regulation 19 statement of representations · policy lg1 city regions 3 representations – 3...
TRANSCRIPT
1
Regulation 19 Statement of Representations – Barnsley Local Plan Publication 2016
1. Introduction This statement considers the representations received following the consultation on Barnsley’s Local Plan Draft 2014 and Addittional Consultation 2015. It sets out how many representations were received and summarises the main issues raised by the representations and how they were taken into account. Local Plan Consultation Draft 2014 The Local Plan Consultation Draft was available for consultation for 6 weeks from 10th November to the 21st December 2014. We extended this period to allow additional comments for 3 weeks from 22nd December 2014 to 11th December 2015. In addition as the consultation portal prematurely closed due to an error in how the date and time of the event were set, the consultation portal was reopened until Friday 16th January 2015 to allow those people using the consultation system to complete their comments online. We wrote to around 5300 people and organisations either by letter or email. This included specific and general consultees, Duty to Cooperate consultees and everyone on our consultation database. Appendices 1 to 5 provide a summary of the consultation undertaken.
A total of 3782 representations were received from 1900 people. The detailed representations are stored and collated on a database system. All of these representations are being taken into account when preparing the next stage of the plan.
Barnsley Local Plan Additional Consultation 2015 The Local Plan Additional Consultation was available for consultation for 6 weeks from 30th October to 11th December 2015.
2
We extended this period to allow comments on site AC42 from 11th to 23rd December 2015. We wrote to around 5300 people and organisations either by letter or email. This included specific and general consultees, Duty to Cooperate consultees and everyone on our consultation database. In addition, notices were posted at each of the sites we consulted on. Appendices 1-4 provide a summary of the consultation undertaken. A total of 1415 representations were received from 643 people. The detailed representations are stored and collated on a database system. All of these representations are being taken into account when preparing the next stage of the plan.
2. Representations This section of the statement outlines the main issues raised during the consultations. It should be noted that this is not a definitive list of all the individual representations received but rather a broad summary of the main issues raised. The issues are summarised from representations therefore do not represent the views of planning officers or the Council. The statement does not set out the Council’s response to the representations. The numbers of representations quoted are current indicative figures. We are unable to guarantee that the figures are exact for a number of reasons such as where representations have been entered via the website they have often been made against the wrong consultation point and therefore may not have been included in a count against a specific policy. Other issues may be where we have received duplicates, or where we have no contact details or comments are illegible. Where we have received petitions, representations are logged against each of the individual valid entries. A valid entry is one which includes a legible name, full address (including house name or number) and signature.
Local Plan Consultation Draft 2014
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Consultation Process 897 objections were received on the consultation process itself. The main emphasis of these objections is summarised as follows:
The consultation documents were complicated and
The Statement of Community Involvement was revised in 2015 in order to make clear how people would be consulted.
3
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
difficult to understand.
It was difficult for people without a computer to access or comment on the consultation documents.
Not all supporting documents where made available during the consultation period.
There was a lack of publicity about the consultation.
Residents were not informed about the consultation and/ or a specific proposal.
Public meetings should have been held.
The early closure of consultation portal denied people the opportunity to comment online.
The Local Plan covers a wide range of complex issues and is supported by technical evidence base. We try to write documents in plain English, however the terminology we need to use makes this difficult. We did our utmost to make as much information as possible available. We accept some additional information that may have provided assistance in the form of background papers were not released for all topics. Barnsley Central Library and branch libraries have computer equipment available for people to use. We publicised the Local Plan consultation widely. Appendix 1 sets out how we have consulted. Our approach is to hold drop in sessions rather than public meetings. In our experience these work better as they allow officers to explain issues more fully.
Vision and Objectives 10 representations – 5 objections, 2 conditional supports, 2 comments, 1 support
Considers proposals do not meet the needs of
The Vision and Objectives remain unchanged. The monitoring and indicators section sets out some indicators and targets
4
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
existing local communities
Vision is unrealistic – plan appears to have been engineered to facilitate removal of large tracts of land from the Green Belt.
Plan fails to take account of relevant topics and should clarify what the objectives really mean
Need to do more than just provide opportunities
Definition of ‘Urban Barnsley’ needs clarifying
Vision should be amended to allow for monitoring of success and to indicate the specific objectives needed to deliver it
Supports aims to widen choice of high quality homes and improve design to enhance Barnsley as a place that will improve quality of life but considers large developments will not achieve these aims
Broad support, subject to consistency with other policies, particularly in relation to employment land requirements and housing numbers
Comment confirming no objections to the Plan.
against the objectives.
Figure 1 No representations received
Figure 2 14 representations – 7 objections, 4 support, 3 comments
Concern at loss of local distinctiveness of Darton village from inclusion with Urban Barnsley settlement
The importance of the Trans-Pennine Trail for recreation and as a means of sustainable transport should be recognised and shown on the key diagram
Welcomes statement on retention of local
The key diagram remains unchanged. The ‘Northern Economic Corridor’ was not on the key diagram but on the Local Plan Policies Map in 2014. This has now been removed.
5
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
distinctiveness but considers that the importance of Elsecar needs to be acknowledged
Clarification sought on the function, role and aspirations of the Northern Economic Corridor. Objects to the proposed route and suggests alternative road alignments
Support for the general thrust of the Plan but considers a number of policies to be unsound in their current form
Concerns that perpetual growth will be unsustainable and will detrimentally affect health, living conditions and the environment
Support for Spatial Strategy as considered to be consistent with national policy
Support for identification of Royston as a Principal Town
Support the principles of the spatial strategy and settlement hierarchy
Comment welcoming the retention of the Core Strategy Spatial Strategy but suggesting that existing transport links to Sheffield City Region could be highlighted further
Suggestion that the forthcoming Nature Improvement Area Planning Advice Note referred to in the chapter on Green Infrastructure is also referenced at para. 5.23 in Spatial Strategy chapter.
Comment expressing the opinion that proposals will go ahead regardless of objections
Policy SD1 Presumption in favour
6 representations – 2 support, 2 conditional support, 2 comments
Policy SD1 remains unchanged as it was a model policy suggested by the Planning
6
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
of Sustainable Development
General support for policy and wording
Supports the collaborative approach described in the policy
Support the policy but need to ensure all other plan policies are consistent with it
Considers the policy should include reference to transport
Comments that permissions given need to be monitored to ensure requirements are delivered.
Inspectorate.
Policy GD1 General Development
21 representations – 18 objections, 3 comments
Objection to use of Green belt for housing allocations
Suggestion that policy should make reference to the social and economic aspects inherent to sustainable development
Policy should ensure no loss of valued community services and facilities
Consider policy to be unsound as it is neither positively prepared, effective nor sufficiently justified. Proposes amended wording
Support in principle but requires further clarification and suggests alterations/additions to wording
Welcomes reference to planting and green walls and to supporting development that protects or enhances quality and efficient use of natural assets including water, but suggests reference to protecting and enhancing soils should also be included
Encouraged that the policy will minimise and
Some issues have been added to GD1.
7
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
mitigate the impact on the environment, natural resources, waste and pollution, but could go further in promoting enhancements measures. Also happy that proposed developments will be assessed for their impact on living conditions
Comments that permissions given need to be monitored to make ensure requirements are delivered, otherwise there is limited use in making the requirements.
Policy GD2 Temporary Buildings and Uses
2 representations – 1 support, 1 comment
Supports the wording of the policy as temporary buildings are beneficial to the on-going delivery of healthcare services
Comment seeking confirmation that the policy covers use for temporary car parks and requests a revision to the text
GD2 remains unaltered. Specific uses will be considered on their individual merits depending on location, access issues etc.
Policy LG1 City Regions
3 representations – 3 objections
Objects that proposed plan is to create commuter housing for the surrounding cities and fails to take account of transport infrastructure or local services.
Policy needs to encourage sustainable development close to public transport hubs and maximise links to them.
Unclear how co-operation has been translated into the plan. Recommendation that a background paper on duty to co-operate is produced prior to the next stage of consultation and LG1 is amended to include positive statements to aid a decision maker.
Minor amendment made to LG1, change to read ‘favourable economic position’. Our view is that the Plan does not propose to create commuter housing. The starting point for the Objectively Assessed Housing figure is household projections for Barnsley. A Duty to Co-operate Background Paper will be available with the Publication version of the Local Plan in order to set out how we have met the legal duty to date.
8
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Other policies in the Local Plan deal with encouraging sustainable travel and development.
Policy LG2 The Location of Growth
21 representations – 11 objections, 5 support, 2 conditional support, 3 comments
Support for focus of growth of Urban Barnsley and Principal Towns but consider sustainable credentials of other settlements should not be overlooked where there may be opportunities for growth
Concern that lack of an archaeological scoping study of proposed allocation sites could cause conflict between the desire to protect the historic environment and the need to agree areas of growth
Considers that the Council continues to ignore the wishes of the local population
Concern that sites not allocated for executive housing in the rural west
Policy considered too restrictive for villages
Policy should be amended to provide more flexibility for development in a range of locations
Numerous concerns with the approach of the plan, particularly with regard to the reasons for and impact of releasing Green Belt land.
Considers that not supporting significant development in villages in the west of the borough will have a negative impact on local facilities and will restrict economic growth of the borough by not providing appropriate housing for business owners and senior employers and employees.
Policy LG2 remains unchanged. The rationale for the settlement hierarchy is set out in our supporting information, for example the Plan Wide Viablility Study.
9
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Supportive of policy which focuses development in already developed areas, leaving greenbelt intact.
Support for the approach and aims of the policy.
Policy E1 Providing Strategic Employment Locations
12 Representations – 6 Objections, 4 Supports, 2 Comments Concerns include:
Employment land requirement is too ambitious.
Proposed job increase targets are unrealistic.
Questions the need to allocate more land when there are empty shops and factories.
Employment land requirement lacks ambition and aspiration.
Policy should make reference to strategic sites which have more certainty over delivery.
Employment land requirement needs to be consistent with and informed by Sheffield City Region Economic Plan and its evidence base.
Policy E1 remains unchanged. The reason for our approach is set out in our supporting information, for example Infrastructure Delivery Plan and the Plan Wide Viablility Study.
Policy E2 The Distribution of New Employment Sites
7 representations – 4 objections, 2 comments, 1 support
Concerns include:
Policy needs to be less prescriptive.
The Council has failed to promote an appropriate portfolio of sites.
The policy reinforces a motorway based approach to employment location which is unsustainable
The proposed distribution of employment sites has changed slightly due to dealing with issues raised and more information gathered about specific sites. The policy reflects the actual sites proposed. The reason for our approach is set out in our supporting information, for example Infrastructure Delivery Plan and the Plan
10
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Welcomes employment allocation in the Rockingham area.
Wide Viablility Study.
Policy E3 Employment Site Policies
7 Representations – 5 Objections, 1 Support, 1 Comment
Concerns include:
Site Policy for UB1 required which makes reference to the need to safeguard heritage assets.
MU1 should be considered in its own right due to the mix of uses proposed.
An additional mechanism is required to assess the cumulative impact of development across the suite of sites.
Welcomes the inclusion of reference to the protection and enhancement of biodiversity and landscape assets in the site policies. Reference to the Nature Improvement Area SPD should also be made.
Site specific policies included in Publication version.
Table 1 Proposed allocations in Urban Barnsley
No representations
UB1 Birthwaite Business Park
No representations
UB3 Claycliffe Business Park
No representations
UB5 Zenith No representations
11
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
UB7 Capitol Park Extension
1 Representation – 1 Support The site is proposed as an employment land allocation.
UB8 Capitol Park No representations
UB9 Land east of Wakefield Road
2 Representations – 1 Objection, 1 Comment
Site should be proposed for mixed use.
Due to the proximity of overhead power lines, any development on this site will need to take into account restrictions on statutory safety clearances.
The site is proposed as a housing allocation in the Publication version, reference AC3. We have added a reference to pylons to policy GD1 and cross referred to that policy in H3 Housing Site Policies
UB12 Bromcliffe Business Park
No representations
UB13 Oaks Business Park
No representations
UB15 Land south of Doncaster Road
No representations
UB16 Bleachcroft Way Industrial Estate
3 Representations – 2 Objections, 1 Support Concerns include:
Impact on the historic environment.
Site is unviable for employment use.
Welcome the reference to the protection of wet woodlands.
The site is proposed as an employment site in the Publication version.
Table 2 Mixed Use allocation in Barnsley
No representations
MU1 Land South of Barugh Green Road
837 Representations – 824 Objections (including a petition containing 563 valid entries), 9 Comments, 4 Supports
The site is proposed as a mixed use allocation in the Publication version. Some of the issues raised have been considered
12
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Concerns include:
Highways capacity, congestion and safety.
Inadequate public transport provision.
Local infrastructure will not be able to cope.
Increased pressure on Schools, health services and local amenities (shops) and the emergency services.
Loss of Green Belt, Countryside and Greenspace leading to the merging of villages and the loss of their identity.
Loss of agricultural land.
Brownfield sites should be developed first.
Site has potential for aspirational (executive) housing.
Proposed density (40 dph) is not compatible with existing housing.
Negative Biodiversity/ Ecological impact.
Ground stability questioned due to mining legacy.
Inadequate drainage and flood risk.
Negative impact on the landscape and character of the area.
Increased pollution (air, noise and light).
Negative impact on sensitive neighbouring uses (including Barnsley Hospice).
Questions the need for more houses and employment land.
Questions why it is the only mixed use site.
Non planning issues (impact on property values, loss of views).
Allocation/ development is a done deal (due to
as part of the site selection process. A site policy is provided which sets out specific issues that need to be addressed. It requires a masterplan and provision of a primary school on the site. Further information about this site and relevant transport modelling work is in the Infrastructure Delivery Plan. Comments about the consultation process have been dealt with above.
13
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
developer discussions, submission of funding bids and development is a means of funding the link road).
Questions the integrity of the evidence base.
Policy will need to consider the drain/ culvert on site.
Assessment of coal reserves on site should be undertaken.
Proposal is contrary to the Governments Green Economy objectives.
Development will compromise the wellbeing of residents.
Heritage should not be sacrificed for developers profits.
Site is viable.
Any disruption will be minimal and once completed the plans will benefit the area.
Key concerns raised in the petition include:
Consultation process (access to consultation documents is too complicated for those without access to a computer)
Loss of Green Belt (consider Green Belt review is flawed)
Housing mix and density incompatible with existing
Insufficient use being made of brownfield sites
Lack of demand for industrial sites throughout the Borough
Impact on air quality and pollution
Loss of farmland and effect on associated livelihoods
Impact on wildlife
14
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Flood risk and drainage
Table 3 Proposed allocations in Cudworth
No representations
C2 land off Ferrymoor Way
1 Representation – 1 Support
Welcome the reference to no built development in Flood Zone 2 and 3.
This site is proposed as an employment allocation. A site policy is provided which picks up the flood zone issue.
C3 Land west of Springvale Road
No representations
C4 Land east of Springvale Road
No representations
Table 4 Proposed allocations in Goldthorpe
No representations
D1 Land South of Dearne Valley Parkway
10 Representations – 10 Objections Concerns include:
Highways capacity, congestion and safety.
Biodiversity and ecological impact, particularly on RSPB reserve.
The proposed allocation is incompatible with the Nature Improvement Area and the Dearne Valley Eco-vision
Ground stability concerns due to mining legacy.
Reference is needed to the area of Flood Zone 3 and watercourses within the site.
Development could increase flood risk.
The site is proposed as an employment land allocation in the Publication version. The site area has been increased to 72.9ha. A site policy is provided to deal with issues such as biodiversity and flood risk. Further information about this site is in the Infrastructure Delivery Plan.
15
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Increased pollution (air, noise and light).
Negative impact on people’s health and wellbeing.
Negative impact on Billingley Conservation area.
Loss of Green Belt.
Loss of agricultural land.
Negative impact on the landscape and character of the area.
Brownfield sites should be developed first.
Questions the need for more employment land.
More employment land should be allocated in this location.
D2 Fields End Business Park
1 Representation – 1 Objection
The policy should refer to the culvert/ drain running through the site.
This issue applied to a number of sites. Therefore we have added this point to policy GD1 and crossed referenced the site policies to it.
D3 Thurnscoe Business Park
1 Representation – 1 Objection
The policy should refer to the culvert running through the site.
This issue applied to a number of sites. Therefore we have added this point to policy GD1 and crossed referenced the site policies to it.
D4 Lidget Lane Industrial Estate
No representations
Table 5, RSV1 Land South of Dearne Valley Parkway
11 Representations – 11 Objections Concerns include:
Highways capacity, congestion and safety.
Biodiversity and ecological impact, particularly on RSPB reserve.
The proposed allocation is incompatible with the
The site is proposed as a reserve employment land allocation in the Publication version. The site area has been decreased to 98 ha. A site policy is provided to deal with issues such as biodiversity and flood risk. Further information about this site is in the Infrastructure Delivery Plan.
16
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Nature Improvement Area and the Dearne Valley Eco-vision.
Areas of Flood Zone 2 and 3 within the site should not be built on.
Development could increase flood risk.
Increased pollution (air, noise and light).
Negative impact on Billingley Conservation area.
Loss of Green Belt.
Loss of agricultural land.
Negative impact on the landscape and character of the area.
Brownfield sites should be developed first.
Questions the need for more employment land.
More detail is needed on what is being proposed and how it will come forward.
More employment land should be allocated in this location.
Table 6 Proposed allocations in Hoyland
3 Representations – 2 Objections, 1 Comment
Hoyland is receiving a disproportionate share of the new employment sites proposed for Barnsley.
Development should come forward in a phased approach in accordance with representor’s masterplan.
Dialogue is required with the Highways Agency to ensure planned highways improvements are sufficient to meet future demand on the network.
Discussions are held with Highways England under Duty to Co-operate.
HOY1 Land West of Sheffield Road
7 Representations – 6 Objections, 1 Support, 1 Conditional Support
The site is proposed as an employment land allocation in the Publication version. A site policy is included which seeks production of
17
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Concerns include:
Highways infrastructure is not adequate.
Biodiversity and ecological impact.
Negative impact on the landscape.
Loss of Green Belt, Countryside and Green Space.
Brownfield sites should be developed first.
Questions the need for more employment land.
Potential to expand the proposed allocation.
Supports the sites removal from Green Belt, would also support sites allocation for housing.
a masterplan covering a number of sites, and deals with issues such as biodiversity. Further information about this site is in the Infrastructure Delivery Plan.
HOY2 Rockingham 1 Representation – 1 Conditional Support
Support, potential for more land to be included in the allocation.
The site is proposed as an employment land allocation in the Publication version. A site policy is included which seeks production of a masterplan covering a number of sites.
HOY3 Shortwood Extension
3 Representations – 1 Objection,1 Support, 1 Conditional Support
Loss of Green Belt and Green space.
Questions the need for more buildings/ employment land.
Support the protection of Green Ways and public footpaths.
Support, subject to the amendment of other plan policies.
The site is proposed as an employment land allocation in the Publication version. A site policy is included which seeks production of a masterplan covering a number of sites.
HOY4 Shortwood Business Park
1 Representation – 1 Comment
The site is on a historic landfill. Developments will be expected to undertake contamination investigations prior to development and complete necessary
The site is proposed as an employment land allocation in the Publication version. A site policy is included which seeks production of a masterplan covering a number of sites. The site policy deals with this point.
18
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
remedial works.
HOY5 land South of Dearne Valley Parkway
319 Representations – 317 Objections (including a petition containing 166 valid entries), 1 Support, 1 Conditional Support Concerns include:
Highways congestion and safety.
Loss of Green Belt
Loss of Green space
Loss of Countryside
Loss of agricultural land.
Urban sprawl leading to loss of settlements identity, character and community spirit.
Damage to the areas landscape character.
Biodiversity and ecological impact.
Increased air and noise pollution.
Neighbouring land uses (loss of privacy).
Questions need for more employment land.
Brownfield sites should be developed first.
The site floods following heavy rainfall.
Adverse impact on the setting of a listed building.
Questions the integrity of the Green Belt review.
Non planning matters (devaluation of property, loss of views).
Support the protection of Green Ways and public footpaths.
Support, subject to the amendment of other plan policies.
The site is proposed as an employment land allocation in the Publication version. A site policy is included which seeks production of a masterplan covering a number of sites that will deal with issues such as biodiversity. Further information about this site is in the Infrastructure Delivery Plan.
19
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Petition objects to the proposed sites due to lack of awareness of the consultation and request to be consulted at next stage of process
HOY7 Ashroyds No representations
Table 7 Proposed allocations in Penistone
1 Representation – 1 Objection
More employment land should be allocated in Penistone.
One site is proposed as an employment land allocation in the Publication version.
P2 Land North of Sheffield Road
5 Representations – 4 Objections, 1 Support
Road safety concerns.
Safeguards needed to protect the woodland and river behind the site.
Developer should be required to retain dry stone walls.
Questions need for more employment land.
Due to the proximity of overhead power lines, any development on this site will need to take into account restrictions on statutory safety clearances.
P2 is proposed as an employment land allocation in the Publication version. A site policy is included which covers issues such as protection of woodland and overhead power lines.
Table 8 Proposed allocations in Wombwell
No representations
W1 Mitchells Industrial No representations
W2 Everill Gate Lane 1 Representation - 1 Objection
Site should be given housing allocation.
W2 is proposed as an employment land allocation in the Publication version. We consider the site better suited to employment than housing.
Table 9 Proposed allocations outside
No representations
20
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Urban Barnsley and Principal Towns
N1 Wentworth Industrial Park, Tankersley
No representations
N2 Land West of Park Spring Road, Houghton
3 Representations – 1 Objection, 2 Supports
The western part of the site is located in Flood Zone 2. The policy should reflect this and apply the Flood Risk Sequential Test.
N2 is proposed as an employment land allocation in the Publication version. A small part of the site is in Flood Zone 2 which can be avoided by built development.
N5 Land east of Park Spring Road, Houghton
1 Representation – 1 Support N5 is proposed as an employment land allocation in the Publication version.
Policy E4 Land reserved for Employment
4 Representations – 4 Objections
A criterion for proving need should be stipulated in the policy as well as the guidance.
Queries the need for both policy E4 and RSV1 as there is only one site in this category.
The land should be allocated as a key business park and merged with D1.
The reference to Green Belt policies has been removed from the policy. We felt a separate policy E4 and site policy for RSV1 was warranted. No criterion has been added on need.
Policy E5 Uses on employment land
8 Representations – 7 Objections, 1 Comment
The Policy should be revised to acknowledge that alternative uses will be supported where it can be demonstrated it is the most sustainable option for the site.
The Policy is too restrictive.
The Policy is unnecessary.
The policy remains largely unchanged apart from a few minor tweaks. We consider the policy to be necessary and to have flexibility. A reference to the Joint Waste Plan has been added to the supporting text.
21
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Additional Policy text is required to support additional investment and development in existing businesses.
A link between this Policy and Joint Waste Plan Policies WCS1 and WCS4 is required.
Policy E6 Protecting Existing Employment Land
2 Representations – 2 Objections
The first bullet point should be removed to prevent re-use of a site which in all other respects is appropriate.
Concerned that the policy could prejudice non B class proposals. Additional wording is required to allow development that would significantly contribute to the Boroughs economy.
Minor tweaks have been made to the policy. We consider there is flexibility to allow other uses if the criteria in the policy can be satisfied.
Policy E7 Promoting Tourism and encouraging Cultural provision
6 Representations – 3 Objections, 2 Conditional Supports, 1 Comment
Questions what Barnsley has to offer to make it a place to visit.
Reference should be made to specific tourism opportunities.
The following text should be added to the Policy ‘Ensuring that any development proposals in the vicinity of existing tourist or cultural facilities do not threaten the attractiveness of these assets’.
Acknowledgement should be made of the role cultural facilities play in health, social and cultural wellbeing of residents.
The policy remains unchanged. The issue of development affecting tourist and cultural attractions is covered both in the second bullet point and in the heritage policies.
Policy E8 Rural 3 Representations – 2 comments, 1 Objection Final bullet point has been amended to read
22
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Economy
Policy should be worded to make it clear that the preference is to develop lower quality agricultural land before the best agricultural land.
The Policy needs to distinguish between ‘rural’ and ‘urban fringe’.
Encouraging investment in active travel will attract further investment.
“protect the best quality agricultural land, areas of lower quality agricultural land should be used for development in preference to the best and most versatile land”
Policy E9 Loss of Shops and Local Services in Villages
3 Representations – 2 Supports, 1 Conditional support
Preference would be for an overarching Policy which covers all valued community facilities.
Policy title and wording amended to include community facilities.
Policy H1 The Number of New Homes to be Built
35 representations – 25 objections, 5 support
Considers that the housing allocation should be reduced in line with the SCR report, enabling development in the most sensitive green belt areas to be reduced or eliminated. Housing allocations should be based on what is right for Barnsley, not Sheffield.
Expresses concern at lack of any policy to bring empty and derelict homes back into use and reduce loss of green belt land
Concerned about the numbers of proposed new homes being built and a lack of corresponding uplift to local infrastructure / services i.e. schools, health services and roads.
Suggests proposed housing target figures should be revised to ensure housing provision supports economic growth
The net additional homes figure has been increased to 20,900 to ensure we meet our full objectively assessed housing need. A sentence has been added to the supporting text to make clear that empty homes will form part of our housing land supply. Site specific policies and other policies in the Local Plan will deal with air quality and pollution control issues. Further information on our approach is in our supporting documents such as the Infrastructure Delivery Plan and the Plan Wide Viability Study.
23
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Questions the need for so many new homes
Brownfield land should be utilised before taking land from the Green Belt
Considers that additional land should be identified as suitable for residential development,
Concerns regarding the effect on health/pollution from proposed development adjoining the M1
Refers to lack of provision in the policy for children and vulnerable adults.
Considers all sites should have infrastructure in place to encourage and enable active travel.
Supports the requirement to maintain a minimum 5 year supply of deliverable housing sites
Supports ambitious housing target but questions reliance on windfall development
Policy H2 The Distribution of New Homes
25 representations – 19 objections, 4 support
Objection. Considers sites should be phased to ensure greenfield sites are developed last
Objection to proposed allocations for Hoyland and considers should be reduced in line with Core Strategy figures
Housing target is insufficient to meet needs
Notes that some of the densities set out in the plan are higher than permissions granted and questions how the shortfall in housing targets will be dealt with
Objection seeking an increase in distribution of housing development in Penistone to a minimum of 10%
The proposed distribution of housing sites has changed slightly due to dealing with issues raised and more information gathered about specific sites. The policy reflects the actual sites proposed together with planning permissions already granted that are part of our supply.
We have done further work on sites to ensure yield figures are realistic in terms of excluding areas of sites that are to remain undeveloped and applying a realistic gross
24
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Object that the distribution of housing requirement is too restrictive for villages
Considers higher proportion of sites need to be allocated to meet housing requirement and reference to windfalls should be deleted
Policy needs to be less prescriptive and more flexible in terms of housing land supply and locations
Greater flexibility should be built into the plan through the allocation of additional sites
The distribution should offer more flexibility for the market by allocating sites outside of the Principal Towns.
Local Plan is consistent with utility providers expected uptake areas.
Support proposed growth in Penistone, Hoyland and Urban Barnsley as a number of the residents are likely to commute to Sheffield for work
to net ratio.
The distribution reflects the settlement hierarchy. There are other policies in the Plan that provide flexibility to allow development outside Urban Barnsley and the Principal Towns where appropriate.
Further information on our approach is in our supporting documents such as the Infrastructure Delivery Plan and the Plan Wide Viability Study.
Table 11 Urban Barnsley
3 representations – 1 objection, 2 comments
Comments that some proposed sites present accessibility challenges in terms of public transport which must be addressed
Concerns regarding development of agricultural land.
Comments on flood risk management issues on various sites
Sites that are proposed as allocations have site policies where specific issues need to be addressed. Public transport accessibility and flood risk have been considered as part of the site selection process.
H5 Site South of Coniston Avenue, Darton
3 representations – 3 objections
Increased traffic/road safety issues
The site is proposed as a housing allocation in the Publication version. Access and highways issues have been considered as part of the housing site selection process.
25
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Concerns regarding capacity of existing schools, health services
Noise/pollution
Issues with mains services in former mining area
Brownfield sites should be developed first
Access to site
H13 Site East of Burton Road, Monk Bretton
10 representations – 7 objections, 3 support
Concerns regarding highways/road safety issues
Lack of school places/health facilities
Impact on ecology
Flooding and drainage concerns
Loss of views/privacy
Disruption from construction
Loss of Green Belt/recreational land
Objects to 3 or 4 storey house or flats being built
Loss of property values
Support for site allocation
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H14 Site West of Wakefield Road, Mapplewell
2 representations – 2 objections
Concerns regarding traffic, highway safety and car parking
Lack of school places/health facilities
Loss of footpaths and effect on health and wellbeing
Need for more facilities for children and young people
Ecological impact
Flooding and drainage issues
Pollution
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
26
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Effect on local character
Use brownfield land before Green Belt
H15 Site East of Dearne Hall Road, Low Barugh
1 representation – conditional support
Landowner support for proposed allocation subject to increase in dwelling numbers to reflect extant planning permission
The site is not included as a housing allocation as planning permission was granted before 1st April 2014. The site is included in the planning permission figures.
H18 Site East of Smithy Wood Lane, Gilroyd
10 representations – 9 objections, 1 support
Considers site unsuited to aspirational housing due to access
Impact of development on setting of nearby Grade 1 listed park and gardens should be assessed
Loss of Green Belt
Houses in this area are already difficult to sell
Brownfield sites should be developed first
Devaluation of existing properties
Fear of increase in crime and anti-social behaviour
Loss of views
Merging of settlements
Highway safety/traffic issues
Lack of existing infrastructure, e.g. shops, schools
Pollution
Loss of trees
Objects to piecemeal development approach and considers a cohesive plan is required
Landowner support for proposed allocation
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H19 Site North of Keresforth Road,
7 representations – 7 objections
The site is proposed as a housing allocation in the Publication version. Some of the
27
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Dodworth Not suited to aspirational housing due to proximity of motorway
Concerns over increase in noise/air pollution
Highway safety/traffic issues
Lack of existing infrastructure, e.g. shops, schools
Loss of trees
Objects to piecemeal development approach and considers a cohesive plan is required
issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H20 Site South of Bloomhouse Lane, Darton
7 representations – 7 objections
Increased traffic/road safety issues
Concerns regarding capacity of existing schools, health services
Noise/pollution
Issues with mains services in former mining area
Brownfield sites should be developed first
Lack of local shops/community facilities
Flooding/drainage
Loss of green belt
Density too high for executive homes
Concerns area will become a dormitory for Leeds/Wakefield/Sheffield
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H21 Site of Former North Gawber Colliery, Carr Green lane, Mapplewell
1 representation in support
Support for proposed allocation
The site is not included as a housing allocation as planning permission was granted before 1st April 2014. The site is included in the planning permission figures.
H24 Site North of Carlton Road, Monk Bretton
1 representation – 1 comment
Considers site unlikely to be delivered due to
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part
28
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
multiple development constraints of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H28 Site of Former Priory School, Lundwood, Barnsley
1 representation – 1 objection
Asks how the 'by pass' to accommodate access to the Littleworth Lane site will be factored in
Impact on green infrastructure and greenspace
Loss of trees
Queries increase in housing numbers in Local Plan from 2014 planning application
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H29 Site at Garden House Farm, Harden House Close, Monk Bretton
No representations received
H31 Site to the West of Smithy Wood Lane, Gilroyd
9 representations received – 8 objections, 1 support
Considers site unsuited to aspirational housing due to access
Loss of Green Belt
Houses in this area are already difficult to sell
Brownfield sites should be developed first
Devaluation of existing properties
Fear of increase in crime and anti-social behaviour
Loss of views
Merging of settlements
Highway safety/traffic issues
Lack of existing infrastructure, e.g. shops, schools
Pollution
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
29
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Loss of trees
Objects to piecemeal development approach and considers a cohesive plan is required
Landowner support for proposed allocation
H33 Site to the East of St Helens Avenue, Monk Bretton
1 representation - 1 comment
Comments on highways and access constraints
Loss of green space
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H42 Site West of Wakefield Road, New Lodge
3 representations – 1 objection, 1 conditional support, 1 comment
Concerns regarding impact on setting of nearby Scheduled Ancient Monument
Comment on impact on traffic congestion – specifically Wakefield Road
Strongly supports the allocation for residential development subject to changes proposed to relevant policies
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H44 Site to the North of West Green Way, West Green
1 representation in support
Support for proposed allocation from landowner of part of site
Support noted and will have been taken into account in deliverability score
H48 Site of Former Kingstone School, Broadway, Barnsley
5 representations – 5 objections
Highways issues
Considers site unsuited to aspirational housing due
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need
30
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
to neighbouring land uses to be dealt with. The site has planning permission which was granted after 1st April 2014.
H49 Site South East of West Street, Worsbrough Dale
1 representation – comment
Concerns regarding capacity of highways network
Loss of green space
Access constraints
Impact on adjacent Green Belt
The site is not proposed as a housing allocation in the Publication version.
H53 Site North of Wilthorpe Road, Barnsley
1 representation – comment
Comments on highways and access constraints to development
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with. The site has planning permission which was granted after 1st April 2014.
H54 Land off High Street, Dodworth
6 representations – 6 objections
Highway safety/traffic issues
Lack of existing infrastructure, e.g.. shops, schools
Pollution
Loss of trees
Objects to piecemeal development approach and considers a cohesive plan is required
Not suited to aspirational housing due to neighbouring uses and density
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H57 Monk Bretton Reservoir and land to the East of Cross
No representations received
31
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Street, Monk Bretton
H59 Land at St Michaels Avenue, Carlton
1 representation – comment
Considers site acts as a buffer between residential and industrial uses and development would be detrimental to the amenities of current and future occupants
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H60 Site between Rotherham Road & Former Priory School Site, Cundy Cross, Barnsley
1 representation – 1 objection
Asks how the 'by pass' to accommodate access to the Littleworth Lane site will be factored in
Impact on green infrastructure and greenspace
Loss of trees
Queries increase in housing numbers in Local Plan from 2014 planning application
The site is proposed as part of a housing allocation in the Publication version. This site has been merged with H28 and the H28 reference has been used. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H62 Land off Highstone Lane, Worsbrough Common
4 representations – 4 objections
Loss of well used recreation space
Considers new build would be out of character with existing properties
Loss of views
Loss of allotments
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H65 Hospital Site off Mount Vernon Road, Worsbrough
112 representations – 111 objections (including a petition containing 64 valid entries), 1 support
Concerns regarding highway safety and increase in traffic
Concerns regarding pressure on schools, health facilities, shops, community facilities
The site is not proposed as a housing allocation in the Publication version.
32
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Loss of Green Belt and greenspace
Loss of views
Loss of hospital – The buildings importance in history should be recognised
Lack of efficient public transport
Impact on wildlife/ecology
Access to site
Capacity of existing sewerage infrastructure
Noise/air pollution
Questions need for number of new homes proposed
Considers proposals inappropriate to the scale, role, function and character of the area
Support for the proposal as it is a brownfield site and may alleviate parking problems associated with current use
Petition objects to proposed housing sites on the basis that the process of consultation was improper and concerns regarding loss of Green Belt
H66 Hospital Site off Broadway, Barnsley
No representations received
H72 Land North of Kingwell Road, Worsbrough
128 representations - 127 objections (including a petition containing 64 valid entries), 1 support.
Concerns regarding traffic, highway safety and parking – especially in relation to local school
Lack of infrastructure/facilities (public transport, schools, health facilities, shops, leisure facilities)
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
33
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Loss of well used recreation space/public right of way
Who will houses be for (private, social, commuters)?
Location of site access
Ecological impact
Flooding/drainage – site has natural springs
Loss of historic ‘pinfold’
Loss of views/privacy/impact on quality of life
Increase in pollution
Decrease in property values
Loss of Green Belt – community value
Need for quantum of housing – regenerate existing empty properties first/use brownfield sites first
Effect on local economy
Landowner support for site allocation
Object to proposed housing sites on the basis that the process of consultation was improper and concerns regarding loss of Green Belt
H73 Land between Mount Vernon Road & Upper Sheffield Road, Worsbrough
125 representations - 123 objections (including a petition containing 64 valid entries), 2 supports.
Concerns regarding traffic, highway safety and parking – especially in relation to local school
Lack of infrastructure/facilities (public transport, schools, health facilities, shops, leisure facilities, emergency services)
Loss of well used recreation space/public right of
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
34
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
way – health benefits
Will houses be private or social?
3 storey houses would be out of character with the area
Location of site access
Ecological impact
Capacity of existing drainage
Concerns regarding stability of land – fault line runs through site
Impact on Listed Building
Loss of views/privacy/impact on quality of life
Increase in pollution
Decrease in property values
Loss of agricultural land
Scale of development and impact on the community – urban sprawl
Objects to loss of Green Belt - use brownfield sites first
Landowner support for site allocation
Supports proposed removal of land from Green Belt and allocation for Housing
Object to proposed housing sites on the basis that the process of consultation was improper and concerns regarding loss of Green Belt
H83 Land to the east of Woolley Colliery Road, Darton
4 representations – 2 objections, 2 support
Concerns that increased traffic will adversely affect
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part
35
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
existing highways and highway safety
Objects to removal of land from Green Belt
Concerns regarding increased risk of flooding
Increase in noise and pollution
Supports removal of land from Green Belt and allocation for Housing
Landowner support for site allocation
of the housing site selection process. A site policy is provided to set out issues that need to be dealt with
Table 12 Mixed Use land in Urban Barnsley
Summarised under Table 2 above. See above
MU1 Land South of Barugh Green Road,
Summarised under Table 2, MU1 above See above
Table 13 Cudworth 2 representations – 1 comment, 1 objection/comment
Comments that some proposed sites present accessibility challenges in terms of public transport which must be addressed
Comments on flood risk management issues on various sites
Issues raised have been considered as part of the housing site selection process.
H10 Site to the West of Brierley Road, Grimethorpe, Barnsley
No representations received
H22 Site North of Blacker Lane, Shafton
No representations received
H32 Site adjacent to Carrs Lane/Summerdale Road, Cudworth
5 representations received - 3 objections, 1 support, 1 conditional support
Concerns regarding traffic, parking and road safety
Concerns regarding flooding and drainage
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with
36
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Impact on living conditions of existing residents
Loss of agricultural land – arable land should be retained for food production
Concerns over impact on public services – schools, health, local authority
Effect on property values
Support for allocation subject to removal of first bullet point in site policy H32
Support for site, with strong developer interest
H39 Site at Weetshaw lane, Cudworth
No representations received
H74 Land North of Sidcop Road, Cudworth
3 representations – 2 objections, 1 support
Objects to proposed site density – a more appropriate and realistic figure would be 20-30 dph
Concerns at impact on public services – schools, health, local authority
Increase in traffic and pollution
Concerns regarding flooding and drainage
Impact on living conditions of existing residents
Effect on property values
Landowner support for allocation
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A masterplan is required that covers sites H74, H75 and H87. A site policy is provided to set out issues that need to be dealt with.
H75 land South of Sidcop Road, Cudworth
2 representations – 1 objection, 1 support
Objects to proposed site density – a more appropriate and realistic figure would be 20-30 dph
Concerns over impact on public services – schools, health, local authority
Increase in traffic and pollution
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
37
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Concerns regarding flooding and drainage
Impact on living conditions of existing residents
Effect on property values
Landowner support for allocation
H76 Land West of Three Nooks Lane, Cudworth
2 representations in support
Landowners support for allocation
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H86 Land off Pontefract Road, Cudworth, Barnsley
1 representation – conditional support
Strong support for allocation subject to proposed changes to relevant policies
H87 Land North of Oak Tree Avenue, Cudworth
No representations received The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with
Table 14 Dearne Towns
2 representations received – 1 comment, 1 objection/comment
Comments that some proposed sites present accessibility challenges in terms of public transport which must be addressed
Comments on flood risk management issues on various sites
These issues have been considered as part of the housing site selection process.
H1 Former Reema Estate and adjoining land, off School
No representations received
38
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Street, Thurnscoe, Rotherham
H12 Bolton House Farm, Barnsley Road, Goldthorpe
No representations received
H17 Site South of Barnburgh Lane, Goldthorpe
No representations received
H23 Land West of Holly Grove, Goldthorpe
No representations received
H30 Land North of East Street, Goldthorpe
No representations received
H38 Site South of Lindley Crescent, Thurnscoe
1 representation received in objection
Objects to proposed site density – a more appropriate and realistic figure would be 20-30 dph
The site is not a proposed housing allocation in the Publication version.
H50 Site to the North of Dearne ALC, Goldthorpe
No representations received
H51 Land North of Barnburgh Lane, Goldthorpe, S63 9NT
No representations received
H52 Site South of Beever Street, Goldthorpe
1 representation in support
Landowner support for allocation
Support noted and will have been taken into account in deliverability score.
H55 Site at Brunswick Street, Thurnscoe
No representations received
H67 Site to the East 1 representation in support The site is proposed as a housing allocation
39
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
of Broadwater Estate, Bolton on Dearne
Full support for the allocation
in the Publication version. A site policy is provided to set out issues that need to be dealt with
H84 Site South of Bridge Lane, Thurnscoe
1 representation in support
Supports the allocation and considers the site to be capable of subdivision in order to allow schemes to come forward individually
The site is proposed as a housing allocation in the Publication version. A site policy is provided to set out issues that need to be dealt with
Table 15 Hoyland 121 Representations – 119 Objections, 1 Support, 1 Comment
Objects to the development of Green Belt, as it would have a negative impact the landscape and people’s health.
The increase in housing in Hoyland should balance against the large increase in employment land.
Generally supports housing allocations in this area, however some of the sites have limited connectivity.
The housing and employment sections of the Plan set out which sites are proposed as allocations. Site policies have been provided where specific issues need to be addressed.
H2 Land West of Fitzwilliam Street, Elsecar, S74 8EQ
No representations
H4 Land South of Hay Green Lane, Birdwell (HOY14)
4 Representations – 2 Objections, 1 Support, 1 Conditional Support
A more realistic density for the site would be 20 - 25 dwellings per ha due to access and neighbouring use constraints.
The site appears to be in allotment use. The loss of these allotments would have a negative impact on
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
40
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
the community.
Concerns regarding highways congestion and safety.
Potential impact on heritage assets and need for mitigation.
H6 Greenside Lane, Hoyland, Barnsley
No representations
H7 Land off Clough Fields Road, Hoyland, Barnsley
No representations
H8 Land off Meadowfield Drive, Hoyland, Barnsley
No representations
H9 Land off Welland Crescent, Elsecar, Barnsley
1 Representation – 1 Objection
A more appropriate and realistic density for the site would be between 20 and 30 dwellings per ha.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with
H16 Land North of Hoyland Road, Hoyland Common
321 Representations - 317 Objections (including a petition containing 166 valid entries), 2 Comments, 1 Support, 1 Conditional Support Concerns include:
Highways congestion and safety.
Concerns about the disruption caused by this proposal, particularly in an area where residents are already concerned about the impact of HS2.
Query regarding the impact on and provision of public utilities.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with
41
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Pressure on schools, health services, community facilities, local amenities and emergency services.
Biodiversity and ecological impact.
Concern regarding a fault line which runs through the site.
The site floods and is used for drainage for adjacent development.
Negative impact on the landscape.
Health impacts caused by increased levels of pollution.
Loss of Green Belt, Countryside and agricultural land.
Questions the integrity of the Green Belt review.
Questions the need for more housing.
Brownfield sites should be developed first.
Loss of community and identity.
Increase in crime levels.
Loss of privacy.
Non planning issues (impact on property values, loss of views).
Impact on quality of life during, and after, construction
Loss of recreation space/footpaths
Support the allocation, subject to relevant policy amendments.
Petition objects to the proposed sites due to lack of awareness of the consultation and request to be consulted at
42
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
next stage of process
H37 Land North of Railway Station, King Street, Hoyland
No representations
H45 Springwood Farm and surrounding land, Hoyland
20 Representations – 19 Objections, 1 Conditional Support Concerns include:
Highways capacity, congestion and safety.
The disruption caused by this proposal, particularly in an area where residents are already concerned about the impact of HS2.
Pressure on schools, health services, community facilities, local amenities and emergency services.
Loss of Green Belt, countryside, agricultural land, Green space and paths for recreational use.
Biodiversity and ecological impact.
Health impacts caused by increased levels of pollution.
Questions the need for more housing.
Brownfield sites should be developed first.
Increase in crime rates.
Loss of privacy.
Disruption caused during construction.
Support, subject to the provision of higher density development.
Non-planning issues (loss of views, devaluation of property).
Loss of local identity
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with
43
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
H46 Land west of Fitzwilliam Street, Hoyland/ Elsecar
4 Representations – 2 Objections, 1 Comment, 1 Support
Development will connect Hoyland and Elsecar. Elsecar is defined as a village, but does not seem to have the same safeguards as villages in the west of the borough.
Potential impact on Elsecar Conservation Area and adverse impact on tourism.
The site is not proposed as a housing allocation in the Publication version.
H77 Land West of Upper Hoyland Road
143 Representations – 142 Objections, 1 Support Concerns include:
Highways capacity, congestion and safety.
Concerns about the disruption caused by this proposal, particularly in an area where residents are already concerned about the impact of HS2.
Query regarding the impact on and provision of public utilities.
Pressure on schools, health services, community facilities, local amenities and emergency services.
Loss of Green Belt, countryside, Green space and paths for recreational use.
Biodiversity and ecological impact.
The site floods and is used for drainage for adjacent development.
Impact on the setting of a listed building.
Concerns regarding the effect of increased pollution on the health of the community.
Loss of community and identity.
Loss of privacy.
Questions the need for more housing.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
44
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Brownfield sites should be developed first.
Increase in crime levels.
Non planning issues (loss of views).
Impact on quality of life during, and after, construction
H78 Land North of Armroyd Lane
2 Representations – 1 Objection, 1 Conditional Support
Loss of unique character and impact on tourism.
Support, subject to criticism of the housing site selection methodology.
The site is not proposed as a housing allocation in the Publication version.
H79 Land North of Wood Walk, Hoyland
1 Representation – 1 Support The site is not proposed as a housing allocation in the Publication version. It is proposed as Safeguarded Land which is land which may be considered to meet longer term needs after the plan period.
H85 Land North East of Hemingfield
76 Representations – 72 Objections, 3 Supports, 1 Comment Concerns include:
Highways capacity, congestion and safety.
Pressure on existing and need for more schools and health services.
Increased pressure on Community facilities, local amenities and the emergency services.
Concern at loss of Green Belt, countryside, agricultural land and paths and bridleways.
Questions the need for more housing.
Brownfield sites should be developed first.
Biodiversity and ecological impact.
The site is not proposed as a housing allocation in the Publication version. It is proposed as Safeguarded Land which is land which may be considered to meet longer term needs after the plan period.
45
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Concern that village will lose its character and identity.
Negative impact on the landscape and visual amenity.
Disruption caused to existing residents through construction works.
Development of this land will increase flood risk.
Site is unsuitable due to noise and air pollution from the Dearne Valley Parkway.
Non Planning (loss of views from property).
Table 16 Penistone 13 Representations – 12 Objections, 1 Comment Concerns include:
The scale of development will cause Penistone to lose its identity as a rural market town.
Highway capacity, congestion and safety.
The impact on, and the ability of, infrastructure, health services and schools to cope.
Loss of Green Belt, which will damage the landscape and local wildlife.
Brownfield sites should be developed first.
The anticipated yields of the sites are unrealistic.
More affordable housing is needed.
A new town should be built.
The majority of sites are not LUTI compliant and will require comprehensive public transport solutions.
Some of issues raised have been considered through the housing site selection process.
H25 Land at Talbot Road, Penistone, S36
12 Representations – 12 Objections
The site is proposed as a housing allocation in the Publication version. Some of the
46
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
9ED Concerns regarding highways capacity, congestion and safety.
Concerns regarding the impact on infrastructure, health services, schools, community facilities and emergency services.
Impact on the adjacent conservation area, character of the town and landscape.
Impact on drainage.
Increased levels of pollution.
Site has limited appeal for aspirational housing.
The anticipated yield of the site is too high.
issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H26 Land West of Talbot Road, Penistone, S36 9ED
10 Representations – 10 Objections
Concerns regarding highways capacity, congestion and safety.
Concerns regarding the impact on infrastructure, schools and community facilities and emergency services.
Impact on drainage.
Increased levels of pollution.
Site has limited appeal for aspirational housing.
The anticipated yield of the site is too high.
The site is not proposed as a housing allocation in the Publication version.
H34 Land East of Saunderson Avenue, Penistone
11 Representations – 10 Objections, 1 Support
Concerns regarding highways capacity, congestion and safety.
Loss of Greenfield land will result in increased flood risk.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
47
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Concerned about the impact on infrastructure and schools.
The proposal represents over development.
Site has limited appeal for aspirational housing.
The anticipated yield of the site is too high.
H47 Land South East of Schole Hill Lane, Penistone, S36 9AW
10 Representations – 10 Objections
Concerns regarding highways capacity, congestion and safety.
Concerned about the impact on schools, health services and the landscape.
Negative impact on tourism.
Increased levels of pollution.
Brownfield sites should be developed first.
Site has limited appeal for aspirational housing.
The site is proposed as a housing allocation in the Publication version. It has planning permission which was granted after 1st April 2014.
H69 Land at Sheffield Road, Penistone
8 Representations – 7 Objections, 1 Support
Concerns regarding highways capacity, congestion and safety.
Concerned about the impact on infrastructure and schools.
Part of the site is subject to flooding.
Site has limited appeal for aspirational housing.
Site remediation costs make the site unviable.
The site is not proposed as a housing allocation in the Publication version.
H80 Land North & East of Joan Royd Lane, Cubley
21 Representations – 19 Objections, 2 Supports
Concerns regarding highways capacity, congestion, safety and parking.
The site is not proposed as a housing allocation in the Publication version.
48
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Public transport links are poor.
Pressure on schools, health services, community facilities and emergency services.
Drainage and flood risk concerns due to increased surface water run off.
Loss of Green Belt, Green Space, countryside and agricultural land.
Damage to the character of the market town and the landscape.
Biodiversity and ecological impact.
Site has limited appeal for aspirational housing.
The anticipated yield of the site is too high.
Pollution from increase in traffic will have negative quality of life and health impacts.
Question the need for more housing, more employment land is needed.
Brownfield sites should be developed first.
H81 Land South of Well House Lane, Penistone
27 Representations – 26 Objections, 1 Conditional Support
Concerns regarding highways capacity, congestion, safety and parking.
Site has poor public transport links.
Concerned about the impact on utilities infrastructure, schools and health services.
Loss of Green Belt and agricultural land.
Concerns that urban sprawl will damage the character of the area.
Biodiversity, ecological and landscape impact,
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
49
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
particularly in the Scout Dike area.
Loss of jobs
Residential restrictions are in place on part of the site due to HSE statutory licencing constraints.
Question the need for more housing.
Site has limited appeal for aspirational housing.
More affordable housing is needed.
Drainage issues could increase flood risk in the wider area.
Increased levels of pollution.
Brownfield sites should be developed first.
H82 Land South of Halifax Road, Penistone
30 Representations – 27 Objections, 2 Supports, 1 Conditional support
Concerns regarding highways capacity, congestion, safety and parking.
Site has poor public transport links.
Concerned about the impact on utilities infrastructure, schools, and health services.
Loss of Green Belt, Green Space and agricultural land.
Concerns that urban sprawl will damage the character of the area.
Biodiversity, ecological and landscape impact, particularly in the Scout Dike area.
Loss of jobs
Increased levels of pollution.
Questions need for more housing.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
50
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Site has limited appeal for aspirational housing.
Brownfield sites should be developed first.
Residential restrictions are in place on part of the site due to HSE statutory licencing constraints.
Support, however anticipated yield of the site is too high.
Table 17 Royston 2 Representations – 1 Objection, 1 Comment
The relevant infrastructure should be put in place before new houses are built.
Some sites have accessibility challenges from a LUTI perspective.
Accessibility has been taken into account as part of the housing site selection process. Infrastructure to support the delivery of the Plan has been considered in the Infrastructure Delivery Plan.
H11 Land off Lee Lane, Royston
5 Representations – 5 Objections
Concerns regarding highways capacity, congestion, safety and parking.
Concerned about the impact on schools and health services.
Loss of Green Belt, Greenfield land and public rights of way.
Biodiversity and ecological impact.
Concerns regarding ground stability due to recent subsidence and flooding events.
Question the need for more housing.
Objects to the requirement for a masterplan for the site.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
51
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
H35 Land North West of Windmill Terrace, Royston
No representations
H43 Land at end of Monkton Way
No representations
H58 Land at Lineside Lane, Royston
No representations
Table 18 Wombwell 1 Representation – 1 Comment
Residential growth generally supported but some sites require public transport improvements.
Public transport accessibility is considered as part of the site selection process.
H3 Land to the South of Doncaster Road, Darfield
11 Representations – 9 Objections, 2 Supports
Concerns regarding highways capacity, congestion, safety and parking.
Pressure on infrastructure, schools and health services.
Development may be restricted by the underground pipeline which runs through the site.
Development would increase flood risk due to surface water run off.
Concerns that site many be contaminated as it is on a former landfill site.
Loss of agricultural land.
Questions the need for more housing and the impact it would have on the village.
Existing bungalows would be overshadowed by the new development.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
52
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Brownfield sites should be developed first.
Smaller scale development would be more appropriate.
H27 Site of Former Wombwell High School, Wombwell
1 Representation – 1 Objection
Concerns regarding highways capacity, congestion and safety.
Concerns regarding the loss of recreational Green Space.
Access should be from the Dearne Valley Parkway.
The site is proposed as a mixed use site in the Publication version for housing and a primary school. A site policy is provided which sets out the issues that need to be addressed.
H36 Land North of Barnsley Road, Wombwell
No representations
H40 Site of the Former Foulstone School Playing Fields, Darfield
5 Representations – 5 Objections
Concerns regarding highways capacity, congestion, safety and parking.
Pressure on infrastructure, schools and health services.
Loss of recreational Green Space.
Questions the need for more housing and the impact it would have on the village.
More affordable housing is required.
Threat of anti-social behaviour.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
H41 Site of the Former Foulstone School, Darfield
2 Representations – 2 Objections
Concerns regarding highways capacity, congestion, safety and parking.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site
53
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Pressure on schools and health services.
Questions the need for another supermarket.
policy is provided to set out issues that need to be dealt with.
H56 Land to the rear of Kings Oak Primary School, Wombwell
No representations
H63 Land off Newsome Avenue, Barnsley
No representations
H64 Former Kings Road School Site, Wombwell
No representations
H70 Land East of Lundhill Road, Wombwell
4 Representations – 2 Objections, 2 Supports
Concerns regarding highways capacity and congestion.
The site should be shown as safeguarded land.
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be dealt with.
Policy H3 Housing Site Policies
17 representations – 12 objections 1 support
Questions why some sites do not have site policies and why site policies are not more restrictive to exercise greater control over development.
Numerous objections seeking amendments to various site specific policies
Considers policy unsound and suggests amendments to wording
Objects to the policy on the basis it is almost entirely about numerical housing targets
Considers all site specific policies should provide cycle links alongside pedestrian links, particularly
In the Publication version we have taken the approach to put each site in a site policy orange box, rather than in a list. Where the orange boxes do not contain any further details other than reference number, address and indicative yield, this means there were no specific issues to be raised other than those that will be dealt with through other policies of the Local Plan, for example GD1.
54
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
those that link to local schools, retail developments.
Objection. The site specific policies for sites in proximity to local wildlife sites should be amended to ensure that development avoids impacts, or includes appropriate and effective mitigation measures where necessary.
Welcome inclusion of protection and suggestions of enhancements to biodiversity, landscape and access assets in site policies
Comments that the plan should make specific reference to the use of LUTI in assessing sites
Concern at the potential impact on the highway network in Wakefield from developments in the vicinity of Woolley Grange
Policy H4 Uses on Allocated Housing Sites
2 representations – 2 objections
Considers policy needs revising to provide greater flexibility and suggests revised wording
Objects to the policy on the basis it is almost entirely about numerical housing targets
Policy H4 remains unchanged as it is considered appropriate to protect housing land supply to ensure we are able to meet our Objectively Assessed Housing Need by ensuring other uses on housing allocations are restricted to small scale ancillary uses or those that provide a service or facility to serve local residents
Policy H5 Residential development on Small Non-allocated Sites
5 representations – 5 objections
Considers that policies H5 and H6 could be combined to form a single policy
Suggest dependency on windfall sites should be reduced by identifying additional sustainable sites
Objects to the policy on the basis it is almost entirely about numerical housing targets
Policies H5 and H6 remain as separate policies. The reference to settlement boundaries has been removed from the policy and supporting text.
55
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Policy H6 Residential development on Large Non-allocated Sites
10 representations – 7 objections, 3 support
Considers that policies H5 and H6 could be combined and particularly objects to the requirement that sites over 0.4ha will be expected to be on brownfield land
Considers the policy should not preclude development of Greenfield sites within development boundaries.
Recommends that policy H6 be deleted and larger sites be treated against the same policy considerations as policy H5 to provide greater flexibility within the plan and provide a more viable source of windfall sites over the plan period.
Considers policy needs revising to provide greater flexibility and suggests revised wording
Objects to the policy on the basis it is almost entirely about numerical housing targets
Support for principles of policy
Welcomes policy subject to developers being asked to prove how the residential area is accessible and supports active travel
Policies H5 and H6 remain as separate policies. The policy has been amended to reflect comments. Proposed wording reads priority will be given to sites located on previously developed land and within Urban Barnsley and the Principal Towns. Text relating to greenfield sites which are not allocated will not be released until all allocations have been delivered or those left are not deliverable has been deleted.
Table 19 Essential Facilities
1 representation
Objects to inclusion of doctors’ practices in this table and suggests tables 19 & 20 could be combined.
Table remains unchanged and tables remain separate. It is considered helpful to separate essential and other facilities.
Table 20 Other Services/Facilities
No representations
Figure 3 1 representation – 1 comment
Support noted.
56
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Welcomes the clarity of the diagram which will facilitate transport planning
Policy H7 Housing Mix and Efficient Use of Land
15 representations – 11 objections, 2 support
The expected density of 40 dph is too high and seeks clarification for the justification
Would like to see more flexibility in the density approach
Policy could enable densities that are far too low to address existing problems
Concerns expressed that OAHN numbers are too low and should be raised.
Concerns that some developments won’t achieve the expected density due to site constraints affecting the ability to achieve the housing requirement
Supports the objective to provide an appropriate mix of housing in particular larger, executive type, housing to support aspirations of the economic policies.
Comment recommending an aspirational housing policy be included in Local Plan
Policy remains unchanged. We consider about 40 to be reasonable and it is borne out by monitoring data. We consider the policy to contain sufficient flexibility to enable a site to be developed at an appropriate density.
Policy H8 Affordable Housing
11 representations – 6 objections, 2 support
Objects to the threshold of 15 or more dwellings as inappropriate for rural areas where it will severely limit the opportunities for affordable housing
Notes there is no percentage requirement for Cudworth and suggests this should be 10%.
Policy remains unchanged. Cudworth is an omission and will be rectified. Viability work was updated in 2015 and will be made available with Publication version. Further information on our approach is in the Plan Wide Viability Study.
57
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Objection seeking further clarification and justification of specific percentage requirements.
Considers viability work supporting draft policy is out of date. Further viability work should be undertaken prior to the next stage of consultation
Objects to policy as is considered to include a deeply flawed get out clause which will make it difficult to secure affordable housing
Welcomes the statement "The developer must show that arrangements have been put in place to keep the new homes affordable." within the policy.
Support for policy and 10% contribution in Royston although seeks to ensure this is subject to viability testing
Policy H9 Housing Regeneration Areas
1 representation – objection
Request to include Cudworth in list of areas of low housing demand
Policy remains unchanged.
Policy H10 Protection of Existing larger Dwellings
No representations
Policy GT1 Sites for Travellers and Travelling Showpeople
4 representations – 1 objection, 1 support, 2 conditional support
Policy considered unsound as evidence base is out of date
Considers insufficient sites identified to meet existing need
Why can’t land be released from Green Belt as it has been for housing?
Policy remains unchanged. An updated needs assessment has been carried out which identifies a five year requirement of 15 pitches between 2014/15 and 2018/19. A further annualised requirement of 1.83 pitches can be applied to account for household formation. Two sites are proposed to deliver a total of
58
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Reference to flood risk in the policy should be in line with NPPF/PPG
Welcomes inclusion of the 3 site allocations
2 representations proposing additional sites for consideration
up to 18 pitches. One of the sites is in Green Belt.
Site TRAV013A 466 representations – 459 objections, 7 comments
Impact on local business/ jobs/economy
Concerns regarding highway/road safety due to proximity to main road
Lack of existing local services to support proposed development i.e. school places/health services
Lack of existing local amenities to support proposed development i.e. shops, chemist, library
Visual impact on existing residents and future occupiers of the site
Lack of privacy for existing and new residents
Impact on site from noise/air pollution due to proximity to industrial estate
Cost of developing the site due to land contours
Effect of development on wildlife and biodiversity – is an ecology survey required?
Loss of green space/Green Belt
Flood risk – site prone to flooding
Loss of footpaths/community recreation land
Decrease in property values
Concerns regarding anti-social behaviour
Effect on the environment
Effect on local character
Part of the site is proposed as a Gypsy and Traveller site in the Publication version. Some of the issues raised have been covered through the site selection process.
59
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Lack of public transport
Other sites in the Borough are more suitable
Comments on flood risk management issues on various sites
Considers scoring methodology is flawed
Other non-planning issues (safety, security, lifestyle concerns)
Site TRAV080 1 representation supporting continued use of site for family occupation
Site not proposed as an allocation in Publication version
Site TRAV082A 1 representation commenting on presence of watercourse on site
Site not proposed as an allocation in Publication version
Policy T1 Accessibility Priorities
14 Representations – 8 objections,1support/comment, 1 conditional support, 4 comments
Concern that the emerging Transport Strategy priorities are not shown in the Local Plan
Request that the emerging Transport Strategy considers active ways to restrict the use of country roads as short cuts.
Concern raised regarding a number of highways issues and constraints across the Borough
Expresses concern at lack of reference to needs of horse riders and considers that alternatives to busy roads must be provided for all vulnerable road users, including horse riders
Car parking provision will be necessary in certain rural locations and the Plan and forthcoming Transport Strategy should allow for this.
Policy fails to concentrate on Barnsley's strengths
The Barnsley Transport Strategy was adopted in 2015. Further work is ongoing to develop an implementation plan which would detail projects and schemes. The policy seeks to improve access, particularly between prinicipal towns
60
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
i.e. good motorway links and its location between two large cities. Economic growth should not be stifled by restricting car travel.
Comments on inadequacy of public transport between Penistone and Barnsley
General support for the transport policies, but has serious concerns associated with the proposed locations of new development and the way in which transport impacts of new developments are assessed. Suggests amendments
Notes the consistency of the policy with Sheffield’s Core Strategy policy CSP56 Priority Routes for Bus and Rapid Transport. Suggests that it may also be appropriate to highlight potential future improvements to connectivity in the Penistone-Stocksbridge-Sheffield axis.
Supports the councils focus on good transport connectivity. Neighbouring authority would be willing to collaborate to promote better transport services to connect with the proposed HS2 station proposed at Meadowhall.
Proposes alternative potential new entry/exit to M1.
Asks if consultation will take place with local residents, cycling and walking groups to help identify priority corridors and the infrastructure improvements required to make this safe for both cyclists and pedestrians
Figure 4 No representations
Figure 5 No representations
Policy T2 4 representations – 2 objections, 1 support The policy remains unchanged. The
61
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Safeguarding of Former Railway Lines
Suggests that consideration could be given to interim arrangements for former railway lines to be developed into walking and cycle ways
Asks if consultation will take place with local residents, equality groups, cycling and walking groups to help identify priority corridors and the infrastructure improvements required to make this safe for both cyclists and pedestrians.
General support for the transport policies, but has serious concerns associated with the proposed locations of new development and the way in which transport impacts of new developments are assessed. Suggests amendments.
Continues to support the policy as, although HS2 is referenced in the document, it is still too early to know whether the final route will impact on the potential for reinstatement of the former railway lines in the plan period
Local Plan should take account of Neighbourhood Plan proposals to enhance and improve access to the Trans Pennine Trail. The route should also be protected as a National route to facilitate sustainable transport
transport implications of proposed development are considered in the site selection process or planning application process. Protection and enhancement of the Trans Pennine Trail would be supported under Green Infrastructure policies and policy GS2 on Green Ways and Public Rights of Way.
Figure 6 No representations
Policy T3 New Development and Sustainable Travel
8 representations – 6 objections, 1 support
Asks how travel plans are monitored and whether we can provide more proactive advice to developers about how to incorporate active travel into design
The policy remains unchanged. The policy signposts to Good Practice guidance on Travel Plans. The current requirements for car parking are
62
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Comments on the importance of developer contributions element of the plan, both for new and existing infrastructure
Welcomes approach to Travel Plans and suggests new policy on other measures to increase sustainable travel and low carbon vehicle infrastructure
Seeks clarification on requirements for car parking
Has concerns that development may significantly impact on level crossing safety and service provision and considers that these potential impacts should be addressed through the Local Plan,
Seeks reference in policy to require developer contributions to secure appropriate improvements to rail infrastructure.
General support for the transport policies, but has serious concerns associated with the proposed locations of new development and the way in which transport impacts of new developments are assessed. Suggests amendments
set out in the Supplementary Planning Document Parking adopted in 2012.
Policy T4 New Development and Highway Improvement
3 representations – 1 objection, 1 support
General support for the transport policies, but has serious concerns associated with the proposed locations of new development and the way in which transport impacts of new developments are assessed. Suggests amendments
General support for policy but considers need for design to facilitate access to public transport facilities should be clarified
The policy remains unchanged. The transport implications of proposed development are considered in the site selection process or planning application process.
63
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Comment on highway design with a view to encouraging liveable space
Policy T5 Reducing the Impact of Road Travel
3 representations – 3 objections
General support for the transport policies, but has serious concerns associated with the proposed locations of new development and the way in which transport impacts of new developments are assessed. Suggests amendments
Asks questions regarding promotion of the use of Eco Stars; promotion of cycle awareness training for freight; provision of more on road cycle training for adults targeting businesses
Various amendments and alterations suggested to policy wording
The policy remains unchanged. The transport implications of proposed development are considered in the site selection process or planning application process. Proejcts and initiatives such as Eco Stars and active travel are promoted by other services of the Council and partners.
Policy D1 Design 11 representations – 4 objections, 4 support, 3 comments, 1 conditional support
Considers policy should be reviewed to place emphasis on seeking quality development
Objects to policy as consider it places onerous requirements on developers
Considers Police 'Secure By Design' initiative should be included within the local plan, as with other authorities
Policy should be amended to indicate that the Council will encourage the use of Building for Life 12 as a method for assessing design quality.
Support for the inclusion of Building for Life 12
Support for the policy and suggests amendments to
The policy remains unchanged. The south Yorkshire Residential Design Guide is used as best practice.
64
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
the opening paragraph to strengthen it
Comment seeking more emphasis on local circumstances and consideration of adoption of South Yorkshire Residential Design Guide
Welcomes emphasis on GI, habitats, woodlands, natural features and sustainable environment.
Asks whether community-led design can be incorporated into the planning process i.e. through masterplanning.
Policy HE1 The Historic Environment
5 representations – 2 objections,1 support, 2 conditional support
Comments on omissions from the policies map and discrepancies between the key and the map
Objects to lack of support in the document for private owner occupiers of historic and listed buildings who wish to improve their properties
Support for policy but would like the council to take proactive steps to protect and conserve all heritage assets.
Considers the council should take proactive steps to protect and conserve all heritage assets. Local lists of 'at risk' grade 2 listed buildings should be compiled and included in the Local Plan.
Supports the policy but would like a further building to be added to the list
The policy has been redrafted to take account of comments. We would not seek to include a list of at risk listed buildings in the Local Plan as this is information would become out of date.
Policy HE2 Conservation Areas – planning application procedure
2 representations – 1 objection, 1 support
Considers policy unsound and suggests revision required to consider consequences arising from the
The policy has been amended to take account of comments.
65
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
interpretation of 'setting'
General support for policy
Policy HE3 Listed Buildings – planning application procedure
2 representations – 1 objection, 1 support
Concerns regarding the interpretation of 'setting' and considers policy needs revising
General support for policy
The policy has been amended to take account of comments.
Policy HE4 Listed Buildings – demolition
1 representation in support
Supports the policy and considers the conditions for demolition should also apply to buildings on a local list.
The policy has been amended. It has also been re-numbered HE5
Policy HE5 Archaeology – planning application procedure
2 representations in support of the policy
Supports the policy
The policy has been amended and merged with policy HE6. The combined policy has been given the reference HE6.
Policy HE6 Archaeology and Development
1 representation supporting the policy
Supports the policy
The policy has been amended and merged with policy HE6. The combined policy has been given the reference HE6.
Policy HE7 Development Proposals Affecting a Historic Park or Garden
1 representation supporting the policy
Supports the policy
The policy has been amended and is now referenced HE4 Developments affecting Historic Areas or Landscapes
Policy TC1 Town Centres
7 representations – 3 objections, 2 support, 1 conditional support, 1 comment
Concerned that Darton is only designated as a 'local centre' which is considered to be at odds with Darton's inclusion in the highest priority for new
The policy remains unchanged.
66
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
housing build.
Support the inclusion of Kings Head Public House site within the defined Mapplewell local centre boundary
Questions how the aim to improve car parking in Penistone town centre will be achieved given the lack of available land in the town centre and the nature of proposed development sites in Penistone as a whole
Would like to see Barnsley West included in the list of District Centres
Supports Council's aspirations to promote economic regeneration and recommends minor policy amendments to recognise the Peel Centre's favourable location and ability to act as a key attractor for shopping visits to the town.
Concerns expressed at lack of reference to protecting community services in town centres, such as pubs
General support for overall approach of the policy
Policy TC2 Primary and Secondary Shopping Frontages
No representations received
Policy TC3 Thresholds for Impact Assessments
1 representation – objection
Considers the threshold for impact assessments outside the Primary Shopping Area of Barnsley Town Centre should be reduced to 1,000 square metres
The policy remains unchanged.
Policy TC4 Retail 1 representation – objection The policy remains unchanged.
67
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Parks
Considers that wording of the policy is not flexible enough and, as such, exceeds NPPF guidance. Proposes alternative wording.
Alternative site proposed for consideration
Policy TC5 Small Local Shops
2 representations – 1 objection, 1 conditional support
Can we be more proactive in capturing what local need comprises and do Area Councils have a role in facilitating this?
Supports wording of policy provided it can be used to support the enhancement and increase in retail provision at the hospital
The policy remains unchanged.
Table 21 8 representations – 4 comments,3 objections, 1 support
Suggests there are gaps in the current proposals for the Town Centre
Support for the Vision for Barnsley Town Centre and the intention to use the strengths of the town centre to deliver it
Welcome retail and leisure focus in the Town Centre but closure of Jumble Lane crossing should incorporate sustainable transport movements into the Town Centre.
Suitable parking for shoppers and visitors is desperately lacking, particularly disabled parking, leading to a decline in shopping. Suggests the use of free small 'rover' buses to improve access to shops and facilities and help reduce congestion.
Asks why is there no specific policy on homes and
Comments of support noted.
68
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
residential aspects of Barnsley Town Centre
Should there be a separate policy for Movement and Transport?
Table 22 No representations
Table 23 No representations
Table 24 No representations
Table 25 No representations
Policy BTC1 The daytime and evening economies
2 representations in support
General support for the policy and its principles
The policy remains unchanged.
Policy BTC2 Late Night Uses
1 representation in support
supportive of the restriction of late night opening to a defined area based on that outlined in BTC2
The policy remains unchanged.
Table 26 1 representation in support of the policy Support noted
Table 27 No representations
Policy BTC3 Public Spaces
2 representations in support
Support for principles of policy but considers more could be done to improve the setting of Mandela Gardens
The policy remains unchanged.
Policy BTC4 Improving Public Spaces
5 representations – 3 objections, 2 support
Seeks clarification as to whether policy only applies to sites within the Town Centre boundary
Suggests amended wording
Support the principle of BTC4 and the identification of thresholds above which developers should include proposal to create or improve public spaces
The policy remains unchanged. Under section 106 rules development would have to be reasonably well related to the site contributions are sought for. Therefore this policy will apply to developments in the Town Centre.
Policy BTC5 2 representations – 2 support The policy remains unchanged.
69
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Landmark Buildings
Supports the policy and suggests other buildings for inclusion as landmark buildings
Suggests there is a need to consider more distant views into and also out of the town centre reaching up to the skyline.
Policy BTC6 Building Heights
2 representations in support
Support for policy but notes the need to avoid wind tunnels and overshadowed areas as well as aesthetic and design considerations
The policy remains unchanged.
Policy BTC7 Gateways
2 representations in support
Supports the identification of Gateways to Barnsley Town Centre and requirement for development close to Gateways to be attractive
The policy remains unchanged.
Policy BTC8 Temporary Uses and Phased Development
2 representation in support
Supports policy as temporary activities are preferable to empty units
The policy remains unchanged.
Table 28 No representations
Policy BTC9 Cycling 2 representations in support
Supports the policy but questions if there is an overall cycle route plan and whether developers obligated to make contributions for providing a more cycle oriented environment? Also asks how breaks in the cycle routes can be avoided
Supports the policy as it provides the potential for
The policy remains unchanged. The Transport Strategy was adopted in 2015. Further work is ongoing to develop an implementation plan which will include details of projects and schemes.
70
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
active travel
Policy BTC10 The Green Sprint
2 representations in support
Supports the policy as it provides the potential for active travel
Supports the policy but seeks clarification on whether the whole of the Green Sprint is for pedestrians and cyclists as the map is not clear
The policy remains unchanged. Further detail will evolve as the detail of the Town Centre redevelopment progresses.
Table 29 No representations
Policy BTC11 Car Parks
1 representation in support
Supports the policy but points out the need for long stay car parking if visitors and shoppers are to be encouraged
The policy remains unchaged. It includes provision of long stay car parks.
Table 30 1 representation -
Objects that there do not appear to be policies to govern the visual appearance of shop frontages and signage
The policy remains unchanged. The design of shop frontages is covered by a Supplementary Planning document that currently hangs off the Core Strategy design policy. Shopfront Design remains on the list of proposed SPD’s in appendix 3 of the Local Plan. Once the Plan is adopted SPD’s will be refreshed and this would hang off policy D1 Design.
Table 31 No representations
Policy BTC12 The Markets Area District
3 representations - 1 objection, 2 support
Questions proposals for a cinema when there are no shops to attract people to the town centre
Welcomes inclusion of the statement ‘Pedestrian priority will be upgraded to make a safe environment
The policy remains unchanged.
71
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
for pedestrians and cyclists’
Policy BTC13 Development Site 1 – Better Barnsley including former TEC building and CEAG site
1 representation in support The policy remains unchanged.
Figure 8 No representations
Table 32 No representations
Policy BTC14 The Yards District
1 representation in support
Considers Doncaster Road has potential to be an area in its own right with the opportunity for small scale specialist shops
The policy remains unchanged.
Figure 9 No representations
Table 33 No representations
Policy BTC15 Southern Fringe
1 representation in support
Support for policy and considers there is a need for the preservation and enhancement of the remaining and adjoining architectural and historic character of the area
The policy remains unchanged
Policy BTC16 Development Site 2 – Heelis Street/New Street/Gala Bingo/ Burleigh Court Site
3 representations – 2 objections, 1 support,
Considers the proposed uses are too prescriptive and need to be widened. Considers that the ability to offer a wider variety of uses will enable promotion of their vacant site which will, in turn, benefit the viability of the town centre by encouraging linked trips.
The policy remains unchanged. Some of the supporting text has been updated.
72
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Considers that the policy should incorporate improvements to pedestrian and cycling access throughout the area and to the proposed retail outlets.
Supports policy principles. The apartments at City Reach will be an asset once completed.
Figure 10 No representations
Table 34 No representations
Policy BTC17 Southgate District
1 representation in support
Supports the principles of the policy and considers it is vital to conserve the architectural heritage of the three former Co-op buildings including Wellington House, the former Hedonism, the former Salvation Army Building and Theatre Royal.
The policy remains unchanged
Figure 11 No representations
Table 35 No representations
BTC18 Westgate/Churchfields
3 representations – 1 objection, 2 support
Support for the principles of the policy and priority for office development but questions how the Lamproom Theatre can be expanded without losing its character
General support for policy
Considers that the policy should include improvements to Westgate to allow cyclist access in both directions
The policy remains unchanged.
Figure12 No representations
Table 36 No representations
BTC19 Market Hill 2 representations in support The policy remains unchanged. The historic
73
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Supports policy but considers that the boundaries and overlaps with adjoining areas are unclear and attention to neighbouring conservation areas is essential
environment policies
Figure13 No representations
Table 37 No representations
BTC20 The Lanes 1 representation in support
The policy remains unchanged
Figure14 No representations
Table 38 No representations
BTC21 Courthouse Campus
1 representation in support
Supports the policy as the area is not currently used efficiently
The policy remains unchanged apart from a correction to a policy reference.
BTC22 Development Site 3 – Courthouse Campus
2 representations – 1 objection, 1 support
Suggested change to policy wording to include reference to Listed Buildings.
Minor amendments have been made. Listed Buildings are protected by the historic environment policies.
Figure 15 No representations
Table 39 No representations
BTC23 Eastern gateway
1 representation in support
Supports the enhancement of the Transport Interchange hub
The policy remains unchanged
BTC24 Development Site 4 – Land between the Transport
1 representation in support
Supports the principles of the policy and the uses
A minor change has been made to this policy.
74
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Interchange and Harborough Hill Road
proposed. Also supports the opportunity for ‘tall buildings’ if carefully considered
Figure 16 No representations
Table 40 No representations
Table 41 No representations
Figure17 2 representations – 1 objection, 1 support/comment
Trans-Pennine Trail should be included in this plan
Supports the inclusion of Regionally Important Geological and Geomorphological Sites and non-designated geological features within Green Infrastructure
The diagram is included in the Publication version.
Policy GI1 Green Infrastructure
11 representations – 4 comments,3 support, 3 objections, 1 conditional support
Welcomes the approach outlined in Policy and would also welcome the publication of the Barnsley Green Infrastructure Strategy.
Supports the policy and suggests Historic Landscape Corridor could be extended into Rotherham to include Grade II* Wentworth Woodhouse Estate
Concerns that policy does not include provision for horse riders as vulnerable road users who would be affected by increased traffic arising from new developments and requests that multi-user routes are provided where possible.
Suggests changes to Policy and supporting text
Pleased to see the importance of green
The policy wording has been amended to include reference to blue and green spaces.
75
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
infrastructure is acknowledged and that river networks are included in the list of important assets. Links to SuDS policy CC4 should be mentioned here.
Comment suggesting a stronger commitment in this policy for tree planting and woodland creation
Comments on reference to PPS9 which no longer exists.
Welcomes the policy and positive strategic approach but suggests more detailed mapping
Policy GI2 Canals – Safeguarded Routes
4 representations – 3 objections, 1 comment
Concern that needs of horse riders as vulnerable road users have been ignored and that canals have potential to provide routes for all categories of user, including horse riders, who need greater provision to avoid increasingly busy roads.
Considers that the Trans Pennine Trail should be included in this policy.
Objects to the policies not safeguarding disused parts of the former canal, to allow future restoration.
The policy has been amended to include a reference to horse riding networks.
Policy GS1 Green Space
26 representations – 14 objections, 9 supports (including a petition containing 7 valid entries), 3 comments
Objects to development of Green Belt
Suggested amendment to allocate additional land within the Green Space designation
Seeks allocation of additional land in Penistone for allotments
Policy does not provide sufficient protection for
Where necessary, the policy has been amended to take account of comments.
76
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Green Space, nor adequate provision to secure new green space through development
Numerous objections seeking removal of individual sites from green space allocation and re-allocation for other uses
Questions how policy will be monitored and appropriate compensation determined
Support for minor amendment at Grimethorpe to remove land from Green Belt and re-allocate as green space
Petition supports continued allocation of land at Boggard Lane, Penistone for allotment use
Policy GS2 Green Ways and Public Rights of Way
5 representations – 2 objections, 2 comments, 1 support
Requests provision of multi-user routes where appropriate to provide safe routes for all vulnerable road users.
Objects to policy, on the basis that it does not provide sufficient protection for green ways, nor adequate provision to provide for new green spaces through development
Support for Policy and approach that Green Ways should, where necessary, be diverted in order to ensure developments can progress
Comment questioning whether we have the appropriate resources to monitor and police the plan requirements
Welcomes the policy and encourages consideration
The policy remains unchanged. We consider it does provide protection for green ways. Policy GS1 is the appropriate policy to secure new green spaces.
77
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
of access to natural features and existing long distance trails within new developments where appropriate.
Policy BIO1 Biodiversity and Geodiversity
10 representations – 4 objections, 3 conditional support, 2 comments, 1 support/comment
Considers habitat and biodiversity requirements for sites should be assessed by an ecologist
Supports the policy and welcomes strong emphasis on enhancement but considers that Old Moor should be included as a key ecological asset and suggests additional wording to supporting text.
Supports the inclusion of the Dearne Valley Nature Improvement Area into the Local Plan and supports the intention to adopt a NIA Planning Advice Note.
Consider the policy should include the principle at para.118 of the NPPF in order to protect irreplaceable habitats, such as ancient woodland, for which development impacts are difficult, if not impossible, to mitigate and compensate for.
Supports the policy but suggests a change to the wording to include 'protection of ancient and veteran trees'.
Supports the policy and the approach identified in the Sustainability Appraisal, but makes recommendations on how the wording can be changed to strengthen the position of Biodiversity and Geodiversity in the Local Plan.
Welcomes the expectation for developments to conserve and enhance the biodiversity and
Where necessary, the policy has been amended to take account of comments
78
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
geological features of the borough and welcomes the preparation of SPD on Biodiversity and Geodiversity
Welcomes the policy. Suggests some stronger wording for final bullet point and considers para 18.24 listing key ecological assets should include reference to NIA.
Comments on Habitats Regulations Assessment including some concern over how and at what stage potential impacts on protected sites are proposed to be dealt with and the provision of further information is recommended.
Concern at failure to address potential risks associated with recreational pressures at identified hot spots.
Table 42 No representations
Policy LC1 landscape Character
3 representations – 1 objection, 1 support, 1 comment
Makes particular reference to development which may affect the setting of fringe landscapes of the Peak District National Park and offers suggestions on possible forms of wording.
Supports the policy
Welcomes the policy but strongly recommends the inclusion of specific reference to Peak District National Park.
Text has been added which reads ‘Development which may adversely affect the purpose of the Peak District National Park or be harmful to its valued characteristics will not be allowed’.
Policy GB1 Protection of Green Belt
113 representations – 100 objections, 7 comments, 2 support, 4 conditional support
83 objections seeking removal of various sites from
The policy remains unchanged.
79
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
the Green Belt and re-allocation for other purposes
Objections to use of Green Belt land when brownfield/other land is available
Objection to proposed Green Belt changes north of Penistone
Green Belt review appears to conflict with aim of increasing biodiversity in the area
Current housing stock should be improved before taking Green Belt land
Considers the Green Belt review is flawed
Supports policy subject to a robust review of the Green Belt, to enable sustainable sites not required to protect openness of the Green Belt to be allocated for housing/employment uses
Support for various Green Belt amendments
Notes that the Green Belt Review is in line with the SCR common approach and therefore contributes to Duty to Cooperate
Extensive representation on deliverability of sites in Penistone
Policy GB2 Replacement, extension and alteration of existing buildings in the Green Belt
4 representations – 4 objections
Objects to policy as it is too restrictive and not compliant with the NPPF
Policy should be rewritten to take para.89 of NPPF into account
The policy has been changed slightly. We consider the policy to be NPPF compliant
Policy GB3 Changes of use in the Green Belt
3 representations – 3 objections
Objects to policy as it is too restrictive and not
The policy remains unchanged. We consider the policy to be NPPF compliant.
80
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
compliant with the NPPF
Policy GB4 Permanent Agricultural and Forestry Workers Dwellings
No representations
Policy GB5 Temporary Agricultural and Forestry Workers Dwellings
No representations
Table 43 Safeguarded Sites
7 representations - 6 objections, 1 objection/comment
Concern expressed regarding quantum of safeguarded sites identified and considers additional safeguarded land should be allocated to ensure a robust Plan
Supports the principle of safeguarded land but does not consider that sufficient sites have been identified in Royston
Welcomes the protection of sites in the west of the Borough for the foreseeable future but has concerns that, if developed, these parcels are comparatively large in relation to the settlements they border.
Comments on flood risk management issues on various sites
Comments on deliverability and availability of certain sites and suggests more land needs to be identified.
Comments noted regarding quantum. We have aimed to allocate enough land to provide capacity for a five year supply of housing development.
SAF1 North of Burton Road, West Green (a)
No representations
SAF2 South of Shaw No representations
81
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Lane, Carlton
SAF4 North of Burton Road, West Green (b)
No representations
SAF 5 North of Staincross Common
1 representation in objection
Proposes land should be allocated for Housing
The site is proposed as Safeguarded Land in the Publication version.
SAF 6 West of Barugh
1 representation in objection
Proposes land should be allocated for Housing
The site is proposed as Safeguarded Land in the Publication version.
SAF7 East of Sheffield Road, Hoyland Common
1 representation in objection
Objects to safeguarded allocation and proposes site for Housing
The site is proposed as Safeguarded Land in the Publication version.
SAF8 South of Hough Lane, Wombwell
No representations
SAF9 East of Sandybridge Lane, Shafton
No representations
SAF10 Land behind Queens Drive, Shafton
1 representation in objection
Objects to safeguarded designation and considers should be re-allocated for housing
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF12 North of Midland Road, Royston
2 representations – 1 objection, 1 comment
Considers site to be previously developed land and should, therefore, be allocated for housing
Considers land should be allocated for housing due to proximity to local services
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
82
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
SAF13 South of Church Hill Road, Royston
No representations
SAF14 South of Lowfield Road, Bolton
2 representations in objection
Concerns regarding proximity to Scheduled Ancient Monument
Objects to continued allocation as safeguarded and seeks allocation for housing
The site is proposed as a housing allocation in the Publication version, reference AC26.
SAF 15 South of Coniston Drive, Bolton
1 representation commenting that the site should be brought forward for housing immediately
The site is proposed as Safeguarded Land in the Publication version.
SAF16 West of Castle Lane, Penistone
No representations
SAF17 East of Castle Lane, Penistone
1 representation in support of the allocation The site is proposed as Safeguarded Land in the Publication version.
SAF18 North and South of Roughbirchworth Lane, Oxspring
2 representations – 1 objection, 1 support
Objects to proposed allocation as safeguarded land
Supports allocation but suggests any proposals should await publication of Oxspring Neighbourhood Plan
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF20 Off High Street, Great Houghton
No representations
SAF21 South of New Smithy Drive, Thurlstone
4 representations in objection Concerns regarding the implications of future development of the site. Key issues include:
Access, congestion and highway safety
Considers that SHLAA site 255 should be
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
83
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
disconnected from the wider SAF21 as it does not meet requirements to be classified as safeguarded land
Concerns regarding proximity to Conservation Area
SAF22 Site north of Halifax Road, Thurgoland
3 representations – 1 objection, 1 support, 1 conditional support
Objects to proposed allocation for safeguarded land -would prefer to retain existing housing allocation
Supports proposed allocation but considers site should be brought forward before 2033
Supports proposed allocation
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF23 South of Springwood, off Cote Lane, Thurgoland
3 representations – 2 objections, 1 support
Concerns regarding impact on nearby Listed park/gardens and Scheduled Ancient Monument
Objects to safeguarded allocation – would prefer site to be allocated for housing
Support for the allocation
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF24 South of Halifax Road, Thurgoland
2 representations in support of the proposed allocation The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF25 East of Beech Avenue, Silkstone Common
1 representation in support of the proposed allocation The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to
84
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
put them back into Green Belt.
SAF26 West of Church Heights, Hoylandswaine
3 representations – 2 objections, 1 support
Concerns regarding impact on setting of adjoining Grade II listed Church
Objects to safeguarded designation and considers site should be promoted to housing allocation due to pending decision on a planning application
Support for the allocation
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt. The setting of listed buildings will be taken into account in any future development of the site in accordance with the historic environment policies.
SAF27 North of Darton Road, Cawthorne
20 representations – 18 objections, 2 supports Numerous concerns regarding the implications of future development of the site. Key issues include:
Village lacks basic infrastructure e.g. schools, shops, health facilities, public transport, drainage, community facilities, to support more housing, people and traffic
Concerns regarding traffic and highway safety
Land should be re-designated as Green Belt
Site has history of flooding
Biodiversity issues
Impact on historic park/gardens and Conservation Area
Support for safeguarded allocation
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF28 South of Wellthorne Lane, Ingbirchworth
No representations
85
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
SAF30 Land South of Wellthorne Lane, Ingbirchworth
1 representation commenting that planning permission has already been granted for this site.
The site is proposed as Safeguarded Land in the Publication version. We acknowledge the point about the site already having planning permission therefore it is logical that it is shown as a housing allocation. However if the planning permission remains unimplemented we have taken the approach that it would be preferable as safeguarded land in the villages that we consider to be less sustainable than Urban Barnsley and Principal Towns. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF31 Land off Mortimer Road, Cubley
1 representation in objection
Concerns regarding impact on setting of nearby Grade II listed buildings
The site is proposed as Safeguarded Land in the Publication version. Any future development considered on the site will take into account the setting of listed buildings in accordance with historic envirnonment policies of the Plan.
SAF32 North of Upper Field Lane, High Hoyland
5 representations – 4 objections, 1 support
Concerns regarding impact on setting of adjacent Conservation Area
Part owner of site has no intention of selling the land and site is therefore undeliverable and request withdrawal as a potential development site.
Concerns regarding the implications of future development of the site due to impact on the Green
The site is proposed as Safeguarded Land in the Publication version. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
86
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Belt, impact on village character, access and highway safety issues, and lack of existing infrastructure, services and public utilities.
Support for safeguarded allocation
SAF33 Land off New Road and Lidgett Lane, Pilley
2 representations - 1 objection, 1 support/comment
Land should not be safeguarded as planning permission already granted and should, therefore be allocated for Housing
Supports the allocation but notes planning permission is already granted and questions the point of the consultation
The site is proposed as Safeguarded Land in the Publication version. We acknowledge the point about the site already having planning permission therefore it is logical that it is shown as a housing allocation. However if the planning permission remains unimplemented we have taken the approach that it would be preferable as safeguarded land in the villages that we consider to be less sustainable than Urban Barnsley and Principal Towns. We have rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF34 Land off Lidgett Lane and Pilley Green, Pilley
2 representations - 1 objection, 1 support/comment
Land should not be safeguarded as planning permission already granted and should, therefore be allocated for Housing
Supports the allocation but notes planning permission is already granted and questions the point of the consultation
The site is proposed as Safeguarded Land in the Publication version. We acknowledge the point about the site already having planning permission therefore it is logical that it is shown as a housing allocation. However if the planning permission remains unimplemented we have taken the approach that it would be preferable as safeguarded land in the villages that we consider to be less sustainable than Urban Barnsley and Principal Towns. We have
87
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
rolled forward the safeguarded land notation in all villages as we do not feel we could demonstrate exceptional circumstances to put them back into Green Belt.
SAF35 Land off Cemetery Road, Grimethorpe
No representations
SAF36 Land South of Broadwater Estate, Bolton on Dearne
1 representation in objection
Proposes change to housing allocation
The site is proposed to be put back into Green Belt in the Publication version due to site constraints.
SAF37 Land at Springvale, Penistone
No representations
SAF38 Land off Moors Avenue, Penistone
No representations
Policy GB6 Safeguarded Land
11 representations – 9 objections, 1 support, 1 conditional support
Objects to policy of removing land from Green Belt to create Safeguarded land as considers it substantially weakens the protection from inappropriate or premature development. Suggests policy be deleted.
Suggests in the absence of a clear housing target a higher number of Safeguarded sites needs to be allocated
Considers wording of paragraph 19.22 should be included within the policy
Objects to the wording of the policy and considers that greater flexibility should be included to bring safeguarded sites forward when circumstances
Allocation of safeguarded land is in accordance with NPPF paragraph 85. Policy remains unchanged. Amendments have been made to supporting text to clarify circumstances in which safeguarded land may be developed prior to Local Plan review.
88
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
require.
Recommends that the Council identifies further allocations of safeguarded land to ensure compliance with NPPF, paragraph 85
Considers policy to be sound in principle subject to further justification in its underlying approach
Policy CC1 Climate Change
8 representations – 4 objections, 2 support, 2 comments
Considers policy should set more specific targets for achievement and encourage more sustainable energy saving construction, particularly in new homes
Consider policy should be merged with Policy CC2 and parts of Policy RE1
Policy should make reference to viability
Consider policy contrary to NPPF paras. 17 and 111 and wording should be amended
2 representations welcoming the policy
Suggestion that the policy should include reference to the importance that trees and woods can make in mitigating climate change
Comments that a large part of climate change mitigation is how well development sites are integrated with public transport
CC1 and CC2 merged and now called Climate Change and Sustainable Construction.
Policy CC2 Sustainable Construction
9 representations – 6 objections, 2 comments, 1 conditional support
Considers policy should set more specific targets for achievement and encourage more sustainable energy saving construction, particularly in new homes
Policy has been deleted from the Publication version and some of the issues it covered have been subsumed into policy CC1.
89
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Consider policy should be merged with Policy CC1 and parts of Policy RE1
Policy should make reference to viability
Policy is unjustified and too onerous
Objects to policy and asks that it be strengthened to require all new homes to be zero-carbon
Paragraph 20.6Â is contrary to the Governments stated intentions for a Building Regulations only approach to energy.
Would like to see the promotion of water efficiency (measures and technologies) in building design, in order to reduce the demand for water consumption.
Comment seeking clarity as to whether development will be assessed against code for sustainable homes or through building regulations process.
Comment seeking clarification of application of BREEAM to non-residential development
Policy CC3 Flood Risk 3 representations – 3 objections
Objects to expectation to reduce surface water run-off by 30% on all brownfield sites and queries justification for this figure.
Seeks review of functional flood plain notation
Suggested amendments to wording of policy and supporting text
The policy remains largely unchanged. Text has been added regarding not allowing development in the Functional Floodplain (Flood Zone 3b) unless it can be demonstrated that there would not be a harmful effect on the ability of this land to store floodwater.
Policy CC4 Sustainable Drainage Systems (SuDS)
7 representations – 5 objections, 2 comments
Considers policy wording is too restrictive
Suggested amendments to policy wording and
The policy has been redrafted and now reads ‘All major development will be expected to use Sustainable Drainage Systems (SuDS) to manage surface water drainage, unless it can be demonstrated that
90
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
supporting text
Welcomes the policy but would also welcome reference to the protection of hydrologically sensitive habitats.
Seeks reference to 'detailed planning applications' in policy wording.
all types of SuDS are inappropriate. The Council will also promote the use of SuDS on minor development. To enable the Council to determine the suitability of a proposed SuDS scheme: Outline Planning applications must be supported by a conceptual drainage plan and SuDS design statement.Detailed Planning applications must be supported by a detailed drainage plan and SuDS design statement, which should contain information on how the SuDS will operate, be managed and maintained for the lifetime of the development.
Policy RE1 Low Carbon and Renewable Energy
10 representations –4 objections, 3 support, 2 conditional support, 1 comment
Supports the consideration that water resources are energy sources.
Support for policy wording as it positively allows development that produces renewable energy provided no harmful effect on bulleted list
Support in principle but suggests amended wording
Welcomes the policy
Support the policy but suggest reconsideration of wording as 'harm' to listed buildings as been held in recent Court decisions to rule out many wind turbine developments.
The Plan does not provide sufficient detail as to the appropriate siting of wind turbines. The Scottish Planning Policy approach should be considered.
The policy remains largely unchanged aside from some minor changes. Some supporting text has been added about the potential for water at or near the surface of flooded redundant mineworkings may form a sustainable local means to power ground source heat pumps.
91
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Considers policy unsound as it is not effective. Suggests amendments to combine CC1, CC2 and parts of RE1 into a new policy.
First paragraph of policy should be deleted as it duplicates policy CC2
Broadly support the policy and are pleased that the sensitivity of the South Pennine fringe landscapes have been recognised. Suggest some amendments to address the cumulative impact of wind turbines. Welcome the commitment to identify areas appropriate for wind energy and would like to see this approach extended to other forms of location specific renewable energy. Once more is known about landscape capacity, targets for renewable energy should be identified.
Policy MIN1 Minerals 10 representations, 6 objections, 3 comments and 1 support Key concerns include
References to clean coal technology should be clarified further
Over emphasis on environmental concerns and use of the Energy White Paper as Evidence Base.
The policy should allow for the consideration of new sites as well as extensions to existing sites.
Fracking should not be supported over and above any other kind of extraction without appropriate consideration of the relevant plan, contrary to NPPF
Insufficient consideration of demand for brick and fire clays
Object to representation of shallow coal extraction
The policy remains unchanged.
92
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
simply as a result of other development, rather than as an extraction form in its own right
Considers that the local plan should include specific policies for the extraction of minerals of national and local importance.
Document fails to acknowledge that demand for coal will still exceed UK supply.
Noted that encouraging removal of shallow coal along routes of old and new rail links could assist with funding.
Suggest policy should allow for reopening of former quarries where stone is required for repair or restoration of heritage assets.
Should consider reclamation of historical sites
Unconventional natural gas exploitation should be given more detailed consideration
Insufficient reference to the protection of ancient woodland at existing sites.
Concerns over consistency with National Planning Policy with particular reference to onshore oil and gas, conventional and unconventional hydrocarbons, the extraction of coal by surface mining
Omission of minerals safeguarding area for surface coal reserves and insufficient reference to existing and potential aggregates
Further clarity on reclamation requested Broad support for the policy
Policy MIN2 Existing permitted Reserves
1 representation, 1 objection
The policy and supporting text remains unchanged.
93
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
and Areas of Search Considers that further clarity required on safeguarding of shallow coal, Fireclay and Brick Clay
Policy MIN3 Non Mineral Development and Safeguarding Minerals
4 representations – 3 objections, 1 support
Objects to proposed use of thresholds – would prefer an approach that looks at exemption criteria alone. Section on viability needs clarification
Objects to developing Mineral sites south of Brierley. Considers plan is unclear on whether the future extraction of minerals is safeguarded by the policies in the plan.
Amendments suggested to Para 23.29.
Welcomes the policy
The policy remains unchanged. We consider a size threshold appropriate. Exemptions are set out in the supporting text.
Policy MIN4 Mineral Extraction
2 representations – 1 objection; 1 support
Considers the policy to be overly negative and biased towards the environmental aspects of sustainability and inconsistent with the NPPF. Suggests policy should be re-written
General support for the policy
The policy remains unchanged. We consider it to be in accordance with the NPPF.
Policy CL1 Contaminated Land and Unstable Land
3 representations – 1 support, 1 support/comment,1 objection
Support for this policy and the proposal to prepare a Supplementary Planning Document to provide more information about how this policy will be applied.
Comment that PPS23 Planning and Pollution Control referred to at para 24.1 has now been superseded by the NPPF.
The PPS reference is an error and will be rectified.
Policy POLL1 1 representation – support/comment Comments noted.
94
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Pollution Control and Protection
Welcomes the inclusion of groundwater in this policy but comments on the importance of ensuring that secondary aquifers are protected from pollution associated with new development
Policy AQ1 Development in Air Quality Management Areas
No representations received
Policy UT1 Hazardous Substances
No representations received
Policy UT2 Utilities Safeguarding
1 representation of support
Supports the inclusion of water resources and land drainage systems in the policy
Support noted.
Policy I1 Infrastructure and Planning Obligations
10 representations – 9 objections, 1 comment
Concern at the impact of new housing developments on schools and distance children may have to travel given predicted shortage of school places in Penistone
Considers policy should specify ‘Superfast Broadband’ to ensure consistency with para. 26.3
Consider reference to broadband is unnecessary as it is automatically available through telephone lines
Concerns at lack of reference to requirement for health facilities. Suggests more consultation with Clinical Commissioning Group is required.
Local plan should have a specific telecommunications policy
Comment on lack of evidence base demonstrating
The policy remains unchanged. The Publication version will be supported by an updated draft Infrastructure Delivery Plan.
95
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
infrastructure requirements on Strategic Road Network (SRN) as a result of the Local Plan. Queries funding of large schemes and raises concerns at effect of future development proposals on capacity and speed stress on sections of the SRN
Flood defences should be mentioned as a key infrastructure requirements linked to economic growth
Policy I2 Educational Facilities and Community Uses
4 representations – 3 objections, 1 comment
Considers the policy needs strengthening to ensure protection of existing facilities as well as encouraging new facilities. Additional wording suggested.
Notes reference to support for community facilities but suggests additional wording to clarify what is meant by this. Expresses concern at number of pub closures in the Borough and considers that any further losses will have an adverse impact on community life. Proposes adoption of a specific policy/SPD to protect pubs and clubs as important community facilities which also support local economy and offers suggested wording.
Welcomes policy regarding provision of community facilities but seeks amendments to include reference to healthcare facilities.
Comment considering policy to be sound in principle.
The policy remains unchanged. The policy is intended to protect existing community facilities. No specific reference to healthcare facilities added but they are
Figure 18 7 representations – 4 objections; 3 comments The housing trajectory has been updated in
96
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
Housing trajectory considered to be unrealistic
Proposed approach is not robust and will not be compliant with the National Planning Policy Framework
Concern at widely fluctuating rates over the Plan period
Comment on contradictions between proposed housing trajectory and monitoring information
Considers that trajectory is unsound as it is unjustified and not positively prepared. Suggests revision
the Publication version.
Supplementary Planning Documents
3 representations -3 comments
Comment suggesting that an SPD should be produced specifically to cover pubs and licensed clubs
2 requests to be consulted on any draft of the refreshed SPD on advertisements
An SPD on pubs and clubs has not been added to the list in the Publication version, however the list is not exhaustive.
Evidence Base 22 representations – 14 objections, 8 comments
Comments on scoring system for HSSM and Employment Land Review
Comments on 2014 Green Belt Review and 2007 Settlement Assessment
Considers Green Belt Review scores have been manipulated to achieve desired outcomes
Comments that the 2011 Gypsy and Traveller Accommodation Needs Assessment should be
Comments on evidence base noted. Where issues have been raised on HSSM scoring on individual sites these scores have been checked and any necessary amendments made.
97
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
available for public scrutiny if it is to be relied upon as part of evidence base
Comments received on Strategic Housing Market Assessment in terms of density assumptions and deliveries
Suggests additional wording to be inserted after paragraph 4.14 or 4.16 to reference the Barnsley NHS Foundation Trusts emerging Clinical Service Strategy
Concerns raised regarding referencing and relationship with plans and strategies relating to Health and Wellbeing
Considers the amount of employment land required over the plan period has been significantly under-estimated.
Suggests an aspirational housing report is commissioned.
Additional documents relating to flood risk management should be considered as part of the Local Plan preparation and listed in the Evidence Base
General critique of the Evidence Base
Viability Assessments 3 representations – 2 objections, 1 comment
Considers the specified approach will not be appropriate in all circumstances and this should be acknowledged within the appendix
Policy wording should be amended and offers suggested amendment
Comment supporting recognition of the importance
The viability assessment text remains unchanged. We consider it has flexibility built into it.
98
Section, policy, question or site
Summary of the main issues raised How issues raised have been taken account of
of viability but recommends caution in applying the approach to every site.
Alternative Site Proposals
137 representations were received proposing alternative sites for consideration for a variety of uses including: -
Allotments
Development
Employment
Family & retirement housing
Green Space
Gypsy and Traveller site
Mixed use
New motorway junction
New road
Public transport interchange/park & ride facility
Retail park
Urban Fabric
Where alternative sites were suggested they have been run through the site selection process. If they are not proposed as allocations in the Publication version, where proposed for housing they will appear on the rejected site list with reasons for their rejection or will be shown in the initial exclusions list. Where proposed for employment they will be on the rejected sites list. Where other allocations were proposed such as Urban Fabric these changes can be seen on the Policies Map.
Local Plan Additional Consultation 2015
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Local Plan Additional Consultation 2015
137 Representations Alongside comments on the individual sites which are considered in the remaining sections of the table, we also received general comments on the 2015 Additional Consultation document, comments concerning the former 2014 Local Plan Consultation, and suggestions for alternative sites that should be taken forward. Where comments on the 2014 document concern issues that were
Where alternative sites were suggested they have been run through the site selection process. If they are not proposed as allocations in the Publication version, where proposed for housing they will appear on the rejected site list with reasons for their rejection or will be shown in the initial exclusions list. Where proposed for employment they will be on the rejected sites
99
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
raised in response to the previous consultation they are not repeated again here, any new issues raised are noted.
15 new sites (that have not previously been considered through the Local Plan process) proposed for development.
Representations considering that the following sites shown as 2015 Additional Consultation rejected sites, should be taken forward for development:
o AC50 (part) Land south of Intake Crescent, Dodworth
o AC58 Land at junction of Warren Lane and Windhill Lane, Urban Barnsley
o AC65 Land north of Lowfield Road, Bolton on Dearne
o AC72 Site south of Armroyd Lane, Elsecar o AC76 Land east of Bell Ground, Hoyland o AC77 West of Sheffield Road, Birdwell o AC80 Monckton Cokeworks
Comments that rejected site AC47 Dodworth Road, Barnsley should also be rejected due to serious drainage issues
Comments that rejected site AC49 is not in a resultant parcel, but is subject to a current planning application for five detached dwellings
Comments that rejected site AC57 Spark Lane, Darton is not in a resultant parcel and is mainly in Flood Zone 3.
Comments that rejected site AC81 Church Street, Royston is not in a resultant parcel and part is in Flood Zone 3.
list. The Statement of Community Involvement was revised in 2015 in order to make clear how people would be consulted. The Local Plan covers a wide range of complex issues and is supported by technical evidence base. We try to write documents in plain English, however the terminology we need to use makes this difficult. We did our utmost to make as much information as possible available. We accept some additional information that may have provided assistance in the form of background papers were not released for all topics. Barnsley Central Library and branch libraries have computer equipment available for people to use. We publicised the Local Plan consultation widely. Appendix 1 sets out how we have consulted. Our approach is to hold drop in sessions rather than public meetings. In our experience these work better as they allow officers to explain
100
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Queries the future plans for Monckton Cokeworks as industrial activity has ceased.
Criticisms of the consultation process
The additional sites have fundamentally changed the scope of the original document and as such the consultation of the “Draft Local Plan 2014” should be re-opened
Considers that the Council has failed to properly consider merits of sites raised in 2014 consultation
Believes it is not possible to consult on sites without specific policies being provided
General objection to the level of additional development in Penistone and concerns about capacity of highways infrastructure and local services to support this
Concerns about the lack of primary school places in Penistone
Queries the need for more primary schools in Royston
Concerns about the lack of new housing sites in the western villages
Concerns about lack of indicative dwelling numbers
Welcomes reference to undertaking ecological assessments prior to sites being taken forward but some concerns over development sites in close proximity to Local Wildlife Sites and other significant habitats.
AC42 should be described as land between Pit Lane and Cowley Green/ Pashley Croft
Objects to the scale of development proposed in Hoyland and concerns it will lead to an increase in air pollution
issues more fully. Comments from both stages of consultation, including those made in 2015 on the 2014 consultation draft have all been taken into account. The Appropriate Assessment has been renamed Habitat Regulations Assessment for the Publication version. Following concerns raised over the original site description for site AC42 site notices were amended to read Land south of Pit Lane and West of Windmill Road, Wombwell. This has been reflected in the Publication version document. .
101
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
The Appropriate Assessment should be renamed Habitats Regulations Assessment
Proposed allocations within the Dearne Valley Green Heart Nature Improvement Area should support the NIAs vision and objectives
Keen to ensure that coal resources are not unnecessarily sterilised by new development and welcomes the inclusion of criteria relating to ground conditions and coal mining legacy within site selection methodology.
Comments regarding identification of major accident hazard consultation zones and compatible land uses in local plans with specific reference to proposed site AC12.
Concern that a sustainable plan for Penistone should include employment land, a shopping allocation, leisure facilities, a transport plan and affordable housing.
Objection to additional proposed housing sites, considers that the focus should be the provision of local jobs for local people rather than the provision of additional homes likely to be purchased by people commuting to Leeds and Sheffield for work.
Queries whether the housing requirement calculations take into account empty homes
Comments that further work is required to determine the impact on the strategic road network and that Highways England will continue to work with the Council.
New issues concerning the 2014 Local Plan Consultation document included:
102
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Amendment sought to Policy T1 to ensure that appropriate consultation and assessment takes place where any proposed development will impact on railway infrastructure.
With reference to concerns over air pollution, further evidence prepared in association with the 'East End Quality of Life Initiative' to monitor pollution levels in the Hoyland Common area.
Affordable housing policy should ensure that affordable homes are allocated to local people
A more flexible approach to the development strategy in relation to rural settlements is needed to allow sustainable growth of villages
The Council must find a way to incentivise development of brownfield sites
Questions how overall targets fit within City Region context
Queries whether the Local Plan and Green Belt review are flexible enough to respond to wider cross boundary growth ambitions at SCR level
Considers that the use of the term ‘safeguarded land’ is misleading
Concerns at apparent release of Green Belt around the proposed HS2 route.
Concerns over the proposed HS2 route.
Considers that Hoyland and Hoyland Common area is unfairly burdened with housing and employment allocations.
With reference to H46 Land west of Fitzwilliam Street, Elsecar concerns about loss of area of important mining,
Many of the site specific issues raised will have been considered as part of the sites selection process. Where specific issues need to be addressed site policies have been provided. We consider that the jobs and homes figures in the Local Plan are compatible with the figures set out in the Strategic Economic Plans of both the Leeds and Sheffield City Regions. The Green Belt review has been prepared in accordance with the Sheffield City Region agreed Common Approach. We consider the review is a robust basis going forward when dealing with any cross boundary issues that may arise.
103
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
rail and iron making importance which could contribute the Elsecar Heritage Centre and its setting.
With reference to site H78 concerns include loss of farmland and green space and intensification of existing parking issues
With reference to sites H2 and H46 Land West of Fitzwilliam Street, and H78 Land North of Armroyd Lane, all in Elsecar, concerns regarding:
o the quantum of development o disruptions from development o lack of infrastructure such as schools, medical
facilities, roads and other public services
Considers safeguarded site SAF7 east of Sheffield Road, Hoyland Common should remain in the Green Belt.
With reference to site H8, Land off Meadowfield Drive, Hoyland, concerns over impact on ancient woodland and local wildlife site.
With reference to employment site HOY1 Land west of Sheffield Road, concerns regarding:
o consider that the rural aspect should be maintained to encourage the visitor economy
o impact on air pollution o impact on climate change o creation of urban sprawl o flood risk, surface water and drainage concerns o lack of local infrastructure o disruption to local residents o lack of sustainable employment for new
residents
104
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
o Impact on Hoyland Lowe Stand
With reference to site housing H4 Land south of Hay Green Lane, Birdwell, concerns regarding:
o loss of agricultural green belt o impact on ecology o increase in noise and air pollution o effect on climate change o urban sprawl o lack of existing infrastructure o impact on facilities such as health services and
schools o Loss of allotments and grazing land o Site access concerns
With reference to site mixed use site MU1, concerns regarding increase in flooding in Redbrook if deep mine drain is disturbed
Support for housing development on housing site H41, the former Foulstone School, Darfield.
With reference to employment site P2, Land North of Sheffield Road. Considers that
o B1 uses should be prioritised due to restricted access for large vehicles and proximity to existing residential uses.
o The Local plan should be more consistent with the Oxspring Neighbourhood Plan proposals with respect to renewable energy and the design of the site to protect important characteristics.
With reference to site H80, Land north and east of Joan Royd Lane, Cubley:
o concerns about microclimate in area, icy
105
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
conditions of roads and the suitability of Woodend Avenue to accept construction traffic due to the risk of collapse
o concern about the capacity of utilities with particular reference to power supply
Site AC1: Former Woolley Colliery
5 representations – 2 support, 1 objection, 2 comments
Support for housing development as it would encourage regeneration of a previously developed site and proposes amendments to site scoring
Considers proposal unsustainable
Concerns regarding increase in traffic and impact on local highway network
Considers development would incur abnormal costs which should be reflected in expectations for affordable housing and CIL
The site is within 400m of the Core Public Transport Network
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
Site AC2: Land to the South of Darton Lane, Mapplewell
8 representations – 4 objections, 3 comments, 1 support
Loss of Green Belt
Concerns regarding highway safety
Effect on infrastructure, e.g. schools, healthcare, local services
Impact on ecology
Comments on lack of information demonstrating site suitability and deliverability
Impact on local highway network in adjoining Authority
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
106
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Queries potential housing yield due to site constraints
Site within 400m of Core Public Transport Network
Site is suitable for housing.
Site AC3: Former William Freeman Site, Wakefield Road, Mapplewell
5 representations – 2 support, 2 comments, 1 objection
Support for proposed Housing allocation
Landowner support for housing due to lack of interest for employment use
Site within 400m of Core Public Transport Network
Comments that site is on an historic landfill
Questions whether continued use of land for employment been rigorously examined
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
Site AC4: Proposed extension to H33, Carlton Road, Athersley
3 representations – 2 comments, 1 objection
Site within 400m of Core Public Transport Network
Questions reasons for allocating such a small site
Queries evidence that site no longer in use/required for recreation
This site has been added to proposed housing allocation H33.
Site AC5: Land between Stocks Lane/West Road, Pogmoor
9 representations – 5 support, 2 comments, 2 objections
Support for housing as it would improve visual appearance
Support for site but proposes amendments to site scoring
Supports re-use of brownfield site for housing as it would reduce the need to release green belt sites
The site is not proposed as a housing allocation in the Publication version. It has been shown as Urban Fabric.
107
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
elsewhere in the Borough
Considers the site suitable for mixed use and/or housing
Site is partly within 400m of Core Public Transport Network
Comments that site is close to a number of waste regulated sites
Questions quality and deliverability of site
Lack of evidence demonstrating site sustainability and deliverability of site for housing
Site AC6: Former Longcar PDC, Racecommon Road, Barnsley
3 representations – 2 comments, 1 support
Site within 400m of Core Public Transport Network
Notes that planning application is under consideration and the site demolition has commenced
Developer support for the allocation
The site is proposed as a housing allocation in the Publication version. It has planning permission for 32 dwellings which was granted after 1st April 2014.
Site AC7: Former Springfield House, Springfield Street, Barnsley
4 representations – 2 objections, 2 comments
Site unviable due to demolition costs
Lack of evidence to demonstrate sustainability and deliverability of site for housing
Site is within 400m of Core Public Transport Network
Comments on proximity of site to Sough Dike
The site is not proposed for housing in the Publication version.
Site AC8: land at Tower Street, Barnsley
8 representations – 6 objections, 2 comments, 1 support
Site cannot be accessed
Ecological impact
The site is not proposed for housing in the Publication version.
108
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Development constraints
Traffic congestion
Highway safety
Access for emergency vehicles
Lack of evidence to demonstrate sustainability and deliverability of site for housing
More assessment required regarding impact on historic park and garden
Site is within 400m of Core Public Transport Network
Site is deliverable and available
Site AC9: Land off Upper Sheffield Road, Barnsley
10 representations – 7 objections, 2 comments, 1 support
Loss of Green Belt – brownfield sites should be used
Objects to inclusion of this site as a means of access to H73
Queries evidence that site no longer in/required for recreational use
Concerns regarding geology of site and proximity to telecommunications installation
Loss of playing field
Impact on Grade II/II* Listed Buildings
Questions deliverability and housing yield of site
Site is within 400m of Core Public Transport Network
The site is not proposed as a housing allocation in the Publication version.
Site AC10: Land at West Street, Worsbrough
4 representations - 2 objections, 1 comments, 1 support
Unsuitable for housing due to potential conflict with neighbouring employment uses
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is
109
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Questions evidence that site no longer viable for employment
Site is within 400m of Core Public Transport Network
Site suitable for housing due to brownfield status and is available and deliverable
provided to set out issues that need to be addressed.
Site AC11: Mixed Use proposal – Land between Fish Dam Lane & Carlton Road, Carlton
218 representations – 213 objections (including a petition containing 197 valid entries), 5 comments
Loss of Green Belt and greenfield land
Impact on green space
Changing green belt boundary contravenes Government guidelines
Increased impact on existing local infrastructure and amenities
Concern at the potential scale of development and uncertainty as to the area of land that would be left as greenfield/green space
Proximity to industrial estate and potential increase in noise and air pollution
Steeply sloping site subject to flooding
3 streams, 2 main sewer pipes and a coal seam run through the site
Loss of public footpath
Impact on ecology
Site also still under consideration for a traveller site
Lack of amenities
Urban sprawl
Geological fault on site
The site is proposed as a mixed use allocation for housing and extension of Carlton Junior and Infant school in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
110
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Impact on Carlton Village
Questions the involvement of builders in the process – conflict of interest?
Lack of supporting infrastructure
Impact on Carlton Beck and effect on biodiversity
Questions sustainability and deliverability of site
Loss of playing field
Impact on local jobs and businesses
Detrimental effect on local residents
Further assessment of impact on Conservation Area required
Considers site appropriate for mixed use but expected yield needs to take account of landscaping issues
No objection to principle of mixed use provided development does not compromise existing commercial operations.
Site is within 400m of Core Public Transport Network
Comments on presence of ordinary watercourse on site.
Site AC12: Mixed Use proposal between Shaw Lane & West Green Link Road, Carlton
221 representations – 216 objections (including a petition containing 197 valid entries), 4 comments, 2 supports
Loss of Green Belt and greenfield land
Impact on green space
Increased impact on existing local infrastructure and amenities
Lack of confidence in BMBC as to the scale of the development
Loss of public footpaths/recreational space
The site is proposed as a mixed use allocation in the Publication version for housing and green space with Wharncliffe Woodmoor being retained. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed. A masterplan is required covering this site and proposed site H44.
111
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Loss of farmland
Impact on ecology and biodiversity
Parts of site prone to flooding
Development previously refused for Carlton Colliery site due to contamination
Site unsuitable for housing due to neighbouring commercial uses
Ground stability
Urban sprawl
Inadequate drainage infrastructure
Questions the involvement of builders in the process – conflict of interest?
Impact on Carlton Village
Lack of amenities and medical facilities
Impact on traffic and schools
Railway line to east of site should be safeguarded
Impact on Calder Beck and effect on biodiversity
Air pollution
Concerns over deliverability and developer interest
Impact on local jobs and businesses
Detrimental effect on local residents
Impact on major accident hazard consultation zones
Impact on Strategic Road Network
No objection to principle of mixed use provided development does not compromise existing commercial operations
Site is partly within 400m of Core Public Transport Network
Comments on presence of watercourse/culverts on site
Proximity to waste regulated sites
112
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Land owners support for individual portions of the site
Potential for encroachment on major hazard accident consultation zone.
Site AC13: Mixed Use site, Former Oakwell Brewery, Pontefract Road, Barnsley
5 representations – 2 objections, 2 comments, 1 support
Considers site unsuitable for housing due to adjacent employment uses
Questions sustainability and deliverability of site for housing
Main river culvert runs through site
Site within 400m of Core Public Transport Network
Supports development of site as previously developed land
The site is not proposed as mixed use in the Publication Version. It is proposed as Urban Fabric.
Site AC14: Land at Bleachcroft Way, Stairfoot
6 representations – 3 objections, 2 comments, 1 support
Concerns regarding impact on nearby Listed Buildings
Considers unsuitable for housing due to adjacent commercial uses. More suited to commercial or retail
Questions sustainability and deliverability of site
Comments on presence of watercourse on site
Site within 400m of Core Public Transport Network
Site is capable of delivering sustainable development
This site has not been proposed as a mixed use site in the Publication version. Part of the site has been proposed as an employment land allocation reference UB16 and the remainder as Urban Fabric.
Site AC15: Land at Oaks Lane/Doncaster Road, Kendray
4 Representations – 3 comments, 1 objection
The site is suitable for housing
The site should be considered for housing/mixed use
The site is not proposed as a primary school site in the Publication version.
113
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Objects due to loss of playing fields
The site is within 400m of the Core Public Transport network
Site AC16: Land off Broadway, Barnsley
10 representations – 5 objections, 4 support, 1 comment
Objects to loss of green space
Objects to proposal and questions what will happen to existing residential properties
Questions sustainability and deliverability of site
Concerns regarding merging of settlements
Objects to loss of playing field
Supports the use for housing as it would reduce the need to release green belt land elsewhere in the borough
Support for mixed use for housing and urban green space
Site should be taken forward for housing
Site within 400m of Core Public Transport network
The site is proposed as a mixed use allocation for housing and green space in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
Site AC17: Land off Laithes Lane, Athersley
4 Representations – 3 objections, 1 comment
Loss of well used green space/ playing fields
Loss of safe route to Carlton Community College
Increased traffic, effect on wildlife and loss of views
The site is within 400m of the Core Public Transport network
The site is proposed to remain as green space in the Publication version.
Site AC18: 3 representations – 2 objections, 1 comment The site is proposed as Urban Fabric in the
114
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Claycliffe Business Park, Barugh Green
Site should be allocated for commercial/employment use as it is within an industrial estate
Site within 400m of Core Public Transport Network
Publication version.
Site AC19: Land South of Darton Lane, Barnsley
4 representations – 3 objections, 1 comment
Objects to loss of playing fields
Site should remain as Green Belt
Considers site should be allocated for housing or mixed use
Site within 400m of Core Public Transport Network
The site is not proposed as a housing allocation in the Publication version.
Site AC20: Land South of Doncaster Road, Stairfoot
4 representations – 2 objections, 2 comments
Objects to proposed green space allocation – land should remain as employment or urban fabric
Questions ecological value of site
Comments that site is on an historic landfill
Site within 400m of Core Public Transport Network
The site is proposed as green space in the Publication version due to high ecological value.
Site AC21: Former Woolley Colliery
5 representations – 3 objections, 2 comments
Objects due to increase in traffic and impact on local highway network
Objects t loss of playing fields
Considers site should be allocated for industrial use
Site is partly within 400m of Core Public Transport Network
This site is proposed as green space in the Publication version.
115
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Comments on lack of details regarding the site
Site AC22: Land at High Street, Shafton
1 representation – 1 comment
Site within 400m of Core Public Transport Network
The site is proposed as an allocation in the Publication version. It has planning permission for 38 dwellings which was granted after 1st April, 2014.
Site AC 23: Land at Cadwell Close, Cudworth
10 representations – 8 objections, 2 comments
Number of objections to allocation due to lack of suitable access
Site is not deliverable due to small size
Questions deliverability of site
Queries allocation for housing when previously rejected as Traveller site
Site lies outside 400m of Core Public Transport Network
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
Site AC24: Former Willowgarth School, Grimethorpe
6 Representations – 3 objections, 2 comments, 1 support
Site is unsuitable for a primary school as few children live within walking distance
The site is suitable for housing
An assessment into potential impact on heritage assets should be undertaken
Supports the removal of the land from the Green Belt, the site should be extended
Objects due to loss of playing fields
Part of the site is within 400m of the Core Public transport Network
The site is not proposed as a primary school in the Publication version.
116
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Site AC25: Clayton Lane Playing Fields, Thurnscoe
16 representations – 15 objections, 1 comment
Increased traffic congestion
Impact on highway safety
Loss of green space
Loss of well used playing field/sports facilities
Loss of privacy/overlooking
Drainage/flooding concerns
Impact on wildlife
Devaluation of property
Safety and security issues
Japanese knotweed issue
Questions demand for housing in this area
Questions site deliverability
Lack of existing amenities to support development
Site within 400m of Core Public Transport Network
The site is not proposed as a housing allocation in the Publication version.
Site AC26: Land South of Lowfield Road, Bolton Upon Dearne
108 representations – 104 objections, 3 comments, 1 support
Objects due to area already being overdeveloped
Existing highway infrastructure inadequate
Overstretched public utilities
Land currently acts as a soakaway
Impact of development on local RSPB reserve
Questions site deliverability
Access concerns
Urban sprawl
Traffic congestion
Pollution of river Dearne
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
117
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Questions demand for new houses in this locality – existing empty properties
Lack of public transport
Lack of highway maintenance
Impact on Scheduled Ancient Monument
Proximity to waste water treatment works
Site partly within 400m of Core Public Transport Network
Proximity to flood zones 2 and 3
Site AC27: Land South of Dearne Valley Parkway, Goldthorpe
14 Representations – 9 objections, 3 comments, 2 supports
Highways capacity and safety concerns
Biodiversity impact, particularly on RSPB reserve
Increased pollution, AQMA issues
Increased flood risk, part of site is in flood Zone 3
Loss of Green Belt
Loss of agricultural land
Impact on Billingley Conservation Area
Sites lies outside Core Public Transport Network
Notes that could provide additional employment opportunities for Rotherham residents
The site is proposed as an employment land allocation in the Publication version. The site is part of D1 and the area has been increased to 72.9ha. A site policy is provided which deals with issues such as biodiversity and flood risk.
Site AC28: land South of Broadwater Estate, Bolton Upon Dearne
7 representations – 3 comments, 2 support, 2 objections
Site partially within Core Public Transport Network
Comments site in flood zone 2/3
Supports proposal given site’s development constraints
Supports recognition of sites importance for natural
The site is proposed to be put back into Green Belt in the Publication version due to site constraints.
118
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
habitat
Objects to site for housing allocation
Notes the acknowledgement that this site can be re-designated as Green Belt
Objects to the proposed allocation and considers the Plan unsound
Site AC 29: Land off Shortwood Roundabout, Hoyland
19 representations – 16 objections, 2 comments, 1 support
Concerns regarding lack of parking
Traffic congestion
Lack of/impact on infrastructure – e.g. local public services, school places, highways, health
Air pollution
Loss of Green Belt/green space
Impact on wildlife
Climate change
Flood risk
Urban sprawl
Disruption to existing community
Lack of sustainable employment for new residents
Loss of agricultural land
Impact on Grade II listed building
Loss of local character
Lack of demand
Housing targets flawed
Use brownfield sites before green belt
Site partly within 400m of Core Public Transport Network
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
119
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Supports site allocation
Site AC30: Land at Tankersley Lane, Hoyland Common
31 representations – 28 objections, 2 support, 1 comment
Access concerns
Highways/traffic concerns
Air/noise pollution
Lack of public services
Drainage issues
Concerns regarding capacity of existing infrastructure, e.g. doctors, schools, police
Lack of sustainable transport
Questions need for new dwellings
Loss of local identity due to scale of proposals
Loss of Green Belt
Loss of green space/woodlands
Impact on wildlife/ecology
Impact on community
No guarantee that jobs/houses will go to local community
Flood risk
Loss of agricultural land
Impact on Grade II listed building
Climate change
Urban sprawl
Lack of parking
Questions site deliverability
Housing targets flawed
Use empty/dormant sites before green belt
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
120
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Support for site allocation
Site within 400m of Core Public Transport Network
Visual impact
Devaluation of property
Disturbance from development
Site AC 31: Land at Broad Carr Road, Hoyland
42 representations – 39 objections, 1 support, 2 comment
Concerns regarding future of existing residential property within the site
Queries whether woodland will be felled
Land should remain as Green Belt
Impact on ecology
Insufficient details of proposals
Development should utilise existing empty properties/neglected land
Development should cater for local people and not encourage migration
Merging of settlements/loss of community identity
Loss of outdoor recreation area
Loss of footpaths
Loss of grazing land
Concerns regarding capacity of existing infrastructure, e.g. healthcare, highways, public services school places
Lack of parking
Concerns regarding stability of land – historic mine works
Criticises Green Belt Review
Highway safety and traffic implications
Other brownfield sites more appropriate
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
121
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Impact on adjacent Ancient Woodland
Urban sprawl
Noise and air pollution
Disturbance from development
Concern over quantum of development
Devaluation of property
Site is suitable for development
Site partly within 400m of Core Public Transport Network
No objection in principle subject to closure of PROW crossing railway line adjacent the site
Site AC32: Rockingham Sports Club Field, Hoyland Common
54 Representations – 52 objections, 2 supports
Loss of sports/community facilities which have recently been improved (with national lottery money)
Site has not been properly researched
Land ownership disputed. Representor states they hold a 25 year lease on the land
Loss of Green Belt and green space
Highways congestion and safety concerns
Increased pollution and noise levels
Impact on wildlife
Climate change
Increased flood risk
Disruption to residents
Urban sprawl
Negative impact on heritage assets
Questions the need for more employment land in the Hoyland area
This site is proposed as an employment land allocation in the Publication version as part of HOY1. Text has been included in the site policy to specify that replacement sports ground and facilities must be constructed and available for use before development on the existing sports ground commences.
122
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Ground stability issues
Concerns regarding capacity of existing infrastructure, e.g. doctors, schools, police
Visual impact
Devaluation of property
Site AC33: Land North of Rockingham, Birdwell
36 Representations – 20 objections, 5 comments, 2 supports
Loss of Green space
Loss of Green Belt
Noise and air pollution
Biodiversity impact
Risk to wildlife
Climate change
Urban sprawl
Increased flood risk
Traffic congestion, safety and access concerns
Pressure on infrastructure
Disruption to residents
Impact of large employment buildings on nearby houses.
Loss of agricultural land
Negative impact on heritage assets
Brownfield sites should be prioritised
Concerns regarding capacity of existing infrastructure, e.g. doctors, schools, police
Concern over proposed route HS2
Concern over quantum of development
The site is proposed as Safeguarded Land in the Publication version. This is land that may b considered to meet development needs in the longer term maybe outside the plan period.
123
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Visual impact
Devaluation of property
Notes that could provide additional employment for Rotherham residents
Site AC34: Land to the East of Penistone Grammar School, Penistone
66 Representations – 61 objections, 3 comments, 2 supports
Flood risk (Part of site in Flood Zone 2 and 3) drainage and water pollution concerns
Negative impact on the present population
Site previously rejected due to access constraints
Loss of Green Belt, Greenfield land and Countryside
Brownfield sites should be prioritised/ exhausted before Green Belt is considered
Existing infrastructure at capacity (schools, health services, highways)
Unsuitable access
Increased pressure on Penistone Grammar
Land would be better suited to expansion of Grammar school
Road capacity, congestion and safety concerns
Ecological impact, loss of wildlife
Loss of towns identity/ character
Impact on tourism
Increased pollution
Impact on property prices
An assessment of the sites impact of historic assets is required.
Awkward shape of the site limits potential for
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
124
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
development
Further evidence is required to demonstrate the sustainability and deliverability of the site.
Allocation will increase the demand for allotments. Developers should be required to provide allotments.
Loss of playing fields
National coal board land owned by BMBC should be prioritised
Boundary should be extended to reflect SHLAA sites 599 and 687
Site AC35: Land at Castle Lane, Penistone
83 Representations – 81 objections, 1 comment, 1 support
Questions expected site yield
Access constraints, notes the site was previously rejected due to poor access and asks what has changed?
Highways capacity and safety concerns
Loss of Penistone’s rural character and community spirit
Loss of access to and views of the countryside
Loss of amenity and recreation opportunities, leading to detrimental health impacts.
Ecological impact
Increased pressure on existing infrastructure (schools, health services, and parking)
Brownfield land should be exhausted before Green Belt is considered.
Loss of Green Belt, Green space, green field and
The site is not proposed as a housing allocation in the Publication version.
125
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
agricultural land
Increased demand for allotments
Merging of settlements
Impact from construction
Damage to watercourses, drainage and flood risk concerns
Proximity to powerlines
No evidence that site is deliverable
Delivery of housing on site is achievable subject to technical issues being addressed.
If development goes ahead adjacent play park should be refurbished
Preference for affordable housing
Site AC36: Land to East of Penistone Grammar School, Penistone
40 representations – 19 support, 17 objections, 4 comments
Supports designation as green space
Supports designation provided land will be protected from future development
Supports designation subject to provision of allotment land within the site
Supports but questions green space designation when land is already in Green Belt
Considers brownfield sites should be exhausted before taking Green Belt
Loss of Green belt
Increased traffic congestion
Pressure on schools and health services
Impact on wildlife
This site is not proposed as a housing allocation in the Publication version.
126
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Traffic/parking concerns
Site should be retained for future expansion of Penistone Grammar School
Concerns regarding flooding – site in flood zone 3a
Lack of local infrastructure
Site partly within 400m of Core Public Transport Network
Comments that Scout Dike runs through the site
Site has moderate Water Framework Directive ecological status
Site AC37: Former Royston High School, Royston
7 Representations – 5 objections, 2 comments
There is already sufficient primary school provision in Royston
Development will increase traffic and worsen the parking situation
Site should be used for open space, light industry and additional parking
Proposes an alternative site for a primary school to serve the Lee Lane extension
Loss of playing fields
Site is within 400m of the Core Public Transport Network
The site is on an historic landfill
This site is not proposed as a primary school allocation in the Publication version.
Site AC38: Land at Lee Lane, Royston
7 Representations – 4 objections, 2 comments, 1 support
There is already sufficient primary school provision in
Site not proposed for a primary school in the Publication version. Proposed as part of a housing allocation. An alternative site off Lee
127
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Royston
Development will increase traffic, road safety and worsen the parking situation
Subject to the satisfactory resolution of drainage issues the site is considered to be a good site for a primary school
Proposes an alternative site for a primary school as not to hinder proposed development along Lee Lane
The site should remain a housing allocation
Concerns regarding site access
Site is partly within 400m of the Core Public Transport Network
Lane was suggested for a primary school which has been proposed in the Publication version.
Site AC39: Pitt Street, Wombwell
17 representations – 14 objections, 2 support, 1 comment
Loss of views
Devaluation of property
More suitable sites available
Access issues
Increased pressure on highway network
Highway safety
Flood risk/loss of natural flood defences
Drainage concerns
Impact on ecology/wildlife
Loss of light to existing properties
Considers brownfield sites should be prioritised
Urban sprawl/merging of settlements/loss of identity
Alternative derelict sites should be identified
Loss of Green Belt
The site is proposed as a housing allocation in the Publication version. Some of the issues raised have been considered as part of the housing site selection process. A site policy is provided to set out issues that need to be addressed.
128
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Overlooking concerns
Concerns regarding anti-social behaviour
Support subject to yield reflecting access constraints
Supports inclusion of site and considers additional land should also be released for housing
Site within 400m of Core Public Transport Network
Site AC40: Former Wombwell High School, Wombwell
8 Representations – 4 objections, 3 comments, 1 support
Questions how much of the land will be for a school and how much for development
Access to the site is poor, a new access road would need to be built
Objects to the loss of wooded area, playing field and effect on wildlife
Supports proposal as it would reduce overcrowding at nearby schools
Considers the site should be a housing allocation
Site is partly within 400m of the Core Public Transport Network
The site is proposed as a mixed use site in the Publication version for housing and a primary school. A site policy is provided to set out issued that need to be addressed.
Site AC41: Pitt Street, Wombwell
8 representations – 5 objections, 3 comments
Loss of Green Belt
Urban sprawl/merging of settlements
Objects to safeguarded allocation as considers site suitable for development in the short term
Objects to allocation as affords no protection from future development which may result in significant biodiversity
The site is proposed as Safeguarded Land in the Publication version. This is land that may be considered for development needs in the longer term but not necessarily in the plan period.
129
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
losses
Objects to proposal as considers the site more suitable for housing
Site is partly within 400m of Core Public Transport Network
Comments on the importance of habitat and important national species
Part of site in flood zone 2 along watercourse
Site AC42: land South of Pit Lane & West of Windmill Road, Wombwell (Land between Summer Lane & Hough Lane, Wombwell)
48 representations – 45 objections, 2 support, 1 comments
Loss of Green belt
Importance of boundary hedgerow for birds/wildlife
Impact on ecology/biodiversity
Loss of natural drainage area – increase in flooding?
Loss of well used recreation area
Lack of local services and amenities, e.g. schools, healthcare,
Concerns regarding access
Devaluation of existing properties
Noise, traffic and air pollution
Traffic/highway safety/highway infrastructure concerns
Should use land that is already vacant
Thinks land was earmarked for extension to cemetery – is this still going to happen?
Concerns regarding public utilities network
Questions validity of Green Belt Review
Loss of character
Impact on residential amenity - loss of views/privacy
The site is proposed as Safeguarded Land in the Publication version. This is land that may be considered for development needs in the longer term but not necessarily in the plan period.
130
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Lack of capacity of train services at busy times
Support for allocation – considers site is suitable for development
Site is partly within 400m of Core Public Transport Network
Site AC43: South of Hough Lane, Wombwell (rear of old Wombwell Foundry)
3 representations – 1 support, 1 objection, 1 comment
Supports proposal as it will protect habitat from development
Site should be allocated for housing due to its quality and likely deliverability
Site within 400m of Core Public Transport Network
The site is not proposed as a housing allocation in the Publication version.
Site AC44: paper Mill, Oughtibridge, Sheffield
11 Representations – 4 supports, 4 comments, 3 objections
Potential contamination due to previous use
Lack of infrastructure (schools and health services)
Access concerns and increased pressure on highways infrastructure
Lack of public transport links
Requirement for a Transport Assessment
Effect on protected trees and wildlife
Flood risk concerns, site is within Flood Zone 2.
Damage to watercourse (which is currently ecologically poor)
Lack of consultation publicity
Devaluation of existing properties
Supports proposed allocation
Site proposed as a housing allocation in Publication version. Whilst part of the site is jus within the borough boundary the impact of development will lie in Sheffield and any subsequent planning application would be determined by Sheffield. Therefore we propose this site will contribute towards Sheffield’s housing need figure.
131
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
Site AC45: Wentworth Industrial Park, Tankersley
7 representations – 5 support, 1 objection, 1comment
Supports proposal
Welcomes recognition of high ecological and recreational value
Questions the site’s ecological value
Site is within 400m of Core Public Transport Network
Site AC46: Burntwood Cottages, Brierley
4 representations – 3 support, 1 comment
Support for extension to Traveller site
Site not within 400m of Core Public Transport Network
The site is proposed as a Gypsy and Traveller site allocation in the Publication version.
Policy CC AC1: Water Resource Management
9 Representations – 8 supports, 1 comment
The Council should require development proposals to be accompanied by a survey of watercourses on or underneath the proposed development site
The policy remains unchanged
Policy RE AC1: Wind Turbine Areas of Search
31 Representations – 22 objections, 6 Supports, 3 comments
The policy does not satisfy the Ministerial Statement (June 2015)
Wind turbines should only be permitted on suitable sites which are allocated in the Local Plan and where they have community support
Further work is required to identify more specific sites
There are already too many wind turbines in the west of the borough
Policy remains unchanged. Wording added to supporting text about valued landscapes in the west and peak District National Park.
132
Section, site or policy
Summary of the main issues raised How issues raised have been taken account of
The policy will increase the threat to the Green Belt
The policy does not give sufficient heed to the impact of wind turbines on the landscape, ecology and sustainability
Landscape character assessment should be considered alongside the policy
The policy is not consistent with the Peak District National Park’s policies.
The Peak District National park should be consulted on planning applications that affect its setting
Wind turbines require careful siting to minimise impact on local bird and bat populations and ensure natural habitats are not damaged or lost during installation
Any detailed development principles for Wind Turbines should be set out in a Local Plan policy
133
Appendix 1: Summary of consultation undertaken
Key methods of consultation 2014
Contacted all those residents, business and organisations on our consultation database who have shown an interest in previous stages of the plan and have asked to be kept informed. We also contacted community groups across the borough.
Article in the Council’s ‘Open Door’ magazine, delivered to all households at the beginning of September (see appendix 4)
Press releases on 14th October, 28th October, 5th November, 2nd December, 7th January, 12th January. These press releases were also sent out via the council’s e-newsletter Open Mail (sent to over 1900 people), Facebook and Twitter (see appendix 4)
Press coverage (examples attached in appendix 4) Press notice in Barnsley Chronicle, 7th November 2014 (see appendix
2) Posters in local areas to publicise drop in sessions we held in various
locations around the borough (see list of venues in appendix 3) Advert in ‘Your Town’ publication - a publication produced by and on
behalf of Barnsley Town Centre Services Team and distributed widely across the Borough in the week commencing 18th November (see appendix 5)
We put a link direct from the homepage of the Council’s website to the Local Plan consultation pages to make it easier for people to navigate the website.
We held discussions with adjoining authorities and key stakeholders such as infrastructure providers on key issues including cross boundary issues
Fliers explaining the Local Plan and how to use our online consultation system were available in local areas and at our drop in sessions
Exhibition material available to view in Barnsley Town Centre in ‘Better Barnsley’ shop unit
Made paper copies available in Barnsley Civic Connects Centre and Central and all branch libraries where possible
Key methods of consultation 2015
Contacted all those residents, business and organisations on our consultation database that have shown an interest in previous stages of the plan and have asked to be kept informed. We also contacted community groups across the borough.
Details of the consultation shared with Barnsley’s Equality Forums Press releases on 13th October, 27th October, and 30th November
2015. These press releases were also sent out via Facebook and Twitter (see appendix 4)
Article in the ‘Love Where You Live’ e-newsletters issued 7th November, 21st November and 4th December 2015.
Press coverage (examples attached in appendix 4)
134
Press notice in Barnsley Chronicle, 30th October 2015 (see appendix 2) Posters in local areas to publicise drop in sessions we held in various
locations around the borough (see list of venues in appendix 3) We posted notices at every site included in the consultation document
to publicise the consultation. We put a link to the Local Plan consultation pages from the Planning
and Buildings button on the homepage of the Council’s website to make it easier for people to navigate the website
We held discussions with adjoining authorities and key stakeholders such as infrastructure providers on key issues including cross boundary issues
Fliers explaining the Local Plan Additional Consultation and how to use our online consultation system were available in local areas and at our drop in sessions
Exhibition material available to view in Barnsley Town Centre in ‘Better Barnsley’ shop unit
Made paper copies available in Barnsley Civic Connects Centre and Central and all branch libraries where possible
135
Press Advert in the Chronicle 7th November 2014
Appendix 2:
BARNSLEY METROPOLITAN BOROUGH COUNCILSPECIAL NOTICE:
HOW YOU CAN BE INVOLVED IN THE BARNSLEY LOCAL PLAN
Barnsley Local Plan Consultation We are producing a Local Plan for Barnsley which will replace the Core Strategy and the Unitary Development Plan. Wewould like to invite you to comment on the draft document which will guide development in Barnsley up to the year2033. The consultation period for this document begins on Monday 10 November and runs until 21 December 2014.
Once adopted, this document, together with the Joint Waste Plan adopted in March 2012 prepared with Doncasterand Rotherham, will be our statutory development plan for Barnsley. It considers the future use of all land within theborough including Barnsley Town Centre, and includes text previously set out in a stand alone document called theTown Centre Area Action Plan. It establishes policies and proposals up to the year 2033. It will be used whenconsidering planning applications and to coordinate investment decisions that affect the towns, villages andcountryside of Barnsley.
How can I see the Local Plan?• On our online consultation system at consult.barnsley.gov.uk/portal • On our website at www.barnsley.gov.uk/localplanconsultation• At Barnsley Central Library and branch libraries across the borough, either online or as a paper copy (during normal
opening hours) • At the Barnsley Civic Connects service centre (Monday to Friday between 9am and 5pm)
How can I comment?Using our online consultation at consult.barnsley.gov.uk/portal
If you have not previously received an email from us containing a username and password for the onlineconsultation system, you will need to register (supply your name, address and email address) the first time you usethe system. As this is a Council wide system, please make sure that you select planning as an interest when youregister.If you have registered with us before but have forgotten your username password you can reset these atconsult.barnsley.gov.uk/portal You will need to click on the Login/Register button and select either the ‘forgotten password’ and/or the ‘forgottenusername’ link.
Or by sending us a completed comments form. You can send us your completed comments form and/or deliverabilityproforma in one of the following ways:
• By email to: [email protected] • By post to: Planning Policy, Development, BMBC, PO Box 604, Barnsley, S70 9FE
You can also comment on the Sustainability Appraisal which accompanies the document in the same way. This isavailable on our website and at the Barnsley Civic Connects service centre.
We must receive all responses by midnight on Sunday 21 December 2014 to enable us to give them properconsideration.
Please note that any comments you make will be made publically available and attributed to your name.Please use one method of reply only to avoid duplication of representations.
We will be visiting different locations around the borough where you will be able to drop in to see information about thedocuments and talk to us:
*We have tried to organise sessions in all principal towns. We intended that the town centre sessions would beaccessible for people living within urban Barnsley. Urban Barnsley covers a lot of settlements and it would be difficultfor us to visit all of them. Drop in sessions are being made available rather than public meetings as they will alloweveryone to have their say.
The comments received as a result of these consultations will be carefully considered and taken into account.We intend to make available a summary of all the comments received as soonas is possible.
If you require any further information please contact Planning Policy on 01226 772606.
Where* Venue When (2014) Time
Barnsley
Cudworth
Goldthorpe
Hoyland
Penistone
Royston
Wombwell
Better Barnsley Unit, formerHMV shop, Cheapside,Barnsley Town Centre
Cudworth Library, CudworthCentre of Excellence,Roberts Street
Goldthorpe Library,Barnsley Road
The Hoyland Centre,High Croft
Penistone Market Hall
Penistone Town Hall,Shrewsbury Road
Carlton Community College
Royston Methodist Church,Midland Road
Wombwell Library,Station Road
Saturday 29 November
Wednesday 3 December
Monday 24 November
Monday 1 December
Thursday 27 NovemberTuesday 2 December
Thursday 27 NovemberMonday 1 December
Saturday 22 November
Thursday 4 December
Tuesday 25 November
Saturday 6 December
Tuesday 25 November
Thursday 4 December
10am to 12 noon
1pm to 3pm
5pm to 7pm
12 noon to 2pm
5pm to 7pm10am to 12 noon
11.45am to 1.45pm5pm to 7pm
10am to 12 noon
2pm to 4pm
5pm to 7pm
11am to 1pm
12 noon to 2pm
5pm to 7pm
136
Press Advert in the Chronicle 30th October 2015
BARNSLEY METROPOLITAN BOROUGH COUNCIL
SPECIAL NOTICE
HOW YOU CAN BE INVOLVED IN THEBARNSLEY LOCAL PLAN ADDITIONAL CONSULTATION
Local Plan Additional Consultation The Local Plan Additional Consultation document follows on from the Draft Local PlanConsultation 2014. The Consultation runs from Friday 30 October to Friday 11 December 2015.We are now carrying out additional consultation because
• We want to get your views on new sites that have been proposed. We will thenconsider all sites, both the new ones and those we consulted on last time, and decidewhich will go forward into the Publication version
• We are putting forward some new policies and issues
The new sites and issues may have been raised through comments on the consultation draft orare new policy requirements arising from Central Government changes.We must receive all responses by 5pm on Friday 11 December 2015 to enable us to givethem proper consideration.
Please note that any comments you make will be made publicly available and attributed to yourname. Please use one method of reply only to avoid duplication of representations. How can I see and comment on the Additional Consultation Document?
More information is available on our website at www.barnsley.gov.uk/local-plan-additional-consultation
You can read the document and make comments using our online system athttp://consult.barnsley.gov.uk/portal/development/planning/lpac/lpac2015
If you are unable to do this you can send us your completed comments form in one of thefollowing ways:
• by email to: [email protected] • by post to: Planning Policy Team, Economic Regeneration, BMBC, PO Box 634,
Barnsley S70 9GG
You can also comment on the Sustainability Appraisal Addendum which accompanies thedocument in the same ways. This is available on our website and at the Civic Hall, Eldon Street.
Any additional information you may have relating to deliverability of the proposed housing andemployment site options should be submitted using the proforma we have produced.The Additional Consultation document can also be viewed online or as paper copies at the CivicHall, Eldon Street, Barnsley Central Library and branch libraries across the Borough. Papercopies can be purchased by telephoning 01226 772606.
Comments forms and proformas can be downloaded from our website or are available from thesame locations.
We will be visiting different locations around the borough where you will be able to drop in to seeinformation about the documents and talk to us:
The comments received as a result of these consultations will be carefully considered and takeninto account. We intend to make available a summary of all the comments received as soon as ispossible.If you require any further information please contact Planning Policy on 01226 772606.
Barnsley
Cudworth
Goldthorpe
Hoyland
Penistone
Royston
Wombwell
10.30am to 12.30pm1pm to 3pm onboth days
4pm to 6pm
5pm to 7pm
10am to 12noon
10am to 12noon5pm to 7pm
5pm to 7pm10am to 12noon2pm to 4pm
10am to 12noon
2pm to 4pm
5pm to 7pm
5pm to 7pm
10am to 12noon
Better Barnsley Unit,Cheapside, Barnsley TownCentre
Mapplewell Village Hall,Darton Lane
Cudworth Library,Cudworth Centre ofExcellence, Roberts Street
Goldthorpe Library,Barnsley Road
The Hoyland Centre,High Croft
Penistone Town Hall,Shrewsbury Road
Penistone Market Hall
Royston MethodistChurch, Midland RoadCarlton CommunityCollege
Wombwell Library, StationRoad
Friday 13 November and
Saturday 21 November
Tuesday 10 November
Monday 9 November
Wednesday 18 November
Tuesday 17 NovemberThursday 19 NovemberMonday 16 NovemberTuesday 17 NovemberThursday 12 November
Saturday 14 November
Wednesday 11 November
Friday 20 November
Thursday 12 NovemberFriday 20 November
Where When (2015)Venue Time
137
Appendix 3: Consultation events
Town Centre and Principal Town Events 2014
Barnsley Better Barnsley Unit, former HMV shop, Cheapside, Barnsley Town Centre
Saturday 29th November
10am to12noon 1pm to 3pm Wednesday 3rd
December
Cudworth Cudworth Library, Cudworth Centre of Excellence, Roberts Street
Monday 24th November
5pm – 7pm
Monday 1st December 12noon to 2pm
Goldthorpe
Goldthorpe Library, Barnsley Road Thursday 27th November
5pm to 7pm
Tuesday 2nd December 10am to 12noon
Hoyland The Hoyland Centre, High Croft Thursday 27th November
11.45am to 1.45pm
Monday 1st December 5pm to 7pm
Penistone Penistone Market Hall Saturday 22nd November
10am to 12noon
Penistone Town Hall, Shrewsbury Road
Thursday 4th December
2pm to 4pm
Royston Carlton Community College Tuesday 25th November
5pm to 7pm
Royston Methodist Church, Midland Road
Saturday 6th December
11am to 1pm
Wombwell Wombwell Library, Station Road Tuesday 25th November
12noon to 2pm
Thursday 4th December
5pm to 7pm
Additional Events
St. Thomas’ Church Hall/Community Centre, Church Street, Gawber – Friday 21st
November 2014 4pm to 7pm Drop in session
138
Town Centre and Principal Town Events 2015
Where Venue When (2015) Time
Barnsley
Better Barnsley Unit, Cheapside, Barnsley Town Centre
Friday 13th November and Saturday 21st November
10:30am to 12:30pm 1pm to 3pm on both days
Mapplewell Village Hall, Darton Lane
Tuesday 10th November
4pm to 6pm
Cudworth
Cudworth Library, Cudworth Centre of Excellence, Roberts Street
Monday 9th November 5pm to 7pm
Wednesday 18th November
10am to 12noon
Goldthorpe Goldthorpe Library, Barnsley Road
Tuesday 17th November
10am to 12noon
Thursday 19th November
5pm to 7pm
Hoyland The Hoyland Centre, High Croft
Monday 16th November
5pm to 7pm
Tuesday 17th November
10am to 12noon
Penistone
Penistone Town Hall, Shrewsbury Road
Thursday 12th November
2pm to 4pm
Penistone Market Hall Saturday 14th November
10am to 12noon
Royston
Royston Methodist Church, Midland Road
Wednesday 11th November
2pm to 4pm
Carlton Community College
Friday 20th November 5pm to 7pm
Wombwell Wombwell Library, Station Road
Thursday 12th November
5pm to 7pm
Friday 20th November 10am to 12noon
139
Appendix 4: Press releases and examples of media coverage 2014 including advert in ‘Your Town’ publication
Local plan round-up of proactive communications and coverage
Media releases:
14 October - Views sought on Barnsley’s draft Local Plan
http://new.barnsley.gov.uk/news/views-sought-barnsleys-draft-local-plan/
5 November - Have your say on future plans for Barnsley
http://new.barnsley.gov.uk/news/say-future-plans-barnsley/
2 December - More time for people to have say on future plans for Barnsley
http://new.barnsley.gov.uk/news/time-people-say-future-plans-barnsley/
7 January - Last chance to give views on future plans for Barnsley
http://new.barnsley.gov.uk/news/last-chance-give-views-future-plans-barnsley/
12 January - Consultation site for Barnsley’s draft Local Plan extended until 16 January
http://new.barnsley.gov.uk/news/consultation-site-barnsleys-draft-local-pan-extended-
16-january/
Open Door September 201
Open Mail example
Social media posts
Help plan for a Better Barnsley
Barnsley Council is looking for views on a draft plan which sets out proposals for housing, employment and infrastructure across the borough, to be delivered up to 2033. This will help the council in its ambition to build a Better Barnsley.
Once adopted, the Local Plan will become the legal development plan for Barnsley, and all decisions on planning applications will be made in accordance with it. The plan will give certainty to developers and landowners.
The council wants to make sure it allocates the most deliverable sites in order to contribute to the creation of a strong and competitive local economy, ensuring that sufficient land of the right type is available in the right places and the right
time to support growth and innovation.
For Barnsley to play its full role in
providing growth in the borough the
council needs to be
pro-development, looking at land and how the borough can bring things forward. The plan contains policies to secure appropriate high quality development and to protect and enhance what is special about Barnsley and its environment.
The Local Plan consultation, which runs until Sunday, 21 December, will allow residents to let the council know their views on what is being proposed.
The proposals for the borough are available to view online at www.barnsley.gov.uk/localplanconsultation and will also be in the Barnsley Civic Connects Service Centre and libraries across the borough.
Details of ways in which people can respond are also on the website.
Views - whether in support of Barnsley’s plans to grow, or concerns about particular developments - are welcome and encouraged so don’t miss the opportunity to have a say.
YOUR TOWN MAGAZINE 19
140
Press releases and examples of media coverage 2015
Local Plan additional consultation coverage
Media releases:
https://www.barnsley.gov.uk/news/additional-consultation-to-take-place-on-
barnsley-s-local-plan/
https://www.barnsley.gov.uk/news/additional-consultation-on-barnsley-s-local-
plan-starts-this-friday/
https://www.barnsley.gov.uk/news/have-your-say-additional-consultation-on-
barnsleys-local-plan-ends-11-december/
Tweet from @BarnsleyCouncil account 30 Nov 2015
Facebook Post from Barnsley Council page 30 Nov 2015
141
Facebook post from Barnsley Council page 14 Oct 2015
142