record of decision amendment #5 for operable unit 2 … · twin cities army ammunition plant office...
TRANSCRIPT
RECORD OF DECISION AMENDMENT #5
FOR
OPERABLE UNIT 2 (OU2)
NEW BRIGHTON/ARDEN HILLS SUPERFUND SITE
March 2014
FINAL
Table of Contents
TABLE OF CONTENTS .............................................................................................................. i
ACRONYMS ................................................................................................................................ iii
1.0 INTRODUCTION .......................................................................................................... 1-1
1.1 Proposed Changes in the Remedy .......................................................................... 1-1 1.2 Procedure for Changing the Remedy ...................................................................... 1-2 1.3 Public Comment Period .......................................................................................... 1-3
2.0 BACKGROUND ............................................................................................................ 2-1
2.1 Site History ............................................................................................................. 2-1 2.1.1 Site A .......................................................................................................... 2-2 2.1.2 13 5 Primerffracer Area .............................................................................. 2-2 2.1.3 EBS Areas ................................................................................................... 2-3
2.2 Engineering Evaluation/Cost Analysis and Additional Investigation .................... 2-4 2.3 Removal Action Implementation ............................................................................ 2-7
3.0 BASIS FOR THE FUNDAMENTAL CHANGE TO THE SELECTED REMEDY3-1
4.0 DESCRIPTION OF REMEDY CHANGES ................................................................ 4-1
5.0 EVALUATION OF ALTERNATIVES ....................................................................... 5-1
6.0 STATUTORY DETERMINATIONS .......................................................................... 6-1
6.1 Protection of Human Health and the Environment.. ............................................... 6-1 6.2 Compliance with ARARs ....................................................................................... 6-1 6.3 Cost Effectiveness ................................................................................................... 6-1 6.4 Utilization of Permanent Solutions and Alternative Treatment Teclmologies or
Resource Recovery Technologies to the Maximum Extent Practicable ................. 6-2 6.5 Preference for Treatment as a Principal Element .................................................... 6-2 6.6 Five-Year Review Requirements ............................................................................ 6-2
1
T·\1561 TCAAP\OU2\2014 ROD Amendment\Text\OU2 ROD Amend #S_FinaLdoc
Table of Contents (Cont.)
FIGURES
I Site Map
APPENDICES
A Responsiveness Summary B Applicable or Relevant and Appropriate Requirements C References
11
T:\1561 TCAAP\OU2\2014 ROD Amendmcnt\Text\OU2 ROD Amend #5_FinaLdoc
AOC
ARAR
Army
BAP
CERCLA
coc cPAHs
EBS
EE/CA
ESD
FFA
LUC
LUCRD
mg/kg
MNARNG
MPCA
NB/AH
NCP
NPL ou PAHs
PTA
RAO
Rl/FS
ROD
RRG
SLV
SRV
TCAAP
TCLP
Acronyms
Area of Concern
Applicable or Relevant and Appropriate Requirements
U.S. Army
Benzo(a)Pyrene
Comprehensive Environmental Response, Compensation, and Liability Act
Chemical of Concern
Carcinogenic Polycyclic Aromatic Hydrocarbons
Environmental Baseline Survey
Engineering Evaluation/Cost Analysis
Explanation of Significant Difference
Federal Facility Agreement
Land Use Control
Land Use Control Remedial Design
Milligrams per Kilogram
Minnesota Army National Guard
Minnesota Pollution Control Agency
New Brighton/ Arden Hills
National Oil and Hazardous Substances Pollution Contingency Plan
National Priorities List
Operable Unit
Polycyclic Aromatic Hydrocarbons
Primer/Tracer Area
Removal Action Objective
Remedial Investigation/Feasibility Study
Record of Decision
Recommended Remediation Goal
Soil Leaching Value
Soil Reference Value
Twin Cities Army Ammunition Plant
Toxicity Characteristic Leaching Procedure
ll1
T:\156\ TCAAP\OU2\2014 ROD Amendment\Text\OU2ROD Amend #5_Final.doc
USEPA
voc Wenck
Acronyms (Cont.)
U.S. Environmental Protection Agency
Volatile Organic Compound
Wenck Associates, Inc.
lV
T:\1561 TCAAP\002\2014 ROD Amendment\Text\OU2 ROD Amend #S_Final.do~
1.0 Introduction
1.1 PROPOSED CHANGES IN THE REMEDY
This decision document amends the Record of Decision (ROD) for Operable Unit 2 (OU2) of the
New Brighton! Arden Hills Superfund Site (NB/ AH site). The Site, which includes the Twin
Cities Army Ammunition Plant (TCAAP), is located in Arden Hills, Minnesota. OU2 consists of
affected soil, sediment, surface water, and groundwater within the boundaries of the TCAAP
facility that were impacted by waste materials such as volatile organic compounds (VOCs),
heavy metals, and explosives as a result of site operations and/or waste management and disposal
activities that occuned in the period from 1941 to 1981. Figure 1 shows the location of TCAAP
and its boundary in 1983 (i.e., the OU2 boundary) and the location of the soil areas of concern
that are addressed in this ROD amendment, which is ROD Amendment #5 for the OU2 ROD.
The OU2 ROD was issued in 1997. ROD Amendment #1 for Site C-2 (a portion of Site C) was
finalized in 2007. ROD Amendments #2 and #3, along with Explanation of Significant
Difference (ESD) #1 and #2, were all finalized in 2009 and documented final remedies at various
soil and dun1p sites and also addressed land use controls (LUCs) at various soil, groundwater,
and dump sites. ROD Amendment #4 was finalized in 2012 and documented final remedies at
various aquatic sites, two soil sites, and Building 102 shallow groundwater. OU2 is one of three
Operable Units cunently established for the NB/ AH site. OUl addresses the North Plume of
groundwater contamination located off-TCAAP and OU3 addresses the South Plume of
groundwater contamination off-TCAAP.
Under the authority of the Comprehensive Enviromnental Response, Compensation, and
Liability Act of 1980, as amended (CERCLA), 42 U.S. C. §9601, et seq. and Executive Order
12580, the United States Army (Army) is the lead agency for response actions at the Superfund
Site. All remedial actions are subject to the provisions of the Federal Facility Agreement (1987)
1-1
T:\1561 TCAAP\OU2\2014 ROD Amendment\Text\OU2 ROD Amend #S_FinaLdoc
among the Army, the U.S. Environmental Protection Agency (USEPA), and the Minnesota
Pollution Control Agency (MPCA).
ROD Amendment #5 addresses soil areas of concern (AOCs) where a removal action has been
completed (Site A, 135 Primer/Tracer Area (PTA), and Environmental Baseline Survey (EBS)
Areas), and industrial use cleanup levels were met. Since the removal action has already been
implemented, Amendment #5 documents that the completed Removal Action constitutes the
final remedy for these soil areas of concern and that the only additional remedial action required
is implementation of a LUC. Hence, the selected remedy for the soil AOCs is No Further Action
with Land Use Controls, which includes a LUC to restrict property uses to those that are
compatible with the exposure assumptions used to derive the cleanup levels.
1.2 PROCEDURE FOR CHANGING THE REMEDY
Under Section 117 of CERCLA and Section 300.435( c )(2)(ii) of the National Oil and Hazardous
Substances Pollution Contingency Plan (NCP), if a new, proposed remedial action fundamentally
differs from a final ROD with respect to scope, perfonnance, or cost, the lead agency is required
to prepare an amendment to the ROD describing the changes that are to be made, stating the
reasons such changes are being made, and providing assurances that the proposed remedy
satisfies the statutory requirements. The decision to change the remedy for OU2 constitutes a
fundamental change in the OU2 remedy, necessitating the issuance of a new Proposed Plan and
an amended OU2 ROD.
This OU2 ROD amendment and all supporting documents will become part of the NB/AH site
Administrative Record file in accordance with Section 300.825(a)(2) of the NCP. The
Administrative Record is available during business hours and is located at:
Twin Cities Army Ammunition Plant Office 470 West Highway 96, Suite 100
Shoreview, MN 55126
1-2 T:llS61 TCAAP\OU2\2014 ROD Amendment\Text\OU2 ROD Amend #S_FinaLdoc
1.3 PUBLIC COMMENT PERIOD
In accordance with Section 300.435(c)(2)(i) of the NCP, the Army prepared a Proposed Plan and
facilitated a newspaper notice of the proposed OU2 ROD modification in January 2014. This
notice identified a 30-day public comment period that ended on February 10, 2014, and also
included an offer to hold a public meeting, if requested. No public meeting was requested and
no written comments were received during the comment period. The Responsiveness Summary
is included as Appendix A.
1-3 T:\1561 TCAAP\OU2\2014 ROD Amendment\Text\OU2 ROD Amend #S_Final.doc
2.0 Background
2.1 SITE HISTORY
The NB/ AH site consists of a 25-square mile area located in Ramsey County, Minnesota. It
includes the approximately 4-square mile area of the original TCAAP facility and portions of
seven nearby communities: New Brighton, Arden Hills, St. Anthony, Shoreview, Mounds View,
Columbia Heights, and Minneapolis.
TCAAP was constructed in 1941 to produce small-caliber ammunition for the United States
military. Production activities included manufactming small mms ammunition and related
materials, proof-testing small arms ammunition and related items as required, and handling and
storing strategic and critical materials for other government agencies. Ammunition production
and related activities have occmred periodically, commensmate with operations in wars,
conflicts, and other national emergencies, and ceased in 2005.
In 1983, the site was put on the National Priorities List (NPL) because USEPA and MPCA
determined that hazardous substances from TCAAP had been released into the enviromnent.
The NB/ AH site was divided into three operable units, as discussed in Section 1.1. Figme 1
shows the location ofTCAAP and its boundary in 1983 (i.e., the OU2 boundary) and the location
of the soil AOCs that are addressed in this ROD amendment.
Background infonnation for each of the individual sites is presented in the remainder of this
section.
2-1 T:\1561 TCAAP\OU2\2014 ROD Amendment\Text\OU2 ROD Amend #5_Final.doc
2.1.1 Site A
The area designated as Site A was reportedly used from the early 1940s to 1966 for burial and/or
burning of various wastes, such as sewage sludge, solvents, explosive-containing wastes, and
mercury crack cases, which resulted in contamination of soil and groundwater. The 1997 OU2
ROD selected excavation, stabilization, and off-site disposal for remediation of metals
contaminated soil at Site A and, in 1998 and 1999, approximately 16,300 cubic yards of ~·,.
contaminated soil and debris were removed to achieve the cleanup levels. Refer to the "Final
Remedial Action Completion and Shallow Soils Close Out Report, Site A Activities", Stone &
Webster, December 2001. Years after completion of this remedial action work at Site A,
Minnesota Army National Guard (MNARNG) personnel observed an area that had no vegetation
located near the edge of one of the previously-excavated areas. Initial field sampling activities
were completed by the MNARNG in 2009, which confirmed the presence of metals
contaminated soil at two soil AOCs. The two AOCs were located near the edge of a previously
excavated area, suggesting that the previous area of excavation had needed to be slightly larger
in these two areas. The AOCs were concluded to be associated with the metals-contaminated
area that was addressed in 1998/1999 remediation work, where the chemicals of concem (COCs)
established in the OU2 ROD were antimony, barium, copper, and lead. The source of the metals
contamination appears to be the same as for the metals-contaminated areas of Site A that were
remediated in 1998/1999, i.e., TCAAP industrial operations.
2.1.2 135 Primer/Tracer Area
The 13 5 PTA was utilized for raw material storage and all aspects of manufacturing for primer
production and tracer mixing for use in TCAAP small caliber annnunition production. A
Preliminary Assessment of the 135 PTA was completed in November 2001, which recommended
that a Site Inspection be conducted. A Site Inspection Work Plan was completed in May 2002.
Initial field sampling activities were completed in 2002, which confirmed the presence of
contamination at two AOCs, designated AOC #l and AOC #2. As docmnented in the
engineering evaluation I cost analysis (EE/CA) for the soil AOCs, soil contamination was
2-2
T:\1561 TCAAP\OUl\2014 ROD Amendment\Text\OU2 ROD Amend #5_Final.doc
determined to be limited to Polycyclic Aromatic Hydrocarbons (PAHs), and no further
groundwater investigation was determined to be necessary.
The source of P AH contamination is not known. Historical documents did not identify any
industrial processes at the 135 PTA that would have been a potential source ofPAH
contamination at the site. At AOC #1, the source is most likely related to some type of
constmction material (e.g., asphaltic roofing compounds, disintegrated asphalt, etc.). At
AOC #2, the source of the P AH contamination is also unknown; however, in addition to possibly
being related to some type of construction material, it could also be related to building
demolition that was accomplished by burning the building.
2.1.3 EBS Areas
Between 1996 and 2005, EBS work was conducted by the MNARNG in anticipation of the
transfer offederal property control from TCAAP to the National Guard Bureau. Initial field
sampling activities conducted by the MNARNG during this work identified two soil areas of
concern having metals contamination. One area (AOC #1) was part of an open storage area that
had been selected for investigation based on review of aerial photographs fi·om the
Environmental Photographic Interpretation Center (EPIC) report. Photographs from 1945
through 1972 noted storage (or possible storage) of such items as debris piles, lumber, coal, and
drums. The second area (AOC #2) was a possible burning area located on a concrete
pad/loading dock. Initial sampling activities completed in 1999 indicated the two soil AOCs
were contaminated with metals/mercury. As documented in the EE/CA, no groundwater
investigation was determined to be necessary. Sampling conducted in support of the EE/CA
determined that carcinogenic PAHs (cPAHs) were also a COC at AOC #1.
The source ofmetals/PAH contamination at AOC #1 and the metals contamination at AOC #2 is
not known with certainty. AOC #I was noted as being within an open storage area evidenced in
historical aerial photographs; however, field observations detern1ined that contamination at
AOC #1 resulted from an area of shallow fill that was placed along the railroad tracks. Soils
2-3
T:\1561 TCAAP\OU2\2014 ROD i\mendment\Text\OU2 ROD Amend #S_FinaLdoc
were noted to contain scrap metal and relatively small pieces of asphalt/concrete (corresponding
to approximately the upper 2 feet of soil). At AOC #2, the somce of the metals contamination is
unknown. A 1944 steam layout plan had labeled the concrete pad on the north edge of AOC #2
with "Bmning Kettles" and had shown two small structmes. Also, the south end of the concrete
pad is an elevated loading dock. Since AOC #2 is located at this end of the concrete pad, the
contamination may have resulted from spillage dming truck loading/unloading, possibly then
being tracked/spread through the immediate vicinity due to vehicle traffic. The highest lead
results were located immediately off the southwest comer of the pad, potentially supporting the
idea ofloading dock spillage. Also, some small caliber munitions components (casings and
projectiles, but no live rounds) were noticed within the area of soil contamination, possibly
contributing to the metals contamination. Here again, the stray components suggested general
spillage issues associated with the loading dock operations.
2.2 ENGINEERING EVALUATION/COST ANALYSIS AND ADDITIONAL
INVESTIGATION
To support preparation of the EE/CA, sampling was conducted by Wenck from March 2012
through June 2012 to define the extent and magnitude of contamination at the soil AOCs (results
were documented in the EE/CA). After the EE/CA investigation sampling was completed, and
during the time that EE/CA review/revision was occurring, the Army elected to collect additional
perimeter samples at the two EBS AOCs. Delineation of the perimeter of these two AOCs had
been considered adequate for purposes of preparing the EE/CA, but included minor gaps around
the perimeters. Hence, the EBS AOC perimeters were better defined with this additional
sampling, conducted by Wenck in September- November 2012. Results were documented in the
Removal Action Work Plan. The depths of soil contamination in the soil AOCs were generally
limited to the uppermost 1 to 2 feet of soil.
2-4 T:\1561 TCAAP\OU2\2014 ROD Amendment\Tc;oj;\QU2 ROD Amend #S_Final.doc
The cleanup levels established for each soil AOC are documented in the EE/CA, and are listed
below for reference (all values are mg/kg):
Site A: Antimony 33.6
Barium 21,745
Copper 19,593
Lead 1,200
135 PTAAOC#1: cPAHs 3
Naphthalene 7.5
135 PTA AOC #2: cPAHs 3
EBS AOC #1: Lead 700
Mercury 1.5
cPAHs 3
EBS AOC #2: Antimony
Copper
Lead
Mercury
100
9,000
700
1.5
Note that cleanup levels for cPAHs are based on the MPCA's benzo(a)pyrene (BAP) equivalent
methodology. For Site A, given that the areas of concern were immediately adjacent to the prior
Site A remediation area conducted in 1998/1999, the same cleanup levels as established for the
1998/1999 work were selected for the Site A AOCs. These cleanup levels were based on a
TCAAP site-specific industrial exposure scenario. For the areas of concern at the 135 PTA and
EBS Areas, the cleanup levels were based on MPCA Industrial Soil Reference Values (SRVs),
which are risk-based human health criteria for exposure to contaminated soil under an industrial
scenario. For the 135 PTA, if the MPCA Tier 1 Soil Leaching Value (SLY) for a given
2-5 T:\1561 TCAAPIOU2\2014 ROD Amendmcnt\Text\OU2 ROD Amend #5_Final doc
contaminant of concern was lower than the Industrial SRV, then the SLV was used. SLVs are
based on the exposure pathway of contaminants leaching to groundwater. Groundwater is
shallow in the 13 5 PTA, and typically ranges from several feet in the western portion to at or
near the surface in the northeast portion. Hence, SLVs are applicable to the 135 PTA. SLVs
were not deemed appropriate at the EBS areas, given the presence of Unit 2 (confining layer) at
the ground surface and given the large depth to Unit 3 groundwater (approximately I 00 feet).
The EE/CA evaluated removal action alternatives for the soil AOCs. The document included the
following:
I. Summary of remedial investigations;
2. Identification of chemicals of concem (COCs);
3. Identification of removal action objectives, chemical specific applicable or relevant and
appropriate requirements (ARARs), and Recommended Remediation Goals (RRGs);
4. Description of the nature and extent of contamination in soil; and
5. Identification and evaluation of removal action alternatives that included:
a) Alternative I: No Action (Except Land Use Controls);
b) Alternative 2: Soil Cover; and
c) Alternative 3: Excavation and Offsite Disposal.
The no action altemative was included to provide a baseline alternative for comparison to other
action-oriented alternatives. These three potential alternatives were compared against each other
on the basis of effectiveness, implementability, and cost. The EE/CA recommended the
Excavation and Offsite Disposal alternative for remediation of the soil AOCs. This alternative
was noted to protect human health and the environment, meet ARARs, and accomplish the
removal action objectives (RAOs). The No Action alternative was not deemed acceptable
because it would not reliably protect human health. Excavation and Offsite Disposal was
selected over the Soil Cover alternative because, at comparable (though somewhat higher) cost,
the Excavation and Offsite Disposal alternative would not conflict with any potential future
property redevelopment of these areas (whereas the Soil Cover alternative clearly would), as
2-6 T:\1561 TCAAP\OU2\2014 ROD Amendment\Text\OU2 ROD Amend #S_Final doc
long as that future development is consistent with the established LUC. It was also selected
because the contamination would not remain on the property, avoiding long-term soil cover
management.
The EE/CA received consistency approval by the USEPA and MPCA on November 1, 2012.
The Army published legal notices in newspapers regarding the availability of the EE/CA for
public comment and established a 30-day public comment period beginning on November 7,
2012. No comments were received. The Army selected the EE/CA-recommended remedy in an
Action Memorandum signed on December 18,2012.
2.3 REMOVAL ACTION IMPLEMENTATION
The Removal Action was completed in May-June 2013. All of the contaminated soils removed
from the AOCs were disposed of in the SKB Rosemount Industrial Waste Facility, Rosemount,
Minnesota. The total weight of contaminated soils was 1846 tons (or approximately 1230 cubic
yards, based on an estimated unit weight of 1.5 tons per cubic yard). A portion ofthese soils
(711 tons) were stabilized prior to transport to the landfill. The excavation areas were backfilled
to the approximate pre-excavation grades. The backfill material that was utilized was
commercially-available, clean common backfill and topsoil fi'om off-TCAAP sources. The
common backfill was placed and compacted to a level approximately 6 inches below the final
grade. Topsoil was then placed in the uppermost 6 inches, and then seeded to re-establish grass.
The Removal Action Completion Report documenting this work was approved by the USEP A
and MPCA on November 15,2013.
2-7 T:\1 561 TCAAPIOU2\2014 ROD Amendment\Text\OU2 ROD Amend #5_FinaLdoc
3.0 Basis for the Fundamental Change to the Selected Remedy
The soil AOCs (Site A, 135 PTA, and EBS Areas) were not included in the OU2 ROD. A soil
removal action (Excavation and Offsite Disposal) was completed in May-June 2013, as
described in Section 2.3, which removed contaminated soils that exceeded industrial use cleanup
levels. Since the soil removal action has already been implemented, ROD Amendment #5
documents that the completed Removal Action constitutes the final remedy for these soil areas of
concern and that the only additional remedial action required is implementation of a LUC (which
technically is already in place given the "blanket" LUC described in the OU2 LUCRD). Since
cleanup levels were based on an industrial use scenario, a land use control is needed to restrict
property uses to those that are compatible with the exposure assumptions used to derive the
cleanup levels.
3-l T:\1561 TCAAP\OU2\2014 ROD Amendment\Text\OU2 ROD Amend #5]inal.doc
4.0 Description of Remedy Changes
The soil AOCs (Site A, 135 PTA, and EBS Areas) were not included in the OU2 ROD. The
selected remedy for the soil AOCs is No Further Action with Land Use Controls, since soil
excavation and offsite disposal was previously completed in May-June 2013, as described in
Section 2.3. The LUC is:
• Restrict property use in these areas to uses that are compatible with industrial use (e.g.,
residential development would not be allowed). Technically, this LUC is already in place
given the "blanket" LUC described in the OU2 Land Use Control Remedial Design
(LUCRD).
Given that the cleanup levels were based on an industrial use scenario, the contamination levels
existing at this site will not allow for unlimited use and unrestricted exposure to soils. Hence,
CERCLA Section 121 (c) 5-year reviews and a LUC are part of the remedy for this site.
Although the "blanket" LUC already encompasses the areas of OU2 in which the soil AOCs are
located, a specific description of the soil AOCs and the LUC requirement established for this site
will also be documented in the next revision of the OU2 LUCRD.
4-1
T.\156! TCAAP\OU2\2014 ROD Amendment\Texl\OU2 ROD Amend #S_Final.doc
5.0 Evaluation of Alternatives
The soil AOCs were not included in the OU2 ROD. The "original selected remedy" was
selected in the December 2012 Action Memorandum, as discussed in Section 2.2. However, the
identified remedy had only noted the possibility that a LUC might be required if, after soil
removal was completed, soils remained onsite that exceeded the MPCA residential SRV (i.e.,
remaining soils were below the industrial cleanup levels but exceeded the MPCA Residential
SRVs). With the soil removal work now completed, it is known that some of the remaining soils
do in fact exceed the MPCA residential SRVs, and thus will require the additional remedy
component of a LUC. Hence, the evaluation of alternatives presented in this section is a
comparison of the original selected soil AOC remedy (i.e., without a definite LUC component)
against the amended remedy (No Further Action with Land Use Controls). These two
alternatives will be discussed with respect to the nine criteria specified in the CERCLA Rl/FS
guidance document (USEPA, 1988). Evaluation is based on information presented in the
Proposed Plan and the EE/CA.
I. Overall Protection of Human Health and the Environment
The soil removal action implemented alone (without a LUC) would not reliably protect
human health and the environment. Since there are soils that are above Residential SRVs
(but below industrial cleanup levels) remaining onsite, a LUC is necessary to restrict
property use in these areas to uses that are compatible with the exposure assumptions
used to derive the cleanup levels, which precludes certain property uses (e.g., residential).
The amended remedy includes this LUC.
2. Compliance with Applicable or Relevant and Appropriate Requirements (ARARs)
The soil removal action implemented alone (without a LUC) would not meet ARARs.
One ARAR exists, MN Statute§ 115B.l6 (Appendix B), and it pertains to the LUC. This
ARAR requires that, for prope1ty contaminated by release of a hazardous substance, the
5-l T:\1.561 TCAAP\OU2120!4 ROD AmendmenLIText\OU2 ROD Amend #5_Final doc
property owner record (with the county recorder of the county in which the property is
located) an affidavit notifYing any potential transferee that the land was contaminated by
a release of a hazardous substance, a description of the contamination, and the nature of
property use restrictions. The amended remedy will comply with the substantive portion
of this ARAR.
3. Long-Term Effectiveness and Permanence
The soil removal action implemented alone (without a LUC) would have poor long-term
effectiveness since human health would not be reliably protected. The amended remedy
is considered to have good long-term effectiveness, given its incorporation into the OU2
LUCRD.
4. Reduction of Toxicity, Mobility, or Volume Through Treatment
The two alternatives are considered equal, given that the field work for the soil removal
action has been completed and thus no further reduction of toxicity, mobility, or volume
through treatment will occur with either alternative.
5. Short-Term Effectiveness
The two alternatives are considered equal, given that the field work for the soil removal
action has been completed and thus no short-term risk to site workers, the community,
and the environment will occur with either altemative.
6. lmplementability
The soil removal action implemented alone (without a LUC) would be slightly more
implementable, given that there would be no administrative effort being expended to
maintain the LUC. However, the additional effort to implement the LUC included in the
amended remedy is minimal, given that the same type of LUCs are being implemented at
other TCAAP sites already, and given that the OU2 LUCRD is already approved and
being implemented.
5-2
T\1561 TCAAP\OU2U0!4 ROD Amendment\Text\OU2 ROD Amend #S_FinaLdoc
7. Cost
The only difference in cost between the two alternatives is the additional cost of the
administrative effort to maintain the LUC associated with the amended remedy.
However, as noted above, the additional effort to implement the LUC included in the
amended remedy is minimal, given that the same type ofLUCs are being implemented at
other TCAAP sites already, and given that the OU2 LUCRD is already approved and
being implemented. This additional cost is therefore considered negligible.
8. State Acceptance
The State, with its approval of the Removal Action Completion Report on November 15,
2013, has indicated its acceptance of the amended remedy.
9. Community Acceptance
An invitation for public comment on the EE/CA and its recommended alternative
(Excavation and Offsite Disposal) was published in November 2012, which established a
30-day public comment period beginning on November 7, 2012. No comments were
received. Also, for this proposed ROD modification, the Army prepared a Proposed Plan
and facilitated a newspaper notice (which included identification of the prefened remedy
for the soil AOCs) in January 2014. This notice established a 30-day public comment
period that ended on February 10, 2014, and also included an offer to hold a public
meeting, if requested. No public meeting was requested and no written comments were
received during the comment period. With no comments received, it is concluded that
the community accepts the amended remedy (No Further Action with Land Use
Controls).
Based on the alternatives evaluation, the selected alternative for the soil AOCs (Site A, 135 PTA,
and EBS Areas) is No Further Action with Land Use Controls. This alternative protects
human health and the environment, meets ARARs, and accomplishes the RAOs. The soil
removal action implemented alone (without a LUC) was not deemed acceptable because it would
not reliably protect human health aJ1d the environment.
5-3 T:\1561 TCAAP\OU2\2014 ROD Amendment\Te:<t\OU2 ROD Amend #5_FinaLdoc
6.0 Statutory Determinations
This section discusses how the remedy for the soil AOCs (Site A, 135 PTA, and EBS Areas)
meets the five statutory requirements established by Section 121 of CERCLA.
6.1 PROTECTION OF HUMAN HEALTH AND THE ENVIRONMENT
The amended remedy protects human health by including a LUC to restrict property use in tbese
areas to uses that are compatible with the exposure assumptions used to derive the cleanup levels
(e.g., industrial use), which precludes certain property uses tbat would not be adequately
protected (e.g., residential).
6.2 COMPLIANCE WITH ARARS
The amended remedy complies with ARARs, which are identified in Appendix B.
6.3 COST EFFECTIVENESS
The amended remedy is a cost-effective method for addressing the shallow soil contamination at
the soil AOCs, i.e., the soils having contamination levels that are between the MPCA Residential
SRV s and the industrial cleanup levels.
6-1 T:\1561 TCAAPIOU2\2014 ROD Amendment\Tcxt\OU2 ROD Amend #5_Final.doc
6.4 UTILIZATION OF PERMANENT SOLUTIONS AND ALTERNATIVE
TREATMENT TECHNOLOGIES OR RESOURCE RECOVERY
TECHNOLOGIES TO THE MAXIMUM EXTENT PRACTICABLE
The amended remedy was selected, in part, due to its permanent nature. The remedy removed
contamination exceeding the selected industrial cleanup levels for each AOC and does not
conflict with any potential future property redevelopment of these areas, as long as that future
development is consistent with the established LUC.
6.5 PREFERENCE FOR TREATMENT ASAPRINCIPALELEMENT
The original selected remedy (the soil removal action) included treatment of some of the
contaminated soils (i.e., use of a stabilizing agent for metals); however, the treatment component
is not applicable to the amended remedy, since the field work has already been completed.
6.6 FIVE-YEAR REVIEW REQUIREMENTS
For the soil AOCs (Site A, 135 PTA, and EBS Areas), because the remedy will result in
hazardous substances, pollutants, or contaminants remaining onsite above levels that allow for
unlimited use and unrestricted exposure, CERCLA Section 121(c) 5-year reviews will be
required for this site.
6-2 T:\1561 TCAAP\OU2\2014 ROD Amendment\Te:>.1\0U2 ROD Amend #S_Fina!.doc
Chief, Operational Army and Medical Branch Base Realigmnent & Closure Division
Richard C. Karl Director, Superfund Division U.S. Enviromnental Protection Agency, Region 5
Kathryn Sather Director, Remediation Division Minnesota Pollution Control Agency
T:\1561 TCAAP\OU2\20!4 ROD Amendment\Text\OU2 ROD Amend #S_FinaLdDc
6-3
Date
Date
t~ 3, c::roJ'/ Date
Figures
Notes: 1. AOC =Area of Concern 2. "BAP" means MPCA's BAP Equivalent methodology 3. 2012Aerial Photograph (Source: ESRI)
2,000 1,000 0 -- 2,000
Feet ---N
A OU2 ROD AMENDMENT #5
Site Map
______..
Operable Unit 2 of the New Brighton/ Arden Hills Superfund Site (the same
Cl area occupied by The Twin Cities Army Ammunition Plant in 1983, when the Site was placed on the NPL.)
• Soil Boring Locations (original samples that indicated contamination , which was excavated in the Removal Act ion)
General location of site (see note below)
(Note: The site boundaries are only intended to illustrate the general locations and should not be interpreted as representing areas of contamination.)
Wenck MAR 2014 Engineers · Scientists 1800 Pioneer Creek Center Business Professionals Maple Plain, MN 55359-0429 www.wenck.com 1-800-472-2232
Figure 1
Appendix A
Responsiveness Summary
Responsiveness Summary
The Army prepared a Proposed Plan and facilitated a newspaper notice of the proposed OU2 ROD modification in January 2014. This notice identified a 30-day public comment period that ended on February I 0, 2014, and also included an offer to hold a public meeting, if requested. No public meeting was requested and no comments were received during the comment period.
AppendixB
Applicable or Relevant and Appropriate Requirements
Summary of ARARs for Soil AOCs (Site A, 135 PTA, EBS Areas)
ARAR ARAR Regulating Typel'l Agency
Rule Selected Remedy: No Further Action with Land Use Controls
Land Use Controls Action MPCA MN Statute§ 1158.16 ARAR, since land use controls are required for limiting land uses to those that are compatible
with industrial use. (applicable)
Notes:
1) ARAR Types: Action = Action-Specific Chemical ::::: Chemical-Specific Location :;:;: Location-Specific
T:\1561 TCAAPIOU2\2014 ROD Amendment\l>.ppendices\App B_ARARs
Appendix C
References
References
Alliant Techsystems, Inc., December 2001. Final Preliminary Assessment, 135 Primer/Tracer Area.
Alliant Techsystems, Inc., March 2002. Site Inspection Work Plan, Field Sampling Plan, Site Specific Health and Safety Plan, 135 Primer/Tracer Area.
EnecoTech Midwest, Inc., January 2005. Summary Report for 135 Primer/Tracer Area Site Inspection Investigation. (Revised by Tecumseh/Wenck Installation Support Services and Alliant Techsystems, Inc.)
Federal Facility Agreement. August 12, 1997.
Minnesota Pollution Control Agency, May 1998. Draft Guidelines: Risk-Based Guidance for the Soil Leaching Pathway, Users Guide.
Minnesota Pollution Control Agency, September 1998. Draft Guidelines: Risk-Based Site Characterization and Sampling Guidance.
Minnesota Pollution Control Agency, January 1999. Draft Guidelines: Risk-Based Guidance for the Soil- Human Health Pathway, Volume 2, Technical Support Document.
Mi1mesota Pollution Control Agency, June 2011. Remediation Division Policy on Analysis of Carcinogenic Polynuclear Aromatic Hydrocarbons (cP AH).
Montgomery Watson, March 1997. Operable Unit 2 Feasibility Study.
Montgomery Watson, December 1999. Final Training Area F Addendum, Phase II Environmental Baseline Survey.
Stone & Webster, Inc., December 2001. Final Remedial Action Completion and Shallow Soils Close Out Report, Site A Activities.
Twin Cities Army Ammunition Plant, New Brighton/Arden Hills Superfund Site, Operable Unit 2, Record of Decision. 1997.
U.S. Army, December 2012. Action Memorandum- Non-Time Critical Removal Action for Soil Areas of Concern (Site A, 135 Primer/Tracer Area, EBS Areas), New Brighton/Arden Hills Supe1jund Site.
T.\1561 TCAAPIOU211014 ROD Amendment\Appendices\App C ~References.doc 1
U.S. Environmental Protection Agency, October 1988. Guidance for Conducting Remedial Investigations and Feasibility Studies under CERCLA.
U.S. Environmental Protection Agency, August 1993. Guidance on Conducting Non-TimeCritical Removal Actions under CERCLA.
Wenck Associates, Inc., June 2011. Operable Unit 2 (OU2) Land Use Control Remedial Design (LUCRD). Revision 2.
Wenck Associates, Inc., January 2012. Quality Assurance Project Plan for Engineering Evaluation/Cost Analysis Soil Investigations, Site A- AOCs, 135 Primer/Tracer AreaAOCs, EBS- AOCs. Revision 2.
Wenck Associates, Inc., November 2012. Engineering Evaluation I Cost Analysis for Soil Investigations at Areas of Concern, Site A, 135 Primer/Tracer Area, EBS Areas.
Wenck Associates, Inc., March 2013. Removal Action Work Plan, Soil Areas of Concern, Site A, 135 Primer/Tracer Area, EBS Areas.
Wenck Associates, Inc., November 15, 2013. Removal Action Completion Report for Soil Areas of Concern, Soil Areas of Concern, Site A, 135 Primer/Tracer Area, EBS Areas.
T:\1 561 TCAAP\OU2\2014 ROD Amendment\Appendices\App C_References.doc 2