recognizing life cycle cost analysis sensitivity for...

24
Recognizing Life Cycle Cost Analysis Sensitivity for Pavement Preservation Treatments Doug Gransberg PhD, PE Iowa State University Ames, Iowa 50010 [email protected]

Upload: others

Post on 09-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Recognizing Life Cycle Cost Analysis Sensitivity for Pavement Preservation

Treatments

Doug Gransberg PhD, PE

Iowa State University

Ames, Iowa 50010

[email protected]

Page 2: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Life Cycle Cost Analysis Issues• Exclusive use of Present Value Analysis for public projects.

• Selection of a period of analysis.

• Selection of an interest rate.

• Calculation of asset residual value.

• Calculation of user costs.

• Use of the same interest rate for both agency and user

costs.

• The lack of recognition of the value of cost certainty when

comparing materials with different levels of historic

volatility.2

Page 3: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Present Value Analysis Issues

State and Federal governments mandate the use of Net Present

Value (NPV) for life cycle cost analysis of public project design

alternatives.

1. Replication of multiple services lives is an artificial

computational trick that in no way models actual

circumstances.

2. Calculation of residual value for most assets is difficult

without empirical deterioration models.

3. Mandated use of PV analysis precludes the use of Equivalent

Uniform Annual Cost (EUAC) analysis which furnishes a

technically viable solution to issues 1 and 2

3

Page 4: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Period of Analysis Issues

• LCCA outcomes are sensitive to the period of analysis.

• Arbitrary selection can bias the output.

• Example – Asphalt pavement versus Concrete.

– Asphalt service life 12-15 years and cost to

reconstruct relatively low.

– Concrete service life 20-30 years and cost to

reconstruct is more than initial cost because of high

demolition cost.

• Thus, if period does not include a concrete reconstruction

cost, concrete wins.4

Page 5: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

5

The DOT’s Dream: Concrete vs Asphalt

(Cross and Parsons, 2001)

Concrete Asphalt

Page 6: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Life Cycle Cost Analysis IssuesProblem: What is the proper discount rate to use in life cycle cost analysis

to make pavement design decisions IAW federal funding regulations?.... Or

any other LCC-based design decisions?

6

AgencyRequired LCCA

Interest RateAgency

Required

LCCA

Interest Rate

FHWA 3%-5% North Carolina DOT 4%

Arizona DOT 4% Pennsylvania DOT 6%

California DOT 5% Texas DOT 5%

Idaho DOT 4% Washington DOT 4%

Kentucky DOT 3%-10% Wisconsin DOT 5%

Nevada DOT 4% New Zealand Transport Agency 8%

Maryland DOT 6%

British Columbia Ministry of

Transportation

6%

Michigan DOT 3.90% Ontario Ministry of Transportation 5%

Page 7: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

7

Possible Discount Rates

• Global: loss in buying power of the US dollar.

FHWA approved approach

• Industry based: Inflation in transportation

construction projects – construction cost indices.

• Material based (econometric): Inflation of major

commodity – asphalt, Portland cement, steel, etc.

Page 8: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

8

Different Discount Rates:

Monte Carlo ResultsStatistical Measures of Simulation Results

Statistic

Asphalt

CalTrans

ACP

Index

Concrete

CalTrans

PCCP

Index

Asphalt

CalTrans

CCI Index

Concrete

CalTrans

CCI Index

Asphalt

ENR CCI

Index

Concrete

ENR CCI

Index

Minimum 3.60E+06 1.07E+07 3.59E+06 1.07E+07 3.59E+06 1.07E+07

Mean 1.96E+08 1.22E+14 2.76E+07 2.77E+07 1.10E+07 2.75E+07

Maximum 6.80E+10 1.18E+17 7.87E+09 5.76E+09 1.53E+09 1.30E+10

Std Dev 2.87E+09 3.74E+15 2.66E+08 1.93E+08 5.43E+07 4.10E+08

Variance 8.24E+18 1.40E+31 7.09E+16 3.74E+16 2.95E+15 1.68E+17

Winning

Alternative

Asphalt always has

lower expected life

cycle cost.

Asphalt to $24.5 M

then Concrete

Asphalt to $26.5 M

then Concrete

Conclusion: Need research to develop state-level econometric

discount rates for pavement LCCA-based design.

Page 9: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Impact of Interest Rate Sensitivity on Design

9

WASHINGTON - FPS-19 - Discount Rate

1,200,000

1,300,000

1,400,000

1,500,000

1,600,000

1,700,000

1,800,000

1,900,000

2,000,000

2,100,000

2,200,000

2,300,000

2,400,000

2,500,000

2,600,000

2,700,000

2,800,000

0.5%

0.6%

0.7%

0.8%

0.9%

1.0%

1.5%

2.0%

2.5%

3.0%

3.5%

4.0%

4.5%

5.0%

5.5%

6.0%

6.5%

7.0%

7.5%

8.0%

8.5%

9.0%

9.5%

10.0

%

11.0

%

12.0

%

13.0

%

14.0

%

15.0

%

16.0

%

17.0

%

18.0

%

19.0

%

20.0

%

Discount Rate (%)

NP

V

- (

$ )

Design 1 Design 2 Design 3 Design 4

Design 3

14.5"

Design 1

5.5"

Design 2

8"

Design 4

11"

AI

AASHTO

FPS-19 #1FPS-19 #2

Design 3:

14.5”

Design 4:

11.0”Design 2:

8.0”

Design

1:

5.5”

When the ECONOMIST picks the rate – the ENGINEER no longer controls the design

Page 10: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

10

Same Rate for Agency and User Costs

• Standard is use the same rate for both.

• World Bank uses a “social discount rate” to evaluate

infrastructure projects.

– Recognizes that the impact of discounting on humans

impacted by project and

applied to user costs.

– Financial rate is used

for capital costs.

– Figure shows sensitivity

to this issue.

Deterministic Sensitivity Analysis,

Financial discount Rate = 4%

$20,000,000

$21,000,000

$22,000,000

$23,000,000

$24,000,000

$25,000,000

$26,000,000

0% 1% 2% 3% 4% 5% 6% 7% 8% 9%10%

Social Discount Rate

Life

Cyc

le C

ost

HMA PCCP

Page 11: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

User Cost Issues• Research estimates user cost of an urban freeway can

exceed $10,000 per lane-mile per day.

• Thus, a 5-mile 8-lane freeway could incur $400,000 per day in user costs of construction.

• These can outstrip the actual capital costs.

• Use of a “weighted” amount is an option– i.e. user costs @ 20% & capital costs @ 80%

• However, the weight is arbitrary and the output can be manipulated by manipulating the weights.

• Adding user costs favors:– Design that are fast to build and/or have longer service lives.

– Long term analysis to put a value on a short-term aspect11

Page 12: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Residual Value Issues

• An infrastructure asset does have value after its service life is

exceeded.

• Current methods use depreciation theory

– FHWA uses straight-line

– International agencies use empirical deterioration models

• Two questions have not been satisfactorily answered:

– Does an asset REALLY have value if it costs more to remove

than the value of its materials?

– Does renovating an asset, which actually incurs a cost not a

benefit, cancel the residual value?

12

Page 13: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Volatility Issues• How certain are the numbers used in LCCA?

– When an agency does a cost estimate for a job to built in 2 years, it includes a contingency for uncertainty.

– Why don’t we include a contingency in LCCA that spans 50 years?

– Perhaps design-oriented LCCAshould designaround materials that are the leastvolatile

13

Regression Sensitivity for Monthly Project Applied/P98

0.928

0.403

0.267

0.087

0.009

-1 -0.5 0 0.5 1

Cement / Material/M96

Steel / Material/M98

Diesel / Equip/N97

Asphalt / Material/M94

Aggregates / Material/M95

Std b Coefficients

Page 14: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

LCCA in Transportation• Limited application due to complexity

• Very sensitive to discount rate & analysis period

• Limited at project/implementation level

• No specific stochastic LCCA/PPT – adapted tool

• Network-level LCCA tool (FHWA CASE STUDIES):not applied to PPT or needs to be customized for PPT

• Economic analysis tools still being developed (FHWA, 2007)

• No consensus among SHAs

• SHA to develop own tools (Hall et al, 2003)

Page 15: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Deterministic v. Stochastic LCCALCCA to determine most cost-effective alternative and could justify pavement preservation treatment decisions

• Deterministic approach: *traditional approach in transportation*point estimate based on input assumptions*limited sensitivity analysis*less complex than stochastic approach

• Stochastic approach:*exposes inherent uncertainties (simultaneously)*identifies/quantifies risk associated with commodity price volatility

*to address budget issues and mitigate risk*recommended by the FHWA (if uncertainty impact)

Page 16: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Deterministic EUAC for PPT evaluation

HMA EUAC ($/lane-mile), Deterministic Method

Discount Rate

Service Life (YR) 3% 4% 5%

8 4,917 5,086 5,259

10 4,387 4,551 4,719

12 3,759 3,933 4,111

Page 17: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Stochastic EUAC for PPT evaluation

HMA EUAC ($/lane-mile), Deterministic Method

Discount Rate

Service Life (YR) 3% 4% 5%

8 4,917 5,086 5,259

10 4,387 4,551 4,719

12 3,759 3,933 4,111

$4,551 falls at the 37th percentile

Page 18: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Stochastic EUAC for PPT evaluation

HMA EUAC ($/lane-mile), Deterministic Method

Discount Rate

Service Life (YR) 3% 4% 5%

8 4,917 5,086 5,259

10 4,387 4,551 4,719

12 3,759 3,933 4,111

$3,759 falls at the 5th percentile

Page 19: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Stochastic EUAC for PPT evaluation

HMA EUAC ($/lane-mile), Deterministic Method

Discount Rate

Service Life (YR) 3% 4% 5%

8 4,917 5,086 5,259

10 4,387 4,551 4,719

12 3,759 3,933 4,111

$5,259 falls at the 82nd percentile

Page 20: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

EUAC & Risk AnalysisSensitivity Analysis: Regression

Input Variable St. DeviationRegression

Coefficient

Net Change in

EUAC

Discount Rate 2.76% 0.869 478.09

Service Life 1.2 Years -0.419 -230.63

Asphalt Binder $0.13 0.203 111.74

Diesel $0.008 0.015 8.38

Labor $0.006 0.011 5.84

Aggregate $0.006 0.009 5.07

Page 21: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

1” HMA 5/8” Chip Seal

DeterministicService Life,

Discount Rate

EUAC

($/lane-mile)

Service Life,

Discount Rate

EUAC

($/lane-mile)

Low 12-YR, 3% 3,759 6-YR, 3% 3,019

Average 10-YR, 4% 4,551 4-YR, 4% 4,478

High 8-YR, 5% 5,259 2-YR, 5% 6,900

Probabilistic

Mean 4,742 4,574

St. Deviation 557 983

5th Percentile 3,844 3,288

95th Percentile 5,669 6,505

Max. Value 7,191 8,633

Net Change in

EUAC

Net Change in

EUAC

Regression Analysis

(Service Life)-230.63 -911.66

LCCA Example

Page 22: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

1” HMA 5/8” Chip Seal

DeterministicService Life,

Discount Rate

EUAC

($/lane-mile)

(percentile)

Service Life,

Discount Rate

EUAC

($/lane-mile)

(percentile)

Low 12-YR, 3% 3,759 (4th) 6-YR, 3% 3,019 (P<1st)

Average 10-YR, 4% 4,551 (37th) 4-YR, 4% 4,478 (53rd)

High 8-YR, 5% 5,259 (82nd) 2-YR, 5% 6,900 (99th)

Probabilistic

Mean 4,742 4,574

St. Deviation 557 983

5th Percentile 3,844 3,288

95th Percentile 5,669 6,505

Max. Value 7,191 8,633

Net Change in

EUAC

Net Change in

EUAC

Regression Analysis

(Service Life)-230.63 -911.66

LCCA Example

Page 23: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Conclusions

• Stochastic LCCA is practical at the PPT level, facilitated by software

• Deterministic LCCA provides comparable results to stochastic LCCA, is less complex, and is appropriate when uncertainty is not expected to affect results

• Probabilistic treatment of volatile commodities can expose LCCA sensitivities and enhance LCCA process

• Stochastic LCCA can enhance a pavement engineer’s ability to address budget issues, mitigate risk and justify PPT decisions

Page 24: Recognizing Life Cycle Cost Analysis Sensitivity for ...pavementvideo.s3.amazonaws.com/2016_NPPC/Track2/TRACK 2...impacted by project and applied to user costs. –Financial rate is

Summary

• Design-oriented LCCA is not as simple as the Engineering Economics textbooks claim.– The books have unintentionally over-simplified the

analysis to avoid thorny computational issues– This makes it easy to teach to engineers with no formal

education in economics and finance.

• Sensitivity analysis MUST be used to understand the dynamics of the LCCA model.

• Monte Carlo simulation can be used to quantify uncertainty.

• The least sensitive option may be the best even if its LCC is higher than another.

24