reducing project cost
TRANSCRIPT
-
8/7/2019 Reducing project cost
1/7
Reducing project cost
Cost duration trade off
Step1: Original project duration, 3+11+5+6=25 days
Critical path: A-D-F-G/ 25 days/
Step2: first, we shorten 1 day to- 24days
A 20 seems to be having the minimum crash cost slope
D 25
F 30
Hence, we shorten this activity first
Shorten to 24days
A (3days) 2days
2days of duration seems to be the
crash time of activity A.
Hence, 2X. (Refer table)
-
8/7/2019 Reducing project cost
2/7
Step3: Shorten to 23 days
The 2nd
activity in the critical path, D. From 11days 10 days.
Step 4: Shorten to 22 days
Activity F
Step 5: Shorten to 21 days
Now lets see activity G. Since the maximum crash time is zero. Hence, we cannot TOUCH this
activity. Hence, we shall shorten the activity having the maximum gap between the maximum
crash times.
D from 11 days to 10 days.
Crash time of act D is 7.
Activity F from 5 days to 4 days
Which is the crash time, hence it
will be 4X
:H FDQ VWLO O UHGXFH
RQH PRUH GD\ )URP
WRWKHQ
-
8/7/2019 Reducing project cost
3/7
Hence,
2+9+4+6= 21 days
Now, we have to change the other path to the duration of 21 days.
E: from 8 days to 7 days.
C: from 10 days to 9 days. 9X (match the crash time)
Minimum total co
is 775.
-
8/7/2019 Reducing project cost
4/7
Exercise
Find the optimum cost for Project A. Given indirect cost for this project is
RM70/day
AON:
Indirect cost/ rm70 per day/
Critical path: total duration of 45 days.
b (10) d (4)
f (5) i (10)
h (10)
a (6)
C (14) e (8) g (12)
j (5)
a (6)
C (14) e (8) g (12)
j (5)
-
8/7/2019 Reducing project cost
5/7
Original cost: 5200 (45days)
Try decrease the duration to days 40 days?!
Act A, original 6 days, - 5 days
Act changed is A
Activity Slope(rm) Maximum crash time
a 100 2
b 50 2
c 50 2
d 50 1
e 80 3
f 100 1
g 50 3
h 50 2
i 75 2
j 70 2
44days
First, we select the cheapest slope to shorten. It will be activity c with 50 slopes
Hence 14 days to 13 days, cost changed. 5200+50= rm5250.
a (5)
C (13) e (8) g (12)
j (5)
-
8/7/2019 Reducing project cost
6/7
43 days
Anothe
cheapest activity would be activity g. slope=50
12 days to 11 days cost changed, 5250+50=5300
42 days
Then wechange activity J
5 days to 4 days. Cost changed, 5300+70=5370
41 days
Change act e.
8 days to 7 days. Cost changed, 5370+80=5450
a (5)
C (13
e (8
g (11
j (5
a (5)
C (13
e (8
g (11
j (4
a (5)
C (13
e (7
g (11
j (4
-
8/7/2019 Reducing project cost
7/7
At last, wechanged activity a and any othes path. To 40 days.
Changed a / 100
Changed 5450+100=5550
Days Direct cost In Direct cost Total cost
45 5200 3150 835044 5250 3080 833043 5300 3010 831042 5370 2940 831041 5450 2870 832040 5550 2800 8350
b (10
d (4
f (5 i (10
h (10
a (4
C (13 e (7 g (11
j (4