regulatory issues for setting up a wind power plant
TRANSCRIPT
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
1/25
INTRODUCTION
STAKE HOLDERS
RISK MITIGATION
DEVELOPMENT CONSIDERATIONS
TENDERING
CONTRACT
OWNERSHIP
FINANCE MODELS
LEGAL FRAMEWORK
INCENTIVES
WIND POWER IN INDIA
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Presented by: P R AT E E K D A S G U P TA
P R A N A V M I S H R A
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
2/25
W I N D E N E R G Y
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
India is blessed with 7517 km of coastline and
territory up to 12 nm into the sea. This iswhere lies the potential of sustained energy
growth.
India is 5th largest producer of wind energy in
the world, with 16078 MW of installed
capacity ( Dec. 2011)
658 wind monitoring stations are set up by
MNRE, of which 75 are in operation.
Tamil Nadu, Maharashtra, Gujarat, Karnataka
are leading wind energy producers in India.
Short construction period and low O&M cost
makes it an attractive proposition.
Project life is 25 years.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
3/25
STAKE H O LD ER S
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Ministry of New &
Renewable Energy
IREDA (Finance) C-WET( R&D) (State agencies)
Implementing agencies and NGOs
Manufacturer / vendors
Users or consumers
PRIMARY SECONDARY
Ministry of power
Ministry of environment and forest
Department of science and technology
Central and state regulators
Multilateral agencies
Education and research institutes
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
4/25
R I S K S A N D M I T I G A T I O N
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Risk Mitigation
Wind availability Minimum 1-2 year site specific data
Equipments Performance data, warranties
Operations and maintenance Experienced managers, maintenance
contracts
Revenue Power purchase agreements
Construction Fixed completion dates and penalties,
performance bond
Force majeure Insurance
Transmission Interconnection agreements
Tax benefit utilizations
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
5/25
D E V E L O P M E N T C O N S I D E R A T I O N S
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Choice of investment Contractual obligations
Major concerns
Type of development:
Third party wind developer
Small turbine
Commercial scale wind
project
Legal issues
Land agreements
Option to purchase
or lease
Purchase
LeaseEasement
Covenant
License
Siting
Environment
Electricity
Other permissions
Financial issues
Sources of initial project financing.
Steps in acquiring finance.Seed money to evaluate feasibility.
Equity investment for pre construction
development
Debt/equity for construction and operation.
Financial models
Business structure
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
6/25
D E V E L O P M E N T C O N S I D E R A T I O N S
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
ENERGY AND ELECTRICITY SUPPLY POLICIES
National Development policies and plan.
Implementation mechanisms for National Development plan.
National policies for the Energy and Electricity sectors. Perceptions of major constraints, priorities.
Electricity tariff policies.
Environmental Protection Policies and their impact on the energy sector.
FINANCIAL MECHANISM
Mechanisms for International Financing.
Mechanisms for Local Financing.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
7/25
T E N D E R S
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Information provided by the owner
1. INVITATION LETTER
2. ADMINISTRATIVE INSTRUCTIONS
3. GENERAL INFORMATION
4. TECHNICAL REQUIREMENTS
5. SCOPE OF SUPPLY AND SERVICES6. NATIONAL PARTICIPATION
7. BID EVALUATION CRITERIA
8. DRAFT CONTRACT TERMS AND CONDITIONS
9. COMMERCIAL CONDITIONS
10. SAFETY AND SECURITY CONSTRAINTS
Information requested from bidders
1. GENERAL INFORMATION
2. GENERAL TECHNICAL ASPECTS
3. TECHNICAL DESCRIPTIONS
4. SCOPE OF SUPPLY AND SERVICES
5. ALTERNATIVES AND OPTIONS6. QUALITY ASSURANCE PROGRAMME
7. TRAINING
8. PROJECT SCHEDULE
9. TECHNOLOGY TRANSFER
10. GUARANTEES AND WARRANTIES
11. DEVIATIONS AND EXCEPTIONS
12. COMMERCIAL CONDITIONS
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
8/25
C O N T R A C T
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Definitions
General clauses
Object of the contract
Planning and execution of the work
Information, inspection, testing and controlAssignment of the work and subcontracting
National participation and technology transfer
Training of personnel
Changes and additional work
Transport and customs clearance
Risks and transfer of titleLiability
Insurances
Quality assurance
Licensing
Delivery times
Documentation
Spare and wear parts, consumables and special
toolsGuarantees or warranties
Take-over
Prices, price adjustments and terms of payment
Force majeure
Termination and suspension of the contract
Guarantee of title and proprietary informationExecution of the contract
Applicable law
Arbitration
Contract Components
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
9/25
C H O I C E O F I N V E S T M E N T
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
A landowner has a windy site and he wants to utilize the wind, he can choose to :
Deciding factors for a landowner may be :
Their financial situation
Their comfort level with riskTime they can commit to develop the project
Degree of interest
Commercial scale production
Install small turbine for on site energy use
Negotiate with the third party to develop project on his site
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
10/25
O W N E R S H I P
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Commercial scale production
Owner may invest directly on his own or with
collaboration with others.
Power generated is sold for profit.
Expensive, time consuming and risky
endeavor.
Legal issues related to land, government lawsand liability concerns.
Financing to be secured.
Contract to sell in advance or PPA
Business structure
Access to the grid for transfer of electricity.
Install small turbine for on site energy use
Energy is used for own purposeMay cell excess electricity to grid.
Net metering
Will have to comply vast array of regulations like
land use restrictions, environmental regulations.
Negotiate with the third party
Selling or leasing their rights to someone else
who will construct and operate wind energy
power plant.
The developer will do all the work to develop,
build and operate the plant.
The owner will receive some rental or part of
revenue, as decided between them.
Less risk to land owner.
No initial capital investment required.
Land owners risk lies in carefully negotiating
legal agreements to ensure fair compensation,
allocation of rights, responsibilities and risk.
Usually, a developer approaches a land owner.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
11/25
F I N A N C I N G
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
ModelsSole ownership
If the land owner has resourcesto put the project and can
provide required equity.
Local investor ownership
Groups of individuals who
have purchased shares in the
project.
formed as LLC (Limited
Liability Corporations)
Investors are insulated from
liability and profit lossesflows through to individual
members.
Joint ventures
An outside corporate investor joins hand withlocal investors.
Entails complex legal and tax challenges.
Loan to own
Local investor group makes a loan to corporate
investor.
Local investors would earn interest only over
term of the loan.
Initially, corporate body is 100% owner and
receives all the projects income, losses and tax
benefits.
At the end of the specified period, corporate
investors sell the project to local investors at a
pre negotiated price.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
12/25
F I N A N C I N G
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
ModelsProject lease
It involves, leasing thedevelopment rights to outside
investors.
Land owners will do the pre-
development work. ( wind
monitoring, zoning, permissions,
PPA ) and contracting with project
operator.
they lease the wind rights and
assign a portion of PPA to
investors.
The investor would own the
project for pre negotiated period
and landowner would receive anegotiated royalty.
At the end of the period,
landowners have option to
purchase the project at fair market
price.
Sweat equity
It is similar to the project lease
model.
But in this model, local investors
are not retaining any ownership
stake, either upfront or later.
Rather, they receive a more
generous royalty stream.It avoids legal tax and
management issues associated
with splitting ownership interests
between corporate and local
investors.
Joint ventures
An outside corporate investor joins hand with local
investors.
Entails complex legal and tax challenges.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
13/25
F I N A N C I N G
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Sources
EQUITY
One of the greatest hurdles for
wind projects
Potential sources for equity
financing are :
Strategic investors, such as
utility companies or their
subsidiaries.
Institutional investors,
usually for large commercial
scale projects.
Corporate investors, whowants to reduce their tax
liabilities by investing in
green energy projects
DEBT
Can be a challenging and time
consuming process.
Requires developers to
complete all the pre
development work.
Potential sources of debt
financing are :
Local lenders
Regional agricultural
lenders
Commercial banksCommercial finance
Vendor financing
Most projects are structured
with 40-70 % debt.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
14/25
F I N A N C I N G
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Following information are required :
A comprehensive wind monitoring study (minimum 1 year of data) conducted at the site
A project feasibility study by a credible consultant
Proven expertise in managing a wind project or an agreement with a qualified 3rd party project
manager
Zoning and site permitting approval
Turbine performance data
Turbine warranties and operations and maintenance agreement
A completed interconnection study
A long-term power purchase agreement (at least 10 years and preferably 15 years) with a
creditworthy utility that will purchase the electricity generated at specified prices
Commitments for all required equityA business, financial and risk management plan for the project including complete proforma
financial statements
For getting a project financed
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
15/25
F I N A N C I N G
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Schematic summary of wind financing structures
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
16/25
L E G A L F R A M E W O R K
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Siting
Measuring the wind resource.Access to electric grid.
Impact on neighbors.
Environmental impacts
Wind and land agreement
Property requirements.
Property rights.
Land
Wind ( easements )
Type of agreement
Option to lease or purchaseRight to first refusal
Sale
Lease
Easement
Permit or license
Other issues to regulate are :
Duration of agreement.Compensation.
Uses of land
Taxes
Liabilities
Assignment of contract by developer.
Termination of agreement.
End of project life.Dispute resolution.
Eminent domain
Permissions
Land use
Environment ( air, water, land, wetland)
Local building and electrical codes
Permission from aviation ministry.
Historic preservation.
Statement of need
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
17/25
L E G A L F R A M E W O R K
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Electricity regulatory commissions act, 1988
The state commissions are key players for regulating the electricity sector
and including determining electricity tariffs
Electricity Act. 2003
Promotes generation of electricity from renewable energy.
Section 3 - National Electricity policy and plan including optimalutilization of renewable energy.
Section 4 national policy permitting stand alone system for those
based on renewable source of energy.
Section 61- appropriate commission while determination of tariff
shall be guided by promotion of generation and co generation of
electricity from renewable energy.
National Electricity Policy, 2005
Aims at accelerated development of power sector, providing supply of
electricity to all areas and protecting interests of consumers and other
stakeholders
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
18/25
L E G A L F R A M E W O R K
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Integrated Energy Policy, 2006
It emphasizes the use of renewable energy to reduce dependency on
energy imports
Rural Electrification Policy, 2006
The policy recognized that non-conventional energy sources can beappropriately and optimally utilized to make available reliable supply of
electricity to each and every household.
National Tariff Policy, 2006
SERCs to fox minimum percentage of purchase of energy from renwable
energy sources, taking into account availability of such resources into the
region and its impact on retail tariff.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
19/25
L E G A L F R A M E W O R K
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Renewable Energy Policy
The broad objective of the draft policy are to meet a minimum energy
needs through renewable energy.
Foreign Investment Policy
Foreign investors can enter into a joint venture with an Indian partner for
financial and/or technical collaboration and for setting up of RE-based
power generation projectsHundred per cent foreign investment as equity is permissible with the
approval of the Foreign Investment Promotion Board (FIPB).
The Government of India encourages foreign investors to set up power
projects on BOO basis. Investors are required to enter into a power
purchase agreement with the concerned state government
No prior approval of the government is required to set up an industrial
undertaking with Foreign Direct Investment (FDI) by Non-Resident Indians
(NRIs) or Overseas Corporate Bodies (OCBS)
The Reserve Bank of India (RBI) has permitted Indian companies to
accept investment without obtaining prior approval from RBI. Investors
are required to notify the regional office of RBI, of receipt of inward
remittances within 30 days of such receipt.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
20/25
L E G A L F R A M E W O R K
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Power Purchase Policy
Policies introduced/incentives declared by the State Governments for
private sector Wind Energy projects
Industrial Policy
MNES is promoting medium, small, mini and micro enterprises for
manufacturing and servicing of various types of RE systems and devices.
Industrial clearances are not required for setting-up of an RE industryNo clearance is required from Central Electricity Authority (CEA) for
power generation projects up to Rs 1,000 million
A five-year tax holiday is allowed for RE power generation projects
Soft loans are available through IREDA for RE equipment manufacturing
Financial support is available to RE industries for R&D projects in
association with technical institutions
Import of power projects are allowed
Private sector companies can set up enterprises to operate as licensee or
generating companies
Excise duty on a number of capital goods and instruments in the RE
sector has been reduced or exempted
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
21/25
I N C E N T I V E S
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Incentives for Investing in Renewable Energy Technology
MNES provides financial incentives, such as interest and capital subsidy
Soft loans are provided through:
IREDA, a public sector company of the Ministry
Nationalised banks and other financial institutions for identified
technologies/systems
The government also provides various types of fiscal incentives for the RE
sector, which include:Direct taxes - 100 per cent depreciation in the first year of the
installation of the project
Exemption/reduction in excise duty
Exemption from Central Sales Tax, and customs duty concessions on
the import of material, components and equipment used in RE
projects
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
22/25
I N C E N T I V E S
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Concession under Income Tax Rules
Section 32 - Accelerated 80% depreciation on specified RE- based
devices/projects.
Section 80 IA - Industrial undertakings set up in any part of India for the
generation or generation and distribution of power, a 100% deduction is
allowable from profits and gains for first five years and thereafter 30% of
the profits and gains. Further, the Budget has also proposed a 10-year tax
holiday for the generation and distribution of power, to be availed duringthe initial 15 years.
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
23/25
W I N D P O W E R I N I N D I A
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
The Ministry of New and Renewable Energy (MNRE) is the nodal Ministry of the Government of India
for all matters relating to new and renewable energy. The broad aim of the Ministry is to develop
and deploy new and renewable energy for supplementing the energy requirements of the
country. Creation CASE and Ministry:Commission for Additional Sources of Energy (CASE) in 1981.
Department of Non-Conventional Energy Sources (DNES) in 1982.
Ministry of Non-Conventional Energy Sources (MNES) in 1992.
Ministry of Non-Conventional Energy Sources (MNES) renamed as Ministry of New and Renewable
Energy (MNRE) in 2006.
Ministry of New & Renewable Energy
Indian Renewable Energy
Development Agency
Centre for Wind Energy
Technology
State Renewable Energy
Development Agency
(Finance) (Research) (State agencies)
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
24/25
W I N D P O W E R I N I N D I A
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S
Other financial institutions
PTC India
Gujarat Industrial InvestmentICICI
Industrial Finance Corporations
NABARD
SIDBI
Associations/societiesIndian Wind Energy Association,
Indian Wind Power Association,
Indian Wind Turbine Manufacturers
Association,
Winrock International India,
World Institute of Sustainable Energy
Consultants
TCS,
TERI,
Hitech Wind Solutions,
Sri Ganesh Wind Power,
Power & Energy Consulatants,
Resurge Energy
Testing and certification
C-WET,
Det Norske Veritas AS,
Germanischer Lloyed
Testing and certification
Bajaj Allianz,
ICICI Lomabard,
IFFCO Tokio,
National insurance Company,
Oriental Insurance,
New India Assurance,
Reliance general Insurance,
Royal Sundaram,
Tata AIG,
United India Insurance
-
7/30/2019 REGULATORY ISSUES for setting up a Wind Power Plant
25/25
W I N D P O W E R P R O J E C T S
INDIAN INSTITUTE OF TECHNOLOGY KHARAGPURI N F R A S T R U C T U R E R E G U L A T O R Y I S S U E S