re: additional information document for categorical ... for ce2 signed 11.18.19.pdf ·...

45
101 West Ohio Street, Suite 2121 | Indianapolis, IN 46204 Direct: +1 317.616.1000 | Fax: +1 317.616.1033 | www.parsons.com November 13, 2019 To: Ryan Falls Indiana Department of Transportation Vincennes District Office 3650 South US 41 Vincennes, IN 47591 From: Juliet Port, LPG Senior Environmental Planner Parsons 101 West Ohio Street, Suite 2121 Indianapolis, IN 46204 RE: Additional Information Document for Categorical Exclusion, Level 2 Des. No. 0710929 (lead) and 1296642 SR 66 Intersection Improvement and Small Structure Replacement Spencer County, Indiana On August 18, 2017, the Vincennes District approved the Categorical Exclusion, Level 2 (CE-2) for the above referenced project. Since that time, the design was modified from a roundabout to a signalized intersection. This Additional Information document (AI) has been prepared to document the changes in project scope and evaluate their impacts. Preferred Alternative – Signalized Intersection with Added Turn Lanes The revised preferred alternative includes a mill and overlay of existing pavement, widening the intersection to accommodate added left turn only lanes along SR 66, drainage improvements, an upgraded signal, and upgraded signs (see project plans, Attachment 1). Travel lanes in all directions would remain unchanged. As part of this project, several pipes and culverts will be replaced, including INDOT Structure CV 066-074-54.00. The project does not include work on existing permanent lighting. Guardrail will be installed where needed. All work will occur within 50 feet of the existing edge of pavement. Approximate project termini were expanded east and west to achieve left turn lane deceleration and storage lengths. The approximate termini are from 1,105 feet west to 595 feet east of the intersection center, and from 320 feet south to 265 feet north of the intersection center. In the expanded areas, construction is limited to existing paved surfaces, plus three areas where existing signs and a driveway pipe will be replaced. These three areas are south of SR 66 and west of Orchard Road within previously-disturbed soils. Based on Parsons October 16, 2019 site visit, the areas are maintained grassy roadsides located within ten feet of existing pavement. A total of 0.82 acre of permanent right-of-way and up to 0.5 acre of temporary right-of-way will be acquired for this project. The project is scheduled to begin in the spring of 2020, and work will occur year-round. During construction, temporary lighting may be used, and the intersection will remain open to traffic along SR 66. The area will be restricted to one lane of traffic, which will be controlled by temporary signals. Traffic traveling north- and south-bound along Orchard Road will experience temporary disruptions requiring detours via local roads, SR 161, and SR 66.

Upload: others

Post on 15-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

  • 101 West Ohio Street, Suite 2121 | Indianapolis, IN 46204Direct: +1 317.616.1000 | Fax: +1 317.616.1033 | www.parsons.com

    November 13, 2019 To: Ryan Falls Indiana Department of Transportation Vincennes District Office 3650 South US 41 Vincennes, IN 47591 From: Juliet Port, LPG Senior Environmental Planner Parsons

    101 West Ohio Street, Suite 2121 Indianapolis, IN 46204 RE: Additional Information Document for Categorical Exclusion, Level 2

    Des. No. 0710929 (lead) and 1296642 SR 66 Intersection Improvement and Small Structure Replacement Spencer County, Indiana

    On August 18, 2017, the Vincennes District approved the Categorical Exclusion, Level 2 (CE-2) for the above referenced project. Since that time, the design was modified from a roundabout to a signalized intersection. This Additional Information document (AI) has been prepared to document the changes in project scope and evaluate their impacts. Preferred Alternative – Signalized Intersection with Added Turn Lanes The revised preferred alternative includes a mill and overlay of existing pavement, widening the intersection to accommodate added left turn only lanes along SR 66, drainage improvements, an upgraded signal, and upgraded signs (see project plans, Attachment 1). Travel lanes in all directions would remain unchanged. As part of this project, several pipes and culverts will be replaced, including INDOT Structure CV 066-074-54.00. The project does not include work on existing permanent lighting. Guardrail will be installed where needed. All work will occur within 50 feet of the existing edge of pavement. Approximate project termini were expanded east and west to achieve left turn lane deceleration and storage lengths. The approximate termini are from 1,105 feet west to 595 feet east of the intersection center, and from 320 feet south to 265 feet north of the intersection center. In the expanded areas, construction is limited to existing paved surfaces, plus three areas where existing signs and a driveway pipe will be replaced. These three areas are south of SR 66 and west of Orchard Road within previously-disturbed soils. Based on Parsons October 16, 2019 site visit, the areas are maintained grassy roadsides located within ten feet of existing pavement. A total of 0.82 acre of permanent right-of-way and up to 0.5 acre of temporary right-of-way will be acquired for this project. The project is scheduled to begin in the spring of 2020, and work will occur year-round. During construction, temporary lighting may be used, and the intersection will remain open to traffic along SR 66. The area will be restricted to one lane of traffic, which will be controlled by temporary signals. Traffic traveling north- and south-bound along Orchard Road will experience temporary disruptions requiring detours via local roads, SR 161, and SR 66.

  • CE-2 Additional Information (AI) SR 66 Intersection Improvement, Des. Nos. 0710929 and 1296642 November 13, 2019

    2

    The preferred alternative will meet the project’s purpose and need by improving safety with lengthened deceleration areas, increasing capacity of the intersection, and maintaining a sufficient crossing of SR 66 over UNTs to Huffman Drain. Alternatives Analysis Due to public concerns about the proposed roundabout, the following project alternatives were reanalyzed and compared to the revised preferred alternative (signalized intersection with added turn lanes). Alternative 1 – No-Build (Signalized Intersection) This alternative would leave the intersection in its present condition. The no-build alternative would not address the project’s purpose and need because it would not increase capacity of the intersection and it would not correct the intersection’s drainage issues (small structure project Des. No. 1296642). Therefore, it was dismissed from further consideration. Alternative 2 – Offset Roundabout (Former Preferred Alternative from the 2017 CE-2) This alternative is an offset roundabout with a single 16-foot wide travel lane. Additionally, INDOT Structure CV-066-074-54.00 would be replaced. While this alternative would meet the project’s purpose and need, there were public concerns about the roundabout and its potential impact to area businesses and oversized agricultural vehicles. Additionally, this alternative would impact over 800 linear feet of streams (UNTs to Huffman Drain). While the off-set roundabout alternative would meet the project’s purpose and need, it lacked public support and would incur more stream impacts compared to the preferred alternative, therefore it was dismissed from further consideration. Right-of-Way The preferred alternative will require the same permanent right-of-way that was analyzed in the 2017 CE-2 document, a total of 0.82 acre consisting of strips from commercial and school corporation real estate. No relocations are proposed. This right-of-way is needed to correct the intersection’s drainage issues. Up to 0.5 acre of temporary right-of-way may be required to match private driveway profiles. Red Flag Investigation The Red Flag Investigation (RFI) approved February 8, 2016 was reevaluated. The current RFI data was reviewed and found to be consistent with the information previously approved, therefore no addendum was needed (Attachment 2). Water Resources Due to the expanded project limits, the Waters of the US Report approved November 3, 2017 was reevaluated. Expanded project limits are limited to existing paved surfaces, except for three locations where existing signs and a 15-inch diameter driveway pipe will be replaced. These areas were reviewed by Parsons on October 16, 2019. They are located within 10 feet of existing pavement and consist of mowed grass. No evidence of water resources was noted. Therefore, no revisions to the Waters of the US Report are required. Threatened and Endangered Species Since this project was initiated in 2016, the potential impact to Threatened and Endangered Species was updated (Attachment 2). Project information was submitted through the United States Fish and Wildlife Service’s (USFWS’s) Information for Planning and Consultation (IPaC) portal, and an official species list was generated (Attachment 4). The project is within range of the federally endangered Indiana bat (Myotis sodalis) and the federally threatened northern long-eared bat (NLEB) (Myotis septentrionalis). Other species were found to be present within or adjacent to the project area along with the Indiana bat and NLEB, discussed further below.

  • CE-2 Additional Information (AI) SR 66 Intersection Improvement, Des. Nos. 0710929 and 1296642 November 13, 2019

    3

    The project qualifies for the Range-wide Programmatic Informal Consultation for the Indiana bat and NLEB, dated May 2016 (revised February 2018), between FHWA, Federal Railroad Administration (FRA), Federal Transit Administration (FTA), and USFWS. An effect determination key was completed on October 23, 2019, and based on the responses provided, the project was found to “May Affect, Not Likely To Adversely Affect” the Indiana bat and/or the NLEB. INDOT reviewed and verified the effect finding on October 24, 2019, and requested USFWS’s review of the finding (Attachment 5). No response was received from USFWS within the 14-day review period; therefore, it was concluded they concur with the finding. Avoidance and Mitigation Measures (AMMs) are included as firm commitments in the Environmental Commitments section of this document.

    The official species list generated from IPaC indicated two other species present within the project area, the gray bat (Myotis grisescens) and the least tern (Sterna antillarum). The project qualifies for the USFWS Interim Policy. Further coordination is not needed with USFWS.

    Public Involvement Following approval of this AI, INDOT will hold a public information meeting to inform the public of the project changes.

    Permitting Permits will be updated to reflect the current project limits and revised impacts. No additional permits are necessary. Revisions will be coordinated through the INDOT Ecology and Permitting Office (EWPO).

    Environmental Commitments The following firm environmental commitments will be added to the existing list of project commitments:

    General AMM 1 - Ensure all operators, employees, and contractors working in areas of known or presumed bat habitat are aware of all FHWA/FRA/FTA (Transportation Agencies) environmental commitments, including all applicable AMMs.

    Lighting AMM 1 - Direct temporary lighting away from suitable habitat during the active season.

    Conclusions Based on the information provided in this AI, the impacts associated with this project remain consistent with the thresholds of a CE-2. This addendum validates the CE-2 and reflects the current scope of the project as of the date of this AI. The documentation and determinations in the CE-2 approved on August 18, 2017 remain valid unless otherwise stated in this document. If the scope of work or permanent or temporary right-of-way amounts change, INDOT Environmental Services Division (ESD) and the INDOT District Environmental Section will be contacted immediately. This Additional Information addendum and the approved CE-2 fulfill the responsibilities of INDOT and FHWA as required by the National Environmental Policy Act, as amended.

    Approval of AI: Date: Environmental Scoping Manager or

    Environmental Policy Manager

    11/18/2019

  • Proposal Title 1 SR 66 Intersection Improvement – Des. 0710929

    Attachments

    Attachment 1

    Project Plans (Excerpts) ...................................................................................................................................... 1-11

    Attachment 2

    INDOT Email, October 15, 2019 ......................................................................................................................... 1-2

    Attachment 3

    Structure Assessment Forms ............................................................................................................................ 1-5

    Attachment 4

    USFWS Official Species List .............................................................................................................................. 1-7

    Attachment 5

    USFWS Concurrence Verification Letter ............................................................................................................. 1-12

  • SR 66 Intersection Improvement – Des. 0710929

    Attachment 1 Project Plans

  • SPENCER COUNTY

    LOCATION MAP

    Scale 1" = 4000'

    0710929 0710929

    S.R. 66

    0710929

    0710929

    0710929

    0.322

    0.322

    0.72

    2020

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    R-30399

    66

    66

    161

    CR N 2

    75 W

    CR N 2

    00 W

    CR W 200 N

    CR W 300 N

    W BASE RD

    W EUREKA RD

    CR W 100 S

    CR W 200 S

    CR N 3

    50 W

    CR N 4

    00 W

    CR N 4

    50 W

    CR N 5

    00 W

    N SILV

    ERD

    ALE R

    D

    N B

    ASE R

    D

    Sta. 328+85 "B"

    Begin Project Sta. 345+86 "B"

    End Project

    0710929

    0710929

    0710929R-30399

    R-30399

    0710929

    1

    T-7-S, R-6-W, Ohio Township, Spencer County, Indiana.

    located 1,375 feet East of SR 161 (East Jct.), in Sections 17, 20,

    Intersection Improvement on State Road 66 at Orchard Road (CR 275 W),

    Sta. 201+75 "S-2-A"

    End Construction

    Taffic and Design Data

    See Index Sheet For

    67

    53+0.77

    Sta. 196+90 "S-1-A"

    Begin Construction

    October 15, 2019

    Stage 3 Plans

    1296642

    KIN DES. NO. DESCRIPTION

    SMALL STRUCTURE (INCLUDED IN THIS SET)

    54+0.09

    IP_PWP:dms10674\SR66_Title.dgn

    ROAD PLANS

    PROJECT NO. P.E.

    R/W

    CONST.

    Gross Length:

    Net Length:

    Maximum Grade:

    ROUTE: FROM: RP TO: RP

    %

    PROJECT LOCATION SHOWN BY

    DESIGNATION

    SHEETS

    PROJECT

    SURVEY BOOK

    CONTRACT

    of

    PROJECT DESIGNATION

    CONTRACT

    OF TRANSPORTATION

    INDIANA DEPARTMENT

    O A

    A

    AT

    I

    NT

    F TRN

    SP

    OR

    TA

    TIO

    N

    NA

    DE

    PR

    ME

    NDI

    FOR LETTING:

    APPROVED

    DATE

    PHONE NUMBER

    PREPARED BY:

    PLANS

    DATE

    CERTIFIED BY:

    LATITUDE: LONGITUDE:

    MI.

    MI.

    INDIANA DEPARTMENT OF TRANSPORTATION

    TO BE USED WITH THESE PLANS

    DATEDSTANDARD SPECIFICATIONS

    INDIANA DEPARTMENT OF TRANSPORTATION

    29-OCT-2019

    Electronic

    Des. 0710929 Attachment 1 Page 1

  • Construction Area

    Detour Route (Direction of Travel)

    SR 66

    Reo Dr.

    N N

    orth

    Reo Dr

    W E

    Rebel S

    quare

    C.R. 40 N

    C.R. 40 N

    C.R. 50 N

    C.R. 3

    50 W

    N M

    eado

    w Ct.

    340 W

    W C.R. 150 N

    C.R. 3

    12 W

    W C.R. 170 N

    N C.R. 2

    94 W C.R. 284 W

    W Fairview Dr

    Fairvie

    w Ct

    W Country Ln

    Meadowland Dr

    W C.R. 200 N

    N Silv

    erd

    ale R

    d

    C.R. 3

    50 W

    See Detail "A"

    See Detail "B"

    Orc

    hard R

    d

    1

    W20-3

    2

    W20-2

    3

    R11-3a R11-2

    B

    4

    A

    M1-6

    XM4-8

    C(L OR R)

    M6-1S

    D

    F

    E

    (L OR R)

    M5-1S

    M1-6

    XM4-8

    M1-6

    XM4-8

    M4-6

    (L OR R)

    M6-1S

    M1-6

    XM4-8

    M1-6

    XM4-8

    (L OR R)

    M5-1S

    M1-6

    XM4-8

    M4-6

    A

    B C

    3

    3Barricade, Type IIIB &

    A

    B

    ALH

    MAT

    DH

    MAT

    N/A

    0710929

    DETOUR PLAN

    CR 275 W & ORCHARD ROAD

    1" = 600'

    N/A

    R-30399

    0710929

    S.R. 66S.R. 66

    S.R. 1

    61

    CC.R. 200 N

    B

    A

    C.R. 2

    00 W

    D E

    C.R. 2

    75 W

    F

    F

    E

    D

    D

    E

    C.R. 2

    00 W

    E

    B

    D

    A

    2

    17

    M3-1

    M1-6

    8

    M3-3

    M1-6

    SR 66 to Remain Open to Traffic.Businesses Along CR 275 W and Orchard Road.Detour Provided to Allow Access to School andNote to Reviewer:

    500' 500' 500'

    Detail "A"

    1 2 A B

    500' 500' 500'

    Detail "B"

    1 2 A B

    500'

    500'

    500'

    E

    D

    ED

    5

    B

    A

    Barricade, Type IIIB &

    Barricade, Type IIIB & 3 5

    CR 275 Detour

    Orchard Road Detour

    5

    (L OR R)

    M4-10

    FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    IP_PWP:dms10674\SR66_MOT Detour_01.dgn

    6 67

    Des. 0710929 Attachment 1 Page 2

  • FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_MOT_01.dgn

    7 67

    335+00340+00

    345+00

    1

    2

    3

    Construction Warning Light

    Type IIIB Barricade w/Type "B"

    Standard Drum

    Construction Warning Light

    Construction Sign w/Type "A"4

    Temp. Pvm't. Marking, Solid, White, 4"

    Temp. Pvm't. Marking, Broken, White, 5"

    Temp. Pvm't. Marking, Solid, Yellow, 4"

    (3' Dash, 9' Gap)

    Temp. Pvm't. Marking, Dotted, White, 5"

    Temp. Pavement

    Previously Constructed

    Construction Area

    Construction Sign

    5

    Temp. Pvm't. Marking, Solid, Yellow, 8"6

    Temp. Pvm't. Marking, Solid, White, 8"

    8 Temp. Pvm't. Marking, Solid, White, 24"

    Type 2

    Temporary Traffic Barrier,

    Direction of Traffic

    Temp Signal Head

    Video Detection Wood Pole & Down Guy

    32 Energy Absorbing Terminal, CZ TL-2

    S.R. 66 S.R. 66

    DH

    1" = 50' N/A

    Line "B"

    LINE "B"

    ALH

    MAT MATR-30399

    0710929

    0710929

    N/A

    Line "S-1-A"

    Line "S-2-A"

    S.R. 66

    MAINTENANCE OF TRAFFIC

    Speeding

    Reckless Driving

    Max 6 Yrs

    Max $1000 AHEAD

    WORK

    ROAD

    ROAD WORK

    END

    XW2-6-A

    1

    LIMITSPEED

    35

    2 5

    WORKSITE

    SPEED

    LIMIT

    35

    3

    G20-2

    8

    STOPHERE ON

    REDONE LANE

    ROAD

    AHEAD

    4

    XW20-4

    6 7

    R10-6

    500'

    735

    500'

    2

    500'

    11

    500'

    10

    500'

    8

    500'

    7 3 5

    500'

    2

    500'

    11

    500'

    10

    500'

    8

    WORKSITE

    XW20-1 R10-11

    Orc

    hard R

    oad

    +05

    24.00' Lt.

    +80 "S-2-A"

    R11-2

    9

    9&

    Barricade

    Type IIIA

    App. Ex. R/W

    App. Ex. R/W

    App. Sec. LineApp. Sec. Line

    App. Ex. R/W

    App. Ex. R/W

    Prop R/W

    Pro

    p R/W

    Pro

    p R/W

    Prop R/W

    Pro

    p R/W

    Pro

    p R/W

    Prop R/W

    Pro

    p R/W

    Prop R/W

    Pro

    p R/W

    Prop R/W

    Prop R/W

    Prop R/W

    Prop R/W

    Pro

    p R/W

    Prop R/W

    Pro

    p R/W

    App.

    App.

    Te

    mp R/W

    S.R. 66 PHASE 1

    LIMITSPEED

    45

    10

    WORKSITE

    SPEED

    LIMIT

    45

    11

    R2-1-B (45)

    XG20-5P

    WORKSITE

    XW3-5 (45)

    XG20-5P

    4

    500'

    1

    500'

    7

    4

    500'

    1

    500'

    323+

    85

    6

    200+53

    100'91'

    204'

    +25

    +29100'50'

    245' +00

    500'

    +68

    50'

    500'

    NO

    RED

    TURN

    ON

    R2-1 (35)

    XG20-5P

    XW3-5 (35)

    XG20-5P

    Approach and the New Structures on the South Side of SR 66.

    3. Construct Widening on the South Side of SR 66, CR 275W

    Shall be Maintained to the First Drive South of SR 66.

    2. Maintain Traffic on CR 275W Using Detour. Access

    the Signal for Orchard Road in a Three Phase Operation.

    Operation with a Temporary Signal. Coordinated with

    1. Maintain Traffic on SR 66 Using One-Lane Two-Way

    Phase 1

    8

    8

    4

    10:1 (Max) 10:1 (Max)

    1&

    Barricade

    Type IIIA

    9

    &

    Barricade

    Type IIIA

    9

    Des. 0710929 Attachment 1 Page 3

  • FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_MOT_02.dgn

    8 67

    330+00

    1

    2

    3

    Construction Warning Light

    Type IIIB Barricade w/Type "B"

    Standard Drum

    Construction Warning Light

    Construction Sign w/Type "A"4

    Temp. Pvm't. Marking, Solid, White, 4"

    Temp. Pvm't. Marking, Broken, White, 5"

    Temp. Pvm't. Marking, Solid, Yellow, 4"

    (3' Dash, 9' Gap)

    Temp. Pvm't. Marking, Dotted, White, 5"

    Temp. Pavement

    Previously Constructed

    Construction Area

    Construction Sign

    5

    Temp. Pvm't. Marking, Solid, Yellow, 8"6

    Temp. Pvm't. Marking, Solid, White, 8"

    8 Temp. Pvm't. Marking, Solid, White, 24"

    Type 2

    Temporary Traffic Barrier,

    Direction of Traffic

    Temp Signal Head

    Video Detection Wood Pole & Down Guy

    32 Energy Absorbing Terminal, CZ TL-2

    DH

    1" = 50' N/A

    LINE "B"

    ALH

    MAT MATR-30399

    0710929

    0710929

    N/A

    MAINTENANCE OF TRAFFIC

    S.R. 66

    Note: Maintain Access to all Drives

    App. Ex. R/W

    App. Sec. Line

    App. Ex. R/W

    Matc

    hline Sta. 333+

    00

    123

    500'

    2

    500'

    11

    500'

    LIMITSPEED

    35

    2

    WORKSITE

    SPEED

    LIMIT

    35

    3

    WORKSITE

    XW3-5 (35)

    XG20-5P

    LIMITSPEED

    45

    10

    WORKSITE

    SPEED

    LIMIT

    45

    11

    R2-1-B (45)

    XG20-5-B

    WORKSITE

    XW3-5 (45)

    XG20-5-B

    333+

    00

    S.R. 66 PHASE 2A - DAYTIME HOURS

    10

    500'

    4

    500'

    1

    500'

    R2-1 (35)

    XG20-5P

    Speeding

    Reckless Driving

    Max 6 Yrs

    Max $1000

    XW2-6-A

    1

    AHEAD

    WORK

    ROAD

    4

    XW20-1

    Orchard Road Pavement.

    3. Construct Structures Under Orchard Road and

    Maintained to the First Drive South of SR 66.

    Traffic on CR 275W Using Detour. Access Shall be

    2. Maintain Traffic on Orchard Road Using Detour. Maintain

    Widening Constructed During Phase 1.

    1. Maintain Traffic on SR 66 Using Existing Pavement and

    Phase 2A

    panelSizes:BIKE.:18x18,MIN.:24x24,STD.:30x30,EXP.:36x36,SPCL.:48x48

    12

    W24-1 (L OR R)

    MOT QUANTITIES

    ITEM QUANTITY UNIT

    TEMPORARY WORKSITE SPEED LIMIT SIGN ASSEMBLY 8 EACH

    ROAD CLOSURE SIGN ASSEMBLY 8 EACH

    TEMPORARY PAVEMENT MARKING, REMOVABLE, 4 IN. 3097 LFT

    TEMPORARY TRANSVERSE PAVEMENT MARKING, 24 IN. 24 LFT

    DETOUR ROUTE MARKER ASSEMBLY 30 EACH

    CONSTRUCTION SIGN, A 15 EACH

    CONSTRUCTION SIGN, B 6 EACH

    MAINTAINING TRAFFIC 1 LS

    BARRICADE, III-A 190 LFT

    BARRICADE, III-B 62 LFT

    TEMPORARY TRAFFIC BARRIER, TYPE 2 710 LFT

    PORTABLE SIGNAL 1 LS

    Des. 0710929 Attachment 1 Page 4

  • FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_MOT_03.dgn

    9 67

    335+00340+00

    345+00

    1

    2

    3

    Construction Warning Light

    Type IIIB Barricade w/Type "B"

    Standard Drum

    Construction Warning Light

    Construction Sign w/Type "A"4

    Temp. Pvm't. Marking, Solid, White, 4"

    Temp. Pvm't. Marking, Broken, White, 5"

    Temp. Pvm't. Marking, Solid, Yellow, 4"

    (3' Dash, 9' Gap)

    Temp. Pvm't. Marking, Dotted, White, 5"

    Temp. Pavement

    Previously Constructed

    Construction Area

    Construction Sign

    5

    Temp. Pvm't. Marking, Solid, Yellow, 8"6

    Temp. Pvm't. Marking, Solid, White, 8"

    8 Temp. Pvm't. Marking, Solid, White, 24"

    Type 2

    Temporary Traffic Barrier,

    Direction of Traffic

    Temp Signal Head

    Video Detection Wood Pole & Down Guy

    32 Energy Absorbing Terminal, CZ TL-2

    C.R. 275 W

    S.R. 66

    DH

    1" = 50' N/A

    Line "B"

    LINE "B"

    ALH

    MAT MATR-30399

    0710929

    0710929

    N/A

    Line "S-1-A"

    Line "S-2-A"

    MAINTENANCE OF TRAFFIC

    S.R. 66

    Speeding

    Reckless Driving

    Max 6 Yrs

    Max $1000 AHEAD

    WORK

    ROAD

    XW2-6-A

    1

    LIMITSPEED

    35

    2

    WORKSITE

    SPEED

    LIMIT

    35

    3 4

    8

    ROAD WORK

    END

    XG20-2

    8

    S.R. 66

    12 3

    500'

    2

    500'

    8

    XW20-1

    WORKSITE

    XW3-5 (35)

    XG20-5P

    19.37' Lt.

    +11 "S-1-A"

    13.12' Rt.

    +28 "S-1-A"

    R11-2

    9

    9.26' Lt.

    +90 "S-1-A"9.34' Rt.

    +90 "S-1-A"

    &

    Barricade

    Type IIIA

    9

    Prop R/WPro

    p R/W

    Pro

    p R/W

    Pro

    p R/W

    Prop R/W

    App. Ex. R/W

    App. Sec. Line

    App. Ex. R/W

    Prop R/W

    Pro

    p R/W

    Pro

    p R/W

    Prop R/W

    App.

    Prop R/W

    Pro

    p R/W

    Prop R/W

    Prop R/W

    Prop R/W

    App. Sec. Line

    App. Ex. R/W

    App. Ex. R/W

    Pro

    p R/W

    Prop R/W

    Pro

    p R/W

    App.

    Te

    mp R/W

    Matc

    hline Sta. 333+

    00

    panelSizes:BIKE.:18x18,MIN.:24x24,STD.:30x30,EXP.:36x36,SPCL.:48x48

    12

    LIMITSPEED

    45

    10

    WORKSITE

    SPEED

    LIMIT

    45

    11

    R2-1-B (45)

    XG20-5P

    WORKSITE

    XW3-5 (45)

    XG20-5P

    13

    9Barricades &

    Type IIIA

    9Barricades &

    Type IIIA

    500'

    11

    500'

    10

    500'

    4

    500'

    1

    349+

    25

    350+

    86

    333+

    85

    S.R. 66 PHASE 2A - DAYTIME HOURS

    (Max)

    10:1

    (Max)

    10:1

    +29

    +68

    300'

    300'

    +00

    +25

    2

    1

    1

    R2-1 (35)

    XG20-5P

    X 2

    W24-1 (L OR R)

    &

    Barricades

    Type IIIA

    9

    Des. 0710929 Attachment 1 Page 5

  • FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_MOT_04.dgn

    10 67

    330+00

    1

    2

    3

    Construction Warning Light

    Type IIIB Barricade w/Type "B"

    Standard Drum

    Construction Warning Light

    Construction Sign w/Type "A"4

    Temp. Pvm't. Marking, Solid, White, 4"

    Temp. Pvm't. Marking, Broken, White, 5"

    Temp. Pvm't. Marking, Solid, Yellow, 4"

    (3' Dash, 9' Gap)

    Temp. Pvm't. Marking, Dotted, White, 5"

    Temp. Pavement

    Previously Constructed

    Construction Area

    Construction Sign

    5

    Temp. Pvm't. Marking, Solid, Yellow, 8"6

    Temp. Pvm't. Marking, Solid, White, 8"

    8 Temp. Pvm't. Marking, Solid, White, 24"

    Type 2

    Temporary Traffic Barrier,

    Direction of Traffic

    Temp Signal Head

    Video Detection Wood Pole & Down Guy

    32 Energy Absorbing Terminal, CZ TL-2

    DH

    1" = 50' N/A

    LINE "B"

    ALH

    MAT MATR-30399

    0710929

    0710929

    N/A

    MAINTENANCE OF TRAFFIC

    S.R. 66

    R11-2

    9 Note: Maintain Access to all Drives

    App. Ex. R/W

    App. Sec. Line

    App. Ex. R/W

    Matc

    hline Sta. 333+

    00

    9Barricades &

    Type IIIA

    S.R. 66 PHASE 2B - OVERNIGHT HOURS

    ROAD WORK

    END

    G20-2

    8

    8

    500'

    First Drive South of SR 66.

    on CR 275W Using Detour. Access Shall be Maintained to the

    2. Maintain Traffic on Orchard Road Using Detour. Maintain Traffic

    Shown are Supplemental to the Phase 2A Signs.

    of the Eastbound Lanes in Accordance with Specifications. Signs

    Will be Detoured. Construct the Widening of SR 66 Using Closure

    and Widening Constructed During Phase 1. Westbound SR 66

    1. Maintain Westbound Traffic on SR 66 Using Existing Pavement

    Phase 2B

    Des. 0710929 Attachment 1 Page 6

  • FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_MOT_05.dgn

    11 67

    335+00340+00

    345+00

    1

    2

    3

    Construction Warning Light

    Type IIIB Barricade w/Type "B"

    Standard Drum

    Construction Warning Light

    Construction Sign w/Type "A"4

    Temp. Pvm't. Marking, Solid, White, 4"

    Temp. Pvm't. Marking, Broken, White, 5"

    Temp. Pvm't. Marking, Solid, Yellow, 4"

    (3' Dash, 9' Gap)

    Temp. Pvm't. Marking, Dotted, White, 5"

    Temp. Pavement

    Previously Constructed

    Construction Area

    Construction Sign

    5

    Temp. Pvm't. Marking, Solid, Yellow, 8"6

    Temp. Pvm't. Marking, Solid, White, 8"

    8 Temp. Pvm't. Marking, Solid, White, 24"

    Type 2

    Temporary Traffic Barrier,

    Direction of Traffic

    Temp Signal Head

    Video Detection Wood Pole & Down Guy

    32 Energy Absorbing Terminal, CZ TL-2

    C.R. 275 W

    S.R. 66

    DH

    1" = 50' N/A

    Line "B"

    LINE "B"

    ALH

    MAT MATR-30399

    0710929

    0710929

    N/A

    Line "S-2-A"

    MAINTENANCE OF TRAFFIC

    S.R. 66

    S.R. 66

    8

    19.37' Lt.

    +11 "S-1-A"

    13.12' Rt.

    +28 "S-1-A"

    9.26' Lt.

    +90 "S-1-A"9.34' Rt.

    +90 "S-1-A"

    Prop R/WPro

    p R/W

    Pro

    p R/W

    Pro

    p R/W

    Prop R/W

    App. Ex. R/W

    App. Sec. Line

    App. Ex. R/W

    Prop R/W

    Pro

    p R/W

    Pro

    p R/W

    Prop R/W

    App.

    Prop R/W

    Pro

    p R/W

    Prop R/W

    Prop R/W

    Prop R/W

    App. Sec. Line

    App. Ex. R/W

    App. Ex. R/W

    Pro

    p R/W

    Prop R/W

    Pro

    p R/W

    App.

    Te

    mp R/W

    Matc

    hline Sta. 333+

    00

    13

    9Barricades &

    Type IIIA

    9Barricades &

    Type IIIA

    350+

    86

    S.R. 66 PHASE 2B - OVERNIGHT HOURS

    (Max)

    10:1

    (Max)

    10:1

    300'

    300'

    +00

    +25

    +68

    2

    1

    1

    ROAD WORK

    END

    XG20-2

    8

    R11-2

    9

    X 2

    &

    Barricade

    Type IIIA

    9

    Line "S-1-A"&

    Barricade

    Type IIIA

    9

    Des. 0710929 Attachment 1 Page 7

  • CONDUIT UP

    1 STY WOOD FR1 STY BRICK

    ROCK

    CONDUIT UPASPHALT DRIVE

    NO PIPE FND

    GRASS

    CONC GUTTER

    STONE LOT

    NORHERN STEEL TRANSPORT

    GRASS

    PAINT STRIPE

    ASPHALT SHOULDER

    CONC HEADWALL

    GRASS

    SIGN DAMAGED

    GRASS

    GRASS

    STONE LOT

    5.0

    TALL

    STONE LOT

    CONC LOT

    CONC WALK

    SHRUBS

    SHRUBS

    CONC WALK

    CONC CHAIRBACKCONC DRIVE

    CONC LOT

    CONC DRIVE

    GRASS

    CONC HEADWALL

    GRASS

    STONE

    DRIV

    E

    BEG PAINT STRIPE

    RIPRAP

    6.0

    TALL

    CONC LOT

    ASPHALT

    CONC LOT

    CONC LOT

    6.0

    TALL

    GRASS

    GRASS

    ASPHALT DRIVE

    PAINT STRIPE

    GRASS

    GRASS

    GRASS

    ASPHALT SHOULDERPAINT STRIPE

    GRASS

    GRASS

    ASPHALT DRIVE

    ASPHALT

    ASP

    HALT D

    RIV

    E

    GRASS

    CONC WALK CONC PORCH

    GRASS

    GRASS

    4.0

    TALL

    STONE PU

    LLOFF

    6.5 HIGH

    GRASS

    SOUTH SPENCER HIGH SIGN

    GRASS

    GRASS

    GRASS

    GRASS

    5.5 HIGH

    GRASS

    GRASS

    SILTED BOTTOM

    RIPRAP

    PAINT STRIPE

    ASPHALT SHOULDERASPHALT SHOUDERASPHALT SHOULDER

    GRASS

    GRASS

    GRASS

    GRASS

    STONEPAINT STRIPEEND PAINT STRIPE

    ASPHALT LOT

    ASPHALT LOT

    CONC CHAIRBACK CURB

    END PAINT STRIPE

    CONC WALK

    ASPHALT LOT

    ASPHALT LOT

    CONC

    CONC DRIVE TRU

    ASPHALT LOT

    GRASS

    STONE PULLOFF

    RIGHT TURN LANE

    PAINT STRIPE

    GRASS

    CONC BASE

    ASPHALT SHOULDER

    DECK

    WOOD

    PED-T

    GM

    GV

    PED-T

    WM

    EMER

    ER

    GR

    GR

    GM

    ER

    FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_PLAN_01.dgn

    12 67

    330+00

    335+00

    10' WATER LINE EASEMENT

    ING

    RE

    SS/

    EG

    RE

    SS

    ES

    MT.

    RE

    CO

    RD 162,

    PG.

    744

    370

    380

    390

    400

    410

    420

    430

    440

    370

    380

    390

    400

    410

    420

    430

    440

    328+00 329+00 330+00 331+00 332+00 333+00 334+00 335+00 336+00 337+00

    408.0

    6

    407.6

    4

    407.3

    7

    407.0

    4

    406.7

    0

    406.2

    4

    405.8

    2

    405.6

    3

    405.2

    8

    404.8

    8

    404.5

    3

    404.1

    1

    403.7

    5

    403.5

    3

    403.2

    0

    403.0

    3

    402.6

    2

    402.7

    7

    402.9

    3

    35.05' RT

    +76.37, Line "B", Str. No. MH-1

    (Plotted at Datum)

    103 LFT of 24" Dia. Pipe at 3.41%

    (Plotted at Datum)

    345 LFT of 30" Dia. Pipe at 0.29%Inv. 400.59

    31.93' RT

    +71.52

    Inv. 397.01

    30.46' RT

    +73.37

    Inv. 396.51

    30.40' RT

    +79.37

    El. 407.46'

    Sta. 328+85 "B"

    Begin Project

    El. 406.81'

    Sta. 329+85 "B"

    Begin Full Depth Widening

    Along Line "B"

    Existing Ground

    (Match Existing)

    Proposed Profile

    50' GRET

    OS, Rt.

    +59

    +09

    256.25' MGS W-Beam

    Guardrail, Rt.

    S.R. 66

    SCHOOL CORPORATION

    SOUTH SPENCER COUNTY

    Spencer County

    Ohio Township

    Sec. 20, T-7-S, R-6-W

    App. Ex. R/W

    App. Ex. R/W

    App.

    DH

    1" = 30'

    1" = 10'

    N/A

    PLAN SHEET

    LINE "B"

    TJK

    MAT MATR-30399

    0710929

    0710929

    App. Sec. Line

    E: 2945443.95

    N: 966432.74

    Sta. 328+85 "B"

    Begin Project

    STROXON, LLC

    Huffman Ditch

    UNT2 to

    STA. 328+00.00 TO STA. 337+00.00

    Str. No. MH-1

    +76.37

    SCHOOL CORPORATION

    SOUTH SPENCER COUNTY

    JACK LLC

    JJP JUMPIN

    RUDOLPH

    NATHAN

    BO

    GE

    NH

    AG

    EN

    M.

    DO

    UG

    LA

    S

    Sheets for R/W Details

    See Construction Detail

    Construction Limits

    Construction Limits

    App. Ex. R/W

    App.

    App.

    App.

    App.

    App.

    Spencer County

    Ohio Township

    Sec. 17, T-7-S, R-6-W

    WRIGHT

    ALICE F.

    AND

    JAMES L.

    WRIGHT

    ALICE F.

    AND

    JAMES L.

    ALICE F. WRIGHT

    JAMES L. AND

    Do Not Disturb

    Existing 12" Pipe

    To Be Removed

    Existing 15" Pipe

    W = 59.8'

    Class IV Drive (Mod.)

    +21.64 "B"

    (Include Mailbox Approach)

    W = 40'

    to Existing

    Asphalt Wedge

    Class II Drive (Mod.)

    +75.19 "B"

    W = 12.6'

    to Existing

    Asphalt Wedge

    Class II Drive (Mod.)

    +36.42 "B"

    W = 55.8'

    Class IV Drive (Mod.)

    +95.46 "B"

    74.61' Rt.

    +23.94 "B"

    76.63' Rt.

    +50.88 "B"

    68.63' Rt.

    +85.38 "B"TBM 1

    Prop. R/W

    R=40'

    R=40'

    R=40'R

    =40'

    Line "B"

    at House Number 2929

    M. Spike in Power Pole at South Side SR 66

    Sta. 331+22.92 "B", 32.63' Rt., EL. = 406.02' (NAVD88)

    TBM 1

    Matc

    hline 3

    37+

    00

    Sta. 331+3.70 "B", 29.74' Rt. Sta. 336+36.28 "B", 84.16' Rt.

    Southwest Corner SR 66 and SR 161

    Bronze Disk in Concrete Monument

    Benchmark B-329

    Waste = 907 CYS

    Borrow = 0 CYS

    Fill + 25% = 4,782 CYS

    Excavation, Common = 5,689 CYS

    Earthwork Summary

    Huffman Ditch

    UNT2 to

    Wetland 2

    Des. 0710929 Attachment 1 Page 8

  • CONC WALK

    GRASS

    CONC PORCH

    GRASS

    1 STY WOOD FR

    GRASS

    3 TRANS ATTACHED W/POLES

    CONC WALK

    CONC WALK

    1 STY METAL VACANT

    OVERHANG

    CONDUIT UP

    PAINT STRIPEASPHALT SHOULDER

    CORN FIELD

    CORN FIELD

    CORN FIELD

    CORN FIELD

    GRASS

    RIGHT TURN LANE

    GRASS

    HATCHED AREA

    GRASS

    GRASS

    ASPHALT LOT

    PAINT STRIPE

    RIGHT TURN LANE

    BEG PAINT STRIPE

    PAINT STRIPE

    GRASS

    ASPHALT LOT

    GRASS

    ASPHALT LOT

    ASPHALT LOT

    WEEDS

    WEEDS

    ASPHALT SHOULDER

    RIPRAP

    PAINT STIPE

    RIPRAP

    RIP

    RAP

    WEEDS

    ASPHALT

    WEEDS

    WEEDS

    SILT

    ED B

    OTT

    OM

    SILTED BOTTOMRIPRAP

    WEEDS

    RIPRAP

    RIGHT TURN LANE

    GRASS

    GRASS

    GRASS

    STONE LOT

    SR 66

    ASPHALT

    ASPHALTRIG

    HT T

    URN L

    ANE

    PAINT STRIPE

    STONE LOT

    ASPHALT AND CONC DEBRIS

    NO PIPE FND

    GRASS

    ASP

    HALT D

    RIV

    E

    GRASS

    CONC DRIVE

    CONC HEADWALL

    CONC W

    ALK

    CONC C

    URB

    STEEL RAIL

    GRASS

    9.0 TALL FIBERGLASS SHED

    GRASS

    STEEL FRAME GARAGE

    CONC DRIVE

    GRASS DIRT/STONE LOT

    STONE LOT

    STONE LOT

    DIRT/STONE LOT

    CONC R

    OLL

    ED C

    URB

    CONC DRIVE

    CONC GUTTER

    CONC SLAB

    CONC GUTTER

    ROLLED CUR

    B

    STONE LOT

    OLD CONC WING

    RIPRAP

    RIPRAP

    GRASS

    TURN LANE

    GRASS

    TURN LANE

    PAINT STRIPE

    GRASSGRASS

    SOUTH SPENCER HIGH SCHOOLSHRUBS

    SHRUBS

    BRICK 4.0 HIGH

    LAST MARKED

    2007 2-A BASEBALL CHAMPS

    GRASS

    GRASS

    GRASS

    GRASS

    GRASS

    GRASS

    RIPRAP

    WEEDS

    PAINT STRIPEPAINT STRIPE

    PED-T

    GV

    PED-T

    PED-T

    TR

    TR

    TVR

    TRTR

    EM

    EM

    EMER

    ER

    TVR

    WV

    PED-T

    WV

    WV

    TR

    ER

    PED-T

    TR

    PED-T

    PED-T

    PED-T

    ER

    ER

    FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_PLAN_02.dgn

    13 67

    340+00

    345+00

    370

    380

    390

    400

    410

    420

    430

    440

    370

    380

    390

    400

    410

    420

    430

    440

    337+00 338+00 339+00 340+00 341+00 342+00 343+00 344+00 345+00 346+00

    404.4

    8

    404.0

    7

    403.8

    8

    403.4

    6

    403.2

    5

    403.0

    5

    402.8

    0

    402.7

    3

    402.8

    2

    402.6

    2

    402.7

    0

    402.7

    3

    402.5

    7

    402.4

    6

    402.5

    3

    402.5

    1

    402.6

    2

    402.5

    9

    402.6

    5

    (Sump Str. 6")

    (Plotted at Datum)

    Str. No. 1

    (Sump Str. 12")

    (Plotted 30' Above Datum)

    Str. No. 3

    Inv. 392.00

    +46.21

    Inv. 393.00

    +40.80

    OHWM 394.67

    FL. 394.00

    +40.80

    OHWM 393.67

    FL. 393.00

    +46.21

    OHWM 392.27

    FL. 391.77

    +12.69

    OHWM 393.44

    FL. 392.94

    +12.69

    400.14'

    Q100 =

    Inv. 395.00

    +45.71

    Inv. 393.00

    +38.01

    (Sump Str. 3")

    (Plotted at Datum)

    Str. No. 2

    FL. 395.25

    +45.71

    FL. 393.25

    +38.01

    Inv. 391.27

    30.79' LT

    +12.69

    Inv. 392.44

    29.25' RT.

    +12.69

    Along Line "B"

    Existing Ground

    -0.070%

    -0.200%

    Profile Rt.

    Special Ditch

    Profile Rt.

    Special Ditch

    0.040%

    Profile

    Proposed

    El. 402.71

    Sta. 341+25 "B"

    Construction

    End Full Depth

    El. 402.70'

    Sta. 341+00 "B"

    Construction

    Begin Full DepthEl. 403.32

    Sta. 344+19.48 "B"

    End Full Depth Widening

    (Match Existing)

    Proposed Profile

    El. 404.37

    Sta. 345+86 "B"

    End Project

    (Match Existing)

    Proposed Profile

    Along Line "B"

    Existing Ground

    Terminal Anchor, Rt.

    12.5' MGS Cable

    +66

    +78

    Terminal Anchor, Rt.

    12.5' MGS Cable

    +59

    +90

    +65

    +78

    +34

    31.25' MGS

    W-BeamGuardrail, Rt.

    +47

    +59

    +35

    +91

    +34

    +84

    Terminal Anchor, Lt.

    12.5' MGS Cable

    50' GRET

    OS, Lt.

    50' MGS W-Beam

    Guardrail, Lt.

    31.25' MGS

    Guardrail, Lt.

    Guardrail, Lt.

    43.75' MGS Long Span, Type 1

    FL. 391.77

    +12.69

    -1.870%

    (Plotted 30' Above Datum)

    Profile Rt.

    Special Ditch

    (Sump Str. 6")

    (Plotted 30' Above Datum)

    Str. No. 1

    31.34' RT

    +21.27, Line "B", Str. No. MH-2

    Inv. 395.53

    31.34' RT

    +21.27

    Inv. 395.53

    31.34' RT

    +21.27

    Inv. 395.45

    46.47' RT

    +46.18

    256.25' MGS W-Beam Guardrail, Rt.

    (Plotted at Datum)

    30 LFT of 30" Dia. Pipe at 0.30%

    See Line "S-1-A"

    Guardrail, Rt.

    125' MGS W-Beam

    Span Type I, Guardrail, Rt.

    43.75' MGS Long

    S.R. 66

    C.R. 275 W

    S.R. 66

    SCHOOL CORPORATION

    SOUTH SPENCER COUNTY

    PRACTICE, PLLC

    OWENSBORO MEDICAL

    JONETT WIMSETT

    Spencer County

    Ohio Township

    Sec. 17, T-7-S, R-6-W

    Spencer County

    Ohio Township

    Sec. 20, T-7-S, R-6-W

    App. Ex. R/W

    App. Ex. R/W

    App. Ex. R/W

    App. Ex. R/W

    App. Ex. R/W

    App.

    Line "B"

    Line "S-2-A"

    Line "S-1-A"

    Construction Limits

    Construction LimitsConstruction Limits

    Construction Limits

    App. Sec. Line

    Disturb Sign

    Do Not

    P.O.T. Sta. 339+92.76 "B"

    P.O.T. Sta. 200+00 "S-2-A"

    P.O.T. Sta. 339+89.21 "B"

    P.O.T. Sta. 200+00 "S-1-A"

    115.15' Rt.

    +78.43 "B"

    114.95' Rt.

    +63.77 "B"

    72" RCP

    Str. No. 3

    Point #99

    Control

    Conc. Box Culert

    10'x5' Reinf.

    Str. No. 1

    42" RCP

    Str. No. 2

    M. DOUGLAS BOGENHAGEN

    OHIO TOWNSHIP TRUSTEE

    Huffman Ditch

    UNT2 to

    Erosion In Southeast Corner.

    On Side Slopes To Prevent Further

    Riprap To Be Used

    Note to Reviewer:

    Huffman Ditch

    UNT1 to

    Huffman Ditch

    UNT1 to

    207 SYS Geotextile Req'd

    260 Tons of Class II Riprap on

    509 SYS Geotextile Req'd

    509 Tons of Class I Riprap on

    E: 2947144.81

    N: 966410.77

    Sta. 345+86 "B"

    End Project

    Utility Pole

    Do Not Disturb

    TJK

    MAT

    DH

    MAT

    N/A

    0710929

    PLAN SHEET

    STA. 337+00.00 TO STA. 346+50.00

    LINE "B"

    1" = 30'

    1" = 10'

    R-30399

    0710929

    Do Not Disturb

    Existing 4" Pipe

    Do Not Disturb

    Existing 4" Pipe

    Prop. R/W

    Prop.

    R/W

    Prop. R/W

    Section Line

    41

    App.

    Pro

    p. R/W

    Prop. R/W

    To Be Removed

    Existing 66" CMP

    Do Not Disturb

    Existinig 2" PVC

    Sheets for R/W Details

    See Construction Detail

    App.

    App. Ex. R/W

    GET PROPERTIES LLC

    To Be Removed

    Existing Twin 66" CMPs

    Adjust to New Grading

    Existing 10" HDPE Pipe

    Prop. R/W

    C.R. 275 W

    Pro

    p.

    R/W

    To Be Removed

    Elliptical CMP

    Existing 72"Wx61"H

    EL. = 398.69'

    Sta. 198+90.50 "S-1-A", 18.67' Rt.,

    TBM 2

    Matc

    hline 3

    37+

    00

    Str. No. MH-2

    +21.27

    37 SYS Geotextile Req'd

    28.1 Tons of Class I Riprap on

    TBM #2

    Sta. 339+53.94 "B", 68.42' Lt.

    Wetland 2

    (Do Not Disturb)

    Wetland 1

    Des. 0710929 Attachment 1 Page 9

  • CONC W

    ALK

    CONC W

    ALK

    1 STY M

    ETAL V

    ACANT

    OVER

    HANG

    CONDUIT U

    P

    ASPH

    ALT LO

    T

    WEED

    S

    PAIN

    T STIPE

    RIPR

    AP

    RIPRAP

    WEED

    S

    WEED

    S

    ASPH

    ALT

    ASPH

    ALT LO

    T

    STONE PU

    LLOFFW

    EEDS

    WEED

    S

    ASPH

    ALT

    5.0 HIGH FENCE

    GRASS

    STONE LO

    T

    SILTED BOTTOM

    SILTED B

    OTTO

    MRIPR

    AP

    WEED

    S

    RIPR

    AP

    RIG

    HT T

    URN LA

    NE

    GRASS

    GRASS

    GRASS

    STONE LO

    T

    SR 66

    ASPH

    ALT

    ASPH

    ALT

    RIGHT TURN LANE

    PAIN

    T ST

    RIPE

    STONE LO

    T

    GRASS

    STONE LO

    T

    GRASS

    GRASS

    GRASS

    PAIN

    T ST

    RIPE

    GRASS

    ASH

    ALT D

    RIV

    E

    GRASS

    GRASS

    GRASS

    GRASS

    GRASS

    ASPH

    ALT A

    ND C

    ONC D

    EBRIS

    NO PIPE FN

    D

    GRASS

    STONE LO

    T

    CONC SLA

    B

    ASPHALT DRIVE

    CONC H

    EAD

    WALL

    CONC D

    RIV

    E

    GRASS

    CONC D

    RIV

    E

    CONC H

    EAD

    WALL

    CONC WALK

    CONC CURB

    STEEL RAIL

    GRASS

    9.0 TALL FIB

    ERGLA

    SS SHED

    GRASS

    CONC W

    ALK

    STEEL FR

    AME G

    ARAGE

    CONC D

    RIV

    E

    STONE LO

    T

    DIR

    T/ST

    ONE LO

    T

    CONC ROLLED CURB

    CONC D

    RIV

    E

    CONC G

    UTTER

    CONC SLA

    B

    OLD C

    ONC WIN

    G

    RIPR

    AP

    RIPR

    AP

    TURN LA

    NE

    GRASS

    TURN LA

    NE

    GRASS

    GRASS

    SOUTH SPEN

    CER HIG

    H SC

    HOOL

    SHRUBS

    SHRUBS

    BRIC

    K 4.0 H

    IGH

    LAST M

    ARKED

    2007 2-A B

    ASEB

    ALL C

    HA

    MPSG

    RASS

    GRASS

    GRASS

    GRASS

    RIPR

    AP

    WEED

    S

    PAIN

    T ST

    RIPE

    WM

    PE

    D-T

    TR

    TR

    EM

    EM

    EM

    ER

    ER

    TVR

    PE

    D-T

    WV

    WV

    TR

    TR

    ER

    EM

    EM

    PE

    D-T

    TR

    PE

    D-T

    GM

    GV

    FOR APPROVAL

    RECOMMENDED

    DESIGN ENGINEER DATE

    DESIGNED:

    CHECKED:

    DRAWN:

    CHECKED:

    SURVEY BOOK

    CONTRACT

    DESIGNATION

    SHEET

    of

    PROJECT

    BRIDGE FILE

    DEPARTMENT OF TRANSPORTATION

    INDIANAHORIZONTAL SCALE

    VERTICAL SCALE

    Fax (317) 616-1033

    Bus (317) 616-1000

    Indianapolis, IN 46204

    101 W. Ohio St., Suite 2121

    IP_PWP:dms10674\SR66_PLAN_03.dgn

    14 67

    340+

    00

    360

    370

    380

    390

    400

    410

    420

    196+00 197+00 198+00 199+00 200+00

    399.7

    8

    400.0

    6

    400.7

    7

    401.1

    0

    400.9

    1

    401.3

    2

    399.7

    7

    399.8

    7

    400.2

    7

    400.8

    4

    400.6

    2

    400.9

    1

    402.5

    0

    360

    370

    380

    390

    400

    410

    420

    (Plotted at Datum)

    29.39' LT.

    +46.21, Line "S-1-A", Str. No. 10

    (Plotted at Datum)

    (Sump Str. 12")

    +51.13, Line "S-1-A", Str. No. 2-2

    (Plotted at Datum)

    (Sump Str. 12")

    22.59' LT.

    +72.04, Line "S-1-A", Str. No. 2-1

    Inv. 395.00

    +77.37Inv. 395.50

    +46.21

    Inv. 394.5

    17.23' LT.

    +51.13

    (Plotted at Datum)

    (Sump Str. 3")

    43.62' LT.

    +51.04, Line "S-1-A", Str. No. 2

    (Plotted 10' Below Datum)

    Inv. 395.00

    18.77' RT.

    +51.13

    Inv. 395.00

    43.62' LT.

    +51.04

    (Plotted 10' Below Datum)

    Inv. 393.00

    48.67' RT.

    +46.39

    Along Line "S-1-A"

    Existing Ground

    El. 394.34'

    +81.84 "S-1-A"

    El. 393.00'

    +46.39 "S-1-A"

    Profile Rt.

    Special Ditch

    Profile Lt.

    Special Ditch

    Rl. 398.00'

    +45 "S-1-A"

    Rl. 398.78'

    +50 "S-1-A"

    (Plotted at Datum)

    Dia. Pipe at 0.74%

    68 LFT of 15"

    PVI Elev = 399.73

    PVI Sta = 197+38.00

    PVI Elev = 401.33

    PVI Sta = 198+31.00

    PVI Elev = 400.64

    PVI Sta = 199+29.00

    -0.707%

    Length = 96.00' Length = 90.00' Length = 96.00'

    -0.091% 1.719%

    2.627%

    El 399.77

    Sta. 196+90 "S-1-A"

    Begin Construction

    El 401.90

    Sta. 199+77 "S-1-A"

    End Construction

    +50

    +13

    +75

    50' GRET

    OS, Rt. Guardrail, Rt.

    125' MGS W-Beam

    Line "B"

    See

    Profile

    Proposed

    400.47'

    Q100 =

    OHWM = 395.08

    FL = 394.58

    Inv. 393.58

    22.59' LT.

    +72.04

    360

    370

    380

    390

    400

    410

    420

    201+00 202+00 203+00 204+00 205+00

    401.5

    2

    401.0

    5

    400.8

    1

    400.8

    3

    400.7

    8

    400.7

    3

    400.7

    3

    400.6

    2

    (Plotted at Datum)

    (Sump Str. 12")

    +51.49, Line "S-2-A", Str. No. 3

    Along Line "S-2-A"

    Existing Ground

    -1.560%

    El. 402.07

    Sta. 200+21.42 "S-2-A"

    Begin Construction

    El. 400.82

    Sta. 201+75.00 "S-2-A"

    End ConstructionProposed Profile

    El. 401.38

    Sta. 200+65.82 "S-2-A"

    End Full Depth Construction

    (Match Existing)

    Proposed Profile

    401.6

    2

    (Plotted 10' Below Datum)

    OHWM = 393.67

    FL = 393.00

    Inv. 392.00

    54.66' RT.

    +47.25

    OHWM = 394.67

    FL = 394.00

    Inv. 393.00

    50.73' LT.

    +51.49

    S.R. 66

    SCHOOL CORPORATION

    SOUTH SPENCER COUNTY

    PRACTICE, PLLC

    OWENSBORO MEDICAL

    Spencer County

    Ohio Township

    Sec. 17, T-7-S, R-6-W

    Spencer County

    Ohio Township

    Sec. 20, T-7-S, R-6-W

    App.

    Ex.

    R/W

    App.

    Ex.

    R/W

    App.

    Ex.

    R/W

    App.

    Ex.

    R/W

    App.

    DH

    1" = 30'

    1" = 10'

    N/A

    C.R. 275 W

    BAPTIST CHURCH

    FREE ZION GENERAL

    App. Ex. R/W

    App. Ex. R/W

    App. Ex. R/W

    App. Ex. R/W

    PLAN SHEET

    Line "S-1-A"

    Line "S-2-A"

    Construction Limits

    Construction Limits

    Construction Limits

    Construction Limits

    TJK

    MAT MATR-30399

    0710929

    0710929LINE "S-1-A" & "S-2-A"

    Line "B"

    P.O.T. Sta. 339+89.21 "B"

    P.O.T. Sta. 200+00 "S-1-A"

    P.O.T. Sta. 339+92.76 "B"

    P.O.T. Sta. 200+00 "S-2-A"

    Sec. Line41App.

    Sec. Line41App.

    56.65' Rt.

    +32.15 "S-2-A"

    56.98' Rt.

    +41.64 "S-2-A"

    Begin Line "

    S-2-A

    "

    End Line "

    S-1-A

    "

    72" RCP

    Str. No. 3

    E: 2946549.49

    N: 966593.42

    Sta. 201+75.00 "S-2-A"

    End Construction

    42" RCP

    Str. No. 2

    Conc. Box

    10'X5' Reinf.

    Str. No. 1

    M. DOUGLAS BOGENHAGEN

    TRUSTEE

    OHIO TOWNSHIP

    Huffman Ditch

    UNT2 to

    Huffman Ditch

    UNT1 to

    Huffman Ditch

    UNT1 to

    196 SYS Geotextile Req'd.

    147 Tons of Revetment Riprap on

    Conc. Box

    14'x5' Reinf.

    Str. No. 2-1

    Conc. Box

    8'x3' Reinf.

    Str. No. 2-2

    W = 18'

    Class IV Drive (Mod.)

    +21 "S-1-A"

    E: 2946544.77

    N: 966108.50

    Sta. 196+90.00 "S-1-A"

    Begin Construction

    W = 32'

    Class IV Drive (Mod.)

    +92 "S-1-A"

    To Be Removed

    Existing 18" Twin CMPs

    R=25'R=25'

    Huffman Ditch

    UNT 1 to

    To Be Removed

    Existing 42" Pipe

    To Be Removed

    Existing Triple 30" Pipes

    To Be Removed

    Existing 30" CMP

    Asphalt Wege to Existing

    W = 68'

    Class IV Drive (Mod.)

    +12.31 "S-2-A"

    Req'd.

    Concrete Removal

    394 SYS

    Str. No. 10

    +46.21

    C.R. 275 W/Orchard Road

    Sta. 197+78.55 "S-1-A", 43.38' Rt.

    Sheets for R/W Details

    See Construction Detail

    Connect to Str. 2-1

    Existing 18" HDPE Pipe

    54 SYS Geotextile Req'd.

    54 Tons of Class 1 Riprap on

    Des. 0710929 Attachment 1 Page 10

  • SR 66 Intersection Improvement – Des. 0710929

    Attachment 2

    INDOT Email October 15, 2019

  • From: Falls, Ryan GTo: Port, JulietCc: Malone, Brian; Miller, Daniel J; Taylor, Matt; Wright, Kristy; Ridgley, BradSubject: [EXTERNAL] RE: DES 0710929 SR 66 Intersection AI Questions ResponseDate: Tuesday, October 15, 2019 10:54:06 AMAttachments: image002.png

    image003.pngimage004.pngimage007.pngimage008.pngimage009.pngimage010.pngimage012.pngimage001.png

    Juliet Port, With regards to the RFI, no addendum is necessary. Since the RFI is more than 3 years old, Icoordinated with the SAM group. We reviewed the scope change, the areas of concern in the originalRFI, and the current RFI layers. Since the hazmat sites were deemed to not be impacted fromdistance from the project’s grading work, there is no need for the addendum. Please place thisportion of the email chain into the AI and reference it in the text to verify no addendum to the RFIwas needed. With regards to the Indiana Bat and NLEB Programmatic, please run the project through IPaC. Astime is a factor, I have already completed the USFWS ETR GIS layer check during this emailreview:

    A review of the USFWS database did not indicate the presence of endangered bat species inor within 0.5 mile of the project area. The range-wide programmatic consultation for theIndiana Bat and Northern Long-eared Bat will be completed according to the most recent“Using the USFWS’s IPaC System for Listed Bat Consultation for INDOT Projects”.

    Please proceed with the field inspections for evidence of bats for the structures involved. With regards to Section 106, I agree with your assessment that no NTF to INDOT CRO is necessary. Thank you for your work on this project, Ryan FallsCapital Program Management-Senior Environmental Manager SupervisorIndiana Department of Transportation3650 South US Highway 41Vincennes, IN 47591Office: 812-895-7326Fax: 812-895-7474Cisco: 14605Email: [email protected]*I am usually only able to be reached by the above office numbera few days out of the week. Please email me inquiries if I cannot be reached.

    [facebook.com] [twitter.com] [youtube.com] [in.gov] [in.gov]

    Des. 0710929 Attachment 2 Page 1

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]://urldefense.proofpoint.com/v2/url?u=https-3A__www.facebook.com_INDOTVincennesDistrict&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=Zvf3MaZ0jBh2voBDGlgDnFkzq5P7FN_Ng2jHOGuf1lw&e=https://urldefense.proofpoint.com/v2/url?u=https-3A__www.facebook.com_INDOTVincennesDistrict&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=Zvf3MaZ0jBh2voBDGlgDnFkzq5P7FN_Ng2jHOGuf1lw&e=https://urldefense.proofpoint.com/v2/url?u=https-3A__twitter.com_indotsouthwest&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=Wnmly60IkyPc5EWlvEltI40HQdVqe7_Vhz5-8v2ibOY&e=https://urldefense.proofpoint.com/v2/url?u=https-3A__twitter.com_indotsouthwest&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=Wnmly60IkyPc5EWlvEltI40HQdVqe7_Vhz5-8v2ibOY&e=https://urldefense.proofpoint.com/v2/url?u=http-3A__www.youtube.com_user_IndianaDOT&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=wI22lURHKyN-UinNeN9lC_VuVwdaVmCSedY5Ywvlm9U&e=https://urldefense.proofpoint.com/v2/url?u=http-3A__www.youtube.com_user_IndianaDOT&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=wI22lURHKyN-UinNeN9lC_VuVwdaVmCSedY5Ywvlm9U&e=https://urldefense.proofpoint.com/v2/url?u=http-3A__www.in.gov_indot_2341.htm&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=muaa6kbVYFS-FgunyCctjMJ2dzCz-cXQLLYwZvpLA3Q&e=https://urldefense.proofpoint.com/v2/url?u=http-3A__www.in.gov_indot_2341.htm&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=muaa6kbVYFS-FgunyCctjMJ2dzCz-cXQLLYwZvpLA3Q&e=https://urldefense.proofpoint.com/v2/url?u=http-3A__www.in.gov_indot&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=kSxzsX9YVJxLJ2tZGCk73Cd8YKjly1lXR6fvXk4TrCU&e=https://urldefense.proofpoint.com/v2/url?u=http-3A__www.in.gov_indot&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=kSxzsX9YVJxLJ2tZGCk73Cd8YKjly1lXR6fvXk4TrCU&e=

  • [in.gov] From: Port, Juliet [mailto:[email protected]] Sent: Monday, October 14, 2019 3:27 PMTo: Falls, Ryan G Cc: Malone, Brian ; Miller, Daniel J ; Taylor,Matt Subject: SR 66 Intersection AI scope quick questions **** This is an EXTERNAL email. Exercise caution. DO NOT open attachments orclick links from unknown senders or unexpected email. ****

    AI for the CE-2SR 66 Intersection ImprovementSpencer Co.Des No. 0710929 Ryan, I hope you had a nice holiday weekend. I’d like to verify the scope for the AI. The CE-2 was signedand approved Aug 18, 2017.

    RFI – was signed Feb. 8, 2016. Therefore, an RFI Addendum is probably needed? Pleaseconfirm.Bats – the ECLs were sent in April 2016, therefore the project pre-dated the Indiana Bat andNLEB Programmatic. Could you please confirm if we need to apply that now and run the IPaCDetermination Key??

    If yes, we will need to go out there and inspect the structures and pipes for evidence ofbats. I’d like to do that later this week, if possible, so please let us know ASAP if this isrequired.

    Section 106 – The 800.11 Finding was “No Historic Properties Effected”. The project limits andAPE appear sufficient and the proposed right-of-way is the same. Therefore, do we need tosubmit a Note to File to INDOT-CRO ??

    I appreciate your time and assistance. Thank you, Juliet Port, LPGSenior Environmental PlannerParsons101 W Ohio, Suite 2121Indianapolis, IN 46204317-616-4693

    Des. 0710929 Attachment 2 Page 2

    https://urldefense.proofpoint.com/v2/url?u=http-3A__www.in.gov_indot_&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=H5QCUhlb8ZyRmD6drwtsLES5dowwCMmERnsOpOH83X4&e=https://urldefense.proofpoint.com/v2/url?u=http-3A__www.in.gov_indot_&d=DwMFJg&c=Nwf-pp4xtYRe0sCRVM8_LWH54joYF7EKmrYIdfxIq10&r=tZTUVq3Fp1J0AaV-EELRYlLg_UinY4QO2l2VVCH2h7U&m=DBc8uiicHi11Tu0d6JUdjPtSPOqjZunT2xramC4Kp04&s=H5QCUhlb8ZyRmD6drwtsLES5dowwCMmERnsOpOH83X4&e=mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • SR 66 Intersection Improvement – Des. 0710929

    Attachment 3

    Structure Assessment Forms

  • APPENDIX D: Bridge/Structure Assessment Form This form will be completed and submitted to the District Environmental Manager by the Contractor prior to conducting any work below the deck surface either from the underside; from activities above that bore down to the underside; from activities that could impact expansion joints; from deck removal on bridges; or from structure demolition for bridges/structures within 1000 feet of suitable bat habitat.

    DOT Project #

    0710929

    Water Body

    Huffman Drain

    Date/Time of Inspection

    10/16/2019; 10:10 am

    Within 1,000ft of suitable bat habitat (circle one)

    Yes No

    Route County Federal Structure ID

    SR 66 Spencer CV 066-74-54.00

    If the bridge/structure is 1,000 feet or more from suitable bat habitat (e.g., an urban or agricultural area without suitable foraging habitat or corridors linking the bridge to suitable foraging habitat), check box and STOP HERE. No assessment required. Please submit to the U.S. Fish and Wildlife Service.

    Areas Inspected (Check all that apply) AS SAFELY FEASIBLE

    Bridges Culverts/Other Structures Summary Info (circle all that apply)

    All vertical crevices sealed at the top and 0.5-1.25” wide & ≥4” deep

    Crevices, rough surfaces or imperfections in concrete

    X

    Human disturbance or traffic under bridge/in culvert or at the structure

    High Low

    X None

    All crevices >12” deep & not sealed

    Spaces between walls, ceiling joists

    X Possible corridors for netting

    None/poor Marginal Excellent

    All guardrails

    All expansion joints

    Spaces between concrete end walls and the bridge deck

    Vertical surfaces on concrete I-beams

    Evidence of Bats (Circle all that apply) Presence of one or more indicators is sufficient evidence that bats may be using the structure. None

    Visual (e.g. survey, thermal, emergent etc.) Guano Staining definitively from bats • Live __number seen Odor Y/N Photo documentation Y/N • Dead __number seen

    Photo documentation Y/N Photo documentation Y/N

    Audible

    Assessment Conducted By: ______________________________ Signature(s):

    District Environmental Use Only: Date Received by District Environmental Manager: ______________

    DOT Bat Assessment Form Instructions

    1. Assessments must be completed no more than 2 years prior to conducting any work below the deck surface on all bridges, regardless of whetherassessments have been conducted in the past.

    2. Any bridge/structure suspected of providing habitat for any species of bat will be removed from work schedules until such time that the DOT hascoordinated with the USFWS. Additional studies may be undertaken by the DOT to determine what species may be utilizing each structure identified assupporting bats prior to allowing any work to proceed.

    3. Any questions should be directed to the District Environmental Manager.

    Last Revised June 2017

    Juliet Port

    Des. 0710929 Attachment 3 Page 1

  • APPENDIX D: Bridge/Structure Assessment Form This form will be completed and submitted to the District Environmental Manager by the Contractor prior to conducting any work below the deck surface either from the underside; from activities above that bore down to the underside; from activities that could impact expansion joints; from deck removal on bridges; or from structure demolition for bridges/structures within 1000 feet of suitable bat habitat.

    DOT Project # 0710929

    Water Body UNTs to Huffman Drain and non-jurisdictional drainage features

    Date/Time of Inspection 10/16/2019; 10:30 am

    Within 1,000ft of suitable bat habitat (circle one)

    Yes No

    Route County Federal Structure ID

    SR 66 Spencer N/A – see attached list

    If the bridge/structure is 1,000 feet or more from suitable bat habitat (e.g., an urban or agricultural area without suitable foraging habitat or corridors linking the bridge to suitable foraging habitat), check box and STOP HERE. No assessment required. Please submit to the U.S. Fish and Wildlife Service.

    Areas Inspected (Check all that apply) AS SAFELY FEASIBLE

    Bridges Culverts/Other Structures Summary Info (circle all that apply)

    All vertical crevices sealed at the top and 0.5-1.25” wide & ≥4” deep

    Crevices, rough surfaces or imperfections in concrete

    X

    Human disturbance or traffic under bridge/in culvert or at the structure

    High Low

    X None

    All crevices >12” deep & not sealed

    Spaces between walls, ceiling joists

    X Possible corridors for netting

    None/poor Marginal Excellent

    All guardrails

    All expansion joints

    Spaces between concrete end walls and the bridge deck

    Vertical surfaces on concrete I-beams

    Evidence of Bats (Circle all that apply) Presence of one or more indicators is sufficient evidence that bats may be using the structure. None

    Visual (e.g. survey, thermal, emergent etc.) Guano Staining definitively from bats • Live __number seen Odor Y/N Photo documentation Y/N • Dead __number seen

    Photo documentation Y/N Photo documentation Y/N

    Audible

    Assessment Conducted By: ______________________________ Signature(s):

    District Environmental Use Only: Date Received by District Environmental Manager: ______________

    DOT Bat Assessment Form Instructions

    1. Assessments must be completed no more than 2 years prior to conducting any work below the deck surface on all bridges, regardless of whether assessments have been conducted in the past.

    2. Any bridge/structure suspected of providing habitat for any species of bat will be removed from work schedules until such time that the DOT has coordinated with the USFWS. Additional studies may be undertaken by the DOT to determine what species may be utilizing each structure identified as supporting bats prior to allowing any work to proceed.

    3. Any questions should be directed to the District Environmental Manager. Last Revised June 2017

    Juliet Port

    Des. 0710929 Attachment 3 Page 2

  • Culverts and Pipes inspected on October 16, 2019

    • 72-inch x 42-inch squashed corrugated metal pipe (CMP) beneath Orchard Road, south of SR 66

    • Pipes along and beneath CR 275 W/Orchard Road at the intersection of SR 66:o Three 30-inch CMPs on the west side beneath a concrete commercial driveo One 42-inch smooth-walled steel pipe (SWSP) beneath CR 275 W/Orchard Roado One 36-inch CMP beneath CR 275 W/Orchard Roado Twin 30-inch CMPs on the east side beneath the asphalt drive to the fire station

    • 66-inch CMP beneath Orchard Road, north of SR 66• Two 12-inch SWSP south of SR 66, beneath drive to multi-tenant building and Rudolph Brothers

    Des. 0710929 Attachment 3 Page 3

  • Photo 1 – View of INDOT Structure CV 066-74-54.00 facing northeast (10-16-19).

    Photo 2 – View inside INDOT Structure CV 066-74-54.00 facing north (10-16-19).

    Photo 3 – View of 72-inch by 42-inch squashed CMP facing northwest (10-16-19).

    Photo 4 – View inside squashed CMP, facing west (10-16-19).

    Des. 0710929 Attachment 3 Page 4

  • Photo 5 – View of four pipes on the west side of CR 275 facing north (10-16-19).

    Photo 6 – View inside 66-inch CMP north of SR 66, facing east (10-16-19).

    Photo 7 – View of two 30-inch CMPs east of CR 275 W facing north (10-16-19).

    Photo 8 – View of two 12-inch SWSPs south of SR 66 facing down (10-16-18).

    Des. 0710929 Attachment 3 Page 5

  • SR 66 Intersection Improvement – Des. 0710929

    Attachment 4

    USFWS Species List

  • October 23, 2019

    United States Department of the InteriorFISH AND WILDLIFE SERVICEIndiana Ecological Services Field Office

    620 South Walker StreetBloomington, IN 47403-2121

    Phone: (812) 334-4261 Fax: (812) 334-4273http://www.fws.gov/midwest/Endangered/section7/s7process/step1.html

    In Reply Refer To: Consultation Code: 03E12000-2020-SLI-0114 Event Code: 03E12000-2020-E-00594 Project Name: Des 0710929 SR 66 Intersection Improvement

    Subject: Updated list of threatened and endangered species that may occur in your proposed project location, and/or may be affected by your proposed project

    To Whom It May Concern:

    The attached species list identifies any federally threatened, endangered, proposed and candidate species that may occur within the boundary of your proposed project or may be affected by your proposed project. The list also includes designated critical habitat if present within your proposed project area or affected by your project. This list is provided to you as the initial step of the consultation process required under section 7(c) of the Endangered Species Act, also referred to as Section 7 Consultation.

    Section 7 of the Endangered Species Act of 1973 requires that actions authorized, funded, or carried out by Federal agencies not jeopardize federally threatened or endangered species or adversely modify designated critical habitat. To fulfill this mandate, Federal agencies (or their designated non-federal representative) must consult with the Service if they determine their project may affect listed species or critical habitat.

    Under 50 CFR 402.12(e) (the regulations that implement Section 7 of the Endangered Species Act) the accuracy of this species list should be verified after 90 days. This verification can be completed formally or informally. You may verify the list by visiting the ECOS-IPaC website http://ecos.fws.gov/ipac/ at regular intervals during project planning and implementation and completing the same process you used to receive the attached list. As an alternative, you may contact this Ecological Services Field Office for updates.

    Please use the species list provided and visit the U.S. Fish and Wildlife Service's Region 3 Section 7 Technical Assistance website at - http://www.fws.gov/midwest/endangered/section7/ s7process/index.html. This website contains step-by-step instructions which will help you

    Des. 0710929 Attachment 4 Page 1

  • 10/23/2019 Event Code: 03E12000-2020-E-00594 2

    determine if your project will have an adverse effect on listed species and will help lead you through the Section 7 process.

    For all wind energy projects and projects that include installing towers that use guy wires or are over 200 feet in height, please contact this field office directly for assistance, even if no federally listed plants, animals or critical habitat are present within your proposed project or may be affected by your proposed project.

    Although no longer protected under the Endangered Species Act, be aware that bald eagles are protected under the Bald and Golden Eagle Protection Act (16 U.S.C. 668 et seq.) and Migratory Bird Treaty Act (16 U.S.C. 703 et seq), as are golden eagles. Projects affecting these species may require measures to avoid harming eagles or may require a permit. If your project is near an eagle nest or winter roost area, see our Eagle Permits website at http://www.fws.gov/midwest/ midwestbird/EaglePermits/index.html to help you determine if you can avoid impacting eagles or if a permit may be necessary.

    We appreciate your concern for threatened and endangered species. Please include the Consultation Tracking Number in the header of this letter with any request for consultation or correspondence about your project that you submit to our office.

    Attachment(s):

    Official Species List

    Des. 0710929 Attachment 4 Page 2

  • 10/23/2019 Event Code: 03E12000-2020-E-00594 1

    Official Species ListThis list is provided pursuant to Section 7 of the Endangered Species Act, and fulfills the requirement for Federal agencies to "request of the Secretary of the Interior information whether any species which is listed or proposed to be listed may be present in the area of a proposed action".

    This species list is provided by:

    Indiana Ecological Services Field Office620 South Walker StreetBloomington, IN 47403-2121(812) 334-4261

    Des. 0710929 Attachment 4 Page 3

  • 10/23/2019 Event Code: 03E12000-2020-E-00594 2

    Project SummaryConsultation Code: 03E12000-2020-SLI-0114

    Event Code: 03E12000-2020-E-00594

    Project Name: Des 0710929 SR 66 Intersection Improvement

    Project Type: TRANSPORTATION

    Project Description: The proposed project is an intersection improvement at SR 66 and CR 275 W/Orchard Road in the unincorporated community of Reo, Spencer County, Indiana. Topography in the project area is flat, with adjacent land use consisting of commercial and agricultural to the northeast, South Spencer High School to the northwest, commercial to the southwest, and a fire department to the southeast. The purpose of this project is to the improve the safety and capacity of the intersection, and to ensure a safe and hydraulically adequate crossing of SR 66 over Huffman Drain. This segment of SR 66 consists of two 12-foot lanes, with paved shoulders that range in width from one to two feet. It has dedicated right- turn lanes in each direction. The northbound Orchard Road approach has two 12-foot travel lanes and an additional 12-foot left turn lane. The south Orchard Road approach is a single 12-foot lane that widens into two 12- foot lanes at the intersection. The preferred alternative includes a mill and overlay of existing pavement, widening the intersection to accommodate added left turn only lanes along SR 66, drainage improvements, an upgraded signal, and upgraded signs. Travel lanes in all directions would remain unchanged. As part of this project, several pipes and culverts will be replaced, including INDOT Structure CV 066-074-54.00. The project will not work on existing permanent lighting. During construction, temporary lighting may be used, and the intersection will remain open to traffic along SR 66. The area will be restricted to one lane of traffic, which will be controlled by signals. Traffic traveling north- and south-bound along Orchard Road will experience temporary disruptions requiring detours via local roads, SR 161, and SR 66. The project is scheduled to begin in the Spring of 2020 and work will occur year-round. All work will occur within 50 feet of the existing edge of pavement. A total of 0.82 acre of permanent right-of-way and up to 0.5 acre of temporary right-of-way will be acquired for this project.

    Des. 0710929 Attachment 4 Page 4

  • 10/23/2019 Event Code: 03E12000-2020-E-00594 3

    Suitable summer habitat is present approximately 600 feet northwest of the western project limits. Additionally, there is a narrow, vegetated corridor along Huffman Drain. There are no trees within the project area, therefore this project does not include tree clearing or trimming. A review of the USFWS database on October 15, 2019 did not indicate the presence of endangered bat species in or within 0.5 mile of the project area. The culverts and pipes were inspected on October 16, 2019. No evidence for the presence of bats was encountered.

    Project Location:Approximate location of the project can be viewed in Google Maps: https:// www.google.com/maps/place/37.90165029422813N87.1066589245271W

    Counties: Spencer, IN

    Des. 0710929 Attachment 4 Page 5

  • 10/23/2019 Event Code: 03E12000-2020-E-00594 4

    1.

    Endangered Species Act SpeciesThere is a total of 4 threatened, endangered, or candidate species on this species list.

    Species on this list should be considered in an effects analysis for your project and could include species that exist in another geographic area. For example, certain fish may appear on the species list because a project could affect downstream species. Note that 1 of these species should be considered only under certain conditions.

    IPaC does not display listed species or critical habitats under the sole jurisdiction of NOAA Fisheries , as USFWS does not have the authority to speak on behalf of NOAA and the Department of Commerce.

    See the "Critical habitats" section below for those critical habitats that lie wholly or partially within your project area under this office's jurisdiction. Please contact the designated FWS office if you have questions.

    NOAA Fisheries, also known as the National Marine Fisheries Service (NMFS), is an office of the National Oceanic and Atmospheric Administration within the Department of Commerce.

    MammalsNAME STATUS

    Gray Bat Myotis grisescensNo critical habitat has been designated for this species.Species profile: https://ecos.fws.gov/ecp/species/6329

    Endangered

    Indiana Bat Myotis sodalisThere is final critical habitat for this species. Your location is outside the critical habitat.Species profile: https://ecos.fws.gov/ecp/species/5949Species survey guidelines:

    https://ecos.fws.gov/ipac/guideline/survey/population/1/office/31440.pdf

    Endangered

    Northern Long-eared Bat Myotis septentrionalisNo critical habitat has been designated for this species.This species only needs to be considered under the following conditions:

    Incidental take of the NLEB is not prohibited here. Federal agencies may consult using the 4(d) rule streamlined process. Transportation projects may consult using the programmatic process. See www.fws.gov/midwest/endangered/mammals/nleb/index.html

    Species profile: https://ecos.fws.gov/ecp/species/9045

    Threatened

    1

    Des. 0710929 Attachment 4 Page 6

  • 10/23/2019 Event Code: 03E12000-2020-E-00594 5

    BirdsNAME STATUS

    Least Tern Sterna antillarumPopulation: interior pop.No critical habitat has been designated for this species.Species profile: https://ecos.fws.gov/ecp/species/8505

    Endangered

    Critical habitatsTHERE ARE NO CRITICAL HABITATS WITHIN YOUR PROJECT AREA UNDER THIS OFFICE'S JURISDICTION.

    Des. 0710929 Attachment 4 Page 7

  • SR 66 Intersection Improvement – Des. 0710929

    Attachment 5

    USFWS Concurrence Verification Letter

  • October 24, 2019

    United States Department of the InteriorFISH AND WILDLIFE SERVICEIndiana Ecological Services Field Office

    620 South Walker StreetBloomington, IN 47403-2121

    Phone: (812) 334-4261 Fax: (812) 334-4273http://www.fws.gov/midwest/Endangered/section7/s7process/step1.html

    In Reply Refer To: Consultation Code: 03E12000-2020-I-0114 Event Code: 03E12000-2020-E-00598 Project Name: Des 0710929 SR 66 Intersection Improvement

    Subject: Concurrence verification letter for the 'Des 0710929 SR 66 Intersection Improvement' project under the revised February 5, 2018, FHWA, FRA, FTA Programmatic Biological Opinion for Transportation Projects within the Range of the Indiana Bat and Northern Long-eared Bat.

    To whom it may concern:

    The U.S. Fish and Wildlife Service (Service) has received your request dated to verify that the Des 0710929 SR 66 Intersection Improvement (Proposed Action) may rely on the concurrence provided in the February 5, 2018, FHWA, FRA, FTA Programmatic Biological Opinion for Transportation Projects within the Range of the Indiana Bat and Northern Long-eared Bat (PBO) to satisfy requirements under Section 7(a)(2) of the Endangered Species Act of 1973 (ESA) (87 Stat. 884, as amended; 16 U.S.C 1531 et seq.).

    Based on the information you provided (Project Description shown below), you have determined that the Proposed Action is within the scope and adheres to the criteria of the PBO, including the adoption of applicable avoidance and minimization measures, may affect, but is not likely to adversely affect (NLAA) the endangered Indiana bat (Myotis sodalis) and/or the threatened Northern long-eared bat (Myotis septentrionalis).

    The Service has 14 calendar days to notify the lead Federal action agency or designated non- federal representative if we determine that the Proposed Action does not meet the criteria for a NLAA determination under the PBO. If we do not notify the lead Federal action agency or designated non-federal representative within that timeframe, you may proceed with the Proposed Action under the terms of the NLAA concurrence provided in the PBO. This verification period allows Service Field Offices to apply local knowledge to implementation of the PBO, as we may identify a small subset of actions having impacts that were unanticipated. In such instances, Service Field Offices may request additional information that is necessary to verify inclusion of the proposed action under the PBO.

    Des. 0710929 Attachment 5 Page 1

  • 10/24/2019 Event Code: 03E12000-2020-E-00598 2

    For Proposed Actions that include bridge/structure removal, replacement, and/or maintenance activities: If your initial bridge/structure assessments failed to detect Indiana bats, but you later detect bats during construction, please submit the Post Assessment Discovery of Bats at Bridge/Structure Form (User Guide Appendix E) to this Service Office. In these instances, potential incidental take of Indiana bats may be exempted provided that the take is reported to the Service.

    If the Proposed Action is modified, or new information reveals that it may affect the Indiana bat and/or Northern long-eared bat in a manner or to an extent not considered in the PBO, further review to conclude the requirements of ESA Section 7(a)(2) may be required. If the Proposed Action may affect any other federally-listed or proposed species, and/or any designated critical habitat, additional consultation is required. If the proposed action has the potential to take bald or golden eagles, additional coordination with the Service under the Bald and Golden Eagle Protection Act may also be required. In either of these circumstances, please contact this Service Office.

    The following species may occur in your project area and are not covered by this determination:

    Gray Bat, Myotis grisescens (Endangered)Least Tern, Sterna antillarum (Endangered)

    Des. 0710929 Attachment 5 Page 2

  • 10/24/2019 Event Code: 03E12000-2020-E-00598 3

    Project DescriptionThe following project name and description was collected in IPaC as part of the endangered species review process.

    Name

    Des 0710929 SR 66 Intersection Improvement

    Description

    Des. 0710929 Attachment 5 Page 3

  • 10/24/2019 Event Code: 03E12000-2020-E-00598 4

    The proposed project is an intersection improvement at SR 66 and CR 275 W/Orchard Road in the unincorporated community of Reo, Spencer County, Indiana. Topography in the project area is flat, with adjacent land use consisting of commercial and agricultural to the northeast, South Spencer High School to the northwest, commercial to the southwest, and a fire department to the southeast. The purpose of this project is to the improve the safety and capacity of the intersection, and to ensure a safe and hydraulically adequate crossing of SR 66 over Huffman Drain. This segment of SR 66 consists of two 12-foot lanes, with paved shoulders that range in width from one to two feet. It has dedicated right-turn lanes in each direction. The northbound Orchard Road approach has two 12-foot travel lanes and an additional 12-foot left turn lane. The south Orchard Road approach is a single 12-foot lane that widens into two 12-foot lanes at the intersection. The preferred alternative includes a mill and overlay of existing pavement, widening the intersection to accommodate added left turn only lanes along SR 66, drainage improvements, an upgraded signal, and upgraded signs. Travel lanes in all directions would remain unchanged. As part of this project, several pipes and culverts will be replaced, including INDOT Structure CV 066-074-54.00. The project will not work on existing permanent lighting. During construction, temporary lighting may be used, and the intersection will remain open to traffic along SR 66. The area will be restricted to one lane of traffic, which will be controlled by signals. Traffic traveling north- and south-bound along Orchard Road will experience temporary disruptions requiring detours via local roads, SR 161, and SR 66. The project is scheduled to begin in the Spring of 2020 and work will occur year-round. All work will occur within 50 feet of the existing edge of pavement. A total of 0.82 acre of permanent right-of-way and up to 0.5 acre of temporary right-of-way will be acquired for this project. Suitable summer habitat is present approximately 600 feet northwest of the western project limits. Additionally, there is a narrow, vegetated corridor along Huffman Drain. There are no trees within the project area, therefore this project does not include tree clearing or trimming. A review of the USFWS database on October 15, 2019 did not indicate the presence of endangered bat species in or within 0.5 mile of the project area. The culverts and pipes were inspected on October 16, 2019. No evidence for the presence of bats was encountered.

    Des. 0710929 Attachment 5 Page 4

  • 10/24/2019 Event Code: 03E12000-2020-E-00598 5

    1.

    2.

    3.

    4.

    5.

    Determination Key ResultBased on your answers provided, this project(s) may affect, but is not likely to adversely affect the endangered Indiana bat and/or the threatened Northern long-eared bat. Therefore, consultation with the U.S. Fish and Wildlife Service pursuant to Section 7(a)(2) of the Endangered Species Act of 1973 (ESA) (87 Stat. 884, as amended 16 U.S.C. 1531 et seq.) is required. However, also based on your answers provided, this project may rely on the concurrence provided in the revised February 5, 2018, FHWA, FRA, FTA Programmatic Biological Opinion for Transportation Projects within the Range of the Indiana Bat and Northern Long-eared Bat.

    Qualification InterviewIs the project within the range of the Indiana bat ?

    [1] See Indiana bat species profile

    Automatically answeredYes

    Is the project within the range of the Northern long-eared bat ?

    [1] See Northern long-eared bat species profile

    Automatically answeredYes

    Which Federal Agency is the lead for the action?A) Federal Highway Administration (FHWA)

    Are all project activities limited to non-construction activities only? (examples of non- construction activities include: bridge/abandoned structure assessments, surveys, planning and technical studies, property inspections, and property sales)

    [1