BPM Changes
Managing Full Network Model
Market Instruments
Outage Management
Market Operations
Draft Final Proposal Posted December 3, 2013
Conduct Stakeholder Call December 17, 2013 (pushed from December 10)
Stakeholder Comments due December 23, 2013 (pushed from December 17)
Present to Board of Governors February 6, 2014
External Business Requirements - Draft Posted June 28, 2013
External Business Rules Posted February 26, 2014
Reposted Redlined Version December 26, 2015
External Business Requirements - Final
http://www.caiso.com/Documents/ExternalBusinessRequire
mentsSpecification-OutageManagementSystem-
Replacement.pdf
Page 9
Fall 2014 – Outage Management System (OMS) Milestone Details/Date Status
Technical Specifications
Generation - January 8, 2014
Transmission - January 27, 2014
Other - February 10, 2014
Publish updates - April 9, 2014
Master File (Gen RDT) - May 24, 2014
Publish final updates for Sandbox API testing – May 30, 2014
Publish alternative Doc Attach WSDLs – August 5, 2014
Updates per Market simulation feedback – September 5, 2014
Developer Customer Partnership Group (CPG) Generation: January 21, 2014
Transmission: February 19, 2014
Business CPG
Generation : March 11, 2014
Transmission : March 12, 2014
Joint : March 26, 2014
Cutover CPG August 14, 2014
October 9, 2014
Business Process Changes Manage Generation Outages; Manage Transmission Outages
Updated BPMs September 2014 - PRR Process Ongoing
Sandbox Available for B2B service connectivity testing July 7, 2014
Market Simulation API - July 28, 2014; UI - August 5, 2014
Full System – August 5, 2014 – January 30, 2015
Tariff
File Tariff: July 7, 2014
Tariff Approval: September 5, 2014
Tariff Effective Date Confirmed for February 3 – February 28, 2015
Production Activation
October 1, 2014 for EIM Parallel Production
November 1, 2014 for EIM Tariff and EIM entities
February 3, 2015
Page 10
Fall 2014 – Many to Many: SCP Availability Calculations Milestone Details/Date Status
Application Software Changes
CIRA: • Enhance SCP Availability Calculations
Settlements: • Impacts based on resource availability calculation in CIRA. Current system uses point and actual values in RAAM, with
OMS there are only point values because of which the data settlements receive will be different than today.
Board Approval N/A
BPM Changes
September 16, 2014 - Reliability Requirements, PRR 776
July 29, 2014 – Settlements and Billing (related to OMS), PRR 752 (eff. 10/11/14)
November 5, 2014 – Reliability Requirements, PRR 802 (eff. 12/08/14) for 1 2
substitution for RAAM
External Business
Requirements
Many to Many: January 23, 2014 (original)
March 13, 2014 (revised)
May 16, 2014 (revised)
June 19, 2014 (revised, shows phased approach)
Application Consolidation: March 12, 2014 (original)
June 19, 2014 (revised, shows phased approach)
Market Simulation
October 20 – October 31, 2014
Structured: Scenarios posted w/timeline
Unstructured:
December 3 – December 4, 2014 (Updated)
• Structured: Rerun of Scenarios due to CIDI tickets, posted statements 12/9
File Tariff N/A -
Training August 19, 2014 – SCs for Resources, Settlements (posted RAAM User Guide on 8/5)
Production Activation February 3, 2014
Page 11
Flexible Resource Adequacy Criteria and Must-Offer Obligation (FRAC-MOO) Milestone Details/Date Status
Application Software Changes
RA System: modified to reflect the acceptance, verification and processing of
Flexible Capacity RA data via GUI, determination of Effective Flexible Capacity
(EFC) values, issuing EFC list, performing EFC test and determination of necessary
backstop procurement for FRAC system deficiencies.
Settlements and Billing: Settlement of FRAC-MOO backstop procurement for
Flexible Capacity System Deficiencies. SIBR: modify to receive Flex RA data for RUC
Board Approval March 19, 2014
BPM Changes • Reliability Requirements, Market Operations: October 10, 2014 (effective 11/6/14)
• Settlement & Billing: November 12, 2015 (effective 1/1/15)
External Business Requirements July 21, 2014
May 30, 2014
Technical Specifications N/A
Draft Configuration Guides August 8, 2014
Market Simulation • September 22 – October 3, 2014: Unstructured (posted high level timeline on 8/11)
• December 8 – 19, 2014: Structured & Unstructured for RUC Validation, Settlements
Draft Tariff submitted for comments
File Tariff May 19, 2014
August 1, 2014
Training August 19, 2014 – for LSEs, SCs: posted RA and Supply Plan template on 8/8,
CIRA User Guide posted 9/15
Production Activation • November 6, 2014 (Independent Fall Release)
• December 22, 2014 (RUC Validation only) UPDATED
Page 12
Commitment Costs Enhancements
Milestone Details/Date Status
Application Software
Changes
SIBR: Modification to SIBR rules to accommodate the change of increasing the Proxy Price cap
from 100% to 125%.
Master File: Modification to restrict Non Use-Limited resources to be on Proxy Cost only, as
they shall no longer be allowed to be on Registered Cost. Use-limited resources may use either
Registered or Proxy Cost option.
BPM Changes
Market Instruments: Updates to section C-3 to help manage gas price spikes (in the event that
the more current GPI is greater than 125% of previous day’s GPI in anyone of the ISO’s six gas
regions). A process needs to be in place to allow for revising the gas prices used in the
commitment cost calculation and bid generation in the Day Ahead market.
Business Process Changes Implement a desktop procedure for the gas price spike
Board Approval Sep 18, 2014
External Business
Requirements Oct 15, 2014
Updated BPMs Jan 31, 2014
Technical Specifications N/A
Draft Configuration Guides N/A
Market Simulation N/A
Tariff FERC Order received 12/30/2014; Goes into effect 12/31/2014
Production Activation 125% Cap and Manual Process became effective on 12/31/2014;
Switching non-use-limited resources from registered to proxy will require 3
business days for the changes, and go into effect on 1/6/2015.
Page 13
Enabling Demand Response: Enabling Demand Response
Milestone Details/Date Status
Application Software Changes A new application for DRPs to manage locations via user interface and application
programming interface (API). Application will verify UDC account number uniqueness.
BPM Changes Under review.
Business Process Changes Under review.
Board Approval N/A
External Business Requirements Sep 12th, 2014
Updated BPMs Yes, publication date being assessed.
Technical Specifications
Sep 19th, 2014– Use cases
Sep 19th 2014– Web Service Data Requirements
Oct 15th 2014 –Technical specifications with XSDs
Nov 14th 2014 – Full Technical Specifications (including wsdl’s)
Draft Configuration Guides N/A
Market Simulation Jan 20, 2015 – Jan 30, 2015 (also RDRR Scenario reruns Feb 2-6)
Tariff N/A
Production Activation TBD
Page 14
Pay for Performance Year 1 design changes
Milestone Details/Date Status
Application Software Changes
MQS:
• The monthly performance accuracy calculation will be changed from the simple
average to the weighted average with 15-minute interval instructed regulation
mileage as the weighting factor
• The minimum performance threshold will be reduced from the current 50% to
25%.
BPM Changes Yes: Market Instruments
Business Process Changes No
Board Approval 11/13/14
External Business Requirements Yes
Updated BPMs TBD
Technical Specifications N/A
Draft Configuration Guides N/A
Market Simulation N/A
Tariff Posted December 2, 2014 http://www.caiso.com/Documents/Dec2_2014_TariffAmendment_PFP_YearOneC
hanges_ER15-554-000.pdf
Production Activation January 1, 2015
Page 15
Spring 2015 – Many to Many Substitution/App Consolidation Milestone Details/Date Status
Application Software
Changes
CIRA:
• Add new functionality to process many to many substitution requests
• Enhance SCP Availability Calculations (in Fall 2014 Release)
• Provide single platform for management of resource adequacy and replacements /substitutions for
associated outages
Settlements:
• Impacts based on resource availability calculation in CIRA. Current system uses point and actual
values in RAAM, with OMS there are only point values because of which the data settlements
receive will be different than today.
Board Approval N/A
BPM Changes TBD - Reliability Requirements
External Business
Requirements
Many to Many: January 23, 2014 (original)
March 13, 2014 (revised)
May 16, 2014 (revised)
June 19, 2014 (revised, shows phased approach)
Application Consolidation: March 12, 2014 (original)
June 19, 2014 (revised, shows phased approach)
Technical Specifications TBD - CIRA
Draft Configuration Guides N/A
Market Simulation Yes - TBD
File Tariff January 2015 (tentative)
Production Activation April 1, 2015
Page 16
Spring 2015 – Convergence Bidding on the Interties
Milestone Details/Date Status
Application Software Changes This is an existing market functionality that is currently disabled. Will be reinstated in DAM
in 2015 Spring release. Impacted systems: SIBR, IFM, Settlements, and CTS.
BPM Changes Market Operations, Market Instruments, Settlements and Billing
Business Process Changes N/A
Board Approval
External Business Requirements
February 5, 2014
http://www.caiso.com/Documents/External_Business_Requirements_Sp
ecification_FERC_Order764.pdf
Updated BPMs TBD
Technical Specifications N/A
Draft Configuration Guides N/A
Market Simulation TBD
Tariff FERC Order – March 20, 2014
Production Activation May 1, 2015
Page 17
Fall 2015 – NVE EIM 2015
Milestone Details/Date Status
Application Software Changes Implementation of NV Energy as an EIM Entity
BPM Changes No changes expected
Business Process Changes No changes expected
Board Approval N/A
External Business Requirements No changes expected
Updated BPMs No changes expected
Technical Specifications No changes expected
Draft Configuration Guides No changes expected
Market Simulation
ISO to promote market network model including NVE area to non-
production system and allow NVE to connect and exchange data in
advance of Market Simulation by 5/15/15.
Start of Market Simulation on 8/7/15.
Tariff No changes expected
Production Activation Modeling NVE into the CAISO FNM through the EMS on 1/28/15
Production activation on 10/1/15.
Page 18
Fall 2015 – EIM Year 1 Enhancements
Milestone Details/Date Status
Application Software Changes
Phase 1:
• Settlement of Non-Participating Resources IIE and UIE
• GHG flag and cost based bid adder
• Use of ATC for EIM Transfers
• Resource sufficiency evaluation applied to ISO BAA
• Bidding rules on external EIM interties
• Enforcement of EIM Transfer Limits
• Administrative pricing rules
BPM Changes TBD
Business Process Changes TBD
Board Approval TBD
External Business Requirements TBD
Technical Specifications TBD
Draft Configuration Guides TBD
Market Simulation TBD
Tariff TBD
Production Activation Fall 2015
Page 19
Fall 2015 - Contingency Modeling Enhancements
Milestone Details/Date Status
Application Software Changes
IFM/RTN: Adds a preventive-corrective constraint to the market co-optimization
OASIS/CMRI: Publish preventive-corrective capacity awards with associated LMPC
Settlements: Payment and charges for corrective capacity awards, allocation of cost
of the corrective capacity constraint, no-pay provisions, bid cost recovery
BPM Changes Manage Full Network Model, Market Operations, Market Instruments, Settlement and
Billing, Definitions and Acronyms
Study Results
In Person Call: March 20, 2014
Distribute Results: TBD
Comments Due: TBD
Board Approval Spring 2015
External Business Requirements TBD
Technical Specifications TBD
Draft Configuration Guides TBD
Market Simulation TBD
File Tariff TBD
Production Activation October 1, 2015 (Fall 2015 Release)
Page 20
Fall 2015 – RIMS Function Enhancements
Milestone Details/Date Status
Application Software Changes Functional enhancements resulting from the Customer Partnership Group CPG).
More details to be provided in the future.
BPM Changes TBD
Business Process Changes TBD
Board Approval N/A
External Business Requirements TBD
Updated BPMs TBD
Technical Specifications TBD
Draft Configuration Guides N/A
Market Simulation TBD
Tariff N/A
Production Activation Fall 2015
Page 21
Fall 2015 – OMAR Replacement Project Milestone Details/Date Status
Application Software Changes
Current metering space at the California ISO consists of three major software
systems –
1. A product that processes Revenue Quality Meter Data (RQMD) in to Settlement
Quality Meter Data (SQMD)
2. A data repository of all SQMD used in Settlements
3. An external facing web application to enable market participant access to
SQMD.
The scope of the project is to replace/consolidate all the three above systems with
a New Metering Solution
BPM Changes Metering and Definitions & Acronyms (references to systems may need to change)
Business Process Changes Potential Level-II business process changes under –
• Manage Market & Reliability Data & Modeling
• Manage Operations Support & Settlements
Board Approval Potentially needed – Dates TBD
External Business Requirements N/A
Technical Specifications TBD
Draft Configuration Guides N/A
Market Simulation TBD
Tariff N/A
Production Activation Fall 2015
Page 22
Fall 2015 – ADS UI Replacement and Web Service Standardization
Milestone Details/Date Status
Application Software Changes • Port client from Delphi to new common user interface (ADS Query Tool and
Real Time Functionality)
• Conform APIs to current ISO standards
BPM Changes N/A
Business Process Changes N/A
Board Approval N/A
External Business Requirements N/A
Updated BPMs N/A
Technical Specifications TBD
Draft Configuration Guides N/A
Market Simulation TBD
Tariff N/A
Production Activation Fall 2015
Page 23
Fall 2015 – Capacity Procurement Mechanism Replacement
Milestone Details/Date Status
Application Software Changes The following systems could be impacted based on the below scope: Settlements,
CIRA, and SIBR
BPM Changes Reliability Requirements; Market Operations; Market Instruments; Billing &
Settlements
Business Process Changes TBD
Board Approval Q1 2015
External Business Requirements TBD
Updated BPMs TBD
Technical Specifications TBD
Draft Configuration Guides TBD
Market Simulation Yes
Tariff Yes
Production Activation TBD
Page 24
Fall 2015 – Reliability Services Initiative
Milestone Details/Date Status
Application Software Changes
The following systems could be impacted based on the below scope: CIRA, Settlements,
SIBR, Exceptional Dispatch Tool (internal ISO Operations tool), and Master File.
• Updates to the eligibility criteria for demand response to qualify as a Resource Adequacy
(RA) resources
• Language on the eligibility criteria and must-offer requirement for storage to qualify as a
RA resource
• Replacement and substitution rules for flexible RA resources
• New price and rules for the SCP for all RA resources including flexible resources
• New CPM price
BPM Changes Reliability Requirements; Market Operations; Market Instruments; Billing &
Settlements
Business Process Changes TBD
Board Approval Q1 2015
External Business Requirements TBD
Updated BPMs TBD
Technical Specifications TBD
Draft Configuration Guides TBD
Market Simulation Yes
Tariff Yes
Production Activation TBD
Page 25
Fall 2015 – Flexible Ramping Product
Milestone Details/Date Status
Application Software Changes
ADS: Send Flexible Ramping Up/Down Awards to Market Participants in DAM for CAISO and
FMM for CAISO and EIM.
CMRI : Report Flex Ramp Up/Down Awards to Market Participants.
DAM/RTM: Co-optimize Energy Ancillary Services and Flexible Ramping up/down.
OASIS: Show aggregated Flexible Ramping capacity awards, requirements and marginal prices.
Settlements: Settle Flexible Ramping payment at marginal price in Day Ahead and Real Time
markets. Add no pay and cost allocation for Flexible Ramping.
SIBR: Include Flexible Ramping bidding capability and relevant validation rules of bid cap, self
provision.
BPM Changes Market Operations; Market Instruments; Settlements & Billing; Definitions & Acronyms.
Business Process Changes Maintain Day Ahead Process, Real Time Process, Manage Billing and Settlements
Board Approval
February 2015
Restart Stakeholder Process in May, 2014
http://www.caiso.com/informed/Pages/StakeholderProcesses/FlexibleRampingProduc
t.aspx
External Business Requirements TBD
Technical Specifications TBD; 4/14/2014: Change the FRC penalty price from $247 to $60 in FMM
Draft Configuration Guides TBD
Market Simulation TBD
Tariff
Yes;
The language proposes to change the flexible ramping constraint penalty price from
$247 to $60. The draft tariff language is available on the ISO website at
http://www.caiso.com/Documents/DraftTariffLanguage_FlexibleRampingProduct.doc
Production Activation Fall 2015
Page 26
TBD – Expanding Metering and Telemetry Options Phase 2
Milestone Details/Date Status
Application Software Changes
No ISO Application Software Changes. POC’s to test that current systems support
the proposals.
Proposal 1 - Use of Internet for Telemetry and ISOME Meter Data bridging to the
CAISO Energy Communication Network (ECN); Proposal 2 - Use of Internet for
Telemetry (with SSL) and Meter Data (w/o SSL) transport directly to the CAISO;
Proposal 3 - Expand the use of Inter-Control Center Communications Protocol
(ICCP) as an allowable option for RIG Aggregators (telemetry only); Proposal 4 -
Expand the ability for resources to submit Settlement Quality Meter Data;
Proposal 5 - Remove RIG Aggregator resource ownership and location limitations.
BPM Changes Metering, Direct Telemetry
Business Process Changes TBD
Board Approval TBD
External Business Requirements TBD
Updated BPMs TBD
Technical Specifications TBD
Draft Configuration Guides N/A
Market Simulation N/A
Tariff TBD
Production Activation TBD
Page 27
TBD – Load Granularity Refinements
Milestone Details/Date Status
Application Software Changes
Alternatives: • Existing DLAPs;
• Full Nodal;
• Slight Disaggregation- Assuming 6 LAPs;
• 23 Existing SLAPs;
• Custom LSE-Specific LAPs
BPM Changes TBD
Business Process Changes TBD
Board Approval TBD
External Business Requirements TBD
Updated BPMs TBD
Technical Specifications TBD
Draft Configuration Guides TBD
Market Simulation TBD
Tariff TBD
Production Activation TBD
Page 28
Fall 2016 – BAL-003 Compliance
Milestone Details/Date Status
Application Software Changes
On January 16, 2014, FERC approved BAL-003-1 “Frequency Response and
Frequency Bias Setting,” with different implementation dates for different
requirements. R1 goes into effect the first calendar day of the first calendar quarter
24 months after regulatory approval.
http://www.gpo.gov/fdsys/pkg/FR-2014-01-23/pdf/2014-01218.pdf
4/1/16: RI effective date
12/1/16: 2017 BA FRO in place (start data collection)
4/1/18: Compliance effective date (supply data to NERC) (UPDATED)
BPM Changes TBD
Business Process Changes TBD
Board Approval TBD
External Business Requirements TBD
Technical Specifications TBD
Draft Configuration Guides TBD
Market Simulation TBD
Tariff TBD
Production Activation Fall 2016 (UPDATED)