RCC Overtopping Construction Case Studies and Lessons Learned Jeremy Young, PE May 6, 2015

Upload: jeremy-young-pe

Post on 21-Aug-2015

32 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RCC OT Case Studies - JYoung RCC2015

RCC Overtopping Construction Case Studies and Lessons Learned

Jeremy Young, PEMay 6, 2015

Page 2: RCC OT Case Studies - JYoung RCC2015

POE DAM – CENTRE CO., PAExisting Conditions

33’ High Earth DamMasonry Ogee and Chute30-inch Dia. CMP Outlet Conduit

Page 3: RCC OT Case Studies - JYoung RCC2015
Page 4: RCC OT Case Studies - JYoung RCC2015

POE DAM – CENTRE CO., PADam Safety Upgrades

Grout SpillwayReplace Outlet TowerSlipline/Extend Outlet ConduitRCC Embankment Armoring

Page 5: RCC OT Case Studies - JYoung RCC2015

Poe Dam, PA – Cross Section

Page 6: RCC OT Case Studies - JYoung RCC2015

Conduit Extension

Poe Dam, PA

Page 7: RCC OT Case Studies - JYoung RCC2015

Conduit Extension

Poe Dam, PA

Page 8: RCC OT Case Studies - JYoung RCC2015

Outlet Apron

Poe Dam, PA

Page 9: RCC OT Case Studies - JYoung RCC2015

RCC Apron Reinforcing

Poe Dam, PA

Page 10: RCC OT Case Studies - JYoung RCC2015

RCC Apron Reinforcing

Poe Dam, PA

Page 11: RCC OT Case Studies - JYoung RCC2015

Sloping RCC Apron

Poe Dam, PA

Page 12: RCC OT Case Studies - JYoung RCC2015

Drainfill Placement

Poe Dam, PA

Page 13: RCC OT Case Studies - JYoung RCC2015

Drainfill Placement

Fox Creek Dam, KY

Page 14: RCC OT Case Studies - JYoung RCC2015

Aggregate Stockpiling and RCC Mixing

Poe Dam, PA

Crushed Aggregate

One Pile – Dense Graded Road Base

2-inch MSA

Page 15: RCC OT Case Studies - JYoung RCC2015

Crest Detail

Poe Dam, PA

Page 16: RCC OT Case Studies - JYoung RCC2015

Endsill

Poe Dam, PA

Page 17: RCC OT Case Studies - JYoung RCC2015

Completed RCC/Final Site Grading

Poe Dam, PA

Page 18: RCC OT Case Studies - JYoung RCC2015

Completed 2008

$3.7M Total LS Bid

Unknown RCC Unit Price

10,600 CY RCC

400 LBS Cement/CY

Vebe 30 ± 5 seconds

Poe Dam, PA

Summary

Page 19: RCC OT Case Studies - JYoung RCC2015

LAKE ONEIDA DAMBUTLER CO., PAExisting Conditions

31’ High Earth DamProjecting Concrete Weir and ChuteTwo 30-inch Dia. DIP Blow-off/Supply Line

Page 20: RCC OT Case Studies - JYoung RCC2015

LAKE ONEIDA DAMBUTLER CO., PADam Safety Upgrades

Replace SpillwayRelocate Blow-off LineRCC Embankment Armoring

Page 21: RCC OT Case Studies - JYoung RCC2015

Lake Oneida Dam - Stream Diversion

Page 22: RCC OT Case Studies - JYoung RCC2015

Phased RCC Placement

Lake Oneida Dam, PA

Page 23: RCC OT Case Studies - JYoung RCC2015

Phased RCC Placement

Lake Oneida Dam, PA

Page 24: RCC OT Case Studies - JYoung RCC2015

RCC Apron

Lake Oneida Dam, PA

Page 25: RCC OT Case Studies - JYoung RCC2015

Conventional Concrete Training Wall On Unformed Steps

Lake Oneida Dam, PA

Page 26: RCC OT Case Studies - JYoung RCC2015

Lake Oneida Dam - Summary

Completed 2013 $6.9M Total Cost $103/CY 14,200 CY RCC 350 LBS C+FA/CY 35% Fly Ash (by wt.) 2 Piles

Natural River Sand Crushed OGS – 1.5” MSA

Vebe 30 ± 5 sec

Page 27: RCC OT Case Studies - JYoung RCC2015

Stoney Creek Dam – Bedford, VA

Conventional Concrete Training Walls On Formed Steps

Page 28: RCC OT Case Studies - JYoung RCC2015

Stoney Creek Dam – Bedford, VA

Converging Training Walls

Page 29: RCC OT Case Studies - JYoung RCC2015

Bear Creek Dam – Wise, VA

More Converging Training Walls

Page 30: RCC OT Case Studies - JYoung RCC2015

Unformed/Exposed Steps Allowed by USACE

Picatinny Arsenal, NJ

Photos courtesy of KC Construction

Page 31: RCC OT Case Studies - JYoung RCC2015

Control/Diversion of Water

Fox Creek, KY

Page 32: RCC OT Case Studies - JYoung RCC2015

GERCC Steps

Fox Creek, KY

Page 33: RCC OT Case Studies - JYoung RCC2015

Exposed GERCC Steps/Shrinkage Crack

Fox Creek, KY

Page 34: RCC OT Case Studies - JYoung RCC2015

Ogee Control Section

Fox Creek, KY

Page 35: RCC OT Case Studies - JYoung RCC2015

Fox Creek Dam, KY - Summary

Completed March 2011

$155/CY Avg Bid Price

10,000 CY RCC

400 LBS C+FA/CY

50% Fly Ash (by Wt.)

2 Piles

Natural River Sand

Crushed #8/#57 - 1.5” MSA

Vebe 20 secs

Page 36: RCC OT Case Studies - JYoung RCC2015

Armored Section Adjacent to Replacement Spillway

Lower Owl Creek Dam, PA

Page 37: RCC OT Case Studies - JYoung RCC2015

Lower Owl Creek Dam, PA

Page 38: RCC OT Case Studies - JYoung RCC2015

Sally’s Pond Dam, NJ

Page 39: RCC OT Case Studies - JYoung RCC2015

Sally’s Pond Dam - Design Concept

Page 40: RCC OT Case Studies - JYoung RCC2015

Sally’s Pond Dam - Construction

Page 41: RCC OT Case Studies - JYoung RCC2015

Sally’s Pond Dam - Construction

Page 42: RCC OT Case Studies - JYoung RCC2015

Sally’s Pond Dam - Construction

Page 43: RCC OT Case Studies - JYoung RCC2015

Sally’s Pond Dam, NJ

Completed 2008$1.8 M Total LS Bid2,400 CY RCC330 Lbs Cement/CY1.5” MSAVebe 30±5 sec

Page 44: RCC OT Case Studies - JYoung RCC2015

Questions/Comments?