rc bq 2010 master copy

82
Steel Bar & Concrete Estimation Calculation Notes: Density of Steel 7850 kg/m3 15.15 0 Lapping per steel 40 D 1 L 2 3 2 Wall reinforcement : Bi = Bottom internal; Be = Bottom External; Ui = Upper internal; Ue = Upper external Slab reinforcement : T = Top layer; B = Bottom layer H Only key in column in blue colour 3 t wall I I I I I = S 2-3 S 1-2 Wall Ref. Length Height Thickness Nos. Spacing-V Size - V Spacing - H Size - H Lapping Nos-V Nos-H Length-V Length-H Weight - MT m m m mm mm mm mm m m m kg AT Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 100 12 0.0 0.0 0.0 0.0 0.0 AT Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 100 12 0.0 0.0 0.0 0.0 0.0 ECONDARY CLARIFIER Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.000 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.000 0 150 12 100 12 0.0 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.00 0 150 12 150 12 0.0 0.0 0.0 0.0 Be 0 0 0.00 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Bi 0 0 0.00 0 150 12 150 12 0.0 0.0 0.0 0.0 0.0 Be 0 0 0.00 0 150 12 100 12 0.0 0.0 0.0 0.0 0.0

Upload: nuriasnizamnurisham

Post on 07-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 1/82

Steel Bar & Concrete Estimation Calculation

Notes:Density of Steel 7850 kg/m3 15.15 0

Lapping per steel 40 D

1 L 2Wall reinforcement : Bi = Bottom internal; Be = Bottom External; Ui = Upper internal; Ue = Upper externalSlab reinforcement : T = Top layer; B = Bottom layer H

Only key in column in blue colour 3

wall I I I I I = S 2-3 S 1-2Wall Ref. Length Height Thickness Nos. Spacing-V Size - V Spacing - H Size - H Lapping Nos-V NoMT m m m mm mm mm mm mAT Bi 0 0 0.000 0 150 12 150 12 0.0 0

Be 0 0 0.000 0 150 12 150 12 0.0 0.0

Bi 0 0 0.000 0 150 12 150 12 0.0 0Be 0 0 0.000 0 150 12 150 12 0.0 0.0

Bi 0 0 0.000 0 150 12 150 12 0.0 0Be 0 0 0.000 0 150 12 100 12 0.0 0.0

AT Bi 0 0 0.000 0 150 12 150 12 0.0 0Be 0 0 0.000 0 150 12 150 12 0.0 0.0

Bi 0 0 0.000 0 150 12 150 12 0.0 0Be 0 0 0.000 0 150 12 150 12 0.0 0.0

Bi 0 0 0.000 0 150 12 150 12 0.0 0Be 0 0 0.000 0 150 12 100 12 0.0 0.0

ECONDARY CLARIFIER Bi 0 0 0.000 0 150 12 150 12 0.0 0

Be 0 0 0.000 0 150 12 150 12 0.0 0.0

Bi 0 0 0.000 0 150 12 150 12 0.0 0Be 0 0 0.000 0 150 12 150 12 0.0 0.0

Bi 0 0 0.000 0 150 12 150 12 0.0 0Be 0 0 0.000 0 150 12 100 12 0.0 0.0

0.0Bi 0 0 0.00 0 150 12 150 12 0.0 0Be 0 0 0.00 0 150 12 150 12 0.0 0.0

Bi 0 0 0.00 0 150 12 150 12 0.0 0Be 0 0 0.00 0 150 12 100 12 0.0 0.0

Page 2: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 2/82

ANOXIC TANK Bi 0 0 0.00 0 150 12 150 12 0.0Be 0 0 0.00 0 150 12 150 12 0.0 0.0

Bi 0 0 0.00 0 150 12 150 12 0.0Be 0 0 0.00 0 150 12 150 12 0.0 0.0

Channel Bi 0 0 0.00 0 150 12 150 12 0.0Be 0 0 0.00 0 150 12 150 12 0.0 0.0

Bi 0 0 0.00 0 150 12 150 12 0.0Be 0 0 0.00 0 150 12 150 12 0.0 0.0

CHLORINATION Bi 0 0 0.00 0 200 12 200 12 0.0Be 0 0 0.00 0 200 12 200 12 0.0 0.0

Bi 0 0 0.00 0 200 12 200 12 0.0Be 0 0 0.00 0 200 12 200 12 0.0 0.0

Bi 0 0 0.000 0 200 12 200 12 0.0Be 0 0 0.000 0 200 12 200 12 0.0 0.0

Bi 0.00 0 0.00 0 200 12 200 12 0.0Be 0 0 0.00 0 200 12 200 12 0.0 0.0

Bi 0 0 0.00 0 200 12 200 12 0.0Be 0 0 0.00 0 200 12 200 12 0.0 0.0

Bi 0 0 0.00 0 200 12 200 12 0.0Be 0 0 0.00 0 200 12 200 12 0.0 0.0

Bi 0 0 0.20 0 200 12 200 12 0.0Be 0 0 0.20 0 200 12 200 12 0.0 0.0

Bi 0 0 0.00 0 200 12 200 12 0.0Be 0 0 0.00 0 200 12 200 12 0.0 0.0

PS Bi 0 0 0.00 0 175 12 175 12 0.0Be 0 0 0.00 0 175 12 175 12 0.0 0.0

Bi 0 0 0.00 0 175 12 175 12 0.0Be 0 0 0.00 0 175 12 175 12 0.0 0.0

Bi 0 0 0.00 0 175 12 175 12 0.0Be 0 0 0.00 0 175 12 175 12 0.0 0.0

Bi 0 0 0.00 0 175 12 175 12 0.0Be 0 0 0.00 0 175 12 175 12 0.0 0.0

Page 3: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 3/82

Bi 0 0 0.00 0 175 12 175 12 0.0Be 0 0 0.00 0 175 12 175 12 0.0 0.0

Bi 0 0 0.00 0 175 12 175 12 0.0Be 0 0 0.00 0 175 12 175 12 0.0 0.0

20 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

21 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

20 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

21 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

22 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

23 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

24 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

25 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

26 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

27 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

28 Bi 0 0 0.00 0 175 12 200 12 0.0

Page 4: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 4/82

Be 0 0 0.00 0 175 12 200 12 0.0 0.0

29 Bi 0 0 0.00 0 175 12 200 12 0.0Be 0 0 0.00 0 175 12 200 12 0.0 0.0

3 0.48 1.44 1.44 0Slab Reinforcement Calculation 1 L 2

w Nos-V No3

Slab S 2-3 S 1-2Slab Ref. Length Width Thickness Nos. Spacing- L Size - L Spacing - W Size - W Nos-L Nos-W LengMT m m m mm mm mm mmAT T 0 0 0.00 0 150 12 150 12 0 0

B 0 0 0.00 0 150 12 150 12 0 0 0.0

ECONDARY CLARIFIER T 0 0 0.00 0 150 12 150 12 0 0B 0 0 0.00 0 150 12 150 12 0 0 0.0

ANOXIC TANK T 0 0 0.00 0 150 12 150 12 0 0B 0 0 0.00 0 150 12 150 12 0 0 0.0

Channel T 0 0 0.00 0 150 12 150 12 0 0B 0 0 0.00 0 150 12 150 12 0 0 0.0

CHLORINATION T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

By pass Channel T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

Page 5: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 5/82

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

LEANMain tank T 0 0 0 0 200 12 200 12 0 0

B-D B 0 0 0.00 0 200 12 200 12 0 0 0.0

A-B T 0 0 0 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

PS T 0 0 0.00 0 200 12 200 12 0 01-2-9-10 B 0 0 0.00 0 200 12 200 12 0 0 0.0

2-3-7-8 T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

3-4-5-6 T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

CR T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

CC T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

Page 6: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 6/82

SSH T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

SD T 0 0 0.00 0 200 12 200 12 0 0B 0 0 0.00 0 200 12 200 12 0 0 0.0

L WBeam H

Beam 1 sideLength Width Height Nos. R-Spacing R-Size Nos-Y Y-size Nos-R Length-R

MT m mm mm mm mm mm LappingCM1 0 150 300 0 125 6 4 16 0 0.0

4 16 0

BM1 BM.1.1 5.8 150 450 0 125 6 2 12 0.75 0.02 25 0

BM1 BM.1.2 2.2 150 450 0 100 6 2 25 0.75 0.02 25 0.75

BM1 BM.1.3 2.2 150 450 0 125 6 2 25 0 0.02 20 0

BM1 BM.1.4 3.65 150 450 0 175 6 2 12 1.5 0.02 20 0

BM1 BM.1.5 4.3 150 450 0 125 6 2 25 0 0.02 20 0.75

BM1 BM.1.6 3.65 150 450 0 175 6 2 12 1.5 0.02 20 0

BM1 BM.1.7 2.2 150 450 0 125 6 2 25 0 0.02 20 0

BM1 BM.1.8 2.2 150 450 0 100 6 2 25 0.75 0.02 25 0.75

BM1 BM.1.9 5.8 150 450 0 125 6 2 12 0.75 0.02 25 0

BM2 BM.2.1 5.8 150 450 0 175 6 2 12 0.75 0.02 20 0

BM2 BM.2.2 2.2 150 450 0 125 6 2 25 0.75 0.02 20 0.75

Page 7: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 7/82

BM2 BM.2.3 2.2 150 450 0 125 6 2 25 0 0.02 16 0

BM2 BM.2.4 3.65 150 450 0 175 6 2 12 1.5 0.02 16 0

BM2 BM.2.5 4.3 150 450 0 175 6 2 25 0 0.02 16 0.75

BM2 BM.2.6 3.65 150 450 0 175 6 2 12 1.5 0.02 16 0

BM2 BM.2.7 2.2 150 450 0 125 6 2 25 0 0.02 16 0

BM2 BM.2.8 2.2 150 450 0 100 6 2 25 0.75 0.02 20 0.75

BM2 BM.2.9 5.8 150 450 0 125 6 2 12 0.75 0.02 20 0

BM3 BM.3.1 2.15 150 450 0 175 6 2 12 0 0.02 12 0

BM3 BM.3.2 1.95 150 450 0 175 6 2 12 0 0.02 12 0

0 0 0 0 175 6 2 12 0 0.02 12 0

0 125 175 0 175 6 2 12 0 0.02 12 0

0 0 0 0 175 6 2 12 0 0.02 12 0

0 125 175 0 175 6 2 12 0 0.02 12 0

Dowel Length Dowel leng. Nos. Spacing Size Length1 0 0 0 150 12

2 0 0 0 100 12

3 0 0 0 150 12

BRC Type Length Width Area Layer Nos. Thickness G Concrete needed, m 3

Page 8: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 8/82

AT AT.1 A7 2.05 7.93 0 2 0 0.15 25 0.00

AT.2 A7 2.05 7.85 0 2 0 0.15 25 0.00

AT.3 A7 1.8 7.93 0 2 0 0.15 25 0.00

AT.4 A7 1.8 7.85 0 2 0 0.13 25 0.00

ECONDARY CLARIFIER SC.1 A7 27.9 1.2 0 2 0 0.13 25 0.00

A7 3.6 5 0 2 0 0.13 35 0.00

A7 3.6 6.18 0 2 0 0.13 35 0.00

A7 5.6 5.5 0 2 0 0.13 35 0.00

A7 0.6 0.5 0 2 0 0.13 35 0.00

A7 1.95 1.95 0 2 0 0.13 25 0.00

A7 0 0 0 1 0 0.13 35 0.00

2 A7 0 0 0 1 0 0.13 25 0.00

3 A7 0 0 0 0 0 0 0 0.00

14 A7 0 0 0 0 0 0 0 0.00

15 A7 0 0 0 0 0 0 0 0.00

16 A7 0 0 0 0 0 0 0 0.00

CL Slope A7 3.3 4.6 0 1 0 0.15 35 0

Chamfer Lapping Wall Length T-Spacing pcs No. Y Diameter Y Bar Length KG0 200 0 0 12 2.09 1.86 0.00

0 200 0 0 12 2.09 1.86 0.00

L Lapping Wall Length T-Spacing pcs No. Y Diameter Y Bar Length KG32 100 320 0 12 2.2 1.96 0.007.7 100 77 0 12 2.2 1.96 0.00

8.22 100 83 0 12 2.2 1.96 0.0027.9 100 279 0 12 2.2 1.96 0.00

Page 9: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 9/82

7.85 100 79 0 12 2.1 1.87 0.000 100 0 0 12 2.2 1.96 0.00

Page 10: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 10/82

Grade Concrete Formwork M Run Side Area(paint)

0.0 0 0 1.5 #DIV/0!35 0.0 0 TRUE

0.0 0 0 1.5 #DIV/0!35 0.0 0 TRUE

0.0 0 0 1.5 #DIV/0!35 0.0 0 TRUE

0.0 0 0 1 #DIV/0!35 0.0 0 TRUE

0.0 0 0 1 #DIV/0!35 0.0 0 TRUE

0.0 0 0 1 #DIV/0!35 0.0 0 TRUE

0.0 0 0 1.5 0.00

35 0.0 0 TRUE

0.0 0 0 1.5 0.0035 0.0 0 TRUE

0.0 0 0 1.5 0.0035 0.0 0 TRUE

0.0 0 0 2 0.0035 0.0 0 TRUE

0.0 0 0 2 0.0035 0.0 0 TRUE

m 3

Page 11: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 11/82

0.0 0 0 1 0.0035 0.0 0 TRUE

0.0 0 0 2 0.0035 0.0 0 TRUE

0.0 0 0 2 0.0035 0.0 0 TRUE

0.0 0 0 1 0.0035 0.0 0 TRUE

0.0 0 0 2 0.0035 0.0 0 TRUE

0.0 0 0 2 0.0035 0.0 0 TRUE

0.0 0 0 2 0.0035 0.0 0 TRUE

0.0 0 0 1 0.0035 0.0 0 TRUE

0.0 0 0 1 0.0035 0.0 0 TRUE

0.0 0 0 1 0.0035 0.0 0 TRUE

0.0 0 0 1 0.0035 0.0 0 TRUE

0.0 0 0 1 0.00 #DIV/0! 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

Page 12: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 12/82

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

0.0 0 0

Page 13: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 13/82

35 0.0 0 TRUE

0.0 0 035 0.0 0 TRUE

41 0

Concrete F W Aream Run

0.0 0 0.00.0

0.0 0 0.00.0

0.0 0 0.00.0

0.0 0 0.00.0

0.0 0 0.00.0

0.0 0 0.00.0

0.0 0 0.00.0

0.0 0 0.0 0.00.0

0.0 0 0.00.0

0.0 00.0

0.0 00.0

0.0 00.0

m 3

Page 14: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 14/82

0.0 00.0

0.0 00.0

0.0 00.0

0.0 00.0

0.0 00.0

0.00.0

0.00.0

0.00.0

0.00.0

0.00.0

0.00.0

0.00.0

Page 15: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 15/82

0.00.0

0.00.0

Concrete

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

Page 16: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 16/82

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

Page 17: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 17/82

Page 18: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 18/82

Page 19: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 19/82

Pump sump

Depth, m Length, m Width, m Nos1-2-9-10 6.74 3.15 2.13 0 0.0002-3-7-8 6.02 4.25 4.05 0 0.0003-4-5-6 5.87 1.65 1.4 0 0.000

0.000

Main tank

Depth, m Length, m Width, m NosA-B 3.8 7.67 4 0 0.00B-D 4 13.33 12.25 0 0.00

3 0.004 0.005 0.00

6 0.007 0.00

0.00

Chlorination chamber

Depth, m Length, m Width, m Nos1.55 2.85 3.83 0 0.000

Secondary screen & grit chamber

Depth, m Length, m Width, m Nos0 0 0 0 0.000

Manhole

Depth, m Length, m Width, m Nos0.55 0.6 0.6 12 2.376

Sand drying bed

Depth, m Length, m Width, m Nos0.7 2.05 7.93 0 0.00

Total excavation = 0.00

Labour & Machinery

Nos Period, day Rate/day, RM Amount, RM

Volume, m 3

Volume, m 3

Volume, m 3

Volume, m 3

Volume, m 3

Volume, m 3

Capacity, m 3/day

Page 20: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 20/82

JCB 1 160 0 380.00 -Lorry 2 50 0 420.00 -Excavator 1 250 0 700.00 -

Labour 3 0 50.00 -

Total = -

-Rate of excavation/m 3 =

Page 21: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 21/82

m3

Page 22: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 22/82

Page 23: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 23/82

Summary Of Bill

Wastage 3%

Y Bar size Weight, kg Weight, tonne* Oder R Bar size Weight, kg Weight, tonne*6 0 0.00 6 0.00 0.008 0 0.00 8 0.00 0.00

10 0 0.00 10 0.00 0.0012 0 0.00 12 0.00 0.0016 0 0.00 16 0.00 0.00

20 0 0.00 20 0.00 0.0025 0 0.00 25 0.00 0.0032 0 0.00 32 0.00 0.0040 0 0.00 40 0.00 0.00

TOTAL 0.00 0.00 TOTAL 0.00 0.00

* Include wastage

BRC Pics (2.2m x 6m)A5 0 0.00A6 0 0.00A7 0 0.00A8 0 0.00A9 0 0.00A10 0 0.00

no of holeInner Unit size unit per Formwork 8 Base Fwork size total M run

0.13 0.00 0.0 0 0.13 0.0 9.00.15 0.00 0.0 0 0.15 0.0 8.00.18 0.00 0.0 0 0.18 0.0 6.00.2 0.00 0.0 0 0.2 0.0 6.0

0.23 0.00 0.0 0 0.23 0.0 5.00.25 0.00 0.0 0 0.25 0.0 4.00.28 0.00 0.0 0 0.28 0.0 4.00.3 0.00 0.0 0 0.3 0.0 4.0

0.33 0.00 0.0 0 0.33 0.0 3.00.35 0.00 0.0 0 0.35 0.0 3.00.38 0.00 0.0 0 0.38 0.0 3.0

0.4 0.00 0.0 0 0.4 0.0 3.00.45 0.00 0.0 0 0.45 0.0 2.00.5 0.00 0.0 0 0.5 0.0 2.0

0.55 0.00 0.0 0 0.55 0.0 2.00.6 0.00 0.0 0 0.6 0.0 2.0

TOTAL 0 0 0 TOTAL 0

RCConcrete requirement Wall Fwork size total M runGrade 0.13 0.0

15 0.0 0.15 0.020 0.0 0.18 0.025 0.0 0.2 0.030 0.0 0.23 0.0

35 0.0 0.25 0.0Lean 0.0 0.28 0.00.0 0.3 0.0

0.33 0.0Concrete Surround (Pipe) 0.35 0.0

Grade 0.38 0.015 21.406 0.4 0.025 0.000 0.45 0.035 0.000 0.5 0.0

21.406 0.55 0.00.6 0.0

TOTAL 0CHECK Wall height TRUE WALL HEIGHT O.K.

Area, m 2

Area, m 2

m 3

m3

Page 24: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 24/82

QUANTITY RATE AMOUNTCONCRETE - 275.00 -STEEL - 2600.00 - -Formwork 41.00 35.00 1,435.00Plastering 26.65 15.00 399.75Excavation 0.00 0.00 -Control Room 1 3000.00 3,000.00

Total 4,834.75

RATIO OF CONCRETE TO STEEL #DIV/0!CONCRETE TO TOTAL #DIV/0!

Page 25: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 25/82

Plywood0.00.00.00.00.00.00.00.00.00.00.0

0.00.00.00.00.0

0

Plywood Shell Flinkote0.00.00.0 Slab 0.000.0 Wall #DIV/0!0.0 BRC 0.00

0.00.0 Total #DIV/0!0.00.00.00.00.00.00.00.00.0

0

Area, m 2

m2

Page 26: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 26/82

Page 27: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 27/82

Page 28: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 28/82

Page 29: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 29/82

Page 30: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 30/82

item Qty u. price AmountGate 9 feet (h) 1 set 1,500.00 1,500.00PVC Wire 0 rolls 195.00 -Barbed Wire 0 rolls 42.00 -Fencing ( 9' x 2 1/2 " x 50') 0 rolls 270.00 -Angel Post (2" x 4mm) 12' 0 pcs 42.00 -Coner Post (2" x 4mm) 3 pcs 42.00 126.00Support (11Ft) 0 pcs 36.00 -Base & Curb 0 m #DIV/0! #DIV/0!

Total #DIV/0!

Labour (Fencing) 0 m 13.77 -Material #DIV/0!

Pole Mix (Grade 5 - 10) Curb 150mm HeightMixing Ratio Part Volume Exact Volume Weight

Stone 3 0.4286 0.000 -Sand 3 0.4286 0.000 -cement 50kg 1 0.1429 0.000 - -Water 0.000 -

length 0 meter Cement RMwidth 0.15 meter Sand RMheight / Thickness 0.15 meter Stone RM

Total Volume Required -

- bag of buildcrete 42,N5 RM- cubic yard of sand RM- cubic meters of stone RM

Total cost RM RM

Drain

Drain total Length 50.2 Material RM6" x 9" x 2' 1/2 0.76 Labour RM

Mixing Ratio Part Volume Exact Volume WeightStone 3 0.42857 1.0757 1.18

m3

Page 31: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 31/82

Sand 3 0.42857 1.0757 1.18cement 50kg 1 0.14286 0.3586 0.25 803.2Water 0.1793 0.44

length 50.2 meter Cement RMwidth 0.5 meter Sand RMheight / Thickness 0.1 meter Stone RM

Drain RMTotal Volume Required 2.51

67.00 Drain 6" x 9" x 2' 1/2 RM17.00 bag of buildcrete 42,N5 RM

1.54 cubic yard of sand RM1.18 cubic meters of stone RM9.80 Labour RM

Total cost RM RM

m3

Page 32: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 32/82

0 Ratio of Correction#DIV/0!

15 /50 kg correction on exact volume60 cement 0.76

sand 1.17stone 1.17water 2.64

----

0.00000 Ratio of Correction 0.03Weight #DIV/0! Bricks 54.06

Sand0.00 cement 50kg

Water

15 /50 kg length -60 high 01.9 /pcs Leaf 1

Mortar 0

Total Volume 0

- -- -- -- 0.15-

Mixing Ratio for BuildcreteWater Guide: 90 -100 Litre

250 /20 L

80 cts

/yard 3

formula m 3

/yard 3

Page 33: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 33/82

----

Concrete BRCArea Grade Rate+L Total Rate+L Total

0 25.0 0.00 195.00 $- 280.00 $-

0 25.0 0.00 195 $- 280 $-

0 25.0 0.00 195 $- 280 $-

0.00 0.00 $- $-

Labour Con -Labour BRC -

Sand -Cement - BagsHollow Bricks - pcsSand Bricks - pcsLabour RM -Concrete -BRC - pcs

Labour Material- -- -- -- -- -

-- -

- -

m 3

yard 3

m3

Page 34: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 34/82

0 Correction Ratio#DIV/0!

15 /50 kg6028

----

#DIV/0!

Total Cost/m567.75 11.31491.96 9.80

2.6893 Correction Ratio0.93

/yard 3

/m3

Page 35: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 35/82

15.00 /50 kg60.0028.00

2.80

187.60255.00

92.2432.91

491.961,059.71

/yard 3

/m3

Page 36: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 36/82

Mortar 0 Ratio of C

Mixing Ratio Part Volume Exact Volume Weight #DIV/0!6 0.8571 0.00 0.001 0.1429 0.00 0.00 0

0.00 0.00

meter Cement RM 15 /50 kgmeter Sand RM 604" x 9" Bricks RM 0.28 /pcs

bag of buildcrete 42,N5 RM -cubic yard of sand RM -Bricks RM -Labour RM -

Total cost RM -42,5N = 1:6s per batch or per 2x50kg Builcrete 42,N5

/yard 3

m3

m3

Page 37: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 37/82

Page 38: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 38/82

Page 39: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 39/82

Page 40: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 40/82

orrection

Page 41: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 41/82

Page 42: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 42/82

Page 43: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 43/82

Page 44: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 44/82

Brick WallLength Height Width No.

control room 5.88 3.00 0.00 03.00 3.00 0.00 0

- - 0.00 0

STORAGE HUT 1.25 1.20 1.35 0- - 0.00 0

Others - - 0.00 0- - 0.00 0

Brick WallLength Height Width No.

CHLORINATION CHAMBER 2.93 1.65 0 0- - 0 0

Pump Sump - - 0 0

Secondary Screen - - 0 0- - 0 0- - 0 0- - 0 0

Control Room Length Width Area Nosm m

27' Door Frame 0.69 1.98 1.37 030' Door Frame 0.77 2.14 1.65 036" x 7' Door Frame 0.92 2.14 1.96 052" x 7' Door Frame 1.32 2.14 2.82 0

6' x 4' window frame 1.24 1.84 2.28 04' x 4' window frame 1.24 1.24 1.54 02' x 4' window frame 0.73 1.24 0.91 02' x 2' window frame 0.73 0.73 0.53 0

Fan Opening 1' x 1' 0.31 0.31 0.09 0

Total Brick Wall Area

Mortar 0.03

Bricks 54.06 Mixing Ratio Part Volume Exact Volumeformula m 3

Page 45: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 45/82

Sand 6 0.86 - -cement 50kg 1 0.14 - -Water - -

length - meter Cement RMheight 2.21 meter Sand RMLeaf 0.1 4" / 9" Bricks RM

Mortar -

Total Volume Required -

- bag of buildcrete 42,N5 RM- cubic yard of sand RM- Bricks RM

0.15 Labour RMTotal cost RM

Mixing Ratio for Buildcrete 42,5N = 1:6Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete 42,N5

Plaster Mixing Ratio Part Volume Exact Volume Weight

Sand 6 0.857143 0.000 0.0000cement 50kg 1 0.142857 0.000 0.0000 0.00Water 0.000 0.0000

length - meter Cement RMheight 2.21 meter Sand RM

One Side or Two Sides 2square meter to plaster - Thickness 0.02 m-

bag buildcrete 42,N5 - RMcubic yard of sand - RMLabour 7.00 RM

Total cost RMMixing Ratio for Buildcrete 42,5N = 1:6Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete

PaintsformulaPaints 5 liters 35.00Paints 20 liters 140.00

length - meter Paints RMheight 2.21 meter Undercoat RMOne Side or Two Sides 2 RMsquare meter to paints -

Paints 20 liters - RM

Undercoat - RMLabour 3.30 RM

m3

m3

m2

m³ volume need m 3

m²m²

Page 46: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 46/82

Total cost RM

Total RM

Total Brick - pcs Total Labour Total Sand - Total Material CostTotal Cement - bagTotal Paints (18/20litres) -

MANHOLE, L/S Length Width Height(m) (m) GL IL depth

1 0.6 0.6 0.7 0.15 0.552 0.6 0.6 0.7 0.15 0.553 0.6 0.6 0.7 0.15 0.554 0.6 0.6 0.7 0.15 0.555 0.6 0.6 0.7 0.15 0.55

6 0.6 0.6 0.7 0.15 0.557 0.6 0.6 0.7 0.15 0.558 0.6 0.6 0.7 0.15 0.559 0.6 0.6 0.7 0.15 0.55

10 0.6 0.6 0.7 0.15 0.5511 0.6 0.6 0.7 0.15 0.5512 0.6 0.6 0.7 0.15 0.55

Average = 0.55Mortar

0.03Bricks 54.06 Mixing Ratio Part Volume Exact VolumeSand 6 0.8571 0.04918 0.0537cement 50kg 1 0.1429 0.00820 0.0058Water 0.00410 0.0101

length 30.36 meter Cement RMheight 0.7 meter Sand RMLeaf, inch 0.1 4" / 9" Bricks RM

Mortar 2.13

Total Volume Required 0.057

1.00 bag of buildcrete 42,N5 RM0.07 cubic yard of sand RM

112.00 Bricks RM0.15 Labour RM

Total cost RMMixing Ratio for Buildcrete 42,5N = 1:6Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete 42,N5

Plaster Mixing Ratio Part Volume Exact Volume Weight

Sand 6 0.85714 0.28 0.31cement 50kg 1 0.14286 0.05 0.03 106.26Water 0.02 0.06

yd³

formula m³

m3

m3

Page 47: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 47/82

length 30.36 meter Cement RMheight 0.7 meter Sand RMOne Side or Two Sides 1square meter to plaster 21.25 Thickness 0.02 m

0.33

bag buildcrete 42,N5 3.00 RMcubic yard of sand 0.41 RMLabour 7.00 RM

Total cost RMMixing Ratio for Buildcrete 42,5N = 1:6Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete

base slab (Grade 25)Mixing Ratio Part Volume Exact Volume Weight

Stone 3 0.42857 0.3673 0.40129Sand 3 0.42857 0.3673 0.40129cement 50kg 1 0.14286 0.1224 0.08706 274.23Water 0.0612 0.15083

Total area 5.71 Cement RMheight / Thickness 0.15 meter Sand RM

Stone RMTotal Volume Required 0.8570

6.00 bag of buildcrete 42,N5 RM

0.52 cubic yard of sand RM0.40 cubic meters of stone RM22.00 Labour RM

Total cost RMMixing Ratio for Buildcrete 42,5N = 1 : 3 : 3Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete 42,N5

RateTotal Labour 12 150Total Material

Total

m2

m³ volume need m 3

m2

m3

Page 48: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 48/82

Area

- 1- 1-

- 1-

- `-

-

- 1-

-

----

- 4

Total Nos Cost Total costArea 27”Metal Door Frame (L) 0 65.00 -

- 30'x7' Door Flame (Metal) 0 55.00 -0 3'x7' Door Flame (Metal) 0 55.00 -

- Jenang Pintu Besi 52”x 7 0 75.00 --

4'x6' Window Flame (Wood) 0 125.20 -- 4'x4' Window Flame (Wood) 0 72.00 -- 2'x4' Wood Window Frame 0 53.20 -- 2'x2' Window Flame (Wood) 0 15.20 -- -

-

-

Length Total height- - 2.21

- Ratio of CorrectionWeight #DIV/0!

Page 49: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 49/82

-

15.00 /50 kg correction on exact volume60.00 cement 0.76

0.28 /pcs sand 1.17stone 1.17water 2.64

-----

0 Correction Ratio#DIV/0!

15.00 /50 kg60.00

----

250.00 /20 liters80.00 /20 liters

-

--

/yard 3

/yard 3

Page 50: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 50/82

-

-

--

Area Area Volume of excavation Area - slabL x D x 2 W x D x 2

0.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 1

0.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 10.76 0.76 0.2 0.48 1

Total = 16.7 2.18 5.71 12

Weight 0.06148 Correction Ratio0.93

18.36

15.00 /50 kg60.00

0.28 /pcs

15.004.22

31.3616.8067.38

0.355781 Correction Ratio0.93

/yard 3

Page 51: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 51/82

15.00 /50 kg60.00

45.0024.41

148.76218.17

0.9182 Correction Ratio0.93

15.00 /50 kg60.0028.00

90.00

31.4911.2418.85

151.58

Total Cost1,800.00 184.42

252.71

2,052.71

/yard 3

/yard 3

/m3

Page 52: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 52/82

Sand BedLength Width No. Thickness ton

Sand 11.65 3.07 0 0.15 0 -Aggregate 20-30 11.65 3.07 0 0.15 0 -Aggregate 40-50 11.65 3.07 0 0.25 0 -

Persons Rate Amount DaysLabour 2 50 100 2JCB 1

TotalTotal Labour Total Material

Premix RoaRoad MT CR PS CC SS, GC194 14 26 11 0

BRC Type Length Width Layer Nos. Area1 A7 48.8 25 1 0 -245

Road Length Width Thickness Cover to ton tar ratePremix 0 1 0.08 - - $150.00Aggregate 40-50 0 1 0.3 - - $22.00

Person Rate Cost Days RM per unitBackpushter 0 $380.00Roller 0 $750.00JCB 0 $380.00Oil Tar 200liters 0 $300.00Labour 3 50 150 0 $150.00

Total Labour Total Material

TypeA7

Drain 9" x 2' 1/2 (750mm)

m 3

Total m 3

Page 53: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 53/82

Page 54: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 54/82

pcs of BRC(20.00)

Page 55: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 55/82

Height Length Side AreaMain tank 1.2 47.9 1 57.48

Pump sump 6.89 7.66 1 52.7775.92 14.5 1 85.845.92 4.3 1 25.46

Sand drying bed 0.5 50 1 251 117.76 1 117.76

SS, GC 2.2 3.2 1 7.042.1 10.06 1 21.13

Total 392.48

Tanks PaintsformulaPaints 1 liters 7.00 m2Paints 20 liters 140.00 m2

Paints RM 250.00 /20LUndercoat RM 80.00 cts

RMsquare meter to paints 392.48

Paints 20 liters 3.00 RM 750.00Undercoat 3.00 RM 240.00Labour 3.30 RM 1,295.18

Total cost RM 2,285.18

Tanks Shell Flinkote 18L PaintsformulaPaints 5 liters 35.00 m2

Paints 18 liters 126.00 m2

Paints RM 85 /18Lsquare meter to paints #DIV/0! Undercoat RM 80.00 cts

RM

Paints 18 liters #DIV/0! RM #DIV/0!Undercoat #DIV/0! RM #DIV/0!Labour 3.30 RM #DIV/0!

Total cost RM #DIV/0!

m2

m2

m2

Page 56: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 56/82

Grade U/PriceG15 118.00G20 123.00G25 130.00

G30 138.00G35 147.00

Strengthen Tech S/B Mr Wong 016-2207532Tel: 03-78041809 / 03-80606368

Fax: 03-80605887250mm -Formtie c/w 1 nuts 1.50 100 pcs/ box

250mm -Formtie c/w 2 nuts 1.70 100 pcs/ boxPlastic Cone 0.55 400 pcs/ boxFiat Rib Washer (105 x 50) 0.60 200 pcs / boxFiat Rib Washer (150 x 50) 0.75 150 pcs / boxRubber Ring 0.30 1000 pcs/bg3 Shape Washer (for Pipe) 0.85 200 pcs / boxInner Unit (200-500mm) 0.50Inner Unit (500-1000mm) 0.99

- Premix = 1106 m3

LIAU KOI SOON BUILDING CONSTRUCTION (Tel: 06-6512Description HDPE

375mm = 15" =300mm = 12" = 391.50225mm = 9" = 183.50150mm = 6" = 88.50100mm = 4" = 65.0075mm = 3" =50mm = 2" =

25mm = 1" =

Page 57: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 57/82

Resintech Plastics (M) Sdn Bhd (Ms Angel - Tel: 03-3122 24Mr Goh (019-3522657) , Mr KG Teh (016-6611700) Bank In

Description HDPE375mm = 15" = 675.00300mm = 12" = 391.50225mm = 9" = 180.00150mm = 6" = 99.00100mm = 4" = 63.0075mm = 3" =50mm = 2" =25mm = 1" =

Page 58: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 58/82

x 20.00 = 22,120.00Crusher Run - 2,772.84

Repair Longkang - 80.00Diesel - 20.00

19,247.16

128 Fax: 06-6514003)Socket R.Ring 90 Bend 60 Bend

7.80 96.10 96.1045.50 5.40 81.0028.85 3.00 52.50 52.5017.50 1.80 20.6512.50 1.80

Page 59: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 59/82

22, Fax: 03-3122 2411)(PBB 3085-5094-25)Socket R.Ring 90 Bend 60 Bend45.00 6.50 96.1039.00 4.50 77.5024.00 2.50 46.5018.00 1.50 18.6010.50 1.25 12.40

Page 60: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 60/82

Y L = 5.6z = b x cos 60

L2 = 1

d = 60.00 Area =

x = 2.30

z = 2.30 0.5 4.600

y = 3.984

Length Heightanswer 3.300 4.600

60 °

L

L2 X

YZ

Page 61: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 61/82

Page 62: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 62/82

0.66 145 95.706.6 100.006.6 6 4.5 27.00

222.70

2.2 0.3 1.93 0.3 2.7

0.1 0.030.66 0.13 0.53

Base Floor (Grade 25)

Mixing Ratio Part Volume Exact volume WeightStone 3 0.43 0.43 0.4683Sand 3 0.43 0.43 0.4683cement 50kg 1 0.14 0.14 0.1016 320.0Water 0.07 0.1760

length 1 meter Cement RM 15.00width 1 meter Sand RM 60.00height / Thickness 1 meter Stone RM 28.00

Total Volume Required 1

6.40 bag of buildcrete 42,N5 RM 96.000.61 cubic yard of sand RM 36.750.47 cubic meters of stone RM 13.11

22.00 Labour RM 22.00Total cost RM 167.86

Mixing Ratio for Buildcrete 42,5N = 1 : 3 : 3Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete 42,N5

Mortar ( Hollow Brick)0.03

Bricks 13.8 Mixing Ratio Part Volume Exact Volume WeightSand 6 0.86 23.1428571 25.286170cement 50kg 1 0.14 3.8571429 2.742858 8640.0Water 1.9285714 4.752000

length 1000 meter Cement RM 15.00height 1 meter Sand RM 60.00Leaf 1 15" L x 7 1/2" H 4" T Hollow Bricks RM 1.90

Mortar 1000

m3

formula m 3

m3

Page 63: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 63/82

Total Volume Required 27

172.80 bag of buildcrete 42,N5 RM 2,592.0033.07 cubic yard of sand RM 1,984.38

13,428.00 Bricks RM 25,513.200.80 Labour RM 10,742.40

Total cost RM 40,831.98Mixing Ratio for Buildcrete 42,5N = 1:6Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete 42,N5

Plaster Mixing Ratio Part Volume Exact Volume Weight

Sand 6 0.86 2.38661 2.607636cement 50kg 1 0.14 0.39777 0.282857 891.000Water 0.19888 0.490050

length 2.2 meter Cement RM 15.00height 81 meter Sand RM 60.00One Side or Two Sides 1square meter to plaster 178.20 Thickness 0.02 m

2.78

bag buildcrete 42,N5 17.82 RM 267.30cubic yard of sand 3.41 RM 204.64Labour 7.00 RM 1,247.40

Total cost RM RM 1,719.34Mixing Ratio for Buildcrete 42,5N = 1:6

Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete

Base Floor (Grade 35)Mixing Ratio Part volume Exact volume Weight

Stone 3 0.42857 0.262 0.28611Sand 3 0.42857 0.262 0.28611cement 50kg 1 0.14286 0.087 0.06207 195.52water 0.044 0.10754

length 15.28 meter Cement RM 15.00

width 0.5 meter Sand RM 60.00height / Thickness 0.08 meter Stone RM 28.00

Total Volume Required 0.61

3.91 bag of buildcrete 42,N5 RM 58.660.37 cubic yard of sand RM 22.450.29 cubic meter of stone RM 8.01

22.00 Labour RM 13.44

Total cost RM 102.56Mixing Ratio for Buildcrete 42,5N = 1 : 3 : 3

m3

m2

m3 volume need m 3

m3

Page 64: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 64/82

Water Guide: 90 -100 Litres per batch or per 2x50kg Builcrete 42,N5

Page 65: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 65/82

27 6,012.90

1.07 Ratio of Correction

0.93

correction on exact volumecement 0.76sand 1.17stone 1.17

/50 kg water 2.64

50 kg 320.002086.18 kg 1,277.71

1461 kg 684.1340

2,321.84

152.01 8.02152.01 8.02

28.93 Ratio of Correction 122.14 5.880.93 122.14 5.88

997.72 68.55

1,546.03 96.34

100.00/50 kg 27.00

223.34/pcs

/yard 3

/m3

/yard 3

Page 66: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 66/82

42,551.32 42,327.98 36,521.02

2.98 Ratio of Correction0.93

/50 kg

0.65 Ratio of correction0.93

/50 kg

50 kg 195.52 0.04 0.142086.18 kg 780.68 0.92

1461 kg 418.00 0.9292.37 1.98

1,486.58

/yard 3

/yard 3

/m3

Page 67: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 67/82

Page 68: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 68/82

0.04 0.220.920.92

2.06

27 6,030.30

Page 69: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 69/82

Page 70: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 70/82

Page 71: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 71/82

Pipe diameter, mm 150

Length, m Sand beddingConcrete bedding Sand + Aggregate Excavate/depth, m 0

108 0 Thickness, m 0

% of wastage 1% Period, day 1% of profit 5%

AggregateArea Aggregate

D O Dia O.D.+300 Area OD Cover areamm mm m Cylinder 150 170 0.22 0.023 0.1982

Sand BeddingLength Excavate Thickness Sand

m m m0.0 0 0 0 -

Estimate Excavation per dayExcavator JCB

1 1Total Length 8hrs Evc M run days $700.00 $380.00

108 160 1 $700.00 $380.00

Labour Pipe Layers Supervisor

4 1Total Length days $60.00 $80.00

108 1 $240.00 $80.00

Concrete Su

Area ConcreteD O Dia O.D.+300 Area OD Cover area

mm mm m Cylinder 150 170 0.22 0.023 0.1982

Per length Per Meter Total LengthD.I Socket Pipe price( 6m) Run Sand + Agg. Concrete

150 $371.00 $61.83 0 108

Per length Per Meter Total LengthAB3P Socket Pipe price( 6m) Run Sand + Agg. Concrete

m 2

needed m 3 Yard 3

m 2

Page 72: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 72/82

150 $84.00 $14.00 0 108

D.I. Pipe List Price Mark up 0.7 6DN Pipe Dis Price 1m (RM)

100 $450.00 $450.00 $315.00 $52.50150 $530.00 $530.00 $371.00 $61.83200 $710.00 $710.00 $497.00 $82.83250 $940.00 $940.00 $658.00 $109.67300 $1,200.00 $1,200.00 $840.00 $140.00350 $1,500.00 $1,500.00 $1,050.00 $175.00400 $1,780.00 $1,780.00 $1,246.00 $207.67450 $2,150.00 $2,150.00 $1,505.00 $250.83500 $2,700.00 $2,700.00 $1,890.00 $315.00

600 $3,700.00 $3,700.00 $2,590.00 $431.677008009001,0001,2001,1001,6001,8002,000

Page 73: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 73/82

Bedding 'Class A'Aggregate Aggregate Aggregate

Length needed ton per ton Price Total M Runm

0.0 0 - $22.00 $- $-

Price Total M Run$60.00 $- $-

Lorry10%

$420.00 Total M Run$42.00 $1,122.00 $10.39

Manager 20%$250.00 Total M Run

$50.00 $320.00 $2.96

round

Concrete Concrete ConcreteLength needed Total M Run

m 15108.0 21.406 $160.00 $3,424.93 $31.71

Amounts of D.I Pipe Labour Excavation Crushed Sand Concrete

1 1 1$- $2.96 $10.39 $- $- $31.71

Amounts of D.I Pipe Labour Excavation Crushed Sand Concrete

m 3

per m 3 Pricem 3

Page 74: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 74/82

1 1 1$- $2.96 $10.39 $- $- $31.71

AB3P CLASS C ( PN 9 )O.D DN BELL MOUTH M Run

118 100 182.98 31.07170 155 301.71 51.30222 200 435.10 73.96271 250 663.48 112.86326 300 886.97 150.77378 350 1,176.80 200.07429 400 1,546.96 263.06478532

635738842945

1,0481,2551,4621,6681,8752,082

Page 75: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 75/82

L & M Total Cost w/o bedding Total CostWastage Profit M Run M Run Project

$1.07 $5.34 $51.48 $81.60 $12,237.63

L & M Total Cost w/o bedding Total CostWastage Profit M Run M Run Project

Page 76: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 76/82

$0.59 $2.95 $48.61 $30.90 $6,761.67

DI Pipe L & M Total Cost w/o bedding Total CostM Run M Run M Run Project

$61.83 $51.48 $81.60 $12,237.63

AB3P Pipe L & M Total Cost w/o bedding Total CostM Run M Run M Run Project

$14.00 $48.61 $30.90 $6,761.67

Diferrent $5,475.96

344.5 56.60

Page 77: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 77/82

a = 6.44b = 3.72

c = 7.44

Tangent Formula

A = 60° =a

=a

b 3.72

a = 6.44

c =

a =

b = (c² - a²)

c = 5.00b = 4.00

a = 3.00

c = 5.00

a = 3.00

b = 4.00

(a² + b²)

(c² - b²)

Page 78: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 78/82

Page 79: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 79/82

Circumference and Radius of a Circle

radius: 3.5 m circumference:area:

radius: 11.85 m circumference:area:

radius: 1.35 m circumference:area:

radius: 10.9 m circumference:area:

radius: 0.5 m circumference:

area:

calculator that calculates the volume of a cylinder.

radius : 12.15 mheight : 0.35 m volume :

radius 1 : 1.35height : 1 volume :

radius 2 : 1height : 1 volume :

Wall volume :

radius 1 : 11.85

radius

h e i g h t

radius2

radius1

h e i g h t

Page 80: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 80/82

height : 2.99 volume :

radius 2 : 11.5height : 2.99 volume :

Wall volume :

radius 1 : 0.3height : 3.99 volume :

radius 2 : 0.5height : 3.99 volume :

Wall volume :

Page 81: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 81/82

21.99 m38.48 1

74.46 m441.15

8.48 m5.73

68.49 m373.25

3.14 m

0.79

162.32

5.73

3.14

2.58

Page 82: RC BQ 2010 Master Copy

8/6/2019 RC BQ 2010 Master Copy

http://slidepdf.com/reader/full/rc-bq-2010-master-copy 82/82

1,316.83

1,240.19

76.64

1.13

3.13

2.00