rational team concert 2.0.0.1 svt kickoff july 22, 2009
DESCRIPTION
Rational Team Concert 2.0.0.1 SVT Kickoff July 22, 2009. ISL Manjunathan Nipun Sachin. CDL Jian Qiu Lin. RTP, USA Anu Ken Sanjay. Lexington, USA Carol Cindy Karen Ken Manju Mark Olga Sentella Sujana. Located around the world, but ONE team!. There is someone in SVT testing - PowerPoint PPT PresentationTRANSCRIPT
®
IBM Software Group
© 2009 IBM CorporationIBM Confidential
Rational Team Concert 2.0.0.1 SVT KickoffJuly 22, 2009
IBM Software Group | Rational software
2
IBM Confidential
Located around the world, but ONE team!
ISL•Manjunathan•Nipun•Sachin
CDL•Jian Qiu•Lin
RTP, USA•Anu•Ken•Sanjay
Lexington, USA•Carol•Cindy•Karen•Ken•Manju•Mark•Olga•Sentella•Sujana
There is someone in SVT testing RTC 24 hours a day!
IBM Software Group | Rational software
3
IBM Confidential
Who are we? Anu – Performance Lead
Carol – CC Bridge, Enterprise Deployment Scenario
Cindy – Release Manager
Jian Qiu – Benchmark
Karen – Test Coordinator
Ken McClamroch– SVT Test Architect
Ken Sandler – Automation development
Lin – SVT Manager – Benchmark team
Manju – Performance, Integration Project
Manjunathan –IPv6 Scenario, RTC.net Scenario
Mark – Technical Lead
Nipun – RTC.net Scenario, Co-existence Scenario
Olga – End-to-End Solutions Scenario, RQM Internal Deployment
Sachin – ISL Lead
Sentella – Performance
Sujana – CQ Importer, Mainsoft Lead , Integration Project
IBM Software Group | Rational software
4
IBM Confidential
Themes for 2.0.0.1 We are one team
Communicate, communicate, communicate Talk to each other
Be tolerant of different communication styles
Sustainable pace Realistic estimates, realistic plan, execute to plan
Don’t take on additional tasks without talking to Cindy and Karen first (before you commit)
Done, done, done What does done mean?
Complete all aspects of a task:
RQM – points, test execution records
Communicate the completion – email, update the workitem, Assessment report
Analysis
Posting results
Clean up the machine
Practice the process
IBM Software Group | Rational software
5
IBM Confidential
2.0.0.1 Purpose and Schedule
Key Project Milestones PlanOutlook /
ActualCompletion / Comments
Plan DCP 07/28/09 Green
SVT Prep Start 07/27/09 Green
CTP Review 08/05/09 Green
SVT Prep End 08/10/09 Green
CTP Approval 08/10/09 Green
SVT Entry 08/10/09 Green
SVT Exit 09/04/09 Green
Availability DCP TBD Green
Ship Readiness Entry 09/08/09 Green
Ship Readiness Exit 09/11/09 Green
QCERT TBD Green
GM 09/15/09 Green
eGA 09/22/09 Green
This plan is for a minor release of Rational Team Concert. The primary focus of this release is to:
• enable sales accelerators• continued enterprise deployments of Rational Team Concert by enhancing performance and scalability
IBM Software Group | Rational software
6
IBM Confidential
Process
Analyze content Plan DCP, Plan Items, Enhancements/Features/Defects
Integration Points, Co-existence
Consumabilty
Green Threads
Communicate
Planning CTP
Using RQM
Test prep tasks
Test plans, test cases – using templates
Test case review/approval – use RQM
Consumability worksheet
Communicate
IBM Software Group | Rational software
7
IBM Confidential
Process (cont.)
Execution Take notes for Assessment report
Enter defects early and often (use tags)
Escalate to Karen/Cindy/Development when appropriate
RQM – test points updated, test execution records to track progress
Communicate
Done, done, done Complete analysis and post results (performance)
Assessment report
Customer Collateral
Communicate
IBM Software Group | Rational software
8
IBM Confidential
Team Survey… What meetings are there?
Ones we know about…
SVT Team meetings
Performance (with PRT)
Jazz Integration
Weekly status (with Albert)
CFT
RTC Development Planning meetings
Are there others? Send information to Karen