real-time modelling and simulation of distribution system

79
i REAL-TIME MODELLING AND SIMULATION OF DISTRIBUTION SYSTEM PROTECTION WITH AND WITHOUT RENEWABLE DISTRIBUTED GENERATION By Ntuba Irene Nkhasi 211535371 In partial fulfilment of the academic requirements for the degree of Master of Science in Electrical Engineering, College of Agriculture, Engineering and Science University of Kwazulu Natal December 2017 Supervisor: Dr A K Saha

Upload: others

Post on 18-Dec-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

i

REAL-TIME MODELLING AND SIMULATION OF DISTRIBUTION

SYSTEM PROTECTION WITH AND

WITHOUT RENEWABLE DISTRIBUTED GENERATION

By

Ntuba Irene Nkhasi

211535371

In partial fulfilment of the academic requirements for the degree of

Master of Science in Electrical Engineering,

College of Agriculture, Engineering and Science

University of Kwazulu Natal

December 2017

Supervisor: Dr A K Saha

ii

ABSTRACT

The conventional radial power distribution systems were initially not designed to

accommodate distribution generation (DG). As DG penetration is being considered by many

distribution utilities, there is a rising need to address many incompatibility issues that put a

big emphasis on the need to review and implement suitable protection schemes. For a

significant greenhouse gas reduction using photovoltaic systems, numerous generators ought

to be embedded in the distribution system. For an effective penetration of PV systems on a

large-scale into the current distribution network, considerable work to investigate the nature

of incompatibility problems has been done and research is being carried out to develop

successful integration strategies. The main objectives of the thesis are; to model and simulate

a distribution system protection scheme, to study radial networks’ protection system

challenges after embedding distributed generation sources, investigation on the impacts of

high PV penetrations on protection systems of distribution networks and lastly make

modification recommendations and essential review process of existing protection equipment

settings. To accomplish the above-mentioned objectives, a radial distribution network is

modelled, simulated and protection settings validated. The PV generation system is designed

and added to specific distribution feeders and steady steady-state results obtained. The results

show that addition of DGs cause the system to lose its radial power flow. There is an increase

in fault contribution hence causing maloperation such as protection coordination mismatch.

An overall protection scheme is then proposed based on the addition of DG’s and an efficient

adaptive protection system for the distribution networks with a considerable penetration of

dispersed generations implemented. The impact study is performed which is compared with

the existing protection scheme and necessary modifications done. The entire analysis is

simulated on a real-time digital simulator (RTDS) and results displayed in a MATLAB

environment. For the islanded mode, relaying considerations are provided and

implementation of anti-islanding techniques achieved.

iii

Acknowledgements

My heartfelt gratitude goes to my supervisor Dr. A.K Saha for his constant supervision,

valuable academic support and patience during the course of the research. Thanks for the

encouragement and always being available to guide and advice although it was long and went

through some bumpy times. It has been an absolute pleasure working under his selfless

supervision. My sincere appreciation also goes to my friend N.V. Ndlhozi, who dedicated

time off his busy schedule and work to proofread my drafts. To my mother and family, thank

you for your encouragement and support all the way through my research journey, thanks for

not letting me give up. Finally yet importantly, this thesis is a dedication to my late father and

sister who are not around anymore to witness my academic achievements, this one is for you.

iv

Table of Contents

ABSTRACT ............................................................................................................................... ii

Acknowledgements .................................................................................................................. iii

List of Figures: ......................................................................................................................... vii

List of Tables ............................................................................................................................ ix

List of Abbreviations: ................................................................................................................ x

1. Introduction ........................................................................................................................ 1

1.1. Background ................................................................................................................. 1

1.2. Importance of research ................................................................................................ 2

1.3. Research objectives ..................................................................................................... 3

1.4. Research scope and limitations ................................................................................... 3

1.5. Problem statement ....................................................................................................... 4

1.6. Thesis outline .............................................................................................................. 4

2. Literature Review ............................................................................................................... 6

2.1. Introduction ................................................................................................................. 6

2.2. Review on faults .......................................................................................................... 6

2.3. Protection philosophy .................................................................................................. 7

2.3.1. Essential qualities of protection. .......................................................................... 8

2.4. Protective equipment ................................................................................................... 8

2.5. Protection scheme ....................................................................................................... 9

2.5.1. Transformer protection ...................................................................................... 10

2.5.2. Differential protection ........................................................................................ 10

2.5.3. Overcurrent Protection ....................................................................................... 10

2.6. Protection coordination ............................................................................................. 12

2.7. Distributed generation ............................................................................................... 12

2.7.1. Distributed Generation Technology ................................................................... 13

2.7.2. Grid-tied Photovoltaic System ........................................................................... 13

2.8. Impact of DG integration to the existing grid and protection scheme ...................... 14

2.9. Mitigation methods to DG penetration issues. .......................................................... 16

3. Methodology ..................................................................................................................... 18

3.1. Software selection ..................................................................................................... 18

3.2. Modelling of the distribution network in RSCAD .................................................... 19

3.2.1. Draft programme ................................................................................................ 19

3.2.2. Runtime programme .......................................................................................... 19

v

3.3. Protection set-up ........................................................................................................ 20

3.4. Protection relay testing .............................................................................................. 20

3.5. PV generation system design .................................................................................... 20

3.6. Grid-tied inverter model development ...................................................................... 21

3.7. Stand-alone grid tied PV system ............................................................................... 21

3.8. Optimal relay coordination........................................................................................ 21

3.9. PV impacts mitigation methods ................................................................................ 22

3.10. Recommendation for future works ........................................................................ 23

4. Modelling and real-time simulation ................................................................................. 24

4.1. Test distribution system configuration ...................................................................... 24

4.2. System full load conditions ....................................................................................... 25

4.2.1. Fault and breaker logic control .......................................................................... 27

4.2.2. Relay logic control ............................................................................................. 27

4.3. Software relays’ simulation:...................................................................................... 28

4.3.1. Testing software Relay-3 ................................................................................... 28

4.3.2. Time setting of Relay-2: .................................................................................... 29

4.3.3. Testing software Relay-2: .................................................................................. 30

4.3.4. Time setting of Relay-1: .................................................................................... 31

4.3.5. Testing software Relay-1: .................................................................................. 31

4.3.6. Testing software Relay-4 ................................................................................... 32

4.4. Protection Coordination results ................................................................................. 33

5. Experimentation and Verification .................................................................................... 37

5.1. Hardware-in-loop simulation .................................................................................... 37

5.1.1. Testing Hardware Relay-3 ................................................................................. 38

5.1.2. Testing Hardware Relay-2 ................................................................................. 38

5.1.3. Testing Hardware Relay-1 ................................................................................. 38

5.1.4. Testing Hardware Relay-4 ................................................................................. 39

5.2. Grid-connected PV system ........................................................................................ 40

5.2.1. Inverter model development .............................................................................. 41

5.2.2. Steady-state operation ........................................................................................ 43

5.2 Overcurrent Protection set-up ................................................................................... 48

5.3 Islanding Protection................................................................................................... 52

5.3.2 Passive techniques ............................................................................................. 52

5.3.3 Active techniques ............................................................................................... 53

vi

5.3.4 Islanding operation............................................................................................. 53

6 Conclusion ........................................................................................................................ 57

References ................................................................................................................................ 59

Appendix .................................................................................................................................. 65

vii

List of Figures:

Figure 1: Single line diagram of the modelled distribution system ......................................... 24

Figure 2: System R.M.S Currents ............................................................................................ 26

Figure 3: Distribution system RMS voltages ........................................................................... 26

Figure 4: Fault and circuit breaker logic .................................................................................. 27

Figure 5: Software overcurrent relay used ............................................................................... 28

Figure 6: Relay-3 operating for a fault on 380 V busbar ......................................................... 29

Figure 7: Relay-2 testing for a fault at zone-3 (380V busbar) ................................................. 30

Figure 8: Relay-2 operating for a fault at zone-2 (11 kV busbar) ........................................... 30

Figure 9: Relay-1 operating for a fault at zone-2 (11 kV busbar) ........................................... 31

Figure 10: Relay-1 operating for a fault at zone-1(132 kV busbar) ........................................ 32

Figure 11: Relay-4 operating for a fault on the 22 kV busbar ................................................. 32

Figure 12: Relay-2 failing to operate ....................................................................................... 33

Figure 13: Failure of relay-3 and relay-2 to operate ................................................................ 34

Figure 14: Operation of relay-2 for a fault at protection zone 3 .............................................. 35

Figure 15: Relay-4 failing to operate ....................................................................................... 35

Figure 16: System hardware-in-loop connection ..................................................................... 37

Figure 17: Hardware Overcurrent Relay 3 operating .............................................................. 38

Figure 18: Hardware Overcurrent Relay 2 operating .............................................................. 38

Figure 19: Hardware Overcurrent Relay 1 operating .............................................................. 38

Figure 20: Hardware Overcurrent Relay 4 operating .............................................................. 39

Figure 21: RSCAD model of grid connected PV system ........................................................ 40

Figure 22: Large and small time-step simulation interface ..................................................... 42

Figure 23: Characteristic curves of the PV array at STC ......................................................... 43

Figure 24: PV Array output voltage......................................................................................... 43

Figure 25: Stand-alone PV System output RMS voltage......................................................... 44

Figure 26: Single line diagram of the grid-tied photovoltaic system....................................... 45

Figure 27: Grid-connected PV system voltages....................................................................... 45

Figure 28: Grid-connected PV system CTs secondary RMS current ...................................... 46

Figure 29: PV System RMS voltage ........................................................................................ 47

Figure 30: System RMS currents ............................................................................................. 47

Figure 31: Relay-3 testing ........................................................................................................ 50

Figure 32: Relay-2 testing ........................................................................................................ 50

Figure 33: Testing relay-1 ........................................................................................................ 51

Figure 34: Relay-4 testing results ............................................................................................ 51

Figure 35: A radial feeder with PV generation integrated ....................................................... 53

Figure 36: Distribution system currents due to islanding ........................................................ 54

Figure 37: Protection against islanding layout......................................................................... 54

Figure 38: Circuit breaker logic ............................................................................................... 55

Figure 39: Circuit breaker 1 and 6 opening on fault F-1 occurrence ....................................... 55

Figure 40: System line current during islanding protection..................................................... 56

Figure 41: Circuit breaker 1 and 6 opening on fault F-2 occurrence ....................................... 56

Figure 42: Distribution System Model on RSCAD environment ............................................ 65

viii

Figure 43: GTFPI and GTAO card used for exporting signals ................................................ 66

Figure 44: PV System characteristics graphs........................................................................... 66

Figure 45: Maximum Power Point Tracking control circuit .................................................... 67

Figure 46: 2-level DC/AC inverter and filter ........................................................................... 67

Figure 47: Triangle wave data generator for the DC/AC inverter ........................................... 67

ix

List of Tables

Table 1: Transformers, load and source parameters ................................................................ 25

Table 2: Voltages and Currents measured on the distribution system. .................................... 25

Table 3: Comparison of operating time from software and hardware relays .......................... 39

Table 4: Parameters of Mitsubishi Electric Photovoltaic Module ........................................... 40

Table 5: PV system parameters and expected outputs at STC ................................................. 42

Table 6: PSM and a values ...................................................................................................... 49

Table 7: Dial output and corresponding fault .......................................................................... 65

Table 8: 1st iteration (Slack variables as basics) ..................................................................... 68

Table 9: 2nd iteration (X2 enters as basic, S2 comes out) ........................................................ 68

Table 10: 3rd iteration (X1 enters as basic, S1 comes out) ....................................................... 68

Table 11: 4th iteration (X3 enters as basic, S5 comes out) ....................................................... 68

x

List of Abbreviations:

DG Distributed Generation

IEEE Institute of Electrical and Electronics Engineers

IEC International Electro-technical Commission

PV Photovoltaic

DC Direct Current

AC Alternating Current

RTDS Real-time Digital Simulator

CT Current Transformer

VT Voltage Transformer

CB Circuit Breaker

OCR Overcurrent Relay

TMS Time Multiplier Setting

IDMT Inverse Definite Minimum Time

PSM Plug Setting Multiplier

CTI Coordination Time Interval

LOM Loss of Mains

ETAP Electrical Transient and Analysis Program

PSCAD Power System Computer Aided Design

HVDC High Voltage Direct Current

HIL Hardware-in-Loop

GUI Graphical User Interface

GTFPI Gigabit-transceiver Front Panel Interface

GTAO Gigabit-transceiver Analogue Output

MPPT Maximum Power Point Tracking

RMS Root Mean Square

VSC Voltage Source Converter

IGBT Insulated Gate Bipolar Transistor

STC Standard Test Conditions

NOCT Normal Operating Cell Temperature

PCC Point of Common Coupling

LPP Linear Programming Problem

1

1. Introduction

This research work highlights the effective use of a real-time digital simulator (RTDS) for

modelling, analysis and protection of an electrical distribution network emanating from

a 132 𝑘𝑉 grid. It provides an introduction to overcurrent protection scheme on a distribution

network injected with dispersed generation (DG) and the DG potential benefits to distribution

utilities discussed. A review of the protection issues associated with dispersed generation is

conducted. In this chapter, the research background, objectives and methodologies employed

in this thesis are stated and finally the chapters outline is provided. The system under study is

a modified adaptation of the IEEE test feeders.

1.1. Background

Due to a constantly rising energy demand and roughly two centuries of total dependency on

fossil fuels, the world has begun to feel the greenhouse gas emissions effect. As the demand

for electrical energy seems to be on a rise, alternative fuels are being looked at apart from

fossil fuels that power thermal power plants. Nuclear or hydroelectric power generation

systems do not generate greenhouse gases and are another alternative to be considered except

that a high level of safety is required for nuclear while water levels, which hydroelectric

depend on, are not entirely reliable [1] [2].

Distributed generation systems such as photovoltaic energy, wind turbines, fuel cells and

other energy storage technologies are at present increasingly finding their significance to

solve environmental issues. Unlimited renewable energy resources such as solar can serve as

substitutes for fossil fuels consequently reducing greenhouse gases significantly. Photovoltaic

generation through photovoltaic effect, converts solar irradiation directly into electrical

energy using solar cells. With the technical evolution, finance and electrical markets

expansion, new technologies make possible the electricity generation in small plants closer to

consumers.

This new concept leads to the development of innovative electrical power distribution

systems where photovoltaic (PV) generation systems supplies some of the energy and

centralized generation produces some. Traditional distribution systems are of radial topology,

which only permits flow of power in a single downstream direction and the protection

schemes are dependent on this assumption, particularly overcurrent relay selectivity and

coordination [3]. The unidirectional power flow assumption does however not hold when

2

distributed generation is injected in the distribution system. Back flow of current occurs due

to multiple sources hence disturbing the standard overcurrent protection and their relay

sequential operation.

Major concerns relating to penetration of PV systems include poor relay coordination,

sympathetic tripping and unintentional islands which result from continuous power flow from

the dispersed generation systems although the grid is disconnected due to a fault. Many

power distribution utilities currently mitigate these problems by limiting the DG units’

capacity and using strategic location [4]. This thesis aims to focus on the modelling of a

radial distribution feeder system structure and study the impacts of distributed energy

resources when integrated with distribution systems including relaying considerations when

in islanded mode.

1.2. Importance of research

For any nations’ technological and economic progression, a steady and reliable electric power

supply system is an inevitable pre-requisite. It is a known fact that around the world a higher

percentage of the power systems’ equipment damage and customer service interruptions

results from failure and faults in the electricity distribution feeders since overhead

distribution systems are subject to either temporary or permanent faults. Distribution systems

comprise of many diverse and expensive items that require a substantial capital investment

and it therefore it is very essential to protect this equipment. Moreover, a considerable

quantity of photovoltaic generators has to be injected into the distribution network for a

significant reduction in the greenhouse gas emissions. Large-scale PV penetration however

gives rise to potential distribution system protection problems such as protective equipment

coordination issues, etc. [3]. For an effective penetration of PV systems on a large-scale into

the current distribution network, considerable work to investigate the nature of

incompatibility problems has been done and this research is being carried out with a purpose

to develop and implement strategies for successful integration of PV generators into the

present network. The thesis aims to cover a systematic approach from modelling the

distribution network to various protective devices’ coordination on different nodes of the

feeder, the DG’s impact on the system and to cover lastly the implementation of mitigation

methods on the identified issues.

3

1.3. Research objectives

The core objectives of the thesis are:

Modelling and simulation of a distribution system overcurrent protection scheme

To introduce PV generation system into the distribution network and identify issues

arising concerning the network protection system.

To address the identified and aforementioned issues to maintain and improve the grid-

tied photovoltaic energy systems’ performance.

To investigate the impact of high PV penetrations levels distribution system stability

and on protection systems performance while varying the PV point of common

coupling to different voltage levels.

To make modification recommendations and essential review process of existing

protection equipment settings for correct discrimination.

To implement mitigation strategies to some of the problems arising from introduction

of PV systems to the distribution network

To make recommendations on studies that can be carried out to further this research

work

1.4. Research scope and limitations

The research identifies issues related to interconnection of PV systems to distribution

utilities, reviews and implements some pragmatic mitigation methods. This research scope

and limitations are as follows:

Only the major technical issues with over-current protection relays’ coordination of a

distribution system are covered and addressed.

The DG technologies have been limited to photovoltaic (PV) generation, which are

based on solar panels and DC-AC inverters.

The main focus is on protection scheme and protection issues related to

interconnection of the PV system.

Models have been developed in RSCAD and RTDS simulator and some of the

standard models available in the software have been used.

4

1.5. Problem statement

To demonstrate by simulation and experimental tests a distribution system model and

overcurrent protection scheme implementation and testing of protection devices through a

hardware-in-loop connection. As outlined earlier, the electricity demand is currently fast

growing and power engineers are bound to produce electricity from renewable energy sources

to overcome this upsurge and simultaneously diminish environmental effects and carbon

footprint of power generation. To address mitigation methods to some of the issues created

by addition of distributed generation to electricity distribution network.

1.6. Thesis outline

This section presents an overview of the research work covered. The thesis consists of six

chapters and an appendix. Each chapter’s summary of content is provided and organized

below as follows:

Chapter 1: Introduction

This is an overview to the research work undertaken, outlining aims and objectives,

description of motivation, research scope plus limitations and the background of this

research. It introduces the concept and background of distributed generation, existing

methods of harnessing renewable energy, particularly the role of photovoltaic systems in this

perspective and the drawbacks of connecting DGs on the existing protection systems.

Chapter 2: Literature Review

This section reviews the existing literature on distribution systems overcurrent protection

schemes followed by a discussion the several types and nature of dispersed generation

technologies with distinct reference to inverter tied PV systems. The impacts of grid-tied PV

systems on distribution networks are discussed, focusing mainly on feeder protection

problems due to interconnection of DG systems. It also highlights in theory some of the

mitigation methods to the negative impacts. A comprehensive understanding of the research

problem has been presented and the published research work results discussed in detail.

Chapter 3: Methodology

The chapter outlines a systematic approach deployed in this research to achieve objectives

discussed in the introduction. It gives briefly an overview to overcurrent protection

techniques and describes the type of simulator used, its main features and advantages

pertaining to the research work.

5

Chapter 4: Modelling and real-time simulation

In this chapter, the distribution network and overcurrent protection scheme for the radial

feeder is modelling and implemented. The chapter contains designed models in the graphical

user interface (RSCAD) environment; it also consists of several outcomes from investigations

taken up as a section of the research. It presents model calculations and tables for some of the

relevant algorithms employed in the study. The distribution network is analysed and

protection system coordination implemented, with which results obtained serve as a basis that

results after modifications and interconnection of DGs are compared to.

Chapter 5: Experimentation and verification

All results obtained from the software simulations are verified by substituting the software

relays on the network with the hardware relays through a hardware-in-loop connection. Since

probable problems generated by DG’s addition to distribution networks include protective

device discrimination and possible formation of islanded systems, the test radial distribution

feeder topology is then modified by introducing PV generation at nodes on the network and a

detailed analysis of the simulation results done to understand the PV generation impact on

protection coordination. A solution to overcome the issues is implemented and simulation

results with different DG interconnection points and configurations are presented.

Chapter 6: Conclusion

This chapter recapitulates the research work outcomes and key results as well as some

recommendations for future work. A detailed discussion of the research work results and a

comprehensive understanding of the problems has been presented.

6

2. Literature Review

2.1. Introduction

The diminishing of fossil fuels and increasing environmental awareness is resulting in an

increasing distributed power generation worldwide [5]. On the other hand, the scarcity of

fossil fuels, their increasing costs, the limited investment on new large power plants and

transmission lines construction are the other reasons contributing to the deployment of small

power plants which can be connected to strategic points on distribution systems or close to

load centres [6]. The continuing increase in the penetration of distributed generation (DG)

and the adoption of active network-management solutions in distribution networks across the

world creates a network protection challenge due to the effects on fault levels, fault current

paths, etc. [7].

Distribution systems are generally designed to operate without any generation on the

distribution network or customer loads. Due to the accumulating number of DG connected to

distribution networks, there arise concerns regarding power quality, reliability, protection

devices and control of the utility system [8]. Since integration of distributed generation in

distribution networks imposes many challenges, distribution overcurrent protection has

become more important today than it was a decade ago [9]. The distribution system

protection has faced new challenges due to distributed generation, which may be successfully

accomplished through the combination of the existing protections, such as overcurrent

protection, with modern protections based on evolving technologies discussed in [10].

2.2. Review on faults

Electrical networks, machines and equipment are often subjected to various types of faults

while in operation. Current that flows through the distribution is the element with which

detection of faults can be done given the large increase in current flow during short circuits.

The fault inception also involves insulation and conducting path failures, which result in short

and open circuit of conductors. Faults could either be symmetrical or asymmetrical;

symmetrical faults being the ones with which all lines are affected simultaneously and with

asymmetrical, either one or two phases are affected [11]. With respect to overcurrent

protection on distribution systems, various types of currents such as overload current, short

circuit current and ground fault current are taken into consideration. Overload currents result

from a number of factors such as successive outages of power devices, insufficient available

7

component capacity and incorrect operation. With short circuit, the effects are not limited to

the region of exposure as they could influence the performance of remote equipment as well.

The effects of fault currents include mechanical stress, undesirable overheating, deterioration

of insulation, etc. [12]. Equipment that are frequently exposed to short circuit conditions are,

therefore, very likely to fail as a result of such stresses. In terms of reliability, the failure rate

of these equipment will increase with time. The majority of faults that occur on a power

system involve ground and occur between conductor and tower. Large grounded distribution

systems are subject to system faults near the stations that produce extremely high fault

currents. These high currents may inflict severe circuit breaker interrupting duties and stress

on system equipment. The reduction of ground current is rapid as the fault distance increases

from the source; therefore, the most severe faults are those within a few miles of the station

[13] .

2.3. Protection philosophy

Power distribution systems are subjected to constant disturbances caused by arbitrary load

changes, faults created by natural causes and at times due to equipment or operator failure

[14]. If a fault occurs in an element of the network, an automatic protective device is needed

to clear the fault in a fraction of seconds to keep the healthy section of the system in normal

operation and to isolate the faulty element as quickly as possible [15]. Faults that persist

longer on a system may cause damage to some vital sections due to fire that may result from

heavy short circuits and as a result, the system voltages may decrease causing loss of

synchronism of the system machinery and equipment.

The main objectives of distribution system protection are [11] [16]

To disconnect faulted lines, transformers, or other apparatus.

To limit service outages to the smallest possible segment of the system.

To minimize the duration of a fault on the distribution network.

To eliminate safety hazards as fast as possible.

To protect the consumers’ apparatus.

To protect the system from unnecessary service interruptions and disturbances.

Protective systems include relays, circuit breakers and transducers that function together to

isolate the faulty section from the healthy sections of system. Circuit breakers work to

8

disconnect the faulty section of the system when triggered to do so by the relay which

detects, locates a fault and sends a command to the disconnection circuit breaker [15]. The

relay constantly monitors electrical quantities of the system which differ during abnormal

conditions. Protective relays do not foresee or prevent the occurrence of a fault, they only

take action after a fault has occurred [17] .

2.3.1. Essential qualities of protection.

The protection arrangements for any network must take into account and adhere to the

following basic requirements:

a) Selectivity: also known as discrimination, refers to the ability to maintain continuity

of supply by disconnecting the minimum section of the network necessary to isolate

the fault and the remaining healthy sections left intact [15] [11] [18].

b) Reliability: refers to the ability of protection to operate correctly. It consists of two

elements being dependability and security, which are the certainty of a right operation

on the occurrence of faults and the ability to avoid incorrect operation during faults

respectively [11] [19]

c) Sensitivity: the protective relay should be sufficiently sensitive to the magnitude of

the current and to operate when the current just exceeds the pre-set detection

threshold known as the pick-up current [15].

d) Stability: the ability of the protective system to remain stable even when a large

current is flowing through its protective zone due to an external fault which does not

lie in its zone. The fault is cleared by the concerned circuit breaker [19].

e) Speed: a protective system should quickly isolate the faulty element as quick as

possible to maintain system stability and minimise damage to the equipment.

f) Economics: achieving maximum protection at the lowest cost as possible, which

usually should not be more than 5% of the total cost of the power system being

protected [18] [19].

2.4. Protective equipment

The ability of protective equipment to minimize damage when failures occur and reduce

service interruption is needed not only for economic reasons, but also for reliability of service

to the public in general. Distribution system overcurrent protection is generally accomplished

by use of protection transducers that include current transformers (CTs), voltage transformers

9

(VTs), circuit breakers and overcurrent relays [20] [21]. The protective equipment

collectively functions to detect and isolate only that particular part of the network responsible

for the fault.

a) Voltage transformers

According to Sleva [22], voltage transformers accurately reflect primary network voltage into

the secondary low-voltage winding and are connected in shunt with the distribution system

components. They are used to provide lower input signals to the protective relays and to

physically isolate the relays and other instruments from the high voltages of the network. The

VTs’ secondary windings standard voltage rating is 110 V line to line.

b) Current transformers

Current transformers step down high currents to low values that are suitable for the operation

of relays and other measuring instruments [23]. The standard current ratings of CTs used in

practice are 5 A or 1 A. They are designed to withstand fault currents as high as 50 times the

full load currents for a few seconds.

c) Circuit breakers

Circuit breakers (CBs) are fault-interrupting devices that enable or interrupt the flow of

current to power system components. They separate the faulty parts from the rest of the grid

safely and reliably to avoid endangering unaffected parts and equipment [24]. The circuit

breakers are not self-actuating; they do not have their own tripping intelligence hence they

are used in conjunction with relays and only function when a trip or close signal is received.

d) Relays

Protection relays form the most important part of the protection scheme, as a result, their

capability and functionality plays a significant role in how the protection scheme works [22].

They serve as decision-making elements triggered by current and voltage measurements

obtained from the voltage and current transformers. If the magnitudes of the incoming signal

are outside a pre-set threshold, the relays operate generally to either open or close electrical

contacts to initiate some further operations such as tripping of a circuit breaker [11] [15].

2.5. Protection scheme

It is usually difficult to define precisely the protection scheme that should be adopted for an

electricity distribution system, given the large number of valid alternatives for each situation.

However, any protection scheme should strike a balance between the technical and economic

aspects to avoid use of sophisticated protection devices for small machines or less important

10

system elements [11]. Protection schemes are designed to detect abnormal network

conditions, normally contingency-related, and initiate pre-planned, corrective measures to

mitigate the consequence of the abnormal condition and provide acceptable system

performance [25]. They include one or more relays of the same or different types. The

following are some of the most common protective schemes usually used in modern power

systems [15].

2.5.1. Transformer protection

When large transformers fail, there is a high possibility of consequential damage due to tank

rupture with an oil spill and fire that spreads to the surrounding area. To minimize the

damage, transformer sudden pressure and differential relays are employed to quickly detect

and isolate the faulty transformer [22]. Nowadays the transformer differential protection

resides in microprocessor-based relays, which execute signal processing, filtering, currents

compensation, and computation of differential and restraint currents. The relay providing

transformer differential protection is normally linked to the current transformers from both

transformer windings [26].

2.5.2. Differential protection

Differential protection is a method that functions when the vector difference of two or more

similar electrical magnitudes exceeds a predetermined value. The principle is founded on the

direct application of Kirchhoff's first law [27] [28]. An internal fault is identified by

comparing the electrical conditions at the terminals of the equipment to be protected in a

method. The main component of differential protection scheme is the differential relay that

operates when the phasor difference of similar electrical quantity exceeds a set value.

Differential protection is also referred to as unit protection since it is confined to protecting a

particular unit or equipment of a plant or substation [15].

2.5.3. Overcurrent Protection

Overcurrent protection is a method used for detecting excessive currents in a system and

cutting the delivery of further current into the system when overcurrent is detected [29]. Very

high current levels in electrical distribution systems are usually a result of faults on the

system. These high fault currents can be used to determine the presence of abnormalities on

the distribution network and operate protection devices, which can vary in design depending

on accuracy and complexity required [11]. Among the more common types of protection

11

devices are thermomagnetic switches, moulded case circuit breakers, fuses and overcurrent

relays. Overcurrent relays are the most common form of protection devices used to deal with

excessive currents on electricity distribution networks [11].

2.5.3.1. Time overcurrent protection

To guard against the possible failure of main protection devices in a distribution system, time

overcurrent protection relays usually function as backup protection to prevent the system

from experiencing catastrophic consequences [30].The relays and their variants represent the

largest installed base of protective equipment on any distribution systems and may be

considered as the backbone of any protection strategy. The microprocessor-based relays

possess algorithms for monitoring the system through current and voltage inputs from CTs

and VTs respectively [31] [32].

Overcurrent protection methods directly use the magnitude of the current as indicator that a

fault has occurred and trip if the measured current overcomes a certain threshold [33]. The

relays operate within a time, inversely proportional to the fault current. The fault current

magnitude near the source is higher and hence the shortest tripping time [8]. Due to the

impedance between the two points, the fault current magnitude at the far end of the line is

relatively less and results in longer tripping time. This brings the flexibility on operation of

local protection devices to clear first. According to IEEE Std. C37.112-1996, inverse time

overcurrent protection generally uses the following standard characteristic equation:

𝑡𝑜𝑝 =0.14

𝑃𝑆𝑀 0.02−1× 𝑇𝑀𝑆 (1)

where; 𝑃𝑆𝑀 =𝐼𝑟𝑒𝑙𝑎𝑦−𝑐𝑜𝑖𝑙

𝐼𝑝𝑖𝑐𝑘−𝑢𝑝, 𝑡𝑜𝑝 = time of operation, 𝑇𝑀𝑆 = time multiplier setting and

𝐼𝑝𝑖𝑐𝑘−𝑢𝑝 = pick up current .

The standard inverse time characteristic equation is usually used for line protection, very

inverse time characteristic equation used when the short-circuit current of close-up fault is

much greater than far end fault and the extremely inverse time characteristic equation suitable

for over-thermal protection caused by heavy load currents [34]. With inverse definite time

overcurrent IDMT relays, the pick-up current is taken as 1.2 to 2 times the full load current,

in steps of 0.05. The time dial setting (TMS) defines the operation time of the device for each

current value [32].

12

2.6. Protection coordination

With protective relays, the aim is to achieve coordination between the downstream and

upstream relays and circuit breakers [32] [21] [35]. The goal is to allow enough time for the

relay and breaker closest to the fault to clear the fault from the system before the backup

relay associated with the adjacent section to the source could initiate the opening of its circuit

breaker. The time interval allowed between two adjacent relays’ operation in order to achieve

correct discrimination between them is called the grading margin. Taking into consideration

factors such as circuit breaker operating time, relay overshoot time, contact gap together with

relay and CTs errors, the MiCOM relay user manual shows that a time grading margin of

400 𝑚𝑠 is used.

An undesirable occurrence known as over-trip often happens, a situation whereby a feeder

relay and supply-side relay both trip for the same feeder fault and is usually blamed on poor

relay coordination. The relay and breaker nearest to the point of fault must be able to see the

fault and operate before other relays in the system, so that healthy parts of the system will not

be interrupted [35]. One of the important coordination problems on distribution feeders is the

proper selection of protective devices for correct sequential operation. Protection of

distribution lines can be provided in many different ways. A survey of industry practices in

the protection of distribution circuits showed that a large percentage of utilities employ phase

and ground overcurrent protection for instantaneous tripping of temporary faults with time

delayed tripping for permanent faults [36].

2.7. Distributed generation

According to Borbely and Kreider [37], distributed generation is not entirely a new concept

because originally, all energy was produced and consumed at or near the process that

required it. In relation to them, a fireplace, wood stove, candle, alarm clock and car battery

are all forms of small scale, demand-sited “distributed” energy. Distributed generation is

therefore a new concept in the economics literature about electricity markets, but the idea

behind it is not new at all [38]. A number of terms have emerged to define power that comes

from sources other than from large, centrally dispatched generating units connected to a high-

voltage transmission system or network [39]. The term distributed generation can be used

interchangeably or considered synonymous with embedded generation and dispersed

generation, which are now barely used.

13

Motivated by environmental concerns, the necessity to diversify energy sources, energy

autonomy and efficiency, the penetration of distributed generation from renewable resources

like solar and wind is rapidly growing as the trend moves away from large centralized power

stations towards more meshed power distribution on the electricity grid [40]. Distributed

generation is commonly thought of as small-scale generation that is used onsite and/or

connected to a distribution network [39]. The type of technologies employed have historically

varied, but were generally limited to small engines or combustion turbines fuelled by diesel,

gasoline, or natural gas and also costly to run relative to grid supplied power [39]. More

recently, intermittent renewable resources such as solar, small hydro, and wind energy are

thought of as distributed generation being deployed to reduce overall emissions [41].

2.7.1. Distributed Generation Technology

This section considers the technology deployed in the generation of electrical power from the

sun (solar energy) as a typical example of distributed generation technology. The choice of

this source without any prejudice to other sources such as wind, micro-turbines, fuel cells,

geothermal and internal combustion engines is because of its relevance to the study.

With reference to [42], solar energy could be used to describe any phenomenon that is created

by solar sources and harnessed in the form of energy, directly or indirectly – from

photosynthesis to photovoltaics. According to Langston and Ding [43], the direct conversion

of sunlight into an electrical energy is achieved by a process called photovoltaic (photo =

light, voltaic = electrical potential) effect. Although solar energy is the most abundant energy

resource, only an infinitesimal fraction of the available solar energy is used [44]. Luo and Ye

[44], state that the amount of solar energy reaching the earth surface is so vast that in one

year it is about double as much as will ever be obtained from all of the planet’s non-

renewable resources of coal, oil, natural gas, and mined uranium combined. Therefore, solar

energy consequently appears to be an easy alternative next to conventional sources, like

electricity, coal and other fossil fuels.

2.7.2. Grid-tied Photovoltaic System

Photovoltaic (PV) energy has grown at an average annual rate of 60% in the last five years,

exceeding one third of the cumulative wind energy installed capacity, and is becoming a

significant part of the energy mix in some regions and power systems [45]. Several studies

[45] [46] [47] [48], show that it is driven by a reduction in the cost of PV modules,

environment friendliness, containing no rotating elements and it being an inexhaustible

14

source. Recently, energy generated from clean, efficient and environmentally friendly sources

has become one of the major challenges for engineers and scientists and therefore

photovoltaic (PV) application has been a subject of interest in research since it appears to be

one of the most efficient and effective solutions to this environmental problem [47].

Compared to stand-alone systems, grid-connected PV systems account for more than 99% of

the PV installed capacity. In grid-connected PV systems, the power generated by the PV plant

is uploaded to the grid for direct transmission, distribution, and consumption [49].

PV arrays are built up of combined series or parallel combinations of PV solar cells [48]. The

PV cells generate a direct current (DC) that is significantly dependant on the solar irradiance,

temperature, and voltage at the PV system terminals. This DC power is transformed and

interfaced to the grid via a PV inverter [45]. At a certain environmental condition, one

unique operating point exists to provide the PV generation system with maximum output

power. PV modules exhibit non-linear voltage-current characteristics, and the maximum

power point varies with the irradiation and temperature [47].

2.8. Impact of DG integration to the existing grid and protection scheme

Conventional distribution networks are generally arranged in radial topology and the

protection strategies in use assume single source in-feed and radial flow of current [6] [50].

Conti [51] shows that the introduction of DGs affects several operational aspects of AC

power systems including their protection philosophy. If the PV penetration is high, PV

systems can subject the grid to several negative impacts. The following paragraphs discuss

some of the main issues associated with the protection of AC distribution system embedding

DGs.

a) Varying fault level contribution

Penetration of DGs can influence the performance of a current-based protection scheme by

changing the fault current seen by the protective device [6] [52]. Nuisance tripping can result

if the current measured exceeds the relay’s pick-up setting. The current that flows into a fault

can come from three sources on a distribution network: namely, in-feeds from the

transmission system, in-feeds from distributed generation or in-feeds from loads with

induction motors. DG connection causes fault levels close to point of connection to increase,

which is caused by an additional fault level from the generator and can cause the overall fault

level to exceed the designed fault level of the distribution equipment.

15

The risks when fault levels are exceeded will cause damage and failure of the plant, with

consequent risk of injury to personnel and interruption to supplies. Different distributed

generation technologies come with varying fault level current contribution and provision

needs to be made for adequate system protection under all system configurations. The

situation may lead to protection discrimination problems and impose requirements for

switchgear and potentially other plant capacity upgrade and/or reinforcement.

b) Loss of mains

One of the most important network safety requirements when local generation is present at

the distribution level is the loss of mains (LOM) protection, which has been recognised as

one of the most challenging aspects relating to distributed generation [53]. Loss of mains (or

islanding) occurs when part of the public utility network or a portion of the distribution

system becomes electrically isolated from the remainder power system, yet continues to be

energized by DG connected to the isolated subsystem.

Due to opposite current flow from DG, the reach of a relay is shortened, leaving high

impedance faults undetected. If LOM is not detected, then the generator could remain

connected, causing a safety hazard within the network. When a utility breaker is opened, a

portion of the utility system remains energised while isolated from the remainder of the utility

system, resulting in injuries to the public and utility personnel [35] [36]. In history, up until

not long ago, loss of mains protection was put to use mainly to protect from the viewpoint of

ensuring personnel and public safety since there was little DG in the system.

c) Protection coordination disruption

Since the initiation of electrical systems, coordination tasks were performed to ensure that

protection systems would operate with the necessary reliability and security. DG connection

to a distribution feeder can also change power flow and fault current direction, consequently

disrupting the coordination amongst the protection devices as they are mostly non-directional

units. Protection coordination is employed for cases such as security against failure or

incorrect relay/device operation. Due to one source of power, the relays can be non-

directional since the current flows in one direction, but the injection of distributed generation

poses a threat to the coordination system because the generators also contribute to the total

fault current [54].

16

At the end of a distribution feeder protected by a standard time graded overcurrent protection

scheme, a problem of discrimination appears when additional generation is connected at the

far end of the feeder and thereby results in downstream protection seeing fault current. Also,

the connection of distributed generators to the distribution lines raises challenges for the

effective settings for the feeder protection since the protective system should as well be

designed with due regard for its own unreliability. That is installation of backup protective

systems to operate in case of primary equipment failure [22].

2.9. Mitigation methods to DG penetration issues.

As the penetration of DG increases, grid flexibility requirements also increase. The previous

sections have presented the status of and major obstacles to the establishment of DG within

utility systems. The following are some potential solutions that have been discussed and

recommendations directed towards injection of DG.

a) Modifying the existing system

When fault level exceeds the current design limits because of distributed generation

installation, upgrading the capability of existing equipment such as circuit breakers is an

option to enhance the fault level capabilities of the distribution system [55]. This method is

widely used throughout the world as a solution to the issue of increased fault levels. To avoid

control interactions among several DG units and their controllers, in large distribution

networks, some precautions such as keeping a minimum distance among DG plants and

coordinating controllers should be taken [56].

b) Utilizing Fault Current Limiters (UFLs)

In [55], it is discussed that UFLs are devices that limit the fault current by increasing the

system impedance. During faults, the resistances increase very quickly and sharply for high

fault currents consequently reducing the current to low and acceptable limits.

c) Limiting the Inverter Current

Under the fault conditions, blocking the DG inverter is an extensively used strategy in order

to protect the inverter from the high fault currents and reconnect them when normal operation

has been restored [55].

17

d) Adaptive Overcurrent Protection

One method that can be utilized is the directional overcurrent relay with dynamic settings.

This method needs fast and effective monitoring of system conditions. It will automatically

update relay settings based on prevailing system conditions [57].

e) Distance and Directional Comparison Protection

Even with obvious advantages of better and simpler downstream coordination, fixed reach

zone and relative immunity to the source impedance behind the protection relay, distance

protection was not considered at the radial feeders [57]. However, nowadays many utilities

are applying this protection at the distribution level due to distributed generation. Owing to

distributed generation penetration, the fault current becomes bi-directional, which brings

directionality issues to the protection scheme. Since distance protection is inherently

directional, it solves this problem and secondly, distance is not affected by the changing fault

current level due to changing source impedance compared with overcurrent protection.

18

3. Methodology

The chapter outlines the systematic approach deployed in this study to achieve objectives

discussed in the introduction. As discussed, the purpose of this work is to model and simulate

in real-time, a distribution system protection scheme with and without distributed generation.

For a successful execution of the research work, a systematic method to achieve the final

target was used.

3.1. Software selection

To accomplish the research work objectives, it is imperative that the chosen software has

suitable features to allow modelling of the electricity distribution network, the renewable

photovoltaic system and equivalent sources; it should also allow simulation of faults,

hardware-in-loop (HIL) connection and perform relay coordination. The softwares under

consideration that were checked for suitability were ETAP, PSCAD, RSCAD and Matlab.

Electrical Transient and Analysis Program (ETAP), by Operation Technology Incorporated,

is power systems design, modelling, analysis and planning software that can be used for short

circuit analysis, load flow study, transient study, user-defined dynamic model, modelling of

PV arrays and protective devices coordination. Power System Computer Aided Design

(PSCAD) is a time-domain simulation program predominantly dedicated to the study of

transients in power systems. Its main function is the power system simulation in frequency

and time domain. PSCAD can be used in power system and power electronic studies,

harmonic research of AC systems, transient torque analysis as well as the HVDC system and

commutation starting [58]. PSCAD also provides time domain graphical outputs.

RTDS is a parallel processing computation facility that incorporates both software and

hardware for digital simulation of electromagnetic transient programs [59]. It encompasses

two classes, being digital real-time simulation and hardware-in-loop (HIL) real-time

simulation [60] . RSCAD, which is a user-friendly graphical user interface, further enables

construction and power systems’ analysis by the user. With a digital real-time simulation, the

system modelled inside the simulator does not involve external interfacing whereas in the

HIL simulation, certain parts of the digital simulation are replaced with actual physical

components. RTDS comprises of accurate power system component models that represent

complex elements used for creating physical power systems. RTDS is hence selected for the

purpose of this research, due to its availability and suitable features for successful execution

19

of this work. Graphical results exported from the runtime module are plotted and displayed

on Matlab. Following is a procedural and deeper insight into how the research was carried

out.

3.2. Modelling of the distribution network in RSCAD

3.2.1. Draft programme

The electrical design of the distribution feeders is done by computing the various parameters

of the network such as resistance, inductance and capacitance. Resistance plays an important

role in determining losses since increasing the line current also increases the 𝐼2𝑅 losses. The

system model is then set up and parameters inserted in RSCAD/Draft, which enables the user

to create a system in a user-friendly graphic interface [61]. It comprises of a three-phase AC

supply input voltage with a 132 𝑘𝑉 R.M.S. voltage at 60 𝐻𝑧, which is further stepped down

to 66 𝑘𝑉 substation with each feeder further branching into several subsidiary 22 𝑘𝑉 and

11 𝑘𝑉 laterals that carry power close to the load points. In RSCAD library, all load model

types are available and the constant active and reactive power dynamic load models are used

as indicated in chapter 4.

All CT ratios corresponding to full load conditions are determined and set, voltages and

currents at the transformers' primary and secondary windings of the transformers, the systems

MVA ratings, base frequencies and source parameters are then checked and verified. The

model is compiled, generating the executable code required by the RTDS to run the

simulation. In case of any errors in the modelling stage, the compile process cannot be

completed due to the possibility of unreasonable data for the network model and control

elements, inconsistency as well as duplication of parameter and signal labels.

3.2.2. Runtime programme

After a successful compilation, the runtime module is then opened where available racks

show with red indicators on the right side of the GUI environment. On runtime, different

actions such as controls can be applied and their response observed and analysed by the aid of

graphs and meters. A direct communication is enabled between the RTDS simulator and a PC

with the modelled network. Firstly, the monitored variables and controlled elements are

selected, which are then used for setting different events in the power-system model such as

fault applications and switching. The compiled model is next loaded onto the simulator and

20

real-time simulation run. The system’s power, voltage and current outputs are monitored and

checked to see whether they produce desired results.

3.3. Protection set-up

Current transformers’ appropriate choice and sizing is the first important phase in overcurrent

protection settings [21] [62]. The selection of CT ratios is based on the system’s full load

current. Zones to be protected are then identified on the distribution system and for each zone

overcurrent relays configured. The relays’ pick-up currents are computed based on a chosen

plug setting value and set. The characteristic curve selected for all relays was the IEC

standard inverse curve.

Time dial setting (TDS) selection provides the necessary protection devices coordination [21]

[63], and is dependent on factors such as the maximum fault current, selected IDMT curve

type and the downstream circuit breakers’ operating time. For the most downstream breaker,

the TDS is set to a minimum value, simulations are then ran and coordination studies for all

relays carried out systematically from downstream breakers up to the breaker closest to the

source.

3.4. Protection relay testing

A hardware-in-loop connection was set up and verification of all software simulations results

was accomplished by substituting the networks’ software relays with the physical commercial

relays. Current and voltage signals were exported from the RTDS using OMICRON CMC

156 amplifier and Gigabit-transceiver Front Panel Interface (GTFPI). Combination of the

amplifier and the RTDS produces the actual conditions in which the relay will function

during a fault.

3.5. PV generation system design

In order to simulate the behaviour of a solar panel, a fully functional photovoltaic array

consisting of 150 modules in series and 300 modules in parallel was built and developed in

RSCAD. For varying temperature and irradiation inputs, verification of all desired outputs

from the PV model was carried out to understand the impact of the change in weather

conditions. The PV array's operating point is maintained at the maximum power and output

by using a fractional open circuit voltage based maximum power point trackers (MPPT). The

tracker uses the fact that the PV array voltage corresponding to the maximum power displays

21

a linear dependence relating to array open circuit voltage for varying temperature and

irradiance.

3.6. Grid-tied inverter model development

For a grid-tied photovoltaic generation system, three-phase inverters are used to convert the

DC output into a three-phase AC power [64]. A photovoltaic inverter was configured and

coupled with the distribution network. The essential interface to bridge the large and small

time-step simulation portions is created by transferring voltage and current information

between them. Voltage information from the large time-step side of the simulation is

transferred to the small time-step side and current information from the small time-step side

is brought to the large time step side. Using this interface technique allowed the necessary

power electronics application device to be accurately modelled and simulated with the PV

array model. The main network is then connected to the small time-step sub-network through

three single-phase interface transformers.

3.7. Stand-alone grid tied PV system

The inverter was connected to transformers’ low voltage side and the high voltage to the grid

represented by a constant 11 𝑘𝑉 voltage source. The PV generation system was then

connected to the utility network using the 11 𝑘𝑉 busbar as the point of common coupling.

Steady state results and performance outputs of the whole distribution network and PV

inverter system were then monitored and verified. The PV system fault current contribution

impacts on the capacity of protection components in the distribution network was

investigated and using dual simplex method, relay coordination was achieved. A study was

done on the modelled system to support the theoretical expectations regarding possible

outcomes. The point of common coupling was changed to the 66 𝑘𝑉 busbar to determine PV

penetration impacts on different sections of the network.

3.8. Optimal relay coordination

Tap settings such as the current and time dial setting must be determined for relay

coordination. Full load and minimum fault currents assist in determining all relays’ current

settings [3] [65]. For the time multiplier determination of all the overcurrent relays protecting

the distribution system, the sum of all relays’ operating times are optimized using an

optimization technique [65]. Techniques under consideration were generic algorithm, partial

22

differentiation approach, particle swarm optimization and dual simplex method, of which the

dual simplex method was selected.

The regular simplex method was modified and developed by Lemke into dual simplex

method to solve linear programming problems (LPP). The technique results in the solution to

becoming feasible and optimal at some stage through an iterative computation [65].

Assuming that the OC relay’s TMS and plug setting are specified, its time of operation can be

calculated for a known fault current using the following mathematical equation (5) above.

Below is the algorithm of the dual simplex method used to solve the maximization problem

[65] [66].

a) Start.

b) Convert the problem into maximization problem.

c) Convert all the constraints into ≤ type.

d) Rewrite the functions into standard form by adding surplus variable, which are basic

variables.

e) Form the Dual Simplex table.

f) Find 𝐶𝑗 − ∑(𝐶𝑗 ∗ 𝑎𝑖𝑗)

If any 𝐶𝑗 − ∑(𝐶𝑗 ∗ 𝑎𝑖𝑗) element becomes non-negative, go to step (j).

If all the elements in this row become non-positive and if all the elements in

the RHS column are non-negative, go to step (i).

If at least one element in RHS is negative, go to step (g).

g) Form a dual simplex table after identifying the key column, key row and pivot

element.

h) Go to step (f).

i) Print results

j) Stop.

3.9. PV impacts mitigation methods

When high PV penetration levels, the grid is subjected to several negative impacts hence the

grid flexibility requirements need to increase. The status of and major obstacles to the

establishment of DG within utility systems was then presented and potential solutions

discussed. Implementations have been made to address the issue of reviewing present

protection settings for a reliable protection coordination establishment. Protection method

23

against islanding was implemented to provide basic detection of faults that will separate the

DG from the utility during an islanded mode [67] [68].

3.10. Recommendation for future works

Fields of future investigation were identified and described at the end of the research work.

As mentioned in the literature, distributed generation will be a trend in the near future hence

there will be a high volume distributed generations in the distribution systems. The

implemented anti-islanding technique is not an optimal choice for high-density PV systems

and will have some limitations in future; therefore, the work was carried out to enable the use

of its outcomes for further build up and refining for future research.

24

4. Modelling and real-time simulation

4.1. Test distribution system configuration

Real-time protective relaying is an effective and widely used technique that has been used for

decades by power distribution utilities for protection [31]. The real-time simulator employed

in this work is the RTDS simulator by RTDS technologies. The RSCAD is a graphical user

interface with wide model libraries permitting an extensive range of electrical system

architectures and components designs. Shown in Figure 1 is the modified test distribution

system’s single line and block diagram in which the proposed overcurrent protection method

is tested. For purposes of this research, a radial line configuration was considered because it

is the most commonly encountered distribution network configuration and ideal for

illustrating the time overcurrent protection scheme [31], with the full model shown in the

appendix Figure 42. The input voltage is a three-phase AC supply with an R.M.S. voltage of

132 kV at 60 Hz, which is further stepped down to 66 kV. Each feeder which emanates from

the 66 kV substation branches further into several subsidiary 11 kV and 22 kV feeders to

carry power close to the load points where a transformer further reduces the voltage from 11

kV to 380 V for customers.

Figure 1: Single line diagram of the modelled distribution system

Current transformers’ appropriate choice and sizing is the first important phase in overcurrent

protection settings [62]. The CT ratios and overcurrent relays ae configured for each

protection zone. The network comprises of four main protection zones denoted by circuit

breakers labelled CB-1, CB-2, CB-3 and CB-4, of which the corresponding protection

equipment should be set up to ensure adequate protection coordination. The system

comprises of diverse consumer characteristics, ranging from high consumption households

during holidays, to those that are more active at night, the industrial consumers working 8-

25

hour shift and those who constantly work. Because of the diversity of consumers, the

distribution system is loaded diversely on a daily, monthly and annual basis. Table 1 presents

the loads and the system parameters.

Table 1: Transformers, load and source parameters

Transformer Ratio MVA Load Data

XFM-1 132/66 kV 50 Load P (MW) Q (MVAR) S (MVA)

XFM-2 66/11 kV 10 1 18.5 7.5 20

XFM-3 11/0.38 kV 0.5 2 9 4 10

XFM-4 66/22 kV 20 3 0.23 0.09 0.25

Voltage Source Parameters 4 0.23 0.09 0.25

MVA 120 5 9 4 10

Frequency 50 Hz 6 9 4 10

Voltage 132 kV

In the radial distribution system shown, there is only one path, which connects end-users with

the source. This path is one-way, hence there is a unidirectional flow of current from the

source, which means only the source provides electric power to end-users. If there is a power

outage, the end-users lose electric power completely. Protective relays identify unwanted

conditions within the network, and then trip the circuit breakers to isolate the faulted area

before any damage or interference with the operation of the distribution network as a whole

[69].

4.2. System full load conditions

The section concisely presents findings and results obtained from simulations of the modelled

distribution system. To begin with, all model equipment parameters are set and the system is

run on RSCAD. Shown in Table 2 are bus voltages, line voltages and currents as seen from

the power and current transformers for input to the overcurrent relays.

Table 2: Voltages and Currents measured on the distribution system.

Parameter

Voltage

Value VT secondary

Voltage

Parameter

Current

Value CT Secondary

Current

Bus-1 132 kV 109.8 V IB-1 0.185 kA 1.088 A

Bus-2 10.98 kV 109.7 V IB-2 0.091 kA 0.8741 A

Bus-3 0.379 kV 109.3 V IB-3 0.752 kA 0.752 A

Bus-4 21.89 kV 108.9 V IB-4 0.304 kA 1.042 A

Bus-5 65.96 kV

26

In the no fault scenario, normal RMS currents flow through the CTs and there is no

disturbance in the currents. The current pick-up value for a breaker to generate a trip signal

should be at least 1.2 times of the normal full load RMS current [70]. The current setting is

selected to be above the maximum short time rated current of the circuit involved and since

all relays have hysteresis in their current settings, the setting must be sufficiently high to

allow the relay to reset when the rated current of the circuit is being carried.

Figure 2: System R.M.S Currents

Figure 3: Distribution system RMS voltages

Shown in Figure 2 and Figure 3 are full load current and bus voltages of the distribution

system modelled at no fault. Figure 2 shows the system RMS currents as seen from the CTs

secondary windings. It can be seen that at no fault operating conditions, there is a constant

current flowing from the source to the dynamic loads in the different radial system laterals.

The voltage levels read are as initially set for the system design in section 4.1, with a small

deviation due to the system impedance and loads’ reactive power.

27

4.2.1. Fault and breaker logic control

To verify the fault levels in the system to different branches of the network, faults are applied

on the distribution feeders. For convenience, ability to control the fault type, fault location

and closing of the circuit breakers during runtime is necessary. Shown in Figure 4 is the fault

logic which enables fault application and changing in the runtime interface. The logic is

advantageous in provision of a more efficient way of testing as opposed to switching between

the draft and runtime interface to implement changes to the faults on the system. It allows

activation of fault using a push button, selection of and alteration between the different

combinations of line to ground faults via a dial switch as presented in Table 7 that shows the

binary and dialing outputs along with the corresponding fault type.

Figure 4: Fault and circuit breaker logic

For the design, all the three phases in the distribution lines of the system have to be protected

even if a fault occurs on either single line, double lines or all the three phases. A single logic

input is used to open and close the circuit breaker model in the simulator. The circuit breaker

model is designed to respond to separate open and close commands by means of an SR flip-

flop component. In the system, once the relay issues a trip command to the breaker logic

shown in Figure 4, the circuit breaker receives the signal to open; which can be closed by

means of a ‘close’ push button in runtime.

4.2.2. Relay logic control

The time overcurrent relay forms the vital fragment of the protection scheme, hence its

functionality takes up a significant role in operating as a decision making component in the

protection scheme. For operation, the relay is activated by the voltage and current

transformers’ voltage and currents measurements respectively. If an abnormal condition

exists, the relay then decides if it is large enough to endanger the system followed by an

appropriate preventative action to protect the system. Shown in Figure 5 is the multi-

functional overcurrent relay that is suitable for providing the protection function on

distribution system lines with the (51/67P) overcurrent element (PTOC) enabled. The

28

secondary phase voltages and currents are fed into the six inputs of the relay. These voltage

and current phases are from the secondary side of the voltage transformer and current

transformer respectively. The RMS quantities are calculated and a comparator functions to

determine whether the magnitude of the measured current is greater than the set point value.

If any phase current or residual current is greater than the set point value the comparator

output causes the start and info signals to become active then the trip signal becomes active

after some time delay.

Figure 5: Software overcurrent relay used

The external block serves as a user controller to lock or unlock the relay which is necessary

for relay maloperation simulation.

4.3. Software relays’ simulation:

4.3.1. Testing software Relay-3

References

This section replicates the system in RSCAD where the manifestation of faults on the

distribution system is closely observed for various faults location and types. The downstream

circuit breaker CB-3 is set to function under the control of relay-3, which enables the breaker

to open the circuit when required. It is also necessary that relay-3 be coordinated with

upstream relay-2 for desired system protection discrimination. Inverse time relays are

adjusted by selecting time dial and current settings.

On setting up the protection system, relay-3 current setting of 1.25 is chosen and the time dial

setting set to minimum for the fastest possible fault clearing time, enabling CB-3 to clear the

29

high current fault in a very short time. From Figure 2, it can be seen that the RMS current is

found to be 0.752 𝐴, giving a pick-up current of 0.940 𝐴.

Figure 6: Relay-3 operating for a fault on 380 V busbar

Figure 6 shows the analysis of events that take place when a fault on the 380 V busbar is

applied. A fault is applied at 0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠, the fault current rises and is seen across the current

transformers as 1096 Amps due to 1000:1 CT ratio. Owing to a trip signal received from

relay-3, the CB-3 opens, clearing the hazard from the system. Taking the time multiplier

setting for the relay to be the minimum 0.025, the time of operation is calculated theoretically

as 0.0230 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 for the relay. From the software simulation, the circuit breaker opens at

0.4233 𝑠𝑒𝑐𝑜𝑛𝑑𝑠, giving a time of operation of 0.0229 𝑠𝑒𝑐𝑜𝑛𝑑𝑠, hence it can be concluded

that the theoretical calculated time of operation is approximately equal to the time of

operation obtained from the graph.

With protective relays, the goal is to allow enough time for the relay and breaker closest to

the fault to clear the fault from the system before the backup relay associated with the

adjacent section to the source opens its circuit breaker. The time interval allowed between

two adjacent relays’ operation in order to achieve correct discrimination between them is

called the grading margin. Taking into consideration factors such as circuit breaker operating

time, relay overshoot time, contact gap together with relay and CTs errors, a time grading

margin of 400 𝑚𝑠 is used, as recited from the MiCOM relay user manual.

4.3.2. Time setting of Relay-2:

Relay-3 and relay-2 coordination is achieved by evaluating the maximum fault current seen

by relay-2 for a fault at protection zone-3, denoted by circuit breaker CB-3. On adding a

0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 grading margin, the time of operation for relay-2 on failure of relay-3 will be

0.4231 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 .

30

Figure 7: Relay-2 testing for a fault at zone-3 (380V busbar)

Figure 7 shows the expected outcome of relay-2 time of operation for a fault at zone-3, which

is found to be 0.4269 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. To determine the time dial setting for relay-2, fault-3 current

is transposed onto the 66 𝑘𝑉 line and calculated to be 6310 𝐴𝑚𝑝𝑠. Taking the time of

operation calculated above, the multiplier setting is calculated as 0.25.

4.3.3. Testing software Relay-2:

Using a 0.25 multiplier setting on relay-2, a fault is applied and the time of operation then

verified with the runtime graphs. With a fault current of 1.04 𝑘𝐴 on the 11 𝑘𝑉 bus, the time

of operation is calculated to be 0.2395 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 while Figure 8 gives the time of operation

of 0.0244 𝑠𝑒𝑐𝑜𝑛𝑑𝑠.

Figure 8: Relay-2 operating for a fault at zone-2 (11 kV busbar)

For relay-2, the pick-up current is calculated to be 1.14 𝐴. The 626 kA fault current is seen

from the CT secondary windings as 1.04 kA due to the transformer XFM-2 and 100:1 CT

ratio. Taking the TMS calculated above, the computed time of operation is 0.2395 𝑠𝑒𝑐𝑜𝑛𝑑𝑠

which is equivalent to 0.2538 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 obtain from Figure 8 simulation results.

31

4.3.4. Time setting of Relay-1:

From Figure 9, relay-1 time of operation for fault-2 is found to be 0.7197 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. As

expected, breaker-1 opens at 1.120 𝑠𝑒𝑐𝑜𝑛𝑑s, which is approximately 0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 later than

the time breaker-2 should have opened, confirming proper relay coordination on the

distribution system.

Figure 9: Relay-1 operating for a fault at zone-2 (11 kV busbar)

As seen, Figure 9 confirms and verifies the expected outcome of relay-1 time of operation for

a fault at zone-2. As carried out previously, relay-1 time multiplier setting is calculated and

set up so it operates for a fault at protection zone-2. Following are calculations carried out in

determining the time dial setting for relay-1. Fault-2 current transposed onto the 132 kV line

is calculated to be 52.17 kA and is seen across the relay coils as 260 A due to 200: 1 CT

ratio. Taking the time of operation calculated above using margin grading, the time multiplier

setting for relay-1 is calculated to be 0.52 and therefore set to 0.55.

4.3.5. Testing software Relay-1:

With all relay-1 parameters and time multiplier setting determined and set, fault-1 is applied

and the time of operation calculated and verified with the runtime graphs. Figure 2 shows a

132 kV distribution line full load RMS CT secondary current of 1.088 𝐴𝑚𝑝𝑠; hence, relay-1

pick-up current value is calculated to be 1.36 𝐴𝑚𝑝𝑠. A 26 kA fault current is seen in the

relay coils as 130 𝐴𝑚𝑝𝑠 due to the CT ratio. Taking the time multiplier setting for relay-1 as

0.55 calculated above, the time of operation is 0.7780 𝑠𝑒𝑐𝑜𝑛𝑑𝑠.

32

Figure 10: Relay-1 operating for a fault at zone-1(132 kV busbar)

The time of operation of the relay-1 is calculated to be 0.7997 s from Figure 10. This

confirms the time of operation for the relay, which is equivalent to the manually calculated

value 0.7780 𝑠𝑒𝑐𝑜𝑛𝑑𝑠.

4.3.6. Testing software Relay-4

Relay-4 is downstream on the 22 kV distribution system lateral and is tested for a fault

occurring at protection zone-4. The time multiplier setting for the relay is also set to a

possible minimum and the manual calculation of the time operation carried out and verified.

Relay-4 pick-up current is set to 0.9511 𝐴𝑚𝑝𝑠. Using the minimum 0.025 time multiplier

setting for relay-4, the time of operation is calculated to be 0.03 𝑠𝑒𝑐𝑜𝑛𝑑𝑠.

Figure 11: Relay-4 operating for a fault on the 22 kV busbar

As observed in Figure 11, the time of operation obtained experimentally, 0.0330 𝑠𝑒𝑐𝑜𝑛𝑑𝑠,

confirms the previously calculated relay-4 time of operation of 0.03 𝑠𝑒𝑐𝑜𝑛𝑑𝑠.

33

4.4. Protection Coordination results

Overcurrent protection scheme is implemented for coordination of relay of interest with

upstream relays, which refers to the supply side or higher voltage side of the system. For a

radial network, the coordination is done for the feeder protection with upstream protection. If

the first and second breakers from the fault zone both fail to operate, the circuit breaker closer

to the source should open [70]. Therefore, for a fault on bus 3, relay-3 is set to operate faster

than relay-2 by a time-delayed approach thus defining primary and backup protection zones.

The design approach is mentioned in the previous sections.

Figure 12 and Figure 13 display simulation results showing proper relay coordination for the

distribution system under study. To simulate the proceedings of events that occur in case of a

failure to send or receive the trip signal resulting in a failure of the relay, relays of interest are

disabled by deactivating the trip signal that governs the breaker so it does not open for a fault

on the protection zone. Following is the simulation of relay-2 malfunction; the trip signal

governing the 66 kV breaker is deactivated, disabling it to open for a fault on the line.

Simulation studies are done by applying a fault and observing the upstream active relay’s

response.

Figure 12: Relay-2 failing to operate

34

From Figure 12, verification of the 132 𝑘𝑉 upstream breaker is done, which opens as a

response to a fault occurring at zone-2. As expected, breaker 1 opens at 1.15 𝑠𝑒𝑐𝑜𝑛𝑑𝑠, which

is approximately 0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 later than the time breaker-2 should have opened. Since the

circuit breaker closest to the source opens, there is no current flow to other parts of the

distribution system.

4.4.1. Testing coordination of relays 3, 2 and 1

In this section, relay-3 and relay-2 are disabled to verify coordination between them. A fault

is applied at zone-3, followed by observations as to whether the fault is cleared by the

upstream breaker closest to the source. Shown in Figure 13 are the graphs obtained when

relay-3 and relay-2 fail to operate.

Figure 13: Failure of relay-3 and relay-2 to operate

As can be deduced from Figure 13, the fault on the 0.380 𝑘𝑉 busbar was activated

at 0.50 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. The 132 kV breaker opens at 2.235 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 since the 66 kV breaker

failed to open, giving 1.735 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 as the time of operation. This is as desired since

distribution system philosophy is that the upstream breaker will open slower than the 66 kV

and 0.38 kV downstream breakers.

35

4.4.2. Testing coordination of relays 3 and 2

Figure 14: Operation of relay-2 for a fault at protection zone 3

Using 0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠.grading margin, the time of operation for relay-2 on failure of relay-3 to

operate is calculated to be 0.4231 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. Calculated from Figure 14, the time of operation

of the relay is 0.4269 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. The simulations results show that the time of operation for

relay-2 is approximately equal to the manually calculated one, which goes in agreement with

theory that relay-2 will operate 0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 later than relay-3 would have operated.

4.4.3. Testing coordination of relays 4 and 1

Figure 15: Relay-4 failing to operate

36

As seen in Figure 15, the graphs depict results pertaining to relay-4 failure, which is disabled

and a fault applied at protection zone-4. The relay responds in 0.9499 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 by sending a

trip signal to open the upstream circuit breaker and clear the fault, thus confirming

coordination between relay-1 and relay-4.

37

5. Experimentation and Verification

5.1. Hardware-in-loop simulation

Verification of all results obtained from the software simulations is achieved by substituting

the software relays on the network with the hardware relays. This section considers the

performance of hardware relays in a hardware-in-loop connection with the software

distribution model. As depicted in the appendix Figure 43, Gigabit-transceiver analogue

output (GTAO) and GPC processor cards are configured in RSCAD for the connection

between the RTDS simulator, external protection and control devices replacing the software

components. For exportation of the current signals from the RTDS, OMICRON CMC 156

amplifier and Gigabit-transceiver Front Panel Interface (GTFPI) are used. During a fault, the

relay generates a trip signal which is sent back via GTFPI to the RTDS, which causes

disconnection of a corresponding circuit-breaker in the distribution network model.

The relay input is connected to the RTDS analogue/digital output which is connected to the

power amplifier as shown in Figure 16. The analogue/digital output of the relay is then

connected with the analogue digital input of RTDS. The signal level analogue output voltages

sent from the rack in real-time are converted to correctly-scaled currents and voltages for

input to amplifier. In this way, the real time simulation can be used to drive the relay with the

same power level currents and voltages it would experience in the field [71]. From the

amplifier, these currents are fed to the relay which produces a trip signal when tripping

conditions are fulfilled.

Figure 16: System hardware-in-loop connection

The relay receives current and voltage signals from the secondary side of instrument

transformers of the system simulated on the host PC through digital to analogue conversion

38

and necessary amplification stages. One at a time, the software relays are replaced with the

MiCOM P122 and simulations run to verify results obtained while using the software relays.

Figure 17 to Figure 20 show hardware relays 1 to 4 operating in the distribution system

through a hardware-in-loop connection and same settings used for software relays are in the

similar manner are set for the hardware relays.

5.1.1. Testing Hardware Relay-3

Figure 17: Hardware Overcurrent Relay 3 operating

5.1.2. Testing Hardware Relay-2

Figure 18: Hardware Overcurrent Relay 2 operating

5.1.3. Testing Hardware Relay-1

Figure 19: Hardware Overcurrent Relay 1 operating

39

5.1.4. Testing Hardware Relay-4

Figure 20: Hardware Overcurrent Relay 4 operating

A comparative study for protection coordination of overcurrent relays is presented for

different configurations using both software and hardware relays. From above figures, a

conclusion that verification using hardware relays was accomplished can be drawn. All the

relays were tested for line-line and 3-phase to ground faults.

Table 3: Comparison of operating time from software and hardware relays

Relays Theoretical

value

Software

relay

Hardware

relay

% Difference

Relay 1 0.778 s 0.7990 s 0.821 s 2.69

Relay 2 0.2395 s 0.2438 s 0.273 s 1.79

Relay 3 0.0230 s 0.0229 s 0.035 s 0.44

Relay 4 0.0321 s 0.0330 s 0.038 s 2.80

Shown in Table 3 is the relays’ time of operation obtained from the software and hardware

simulations. The results are compared with the theoretical values obtained from manual

calculations which as expected are approximately equal, with percentage deviations below

3%. As seen in the results, there is a relatively higher time of operation for hardware as

compared to using software relays. The discrepancies in the time of response of the relays are

influenced by the adjusted time multiplier setting when using hardware relays since they are

standard setting so values could not be used exactly as manually calculated and the possibility

of delays from the voltage and current amplification stage. It was also due to the fact that

during the hardware simulations, settings were modified slightly with regards to increasing

fault duration on the distribution system while using hardware relays to allow sufficient time

to pick up.

40

5.2. Grid-connected PV system

A complete RSCAD simulation of the grid connected PV system with the MPPT algorithm,

power active and reactive control of the grid-side inverter has been carried out with the

following parameters tabulated in Table 4. The system is composed of 255 𝑊 PV modules,

Maximum Power Point Tracking (MPPT) modified fractional open circuit voltage tracker, the

full bridge inverter circuit with filter and step-up transformer, synchronizing system and the

connected load. Grid inverter is the core part of PV system connected to the grid. It has the

same grid frequency and its power factor is approximately close to unity.

Table 4: Parameters of Mitsubishi Electric Photovoltaic Module

Parameter Value

STC 1000 𝑊/𝑚2, 25𝑜𝐶

Maximum power rating 𝑃𝑚𝑎𝑥 255 W

Short-circuit current 𝐼𝑠𝑐 8.89 A

Open-circuit voltage 𝑉𝑜𝑐 37.8 V

Maximum power voltage 𝑉𝑚𝑝 31.2 V

Maximum power current 𝐼𝑚𝑝 8.18 A

Normal operating cell temperature 45.7𝑜𝐶

Temperature coefficient

𝐼𝑠𝑐 0.056 %/𝑜𝐶

𝑉𝑜𝑐 −0.350%/𝑜𝐶

𝑃𝑚𝑎𝑥 −0.450%/𝑜𝐶

A PV module with the specifications outlined in Table 4 is used. 150 series connected

modules and 300 parallel-connected modules are used to form the PV array. As shown in

Table 5, for the reference solar intensity of 1000 𝑊/𝑚2 and 25𝑜𝐶 , the expected PV array

output voltage and power at STC will be 37.8 𝑉 × 150 = 5.67 𝑘𝑉, and 255 𝑊 × 45000 =

11.47 𝑀𝑊 respectively.

Figure 21: RSCAD model of grid connected PV system

41

A typical grid connected PV system is considered for simulation to study the impacts of

connecting PV to the grid. The configuration of the PV model simulated for purposes of this

study is shown in Figure 21. The network consists of a 10.2 𝑀𝑊 PV generation system,

which is integrated to the grid by means of a DC/AC inverter, a step-up transformer and the

11 𝑘𝑉 bus as the point of common coupling. The inverter, presented in the appendix Figure

46, forms the core of the grid connected PV system and is responsible for the quality of

power injected into the grid.

As stated in the literature, the solar I-V characteristic is highly nonlinear and changes with

irradiation and temperature. In general, there is a unique point on the I-V curve called the

maximum power point (MPP) at which the PV array operates at maximum efficiency [72].

Maximum power point trackers (MPPT) are used to maintain the PV array's operating point

at the MPP to maximize its output. In this work, a fractional open circuit voltage based MPPT

for photovoltaic array is used. The fractional open circuit voltage based MPPT utilizes the

fact that the PV array voltage corresponding to the maximum power exhibits a linear

dependence with respect to array open circuit voltage for different irradiation and temperature

levels. The minor setback for this method is the power loss since the PV array is disconnected

from the load after regular intervals for the sampling of the array voltage.

5.2.1. Inverter model development

Grid connected PV generator systems always utilise a connection to the electrical network via

a suitable inverter because a PV module delivers only DC power. The RTDS is capable of

simulating sub-networks containing IGBTs and other devices modelled as ideal switches,

which is generally referred to as voltage source converter (VSC). Each VSC circuit is solved

as a sub-network and can be interfaced to the main network solution, which is solved with a

normal time-step size of 50µs whereas the VSC circuit is solved with a time-step of 1.4

to 2.5 𝜇𝑠. The essential interface to bridge the large and small time-step portions of the

simulation is created by transferring voltage and current information between them. Voltage

information from the large time-step side of the simulation is transferred to the small time-

step side and current information from the small time-step side is brought to the large time

step side. The node voltage in the large time step side is transferred to the small time-step

side, driving a voltage source and the current in the small time-step side similarly transferred

back to the large time step side, driving a current source branch.

42

Figure 22: Large and small time-step simulation interface

The PV array is connected to the DC bus, and then to the AC grid via a DC/AC inverter. In

the simulation, the firing pulses applied on the switching of the DC-AC inverters are

determined by a comparison between a Controlled Sinusoidal Reference (CSR) and a

triangular wave provided by the firing pulse generator component [73] , with Figure 47

presenting its control circuit. The inverter output voltage goes through a filtering stage and

then is stepped up into a higher voltage level by three single-phase interface transformers that

connect the main network and small time-step sub-network to the grid voltage at the point of

common coupling. The grid equivalent is modelled as three-phase impedance based on the

short circuit MVA in series with an ideal three-phase AC voltage source. The power is fed

from PV system and the utility to the distribution network consisting of four step-down

transformers. Tabulated in Table 5 are the PV system model parameters and the expected

outputs at standard testing conditions (STC).

Table 5: PV system parameters and expected outputs at STC

Series modules 150

Parallel modules 300

Total number of modules 45000

Maximum power rating 𝑃𝑚𝑎𝑥 255 W

PV array Output power 11.47 MW

PV array Output voltage 5.670 kV

43

5.2.2. Steady-state operation

At the outset of the simulations, the PV model is run and the steady state voltages and

currents observed at different temperature and insolation. The simulated system is first

checked under STC (1000 𝑊/𝑚2 and 25𝑜𝐶). Figure 23 illustrates the corresponding

waveforms of electric characteristics for solar PV plant obtained from runtime in RTDS

simulation.

Figure 23: Characteristic curves of the PV array at STC

The curves have been generated by running the simulation and the results are very close to

the manufacturer’s curves, which imply that the PV panel has been modelled to adequate

accuracy for fulfilling the requirement of this research. Figure 24 shows the PV array output

voltage, the magnitude is found as expected shown in Table 5, corresponding to the chosen

PV system parameters. With increase in irradiation, the solar panel output increases but with

increase in ambient temperature, there is a relatively sharper reduction in the open circuit

voltage (Voc) of the panel than the slight increase in the short circuit current. Hence, the

reduction in Voc contributes to the reduction in overall panel power output.

Figure 24: PV Array output voltage

44

Power supplied by the PV array into the inverter is 10.2 𝑀𝑊 and the inverter outputs

10.18 𝑀𝑊 with a 0.8 power factor. The maximum output power from the array under the

stated conditions is relatively higher than the inverter output due to the estimation of the

maximum power point and power losses in harmonics at the inverter output. A comparison

has been made between the calculated theoretical power and the power obtained from RTDS

simulation in respect of maximum insolation and maximum temperature. Apart from this, in

real time, since the insolation and temperature variation occurs simultaneously, the rise in

insolation results in increase in panel power output, but the rise in temperature exhibits a

different behaviour and the net effect of rise in temperature is lowering the solar PV panel

power output. The three-phase inverter converts the dc voltage to AC for grid interfacing and

supply to the local load. The inverter output voltage is then filtered to remove the harmonic

components, and then stepped up to match the voltage of the point of common coupling.

Figure 25 shows the transformer output voltage that is connected to the 11 𝑘𝑉 busbar.

Figure 25: Stand-alone PV System output RMS voltage

The PV system output voltage is shown in Figure 25. The output power being fed to the grid

has a small percentage dip with respect to the actual power generated by the solar PV array

and this suppression of output power can be attributed to the losses in the converter and

inverter. First, the simulations are carried out without inserting the DG into the network and

all active and reactive power, voltage and current measurements are done. The simulation is

then run with DG implemented into the network and the similar measurements done.

45

5.2.2.1 PV penetration at 11 kV

Figure 26: Single line diagram of the grid-tied photovoltaic system

The system chosen is the parallel operation of one PV generation renewable energy and a

conventional grid represented as a constant voltage source behind short circuit impedance.

The equivalent single diagram circuit of the system is shown in Figure 26, with PV

generation, grid supply and rest of the network.

Figure 27: Grid-connected PV system voltages

46

Figure 28: Grid-connected PV system CTs secondary RMS current

Figure 27 and Figure 28 show the system voltages and CTs secondary RMS currents 1 to 4

respectively after the PV system connection to the distribution network. As can be seen,

current through CT-1 and CT-2 secondary windings is seen to have doubled and quadrupled

respectively, and this can be accounted to the power being injected into the distribution

system and backflow of current resulting from the addition of the PV generation system on

the 11 𝑘𝑉 busbar. The conditions met and results thus obtained are in accordance with the

engineering principles in that the generated voltage of the incoming generator and the

frequency of generated voltage connected in parallel to a busbar are equal to the busbar

voltage and frequency.

5.2.2.2 PV penetration at 66 kV

Similarly, simulations are also carried out by varying the PV penetration level. The following

results show the performance of the grid-connected PV system when point of common

coupling is changed to the 66 𝑘𝑉 busbar. As the PV penetration varies, the distribution

feeders affected by the backflow of power change. The degree of impacts of DG addition to

distribution systems is further illustrated in the following figures.

47

Figure 29: PV System RMS voltage

Figure 29 shows PV system output voltage before connection to the 66 𝑘𝑉 busbar as the new

point of common coupling. The PV system frequ ency and voltage are equal to the grid and

busbar voltage and frequency.

Figure 30: System RMS currents

According to [74], the reverse power flow is the main cause of current rise in distribution

feeders. Figure 30 shows a summary of RMS currents observed on the network after the point

of common coupling is changed to the 66 𝑘𝑉 busbar. Due to the PV generation system, CT-1

secondary RMS current as seen in Figure 30 is 16.9 𝐴𝑚𝑝𝑠, which is higher than the

1.05 𝐴𝑚𝑝𝑠 read in Figure 2 section 4.2 without the PV system. As the PV penetration

increases, the real power supplied by the grid decreases, but the reactive power burden still

remains wholly with the grid. The voltage rises at PCC when power is injected into the

distribution system. PV inverters are capable of absorbing reactive power to mitigate voltage

rise, just as they are capable of injecting reactive power in case of voltage sags [75].

48

5.2 Overcurrent Protection set-up

As stated earlier in the literature, injection of distributed generation to the conventional radial

distribution networks poses challenges concerning the already existing system protection

scheme. As soon as the fault takes place, it is sensed by both primary and backup protection.

The primary protection is the first to operate, as its operating time is less than that of the

backup relay. For the simple radial feeder shown under consideration, relay-3 should be the

first to operate for fault F-3, followed by back-up relay-2 if it fails to operate. The challenge

of coordination of overcurrent relays in distribution systems can be quantified as an

optimization linear programming problem (LPP), whereby using dual simplex method, the

operating times of the relays, for near end fault can be minimized [65], i.e.

min 𝑧 = ∑ 𝑡𝑖𝑚𝑖=1 (2)

where 𝑡𝑖 indicates the operating time of the primary relay at i, for near end fault. The

objective is achieved under the following constraints:

A. Coordination criteria

𝑡𝑏𝑖 − 𝑡𝑖 ≥ ∆𝑡 (3)

Where 𝑡𝑏𝑖 is the operating time of the backup relay for a fault at ‘i' and ∆𝑡 is the

coordination time interval (CTI).

B. Relay operating time boundaries

𝑡𝑖𝑚𝑖𝑛 ≤ 𝑡𝑖 ≤ 𝑡𝑖𝑚𝑎𝑥 (4)

Where 𝑡𝑖𝑚𝑖𝑛 is the minimum operating time of relay and 𝑡𝑖𝑚𝑎𝑥 is the maximum

operating time for the same relay.

C. Relay characteristics

Inverse definite minimum time (IDMT) characteristics are assumed to be same for all

relays and plug setting taken as 1.

𝑡𝑜𝑝 =0.14

𝑃𝑆𝑀0.02−1× 𝑇𝑀𝑆 (5)

Where 𝑡𝑜𝑝 is the time of operation, 𝑃𝑆𝑀 is the plug setting multiplier and 𝑇𝑀𝑆 is the

time multiplier setting. Taking

𝑎 =0.14

𝑃𝑆𝑀0.02−1 (6)

and substituting it into the objective equation (2), it becomes

min 𝑧 = ∑ 𝑎𝑖(𝑇𝑀𝑆)𝑖𝑚

𝑖=1 (7)

𝑃𝑆𝑀 =𝐹𝑎𝑢𝑙𝑡 𝐶𝑢𝑟𝑟𝑒𝑛𝑡

𝐶𝑇−𝑟𝑎𝑡𝑖𝑜 (8)

49

The dual simplex method algorithm used to solve the maximization problem is outlined in the

methodology. Considering relay-1, relay-2 and relay-3, the minimum operating time for each

relay is considered as 0.02 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 and the CTI is taken as 0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. The maximum

fault currents at F-1, F-2 and F-3 are 52 𝑘𝐴, 500 𝑘𝐴 and 930 𝑘𝐴 respectively, with the CT

ratios being set at 400:1, 500:1 and 1000:1 for relay 1, 2 and 3 respectively. Due to

transformers XFM-1, XFM-2 and XFM-3 winding ratios, the fault currents seen by the circuit

breakers CB-1, CB-2 and the relays’ coils are less than the actual currents measured at the

faulted points. The PSM and a values are calculated using equation (6) and (8), and are

tabulated as shown in Table 6. PSM sample calculation for fault-3 current seen by relay-2

gives 𝐼_(3 − 2) = 5354 𝐴 and 𝑃𝑆𝑀 = 10.7.

Table 6: PSM and a values

Fault point and

current

Relays

Relay-1 Relay-2 Relay-3

F-1

52 kA

PSM 65 - -

a 1.6 - -

F-2

500 kA

PSM 104 166.7 -

a 1.43 1.29 -

F-3

930 kA

PSM - 10.7 930

a - 2.88 0.956

Adding slack variables and converting it into a maximization problem, the problem

formulation is carried out using dual-simplex method as follows:

Max 𝑦 = −1.6𝑋1 − 1.29𝑋2 − 0.956𝑋3

Subject to: −1.43𝑋1 + 1.290𝑋2 + 𝑆1 = −0.4

−2.88𝑋2 + 0.956𝑋3 + 𝑆2 = −0.4

−1.6𝑋1 + 𝑆3 = −0.02

−1.29𝑋2 + 𝑆4 = −0.02

−0.956𝑋3 + 𝑆5 = −0.02

The optimum solution is obtained in four basic iterations outlined in the appendix Table 8-11.

At the end of fourth iteration, all the values in the last right-hand column are non-negative

and the optimal solution is reached. The TMS values to be used are therefore 0.41 for relay-

50

1, 0.145 for relay-2 and 0.021 for relay-3. Due to the standard MiCOM P122 relay TMS

settings, the values shall be taken as 0.45, 0.15 and 0.025 for relay 1, 2 and 3 respectively.

5.2.2 Experimentation results:

Of interest initially, is the adequate sequential relay operation. The calculated results are

verified with an experimental model where the optimum relay TMS settings calculated in the

previous section are set on and model simulations run. A positive correlation between the

calculated results and proper relay coordination indicated by graphs from the simulations will

give credence to the dual simplex method employed.

Figure 31: Relay-3 testing

Figure 31 shows results for relay-3 TMS validation. As expected, it can be seen from the plot

that when a fault occurs, a trip signal is sent which consequently opens the circuit breaker

immediately on the signal detection. The relay’s time of operation was computed to

be 0.023 𝑠𝑒𝑐𝑜𝑛𝑑𝑠.

Figure 32: Relay-2 testing

51

In the same manner, the plot in Figure 32 shows successful operation of relay-2 with the

TMS of 0.15 obtained using the dual simplex method. Computed from the graphs, relay-2

time of operation on fault F-2 occurrence is 0.72 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. For fault F-3, i.e. when relay-3

fails, relay-2 opens the circuit breaker in1.12 𝑠𝑒𝑐𝑜𝑛𝑑𝑠, which is 0.4 𝑠𝑒𝑐𝑜𝑛𝑑𝑠 later than

relay-3 would have opened, thus honouring the coordination criteria presented by equation

(3).

Figure 33: Testing relay-1

In Figure 33, relay-1 time of operation while using 0.45 TMS value obtained above is

computed to be 0.805 𝑠𝑒𝑐𝑜𝑛𝑑𝑠. From the simulations indicated in Figure 31 to Figure 33,

relays 3, 2 and 1 times of operation are computed and they adhere to the constraints set in the

dual simplex algorithm while solving the linear programming problem. This shows the

optimum solution of time multiplier setting of relays was attained using dual simplex for the

relays considered. The results also indicate that appropriate relay coordination for the

distribution system under study was achieved. Taking into consideration relay-4 with a fault

current of 95 𝑘𝐴 and using the optimisation technique to compute the time multiplier setting:

𝑃𝑆𝑀 =95 𝑘𝐴

500∶1= 190, giving 𝑎 = 1.26

Min 𝑦 = 1.26𝑋1, subject to 1.26𝑋1 ≥ 0.02

Applying the similar dual simplex method as performed above gives a TMS of 0.015

Figure 34: Relay-4 testing results

52

Figure 34 gives the operation time of relay-4 as 0.088 𝑠𝑒𝑐𝑜𝑛𝑑𝑠, and further simulations

show that when relay-4 fails, relay-1 operates in 0.94 𝑠𝑒𝑐𝑜𝑛𝑑𝑠, indicating that accurate and

optimum solutions were achieved for the overall system relays’ coordination.

5.3 Islanding Protection

Islanding of a grid connected distributed generation (DG) occurs when a section of the utility

system containing such generators is disconnected from the main utility, but the independent

DGs continue to energize the utility lines in the isolated section (termed as an island) [76].

Unintended islanding is a concern primarily because it poses a hazard to utility and customer

equipment, maintenance personnel, and the general public; hence, anti-islanding protection is

essential to ensure that grid-tied energy harvesting systems cut their connection to the grid

when the grid itself loses power. The identification of power loss in the grid can be

challenging, requiring an approach able to find the right balance between sensitivity to

normal fluctuations in the grid and responsiveness to grid power failure. Many anti-islanding

techniques have been proposed to prevent islanding caused by DGs [77] [78]. They are either

passive techniques that monitor the voltage and frequency or active methods where the output

of the reactive power is varied to help destabilize the island and accelerate the dissolving of

the system to extinguish the island.

5.3.2 Passive techniques

a) Under/Over voltage and Under/Over frequency

Under/Over voltage and Under/Over frequency relaying are effective loss of grid (LOG)

techniques for small DGs. According to [67], they usually provide an acceptable level of

protection but may fail to operate if the change of load associated with LOG can be

compensated by the DGs' control system, keeping voltage and frequency more or less stable.

b) Rate of change of frequency (ROCOF)

ROCOF relays monitor the voltage waveform and trips the CB when the measured rate of

change of frequency exceeds a pre-set level for longer than a set period [68]. The settings are

chosen such that the relay operates only for fluctuations associated with islanding and with

the DG operating independently from the utility, but not for those fluctuations governed by

utility time constants [67].

53

5.3.3 Active techniques

a) Reactive power export error detection

A level of reactive power flow in the inter-tie between the DG and the utility is generated by

DG control system interfaced with the reactive power export error detection relay. This level

can only be maintained when the utility generation is connected. There should be a

considerable reduction on the DG disturbance during normal operation and has to, after

islanding, be sufficient to drive the frequency outside its threshold limits [67] [79]. The relay

operates when there is an error between the setting and the actual reactive power being

exported for a period greater than the set value.

b) System fault level monitoring

In this scheme, system fault level is monitored by sensing the short circuit current and

reduction in supply voltage when a shunt inductor is connected across the supply by using

point-on-wave triggered, thyristor switches. It is a faster acting protection technique. Its

tripping is dependent on the power system's source impedance close to the inter-tie. Firing of

the thyristor occurs just before a current zero [80]. This causes a short pulse of current to flow

in the inductor and a voltage glitch. The tripping decision depends on the comparison of the

measured system fault level with that corresponding to a network fed from the utility

generation [67].

5.3.4 Islanding operation

The difficulties with islanded DG have been outlined in the literature review. To prevent

island operation, the protection system has to detect islands quickly and reliably. Much

literature is available concerning protection of distributed generation. Many publications

demonstrate the same problems and issues, but solutions are rare.

Figure 35: A radial feeder with PV generation integrated

Figure 35 shows a simple single line diagram of the distribution feeder modelled with a fault

F-1 applied nearer to the source. As soon as the fault takes place, it is sensed by relay R1

54

which then trips and opens the circuit breaker CB-1 shown in Figure 26. Due to the location

of the fault, the source is cut from and does not supply the grid; however, the PV generation

system denoted by DG is still connected to the rest of the network, resulting in an island.

Figure 36: Distribution system currents due to islanding

Figure 36 indicates network RMS currents after experiencing fault F-1. The utility protection

system detected the overcurrent and opened circuit breaker CB-1, and as can be seen, there is

almost no phase RMS current I1 flowing in the 132 𝑘𝑉 feeder, 0.9 × 10−6 𝐴𝑚𝑝𝑠. Although

the source is disconnected from the rest of the network, the PV system still supplies the grid

and hence current I2, I3 and I4 flows. In the context of power supply to loads, there is current

flowing but the condition is unfavourable as critical situations can occur due to the part of the

utility network which is islanded and the connected integrated PV unit.

Figure 37: Protection against islanding layout

An example of a simple protection technique against islanding is shown in Figure 37. The

overcurrent protection relays R1 and R2 provide basic detection of faults that will separate

the DG from the utility by opening circuit breaker CB-6 if fault F-1 or F-2 occurs. The circuit

breaker is controlled by a trip signal from either R1 or R2.

55

Figure 38: Circuit breaker logic

Shown in Figure 38 is the logic used to control the breaker. As can be seen, the logic circuit

has both trip1 and trip2 signals as inputs. In the system, once either relay R1 or R2 has issued

a trip command to the breaker logic shown, the circuit breaker receives the signal from the S-

R latch to open and it remains open until manually closed by pressing of a ‘close’ push button

in runtime. The circuit breaker model is designed to respond to separate open and close

commands by means of an SR flip-flop component. When F-1 occurs, relay R1 sends a trip

signal that governs both circuit breaker CB-1 and CB-6, disconnecting the source and

distributed generation from the main utility network as shown in Figure 39. For fault F-2

shown in Figure 41, a similar phenomenon takes place where CB-2 and CB-6 open, leaving

the R4 feeder branch connected to the source and load being supplied. In the event of fault F-

3 or F-4 occurring, trip signals are sent from R3 and R4 respectively to open corresponding

circuit breakers, leaving the source and PV generation system connected to the utility.

Figure 39: Circuit breaker 1 and 6 opening on fault F-1 occurrence

56

Figure 40: System line current during islanding protection

Figure 40 shows the distribution system line currents after fault F-1 occurs. Due to the open

circuit breakers disconnecting both the source and PV system from the grid, there is almost

no current flowing since the system is not getting any voltage supply.

Figure 41: Circuit breaker 1 and 6 opening on fault F-2 occurrence

For safety concerns, a successful implementation of anti-islanding assists against unexpected

live wires, which repair crews may be faced with during a fault or maintenance. End-user

equipment is also guarded against damage since customer equipment could theoretically be

damaged if operating parameters differ greatly from the normal.

57

6 Conclusion

Apart from fossil fuels that power thermal power plants, alternative fuels are under

consideration due to the rising electrical energy demand. This lead to the development of

innovative electrical power distribution systems where photovoltaic generation systems

supply some of the energy and centralized generation produces some. Major concerns

relating to penetration of PV systems included poor relay coordination, sympathetic tripping

and unintentional islands that result from continuous power flow from the dispersed

generation systems although the grid is disconnected during a fault. This work involved

modelling and development of an overcurrent protection scheme for a modified test

distribution network with and without dispersed generation. A study of the electricity

distribution systems was done and the system model developed. All the relevant theory prior

to the technical design and all results obtained thus far in terms of the design procedure

progress were discussed. This research work presented the experimental results of the

protection scheme using both software and hardware relays on RTDS. Control logic functions

for system faults and circuit breakers were implemented and tested on all protection zones

and the obtained results demonstrated correct operation. The expected relay operation defined

in the theory was verified, with the higher fault currents showing a reduction in relay time of

operation. The results were discussed and analyzed to verify existing theories under steady

and faulted operating conditions.

Integration of all parts of the work with physical components to obtain a system where the

complete protection philosophy was implemented. The RTDS enables hardware closed-loop

testing with the distribution system digital model. Results were compared with the theoretical

values obtained from manual calculations, which as expected were approximately equal with

percentage deviations below 3%. The results show a relatively higher time of operation for

hardware relays as compared to using software relays. The adjusted time multiplier setting

when using hardware relays and the possibility of delays from the amplification stage

influenced the discrepancies in the relay time of response since physical relays use a certain

TMS values range and standard settings so some values could not be used exactly as

manually calculated. Coordination of the protection relays was tested on the distribution

system and implemented using the software and hardware relays in verification of the relay

coordinated sequential operation during faults. The test system was analysed without the

presence of DG, which served as a basis with which subsequent results were compared to.

58

The research focus was also on the study of DG impacts on the fault current and voltage of

the overall protection scheme for the distribution systems. Described were the PV model

fundamentals, I-V characteristic and its output dependency on temperature and solar

irradiance. Simulations in chapter 5 indicated that PV systems affect fault current and voltage

in the distribution systems by changing the direction and magnitude of the fault current in the

network and these impacts differ depending on the penetration location. Due to the impacts,

the radial distribution systems original protection schemes did not hold anymore hence the

need for an adaptive protection scheme to accommodate DG penetration. Chapter 2 discussed

a number of mitigation methods to the impacts on radial distribution systems overcurrent

protection. The investigation concluded that the inverter-interfaced PV systems’ fault current

contribution is relatively low but it does however disturb the present protection coordination,

and suggested a method for modifying the TMS to meet the requirements of correct relay

discrimination. Some of the methods were found to be rather complicated and not efficient.

To address mainly the issue of relay coordination, which is considered a highly constrained

optimization problem, a dual simplex method optimization algorithm was implemented for

time multiplier settings computation and the objective achieved. Lastly, after the simulation

and ensuring correct and efficient sequential relay operation, the issue of unintentional

islanding had to be investigated and solved. The next step involved developing an

interconnection protection method to protect against the issue of islanding. A modified

adaptive protection scheme’s functionality was successfully implemented and verified on the

interconnected distribution network. For huge volumes of PV units, the control logic used

would have to be modified to accommodate the network under consideration.

Future recommendations

With future inclinations and within the electric power delivery field, wide-ranging view is

that dispersed generation is anticipated to play a significant role in future energy systems.

There is a global increasing demand for alternative renewable energy sources and its storage,

which is fast gaining importance in today’s developments. Further recommendations would

be to study extensively the distributed generation protection and stability analysis along with

islanding and implementation of more effective anti-islanding techniques. Moreover, studies

can be carried out on protection with distinct emphasis on operation and re-synchronization

of islanded parts of distribution systems. Since there is a lot of exciting research in the field

of renewable energy and control systems, the future work should also be on future design of

distribution networks for a simplified DGs interconnection.

59

References

[1] A. Evans and V. Strezov, “A Sustainability Assessment of Electricity Generation,” in 2010

International Conference on Biosciences, Mexico, 2010.

[2] Z. Li, “Natural gas for generation: a solution or a problem?,” IEEE Power and Energy Magazine,

vol. 3, no. 4, pp. 16 - 21, 2005.

[3] N. K. Choudhary, . R. S. Mohanty and . K. R. Singh, “Protection Coordination of Over Current

Relays in distribution system with DG and superconducting fault current limiter,” in 2014

Eighteenth National Power Systems Conference, Guwahati, 2014.

[4] J. Franco, . L. Ochoa and . R. Romero, “AC OPF for Smart Distribution Networks: An Efficient

and Robust Quadratic Approach,” IEEE Transactions on Smart Grid, no. 99, pp. 1-1, 2017.

[5] D. Chengdi, L. Peng, W. Chengshan, W. Zhiying, Y. Dawei, Z. Jin and L. Zheng, “A design and

implementation of FPGA-based real-time simulator for distribution system with DG integration,”

in 2016 China International Conference on Electricity Distribution (CICED), Xi'an, 2016.

[6] M. Monadi, A. M. Zamanic, J. Ignacio , C. Alvaro and L. Pedro, “Protection of AC and DC

distribution systems Embedding distributed energy resources: A comparative review and

analysis,” Renewable and Sustainable Energy Reviews, vol. 51, pp. 1578-1593, 2015.

[7] F. Coffele, C. Booth and A. Dyśko, “An Adaptive Overcurrent Protection Scheme for

Distribution Networks,” IEEE Transactions On Power Delivery, vol. 30, no. 2, pp. 561-568,

2015.

[8] Rakesh Sinha and A. Zaidi, “Protection of Distribution Systems with Significant Penetration of

Distributed Generation,” in Power Generation System and Renewable Energy Technologies,

Karachi, 2015.

[9] G. Electric, “Distribution System Feeder Overcurrent Protection,” GE Power Management,

Canada.

[10] F. B. Costa, A. Monti and S. C. Paiva, “Overcurrent Protection in Distribution Systems with

Distributed Generation based on the Real-Time Boundary Wavelet Transform,” IEEE

Transactions on Power delivery, vol. 32, no. 1, pp. 462-473, 2017.

[11] J. M. Gers and E. J. Holmes, Protection of electricity distribution networks, London: The

Institution of Electrical Engineers, 1998.

[12] S. Behzadirafi and H. Salehfar, “Preventive Maintenance Scheduling Based on Short Circuit and

Overload Currents,” IEEE Transactions on Smart Grids, vol. 6, no. 4, pp. 1740-1747, 2015.

[13] M. Lantz, “Fault-Resistance Effect on Ground Fault Current,” AIEE Transactions, vol. 72, 1953.

[14] S. H. Horowitz and A. G. Phadke, Power System Relaying, England: Research Studies Press

LTD., 1995.

[15] B. Ram and N. D. Vishwakarma, Power System Protection and Switchgear, New Delhi: McGraw

Hill Education Private Limited, 2011.

60

[16] L. J. Blackburn, Protective Relaying Principles and Applications, New York: Marcel Dekker Inc,

1998.

[17] IEEE, “Reducing Outages Through Improved Protection, Monitoring, Diagnostics, and

Autorestoration in Transmission Substations—(69 kV and Above),” IEEE Transactions On

Power Delivery, vol. 31, no. 3, pp. 1327-1334, 2016.

[18] B. Ravindranath and M. Chander, Power system protection and switchgear, New Delhi: New

Age International Publishers, 1995.

[19] T. Guillod, F. Krismer and J. W. Kolar, “Protection of MV Converters in the Grid: The Case of

MV/LV Solid-State Transformers,” IEEE Journal of Emerging and Selected Topics in Power

Electronics, vol. 5, no. 1, pp. 393 - 408, 2017.

[20] Y. G. Paithankar and . S. R. Bhide, Fundamentals of Power System Protection, India: PHI

Learning, 2011.

[21] A. Onal, “Relay coordination in the protection of radially connected power system network,”

Nigerian Journal of Technology , vol. 31, pp. 58-62, 2012.

[22] A. F. Sleva, Protective Relay Principles, Boca Raton: Taylor & Francis Group, 2009.

[23] B. Ram and P. N. Vishwakarma, Power System Protection and Switchgear, India: McGraw-Hill

Education Private Limited, 2011.

[24] B. Feizifar and O. Usta, “Condition monitoring of circuit breakers: Current status and future

trends,” in 2017 IEEE International Conference on Environment and Electrical Engineering and

2017 IEEE Industrial and Commercial Power Systems Europe, Milan, 2017.

[25] J. McCalley, O. Oluwaseyi, V. Krishnan and R. Dai , “System Protection Schemes: Limitations,

Risks, and Management,” Power Systems Engineering Research Center, Texas, 2010.

[26] L. Sevov, U. Khan and Z. Zhang, “Enhancing power transformer differential protection to

improve security and dependability,” IEEE Transactions on Industry Applications, vol. 53, no. 3,

pp. 2642 - 2649, 2017.

[27] Y. Yin, Z. Zhang and Y. Fu, “A bus differential protection scheme using real-time synchrophasor

data,” in 2017 IEEE 30th Canadian Conference on Electrical and Computer Engineering

(CCECE), Windsor, 2017.

[28] C. Edward, O. I. Okoro and T. M. Khan, Concise Higher Electrical Engineering, Cape Town:

Juta and Company Ltd, 2008.

[29] Areva, Network Protection and Automation Guide, Barcelona: Cayfosa, 2005.

[30] C. So, K. Li, K. Lai and K. Fung, “Application of genetic algorithm for overcurrent relay

coordination,” in Sixth International Conference on Developments in Power System Protection,

Nottingham, 1997.

[31] A. Sinclair, D. Finney, D. Martin and P. Sharma, “Distance Protection in Distribution Systems:

How It Assists With Integrating Distributed Resources,” IEEE TRANSACTIONS ON INDUSTRY

APPLICATIONS, vol. 50, no. 3, pp. 2186-2196, 2014.

61

[32] P. Mahat, Z. Chen, B. Bak-Jensen and C. . L. Bak, “A Simple Adaptive Overcurrent Protection

of Distribution Systems With Distributed Generation,” IEEE Transaction on Smart Grid, vol. 2,

no. 3, pp. 428-437, 2011.

[33] N. Gaur and P. Gaur, “Automation in Power Distribution Systems,” Journal of Engineering

Research and Studies, vol. 3, no. 2, pp. 82-84, 2012.

[34] V. Prasad, . P. Rao and . S. Rao, “Coordination of directional relays without generating all

circuits,” IEEE Transactions on Power Delivery, vol. 6, no. 2, pp. 584 - 590, 1991.

[35] D. A. Ko, G. Burt, S. Galloway, C. Booth and J. Mcdonald, “UK distribution system protection

issues,” IET Generation, Transmission & Distribution, vol. 1, no. 4, pp. 679 - 687, 2007.

[36] D. Jones, Analysis and Protection of Electrical Power Systems, Great Britain: Pitman, 1996.

[37] A.-M. Borbely and J. F. Kreider, Distributed Generation: The Power Paradigm for the New

Millennium, Boca Raton: CRC Press, 2001.

[38] A. K. Singh and S. K. Parida, “Need of distributed generation for sustainable development in

coming future,” in 2012 IEEE International Conference on Power Electronics, Drives and

Energy Systems, Bengaluru, 2012.

[39] P. M. Sotkiewicz and I. J. M. Vignolo, “Nodal pricing for distribution networks: efficient pricing

for efficiency enhancing DG,” IEEE Transactions on Power Systems, vol. 21, no. 2, pp. 1013 -

1014, 2006.

[40] T. Wang, D. O’Neill and H. Kamath, “Dynamic Control and Optimization of Distributed Energy

Resources in a Microgrid,” IEEE Transactions on Smart Grid, vol. 6, no. 6, pp. 2884 - 2894,

2015.

[41] H. Jiayi, J. Chuanwen and X. Rong, “A review on distributed energy resources and MicroGrid,”

Renewable and Sustainable Energy Reviews, vol. 12, no. 9, pp. 2472-2483, 2008.

[42] T. Bradford, Solar revolution: the economic transformation of the global energy industry,

Cambridge: MIT Press, 2006.

[43] C. A. Langston and G. K. C. Ding, Sustainable Practices in the Built Environment, Oxford:

Routledge, 2008.

[44] F. L. Luo and H. Ye, Renewable Energy Systems: advanced conversion technologies and

applications, Boca Raton: CRC Press, 2013.

[45] S. Kouro, J. I. Leon, D. Vinnikov and L. G. Franquelo, “Grid-Connected Photovoltaic Systems:

An Overview of Recent Research and Emerging PV Converter Technology,” IEEE Industrial

Electronics Magazine, vol. 9, no. 1, pp. 47 - 61, 2015.

[46] L. Stoyanov and N. Cholakova, “Simulation of the shading in photovoltaic systems,” in 2017

15th International Conference on Electrical Machines, Drives and Power Systems, Bulgaria,

2017.

[47] R.-J. Wai and W.-H. Wang, “Grid-Connected Photovoltaic Generation System,” IEEE

Transactions on Circuits and Systems, vol. 55, no. 3, pp. 953-964, 2008.

62

[48] I. H. Altas and A. Sharaf, “A Photovoltaic Array Simulation Model for Matlab-Simulink GUI

Environment,” in 2007 International Conference on Clean Electrical Power, Capri, 2007.

[49] J. Sreedevi, N. Ashwin and N. Raju, “A Study on Grid Connected PV system,” in 2016 National

Power Systems Conference (NPSC), Bhubaneswar, 2016.

[50] P. T. Manditereza and R. Bansal, “Renewable distributed generation : The hidden challenges – A

review from the protection perspective,” Renewable and Sustainable Energy Reviews, vol. 58, p.

1457–1465, 2016.

[51] S. Conti, “Analysis of distribution network protection issues in presence of dispersed

generation,” Electric Power Systems Research, vol. 79, no. 1, pp. 49-56, 2009.

[52] H. A.Abdel-Ghany, M. Ahmed , N. I. Elkalashy and E. M. Rashad, “Optimizing DG penetration

in distribution networks concerning protection schemes and technical impact,” Electric Power

Systems Research, vol. 128, pp. 113-122, 2015.

[53] D. M. Laverty, . R. J. Best and D. J. Morrow , “Loss-of-mains protection system by application

of phasor measurement unit technology with experimentally assessed threshold settings,” IET

Generation, Transmission & Distribution, vol. 9, no. 2, pp. 146-153, 2015.

[54] H. Zayandehroodi, . A. Mohamed, H. Shareef and M. Mohammadjafari, “Impact of distributed

generations on power system,” International Journal of the Physical Sciences, vol. 6, no. 16, pp.

3999-4007, 2011.

[55] T. M. Masaud and R. D. Mistry, “Fault current contribution of Renewable Distributed

Generation: An overview and key issues,” in 2016 IEEE Conference on Technologies for

Sustainability, Phoenix, 2016.

[56] N. K. Roy and H. R. Pota, “Current Status and Issues of Concern for the Integration of

Distributed Generation Into Electricity Networks,” IEEE Systems Journal, vol. 9, no. 3, pp. 933 -

944, 2015.

[57] Y. Pan, I. Voloh and W. Ren, “Protection issues and solutions for protecting feeder with

distributed generation,” in 2013 66th Annual Conference for Protective Relay Engineers, College

Station, 2013.

[58] H. Teng, C. Liu, M. Han, S. Ma and X. Guo, “IEEE9 Buses System Simulation and Modeling in

PSCAD,” in 2010 Asia-Pacific Power and Energy Engineering Conference, Chengdu, 2010.

[59] K. G. Ravikumar, N. N. Schulz and A. K. Srivastava, “Distributed simulation of power systems

using real-time digital simulator,” in 2009 IEEE/PES Power Systems Conference and Exposition,

Seattle, 2009.

[60] M. D. O. Faruque, T. Strasser, G. Lauss, V. Jalili-Marandi, P. Forsyth, C. Dufour, V. Dinavahi,

A. Monti, P. Kotsampopoulos, J. A. Martinez, K. Strunz, M. Saeedifard, X. Wang, D. Shearer

and M. Paolone, “Real-Time Simulation Technologies for Power Systems Design, Testing, and

Analysis,” IEEE Power and Energy Technology Systems Journal, vol. 2, no. 2, pp. 63 - 73, 2015.

[61] U. Rudež, P. Osredkar and R. Mihalič, “Overcurrent protection-relay testing with Real-Time

Digital Simulator Hardware,” in Elektrotehniski Vestnik, Slovenia, 2012.

[62] D. Rayworth and M. A. Rahim, “Configuration and Setting of Protection Relays or Numeric

63

Relays,” in The IEE Seminar on Advances in Power Protection: Learning the Lessons from

Major Disturbances, London, 2006.

[63] T. T. Trung, S.-J. Ahn and J.-H. Choi, “Real Time Simulation of Distribution System with

Distributed Energy Resources,” Journal of Clean Energy Technologies , vol. 3, no. 1, pp. 57-61,

2015.

[64] M. G. Villalva, J. R. l Gazoli and E. R. Filho, “Comprehensive Approach to Modeling and

Simulation of Photovoltaic Arrays,” IEEE Transactions on Power Electronics, vol. 24, no. 5, pp.

1198 - 1208, 2009.

[65] P. P. Bedekar, S. R. Bhide and V. S. Kale, “Optimum Coordination of Overcurrent Relays in

Distribution System Using Dual Simplex Method,” in International Conference on Emerging

Trends in Engineering & Technology, Nagpur, 2009.

[66] A. Gupta, . G. O. Swathika and S. Hemamalini, “Optimum Coordination of Overcurrent Relays

in Distribution Systems Using Big-M and Dual Simplex Methods,” in International Conference

on Computational Intelligence and Communication Networks, Jabalpur, 2015.

[67] S. Chowdhury, S. Chowdhury, C. F. Ten and P. Crossley, “Islanding protection of distribution

systems with distributed generators — A comprehensive survey report,” in 2008 IEEE Power

and Energy Society General Meeting - Conversion and Delivery of Electrical Energy in the 21st

Century, Pittsburgh, 2008.

[68] X. Ding and P. A. Crossley, “Islanding detection for distributed generation,” Journal of

Electrical Engineering and Technology, vol. 2, no. 1, pp. 19-28, 2007.

[69] A. J. Onal, “Relay Coordination in The Protection Of Radially-Connected Power System,”

Nigerian Journal of Technology, vol. 31, no. 1, pp. 58-62, 2012.

[70] A. Kamal, S. Sankar and R. Soundarapandian, “Optimal Over Current Relay Coordination of a

Real Time Distribution System with Embedded Renewable Generation,” Indian Journal of

Science and Technology, vol. 7, no. 7, pp. 149-155, 2014.

[71] P. G. McLaren, R. Kuffei, R. Wierck, J. Giesbrecht and L. Arendt , “A Real Time Digital

Simulator For Testing Relays,” Transactions on Power Delivery, vol. 7, no. 1, pp. 207-213,

1992.

[72] J. Ahmad, “A fractional open circuit voltage based maximum power point tracker for

photovoltaic arrays,” in International Conference on Software Technology and Engineering, San

Juan, 2010.

[73] G. G. Pinheiro, J. M. d. C. Filho and . D. B. Bonatto, “Modeling, simulation and comparison

analysis of an installed photovoltaic system using RTDS,” in IEEE International Conference on

Industry Applications, Brazil, 2016.

[74] H. Mortazavi, H. Mehrjerdi, M. Saad and D. Asber, “A Monitoring Technique for Reversed

Power Flow Detection With High PV Penetration Level,” IEEE Transactions on Smart Grid, vol.

6, no. 5, pp. 2221 - 2232, 2015.

[75] J. Sreedevi, N. Ashwin and N. M. i Raju, “A study on grid connected PV system,” in 2016

National Power Systems Conference, Bhubaneswar, 2016.

64

[76] V. John, Z. Ye and A. Kolwalkar, “Investigation of anti-islanding protection of power converter

based distributed generators using frequency domain analysis,” IEEE Transactions on Power

Electronics, vol. 19, no. 5, pp. 1177 - 1183, 2004.

[77] R. J. Bravo, S. A. Robles and . E. Muljadi, “Assessing solar PV inverters' anti-islanding

protection,” in IEEE 40th Photovoltaic Specialist Conference, Denver, 2014.

[78] G. Smith, P. Onions and D. Infield, “Predicting islanding operation of grid connected PV

inverters,” IEE Proceedings - Electric Power Applications, vol. 147, no. 1, pp. 1 - 6, 2000.

[79] X. Chen and Y. Li, “An Islanding Detection Method for Inverter-Based Distributed Generators

Based on the Reactive Power Disturbance,” IEEE Transactions on Power Electronics, vol. 31,

no. 5, pp. 3559 - 3574, 2016.

[80] J. Berry, S. Jupe, M. Meisinger and J. Outram, “Implementation of an active fault level

monitoring system for distributed generation integration,” in 22nd International Conference and

Exhibition on Electricity Distribution, Stockholm, 2013.

65

Appendix

A. Distribution system:

A RSCAD model of the distribution system network:

Figure 42: Distribution System Model on RSCAD environment

Dialing outputs that allow activation of fault using a push button, selection and alteration between the

different combinations of line to ground faults via a dial switch.

Table 7: Dial output and corresponding fault

DIAL OUTPUT BINARY OUTPUT FAULT APPLIED

1 001 A-G

2 010 B-G

3 011 AB-G

4 100 C-G

5 101 AC-G

6 110 BC-G

7 111 ABC-G

66

Figure 43: GTFPI and GTAO card used for exporting signals

B. Photovoltaic Generation Systems:

Figure 44: PV System characteristics graphs

67

A PV system MPPT controller:

Figure 45: Maximum Power Point Tracking control circuit

Figure 46: 2-level DC/AC inverter and filter

Figure 47: Triangle wave data generator for the DC/AC inverter

68

C. Grid-tied inverter System:

Dual simplex method iterations:

Table 8: 1st iteration (Slack variables as basics)

Basics 𝑿𝟏 𝑿𝟐 𝑿𝟑 𝑺𝟏 𝑺𝟐 𝑺𝟑 𝑺𝟒 𝑺𝟓 B

𝑺𝟏 -1.43 1.29 0 1 0 0 0 0 -0.4

𝑺𝟐 0 -2.88 0.956 0 1 0 0 0 -0.4

𝑺𝟑 -1.6 0 0 0 0 1 0 0 -0.02

𝑺𝟒 0 -1.29 0 0 0 0 1 0 -0.02

𝑺𝟓 0 0 -0.956 0 0 0 0 1 -0.02

Table 9: 2nd iteration (X2 enters as basic, S2 comes out)

Basics 𝑿𝟏 𝑿𝟐 𝑿𝟑 𝑺𝟏 𝑺𝟐 𝑺𝟑 𝑺𝟒 𝑺𝟓 B

𝑺𝟏 -1.43 0 0.447 1 -1.29 0 0 0 -0.578

𝑿𝟐 0 1 -0.347 0 1 0 0 0 0.138

𝑺𝟑 -1.6 0 0 0 0 1 0 0 -0.02

𝑺𝟒 0 0 -0.447 0 1.29 0 1 0 0.158

𝑺𝟓 0 0 -0.956 0 0 0 0 1 -0.02

Table 10: 3rd iteration (X1 enters as basic, S1 comes out)

Basics 𝑿𝟏 𝑿𝟐 𝑿𝟑 𝑺𝟏 𝑺𝟐 𝑺𝟑 𝑺𝟒 𝑺𝟓 B

𝑿𝟏 1 0 -0.312 -0.699 0.90 0 0 0 0.404

𝑿𝟐 0 1 -0.347 0 1 0 0 0 0.138

𝑺𝟑 0 0 -0.5 -1.12 1.44 1 0 0 0.626

𝑺𝟒 0 0 -0.447 0 1.29 0 1 0 0.158

𝑺𝟓 0 0 -0.956 0 0 0 0 1 -0.02

Table 11: 4th iteration (X3 enters as basic, S5 comes out)

Basics 𝑿𝟏 𝑿𝟐 𝑿𝟑 𝑺𝟏 𝑺𝟐 𝑺𝟑 𝑺𝟒 𝑺𝟓 B

𝑿𝟏 1 0 0 -0.699 0.90 0 0 0 0.41

𝑿𝟐 0 1 0 0 1 0 0 0 0.145

𝑺𝟑 0 0 0 -1.12 1.44 1 0 0 0.636

𝑺𝟒 0 0 0 0 1.29 0 1 -0.046 0.166

𝑿𝟑 0 0 1 0 0 0 0 -1.04 0.021

69