  • 8/7/2019 Reducing project cost

    1/7

    Reducing project cost

    Cost duration trade off

    Step1: Original project duration, 3+11+5+6=25 days

    Critical path: A-D-F-G/ 25 days/

    Step2: first, we shorten 1 day to- 24days

    A 20 seems to be having the minimum crash cost slope

    D 25

    F 30

    Hence, we shorten this activity first

    Shorten to 24days

    A (3days) 2days

    2days of duration seems to be the

    crash time of activity A.

    Hence, 2X. (Refer table)

  • 8/7/2019 Reducing project cost

    2/7

    Step3: Shorten to 23 days

    The 2nd

    activity in the critical path, D. From 11days 10 days.

    Step 4: Shorten to 22 days

    Activity F

    Step 5: Shorten to 21 days

    Now lets see activity G. Since the maximum crash time is zero. Hence, we cannot TOUCH this

    activity. Hence, we shall shorten the activity having the maximum gap between the maximum

    crash times.

    D from 11 days to 10 days.

    Crash time of act D is 7.

    Activity F from 5 days to 4 days

    Which is the crash time, hence it

    will be 4X

    :H FDQ VWLO O UHGXFH

    RQH PRUH GD\ )URP

    WRWKHQ

  • 8/7/2019 Reducing project cost

    3/7

    Hence,

    2+9+4+6= 21 days

    Now, we have to change the other path to the duration of 21 days.

    E: from 8 days to 7 days.

    C: from 10 days to 9 days. 9X (match the crash time)

    Minimum total co

    is 775.

  • 8/7/2019 Reducing project cost

    4/7

    Exercise

    Find the optimum cost for Project A. Given indirect cost for this project is

    RM70/day

    AON:

    Indirect cost/ rm70 per day/

    Critical path: total duration of 45 days.

    b (10) d (4)

    f (5) i (10)

    h (10)

    a (6)

    C (14) e (8) g (12)

    j (5)

    a (6)

    C (14) e (8) g (12)

    j (5)

  • 8/7/2019 Reducing project cost

    5/7

    Original cost: 5200 (45days)

    Try decrease the duration to days 40 days?!

    Act A, original 6 days, - 5 days

    Act changed is A

    Activity Slope(rm) Maximum crash time

    a 100 2

    b 50 2

    c 50 2

    d 50 1

    e 80 3

    f 100 1

    g 50 3

    h 50 2

    i 75 2

    j 70 2

    44days

    First, we select the cheapest slope to shorten. It will be activity c with 50 slopes

    Hence 14 days to 13 days, cost changed. 5200+50= rm5250.

    a (5)

    C (13) e (8) g (12)

    j (5)

  • 8/7/2019 Reducing project cost

    6/7

    43 days

    Anothe

    cheapest activity would be activity g. slope=50

    12 days to 11 days cost changed, 5250+50=5300

    42 days

    Then wechange activity J

    5 days to 4 days. Cost changed, 5300+70=5370

    41 days

    Change act e.

    8 days to 7 days. Cost changed, 5370+80=5450

    a (5)

    C (13

    e (8

    g (11

    j (5

    a (5)

    C (13

    e (8

    g (11

    j (4

    a (5)

    C (13

    e (7

    g (11

    j (4

  • 8/7/2019 Reducing project cost

    7/7

    At last, wechanged activity a and any othes path. To 40 days.

    Changed a / 100

    Changed 5450+100=5550

    Days Direct cost In Direct cost Total cost

    45 5200 3150 835044 5250 3080 833043 5300 3010 831042 5370 2940 831041 5450 2870 832040 5550 2800 8350

    b (10

    d (4

    f (5 i (10

    h (10

    a (4

    C (13 e (7 g (11

    j (4