raw and finished water system improvements april 22, 2014
DESCRIPTION
Raw and Finished Water System Improvements April 22, 2014. Project Purpose…. Replace aged infrastructure Provide for current water demand Provide for future water demand Improve system reliability. Project Area…. - Ford Road- McClure Road - New Boonesboro Road- Colby Road - PowerPoint PPT PresentationTRANSCRIPT
Raw and Finished Water System Improvements
April 22, 2014
Project Purpose….Project Purpose….
Replace aged infrastructure Replace aged infrastructure
Provide for current water demandProvide for current water demand
Provide for future water demandProvide for future water demand
Improve system reliabilityImprove system reliability
Project Area….Project Area….
- Ford Road- Ford Road - McClure Road- McClure Road
- New Boonesboro Road- New Boonesboro Road - Colby Road- Colby Road
- Old Boonesboro Road - Old Boonesboro Road - April Way- April Way
- Water Works Road- Water Works Road - Bypass Road- Bypass Road
Area Impact….Area Impact….
11,761 WMU
2,365 East Clark County Water District
215 Kentucky American Water Company
14,341 Total Customers
Scope of Work….Scope of Work….
12,000’ of 24” Ductile Iron Raw Water Line12,000’ of 24” Ductile Iron Raw Water Line
36,000’ of 24” Ductile Iron Finished Water Line36,000’ of 24” Ductile Iron Finished Water Line
KY Raw Water Intake and Pump Station KY Raw Water Intake and Pump Station
ImprovementsImprovements
In total 9 miles of large diameter raw and In total 9 miles of large diameter raw and
finished water transmission lines finished water transmission lines
Project Cost….Project Cost….
*Does Not Include WMU Staff Time*Does Not Include WMU Staff Time
Raw Water Intake ImprovementsRaw Water Intake Improvements
Raw Water Transmission MainRaw Water Transmission Main
Finished Water Transmission MainFinished Water Transmission Main
EngineeringEngineering
Total Project Cost*Total Project Cost*
$1,040,000.00$1,040,000.00
$2,220,000.00$2,220,000.00
$6,660,000.00$6,660,000.00
$875,000.00$875,000.00
$10,795,000.00$10,795,000.00
Project Disruptions….
Road Closures / DetoursRoad Closures / Detours
Noise Noise
DustDust
Easements….Easements….
Temporary and Permanent Easements RequiredTemporary and Permanent Easements Required
New easement – Not in flood plain – $4.00/ft.New easement – Not in flood plain – $4.00/ft.
New easement – In the flood plain – $3.00/ft.New easement – In the flood plain – $3.00/ft.
Existing easement (Increase width) – $2.00/ft.Existing easement (Increase width) – $2.00/ft.
Temporary (all) – $1.00/ft. Temporary (all) – $1.00/ft.
*Any variance from this payment schedule will require authorization *Any variance from this payment schedule will require authorization from the WMU Commission.from the WMU Commission.
Project Schedule….Project Schedule….
Design Phase Design Phase
Advertising/Bidding PhaseAdvertising/Bidding Phase
Bid OpeningBid Opening
Begin ConstructionBegin Construction
Substantial Completion DateSubstantial Completion Date
Construction TimeConstruction Time
6/14/146/14/14
6/14/14 thru 7/8/14 6/14/14 thru 7/8/14
8/1/148/1/14
8/1/148/1/14
2/1/162/1/16
18-19 Months18-19 Months
Key Contacts….
General Manager:General Manager:
Director of Director of Engineering/Operations:Engineering/Operations:
Utility Engineer:Utility Engineer:
Michael FlynnMichael Flynn
Kenneth “Duke” DrydenKenneth “Duke” Dryden
Eddie HightowerEddie Hightower
Winchester Municipal Utilities150 North Main Street
PO Box 4177Winchester, KY 40392-4177
Phone: (859) 744 – 5434Fax: (859) 745 – 4146