rate analysis for nasik

60
document.xls Shreehari Associates (P) Ltd. Page 1 of 60 Name of Work Construction Agency SHREEHARI ASSOCIATES (P) LTD 1' Sai Vrindavan, Nr. Mahanubhav Ashram, Paithan Road, Aurangabad-431005 T-(0240) 2376648/9, F-(0240) 376656 e- [email protected] "CONSTRUCTION OF PROPOSED CIVIL WORK FOR 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA. RATE ANALYSIS SAPL SHREEHARI ASSOCIATES (P) LTD

Upload: ahmed-sohel

Post on 24-Oct-2015

122 views

Category:

Documents


9 download

DESCRIPTION

Rate Analysis for Nasik

TRANSCRIPT

Page 1: Rate Analysis for Nasik

document.xls

Shreehari Associates (P) Ltd. Page 1 of 59

Name of Work

Construction Agency

SHREEHARI ASSOCIATES (P) LTD1' Sai Vrindavan, Nr. Mahanubhav Ashram,Paithan Road, Aurangabad-431005T-(0240) 2376648/9, F-(0240) 376656e- [email protected]

"CONSTRUCTION OF PROPOSED CIVIL WORK FOR 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

RATE ANALYSIS

SAPL

SHREEHARI ASSOCIATES (P) LTD

Page 2: Rate Analysis for Nasik

Shreehari Associates (P) Ltd.Project: "Construction of Proposed Spinning Mill at Barshi, Dist. Solapur"

Basic Rate ConsideredSr No. Item Description Unit Rate (Rs.) Remarks

1 Cement Bag. As per agreement2 Steel -TMT MT As per agreement3 Structural Steel MT As per agreement4 Brick Nos 4.00 Current Market Rates5 Rubble Cum 400.00 Current Market Rates6 Aggregate (40/60/80MM) Cum 550.00 Current Market Rates7 Aggregate (20MM) Cum 600.00 Current Market Rates8 Aggregate (10MM) Cum 650.00 Current Market Rates9 Crushed Sand / Natural Sand Cum 750.00 Current Market Rates

10 Color Ceramic tiles (30cm x30cmx8cm) Nos 30.00 Current Market Rates11 Color Ceramic tiles (30cm x20cmx8cm) Nos 22.00 Current Market Rates12 Vetrified Tiles (60cm x 60cm) Nos 160.00 Current Market Rates13 Kota Stone 25-30mm Thk Sq.M. 550.00 Current Market Rates

a Cement Mortar (1:6) Cum 2,100.00 Separate analysis attachedb Cement Mortar (1:5) Cum 2,100.00 Separate analysis attachedc Cement Mortar (1:4) Cum 2,100.00 Separate analysis attachedd Cement Mortar (1:3) Cum 2,100.00 Separate analysis attached

Page 3: Rate Analysis for Nasik

SAPL Page 3 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 4: Rate Analysis for Nasik

SAPL Page 4 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

SWITCH YARDB Item No 6 a

Rate Analysis for 1 MTComponent Rate Unit Quantity Amount

1 Material

Steel Cutting Machine 200.00 Day 0.50 100.00 Bar Bending Machine 370.00 Day 0.50 185.00

2 LabourCutting Charges 3.50 Kg. 1,070.00 3,745.00 Fixing Charges 3.50 Kg. 1,070.00 3,745.00 Labour for Shifting 300.00 Day 3.00 900.00

3 Other ExpenditureUnloading Charges LS 500.00 Scrap Loading Charges LS 100.00

A Sub Total 9,275.00 1 Overheads & Profit

Contractors Profit 15% 1,391.25 Overheads

B Sub Total 1,391.25

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Cum 10,666.25 H RATE PROPOSED Rs./Cum 10,000.00

Item Description: Unloading , Cutting, bending, binding, laying, transporting and fixing in position at any levels reinforcement bars for all concrete works including 16 gauge annealed M.S. wire, spacer blocks of C.M. 1:2 with embedded binding wire of suitable length, protective coat of neat cement slurry to be applied as per Engineer-in-charge etc. complete. Only Authorised Lap & Chairs will be measured & paid.Mild steel as mentioned in Approved make

Page 5: Rate Analysis for Nasik

SAPL Page 5 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

B Item No 6 b

Rate Analysis for 1 MTComponent Rate Unit Quantity Amount

1 MaterialSteel Cutting Machine 200.00 Day 0.50 100.00 Bar Bending Machine 360.00 Day 0.50 180.00

2 Labour

Cutting Charges 4.00 Kg. 1,070.00 4,280.00 Fixing Charges 4.00 Kg. 1,070.00 4,280.00 Labour for Shifting 300.00 Day 3.00 900.00

3 Other ExpenditureUnloading Charges LS 200.00 Scrap Loading Charges LS 50.00

A Sub Total 9,990.00 1 Overheads & Profit

Contractors Profit 15% 1,498.50 Overheads 5% 499.50

B Sub Total 1,998.00

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Cum 11,988.00 H RATE PROPOSED Rs./Cum 12,500.00

Item Description: Unloading , Cutting, bending, binding, laying, transporting and fixing in position at any levels reinforcement bars for all concrete works including 16 gauge annealed M.S. wire, spacer blocks of C.M. 1:2 with embedded binding wire of suitable length, protective coat of neat cement slurry to be applied as per Engineer-in-charge etc. complete. Only Authorised Lap & Chairs will be measured & paid.HYSD bars

Page 6: Rate Analysis for Nasik

SAPL Page 6 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 7: Rate Analysis for Nasik

SAPL Page 7 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 8: Rate Analysis for Nasik

SAPL Page 8 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 9: Rate Analysis for Nasik

SAPL Page 9 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 10: Rate Analysis for Nasik

SAPL Page 10 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 11: Rate Analysis for Nasik

SAPL Page 11 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 12: Rate Analysis for Nasik

SAPL Page 12 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 13: Rate Analysis for Nasik

SAPL Page 13 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 14: Rate Analysis for Nasik

SAPL Page 14 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 15: Rate Analysis for Nasik

SAPL Page 15 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 16: Rate Analysis for Nasik

SAPL Page 16 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 17: Rate Analysis for Nasik

SAPL Page 17 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 18: Rate Analysis for Nasik

SAPL Page 18 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 19: Rate Analysis for Nasik

SAPL Page 19 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 20: Rate Analysis for Nasik

SAPL Page 20 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 21: Rate Analysis for Nasik

SAPL Page 21 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 22: Rate Analysis for Nasik

SAPL Page 22 of 59

Shreehari Associates (P) Ltd.

Rate Analysis-Proposed Rates

Project: RATE ANALYSIS FOR SUBCONTRACT OF GENERAL CIVIL WORK FOR PROPOSED 400/132 KV SWITCH YARD & ITS ASSOCIATED WORKS FOR SOLAPUR THERMAL POWER PROJECT OF NTPC AT SOLAPUR ON BEHALF ABB LIMITED VADODARA.

Page 23: Rate Analysis for Nasik

SAPL Page 23 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

Page 24: Rate Analysis for Nasik

SAPL Page 24 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

1 Item No

Rate Analysis for 1 CumComponent Rate Unit Quantity Amount

1 MaterialCement 305.00 Bag 7.60 2,318.00 Aggregate 20MM 1,024.00 Cum 0.86 880.64 Natural Sand 1,766.00 Cum 0.43 759.38

2 Labour - Coolie 250.00 Day 0.50 125.00 Mason 500.00 Day 0.20 100.00 Mixer Operator 200.00 Day 0.05 10.00

3 Other Expenditure - Formwork/Scaffolding 180.00 Sq.M. 8.00 1,440.00 Curing & Watering Lumsump 40.00 Transmit Mixer Charges 160.00 Cum 1.00 160.00

- A Sub Total 5,833.02

1 Overheads & ProfitContractors Profit 15% 874.95 Overheads LS 50.00

B Sub Total 874.95

1 Taxes 10% 583.30 C Sub Total 583.30

G Grand Total (Rate per Unit) Rs./Cum 7,291.28

Item Description: Providing and laying controlled Reinforced Cement Concrete of M20 grade with 20mm down size graded crushed stone aggregates for all elements including scaffolding, opening, recesses, chamfering, finishing top surfaces, vibrating, machine mixing tamping, curing etc.complete as per the specifications, drawing and instruction of Engineer-in-charge (( Cement & Reinforcing steel shall be supplied free of cost by ABB ) Concrete shall be finished to the true line, level & as per tolerances required.)

Page 25: Rate Analysis for Nasik

SAPL Page 25 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

2 Item No

Rate Analysis for 1 CumComponent Rate Unit Quantity Amount

1 MaterialCement 305.00 Cum 8.50 2,592.50 Aggregate 1,060.00 Cum 0.86 911.60 Crushed Sand / Natural Sand 1,908.00 Cum 0.43 820.44

2 Labour - Coolie 250.00 Day 0.50 125.00 Mason 500.00 Day 0.20 100.00 Mixer Operator 200.00 Day 0.05 10.00

3 Other Expenditure - Formwork/Scaffolding 180.00 Sq.M. 8.00 1,440.00 Curing & Watering Lumsump 40.00 Transmit Mixer Charges 160.00 Cum 1.00 160.00

- A Sub Total 6,199.54

1 Overheads & ProfitContractors Profit 15% 929.93 Overheads 50.00

B Sub Total 979.93

1 Taxes 10% 619.95 C Sub Total 619.95

G Grand Total (Rate per Unit) Rs./Cum 7,799.43

Item Description:Providing and constructing cast in situ precast cover for cable trenches etc. of different size of M25 grade concrete with finishing top surface, curing by making necessary platform etc. Precast cover should be vibrated with surface vibrator for attaining proper finish of concrete surface. The rate should be inclusive of shuttering , placing, lifting hook, laying as per instruction of Engineer in charge.

Page 26: Rate Analysis for Nasik

SAPL Page 26 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

3 Item No

Rate Analysis for 1 MTComponent Rate Unit Quantity Amount

1 MaterialSteel (TMT-ISI) 43976 MT 1.00 43,976.00 Steel Cutting Machine 160.00 Day 0.50 80.00 Bar Bending Machine 370.00 Day 0.50 185.00

2 LabourCutting Charges 3.50 Kg. 1,070.00 3,745.00 Fixing Charges 3.50 Kg. 1,070.00 3,745.00 Labour for Shifting 300.00 Day 3.00 900.00

3 Other ExpenditureUnloading Charges LS 150.00 Scrap Loading Charges LS 25.00

A Sub Total 52,806.00 1 Overheads & Profit

Contractors Profit 15% 7,920.90 Overheads

B Sub Total 7,920.90

1 Taxes 10% 5,280.60 C Sub Total 5,280.60

G Grand Total (Rate per Unit) Rs./MT 66,007.50

Item Description:Providing and placing steel inclusing Unloading , Cutting, bending, binding, laying, transporting and fixing in position at any levels reinforcement bars for all concrete works including as per Engineer-in-charge etc. complete.

Page 27: Rate Analysis for Nasik

SAPL Page 27 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

Item No

Rate Analysis for 1 CumComponent Rate Unit Quantity Amount

1 MaterialCement 305.00 Cum 4.42 1,348.10 Aggregate 1,060.00 Cum 0.80 848.00 Crushed Sand / Natural Sand 1,908.00 Cum 0.60 1,144.80

2 Labour - Coolie 250.00 Day 0.50 125.00 Mason 500.00 Day 0.20 100.00 Mixer Operator 200.00 Day 0.05 10.00

3 Other Expenditure - Curing & Watering Lumsump 40.00 Transmit Mixer Charges 150.00 Cum 1.00 150.00 Batching Plant Charges -

A Sub Total 3,765.90 1 Overheads & Profit

Contractors Profit 15% 564.88 Overheads 50.00

B Sub Total 614.88

1 Taxes 10% 376.59 C Sub Total 376.59

G Grand Total (Rate per Unit) Rs./Cum 4,757.38

Item Description: Providing, mixing and laying plain cement concrete M-10 with 25 to 35 mm nominal size graded aggregates of approved quality as a levelling course, under floor as sub base , for foundation etc. including ramming, levelling, curing etc. complete at any level

Page 28: Rate Analysis for Nasik

SAPL Page 28 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 MaterialCement Mortar (1:4) 1,200.00 Cum 0.0150 18.00 GI Chiken Mesh 12.00 Sq.M. 0.25 3.00

- 2 Labour -

Bhisti 250.00 Day 0.15 37.50 Mason 200.00 Day 0.25 50.00

- 3 Other Expenditure -

Formwork/Scaffolding Lumsump 5.00 Water Charges/ Curing 5.00

A Sub Total 118.50 1 Overheads & Profit

Contractors Profit 15% 17.78 Overheads

B Sub Total 17.78

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Sq.M. 136.28 H RATE PROPOSED Rs./Sq.M. 100.00

Item Description:.Providing and applying 12mm thick smooth cement plaster at all heights and below plinth in C.M. 1:6 to walls, beams, column, drain, bends, moulds, grooves, pattas and drip course to all brick and RCC surfaces including raking joints,scaffolding, curing finishing smooth. The plaster shall be rubbed with "Iron Plate" till the surface shows cement paste in line level complete as directed.

Page 29: Rate Analysis for Nasik

SAPL Page 29 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

E Item No E 7.00

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 Material 22.00 Nos 17.00 374.00

1,221.00 Cum 0.01 14.65

1.67 1 time 15.55 25.97

Bags 0.07 -

- 2 Labour -

Bhisti 350.00 Day 0.40 140.00 Mason 225.00 Day 1.00 225.00

- 3 Other Expenditure -

- -

A Sub Total 779.62 1 Overheads & Profit

Contractors Profit 15% 116.94 Overheads 15.00

B Sub Total 131.94

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Sq.M. 911.56 H RATE PROPOSED Rs./Sq.M. 900.00

Item Description: Providing and fixing 300mm x 300mm x 7.3 mm thick heavy duty Ceramic tiles (Matt finish) of "NITCO" or "BELL" make in flooring & skirting / dado including laying over 12mm thick C.M. 1:3 mix bed to proper level or slope and and jointed with grey cement slurry @ 3.3 Kg/ Sqm including pointing in white cement mixed with matching colour pigment etc. complete. ( Rate shall be inclusive of backing coat of cement plaster wherever required) Basic rate of tiles shall be Rs.450/ sqm

Colour Ceramic tiles (30cm x20cm) including wastages

10 mm thk. Cement Mortar 1:3 with coarse sand

Mortar for pointing with white cement

Cement for slurry over bed @ 3.3 kg/sq.m

Page 30: Rate Analysis for Nasik

SAPL Page 30 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

E Item No E 2a

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 Material 220.00 Nos 3.00 660.00

2,100.00 Cum 0.01 25.20

3.50 1 time 15.55 54.43

Bags 0.07 -

- 2 Labour -

Bhisti 350.00 Day 0.50 175.00 Mason 250.00 Day 1.50 375.00

- 3 Other Expenditure -

- -

A Sub Total 1,289.63 1 Overheads & Profit

Contractors Profit 15% 193.44 Overheads 30.00

B Sub Total 223.44

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Sq.M. 1,513.07 H RATE PROPOSED Rs./Sq.M. 1,500.00

Item Description: Providing & laying 1st quality of Marbogranite vitrified tiles of 600 x 600mm size of 9 mm thk, approved make, colour and shade (50% premium & 50% non-premium colours) in flooring over min. 41 mm thick bed of CM 1:4 and jointing with Grey cement slurry @ 3.3 kg per Sqmt incl. pointing in white cement mixed with pigment of matching colour at all levels and all heights etc complete. Basic rate Rs. 750 / sqm

Vetrified Tiles (60cm x60cm) including wastages

10 mm thk. Cement Mortar 1:3 with coarse sand

Mortar for pointing with white cement

Cement for slurry over bed @ 3.3 kg/sq.m

Page 31: Rate Analysis for Nasik

SAPL Page 31 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

G Item No G 6.00

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 MaterialBrick Bats 3.50 Sqm 58.00 203.00 Morter (1:5) 2,700.00 % 0.03 81.00 Cement for Slury 300.00 Bags 0.30 90.00

2 Labour - Mason 350.00 Day 0.20 70.00 Bhistri 250.00 Day 0.30 75.00

3 Other ExpenditureWaterproofing Chemical Lumsump 10.00

A Sub Total 529.00 1 Overheads & Profit

Contractors Profit 15% 79.35 Overheads 50.00

B Sub Total 129.35

1 Taxes 8% 42.32 C Sub Total 42.32

G Grand Total (Rate per Unit) Rs./Sq.M. 700.67 H RATE PROPOSED Rs./Sq.M. 700.00

Item Description:Providing and laying water proofing treatment over flat RCC roof & to vertical surface of parapet wall upto 300 mm high as per drawing shall be done including fillets at juction of roof & vertical walls with M-15 grade concrete finished with 12 mm thick CM 1:4 ( only plan area to be taken for measurement purpose ) as per following layer

Page 32: Rate Analysis for Nasik

SAPL Page 32 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 a

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 115.00 RM 1.00 115.00

- -

2 Labour - Cutting, Fitting Charges 40.00 RM 1.00 40.00

- -

3 Other Expenditure

A Sub Total 155.00 1 Overheads & Profit

Contractors Profit 10% 15.50 Overheads 5.00

B Sub Total 20.50

1 Taxes 8% 12.40 C Sub Total 12.40

G Grand Total (Rate per Unit) Rs./RM 187.90 H RATE PROPOSED Rs./RM 185.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as directed by engineer in charge. for 15mm dia pipe

Page 33: Rate Analysis for Nasik

SAPL Page 33 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 b

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 130.00 RM 1.00 130.00

- -

2 Labour - Cutting, Fitting Charges 40.00 RM 1.00 40.00

- -

3 Other Expenditure

A Sub Total 170.00 1 Overheads & Profit

Contractors Profit 10% 17.00 Overheads 5.00

B Sub Total 22.00

1 Taxes 8% 13.60 C Sub Total 13.60

G Grand Total (Rate per Unit) Rs./RM 205.60 H RATE PROPOSED Rs./RM 200.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as directed by engineer in charge. for 25mm dia pipe

Page 34: Rate Analysis for Nasik

SAPL Page 34 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 c

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 150.00 RM 1.00 150.00

- -

2 Labour - Cutting, Fitting Charges 60.00 RM 1.00 60.00

- -

3 Other Expenditure

A Sub Total 210.00 1 Overheads & Profit

Contractors Profit 10% 21.00 Overheads 5.00

B Sub Total 26.00

1 Taxes 8% 16.80 C Sub Total 16.80

G Grand Total (Rate per Unit) Rs./RM 252.80 H RATE PROPOSED Rs./RM 250.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as

Page 35: Rate Analysis for Nasik

SAPL Page 35 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 d

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 200.00 RM 1.00 200.00

- -

2 Labour - Cutting, Fitting Charges 100.00 RM 1.00 100.00

- -

3 Other Expenditure

A Sub Total 300.00 1 Overheads & Profit

Contractors Profit 10% 30.00 Overheads 10.00

B Sub Total 40.00

1 Taxes 8% 24.00 C Sub Total 24.00

G Grand Total (Rate per Unit) Rs./RM 364.00 H RATE PROPOSED Rs./RM 350.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as directed by engineer in charge. for 40mm dia pipe

Page 36: Rate Analysis for Nasik

SAPL Page 36 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 e

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 280.00 RM 1.00 280.00

- -

2 Labour - Cutting, Fitting Charges 150.00 RM 1.00 150.00

- -

3 Other Expenditure

A Sub Total 430.00 1 Overheads & Profit

Contractors Profit 10% 43.00 Overheads 10.00

B Sub Total 53.00

1 Taxes 8% 34.40 C Sub Total 34.40

G Grand Total (Rate per Unit) Rs./RM 517.40 H RATE PROPOSED Rs./RM 500.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as

Page 37: Rate Analysis for Nasik

SAPL Page 37 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 1

Rate Analysis for 1 NoComponent Rate Unit Quantity Amount

1 MaterialPan 3,500.00 Nos 1.00 3,500.00

2 LabourFitting Charges 900.00 No 1.00 900.00

3 Other Expenditure

A Sub Total 4,400.00 1 Overheads & Profit

Contractors Profit 10% 440.00 Overheads 47.02

B Sub Total 487.02

1 Taxes 8% 352.00 C Sub Total 352.00

G Grand Total (Rate per Unit) Rs./No 5,239.02 H RATE PROPOSED Rs./No 5,200.00

Item Description:Providing and fixing White Orissa type W.C. pan of "CERA" make (no. 2071) of size 580 x 440 mm with `P' or 'S' trap (No. 9002). The rate shall include concealed flush cock with necessary inlet connection upto flush cock and outlet connections in concealed manner ,cutting and making good floor etc. complete.

Page 38: Rate Analysis for Nasik

SAPL Page 38 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 2

Rate Analysis for 1 NoComponent Rate Unit Quantity Amount

1 MaterialCost of Pan 3,200.00 Nos 1.00 3,200.00

- -

2 Labour - Fitting Charges 700.00 No 1.00 700.00

- -

3 Other Expenditure

A Sub Total 3,900.00 1 Overheads & Profit

Contractors Profit 10% 390.00 Overheads 60.00

B Sub Total 450.00

1 Taxes 8% 312.00 C Sub Total 312.00

G Grand Total (Rate per Unit) Rs./No 4,662.00 H RATE PROPOSED Rs./No 4,700.00

Item Description:Providing and fixing glazed earthenware White Wall Hung European type standard WC pan of "Cera" make (no. 2045) with pair of CI chair brackets, white solid plastic seat cover (no. 2345 ) , CP brass hinges and rubber buffers, 25mm concealed Flush cock , 15mm concealed stop cock of "Jaquar" make, C.P. flanges, necessary fastner & fixing , cutting and making good the walls and floors where required, all complete.

Page 39: Rate Analysis for Nasik

SAPL Page 39 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 6

Rate Analysis for 1 NoComponent Rate Unit Quantity Amount

1 Material 420.00 Nos 1.00 420.00

- -

2 Labour - Fitting Charges 100.00 No 1.00 100.00

-

3 Other Expenditure

A Sub Total 520.00 1 Overheads & Profit

Contractors Profit 10% 52.00 Overheads 11.00

B Sub Total 63.00

1 Taxes 8% 41.60 C Sub Total 41.60

G Grand Total (Rate per Unit) Rs./No 624.60 H RATE PROPOSED Rs./No 625.00

Item Description:Providing & fixing in position S.S. towel rail of approved make of 600mm length, 20mm dia. With a pair of brackets or flanges fixed to wall with necessary screws, plugs etc. all as specified & directed.

20 mm NB x 600 mm. long S.S. towel rail.

Page 40: Rate Analysis for Nasik

SAPL Page 40 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

Page 41: Rate Analysis for Nasik

SAPL Page 41 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

1 Item No

Rate Analysis for 1 CumComponent Rate Unit Quantity Amount

1 MaterialCement 305.00 Bag 7.60 2,318.00 Aggregate 20MM 1,060.00 Cum 0.86 911.60 Natural Sand 1,555.00 Cum 0.43 668.65

2 Labour - Coolie 250.00 Day 0.50 125.00 Mason 500.00 Day 0.20 100.00 Mixer Operator 200.00 Day 0.05 10.00

3 Other Expenditure - Formwork/Scaffolding 180.00 Sq.M. 8.00 1,440.00 Curing & Watering Lumsump 40.00 Transmit Mixer Charges 160.00 Cum 1.00 160.00

- A Sub Total 5,773.25

1 Overheads & ProfitContractors Profit 15% 865.99 Overheads LS 50.00

B Sub Total 865.99

1 Taxes 10% 577.33 C Sub Total 577.33

G Grand Total (Rate per Unit) Rs./Cum 7,216.56

Item Description: Providing and laying controlled Reinforced Cement Concrete of M20 grade with 20mm down size graded crushed stone aggregates for all elements including scaffolding, opening, recesses, chamfering, finishing top surfaces, vibrating, machine mixing tamping, curing etc.complete as per the specifications, drawing and instruction of Engineer-in-charge (( Cement & Reinforcing steel shall be supplied free of cost by ABB ) Concrete shall be finished to the true line, level & as per tolerances required.)

Page 42: Rate Analysis for Nasik

SAPL Page 42 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

2 Item No

Rate Analysis for 1 CumComponent Rate Unit Quantity Amount

1 MaterialCement 305.00 Cum 8.50 2,592.50 Aggregate 1,060.00 Cum 0.86 911.60 Crushed Sand / Natural Sand 1,908.00 Cum 0.43 820.44

2 Labour - Coolie 250.00 Day 0.50 125.00 Mason 500.00 Day 0.20 100.00 Mixer Operator 200.00 Day 0.05 10.00

3 Other Expenditure - Formwork/Scaffolding 180.00 Sq.M. 8.00 1,440.00 Curing & Watering Lumsump 40.00 Transmit Mixer Charges 160.00 Cum 1.00 160.00

- A Sub Total 6,199.54

1 Overheads & ProfitContractors Profit 15% 929.93 Overheads 50.00

B Sub Total 979.93

1 Taxes 10% 619.95 C Sub Total 619.95

G Grand Total (Rate per Unit) Rs./Cum 7,799.43

Item Description:Providing and constructing cast in situ precast cover for cable trenches etc. of different size of M25 grade concrete with finishing top surface, curing by making necessary platform etc. Precast cover should be vibrated with surface vibrator for attaining proper finish of concrete surface. The rate should be inclusive of shuttering , placing, lifting hook, laying as per instruction of Engineer in charge.

Page 43: Rate Analysis for Nasik

SAPL Page 43 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

3 Item No

Rate Analysis for 1 MTComponent Rate Unit Quantity Amount

1 MaterialSteel (TMT-ISI) 43976 MT 1.00 43,976.00 Steel Cutting Machine 160.00 Day 0.50 80.00 Bar Bending Machine 370.00 Day 0.50 185.00

2 LabourCutting Charges 3.50 Kg. 1,070.00 3,745.00 Fixing Charges 3.50 Kg. 1,070.00 3,745.00 Labour for Shifting 300.00 Day 3.00 900.00

3 Other ExpenditureUnloading Charges LS 150.00 Scrap Loading Charges LS 25.00

A Sub Total 52,806.00 1 Overheads & Profit

Contractors Profit 15% 7,920.90 Overheads

B Sub Total 7,920.90

1 Taxes 10% 5,280.60 C Sub Total 5,280.60

G Grand Total (Rate per Unit) Rs./MT 66,007.50

Item Description:Providing and placing steel inclusing Unloading , Cutting, bending, binding, laying, transporting and fixing in position at any levels reinforcement bars for all concrete works including as per Engineer-in-charge etc. complete.

Page 44: Rate Analysis for Nasik

SAPL Page 44 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 MaterialCement Mortar (1:4) 1,200.00 Cum 0.0150 18.00 GI Chiken Mesh 12.00 Sq.M. 0.25 3.00

- 2 Labour -

Bhisti 250.00 Day 0.15 37.50 Mason 200.00 Day 0.25 50.00

- 3 Other Expenditure -

Formwork/Scaffolding Lumsump 5.00 Water Charges/ Curing 5.00

A Sub Total 118.50 1 Overheads & Profit

Contractors Profit 15% 17.78 Overheads

B Sub Total 17.78

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Sq.M. 136.28 H RATE PROPOSED Rs./Sq.M. 100.00

Item Description:.Providing and applying 12mm thick smooth cement plaster at all heights and below plinth in C.M. 1:6 to walls, beams, column, drain, bends, moulds, grooves, pattas and drip course to all brick and RCC surfaces including raking joints,scaffolding, curing finishing smooth. The plaster shall be rubbed with "Iron Plate" till the surface shows cement paste in line level complete as directed.

Page 45: Rate Analysis for Nasik

SAPL Page 45 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

E Item No E 7.00

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 Material 22.00 Nos 17.00 374.00

1,221.00 Cum 0.01 14.65

1.67 1 time 15.55 25.97

Bags 0.07 -

- 2 Labour -

Bhisti 350.00 Day 0.40 140.00 Mason 225.00 Day 1.00 225.00

- 3 Other Expenditure -

- -

A Sub Total 779.62 1 Overheads & Profit

Contractors Profit 15% 116.94 Overheads 15.00

B Sub Total 131.94

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Sq.M. 911.56 H RATE PROPOSED Rs./Sq.M. 900.00

Item Description: Providing and fixing 300mm x 300mm x 7.3 mm thick heavy duty Ceramic tiles (Matt finish) of "NITCO" or "BELL" make in flooring & skirting / dado including laying over 12mm thick C.M. 1:3 mix bed to proper level or slope and and jointed with grey cement slurry @ 3.3 Kg/ Sqm including pointing in white cement mixed with matching colour pigment etc. complete. ( Rate shall be inclusive of backing coat of cement plaster wherever required) Basic rate of tiles shall be Rs.450/ sqm

Colour Ceramic tiles (30cm x20cm) including wastages

10 mm thk. Cement Mortar 1:3 with coarse sand

Mortar for pointing with white cement

Cement for slurry over bed @ 3.3 kg/sq.m

Page 46: Rate Analysis for Nasik

SAPL Page 46 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

E Item No E 2a

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 Material 220.00 Nos 3.00 660.00

2,100.00 Cum 0.01 25.20

3.50 1 time 15.55 54.43

Bags 0.07 -

- 2 Labour -

Bhisti 350.00 Day 0.50 175.00 Mason 250.00 Day 1.50 375.00

- 3 Other Expenditure -

- -

A Sub Total 1,289.63 1 Overheads & Profit

Contractors Profit 15% 193.44 Overheads 30.00

B Sub Total 223.44

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Sq.M. 1,513.07 H RATE PROPOSED Rs./Sq.M. 1,500.00

Item Description: Providing & laying 1st quality of Marbogranite vitrified tiles of 600 x 600mm size of 9 mm thk, approved make, colour and shade (50% premium & 50% non-premium colours) in flooring over min. 41 mm thick bed of CM 1:4 and jointing with Grey cement slurry @ 3.3 kg per Sqmt incl. pointing in white cement mixed with pigment of matching colour at all levels and all heights etc complete. Basic rate Rs. 750 / sqm

Vetrified Tiles (60cm x60cm) including wastages

10 mm thk. Cement Mortar 1:3 with coarse sand

Mortar for pointing with white cement

Cement for slurry over bed @ 3.3 kg/sq.m

Page 47: Rate Analysis for Nasik

SAPL Page 47 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

G Item No G 6.00

Rate Analysis for 1 Sq.M.Component Rate Unit Quantity Amount

1 MaterialBrick Bats 3.50 Sqm 58.00 203.00 Morter (1:5) 2,700.00 % 0.03 81.00 Cement for Slury 300.00 Bags 0.30 90.00

2 Labour - Mason 350.00 Day 0.20 70.00 Bhistri 250.00 Day 0.30 75.00

3 Other ExpenditureWaterproofing Chemical Lumsump 10.00

A Sub Total 529.00 1 Overheads & Profit

Contractors Profit 15% 79.35 Overheads 50.00

B Sub Total 129.35

1 Taxes 8% 42.32 C Sub Total 42.32

G Grand Total (Rate per Unit) Rs./Sq.M. 700.67 H RATE PROPOSED Rs./Sq.M. 700.00

Item Description:Providing and laying water proofing treatment over flat RCC roof & to vertical surface of parapet wall upto 300 mm high as per drawing shall be done including fillets at juction of roof & vertical walls with M-15 grade concrete finished with 12 mm thick CM 1:4 ( only plan area to be taken for measurement purpose ) as per following layer

Page 48: Rate Analysis for Nasik

SAPL Page 48 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 a

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 115.00 RM 1.00 115.00

- -

2 Labour - Cutting, Fitting Charges 40.00 RM 1.00 40.00

- -

3 Other Expenditure

A Sub Total 155.00 1 Overheads & Profit

Contractors Profit 10% 15.50 Overheads 5.00

B Sub Total 20.50

1 Taxes 8% 12.40 C Sub Total 12.40

G Grand Total (Rate per Unit) Rs./RM 187.90 H RATE PROPOSED Rs./RM 185.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as directed by engineer in charge. for 15mm dia pipe

Page 49: Rate Analysis for Nasik

SAPL Page 49 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 b

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 130.00 RM 1.00 130.00

- -

2 Labour - Cutting, Fitting Charges 40.00 RM 1.00 40.00

- -

3 Other Expenditure

A Sub Total 170.00 1 Overheads & Profit

Contractors Profit 10% 17.00 Overheads 5.00

B Sub Total 22.00

1 Taxes 8% 13.60 C Sub Total 13.60

G Grand Total (Rate per Unit) Rs./RM 205.60 H RATE PROPOSED Rs./RM 200.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as directed by engineer in charge. for 25mm dia pipe

Page 50: Rate Analysis for Nasik

SAPL Page 50 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 c

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 150.00 RM 1.00 150.00

- -

2 Labour - Cutting, Fitting Charges 60.00 RM 1.00 60.00

- -

3 Other Expenditure

A Sub Total 210.00 1 Overheads & Profit

Contractors Profit 10% 21.00 Overheads 5.00

B Sub Total 26.00

1 Taxes 8% 16.80 C Sub Total 16.80

G Grand Total (Rate per Unit) Rs./RM 252.80 H RATE PROPOSED Rs./RM 250.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as

Page 51: Rate Analysis for Nasik

SAPL Page 51 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 d

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 200.00 RM 1.00 200.00

- -

2 Labour - Cutting, Fitting Charges 100.00 RM 1.00 100.00

- -

3 Other Expenditure

A Sub Total 300.00 1 Overheads & Profit

Contractors Profit 10% 30.00 Overheads 10.00

B Sub Total 40.00

1 Taxes 8% 24.00 C Sub Total 24.00

G Grand Total (Rate per Unit) Rs./RM 364.00 H RATE PROPOSED Rs./RM 350.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as directed by engineer in charge. for 40mm dia pipe

Page 52: Rate Analysis for Nasik

SAPL Page 52 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 15 e

Rate Analysis for 1 RMComponent Rate Unit Quantity Amount

1 MaterialCost of Pipe 280.00 RM 1.00 280.00

- -

2 Labour - Cutting, Fitting Charges 150.00 RM 1.00 150.00

- -

3 Other Expenditure

A Sub Total 430.00 1 Overheads & Profit

Contractors Profit 10% 43.00 Overheads 10.00

B Sub Total 53.00

1 Taxes 8% 34.40 C Sub Total 34.40

G Grand Total (Rate per Unit) Rs./RM 517.40 H RATE PROPOSED Rs./RM 500.00

Item Description:Providing and fixing concealed GI 'B'' class water supply pipe line of "Jindal" make & of following diameters at all levels, including providing & fixing C.P. disc & nipple plug to seal provisional plumbing line outlets with all necessary specials of "R" brand, excavation and refilling the trenches, cutting floors, making hole in RCC/ Brick work and finishing & making good after work etc. including wrapping of layer of polythene sheet over a coat of bituminous paint, hydro test complete as

Page 53: Rate Analysis for Nasik

SAPL Page 53 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 1

Rate Analysis for 1 NoComponent Rate Unit Quantity Amount

1 MaterialPan 3,500.00 Nos 1.00 3,500.00

2 LabourFitting Charges 900.00 No 1.00 900.00

3 Other Expenditure

A Sub Total 4,400.00 1 Overheads & Profit

Contractors Profit 10% 440.00 Overheads 47.02

B Sub Total 487.02

1 Taxes 8% 352.00 C Sub Total 352.00

G Grand Total (Rate per Unit) Rs./No 5,239.02 H RATE PROPOSED Rs./No 5,200.00

Item Description:Providing and fixing White Orissa type W.C. pan of "CERA" make (no. 2071) of size 580 x 440 mm with `P' or 'S' trap (No. 9002). The rate shall include concealed flush cock with necessary inlet connection upto flush cock and outlet connections in concealed manner ,cutting and making good floor etc. complete.

Page 54: Rate Analysis for Nasik

SAPL Page 54 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 2

Rate Analysis for 1 NoComponent Rate Unit Quantity Amount

1 MaterialCost of Pan 3,200.00 Nos 1.00 3,200.00

- -

2 Labour - Fitting Charges 700.00 No 1.00 700.00

- -

3 Other Expenditure

A Sub Total 3,900.00 1 Overheads & Profit

Contractors Profit 10% 390.00 Overheads 60.00

B Sub Total 450.00

1 Taxes 8% 312.00 C Sub Total 312.00

G Grand Total (Rate per Unit) Rs./No 4,662.00 H RATE PROPOSED Rs./No 4,700.00

Item Description:Providing and fixing glazed earthenware White Wall Hung European type standard WC pan of "Cera" make (no. 2045) with pair of CI chair brackets, white solid plastic seat cover (no. 2345 ) , CP brass hinges and rubber buffers, 25mm concealed Flush cock , 15mm concealed stop cock of "Jaquar" make, C.P. flanges, necessary fastner & fixing , cutting and making good the walls and floors where required, all complete.

Page 55: Rate Analysis for Nasik

SAPL Page 55 of 59

Shreehari Associates (P) Ltd.Project: RATE ANALYSIS FOR PROJECT AT NASIK

Rate Analysis-Proposed Rates

H Item No 6

Rate Analysis for 1 NoComponent Rate Unit Quantity Amount

1 Material 420.00 Nos 1.00 420.00

- -

2 Labour - Fitting Charges 100.00 No 1.00 100.00

-

3 Other Expenditure

A Sub Total 520.00 1 Overheads & Profit

Contractors Profit 10% 52.00 Overheads 11.00

B Sub Total 63.00

1 Taxes 8% 41.60 C Sub Total 41.60

G Grand Total (Rate per Unit) Rs./No 624.60 H RATE PROPOSED Rs./No 625.00

Item Description:Providing & fixing in position S.S. towel rail of approved make of 600mm length, 20mm dia. With a pair of brackets or flanges fixed to wall with necessary screws, plugs etc. all as specified & directed.

20 mm NB x 600 mm. long S.S. towel rail.

Page 56: Rate Analysis for Nasik

Rate analysis forExcavator

SR.NO. PARTICULARS Unit Qty RATE AMOUNT 1 diesel Ltr 25.00 54.00 1,350.00 2 hydralic oil gram 300.00 0.50 150.00 3 engine oil grame 150.00 0.50 75.00 3 grease grame 200.00 0.50 100.00 4 operator 1.00 60.09 60.09 5 helper 1.00 28.00 28.00

Total 1,763.09 17.63

6 profit 20% 2.64 7 Maintenance LS 5.00 8 Taxes 15% 2.64 9 Hore charges 5.00

TOTAL 32.92 0.33

Page 57: Rate Analysis for Nasik

B Item No 3 j

Rate Analysis for 1 CumComponent Rate Unit Quantity Amount

1 MaterialCement As per Agreement Aggregate 650.00 Cum 0.80 520.00

750.00 Cum 0.60 450.00

2 Labour - Bhisti 1.00 Day 350.00 350.00 Mason 4.00 Day 240.00 960.00

- 3 Other Expenditure -

Formwork/Scaffolding 250.00 Sq.M. 6.00 1,500.00 Curing & Watering Lumsump 75.00

Mixing Charges 400.00 Cum 1.00 400.00 A Sub Total 4,255.00

1 Overheads & ProfitContractors Profit 15% 638.25 Overheads 100.00

B Sub Total 738.25

1 Taxes As per Agreement C Sub Total -

G Grand Total (Rate per Unit) Rs./Cum 4,993.25 H RATE PROPOSED Rs./Cum 5,000.00

Item Description: Providing, mixing and laying vibrating, curing plain / Reinforced cement concrete M:25Grade at any level with 20 mm and downsized aggregate for all types of works in foundation and superstructure, footings, raft beams, machinery foundations, columns, runners, coping, beam, walls, slabs, lintels, tie-beams, canopies, staircase, fins, ledge, any pattern & shapes etc. all including formwork, centering, staging, shuttering, bracing, propping and per the drawing, specification; but, excluding the cost of Reinforcement. (Minimum Cement Consumption should be 360 kg / Cumt )Sills, copings.

Crushed Sand / Natural Sand

Page 58: Rate Analysis for Nasik

9 Item No

Rate Analysis for 1 Sq.M.Component Area Unit ConsumptQuantityArea Statement

1 Details of cost for 9 sqm of plinth area 2.25 Ltrs 1.20 2.70

12.00 Ltrs 1.20 14.40

9.00 Ltrs 1.20 10.80

Total 27.90 Component Rate Unit Quantity Amount

1 MachineryChlorpyriphos 20% E.C. 95.00 Ltrs 5.58 530.10

2 LabourMason 210.00 Day 0.10 21.00

3 Other Expenditure

A Sub Total 551.10 1 Overheads & Profit

Contractors Profit 15% 82.67 Overheads 1.00

B Sub Total 83.67

1 Taxes As per agreementC Sub Total

G Grand Total (Rate per Unit) Rs./9 Sq.M 634.77 G Grand Total (Rate per Unit) Rs./Sq.M. 70.53 H RATE PROPOSED Rs./Sq.M. 65.00

7 Item No

Rate Analysis for 1 CumComponent Rate Unit Quantity Amount

1 MaterialMetal 450.00 Cum 1.00 450.00

Item Description: Providing, spraying and Injecting Chlorophysyphos / Lindane EC 20% or Biflex TC with 1% concentration or equivalent emulsifiable concentrates or approved chemical for pre constructional antitermite treatment so as to create a chemical barrier under and around the column pits, Wall trenches, basement Excavation, top surfaces of plinth filling, junction of wall and floor, along with external perimeter of the building, expansion joints, Surrounding of pipes and Conduits, etc. complete in accordance with IS 6313 (Part II)-1981. (Plinth area of the building at ground

(i) Footing 1 no 1.5 x 1.5 =(ii) Footing Wall = 4 x 1.5 x 2

(iii) Top surface of plinth fillings - 1x3x3 =

Item Description: Providing and laying Stone / Rubble Soling in single layer of 230 mmcompacted thickness under floor, using 150 to 230 mm size stone, including filling voids with 75 mm down grade metal & small interstices filled with approved murrum & quarry spoils , blinding with Sand / stone dust, watering and consolidating with power roller as directed. First dry rolling & rolling after watering.

Page 59: Rate Analysis for Nasik

Murrum 130.00 cum 0.25 32.50

2 Labour

Labour 215.00 Day 0.20 43.00

3 Other ExpenditureWater Tanker 750.00 Hr. 0.05 37.50 Soil Compactor 850.00 Hr. 0.05 42.50

A Sub Total 605.50 1 Overheads & Profit

Contractors Profit 15% 90.83 Overheads 5.00

B Sub Total 95.83

1 Taxes As per agreementC Sub Total -

G Grand Total (Rate per Unit) Rs./CUM 701.33 H RATE PROPOSED Rs./Sq.M. 247.82