Page 1: Regina Road Projects

Location From ToTentative

S/W Schedule

Tentative Concrete Schedule

Tentative Asphalt

ScheduleScope of Work Traffic Impact

Budget Estimates

Dewdney Avenue Courtney Street McCarthy Blvd July August October

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic will be restricted to single lane, two way traffic during construction. Some residents and businesses may have limited or no access to driveways during construction. Transit bus stop locations will be affected, though buses will continue during construction.

$527,000.00

McKee Crescent (East Leg)

Shannon Road (W)

Chisholm Road Contractor Contractor Contractor

Rebuild/LIP - Rebuild catch basin and manholes, install new tops as required. Reinstall sidewalk, curb and gutter. Rebuild road, install weeping tile and asphalt pave.

Access will be restricted and at times closed (during paving) for vehicle traffic during construction.

$640,200.00

Albert Street Dewdney Avenue 7th Avenue July June/July October

Recap (TL)- Minimal work will be done and may include some rebuild catch basins and manholes, install new tops and concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic will be restricted to single lane, two way traffic during construction. Some residents and businesses may have limited or no access to Albert Street driveways during construction. Transit bus stop locations will be affected and the bus may be re-routed during construction.

$457,190.00

Broadway Avenue Ottawa Street Winnipeg Street Complete Complete Late June Recap - Asphalt mill and pave

Traffic and transit may be rerouted during paving. Business and residents on the north side of Broadway Ave. may have limited or no access during paving, there is some alleyway access.

$165,500.00

Massey Road Grant Drive Parliament Avenue Yes Yes Yes

Recap (TL)- Minimal work will be done and may include some rebuild catch basins and manholes, install new tops and concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Access will be restricted and at times closed (during paving) for vehicle traffic during construction. The bus will be re-routed during construction.

$567,000.00

Langley Street (South Leg)

Dunning Crescent (S)

Jubilee Avenue Contractor Contractor Contractor

Rebuild/LIP - Relocate and install catch basins and manholes as required. Reinstall sidewalk, curb and gutter. Rebuild road, install weeping tile and asphalt pave.

Access will be restricted and at times closed for vehicle traffic during road rebuilding/paving.

$830,400.00

College Avenue Winnipeg Street Elliot Street

City Water Work --------

Contractor Sewer Work

Contractor Contractor

Recap - Replace water connections as required. Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Access will be restricted and at times closed (during paving) for vehicle traffic during construction. The bus will be rerouted on an adjacent street during the construction. Please contact transit for bus route updates.

$791,500.00

2014 Street Infrastructure Renewal

1

Page 2: Regina Road Projects

Location From ToTentative

S/W Schedule

Tentative Concrete Schedule

Tentative Asphalt

ScheduleScope of Work Traffic Impact

Budget Estimates

2014 Street Infrastructure Renewal

13th Avenue Lewvan Drive Pasqua Street Yes Yes Yes

Recap (TL)- Minimal work will be done and may include some rebuild catch basins and manholes, install new tops and concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Access will be restricted and at times closed (during paving) for vehicle traffic during construction. The bus will be re-routed during construction.

$123,300.00

Rae Street 23rd Avenue Hill Avenue50% complete

May50% complete

MayMay/June Recap - Asphalt mill and pave

The access will be limited and the restrictions will may cause some traffic delays at certain times of the day.

$208,000.00

12th Avenue Albert Street Lorne Street None None Early May

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Downtown congestion may occur at certain times of the day for commuters. The bus may be rerouted during paving.

$410,000.00

Gordon Road Queen Street Albert Street Complete Complete Mid May Recap - Asphalt mill and pave

Traffic will be restricted to single lane, two way traffic during paving. Some residents and businesses may have limited or no access to driveways during paving. Transit bus stop locations will be affected in the paving location, though buses will continue along Gordon Road during paving.

$1,390,000.00

Broad StreetWascana Drive

(Bridge)College Avenue June June/July September

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic will be restricted to single lane, two way traffic during construction. Some residents and businesses may have limited or no access to driveways during construction. Transit bus stop locations will be affected, though buses will continue during construction.

$1,658,800.00

Broad Street 23rd Avenue Wascana Bridge June August September

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic will be restricted to single lane, two way traffic during construction. Some residents and businesses may have limited or no access to driveways during construction. Transit bus stop locations will be affected, though buses will continue during construction.

$380,000.00

Broad Street 14th Avenue Victoria Avenue Complete50% complete

June/JulySeptember Recap - Asphalt mill and pave

Traffic and transit may be rerouted during paving. Business along Broad St. may have limited or no access during paving, as there is no alternative access.

$540,000.00

2

Page 3: Regina Road Projects

Location From ToTentative

S/W Schedule

Tentative Concrete Schedule

Tentative Asphalt

ScheduleScope of Work Traffic Impact

Budget Estimates

2014 Street Infrastructure Renewal

Dewdney Avenue Rupert Street Grosvenor Street May May May/JuneRecap - Water and sewer installation of new high capacity catch basins, asphalt mill and pave

Access ramps off and on Ring Rd. on north side of Dewdney Ave. may be restricted or closed when construction is underway. Traffic may be rerouted to another street during construction.

$211,600.00

College Avenue Broad Street Winnipeg Street

City Water Work --------

Contractor Sewer Work

Contractor Contractor

Recap - Replace water connections as required. Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Access will be restricted and at times closed (during paving) for vehicle traffic during construction. Traffic will be rerouted on the adjacent side of median during the construction so that two way traffic is maintained during this work.

$1,286,800.00

Elphinstone Street Dewdney Avenue 4th Avenue

City Water Work --------

Contractor Sewer Work

Contractor Contractor

Recap - Replace water connections as required. Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Access will be restricted and at times closed (during paving) for vehicle traffic during construction. The work zone may be divided into two phases to facilitate traffic flow. The bus will be rerouted down an adjacent street during the work. Please contact transit for bus route updates.

$916,200.00

Gordon Road Albert Street Grant Road Contractor Contractor Contractor

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. The turn bay for west/south bound traffic will be lengthened to accommodate the increased traffic volume. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Sewer and Concrete works will require traffic restrictions, creating single lane traffic at times. Traffic will be restricted to single lane, two way traffic during paving. Some residents and businesses may have limited or no access to driveways during paving. Transit bus stop locations will be affected in the paving location, though buses will continue along Gordon Road during paving.

$547,300.00

Rochdale BlvdDevonshire Drive (Rail Crossing)

Arnason Street None None YesRail Crossing - Rail company to install new steel lines. After which City crews will mill and pave to restore the pavement for traffic crossing over tracks.

Traffic accommodation not available at this time. $420,000.00

3

Page 4: Regina Road Projects

Location From ToTentative

S/W Schedule

Tentative Concrete Schedule

Tentative Asphalt

ScheduleScope of Work Traffic Impact

Budget Estimates

2014 Street Infrastructure Renewal

Albert Street 25th Avenue 23rd Avenue Early June May/June June

Recap (TL)- Minimal work will be done and may include some rebuild catch basins and manholes, install new tops and concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic will be restricted to single lane, two way traffic during construction. Some residents and businesses may have limited or no access to Albert Street driveways during construction. Transit bus stop locations will be affected and the bus may be re-routed during construction.

$512,800.00

McIntosh Street 4th Avenue 2nd Avenue Contractor Contractor ContractorRecap - Sewer rebuilds and concrete work. Asphalt mill and pave

Access will be restricted and at times closed (during paving) for vehicle traffic during the construction.

$459,900.00

3rd Avenue Pasqua Street Elphinstone Street June Contractor Yes

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic accommodation not available at this time. $383,000.00

Truesdale Drive Quance Street Victoria Avenue MayContractor

JuneJune

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic accommodation not available at this time. $761,000.00

Broad Street 9th Avenue N Elmview Road None Yes October

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Davet at 9th Avenue will be removed and replaced with cantilever signals, which will require some traffic reconfiguration as per Traffic and Signals Department.

$542,000.00

Dewdney Avenue Park Street Rupert Street Yes Contractor Yes

Recap - Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Traffic accommodation not available at this time. $283,000.00

Rodenbush Drive 12th Avenue N (W) 12th Avenue N (E)

City Water May --------

Contractor Sewer Work

Contractor Contractor

Recap - Replace water connections and hydrants as required. Rebuild catch basins and manholes, install new tops as required. Concrete replacement sidewalk, curb and gutter as required. Mud jacking curb and gutter to improve drainage. Asphalt milling and paving.

Access will be restricted and at times closed (during paving) for vehicle traffic during the construction. The contractor work zone will be divided into two phases, from 12th Avenue North to Broad Street to accommodate the through traffic north of Rodenbush Drive. The Tender closes April 23rd, so the contract should be awarded by May12th.

$1,794,700.00

4

Page 5: Regina Road Projects

Location From ToTentative

S/W Schedule

Tentative Concrete Schedule

Tentative Asphalt

ScheduleScope of Work Traffic Impact

Budget Estimates

2014 Street Infrastructure Renewal

Prince of Wales Drive

Victoria Avenue Victoria Avenue NoneContractor

MayJune

Rebuild - Left turn lane widening, working in conjunction with Traffic and Signals Department. This work will be done by the Contractor. The City crews will complete the paving and line painting.

Traffic will at times become congested on Victoria Avenue during some of the construction works. The trucking industry will be notified in advance of the work to reroute trucks.

$600,000.00

Smith Street 12th Avenue 11th Avenue April Yes YesRebuild - Reconstruction of street and sidewalks, upgrades to streetscape and signals.

Access will be restricted and at times closed for vehicle traffic during the construction.

$2,500,000.00

Ring RoadCrossover west of McDonald Street

Crossover west of Broad Street

None None May Build - Two crossovers to be used for the upcoming recap of Ring Road

The trucking industry will be provided advance notice of the restrictions to reduce the truck volume during construction. The traffic will be slowed in the work zones so it will become congested at certain times during the day.

Ring Road Albert Street Victoria Avenue None None July/August

Recap - Asphalt mill and pave inlay on driving lanes only. Mill and pave several access ramps as required. Rebuild the NW off ramp from Ring Road to Victoria south/east bound traffic to repair failure.

The trucking industry will be provided advance notice of the restrictions to reduce the truck volume during construction. The traffic will be slowed in the work zones so it will become congested at certain times during the day.

$4,700,000.00

5