red line maintenance facility presentation may 15-2013
DESCRIPTION
Red Line Maintenance Facility Presentation May 15-2013TRANSCRIPT
1
Operations and Maintenance F ilit (OMF)Facility (OMF)
Public Information Meeting
May 15, 2013
2
AgendaAgendaAgendaAgenda
Presentation (20 minutes)
Questions & Comments (30 minutes)
Next Steps – (5 minutes)p ( )
3
Why Are We Here?Why Are We Here?Why Are We Here?Why Are We Here?
Public Involvement is a key element of the Red
Line project. NEPA, Community Compact &
commitment of the MTA
SAACs requested more information on the OMF –q
a follow-up to April 12, 2012 public meeting
The Red Line designers now have preliminaryThe Red Line designers now have preliminary
engineering plans developed.
4
4
Key Milestone DatesKey Milestone DatesKey Milestone DatesKey Milestone Dates
Key Milestone DateKey Milestone Date
Receive Final Environmental Approval (ROD) February 2013
Begin Final Engineering Phase J l 2013Begin Final Engineering Phase July 2013
Full-Funding Federal Grant Agreement Signed June 2014
C H C t ti (D t T l ) A il 2015Commence Heavy Construction (Downtown Tunnels) April 2015
OMF Construction start January 2016
OMF Construction end August 2018
Complete Heavy Construction/Systems December 2020
5
Revenue Service March 2021
Red Line AlignmentRed Line AlignmentSouth of US 40 (Franklin Street) and east of
Franklintown Road North Ave. OMF
Red Line AlignmentRed Line Alignment
C l tR t W t B ltiCalvertonOMF
Rosemont Station
West Baltimore MARC
6
MTA North Avenue OMFMTA North Avenue OMFMTA North Avenue OMFMTA North Avenue OMF
7
Other ShopsOther ShopsOther ShopsOther Shops
Work on roof of LRVd i hi h
8
and cranes require high spaces
OMF Site LocationOMF Site LocationOMF Site LocationOMF Site LocationSouth of US 40 (Franklin Street) and east of
Franklintown Road Perkins SquareBaptist Church
OMFRosemont Station
West Baltimore MARC
9
Why Calverton Site Was Why Calverton Site Was Why Calverton Site Was Why Calverton Site Was ChosenChosen
Close to center of corridor
Works well from an operations standpointp p
Provides adequate space for required functions, i.e.
maintenance vehicle parking materials storage etcmaintenance vehicle parking, materials storage, etc.
Requires relocation of six (6) City DPW facilities and
h (3) b ithree (3) businesses
No residential acquisitions
10
Key Functions & FeaturesKey Functions & FeaturesKey Functions & FeaturesKey Functions & Features
Storage capacity for 34 light rail vehicles (LRV)
Shop capacity for 10 vehicles
Campus of maintenance and administration buildingsp g
Outdoor storage for track and rail systems materials
and equipmentand equipment
Employee reporting location
O it l kiOn-site employee parking
11
OMF Site PlanOMF Site PlanOMF Site PlanOMF Site PlanTraction Power
SubstationMaintenance and
Administration Building
LRV Storage
Franklintown Road
12Storage Building Facility Maintenance & Transportation Building
Franklintown Road Main Entrance
Daily Activities in OMFDaily Activities in OMFDaily Activities in OMFDaily Activities in OMF
Wash and clean the interiorWash and clean the interior
Some cars will receive scheduled inspections
S i iSome cars may receive repairs
16 two-LRV trains depart yard and return at least
once daily
13
Rail Vehicle MovementsRail Vehicle Movements
Trains Pulling out
Rail Vehicle MovementsRail Vehicle Movements
Trains Pulling out4:30 AM to 6:30 AM
Trains Pulling in9:30 PM to 1:15 AM
Street TrafficStreet TrafficStreet TrafficStreet Traffic
Flashers and Gates
Pedestrian Crossing
Only
15
Flashers and GatesFlashers and GatesFlashers and GatesFlashers and Gates
R t ti h tRepresentative photo
2 sets of flashers and
gates (one at each
track lead)
16
AppearanceAppearanceAppearanceAppearance
Aesthetics will be an important consideration for the
OMF
Landscaping provides screening for residencesp g p g
Set back 70’ from FranklinLow lighting polesLow lighting poles
Maximum distance
f t t i ti itfrom most train activity
17
Appearance:Appearance:Appearance:Appearance:Preliminary Rendering of SitePreliminary Rendering of Site
18View to Southwest
Streetscape & Urban DesignStreetscape & Urban DesignStreetscape & Urban DesignStreetscape & Urban Design
Franklin St View West19
Franklin St. - View West
Streetscape & Urban DesignStreetscape & Urban DesignStreetscape & Urban DesignStreetscape & Urban Design
Franklin St View East20
Franklin St. - View EastElements Being Considered
Neighborhood ScaleNeighborhood ScaleNeighborhood ScaleNeighborhood Scale
21
Franklin Street SectionEast End Looking West
Appearance: Appearance: Appearance: Appearance: Neighborhood ScaleNeighborhood Scale
Existing Building
22
Franklintown Street SectionLooking North
Elevation ViewsElevation ViewsElevation ViewsElevation Views
West Elevation
Elevation ViewsElevation ViewsElevation ViewsElevation Views
North ElevationNorth Elevation
North Elevation
Appearance:Appearance:Appearance:Appearance:Fences and LightingFences and Lighting
Low poles will be used
No high-mast poles, 50+ ft.
Low polepole, 30 ft
LEED SilverLEED SilverLEED SilverLEED Silver
Participation in the voluntary LEED process demonstrates leadership, innovation, environmental stewardship and social responsibility.
Lower operating costs and increase asset valueReduce waste sent to landfillsConserve energy and waterBe healthier and safer for occupantsReduce harmful greenhouse gas emissionsReduce harmful greenhouse gas emissionsQualify for tax rebates, zoning allowances and other incentives in hundreds of cities
26
Noise and VibrationNoise and Vibration
FTA T it N i d Vib ti I t A t
Noise and VibrationNoise and Vibration
FTA Transit Noise and Vibration Impact Assessment
(May 2006)
Evaluation CriteriaExisting or Baseline ConditionsF t C ditiFuture ConditionsTemporary Construction Activities
MitigationMitigationConstructionOperationsp
Sources of Noise Sources of Noise
LRT Operations
Sources of Noise Sources of Noise and and VibrationVibration
LRT OperationsPassbysWarning Horn at Grade CrossingsWarning Bells at StationsSwitches
Maintenance YardMechanical EquipmentWheel Squeal at CurvesWheel Squeal at Curves
Noise / Vibration Analysis Noise / Vibration Analysis
Operational Noise at Residences ( W Franklin Street)
Noise / Vibration Analysis Noise / Vibration Analysis at at OMFOMF
Operational Noise at Residences ( W. Franklin Street)Proposed LRT less than existing conditionsBoth current and future sound levels exceed FTA criteria
No Vibration Impacts at Residences are anticipated
Noise / Vibration Noise / Vibration AnalysisAnalysis
Mitigation Measures Under Consideration
Noise / Vibration Noise / Vibration AnalysisAnalysisat at OMFOMF
gUtilize approved control measures to eliminate gaps in traditional switchesTrack side low profile noise barrier/parapet (high enoughTrack-side low profile noise barrier/parapet, (high enough to shield track/wheel noise)MTA reviewing horn and bell policy and criteriaOther options being considered as project moves forward in Engineering
The Design Continues The Design Continues The Design Continues The Design Continues
Site Plan
Noise & Vibration Noise & Vibration
Lighting
Building Architecture
Landscapingp g
Traffic control
31
Maryland New Starts Projects Maryland New Starts Projects and Workforce Developmentand Workforce Developmentand Workforce Developmentand Workforce Development
Red Line and Purple Line Light Rail Projects
Maryland New Starts Maryland New Starts Maryland New Starts Maryland New Starts Workforce Development GoalsWorkforce Development Goals
Connect communities to employment opportunities in
Maryland New Starts projects
Ensure a diverse workforce
Foster employment and training programs
Expand opportunities for disadvantaged businessesp pp g
Connect disadvantaged businesses to opportunities with
the Maryland New Starts projects
33
the Maryland New Starts projects
Workforce Development Workforce Development Workforce Development Workforce Development OpportunitiesOpportunities
Maryland New Starts projects will yield approximately 7 000Maryland New Starts projects will yield approximately 7,000 construction jobso Purple Line-2,639
R d Li 4 223o Red Line-4,223MTA and DLLR have entered into a Memorandum of Understanding to better provide access to five construction trades needed for the New Starts projects:Heavy equipment operatorsElectriciansCement/Brick MasonsCarpenters Ironworkers
34
Ironworkers
Workforce Development Workforce Development Workforce Development Workforce Development OpportunitiesOpportunities
The Red Line Operations and Maintenance Facility will employ approximately 300 staff members in the following seven categories:g
Track maintenanceTransit electrical power These are permanent
MTA Staff positions andCatenary maintenanceTransportation operationsMaterials management
MTA Staff positions and are not included in the 7,000 construction
iti !Materials managementFacilities MaintenanceRail Car Maintenance
positions!
35
Rail Car Maintenance
Workforce Development Workforce Development Workforce Development Workforce Development OpportunitiesOpportunities
How to prepare for future employmentIndividuals should register with the Maryland Department of Labor Licensing and Regulationof Labor, Licensing and RegulationConnect with local workforce development programs/Local Union ChaptersStay connected with the Baltimore Red Line/Purple Line projects
http://www.baltimoreredline.com/workforce-development
36
Public Outreach InitiativesPublic Outreach InitiativesPublic Outreach InitiativesPublic Outreach InitiativesContinuous Public Meetings and Informational Sessions
C it M ti Ci i G d C it E tCommunity Meetings, Civic Groups, and Community Events
Station Area Advisory Committees
Community Resource Hubs
Newsletters and Mailingsg
Website – www.baltimoreredline.com
Facebook:Facebook:
https://www.facebook.com/baltimoreredlineliaisons
37
Community Liaisons
Next StepsNext StepsNext StepsNext Steps
Designers will continue to refine designs.Design will continue through 2013 - 2015The Red Line team will come back to the community asThe Red Line team will come back to the community as the design progresses.
38
Thank you for coming!Thank you for coming!
Questions?
39
40