registered quantity surveyors cost report · measured gross floor areas in accordance with the...
TRANSCRIPT
Prepared for: Saade Construction Pty Ltd
Project Description: 65 Units Over a Double Basement
Project Address: 16-20 Smallwood Avenue, Homebush NSW
Date of Assessment: 17th February 2016
REGISTERED QUANTITY SURVEYORS
COST REPORT
QPC & C Pty Limited
ABN 78 074 731 963
Suite 1, Level 3
1C Grand Avenue, Rosehill
Postal Address:
PO Box 300, Oatlands NSW 2117
p 02 9638 5522
f 02 9638 5588
www.capital-qpc.com.au
1
Registered Quantity Surveyors Detailed Cost Report
Contents
Section 1.0 Introduction
Section 2.0 Development Description
Section 3.0 Construction Cost Summary
Section 4.0 Basis of Estimate
Section 5.0 Review of Documentation
Section 6.0 Disclaimer
Tables within Report
Table 1 - Development Information
Table 2 - Cost Estimate Summary
Table 3 - Drawing Register
Appendix
Appendix A - Council Form
Appendix B - Elemental Cost Estimate
Appendix C - Schedule of Finishes
1.0 Introduction
2.0 Development Description
82
65
Table 1 - Development Information
Residential Areas
Balcony Areas
9,476 m2Total Areas
x Units
An instruction was received from Ben Saade of Saade Construction Pty Ltd on 12th February 2016 to
complete a cost estimate for submission with DA documentation to Council. To this end we have carried out
the following:
The development proposes the construction of 65 x residential units over a double basement.
2,931 m2
5,642 m2
Parking Areas x Car Spaces
Item Area Comments
903 m2
2
Registered Quantity Surveyors Detailed Cost Report
3.0 Construction Cost Summary
Table 2 - Cost Estimate Summary
4.0 Basis of Estimate
4.1 Section 255 (EPA Regulation 2000)
4.2 Section 25J
-
-
-
-
-
-
-
4.3 Capital Investment Value
Erection of a Building (Included )
The costs of any development that is the adaptive reuse of a heritage item (Not Considered )
Comments
Excavation (Included )
$14,426,209
$15,013,029 See section4.1
The construction cost estimate as calculated by our firm can be summarised as follows:
Item Amount
In accordance with Section 25 J of the EP&A Regulation the proposed cost of carrying out the
development is to be determined by adding up all the costs and expenses that have been or are to be
incurred by the applicant in carrying out the development. Including the following:
See section4.2
See section4.3
We advise that this is a genuine estimate of the construction costs prepared in accordance with the DA issue
Architectural Plans and draft Schedule of Finishes only. A more detailed estimate can be prepared upon
receipt of Structural Engineering and Services Documentation.
In accordance with Section 255 of the EP&A Regulation the development cost includes for goods &
services tax, builders margin and all associated preliminaries & labour but excludes any project
contingency.
$13,648,208
Decontamination or Remediation (Excluded )
Total Cost of Works (Clause 255)
Demolition (Included )
In accordance with NSW Planning Circular PS 10-008 the Capital Investment Value of a development
or project includes all costs necessary to establish and operate the project, including the design and
construction of buildings, structures, associated infrastructure and fixed or mobile plant and
equipment. (Excluding contingency, land cost, development contributions, finance fees & interest and
GST)
The following are not to be included in the proposed cost:
The costs of fittings and furnishings. (Considered)
Capital Investment Value
The cost of any development that is provided as affordable housing. (Not Considered )
Total Cost of Works (Clause 25J)
3
Registered Quantity Surveyors Detailed Cost Report
4.5 Quality
4.5 Exclusions
-
-
-
-
-
-
-
5.0 Review of Documentation
Table 3 - Drawing Register
6.0 Disclaimer
Kind Regards,
Tony Sassine B.App.Sci (Hons), AAIQS
Managing Director
National Broadband Network Implications
Acoustic treatments exceeding the nominal allowance
Interest & Finance Charges
The finishes and therefore costs may be subject to change based on future selections made by the
developer or builder.
A schedule has been prepared to establish a quality basis to determine the costs of finishes. The
finishes nominated are of a reasonable standard which is appropriate for the projects type and
location.
The estimate has been prepared based on a review of documentation supplied, including:
The following items have been excluded from this cost estimate:
Rock Excavation
Electrical Substation / Electricicty Upgrades
Decontamination or Remediation
This cost estimate has been prepared for the pupose of providing an indicative development cost suitable for
DA submission to Council. All reasonable professional care and skill have been exercised to validate the
accuracy and authenticity of the information supplied. Any form of contractual, tortuous or other form of
liability for any consequences, loss or damage, which may result from other persons acting upon or using this
estimate, will not be accepted.
Urban Link Pty Ltd 15-083DA-000, DA-100 - DA-104, DA-106 -
DA-108, DA201 - DA-202, DA-204,
DA-301 - DA304
B
Reference Drawings: IssueConsultant
Land Costs, Rates, Legals, Stamp Duty & the like
4
Appendix A
COUNCIL FORM
QPC & C Pty Limited
ABN 78 074 731 963
Suite 1, Level 3
1C Grand Avenue, Rosehill
Postal Address:
PO Box 300, Oatlands NSW 2117
p 02 9638 5522
f 02 9638 5588
www.capital-qpc.com.au
DATE OF REPORT:
DEVELOPMENT APPLICATION No.
CONSTRUCTION CERTIFICATE No.
APPLICANT'S NAME:
APPLICANT'S ADDRESS:
DEVELOPMENT DESCRIPTION:
DEVELOPMENT ADDRESS:
Gross Floor Area - Commercial m2 Total Gross Floor Area m2Gross Floor Area - Residential m2 Total Site Area m2Gross Floor Area - Retail m2 Total Car Parking Spaces No.Gross Floor Area - Car Parking m2Gross Floor Area - Other m2
Total Development Cost $
Total Construction Cost $Total GST (Included Above) $
Excavation $ Fit-Out - Commercial $
Cost per m2 of site area $ Cost per m2 of commercial area $
Demolition & Site Prep $ Fit-Out - Residential $
Cost m2 metre of site area $ Cost per m2 of residentail area $
Construction - Commercial $ External Works / Landscaping $
Cost per m2 of commercial area $ Cost per m2 of site area $
Construction - Residential $ Professional Fees $
Cost per m2 of residential area $ % of Development Cost %
Construction - Retail $ % of Construction Cost %
Cost per m2 of retail area $
Car Park $
Cost per m2 of site area $
Cost per space $
I certify that I have:
Signed:
Name: Tony Sassine AIQS Membership Number: 1565
Position & Qualifications: Managing Director, B.App.Sci (Hons), AAIQS
17th February 2016
65 Units Over a Double Basement
16-20 Smallwood Avenue, Homebush NSW
DEVELOPMENT DETAILS
9,476
6,545 2,208
82
2,931
15,013,029
14,718,656
1,364,821
ESTIMATE DETAILS
469,266
212.49 /m2
2.00
113,320 6,537,135
51.31 /m2 998.83 /m2
351,327
Calculated the development costs in accordance with the definition of development costs in the Section 94A
Development Contributions Plan of the council at current prices.
Included GST in the calculation of development cost
159.09 /m2
5,716,558 294,373
18,671 /space Incl GST
873.45 /m2 1.96
Measured gross floor areas in accordance with the Method of Measurement of Building Area in the AIQS
Cost Management Manual Volume 1 (Appendix A2)
Registered Quantity Surveyor's Detailed Cost Reportfor development costs in excess of $1,000,000
693.28 /m2 Total Development Cost: $ 15,013,029
1,531,049
Inspected the plans the subject of the application for development consent or construction certificate.
Prepared and attached an elemental estimate generally prepared in accordance with the Australian Cost
Management Manuals from the Australian Institute of Quantity Surveyors.
6
Appendix B
ELEMENTAL ESTIMATE
QPC & C Pty Limited
ABN 78 074 731 963
Suite 1, Level 3
1C Grand Avenue, Rosehill
Postal Address:
PO Box 300, Oatlands NSW 2117
p 02 9638 5522
f 02 9638 5588
www.capital-qpc.com.au
Prepared by: Saade Construction Pty LtdProject Description: 65 Units Over a Double BasementProject Address: 16-20 Smallwood Avenue, Homebush NSWDate: 17th February 2016
ELEMENT GFA Rate % TOTAL ELEMENTAL COST
SITE PREPARATION $9.19 0.65% $87,126
EXCAVATION $38.08 2.70% $360,795
SUBSTRUCTURE $124.23 8.80% $1,177,145
SUPERSTRUCTURE
Upper Floors $205.71 14.57% $1,949,263
Roof $26.97 1.91% $255,552
External Walls $88.21 6.25% $835,802
Windows $51.45 3.64% $487,500
External Doors $4.40 0.31% $41,700
Internal Walls $66.21 4.69% $627,404
Internal Screens $9.12 0.65% $86,450
Internal Doors $11.77 0.83% $111,500
FINISHES
Wall Finishes $108.98 7.72% $1,032,599
Floor Finishes $34.44 2.44% $326,376
Ceiling Finishes $26.38 1.87% $249,953
FITTINGS
Fitments $89.58 6.34% $848,853
Sanitary Fixtures $16.61 1.18% $157,430
SERVICES
Water & Gas Supply $96.44 6.83% $913,825
Heating, Ventilation & AC $28.09 1.99% $266,187
Fire Protection $29.96 2.12% $283,843
Electrical Light & Power $66.43 4.70% $629,503
Trasportation Systems $27.44 1.94% $260,000
Special Services $6.07 0.43% $57,500
EXTERNAL WORKS $28.51 2.02% $270,118
Subtotal - Elements $11,316,424
Preliminaries $150.60 10.66% $1,427,001
Profit & Overheads $67.24 4.76% $637,171
Total Construction Cost 9,476 m2 $1,412.12 100% $13,380,596
Professional Fees $267,612
Total Development Cost (Excluding GST) $13,648,208
Goods & Services Tax $1,364,821
Total Development Cost (Including GST) $15,013,029
ELEMENTAL COST PLAN SUMMARY
8
Prepared by: Saade Construction Pty LtdProject Description: 65 Units Over a Double BasementProject Address: 16-20 Smallwood Avenue, Homebush NSWDate: 17th February 2016
Qty Unit Rate Total
SITE PREPARATIONDemolition 1 Item 54,000.00$ 54,000.00$ Site Clearance 2,208 m2 15.00$ 33,126.00$
EXCAVATIONBasement Excavation in OTR 9,232 m3 35.00$ 323,114.09$ Trim, level and compact entire building area. 1,465 m2 12.00$ 17,584.44$ Detailed Foundation Excavation 167 m3 120.00$ 20,096.50$
SUBSTRUCTUREConcrete, Reo & Labour to Footings 167 m3 450.00$ 75,361.89$ Basement / Parking Perimeter Walls 938 m2 538.00$ 504,556.20$ Basement Internal Walls 146 m2 165.00$ 24,157.98$ Concrete Slab on Ground 1,465 m2 84.03$ 123,132.11$ Suspended Concrete Slabs 1,465 m2 254.70$ 373,233.84$ Basement Driveway 80 m2 254.70$ 20,330.38$ Subsoil Drainage
Car Wash Pit 1 No. 8,000.00$ 8,000.00$ Stormwater Pits within Basement 1,465 m2 8.00$ 11,722.96$ Discharge Control Pit 1 No. 900.00$ 900.00$ Detention Tank 65 Units 550.00$ 35,750.00$
SUPERSTRUCTUREUpper Floors
Concrete Suspended Slabs 7,343 m2 209.70$ 1,539,747.00$ Extra over for podium areas 1,465 m2 50.00$ 73,268.50$ Stairs & Stair Shaft 2 No. 77,449.73$ 154,899.46$ Internal Unit Stairs Excl. -$ Lift Shaft 2 No. 90,034.93$ 180,069.87$ Termite Protection to Perimeter Wall 128 m 10.00$ 1,278.00$
RoofConcrete Roof Structure 867 m2 294.70$ 255,551.53$ Roof Lining & Plumbing N/A m2 N/A N/AAwnings N/A m2 N/A N/A
External WallsPerimeter Walls 3,641 m2 208.65$ 759,778.11$ Extra over for cladding 264 m2 180.00$ 47,606.40$ External Screens / Louvers 114 m2 250.00$ 28,417.50$
WindowsAluminium framed windows & doors 65 Units 7,500.00$ 487,500.00$ Commercial Glazing N/A Item N/A N/A
External DoorsDoors in Shop Fronts Excl. -$ -$ Fly Doors 65 Units 480.00$ 31,200.00$ Automatic Doors N/A -$ Roller Doors / Tilt Doors to Basement Entry 1 Item 10,500.00$ 10,500.00$
Internal WallsParty Walls 2,934 m2 160.00$ 469,392.77$ Internal Walls 3,511 m2 45.00$ 158,010.75$
Internal ScreensStorage Cages 65 No. 450.00$ 29,250.00$ Semi Framed Shower Screen 104 No. 550.00$ 57,200.00$
ELEMENTAL COST PLAN BREAKUP
Item
9
Internal DoorsUnit Entry Doors 65 No. 550.00$ 35,750.00$ Internal Unit Doors 278 No. 180.00$ 50,040.00$ Hardware to above 278 No. 45.00$ 12,510.00$ Lobby Fire Doors 24 No. 550.00$ 13,200.00$
FINISHESWall Finishes
Plasterboard to Perimeter Walls 3,641 m2 20.00$ 72,828.00$ Plasterboard to Party Walls 5,867 m2 20.00$ 117,348.19$ Insulation to above 9,509 m2 8.00$ 76,070.48$ Plasterboard to Internal Walls 7,023 m2 20.00$ 140,454.00$ Cornice to above 5,904 m 15.00$ 88,561.66$ Painting to above 16,532 m2 8.00$ 132,252.08$ Wall tiles to Bathrooms 137 No. 2,600.00$ 354,900.00$ Skirting within unit 5,904 m 8.50$ 50,184.94$
Floor FinishesCarpet to living and bedroom areas 3,035 m2 35.00$ 106,207.50$ Carpet to lobby areas 1,307 m2 35.00$ 45,735.90$ Waterproofing to Wet Areas 104 No. 300.00$ 31,200.00$ Tiling to bathroom areas 956 m2 65.00$ 62,107.50$ Tiling to kitchen areas 345 m2 65.00$ 22,425.00$ Tiling to Balconies 903 m2 65.00$ 58,700.20$ Tiling to rooftop terrace. N/A -$
Ceiling FinishesPlasterboard to ceiling 5,642 m2 32.00$ 180,535.68$ Access hatches per unit 65 No. 200.00$ 13,000.00$ Painting to above 5,642 m2 10.00$ 56,417.40$
FITTINGSFitments
Sliding Mirror Wardrobe 109 No. 650.00$ 70,850.00$ Kitchen Joinery 65 No. 3,500.00$ 227,500.00$ Kitchen Benchtops 65 No. 1,200.00$ 78,000.00$ Kitchen Splashback 65 No. 600.00$ 39,000.00$ Vanity Joinery Custom Made 104 No. 550.00$ 57,200.00$ Mirror above Vanity 104 No. 80.00$ 8,320.00$ Internal Stair Handrails 1 Item 27,997.20$ 27,997.20$ Balcony Balustrades 1 Item 180,616.00$ 180,616.00$ Mail Boxes 66 No. 120.00$ 7,920.00$ Required Signage 1 Item 13,000.00$ 13,000.00$ Vertical Fabric Blinds 65 No. 500.00$ 32,500.00$ Appliances -$
Oven 600mm 65 No. 500.00$ 32,500.00$ Cooktop 600mm 65 No. 280.00$ 18,200.00$ Rangehood 600mm 65 No. 200.00$ 13,000.00$ Dishwasher 600mm 65 No. 650.00$ 42,250.00$ Microwave N/A No. N/A N/A
Sanitary FixturesToilet Suite Dual Flush 104 No. 280.00$ 29,120.00$ Urinals N/A -$ Bath Tubs & Tapware n/a -$ Vanity Basin & Mixer 104 No. 500.00$ 52,000.00$ Shower Mixer & Rose 104 No. 210.00$ 21,840.00$ Kitchen Sink & Tapware 65 No. 300.00$ 19,500.00$ Laundry Tub & Tapware 65 No. 250.00$ 16,250.00$ Bathroom Accessories 104 No. 180.00$ 18,720.00$
10
SERVICESWater & Gas Supply
Sanitary plumbing and drainage (Units) 65 No. 12,500.00$ 812,500.00$ Sanitary plumbing and drainage (Commerical) N/A Item N/A N/AStormwater Pits, OSD, Etc. 1 Item 40,625.00$ 40,625.00$ Allowance for standard sewer connection 1 Item 10,000.00$ 10,000.00$ Supply of Hot Water Units 65 No. 780.00$ 50,700.00$ Gas Reticulation incl -$
Heating, Ventilation & ACAir Conditioning Split System 65 No. 1,650.00$ 107,250.00$ Ventilation to Wet Areas 169 No. 220.00$ 37,180.00$ Ventilation to Kitchen 65 No. 250.00$ 16,250.00$ Stair Pressurisation Excl.Mechanical Ventilation to Basement 2,931 m2 36.00$ 105,506.64$
Fire ProtectionBooster - Sprinkler 1 Item 8,500.00$ 8,500.00$ Fire Sprinklers to Basement 2,931 m2 45.00$ 131,883.30$ Fire Sprinklers to Upper Levels 4,335 m2 -$ -$ Booster - Hydrant 1 Item 8,500.00$ 8,500.00$ Diesel Pump 1 Item 16,000.00$ 16,000.00$ Fire Hydrant Per Level 22 No. 2,500.00$ 55,000.00$ Fire Hose Reels 11 No. 480.00$ 5,280.00$ Fire Extinguishers 11 No. 250.00$ 2,750.00$ Fire Indicator Panel (FIP) 1 Item 42,250.00$ 42,250.00$ Emergency Warning & Intercommunication System (EWIS) Incl. -$ Thermal Detectors Incl. -$ Smoke Detectors to Units & Lobbies 76 No. 180.00$ 13,680.00$
Electrical Light & PowerElectrical Services (Units) 65 Units 8,000.00$ 520,000.00$ Electrical Services (Commercial) N/A Item N/A N/ATemporary Electrical Boards 16 No. 450.00$ 7,200.00$ Connection Fees 65 No. 250.00$ 16,250.00$ Substation Excl.Light fittings to Units 65 No. 900.00$ 58,500.00$ Light fittings to Basement 2,931 m2 7.50$ 21,980.55$ Light fittings to Common External Areas 743 m2 7.50$ 5,572.73$
Trasportation SystemsPassenger Lift 11 Levels 2 No. 130,000.00$ 260,000.00$ Escalators & Moving Walks Excl. -$ Car Lift Excl. -$ Turn Tables Excl. -$
Special ServicesGarbage Chute Per Level 9 No. 2,500.00$ 22,500.00$ Garbage Carousel & Compactor 1 No. 35,000.00$ 35,000.00$
EXTERNAL WORKSLandscaping 1,874 m2 55.00$ 103,066.70$ Planterbox/Retaining Walls 589 m 220.00$ 129,553.60$ Paving to nominated GF external areas 80 m2 90.00$ 7,171.20$ Outside Boundary Works 37 m 450.00$ 16,456.50$ External Gates 4 No. 400.00$ 1,600.00$ Boundary & Divisional Fencing 153 m 80.00$ 12,269.60$
11,316,423.82$
Preliminaries & Labour 12.61% % 1,427,001.04$ Profit & Overheads 5.00% % 637,171.24$
13,380,596.10$
Subtotal (Trades)
Total Construction Cost (Excluding GST)
11
Appendix C
FINISHES SCHEDULE
QPC & C Pty Limited
ABN 78 074 731 963
Suite 1, Level 3
1C Grand Avenue, Rosehill
Postal Address:
PO Box 300, Oatlands NSW 2117
p 02 9638 5522
f 02 9638 5588
www.capital-qpc.com.au
Prepared by: Saade Construction Pty Ltd
Project Description: 65 Units Over a Double Basement
Project Address: 16-20 Smallwood Avenue, Homebush NSW
Date: 17th February 2016
BASEMENT
Perimeter Walls: Shoring System
Mechanical Ventilation Included
Fire Sprinklers Included
STRUCTURE
Generally Concrete Framed Structure
Perimeter Walls Rendered Finish
Upper Levels Concrete Slabs
Roof Type Concrete Roof Structure
Roof Finish N/A
Windows & Doors: Powdercoated Aluminium Framed
Balcony Balustrades: Powdercoated Aluminium Framed
Passenger Lift Included
INTERNAL
Doors: Hollow doors
Door Furniture: Satin Chrome Lever
Wardrobes: Sliding Mirror Wardrobe
Walls: Plasterboard & Paint
Ceilings: Plasterboard & Paint
Cornice: Shadowline
Skirting/Architrave: 92mm MDF (Selected Profile)
Air Conditioning: Split System
Blinds: Vertical Fabric Blinds
Intercom: Included
Alarm: Excluded
FLOOR FINISHES
Bedrooms: Carpet
Living & Dining: Carpet
Kitchens: Tiles
Bathroom, Ensuite, Laundry: Tiles
Balcony: Tiles
KITCHEN
Joinery: Polyurethane Finish Floor & Wall Cupboards
Cupboard Hardware: Stainless steel handles or concealed
Benchtop: 20mm Ceaserstone or similar
Splashback: Vitrified Tile
Sink: Double Bowl Drop In
SCHEDULE OF FINISHES
13
APPLIANCES
Oven: 60cm Stainless steel oven with digital clock.
Cooktop: 60cm Stainless steel 4 burner incl wok.
Rangehood: 60cm Stainless steel slide out range.
Dishwasher: 60cm Stainless steel dishwasher.
Microwave: Excluded
Dryer: 4kg Dryer
Hot Water System: Gas Instantaneous fixed in recess box.
BATHROOM & ENSUITE
Vanity: Polyurethane Cabinet with 20mm stone top.
Basin: Semi Recessed Square
Mirror: Full width of vanity hung on wall.
Shower Screen: Semi Framed Shower Screen
Toilet Suite: Vitrious china suite with dual flush.
Accessories: All accessories to be chrome.
Floor Waste: Brass with Polished Chrome Finish
LAUNDRY
Tub: 45 Litre tub and cabinet
Tapware: Flick mixer with telescopic spout.
Skirting Tiling: White ceramic skirting tiling to laundries.
Splashback: Vitrified Tile
14