reinforcement failure
TRANSCRIPT
-
7/28/2019 Reinforcement Failure
1/47
REINFORCING DETAILING
OF R.C.C MEMBERS
-
7/28/2019 Reinforcement Failure
2/47
WHO IS AN ENGINEER?
According to USA President Herbert Hoover, who
was an engineer before he became a politician, said:The great liability of the engineer compared to menof other professionsis that his works are out inthe open where all can see them.
His acts ..step by step are in hard substances.
He cannot bury his mistakes in the grave like theDOCTORS.
He cannot argue them into thin air..or blame thejudge..like the LAWYERS.
He cannot, like the ARCHITECT, cover his figures
with trees and vines.He cannot, like the politicians, screen hisshortcomings by blaming his opponents.and hopethe people will forget. The ENGINEER simply cannotdeny he did it.
If his works do not workhe is damned.
-
7/28/2019 Reinforcement Failure
3/47
A design engineers responsibility should includeassuring the structural safety of the design,details, checking shop drawing.
Detailing is as important as design since properdetailing of engineering designs is an essentiallink in the planning and engineering process assome of the most devasting collapses in historyhave been caused by defective connections or
DETAILING. There are many examples explainedin the book" DESIGN AND CONSTRUCTIONFAILURES by Dov Kaminetzky.
Detailing is very important not only for theproper execution of the structures but for the
safety of the structures.Detailing is necessary not only for the steelstructures but also for the RCC members as it isthe translation of all the mathematicalexpressions and equations results.
-
7/28/2019 Reinforcement Failure
4/47
For the RCC members for most commonly used for buildings we candivide the detailing for
1. SLABS-WITH OR WITHOUT OPENINGS.(RECTANGULAR,CIRCULAR,NON-RECTANGULAR-PYRAMID SLAB,TRIANGULAR ETC)
-BALCONY SLAB,LOFT SLAB,CORNER SLAB etc
2. BEAMS- WITH OR WITHOUT OPENIGS.(SHALLOW & DEEP BEAMS)
3. COLUMNS.(RECTANGULAR,L-SHAPE,T-SHAPE,CIRCULAR,OCTAGONAL,CROSS SHAPE etc)
4. FOUNDATIONS.
Detailing for gravity loads is different from the lateral loads specially forthe SEISMIC FORCES.
Apart from the detailing for the above there is a different detailingrequired for the Rehabilitation and strengthening of damaged structures.
We will now dwell on the DETAILING OF MEMBERS FOR THE GRAVITYAND SOME CODAL DETAILINGS AS PER IS CODE IS 13920 AND IS 4326AS REQUIRED FOR SEISMIC FORCES.
-
7/28/2019 Reinforcement Failure
5/47
DOS & DONOTS FOR DETAILING
DOS-GENERAL
1. Prepare drawings properly & accurately if possible label each bar
and show its shape for clarity.
12
I dia@12c/c
Cross section of retaining wall which collapsed immediately after placing of soil
backfill because rather than 1-1/4 dia. were used. Error occurred because
Correct rebar dia. Was covered by a dimension line.
1- dia@12c/c
-
7/28/2019 Reinforcement Failure
6/47
2. Prepare bar-bending schedule , if necessary.
3. Indicate proper cover-clear cover, nominal cover
or effective cover to reinforcement.4. Decide detailed location of opening/hole and
supply adequate details for reinforcementsaround the openings.
5. Use commonly available size of bars and spirals.
For a single structural member the number ofdifferent sizes of bars shall be kept minimum.
6. The grade of the steel shall be clearly stated inthe drawing.
7. Deformed bars need not have hooks at their
ends.8. Show enlarged details at corners, intersections
of walls, beams and column joint and at similarsituations.
-
7/28/2019 Reinforcement Failure
7/47
9. Congestion of bars should be avoided at points where
members intersect and make certain that all rein. Can be
properly placed.
10. In the case of bundled bars, lapped splice of bundled barsshall be made by splicing one bar at a time; such
individual splices within the bundle shall be staggered.
11. Make sure that hooked and bent up bars can be placed
and have adequate concrete protection.
-
7/28/2019 Reinforcement Failure
8/47
12. Indicate all expansion, construction and contraction joints
on plans and provide details for such joints.
13. The location of construction joints shall be at the point of
minimum shear approximately at mid or near the mid points.
It shall be formed vertically and not in a sloped manner.
DOS BEAMS & SLABS:
1. Where splices are provided in bars, they shall be , as far as
possible, away from the sections of maximum stresses and
shall be staggered.
2. Were the depth of beams exceeds 750mm in case of beamswithout torsion and 450mm with torsion provide face rein.
as per IS456-2000.
3. Deflection in slabs/beams may be reduced by providing
compression reinforcement.
4. Only closed stirrups shall be used for transverse rein. Formembers subjected to torsion and for members likely to be
subjected to reversal of stresses as in Seismic forces.
-
7/28/2019 Reinforcement Failure
9/47
5. To accommodate bottom bars, it is good practice to makesecondary beams shallower than main beams, at least by50mm.
Dos COLUMNS.1. A reinforced column shall have at least six bars of
longitudinal reinforcement for using in transverse helicalreinforcement.-for CIRCULAR sections.
2. A min four bars one at each corner of the column in thecase of rectangular sections.
3. Keep outer dimensions of column constant, as far aspossible , for reuse of forms.
4. Preferably avoid use of 2 grades of vertical bars in thesame element.
DONOTS-GENERAL:
1. Reinforcement shall not extend across an expansion jointand the break between the sections shall be complete.
2. Flexural reinforcement preferably shall not be terminatedin a tension zone.
-
7/28/2019 Reinforcement Failure
10/47
3. Bars larger than 36mm dia. Shall not be bundled.
4. Lap splices shall be not be used for bars larger than
36mm dia. Except where welded.
5. Where dowels are provided, their diameter shall notexceed the diameter of the column bars by more than
3mm.
6. Where bent up bars are provided, their contribution
towards shear resistance shall not be more than 50% of
the total shear to be resisted. USE OF SINGEL BENT UPBARS(CRANKED) ARE NOT ALLOWED IN THE CASE
OF EARTHQUAKE RESISTANCE STRUCTURES.
-
7/28/2019 Reinforcement Failure
11/47
DETAILING OF SLABS WITHOUT ANY CUT
OR OPENINGS.
The building plan DX-3 shows theslabs in different levels for the
purpose of eliminating the inflow of
rainwater into the room from the openterrace and also the sunken slab for
toilet in first floor.
The building plan DX-A3 is one inwhich the client asked the architect to
provide opening all round.Refer the 3d
elevation
-
7/28/2019 Reinforcement Failure
12/47
Different shapes of slabs used in the
buildings. 6depression for OT &9 for sunken slabs.
Portico slab in elevation
19-6
9-6suareopening
5wide corridor all
round
Portico and other rooms
roof slab in plan
Portico slab in plan
-
7/28/2019 Reinforcement Failure
13/47
Minimum and max.reinforcement % in beams, slabs and
columns as per codal provisions should be followed.
SLABS:
It is better to provide a max spacing of 200mm(8) for main
bars and 250mm(10) in order to control the crack width and
spacing.
A min. of 0.24% shall be used for the roof slabs since it is
subjected to higher temperature. Variations than the floor
slabs. This is required to take care of temp. differences.
It is advisable to not to use 6mm bars as main bars as this
size available in the local market is of inferior not only with
respect to size but also the quality since like TATA and SAIL
are not producing this size of bar.
BEAMS:
A min. of 0.2% is to be provided for the compression bars in
order to take care of the deflection.
-
7/28/2019 Reinforcement Failure
14/47
The stirrups shall be min.size of
8mm in the case of lateral load
resistance .The hooks shall be bent to 135
degree .
-
7/28/2019 Reinforcement Failure
15/47
Ld/2Ld/2
Ld
crack
INCORRECT
CORRECT
CLOSE
STIRRUPS
Ldt
Ldt/2
CANTILEVER BEAM
-
7/28/2019 Reinforcement Failure
16/47
NON PRISMATIC BEAM
Ld/2 Ld/2Ld
INCORRECT
CORRECT
CLOSE
STIRRUPS
crack
Ldt/2
Ldt
GRID BEAM
-
7/28/2019 Reinforcement Failure
17/47
GRID BEAMGRID BEAM
INCORRECT
1.5d1.5d1.5d
Close rings
Hanger bars
Slope 1:10
2#extra bars
300300
d
CORRECT
-
7/28/2019 Reinforcement Failure
18/47
Details of Main & Secondary beams
INCORRECT
1.5d1.5d1.5d
Close rings
Hanger bars
300300
d
CORRECT
Secondary beam
Main beam
Secondary beam
60degree
Main beam
-
7/28/2019 Reinforcement Failure
19/47
d
1/4OR
1/5 SPAN
1.5d
CORRECT
INCORRECT
d/2+d/2Cot(t)
tt
Ld
d/2
d/2
Ld
LINE OF CRACK
BEAM
-
7/28/2019 Reinforcement Failure
20/47
Continuous beam
continuous beamSpan/4
Span/4Span/4
Span/4
incorrect
Span/4
Span/4
1.5d1.5d
Span/4
correct
1.5d
-
7/28/2019 Reinforcement Failure
21/47
100%
L1
100% CRACKCRACK
.08L2.08L1 L2
SPAN/4 SPAN/4
CONTINUOUS BEAM
INCORRECT
.08L1
.08L1
SPAN/4
CRACK
100%
L1
100%
.15L2 L2
L1/4 L2/4
CORRECT
0.1L1
.15L1
L1/4100%
20%20%
-
7/28/2019 Reinforcement Failure
22/47
D
D
CRACK
INCORRECT
NONPRISMATIC
SECTION OF BEAM
D
D
DCORRECT
D
CLOSE RING
CLOSE RING
-
7/28/2019 Reinforcement Failure
23/47
COLUMN
INCORRECT
CANTILEVER BEAM PROJECTING
FROM COLUMN
CORRECT
NOT LESS THAN GREATER OF 0.5L OR Ld50mm
0.25Ast
NOT LESS
THAN 0.5Ast
COLUMN
Ld
Ld/3
-
7/28/2019 Reinforcement Failure
24/47
CRACK
SLOPING BEAM
CORRECT
Ld
Ld
-
7/28/2019 Reinforcement Failure
25/47
CRACKCRACK
INCORRECT
HAUNCH BEAMS
CORRECTL/8 TO
L/10 L/8 TO
L/10
L
L
Ld Ld
Ld Ld
-
7/28/2019 Reinforcement Failure
26/47
STRESSES AT CORNERS
C
C-COMPRESSION
T-TENSION
t
t
C
RESULTANT TENSILE STRESS FOR
ACROSS CORNER(ONE PLANE)
t
c
RESULTANT TENSILE STRESS FOR
ACROSS CORNER(DIFFERENT PLANE)t
c
CRACK
CRACK
-
7/28/2019 Reinforcement Failure
27/47
SHEAR AND TORSION REIN. IN
BEAMS
INCORRECT
Min 0.2%bd to control deflection as
well as for seismic requ.
b
D100 to
200mm
d
D-n>500mm
D/5
Skin rein.10dia is
required when depth
exceeds 450mm(0.1%of web area distributed
equally on two faces)
Stirrups taken round outermost
bars spacing
-
7/28/2019 Reinforcement Failure
28/47
CANTILEVER BEAM WITH
POINT LOAD
CORRECT
INCORRECT
2/3dd
Shear rein.
Extra ties
Ld
Ld
-
7/28/2019 Reinforcement Failure
29/47
opening
CORRECT
OPENING IN WEB OF BEAM
crackcrack
opening
INCORRECT
OPENING IN WEB OF BEAM
Ld
d/2 d/2
Closed stps
for d/2Closed stps
for d/2
-
7/28/2019 Reinforcement Failure
30/47
BEAM COLUMN JUNCTION-EXTERIOR COLUMN
CORRECT
INCORRECT
CLOSED STPS2max
IN TENSION-Ld
U TYPE BARS
Ld
-
7/28/2019 Reinforcement Failure
31/47
CORRECT
SPLICE DETAIL FOR COLUMN
INCORRECT
COVER
CLOSE
TIES @S/2
S-SPACING
SLOPE 1:6
-
7/28/2019 Reinforcement Failure
32/47
REDUCTION
COLUMN BOTH
SIDES
INCORRECT
CORRECT
3NO.CLOSE TIES
SPLICE
CLOSE STPS SPACIN
-
7/28/2019 Reinforcement Failure
33/47
TERMINATION OF COLUMN BARS INSIDE BEAM
INCORRECT
CORRECT
Ld
-
7/28/2019 Reinforcement Failure
34/47
BEAM COL. JUNCTION-EQ
REGION
EQREGION-BEAM-COL JN-EXTERIOR
CORRECT
BEAM COL. JUNCTION-EQ
REGION
INCORRECT
END REGION
END REGION
COL.
CORE*
SPACING OF
LATERAL
TIES
-
7/28/2019 Reinforcement Failure
35/47
COLUMN DETAILS IN EQ REGIONS
END
REGION
END
REGION
First stirrups
50mm from beam
face
Spacing of shear rein. In
columns
incorrect
Spacing of shear rein. Incolumns
correct
END REGION-h/6 or D or
450MM whichever is
greater
END
REGION
hd
D
b
EQ REGION CONTINUOUS BEAM
-
7/28/2019 Reinforcement Failure
36/47
EQ-REGION-CONTINUOUS BEAM
INCORRECT
Ld
A=L1/3
CONTINUOUS BARS NOT LESS THAN
AREA OF BARS AT COL.FACE
A=L1/3 A=L1/3
2d
50mmmax
Stirrup spacing=d/4 or
100mm or 8dia whichever is the least
2d2d 2dstp@maxd/2 stp@maxd/2
CORRECT
-
7/28/2019 Reinforcement Failure
37/47
INCORRECT
FOOTING-DETAILS(INDEPENDENT)
CORRECT
COVER TO
STARTER
STARTER
BARS
COLUMN
BARS
NATURAL
G.L
Ldt
Lb3 SIDE COVER
LdtCOVER50mm
IF p.c.c below
or 75mm
Min.300
TYPICAL REIN DETAILS OF
-
7/28/2019 Reinforcement Failure
38/47
TYPICAL REIN DETAILS OF
HAMMER FOUNDATION BLOCKINCORRECT
CORRECT
Ld
Ld
-
7/28/2019 Reinforcement Failure
39/47
SECTION OF TRENCH
CRACK
INCORRECTINCORRECT
CORRECT
LdLd
Ld
-
7/28/2019 Reinforcement Failure
40/47
STAIRCASE-WITH WAIST SLAB
INCORRECT
CORRECT
Ld(min)Extra bar
Ld(min)
Ld(min)
S SS S C S
-
7/28/2019 Reinforcement Failure
41/47
Main bar
Dist.
Main bar
Alternate 1
SLABLESS STAIRCASE
SLABLESS STAIRCASE
-
7/28/2019 Reinforcement Failure
42/47
Main bar
Alternate 2
A=0.25L
L=horizontal span
SLABLESS STAIRCASE
-
7/28/2019 Reinforcement Failure
43/47
DEVELOPMENT LENGTH OF BARS
SLNO BARDIA.
TENSIONmm
COMPRESSION REMARKS
1 8 376.0 301.0
2 10 470.0 376.0
3 12 564.0 451.0
4 16 752.0 602.0
5 20 940.0 752.0
6 22 1034.0 827.0
7 25 1175.0 940.0
8 28 1316.0 1053.0
9 32 1504.0 1203.0
FOR A CONCRETE GRADE M20 &STEEL STRENGTH Fy=415
APPROXIMATELY USE 50Xdia FOR TENSION
-
7/28/2019 Reinforcement Failure
44/47
CONCLUSION:
Before concluding I will show some more details drawnin autocad exported in wwf format
As there is no time to elaborately explaining ,the following topics are notcovered :
1. Flat slabs, Folded plates, shell structures-cylindrical shells, silos,
2. Staircases- helical staircase, central beam type, cantilever type etc.
3. Different types of foundations-raft, pile foundation, strap foundation etc.
4. Retaining wall structures,
5. Liquid retaining structures.
6. Deep beams.
7. Shear wall, walls.
Hope that I have enlighten some of the detailing technique for the mostcommonly encountered RCC members in buildings.
In the above statements if my senior colleagues and ACCE memberscan find different method or any new detailing system it will be of immensehelp not only for me but to other young engineers who should learn in wrightways and not wrong lessons.
REFERENCES
-
7/28/2019 Reinforcement Failure
45/47
REFERENCES:
1. HANDBOOK ON CONCRETE REINFORCEMENT ANDDETAILING-SP:34(S&T)-1987.
2. MANUAL OF ENGINEERING & PLACING DRAWINGSFOR REINFORCED CONCRETE STRUCTURES-
(ACI 315-80
3. MANUAL OF STANDARD PRACTICECONCRETEREINFORCING STEEL INSTITUTE.
4. TWARD BOARD MANUAL FOR RURAL WATERSUPPLY SCHEMES.
5. DESIGN PRINCIPLES AND DETAILING OF CONCRETESTRUCTURES. By D.S.PRAKASH RAO.
6. SIMPLIFIED DESIGN-RC BUILDINGS OF MODERATESIZE AND HEIGHT-BY PORTLAND CEMENTASSOCIATION,USA.
7. DESIGN AND CONSTRUCTION FAILURES BY DOVKAMINETZKY.
-
7/28/2019 Reinforcement Failure
46/47
8. IS:2502-1963 CODE OF PRACTICE FOR BENDING AND
FIXING OF BARS FOR CONCRETE REINFORCEMENT.
9. IS:1893:2000.
10. IS:4326.11. IS:456:2000
12. REINFORCED HAND BOOK BY REYNOLD.
-
7/28/2019 Reinforcement Failure
47/47
THANK YOU.