Ready. Resourceful. Responsive!
NAVAL INVENTORY
CONTROL POINT
PBL SUB-TEAM
OUT-BRIEF3 November 2004
![Page 2: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/2.jpg)
NAVICP
2
PBL TEAM
Team Leader: Steve SantosFacilitator: Jeff Brown/Troy BourgeoisSponsor: CAPT Kenney/CAPT Ellis
Team Members:
Maria Allen (02) Anita Perlman (03) Doug Nevins (02)Buster Jones (07) Elliot Redman (03)Karen Faber (03) Berkley Reid (84)Madeline Moore (02) Bob Wolfe (84)
![Page 3: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/3.jpg)
NAVICP
3
Workload Savings Goals
CategoryFTE Per June 2004
Spread Sheet Savings Goal
F& P Acq Planning
Procurement PBL
Total
70
71
141
7 – 10
7 - 10
14 - 20
Proposed savings
9.0
10.2
19.2
Remove non-value-added steps in the PBL Process Value Stream with the goal of becoming LEAN while reducing the variability in the process.
![Page 4: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/4.jpg)
NAVICP
4
Alpha Negotiation CRBContractComplete
PBL Process and Sub-processesCurrent State
SOW Process
J&A Process
PBL Prep Process
ROM
BCA Process
Data Queries
![Page 5: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/5.jpg)
NAVICP
5
Alpha Negotiation CRBContractComplete
PBL Process and Sub-processesFuture State
SOW Process
J&A Process
BCA Process
KickoffData
Agreement
PBL Prep Process
SOWKaizen 1
SOW K3
SOW K5----SOW
K2SOW
K4
ROM
PricingGuidelines
= ProcessImprovement
BCA E 2
BCA E 3
BCAE 1
![Page 6: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/6.jpg)
NAVICP
6
PBL PROCESS ELAPSED TIME
SOW (19 Months)BCA (21 Months)
J&A (8 Months)
ALPHA (10 Months)
29 MONTHS AVGAS IS
SOW
BCAJ&A
ALPHA
14 MONTHS AVG
TO BE(9 Months)(12 Months)
(5 Months)
(5 Months)
![Page 7: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/7.jpg)
NAVICP
7
PBL PROCESS TOUCH TIME
SOW (1270 Hours)BCA (1371 Hours)
J&A
ALPHA (1076 Hours)
3841 HRS AVG
AS IS
SOW
BCA
J&A
ALPHA
2131 HRS AVG
TO BE(475 Hours)
(768 Hours)(68 Hours)
(820 Hours)
(124 Hours)
![Page 8: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/8.jpg)
NAVICP
8
ROOT CAUSES
• Wide variation in the process– Guidance– Skills– Knowledge
• IPT Meeting time/agenda conflicts• Too many reviews/rework• Manual effort• Inadequate input data (for new equip)• Insufficiently defined requirements• Lack of dedicated resources
![Page 9: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/9.jpg)
NAVICP
9
SOLUTION 1
EVENT DRIVEN PROCESS KICK OFF (3.9 FTE savings)
SOW DEVELOPMENT (1.9 FTE savings)
DATA AGREEMENT (5.0 FTE savings)
PRICING GUIDELINES (1.7 FTE savings)
TOTAL FTE SAVINGS• 12.5 FTE
– Benefits:• 50% Improvement in Cycle Time
• Reduces learning curve/provides training
• Eliminates rework
– Challenges:• Competing Priorities/Scheduling conflicts/Lack of travel funds
![Page 10: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/10.jpg)
NAVICP
10
SOLUTION 2PROJECT MANAGER
– Responsibilities…enabler for “Events”• Schedules and facilitates all events• Develops the POAM • Monitors achievement of milestones • Assigns and tracks action items• Maintains metrics
– FTE SAVINGS: 1.3 FTE Net– Benefits:
• Reduced learning curve• Effective events• Identifies areas for continuous improvement• PBL development process can be monitored and controlled
– Challenges:• Access to resources with the right skill set• Reallocating staffing for the Project Management Team
![Page 11: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/11.jpg)
NAVICP
11
SOLUTION 3
STATEMENT OF WORK TOOL Enabler for SOW event
– WEB Based
– Menu driven…drop down boxes
– Pre-reviewed statements to choose from
– FTE SAVINGS• 3.7 FTE
– Benefits:• Eliminates redundant reviews
• Reduces touch time
• Accelerates document development
– Challenges:• $60K development cost; Initial investment of review time
![Page 12: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/12.jpg)
NAVICP
12
SOLUTION 4J&A Tool
– WEB based
– Electronic signature capability
– Workflow management capability
– Includes checklists from KO/CA/Legal
– FTE SAVINGS• .3 FTE
– Benefits:• Eliminates variation in expectations
• Reduces review time
• Reduces J&A development time
– Challenges:Resistance to workflow controls
![Page 13: Ready. Resourceful. Responsive! NAVAL INVENTORY CONTROL POINT PBL SUB-TEAM OUT-BRIEF 3 November 2004](https://reader036.vdocuments.us/reader036/viewer/2022072006/56649cfa5503460f949cbc10/html5/thumbnails/13.jpg)
NAVICP
13
Summary Of Improvements
•Cycle Time Reduction: 50%
•Touch Time Reduction: 45%
•FTE Savings: 13%
PBL Process