Page 1: Reconstruction of Access Channel for Ship Entrance

Reconstruction of Access Channel for

Ship Entrance into the Port

Environmental impact assessment procedure

Initial public hearing

Riga, 12 O.Kalpaka boulevard.

April 3 , 2009 .

Page 2: Reconstruction of Access Channel for Ship Entrance

Agenda 14.00- start of the meeting 14.05 – Presentation on issues related to planned

access channel reconstruction and to EIA procedure

14.35 - Discussion

Contacts : State Environmental Bureau, 23 Rupniecibas

street , Riga. LV1045.67321173 67321049 Freeport of Riga Authority , 12 O.Kalpaka

boulevard, Riga. LV1010. 67030800 67030835

Page 3: Reconstruction of Access Channel for Ship Entrance

Riga City Development Program 2006-2012

Guidelines : develop new territories outside the historical city center enhance Riga development as the center of logistics Riga port Development program, 1996 - 2010Tasks: Implement terminal capacity ,infrastructure and channel depth planning ; Dredge and expand the main shipping channel

Page 4: Reconstruction of Access Channel for Ship Entrance

līdz 5000 GT

5001-10000 GT

vairāk par 10000 GT

0.0 10.020.030.040.050.060.070.080.0

Ship percentage (%) per GT indicator in the Freeport of Riga

2004- 2008.

2008.g. 2007.g. 2006.g.2005.g. 2004.g.

Project background

Increase of bigger tonnage vessels proportion

Navigational safety in Riga port

Modern , well-equipped and environment- friendly vessels entering Riga port

Modern Riga port, that is competitive in the north-eastern region of the Baltic sea

Dynamic Riga port, relocated from the city center

Page 5: Reconstruction of Access Channel for Ship Entrance

Kundziņsala

Bolderāja

Daugavgrīva

Mangaļsala

Vecmīlgrāvis

Spilve

Vecrīga

Page 6: Reconstruction of Access Channel for Ship Entrance

Project time frame

By 2009- fairway concept 2009-2010- environmental impact

assessment 2009-2011- construction design project 2012- commencement of construction

work, performed in several stages

Page 7: Reconstruction of Access Channel for Ship Entrance

Reconstruction of Access Channel for Ship Entrance into the Port Project concept.

Tasks: specify approximate parameters of the access channel; define changes in guidelines; develop channel route location proposal; calculate approximate volume of dredged soil; develop new channel picketage

Objective-

Define main parameters of access channel reconstruction

Page 8: Reconstruction of Access Channel for Ship Entrance

Further activities(I)

1. implement environmental impact assessment procedure related to the planned activity.

2-1. perform relevant geological, hydrological and hydrodynamic research, perform soundings, investigate and assess water ecological systems, including fish resources, to develop project documentation.

Page 9: Reconstruction of Access Channel for Ship Entrance

Further activities(II)

2.2. Receive technical and special terms and conditions from public and municipal institutions.

2.3. Elaborate work project documentation for hydro-technical structures’ reconstruction on the basis of preliminary investigations and environmental impact assessment results, identifying risks and specifying optimal technological solutions with the aim to reach the set objectives: Ensure the shipping fairway depth up to 15,5 m at the section

from Kurpnieksala up to the middle of Kundzinsala . Ensure fairway depth up to  17 m from the reception buoy up to

the northern part of Kurpnieksala , Ensure fairway width at apprx . 180 m .

Page 10: Reconstruction of Access Channel for Ship Entrance

Further activities(III)

2.4. Parallel to work project elaboration the hydro-technical structures , that are related to access channel and have to be reconstructed, are identified as well as issues , that were specified in the process of EIA development.

3.1. Hydro-technical structures’ reconstruction performed by stages.

It is planned to perform reconstruction works of separate sections by stages in compliance with technological solutions, provided in the project.

Page 11: Reconstruction of Access Channel for Ship Entrance

Characteristics of the Riga port Shipping fairway

Hydro-technical structures(LR “Law on Ports”): Main shipping fairway, Access to berths, Shoreline reinforcements, berths, turning basins , piers, Current regulating jetties, breakwaters, as well as

navigation equipment and appliances that are transferred to possession of the Freeport of Riga Authority

Page 12: Reconstruction of Access Channel for Ship Entrance

Shipping channel parameters

Existing main fairway: From reception buoy „B”

up to Rienzi basin (berth ZO-12) -13.5

From Rinuzi basin (berth ZO-12) up to Pilumuizha -11.7

From Pilumuizha up to passenger terminal -8.0

Milgravis canal -9.05 Sarkandaugava canal-

9.05

4 turning basins

Page 13: Reconstruction of Access Channel for Ship Entrance

EIA stages

30.05.2008 – SEB resolution Nr.252 on EIA procedure application;

27.03.2009- 03.04.2009 – initial public hearing related to the project;

In compliance with the program, issued by SEB : Interim report Interim report submitted to public hearing Final report Final report submitted to public hearing SEB conclusion Riga City Council either approves or

disapproves the planned activity

Page 14: Reconstruction of Access Channel for Ship Entrance

Current status investigation

Surface and underground waterSurface water flow processesRiver water qualityAir quality River biological and ecological systems Waste managementTransport and access

Page 15: Reconstruction of Access Channel for Ship Entrance

Forecasted impacts on :

Existing environment systems: Climate, air quality, noise level River flow directions River condition River water quality Biological systems

Social-economical systems

Page 16: Reconstruction of Access Channel for Ship Entrance

In the framework of EIA the following issues will be specified :

What short-term or long-term changes of Daugava river and adjacent zones topography might occur

What changes of underwater vegetation might occur

What impact on fish resources can be anticipated Planned investigations (wells, tests) Forecasted requirements related to removal

works Forecasted requirements related to construction

works Forecasted requirements related to dredging

works

Page 17: Reconstruction of Access Channel for Ship Entrance

In the framework of EIA the following issues will be specified :

Forecasted requirements related to shoreline strengthening structures

Forecasted requirements related to material storage and transportation

Forecasted requirements related to dredged soil storage and disposal

Forecasted requirements related to risk mitigation at current pipeline crossing locations

Page 18: Reconstruction of Access Channel for Ship Entrance

Thank you!