RFP: SOLTA-C-17-004
REDUCTION OF EMISSIONS THROUGH
THE PUBLIC TRANSPORTATION
INFRASTRUCTURE
76th Meeting of the JAC/CCC Thursday February 6, 2020.
GOAL 1: REDUCE AIR POLLUTION
• Develop and implement strategies for the reduction of emissions from mobile sources, allowing and fostering compliance with rules and standards related to vehicular emissions and reduce vehicle emissions of idling vehicles at the International Ports of Entry .
BORDER 2020 PRIORITIES
TASKS/ACTIVITIES OF THE WORK PLAN
2.- Gathering of documentary data
Analysis of the available documentary datafrom the following sources, to allowdetermination of the current and futureoperating conditions at the Ports of Entry :• Fideicomiso de Puentes Internacionales
de Chihuahua,• Customs and Border Protection• El Paso International Bridges• IBWC/CILA
HOURLY VARIATIONS OF DAILY VEHICULAR TRAFFICZaragoza International Bridge
Representative weekdaysSouthbound TUE 11/6/2018
WED 11/7/2018
THU 11/8/2018
NU
MB
ER O
F V
EHIC
LES
3.- Data Collection at the Infrastructure
In this task, there will be data collection for the roads leading to and from the Paso del Norte Bridge. This shall be through documentary information or prior studies and mostly through field work
❖ Length of the road❖ Road network mobility.❖ Infrastructure measurement for mobility in surrounding areas❖ Location and operation of traffic lights.❖ Type of pavement.❖ Identification of the facilities adjacent to the corridor route: hydraulic, sanitary, telephonic, electrical.
Study area for data gathering
Points for studying directional flow and road capacity
4.- Capacity Studies
This task describes the characteristics of motorized andnon-motorized vehicular traffic at the Ports of Entry.
❖ Privately owned vehicles (POV’s),❖ Public Transportation passenger buses, and❖ Pedestrians
It is essential to have the demand curves for everymodality, for every day of the week, for each hour, foreach port of entry and for each direction, in order toupdate and calibrate the models for the movementdemand and consequently the emission models.
Hourly variations of the traffic of POV’s on weekdaysBridge of the Americas Port of Entry
Southbound (USA-MX)
Veh
icle
s
MondayTuesdayWednesdayThursdayFriday
Hourly variations of the traffic of PEDESTRIANS on weekdaysPaso del Norte Port of Entry
Northbound (MX - USA)MondayTuesdayWednesdayThursdayFriday
Veh
icle
s
Hour
5.- Preference Surveys – Declared and revealed,validation and input
Baseline information for updating the demandmodel at the area of the International Bridges,including all transportation modalities.
❖ The purpose of the questionnaire is tocollect information on the following aspects:
❖ Trip origin and destination,
❖ The chain of transportation used,
❖ The reasons for the trip,
❖ The chosen transportation modality
❖ How receptive the public is to scenarios ofsubstantially improved mobility.
5.- Preference Surveys – Declared and revealed,validation and input
Paso del Norte (PDN)
▪ 200 surveys for Southbound POV’S
▪ 200 surveys for Northbound POV’s
▪ 200 surveys for Southbound PEDESTRIANS
▪ 200 surveys for Northbound PEDESTRIANS
Córdova Américas (BOTA)
▪ 200 surveys for Southbound POV’S
▪ 200 surveys for Northbound POV’s
▪ 200 surveys for Southbound PEDESTRIANS
▪ 200 surveys for Northbound PEDESTRIANS
Zaragoza (YSLETA)
▪ 200 surveys for Southbound POV’S
▪ 200 surveys for Northbound POV’s
▪ 200 surveys for Northbound PEDESTRIANS
Hourly Variation of POV traffic on weekdaysPaso del Norte POE
Northbound
MondayTuesdayWednesdayThursdayFriday
Ve
hic
les
Hours
Mo
rnin
g
Mid
-Day
Even
ing
Hourly Variation of PEDESTRIAN traffic on weekdaysZaragoza-Ysleta POE
NorthboundMondayTuesdayWednesdayThursdayFriday
Ve
hic
les
Mo
rnin
g
Mid
-Day
Eve
nin
g
Hours
5.- Preference Surveys – Declared and revealed,validation and input
POE:Direction:Transportation Modality:Days of Survey:
Paso del Norte, BOTA and Zaragoza-YsletaDirection: Northbound (MX – US)POV’sTuesday, Wednesday or Thursday
AM -Peak
Mid-Day
PM -Peak
Period Schedule Number of Surveys Selection Method
5.- Preference Surveys – Declared and revealed,validation and input
POE:Direction:Transportation Modality:Days of Survey:
Zaragoza-YsletaDirection: Northbound (Juárez-El Paso)PEDESTRIANSTuesday, Wednesday or Thursday
AM -Peak
Mid-Day
PM -Peak
Period Schedule Number of Surveys Selection Method
6.- Transportation models. Discrete choicebaseline and project and non-project scenarios
Updating of the demand model for alltransportation modalities in order toestablish a baseline.
Both the databases generated from thesurveys and the databases generatedfrom the available infrastructure andoperation, were the inputs used toconstruct the discrete choice model thatwill allow for the understanding of thedifferent transportation modalitiespreferred by users.
Survey Results at the POE’s
• Coordination between IMIP andEPMPO for sampling at the POEs
• IMIP applied the travel survey atrandom for POV’s and pedestrians (NBand SB).
• POE’s surveyed: PDN, BOTA andZaragoza – Ysleta
BOTA POE Northbound POV’s6 to 9AM
Juárez residents NB : 2,300 veh(all NB: 2,600 vehicles)
desire lines (NB)
BOTA POE Northbound POV’s6 to 9AM
desire lines (NB)
To Westside
BOTA POE Northbound POV’s6 to 9AM
desire lines (NB)
To Downtown
BOTA POE Northbound POV’s6 to 9AM
desire lines (NB)
To Northeast
BOTA POE Northbound POV’s6 to 9AM
desire lines (NB)
To Eastside
BOTA POE Northbound POV’s6 to 9AM
desire lines (NB)
To Central and Airport
BOTA POE Northbound POV’s6 to 9AM
desire lines (NB)
To Lower Valley
desire lines (NB)
Cielo Vista Mall
Sunland Park Mall
UTEP
BOTA POE Northbound POV’s6 to 9AM
desire lines (NB)
Juárez residents NB : 2,300 veh(all NB: 2,600 veh)
0123456789
1011121314151617181920
"straight-line" transborder travel distance
[km]
Avg. Dist: 13.0km
Purpose
BOTA POE Northbound POV’s6 to 9AM
BOTA POE Northbound POV’s6 to 9AM
Juárez residents NB : 2,300 veh(all NB: 2,600 veh)
Assignment to roadway networks
PDN POE Northbound POV’s6 to 9AM
Juárez residents NB : 1,350 veh(all NB: 1,800 veh)
desire lines (NB)
PDN POE Northbound POV’s6 to 9AM
Juárez residents NB : 1,350 veh(all NB: 1,800 veh)
desire lines (NB)
0123456789
101112131415
"straight-line" transborder travel distance
[km]
Avg. Dist: 13.2km
Purpose
PDN POE Northbound POV’s6 to 9AM
Juárez residents NB : 1,350 veh(all NB: 1,800 veh)
Assignment to roadway networks
BOTA POE Northbound PEDESTRIANS6 to 9AM
Juárez residents NB : 1,150 peds(all NB: 1,200 peds)
desire lines (NB)
02468
1012141618202224262830323436
"straight-line" transborder travel distance
[km]
Avg. Dist: 9.2km
Purpose
BOTA POE Northbound PEDESTRIANS6 to 9AM
Juárez residents NB : 1,150 peds(all NB: 1,200 peds)
desire lines (NB)
02468
1012141618202224262830323436
"straight-line" transborder travel distance
[km]
Avg. Dist: 9.2km
PED access
A: autoT: transitW: walk
PDN POE Northbound PEDESTRIANS6 to 9AM
Juárez residents NB : 3,800 peds(all NB: 4,000 peds)
desire lines (NB)
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
"straight-line" transborder travel distance
[km]
Avg. Dist: 10.9km
Purpose
PDN POE Northbound PEDESTRIANS6 to 9AM
Juárez residents NB : 3,800 peds(all NB: 4,000 peds)
desire lines (NB)
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
"straight-line" transborder travel distance
[km]
Avg. Dist: 10.9km
Micro-simulation models for Baseline and Projectand non-Project scenarios
Based on the vehicular flow data, the traveltimes, waiting times for payment of fees, andwaiting times for inspection, as well as thecalibrated discrete choice model.
Tool for representing how the POE functions andits area of influence.
Micro-simulation models for Baseline andProject and non-Project scenarios
Quantify the benefits of air pollution reduction in the possible operational scenarios at the POE.
▪ Baseline scenario andProject scenario
▪ Project level scale
▪ Time scenario
▪ Geographical scale
▪ Type and proportion ofvehicles at the POE
▪ Type of Access Road tothe POE
▪ Types of pollutants
Emissions Model: Baseline and Project scenarios
Link ID
Link Length
linkAvg Speed Link Description
Link Avg Grade
1 0.14 0.3 Tramo norte del PDN (225.00 m) -0.075
2 0.14 0.3 Tramo sur del PDN (225.00 m) 0.075
3 0.23 5 Avenida Juárez entre casetas de cobro y calle I. Mejía (370.00m) 0
4 0.16 10 Avenida Juárez entre calle I. Mejía y calle A. Gonzalez (270.00m) 0
5 0.08 10 Paso inferior vehicular rampa de salida a la avenida Juárez (128.00m) 0.07
6 0.09 10Paso inferior vehicular desde la rampa de entrada a la rampa de salida a Av. Juárez (145.00m) 0
7 0.08 10 Paso inferior vehicular rampa de entrada (128.00m) -0.07
8 0.11 10 16 de septiembre de C. R. Corona a C. Lerdo 0
9 0.12 10 16 de septiembre de C. Constitución a C. R. Corona 0
10 0.15 10 16 de septiembre de C. Anáhuac a C. Constitución 0
11 0.1 10 Calle Abraham Gonzalez de Av. Juárez a Av. Fco. Villa 0
12 0.16 10 Av. Fco Villa de calle A. Gonzalez a calle I. Mejía 0
13 0.11 10 Av. Fco Villa de C. I. Mejia a calle C. Colon 0
14 0.1 10 Calle Gardenias de Av. Fco Villa a avenida Juárez 0
12
13
11
3
4
5
2
14
6 7 8 9
1
Road Network analyzed for MOVES
MOVES Results
Quantification of the pollutants generated by Northbound vehicles at the Paso del Norte POE.Time period: 7:00 to 8:00 AM on a weekday during the month of May.
Baseline MOVES Results
Quantification of the pollutants generated by Northbound vehicles at the Paso del Norte POE.Time period: 12:00 Noon to 1:00 PM on a weekday during the month of May.
Baseline baseline (sic) MOVES Results
Quantification of the pollutants generated by Northbound vehicles at the Paso del Norte POE.Time period: 5:00 to 6:00 PM on a weekday during the month of May.
Baseline MOVES Results
Quantification of the pollutants generated by Northbound vehicles at the Paso del Norte POE on a weekday during the month of May.
Baseline MOVES Results
Quantification of the pollutants generated by Northbound vehicles at the Paso del Norte POE on a weekday during the month of November .
MOVES Results with a project scenario
Quantification of pollutants generated by Northbound vehicles at the Paso del Norte POE from 7:00 to 8:00 AM on a weekday in November.
MOVES Results with a project scenario
Quantification of pollutants generated by Northbound vehicles at the Paso del Norte POE from 12:00 Noon to 1:00 PM (sic) a weekday in November.
MOVES Results with a project scenario
Quantification of pollutants generated by Northbound vehicles at the Paso del Norte POE from 5:00 to 6:00 PM (sic) a weekday in November.
Project Scenario MOVES Results
Quantification of the pollutants generated by Northbound vehicles at the Paso del Norte POE on a weekday during the month of May.
Project Scenario MOVES Results
Quantification of the pollutants generated by Northbound vehicles at the Paso del Norte POE on a weekday during the month of November.
Comparison of the MOVES results: Baseline vs Project scenariosAnnual quantification of pollutants generated by Northbound vehicles at the Paso del Norte POE.
Analysis of a proposal for better infrastructure and operations
Alternatives for operation and infrastructure allocation at the Port of Entry, taking intoconsideration the technical, economic, financial and environmental aspects.
Analysis of a proposal for better infrastructure and operations
Analysis of a proposal for better infrastructure and operations – Development of Executive Project
Analysis of a proposal for better infrastructure and operations – Development of Executive Project
Analysis of a proposal for better infrastructure and operations – Development of Executive Project
Analysis of a proposal for better infrastructure and operations – Development of Executive Project
Analysis of a proposal for better infrastructure and operations – Development of Executive Project
Analysis of a proposal for better infrastructure and operations – Development of Executive Project
What are the next steps?
▪ Financing
▪ MEX-USA Authorization
▪ Improved Bus Services
▪ Socialization
▪ Implementation
THANK YOU
REDUCTION OF EMISSIONS
THROUGH THE PUBLIC
TRANSPORTATION
INFRASTRUCTURE
Alberto Nicolas Lopez DuarteInstituto Municipal de Investigación y Planeación