rate amount no description qty unit kshs. boq's for...
TRANSCRIPT
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
BOQ's FOR APPARTMENTS ON PLOT NO. 209/20160 AT
PARKROAD IN NGARA (UP TO 5TH LEVEL)
GROUND FLOOR
ELEMENT NO. 1
SUBSTRUCTURE
(ALL PROVISIONAL)
EXCAVATIONS
A
Excavate over site average 150 mm deep to remove vegetable
soil and wheel and cart away from site as directed
1066 SM 100.00 106,600.00
BMass excavation to remove red cotton soil, starting from
stripped level but not exceeding 1.50 metres deep534 CM 200.00 106,800.00
CExcavate foundation trench not exceeding 1.50 metres deep
starting from stripped level98 CM 200.00 19,600.00
D Ditto column pits ditto 50 CM 200.00 10,000.00
Disposal of excavated materials
E Return, fill in and ram excavated material around foundations 90 CM 100.00 9,000.00
F Load surplus excavated material and remove from site 1512 CM 500.00 756,000.00
Planking and Strutting
G Allow for upholding sides of excavations Item 100,000.00
Disposal of Water
H Allow for keeping excavation free from all water Item 100,000.00
SELECTED HARDCORE
I300 mm Thick hardcore filling in layers not exceeding 150 mm
thick300 SM 250.00 75,000.00
J50 mm Thick stone dust blinding to surface of hardcore to
receive concrete300 SM 100.00 30,000.00
Carried to Collection Kshs. 1,313,000.00
Bill No. 3
EI. No. 1
Substructure
3/1/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Damp Proof Membrane
A Single layer of 1000 gauge polythene sheeting laid on blinded
hardcore with 150 mm side laps to receive concrete
366 SM 200.00 73,200.00
Soil sterilization
B
Treat surface of hardcore with 'Dieldrin or similar approved
anti-termite solution applied strictly in accordance with the
manufacturer's instructions
366 SM 200.00 73,200.00
CONCRETE WORK
Plain concrete (1:4:8) in:-
C 50 mm Blinding under column bases and strip foundation 147 SM 325.00 47,775.00
Reinforced concrete (1:2:4) in:-
D Column bases and columns 30 CM 10,000.00 300,000.00
E Foundation trench 58 CM 10,000.00 580,000.00
F 150 mm Thick surface bed 1036 SM 1,500.00 1,554,000.00
Supply and fix steel bar reinforcement including bending,
hooking, tying wires, cutting spacers and supporting all in
position in column bases, strip footing and columns.
G 8 mm diameter bars 860 Kgs 150.00 129,000.00
F 10 mm ditto 732 Kgs 150.00 109,800.00
G 12 mm ditto 2034 Kg 150.00 305,100.00
Steel fabric mesh reinforcement
H
BRC mesh fabric reinforced reference A142 (weighing 2.22
kg/m2) laid in slab (measured net - no allowance made for
laps)
1036 SM 375.00 388,500.00
Carried to Collection Kshs. 3,560,575.00
Bill No. 3
EI. No. 1
Substructure
3/1/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Sawn formwork to:-
A Edge of slab 75 - 150 mm high 130 LM 67.50 8,775.00
B Sides of column bases 120 SM 450.00 54,000.00
C Vertical sides of column 100 SM 450.00 45,000.00
MASONRY
Quarry stone walling in cement mortar (1:4) as described in:-
D 200 mm walling 226 SM 1,500.00 339,000.00
Plinths finishes
E12 mm Thick cement and sand (1:4) render to edge of plinth
40 SM 300.00 12,000.00
FPrepare and apply two coats of bituminous paint on rendered
plinths40 SM 280.00 11,200.00
Carried to Collection Kshs 469,975.00
Bill No. 3
EI. No. 1
Substructure
3/1/3
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
COLLECTION
Page No. 3/1/1 1,313,000.00
Page No. 3/1/2 3,560,575.00
Page No. 3/1/3 469,975.00
TOTAL AMOUNT OF ELEMENT NO. 1
SUBSTRUCTURE
Carried to Summary of Bill No. 3 Kshs 5,343,550.00
Bill No. 3
El. No. 1
Substructure
3/1/4
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 2
REINFORCED CONCRETE SUPERSTRUCTURE
Vibrated reinforced concrete (1:2:4) as described in:-
A Beams 48 CM 10,000.00 480,000.00
B Columns 10 CM 10,000.00 100,000.00
C Suspended Slab (1st Floor slab) 538 SM 1,500.00 807,000.00
High tensile square twisted to B.S 4461 as described in:-
D 8 mm Diameter bars 5548 Kg 150.00 832,200.00
E 10 mm Ditto 9344 Kg 150.00 1,401,600.00
F 12 mm Ditto 5628 Kg 150.00 844,200.00
Sawn formwork as described to:-
G Vertical sides of columns 168 SM 450.00 75,600.00
H Sides and horizontal soffits of beams 478 SM 450.00 215,100.00
I Edge of slab 75 - 150 mm high 232 LM 67.50 15,660.00
J Soffits of suspendend Slab 700 SM 450.00 315,000.00
TOTAL AMOUNT OF ELEMENT NO. 2
RC SUPERSTRUCTURE
Carried to Summary of Bill No. 3 Kshs 5,086,360.00
Bill No. 3
El. No. 2
RC Superstructure
3/2/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 3
STAIRCASE & RAILINGS
Vibrated reinforced concrete (1:2:4) as described in:-
A Slopping stairs 72 CM 8,500.00 612,000.00
B 150 mm Thick landing 96 SM 1,275.00 122,400.00
Steel Bar Reinforcement
High tensile square twisted bars as before described in:-
C 12 mm Diameter bars 1600 Kg 120.00 192,000.00
D 8 mm Ditto 1920 Kg 120.00 230,400.00
Sawn formwork to:-
E Horizontal soffits of landing 96 SM 400.00 38,400.00
F Slopping of stairs 144 SM 400.00 57,600.00
G Edges of landing over 75 and not exceeding 150 mm high 192 LM 60.00 11,520.00
H Edges of risers over 75 and not exceeding 150 mm wide 336 LM 60.00 20,160.00
IOpening edge of string of 300 mm wide (extreme) including
cutting to profile of treads and risers108 LM 120.00 12,960.00
Finishes
JPockets in concrete or block work size 75 x 75 x 50 mm deep
for end of balusters176 No. 50.00 8,800.00
Wrot Mahogany
K 100 x 75 mm moulded handrail screwed to balusters 120 LM 900.00 108,000.00
Carried to Collection Kshs 1,414,240.00
Bill No. 3
El. No. 3
Staircases & Railings
3/3/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Mild Steel
A 50 x 25 x 3 mm RHS baluster, 900 mm long 264 No. 550.00 145,200.00
B 50 x 3 mm Flats screwed to end of baluster 30 LM 450.00 13,500.00
Wrot Mahogany
C 25 mm Thick timber boarding 12 SM 3,000.00 36,000.00
D Ditto to treads, 275 mm wide 66 LM 750.00 49,500.00
E Ditto to risers, 150 mm high 66 LM 450.00 29,700.00
FClosed edge of staircase, 300 mm wide (extreme) and to profile
of treads and risers27 LM 900.00 24,300.00
G Extra over tread for forming non-slip inserts 66 LM 100.00 6,600.00
Two coat lime plasterwork 15 mm thick to: -
H Slopping soffits of stairs 36 SM 240.00 8,640.00
I Soffits of landing 24 SM 240.00 5,760.00
PAINTING AND DECORATING
Prepare and apply three coats gloss oil paint as described:-
Internally on:-
J Plastered soffits of stairs 36 SM 240.00 8,640.00
K Plastered soffits of landing 24 SM 240.00 5,760.00
Carried to Collection Kshs 333,600.00
Bill No. 3
El. No. 3
Staircase & Railings
3/3/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Prepare and apply three coats polyurethane clear varnish to
woodwork as described
Internally on:
A General Surfaces 90 SM 240.00 21,600.00
Prepare and apply two coats gloss oil paint to metalwork as
described
Internally on:
B General surfaces of balustrading (b.s.m - flat overall) 150 SM 240.00 36,000.00
To Collection Kshs 57,600.00
COLLECTION
Page No. 3/4/1 1,414,240.00
Page No. 3/4/2 333,600.00
Page No. 3/4/3 57,600.00
TOTAL AMOUNT OF ELEMENT NO. 3
STAIRCASE & RAILINGS
Carried to Summary of Bill No. 3 Kshs 1,805,440.00
Bill No. 3
El. No. 3
Staircase & Railings
3/3/3
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 4
WALLING
EXTERNAL WALLING
Medium dressed natural stone walling bedded and jointed in
cement and sand (1:4) mortar
A200 mm walls reinforced with hoop iron at alternate course
188 SM 1,750.00 329,000.00
INTERNAL WALLING
Medium chisel dressed/machine cut natural stone walling as
before described
B200mm walls reinforced with hoop iron at every third course
324 SM 1,750.00 567,000.00
C100mm walls reinforced with hoop iron at every third course
20 SM 1,400.00 28,000.00
Horizontal Damp proof course to B.S 743 (measured net - no
allowance for lapse)
D 200 mm wide 322 LM 100.00 32,200.00
E 100mm wide 12 LM 100.00 1,200.00
TOTAL AMOUNT OF ELEMENT NO. 4
WALLING
Carried to Summary of Bill No. 3 Kshs 957,400.00
Bill No. 3
El. No. 4
Walling
3/4/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 5
WINDOWS
CONCRETE WORKS
Precast concrete (1:2:4) in:-
AWindow cill size 250 x 65 mm thick once sunk, weathered and
throated, finished fair face on exposed surfaces353 LM 350.00 123,550.00
JOINERY
Wrot mahogany
B 150 x 25 mm Pelmet top 353 LM 475.00 167,675.00
C 150 x 25 mm Pelmet fascia with three labours 353 LM 475.00 167,675.00
D 150 x 25 mm window board 353 LM 475.00 167,675.00
E 150 x 150 x 25 mm Pelmet box ends 120 No. 250.00 30,000.00
Wrot Cypress
F 50 x 25 mm Bearers, plugged 353 LM 90.00 31,770.00
Curtain track
G
Aluminium or other equal and approved I-section curtain rail
complete with fixing brackets, 10 No. rollers per metre run and
end stops
353 LM 200.00 70,600.00
Carried to Collection Kshs 758,945.00
Bill No. 3
El. No. 5
Windows
3/5/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Supply and fix the following standard steel casement windows
as manufactured by RLCO steel fabricators Ltd. Or other
equal and approved, complete with fixing lugs, ironmongery
and fittings all primed with one coat of red oxide before fixing
including bedding and pointing in cement and sand (1:4)
mortar as described including approved decorative mild steel
grilles
AWindow size 1500 x 1500 mm high overall, in 2 No. panels
openable side hung and 1 No. Fixed panel30 No. 13,000.00 390,000.00
B Ditto size 1500 x 1200 mm high 180 No. 10,800.00 1,944,000.00
C Ditto size 1500 x 1000 mm high 110 No. 8,700.00 957,000.00
EWindow size 900 x 900 mm high overall, in 2 No. panels
openable top hung and 1 No. Fixed panel90 NO 4,400.00 396,000.00
Glazing
F 5 mm clear sheet glass to metal including putty 500 SM 1,200.00 600,000.00
G 5mm Thick obscure sheet glass including putty 80 SM 1,500.00 120,000.00
Carried to Collection Kshs. 4,407,000.00
3/5/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
PAINTING AND DECORATING
Prepare and apply one coat aluminium wood primer on
woodwork before fixing
A Surfaces not exceeding 100 mm girth 48 LM 20.00 960.00
Prepare and paint two undercoats and one finishing coat gloss
oil paint metalwork as described
B General surfaces of windows 1160 SM 260.00 301,600.00
Knot Prime, stop and paint two undercoats and one finishing
coat clear varnish polyurethane on woodwork as described:-
Internally on:-
C General surfaces of pelmet boxes 71 SM 260.00 18,460.00
D Surfaces 200 to 300 mm girth 71 LM 72.00 5,112.00
Carried to Collection Kshs. 326,132.00
COLLECTION
Page No. 3/6/1 758,945.00
Page No. 3/6/2 4,407,000.00
Page No. 3/6/3 326,132.00
TOTAL AMOUNT OF ELEMENT NO. 6
WINDOWS
Carried to summary of Bill No. 3 Kshs 5,492,077.00
Bill No. 3
El. No. 5
Windows
3/5/4
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 6 DOORS
EXTERNAL DOORS
Steel Door
A
Purpose made double leaf steel casement door manufactured
from heavy duty frames complete with 4 mm clear glass and
locking devices fixed to masonry jambs and concrete heads and
all with mastic pointing all round, overall size, 900 x 2100 mm
3 No. 22,000.00 66,000.00
Painting and decorating
Prepare touch up primer and apply two undercoats and one
finishing coat gloss oil paint on metal work :-
B General surfaces of doors 36 SM 300.00 10,800.00
Carried to Collection Kshs 11,410,658.00
Bill No. 3
El. No. 6
Doors
3/6/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
INTERNAL DOORS
Flush door to B.S 459 part II hardwood lipped all round
A45 mm Thick (finished) internal quality semi - solid cored
flush, two leafed door size 830 x 2060 mm high 210 No. 4,500.00 945,000.00
B Ditto size 730 x 2060 mm high 110 No. 4,000.00 440,000.00
Frames and Finishing
Sawn cypress
C 200 x 50 mm Rebated frame, plugged 219 LM 400.00 87,600.00
D 75 x 25 mm moulded architrave 219 LM 150.00 32,850.00
E 25 mm diameter moulded quadrant 219 LM 150.00 32,850.00
Ironmonery
Supply and fix the following ironmongery complete with
matching screws all as per "Union" catalogue or other
equal and approved
F 100 mm pressed steel butt hinges 200 Prs 450.00 90,000.00
GTwo lever mortice lock complete with set of aluminium door
handle363 No. 3,000.00 1,089,000.00
H25 mm Diameter rubber door stop raw bolted to floor to wall
370 No. 100.00 37,000.00
Carried to Collection Kshs 14,241,758.00
Bill No. 3
El. No. 6
Doors
3/6/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
PAINTING AND DECORATING
Prepare and apply one coat aluminium primer on woodwork
before fixing
A Surfaces over 100 and not exceeding 200 mm girth 213 LM 50.00 10,650.00
Prepare and apply three coats polyurethane clear varnish to
woodwork as described
B General surfaces of flush doors ( b.s.m ) 142 SM 280.00 39,760.00
Carried to collection Kshs 39,760.00
COLLECTION
Page No. 3/6/1 11,410,658.00
Page No. 3/6/2 14,241,758.00
Page No. 3/6/3 39,760.00
TOTAL AMOUNT OF ELEMENT NO. 6
DOORS
Carried to Summary of Bill No. 3 Kshs 25,692,176.00
Bill No. 3
El. No.6
Doors
3/6/3
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 7
FINISHES
EXTERNAL FINISHES
Wall Finishes
15 mm Thick cement and sand (1:4) as described to:-
A Sides and soffits of beams 372 SM 240.00 89,280.00
B Keying and Pointing Sides of walls 282 SM 100.00 28,200.00
C Window and door reveals 282 LM 40.00 11,280.00
INTERNAL FINISHES
Floor Finishes
Cement and sand (1:4) screed as described in:-
D 24mm thick backing to receivegrano finish 351 SM 350.00 122,850.00
E 32 mm thick backing to receive ceramic tiles 685 SM 450.00 308,250.00
300 x 300 x 8 mm Approved non-slip ceramic tiles on screed
backing (m.s) with straight joints and pointing in white cement
as described
G Paving to floor 685 SM 1,500.00 1,027,500.00
H 15mm thick grano paving 351 SM 1,800.00 631,800.00
Carried to Collection Kshs 2,219,160.00
Bill No. 3
El. No. 8
Finishes
3/7/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Wall Finishes
15 mm thick two coat gauged lime plaster to:-
A Sides of walls 1536 SM 240.00 368,640.00
B Window reveals and jambs 768 LM 40.00 30,720.00
15 mm thick cement and sand (1:4) in:-
CFloated screed backing on walls to receive white glazed wall
tiles (m.s)183 SM 240.00 43,920.00
Glazed wall tiles as described
D150 x 150 x 6 mm thick tiles on screed backing (m.s) with
straight joints and pointing in coloured cement183 SM 1,000.00 183,000.00
Ceiling Finishes
15 mm Thick two coat gauged lime plaster to:-
E Horizontal soffits of suspended slab 1152 SM 240.00 276,480.00
Carried to Collection Kshs 902,760.00
Bill No. 3
El. No. 7
Finishes
3/7/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
PAINTING AND DECORATING
Prepare and apply one coat aluminium primer on back of wood
before fixing on:-
A Surfaces not exceeding 100 mm girth 468 LM 20.00 9,360.00
Prepare and apply three coats Plastic emulsion paint:-
Internally on:-
B Sides of walls 3214 SM 240.00 771,360.00
C Window reveals and jambs 514 LM 40.00 20,560.00
D Horizontal soffits of suspended slab 2234 SM 240.00 536,160.00
Prepare and apply three coats emulsion paint:-
Externally on:-
E Sides and soffits of beams 732 SM 240.00 175,680.00
F Window and door reveals 542 LM 40.00 21,680.00
Carried to Summary Kshs 1,534,800.00
Bill No. 3
El. No. 7
Finishes
3/7/3
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
COLLECTION
Page No. 3/7/1 2,219,160.00
Page No. 3/7/2 902,760.00
Page No. 3/7/3 1,534,800.00
TOTAL AMOUNT OF ELEMENT NO. 7
FINISHES
Carried to Summary of Bill No. 3 Kshs 4,656,720.00
Bill No. 3
El. No. 8
Finishes
3/7/4
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
BILL NO. 3
GROUND FLOOR
SUMMARY
ELEMENT NO. PAGE NO.
1. SUBSTRUCTURE 3/1/3 5,343,550.00
2. REINFORCED CONCRETE SUPERSTRUCTURE 3/2/1 5,086,360.00
3. STAIRCASE 3/3/1 1,805,440.00
4. WALLING 3/4/1 957,400.00
5. WINDOWS 3/5/3 5,492,077.00
6. DOORS 3/6/5 25,692,176.00
7. FINISHES 5/7/4 4,656,720.00
TOTAL AMOUNT OF BILL NO. 3
MAIN HOUSE
CARRIED TO MAIN SUMMARY KSHS 49,033,723.00
3/S/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
TYPICAL FLOORS (1st 2nd 3rd 4th and 5th FLOORS)
ELEMENT NO. 8
REINFORCED CONCRETE SUPERSTRUCTURE
Vibrated reinforced concrete (1:2:4) as described in:-
A Beams and ring beams 288 CM 10,000.00 2,880,000.00
B Columns 51 CM 10,000.00 510,000.00
C Suspended Slab (2nd, 3rd & 4th Floor slabs) 2421 SM 1,500.00 3,631,500.00
High tensile square twisted to B.S 4461 as described in:-
D 8 mm Diameter bars 21279 Kg 150.00 3,191,850.00
E 10 mm Ditto 33042 Kg 150.00 4,956,300.00
F 12 mm Ditto 16287 Kg 150.00 2,443,050.00
Sawn formwork as described to:-
G Vertical sides of columns 1008 SM 450.00 453,600.00
H Sides and horizontal soffits of beams 2877 SM 450.00 1,294,650.00
I Soffits of Suspended slab 2421 SM 450.00 1,089,450.00
J Edge of slab 75 - 150 mm high 1612 LM 67.50 108,810.00
TOTAL AMOUNT OF ELEMENT NO. 1
RC SUPERSTRUCTURE
Carried to Summary of Bill No. 3 Kshs 20,559,210.00
Bill No. 3
El. No. 8
RC Superstructure
3/8/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 9
WALLING
EXTERNAL WALLING
Medium dressed natural stone walling bedded and jointed in
cement and sand (1:4) mortar
A200mm walls reinforced with hoop iron at alternate course
2031 SM 1,750.00 3,554,250.00
BLabour and materials for eaves filling on 200 mm thick walls
351 LM 250.00 87,750.00
INTERNAL WALLING
Medium chisel dressed/machine cut natural stone walling as
before described
C200mm walls reinforced with hoop iron at every third course
2052 SM 1,750.00 3,591,000.00
D100mm walls reinforced with hoop iron at every third course
330 SM 1,400.00 462,000.00
TOTAL AMOUNT OF ELEMENT NO. 3
WALLING
Carried to Summary of Bill No. 3 Kshs 7,695,000.00
Bill No. 3
El. No. 9
Walling
3/9/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 10
WINDOWS
CONCRETE WORKS
Precast concrete (1:2:4) in:-
AWindow cill size 250 x 65 mm thick once sunk, weathered and
throated, finished fair face on exposed surfaces177 LM 350.00 61,950.00
JOINERY
Wrot mahogany
B 150 x 25 mm Pelmet top 177 LM 475.00 84,075.00
C 150 x 25 mm Pelmet fascia with three labours 177 LM 475.00 84,075.00
D 150 x 25 mm window board 177 LM 475.00 84,075.00
E 150 x 150 x 25 mm Pelmet box ends 264 No. 250.00 66,000.00
Wrot Cypress
F 50 x 25 mm Bearers, plugged 177 LM 90.00 15,930.00
Curtain track
G
Aluminium or other equal and approved I-section curtain rail
complete with fixing brackets, 10 No. rollers per metre run and
end stops
177 LM 200.00 35,400.00
Carried to Collection Kshs 431,505.00
Bill No. 3
El. No. 10
Windows
3/10/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Supply and fix the following standard steel casement windows
as manufactured by RLCO steel fabricators Ltd. Or other
equal and approved, complete with fixing lugs, ironmongery
and fittings all primed with one coat of red oxide before fixing
including bedding and pointing in cement and sand (1:4)
mortar as described including approved decorative mild steel
grilles
AWindow size 2000 x 1200 mm high overall, in 2 No. panels
openable side hung and 1 No. Fixed panel4 No. 14,400.00 57,600.00
B Ditto size 1800 x 1200 mm high 36 No. 13,000.00 468,000.00
C Ditto size 1500 x 1200 mm high 28 NO 11,000.00 308,000.00
D Ditto size 800 x 1200 mm high 36 NO 6,000.00 216,000.00
EWindow size 1000 x 600 mm high overall, in 2 No. panels
openable top hung and 1 No. Fixed panel28 NO 4,400.00 123,200.00
Glazing
F 5 mm clear sheet glass to metal including putty 177 SM 1,200.00 212,400.00
G 5mm Thick obscure sheet glass including putty 17 SM 1,500.00 25,500.00
Carried to Collection Kshs. 1,410,700.00
3/10/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
PAINTING AND DECORATING
Prepare and apply one coat aluminium wood primer on
woodwork before fixing
A Surfaces not exceeding 100 mm girth 177 LM 20.00 3,540.00
Prepare and paint two undercoats and one finishing coat gloss
oil paint metalwork as described
B General surfaces of windows 194 SM 260.00 50,440.00
Knot Prime, stop and paint two undercoats and one finishing
coat clear varnish polyurethane on woodwork as described:-
Internally on:-
C General surfaces of pelmet boxes 177 SM 260.00 46,020.00
D Surfaces 200 to 300 mm girth 177 LM 72.00 12,744.00
Carried to Collection Kshs. 112,744.00
COLLECTION
Page No. 3/10/1 431,505.00
Page No. 3/10/2 1,410,700.00
Page No. 3/10/3 112,744.00
TOTAL AMOUNT OF ELEMENT NO. 10
WINDOWS
Carried to summary of Bill No. 3 Kshs 1,954,949.00
Bill No. 3
El. No. 10
Windows
3/10/4
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 11 DOORS
EXTERNAL DOORS
Steel Door
A
Purpose made double leaf steel casement door manufactured
from heavy duty frames complete with 4 mm clear glass and
locking devices fixed to masonry jambs and concrete heads and
all with mastic pointing all round, overall size, 900 x 2100 mm
56 No. 22,000.00 1,232,000.00
Painting and decorating
Prepare touch up primer and apply two undercoats and one
finishing coat gloss oil paint on metal work :-
B General surfaces of doors 212 SM 300.00 63,600.00
Carried to Collection Kshs 5,377,006.00
Bill No. 3
El. No. 11
Doors
3/11/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
INTERNAL DOORS
Flush door to B.S 459 part II hardwood lipped all round
A45 mm Thick (finished) internal quality semi - solid cored
flush, two leafed door size 830 x 2060 mm high 68 No. 4,500.00 306,000.00
B Ditto size 730 x 2060 mm high 28 No. 4,000.00 112,000.00
Frames and Finishing
Sawn cypress
C 200 x 50 mm Rebated frame, plugged 528 LM 400.00 211,200.00
D 75 x 25 mm moulded architrave 528 LM 150.00 79,200.00
E 25 mm diameter moulded quadrant 528 LM 150.00 79,200.00
Ironmonery
Supply and fix the following ironmongery complete with
matching screws all as per "Union" catalogue or other
equal and approved
F 100 mm pressed steel butt hinges 144 Prs 450.00 64,800.00
GTwo lever mortice lock complete with set of aluminium door
handle96 No. 3,000.00 288,000.00
H25 mm Diameter rubber door stop raw bolted to floor to wall
152 No. 100.00 15,200.00
Carried to Collection Kshs 7,828,206.00
Bill No. 3
El. No. 11
Doors
3/11/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
PAINTING AND DECORATING
Prepare and apply one coat aluminium primer on woodwork
before fixing
A Surfaces over 100 and not exceeding 200 mm girth 528 LM 50.00 26,400.00
Prepare and apply three coats polyurethane clear varnish to
woodwork as described
B General surfaces of flush doors ( b.s.m ) 352 SM 300.00 105,600.00
Carried to collection Kshs 105,600.00
COLLECTION
Page No. 3/11/1 5,377,006.00
Page No. 3/11/2 7,828,206.00
Page No. 3/11/3 105,600.00
TOTAL AMOUNT OF ELEMENT NO. 11
DOORS
Carried to Summary of Bill No. 3 Kshs 13,310,812.00
Bill No. 3
El. No.11
Doors
3/11/3
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 12
ROOFING
The following in roof trusses spanning variously and raised to
6000 mm above ground
A 150 x 50 mm Thick rafter 524 LM 300.00 157,200.00
B 150 x 50 mm Thick tie beam 502 LM 300.00 150,600.00
C 100 x 50 mm struts/tie 527 LM 250.00 131,750.00
D 150 x 50 mm common rafter 645 LM 300.00 193,500.00
E 150 x 50 mm valley rafter 475 LM 300.00 142,500.00
F 150 x 50 mm hip rafter 488 LM 300.00 146,400.00
H 200 x 50 ridge board 490 LM 400.00 196,000.00
I 75 x 50 mm purlins 675 LM 200.00 135,000.00
J 100 x 50 mm wall plate 312 LM 300.00 93,600.00
ROOF FINISHES
28 Gauge galvanized corrugated pre - painted iron sheet
covering as manufactured by GAL SHEET KENYA LTD or
other equal and approved laid with 150 mm end and one - and -
half corrugation side laps and fixed to timber purlins (m.s) all
in strict accordance with printed instructions:-
K Roof covering 509 SM 1,500.00 763,500.00
L Ridge capping 141 LM 350.00 49,350.00
24 SWG galvanized mild steel plain sheet with lapped riveted
and soldered joints including all labours
M 600 mm girth valley gutters 225 LM 750.00 168,750.00
O450 mm girth flashing one edge grouted into and including 50
x 25 mm groove in block wall114 LM 450.00 51,300.00
Carried to Collection Kshs 2,379,450.00
Bill No. 3
El. No. 12
Roofing
3/12/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Eaves finishes
A 225 x 25 mm Fascia or barge boards 249 LM 350.00 87,150.00
Sawn treated cypress
B 50 x 50 mm bearers 249 LM 120.00 29,880.00
C Ditto plugged 249 LM 120.00 29,880.00
PAINTING AND DECORATING
Prepare and apply one coat aluminium primer on wood
surfaces before fixing to:-
D Surfaces not exceeding 100 mm girth 249 LM 20.00 4,980.00
Prepare and apply three coats clear varnish polyurethane paint
on wood surfaces to:-
Externally on:-
Knot, prime, stop, prepare and apply three coats gloss oil paint
on wood work surfaces
Externally to:
E Fascia board surfaces 200 - 300 mm girth 249 LM 72.00 17,928.00
Carried to Collection Kshs 169,818.00
Bill No. 3
El. No. 12
Roofing
3/12/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
COLLECTION
Page No. 3/12/1 2,379,450.00
Page No. 3/12/2 169,818.00
TOTAL AMOUNT OF ELEMENT NO. 5
ROOFING
Carried to Summary of Bill No. 3 Kshs 2,549,268.00
Bill No. 3
El. No. 12
Roofing
3/12/3
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
ELEMENT NO. 13
FINISHES
EXTERNAL FINISHES
Wall Finishes
15 mm Thick cement and sand (1:4) as described to:-
A Sides and soffits of beams 209 SM 240.00 50,160.00
B Keying and Pointing Sides of walls 677 SM 100.00 67,700.00
C Window and door reveals 445 LM 40.00 17,800.00
INTERNAL FINISHES
Floor Finishes
Cement and sand (1:4) screed as described in:-
D 24 mm thick backing to receive terrazo finish 324 SM 500.00 162,000.00
E 32 mm thick backing to receive ceramic tiles 1076 SM 450.00 484,200.00
300 x 300 x 8 mm Approved non-slip ceramic tiles on screed
backing (m.s) with straight joints and pointing in white cement
as described
F Paving to floor 1076 SM 1,500.00 1,614,000.00
G 15mm thick terrazzo pazing 324 SM 1,800.00 583,200.00
Carried to Collection Kshs 2,979,060.00
Bill No. 3
El. No. 13
Finishes
3/13/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
Wall Finishes
15 mm thick two coat gauged lime plaster to:-
A Sides of walls 2554 SM 240.00 612,960.00
B Window reveals and jambs 629 LM 40.00 25,160.00
15 mm thick cement and sand (1:4) in:-
CFloated screed backing on walls to receive white glazed wall
tiles (m.s)1226 SM 240.00 294,240.00
Glazed wall tiles as described
D150 x 150 x 6 mm thick tiles on screed backing (m.s) with
straight joints and pointing in coloured cement1226 SM 1,000.00 1,226,000.00
Ceiling Finishes
15 mm Thick two coat gauged lime plaster to:-
E Horizontal soffits of suspended slab 2014 SM 240.00 483,360.00
Chipboard ceiling
F 12 mm thick chipboard ceiling lining fixed to and including 50
x 50 mm sawn cypress brandering at 600 mm centres both
652 SM 1,250.00 815,000.00
G
Extra over ditto for forming 600 x 600 mm access panel with
50 x 50 mm sawn celcured cypress framing including trimming
softwood brandering and chipboard lining
150 No. 1,250.00 187,500.00
H 100 x 25 mm wrot cypress moulded Cornice, plugged 3214 LM 150.00 482,100.00
Carried to Collection Kshs 4,126,320.00
Bill No. 3
El. No. 13
Finishes
3/13/2
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
PAINTING AND DECORATING
Prepare and apply one coat aluminium primer on back of wood
before fixing on:-
A Surfaces not exceeding 100 mm girth 4586 LM 20.00 91,720.00
Prepare and apply three coats Plastic emulsion paint:-
Internally on:-
B Sides of walls 5478 SM 240.00 1,314,720.00
C Window reveals and jambs 896 LM 40.00 35,840.00
D Horizontal soffits of suspended slab 2513 SM 240.00 603,120.00
E Chipboard soffits 1523 SM 240.00 365,520.00
Prepare and apply three coats emulsion paint:-
Externally on:-
F Sides and soffits of beams 456 SM 240.00 109,440.00
G Window and door reveals 845 LM 40.00 33,800.00
Carried to Summary Kshs 2,554,160.00
Bill No. 3
El. No. 13
Finishes
3/13/3
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
COLLECTION
Page No. 3/13/1 2,979,060.00
Page No. 3/13/2 4,126,320.00
Page No. 3/13/3 2,554,160.00
TOTAL AMOUNT OF ELEMENT NO. 13
FINISHES
Carried to Summary of Bill No. 3 Kshs 9,659,540.00
Bill No. 3
El. No. 13
Finishes
3/13/4
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
BILL NO. 3
TYPICAL FLOORS (1st 2nd 3rd & 4th FLOORS)
SUMMARY
ELEMENT NO. PAGE NO.
8. REINFORCED CONCRETE SUPERSTRUCTURE 3/8/1 20,559,210.00
9. WALLING 3/9/1 7,695,000.00
10. ROOFING 3/10/1 2,549,268.00
11. WINDOWS 3/11/3 1,954,949.00
12. DOORS 3/12/5 13,310,812.00
13. FINISHES 5/13/4 9,659,540.00
TOTAL AMOUNT OF BILL NO. 3
MAIN HOUSE
CARRIED TO MAIN SUMMARY KSHS 55,728,779.00
3/S/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
BILL NO. 3
MAIN HOUSE
SUMMARY
ELEMENT NO. PAGE NO.
DITTO 5 SIMILAR BLOCKS
1. GROUND FLOOR 3/2/1 294,202,338.00
2. TYPICAL FLOORS 3/3/1 334,372,674.00
TOTAL AMOUNT OF BILL NO. 3
MAIN HOUSE
CARRIED TO MAIN SUMMARY KSHS 628,575,012.00
3/S/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
BILL NO.5
PRIME COST AND PROVISIONAL SUMS
ELECTRICAL INSTALLATION
A Provide the sum of Kenya shillings three million five hundred
thousands (Kshs.3,500,000/-) only for Electrical installation
Item 3,500,000.00
PLUMBING AND DRAINAGE
B Provide the sum of Kenya shillings four million (4,000,000/-)
only for Plumbing and internal drainage including septic tank
Item 4,000,000.00
CProvide the sum of Kenya shillings three million (3,000,000/-)
only for fittingsItem 3,000,000.00
DProvide the sum of Kenya shillings five million (5,000,000/-)
only for underground water tank and swimming poolItem 5,000,000.00
EProvide the sum of Kenya shillings three million (3000,000/-)
only for perimeter walling gate houseItem 3,000,000.00
PROVISIONAL SUMS
CONTINGENCY
FAllow the provisional sum of Kenya shillings five million
(Kshs.5,000,000/-) only for contingenciesItem 5,000,000.00
TOTAL AMOUNT OF BILL NO. 4
EXTERNAL WORKS
CARRIED TO MAIN SUMMARY Kshs 23,500,000.00
Bill No. 5
P C & Provisional sums
5/1
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008
No Description Qty Unit Rate
Kshs.
Amount
Kshs.
MAIN SUMMARY
BILL PAGE NO.
1. GENERAL CONDITIONS AND PRELIMINARIES 1/25 100,000.00
2. PREAMBLES TO TRADE 2/41
3. MAIN HOUSE 3/S/1 628,575,012.00
5. PRIME COST AND PROVISIONAL SUMS 5/2 23,500,000.00
TOTAL CARRIED OUT TO FORM OF TENDER KSHS. 652,175,012.00
CONTRACTOR'S SIGNATURE …………………………
NAME ………………………………………………………
ADDRESS …………………………………………………
DATE …………………………………………………….
WITNESS SIGNATURE …………………………………..
NAME ……………………………………………………..
ADDRESS ………………………………………………….
DATE …………………………………………………….
M/S1
PROPOSED DEVELOPMENT FOR APPARTMENTS
ON
PLOT NO. 209/20160 AT PARKROAD IN NGARA
Proposed appartments
at ngara MUTINDA SAMUEL MBITHI B76/0504/2008