Reducing Owner Risk through Effective GMP Negotiations

Steve Zannoni, DirectorProject Management Consultants LLC

Page 2: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Reducing Owner, Architect, and Construction Manager Risk

through Effective GMP Negotiations

Steve Zannoni, DirectorProject Management Consultants LLC

Page 3: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Agenda

• What is a GMP?

• Why a GMP?

• What are the risks?

• What tools are available for reducing risks for

the Owner, Architect and Constructor?

3

Page 4: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

What is a Guaranteed Maximum Price (GMP)?

Page 5: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

What is a GMP?

• Constructor guarantees a not-to-exceed price

for the construction of a building project

• Show of hands: How many of you have participated in a project with a GMP?

‒ Liked it

‒ Hated it

‒ Unsure

5

Page 6: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Why a GMP?

• Reduce or eliminate bid risk

• Owner’s financing requirements

• Owner’s schedule

• Project complexity

6

Page 7: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

What are the Risks?

• Scope disputes

• Budget and wants are not in alignment

• Timing

• Added work and costs to both architect and

construction manager

• Cumbersome process that reaps no benefits

7

Page 8: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

GMP Process

• Should be a relatively easy process

• Many times it is difficult and time consuming

• Why?

– Team not communicating effectively

– Team has failed to honestly deal with

challenges early, especially budget issues

– One or more team members have

unreasonable expectations

8

Page 9: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Tools for reducing Risk

• Walking through the process

9

Page 10: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Construction Manageras Constructor

A/E OWNER

Trade Trade Trade

CM

Trade

•0

Page 11: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Construction Manageras Constructor

Advantages:

1. Pre-construction services

2. Guarantee of price (GMP)

•0

A/E OWNER

Trade Trade Trade

CM

Trade

Page 12: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Fee

General Conditions

Costs of the Work

Contingency

GMP

•0

Page 13: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Fee

General Conditions

Costs of the Work

ContingencyFinal Cost

Savings (Incentives)

•0

GMP

Page 14: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Fee

General Conditions

Costs of the Work

Contingency

Final Cost

Cost Overrun = CM Risk

•0

GMP

Page 15: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

15

Page 16: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Construction Manageras Constructor

Advantages:

1. Pre-construction services

2. Guarantee of price (GMP)

3. Accommodates partial fast track

4. Pre-qualification of bidders

Disadvantages:

1. GMP timing

•0

A/E OWNER

Trade Trade Trade

CM

Trade

Page 17: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

RISK

TIME

POR SD DD CD 75%CD 100%CD

Start Construction

Risk of ScopeDisputes

Cost of Modifications

MarketRisk

0GMPTimingRisk Curve

17

Page 18: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

GMP Timing

• What has been your experience with GMP timing?

– Earlier than 75% CD documents

– 100% CD documents

– After 100% bid has occurred

18

Page 19: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Construction Manageras Constructor

Advantages:

1. Pre-construction services

2. Guarantee of price (GMP)

3. Accommodates partial fast track

4. Pre-qualification of bidders

Disadvantages:

1. GMP timing

2. GMP contingency

•0

A/E OWNER

Trade Trade Trade

CM

Trade

Page 20: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

GMP Contingency

• Owner contingency

• Construction contingency

• Design contingency

• What has been your experience with project contingencies?

– Successful

– Unsuccessful

– Doesn’t matter

20

Page 21: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Construction Manageras Constructor

Advantages:

1. Pre-construction services

2. Guarantee of price (GMP)

3. Accommodates partial fast track

4. Pre-qualification of bidders

Disadvantages:

1. GMP timing

2. GMP contingency

3. Scope disputes

•0

A/E OWNER

Trade Trade Trade

CM

Trade

Page 22: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

The GMP Scope Dispute

• Owner seeks GMP at 75% complete

Construction Documents

• CM offers GMP with standard “Qualifications

and Assumptions”

• When final CDs are issued, CM legitimately

claims “new scope” and requests extras

• Owner and Architect claim scope is

“reasonably inferable” from GMP documents –

deny extras

• Disputes arise – potential cost overrun 22

Page 23: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

The GMP Scope Dispute

• What has been your experience with GMP scope disputes?

• What has been your experience in resolving GMP scope disputes?

23

Page 24: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

An Approach to Avoiding GMP Risks

• Facilitated GMP Approach

24

Page 25: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

What is the Facilitated GMP Process?

• Well defined GMP Documents

• “Narrative Design Intent Prose Statements”

delivered with GMP Documents

• Initial Q&A based on all documentation

• Facilitated GMP session

• Sign-Off on revised GMP Documents, Design

Intent Statement and Q&A Statement

•0

25

Page 26: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

• Bring together the

Owner, A/E, and

CM

• Facilitate

agreement on

intended structure

and content of the

set of documents

upon which GMP is

based. (“GMP Set”)

• Engage in a

normal cost review

and reconciliation

process up until

the date of

submission of the

GMP Set of

documents

• A/E delivers GMP

Set with the “Prose

Statement” that:

‒ Details all

incomplete

design elements

contained in the

GMP Set

‒ Explains A/E’s

statement of

intended scope

with respect to

incomplete

elements

‒ Identifies

“quality and

quantities” that

will appear in

the Construction

Documents

• CM submits

proposed GMP

including

qualifications and

assumptions based

on the GMP Set

Step 6Final GMP

• CM prepares the

final GMP

Amendment with

attachments for the

Owner’s approval

and signing

• Owner, A/E, CM

meet to reconcile

any

discrepancies or

disagreements

related to:

‒ GMP Set

‒ Allowances

‒ CM’s

qualifications

and

assumptions

• Structured and

facilitated

session

• Agreements

reached are

documented

• Qualifications

and assumptions

modified and

documented

Step 5A/E & CM

GMP

Reconciliation

Step 4CM

Proposed

GMP

Step 3A/E

Complete

GMP Set

Step 2Cost Review

&

Reconciliation

Step 1GMP “Set”

Agreement

Facilitated GMP Process

26

Page 27: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Facilitated GMP Process

• Bring together the Owner, A/E, and CM at the start of the project to organize the GMP Process

27

Page 28: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Organizational Meeting of the Project team at the start of the project.

Need to have a serious discussion about:

• Scope and timing of GMP(s) and the

development of a realistic project schedule

• Level of detail for the GMP Basis Documents

• Coordination of estimate protocol

• Estimates by A/E and CM should include all

the GMP elements. SD & DD estimates

should be a “dress-rehearsal for the GMP”

28

Page 29: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Organizational Meeting (cont’d)

• Solicitation of bids before execution of the

GMP Amendment

– What is an acceptable strategy?

– Are there early subcontact packages

executed prior to the GMP Amendment?

• Purpose/function of different contingencies:

– CM Contingency

– Owner Contingency

– “Risk Holds”?

• Shared Expectations!

Page 30: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Facilitated GMP Process

• Engage in a normal cost review and reconciliation process up until the date of submission of the GMP Set of documents

30

Page 31: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Cost Review and Reconciliation

• At each design phase, the estimate should be

a dress rehearsal of the GMP.

– Estimate formatted as GMP, including

contingencies, fees, general conditions, etc.

– Draft Assumptions and Clarifications

document is prepared

– Allowances are identified

– Alternates are identified

Page 32: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Facilitated GMP Process

• A/E delivers GMP Set with the “Design Intent Statement” that:‒ Details all incomplete

design elements contained in the GMP Set

‒ Explains A/E’s statement of intended scope with respect to the incomplete elements

‒ Identifies “quality and quantities” that will appear in Construction Documents.

32

Page 33: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

33

Page 34: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

34

Page 35: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Facilitated GMP Process

• CM submits proposed GMP including Qualifications and Assumptions based on the GMP Set

35

Page 36: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Proposed GMP

36

Page 37: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Assumptions and Clarifications

37

Page 38: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Facilitated GMP Process

• Owner, A/E, CM meet to reconcile any discrepancies or disagreements related to:‒ GMP Set‒ Allowances‒ CM’s Qualifications

and Assumptions• Structured and

facilitated session • Agreements reached

are documented• Qualifications and

assumptions modified and documented

38

Page 39: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

GMP Reconciliation Facilitated Meeting

• Owner, A/E and CM meet to

reconcile discrepancies and/or

disagreements related to the GMP

39

Page 40: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

GMP Reconciliation of:

• GMP Set and Design Intent Statement

• Cost of work and any required value

engineering

• Allowances

• CM’s Assumptions and Clarifications

• Schedule

• Alternates

40

Page 41: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Group Discussion

• From the six-step process presented, what are your thoughts?

• What did you like?

• What didn’t you like?

• What would you change?

41

Page 42: Reducing Owner Risk through Effective GMP Negotiations...GMP Set ‒ Explains A/E’s statement of intended scope with respect to incomplete elements ‒ Identifies “quality and

Closing Remarks

• Confirm and identify project’s GMP Budget

– Starts with accurate Budget

– Confirmed at start of project - be willing to

tell Owner the bad news

• Define scope/timing expectations for the

project’s GMP and have buy-in by all parties

• Identify realistic expectations

• A good GMP process only works if the team

members are informed and engaged!

42