Contents
• Introduction
• Effects of loading on thedurability assessment
• Comparison of 94/20/EC resp. ECE R 55.01 to CARLOS TC
• Summary
-
Page 3GRRF, Geneva 31. 01. 2006
CARLOS TC (CAR LOading Standard, Trailer Coupling) Consortium Participants
Car OEMs:Adam Opel AGAudi AGBMW GroupDaimlerChrysler AGFord-Werke AGPorsche AGSkoda AGVolkswagen AGVolvo Car
Technical Control Boards:RWTÜV Fahrzeug GmbH, EssenTÜV Automotive, München
Suppliers:AL-KO GmbHBosal ResearchKarmann GmbHMVG mbHOris Fahrzeugteile Hans Riehle GmbHPD&E Automotive SolutionsMagna Steyr Fahrzeugtechnik
AG & Co KGWestfalia Automotive GmbH & Co KG
Research Institutes:Fraunhofer Institute for Structural Durability LBF (project manager)KATECH (Korea Automotive Technology Institute)
-
Page 4GRRF, Geneva 31. 01. 2006
Introduction
• Trailer coupling devices (TCD) are safety-critical components
• Tests for the homologation of TCDs according to 94/20/EC are performed with - sinusoidal loading
1-dimensional loading (1-D) constant amplitudes (CA)no mean load (R=-1)
F
• Fatigue relevant local stresses and strains on TCDs are depending on- service loads
3-dimensional loading (3-D)variable amplitudes (VA)variable mean load (R≠–1)
-
Page 5GRRF, Geneva 31. 01. 2006
Uni- & Multiaxial Load – Cycles to Failure
Cycles to Failure N
Res
ult
ing
Fo
rce
F Res
S-N curve uniaxial load
uniaxial load
S-N curve multiaxial load; no phasing
multiaxial load; no phasing
Uni- & Multiaxial Load:- different cycles to failure with the same force amplitudes.
-
Page 6GRRF, Geneva 31. 01. 2006
Constant Amplitude Testing – Type of Failure
CA-Testing:- type of failure depends on load amplitude.
-
Page 7GRRF, Geneva 31. 01. 2006
Mean Load - Cycles to Failure
Cycles to Failure N
Stre
ss A
mp
litu
de
S a
axial loading
Strain Amplitude σa
time
400 N/mm2R = 0R = -1
R = σu / σo
Mean Load:- different cycles to failure with same load amplitude
-
Page 8GRRF, Geneva 31. 01. 2006
Currently used guideline 94/20/EC resp. ECE R 55.01
The 94/20/EC resp. ECE R 55.01 guideline:- sinusoidal loading
1-dimensional loading (1-D) constant amplitudes (CA)no mean load (R=-1)
Durability assessment is critical with respect to:- type of failure- cycles to failure
F
Possible Improvement:A testing procedure oriented on 3-D service loads will lead to customer oriented type of failures resp. cycles to failure .
-
Page 9GRRF, Geneva 31. 01. 2006
Derivation of a Testing Procedure based on Service Loads
Input:42 verification tests / measurements from OEMs
Signal analysis:verifications, normalizations, correlations, load spectra
Derivation of 3 Modules:based on representative 22 load segments
Testing Procedure:damage sums, duration (
-
Page 10GRRF, Geneva 31. 01. 2006
Current EC Homologation Test 94/20/EC (1-D, CA) and CARLOS Trailer Coupling (Realistic loading: 3-D, VA)
Number of load cyclesFo
rce
(am
plit
ud
e) /
D- increasing of max. force amplitude- introducing Fy as further testing direction- 3D-testing with variable amplitudes and mean load
More realistic testing procedure!
-
Page 11GRRF, Geneva 31. 01. 2006
Multiaxial Test-Rig for Trailer Coupling Devices
-
Page 12GRRF, Geneva 31. 01. 2006
Testing Result: CARLOS TC
MOVIE
The additional testing-direction Fy, may lead to additional failures.
Additional failure criteriain the guideline will be needed.
-
Page 13GRRF, Geneva 31. 01. 2006
Summary
• Currently used testing procedure is representing a fictitious testing scenario.
• Proposed testing procedure CARLOS TC is representing customer orientedservice loading.
• Proposed testing procedure leads to customer oriented failures.
The proposed testing procedure is oriented on 3-D service loads and represents the customer usage more closely.
-
Page 14GRRF, Geneva 31. 01. 2006
Thank you for your kind attention!
-
Page 15GRRF, Geneva 31. 01. 2006
-
59th GRRF, item 6 ECE R55-01current test procedure for A50-X (p.1)
current procedure – 1960‘s technology:• hydropulse test bench, uni-axial loading• coupling device rigid (?!) mounted• constant test force ±0,6*D under 15°• 2 * 106 cycles for designs made of steel• no lateral forces • result: fatigue strength (Wöhler)• ??? cycles for design made of light alloy
-
59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.2)
• car manufacturers must release per-missible trailer mass, vertical static loadand fitting points (see also EC directive“mass and dimensions“ 92/21/EEC including 95/48/EC)
• verification: harmonized car loadingstandard (CARLOS) for car bodies
• intention: use of CARLOS test also forA50-X devices and acceptation in ECE 55-01
-
59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.3)
new procedure – state-of-the-art:• hydropulse test bench, multi-axial loading
-
59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.4)
• coupling device directly mounted at car body or directly at the test bench
• not constant test forces – load-time histories of the variable force components: Fx longitudinal, Fy lateral and Fz vertical
• test duration 92 hours• designs made of steel and/or light alloy• result: service strength (long life)
-
59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.5)
proposal for further approach:
Installation of an ad hoc group to studyand discuss the presented details quitesimilar as previously done with maindiscussion for ECE 55-01
time schedule for an ad hoc group meeting:April 2006 or later
Regulation No. 55Mechanical Couplings – Coupling Balls and Towing BracketsRegulation No. 55Mechanical Couplings – Coupling Balls and Towing BracketsCARLOS TC (CAR LOading Standard, Trailer Coupling) Consortium ParticipantsIntroductionUni- & Multiaxial Load – Cycles to FailureConstant Amplitude Testing – Type of FailureMean Load - Cycles to FailureCurrently used guideline 94/20/EC resp. ECE R 55.01Derivation of a Testing Procedure based on Service LoadsCurrent EC Homologation Test 94/20/EC (1-D, CA) and CARLOS Trailer Coupling (Realistic loading: 3-D, VA)Multiaxial Test-Rig for Trailer Coupling DevicesTesting Result: CARLOS TCSummarypresentation 59th GRRFmod.pdf59th GRRF, item 6 ECE R55-01current test procedure for A50-X (p.1)59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.2)59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.3)59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.4)59th GRRF, item 6 ECE R55-01optional test procedure for A50-X (p.5)