record entry - mine

3
High Hazards Unit WorkSafe New Zealand PO Box 165, Wellington, 6140 Email: [email protected] Page 1 of 3 Record Entry - Mine Guardian File Number: 5799082 11 January 2021 Kevin Pattinson Site Senior Executive/Mine Manager Pike River Mine Te Kāhui Whakamana Rua Tekau mā Iwa - Pike River Recovery Agency (PRRA) PO Box 414 GREYMOUTH 7840 PLEASE PLACE THIS RECORD OF INSPECTION ON THE MINE NOTICE BOARD OR DISTRIBUTE TO THE ENTIRE WORKFORCE (INCLUDING CONTRACTORS). Background WorkSafe New Zealand – High Hazards Unit – Specialist Health & Safety Inspectors Bryan Harrington and John Ewen conducted an announced inspection of the Pike River Mine on 2 December 2020. Inspection Inspectors Bryan Harrington and John Ewen were admitted through the mine gate and drove to the mine site where they were met by Mr Dinghy Pattinson Site Senior Executive (SSE) at the bottom office complex. Inspectors met with Mr Pattinson and Mr Greg Duncan Mine Manager (MM). Mr Pattinson gave an overview of the project to date. Overview of Project The recovery of the drift is currently at 2085.5m, this leaves 55m to reach the Rocsil Plug. Advance rates have slowed considerably due to being in the coal measures and having to install mega bolts. The mega bolts are being installed on a one two pattern every metre. Mr Pattinson explained that the recovery of the drift to the Rocsil plug should be complete before Christmas. VCD 2 exact location is still to be identified, but at this stage will be between Bore Hole 23 and 53. The exact location will be identified once the conditions in the area are confirmed. The Police have informed PRRA that all equipment located at the pit bottom in stone is to be brought to the surface for inspection. This has required PRRA to purchase another underground Loader. This will arrive late December 2020. Inspectors asked for the ventilation Officer to send a ventilation plan showing that there is enough ventilation to run all of the machines underground when required. Mr Pattinson explained there will be an overriding Broad Brush Risk Assessment undertaken in the first instance before any equipment is removed to the surface. Then each individual piece of equipment will have a JSA undertaken before removing this to the surface. The site is going down to one shift a day after Christmas, with workers having to re-apply for their jobs. Mr Pattinson explained that during the Christmas break, which is from 3pm on 23 December 2020 to 5 January 2021. PRRA intend to revert to the Covid lockdown procedures, which mean that there will be no underground inspections, but the mine atmosphere will be monitored remotely. The surface will have inspections carried out every two days.

Upload: others

Post on 10-Dec-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Record Entry - Mine

High Hazards Unit WorkSafe New Zealand

PO Box 165, Wellington, 6140 Email: [email protected]

Page 1 of 3

Record Entry - Mine

Guardian File Number: 5799082

11 January 2021

Kevin Pattinson

Site Senior Executive/Mine Manager

Pike River Mine

Te Kāhui Whakamana Rua Tekau mā Iwa - Pike River Recovery Agency (PRRA)

PO Box 414

GREYMOUTH 7840

PLEASE PLACE THIS RECORD OF INSPECTION ON THE MINE NOTICE BOARD OR DISTRIBUTE TO THE

ENTIRE WORKFORCE (INCLUDING CONTRACTORS).

Background

WorkSafe New Zealand – High Hazards Unit – Specialist Health & Safety Inspectors Bryan Harrington

and John Ewen conducted an announced inspection of the Pike River Mine on 2 December 2020.

Inspection

Inspectors Bryan Harrington and John Ewen were admitted through the mine gate and drove to the mine

site where they were met by Mr Dinghy Pattinson Site Senior Executive (SSE) at the bottom office

complex.

Inspectors met with Mr Pattinson and Mr Greg Duncan Mine Manager (MM). Mr Pattinson gave an overview

of the project to date.

Overview of Project

The recovery of the drift is currently at 2085.5m, this leaves 55m to reach the Rocsil Plug. Advance rates

have slowed considerably due to being in the coal measures and having to install mega bolts. The mega

bolts are being installed on a one two pattern every metre.

Mr Pattinson explained that the recovery of the drift to the Rocsil plug should be complete before

Christmas.

VCD 2 exact location is still to be identified, but at this stage will be between Bore Hole 23 and 53. The

exact location will be identified once the conditions in the area are confirmed.

The Police have informed PRRA that all equipment located at the pit bottom in stone is to be brought to

the surface for inspection. This has required PRRA to purchase another underground Loader. This will

arrive late December 2020. Inspectors asked for the ventilation Officer to send a ventilation plan showing

that there is enough ventilation to run all of the machines underground when required.

Mr Pattinson explained there will be an overriding Broad Brush Risk Assessment undertaken in the first

instance before any equipment is removed to the surface. Then each individual piece of equipment will

have a JSA undertaken before removing this to the surface.

The site is going down to one shift a day after Christmas, with workers having to re-apply for their jobs.

Mr Pattinson explained that during the Christmas break, which is from 3pm on 23 December 2020 to 5

January 2021. PRRA intend to revert to the Covid lockdown procedures, which mean that there will be no

underground inspections, but the mine atmosphere will be monitored remotely. The surface will have

inspections carried out every two days.

Page 2: Record Entry - Mine
Page 3: Record Entry - Mine