ramin_shamshiri_risk_analysis_exam2.pdf

Upload: raminshamshiri

Post on 14-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    1/8

    Page 1 of8

    Ramin Shamshiri EMM5622, EXAM II

    EMM5622, RISK ANALYSIS IN ENGINEERING

    EXAM II

    Ramin Shamshiri

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    2/8

    Page 2 of8

    Ramin Shamshiri EMM5622, EXAM II

    Question 1

    A project schedule network has two paths of tasks needed to compute the total time to complete the project.

    They are either or as shown by the following time functions

    Compute the probability of ( ) by calculating the reliability index () using

    a. First-order reliability methodb. Advanced second-moment method

    The noncorrelated random variables are assumed to have the following probabilistic characteristics:

    Random Variable Mean Value Coefficient of Variation Distribution Type

    1 0.25 Normal

    5 0. 50 Normal 4 0.05 Normal 3 0.20 Normal 10 0.25 NormalSolution a:

    () () () () () Coefficient of Variation:

    Also ;

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    3/8

    Page 3 of8

    Ramin Shamshiri EMM5622, EXAM II

    It can be seen than

    Random Variable MeanValue

    Coefficient of Variation Standard Deviation 1 0.25 0.25 5 0. 50 2.5 4 0.05 0.2 3 0.20 0.6 10 0.25 2.5

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    4/8

    Page 4 of8

    Ramin Shamshiri EMM5622, EXAM II

    Solution b:

    ()

    Solving yields Solving yields

    Random

    Variable

    Mean

    Value

    Coefficient of

    Variation

    Standard

    Deviation

    Directional Cosines

    for T1Directional Cosines

    for T2

    1 0.25 0.25 0.09919

    5 0. 50 2.5 0.697139 4 0.05 0.2 0.079352 3 0.20 0.6 0.167313 10 0.25 2.5 0.9919 0.697139 () ()

    (

    )

    () () () 5.951394

    ()

    (

    )

    () () () () 5.019404

    It can be seen than

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    5/8

    Page 5 of8

    Ramin Shamshiri EMM5622, EXAM II

    Question 2

    Describe four engineering systems that can be modeled using the black-box method. What are the inputs

    and outputs for each system?

    Solution:

    A schematic of the black-box system model is shown in the above figure. A structural engineer mightobserve the deflection of a bridge as an output of a input such as load at the middle of its span. By varyingthe intensity of the load, the deflection chances, hence by producing a relationship such as y=f(x) where x isan input variable, y is an input variable and f is a function that relates input to output.

    Example 1: Probable maximum loadInput: Meteorological and Hydrological conditionsOutput: Flood runoffSystem: River Catchment Basin

    Example 2: Greenhouse Environmental Control

    Input: Heating and cooling loadSystem: Relevant actuators

    Output: Environment temperature and relative humidity

    Example 3: DC motor speed control

    Input: Variable voltage to the systemOutput: Speed of the motor shaft in rpmSystem: DC motor

    Example 4: VehicleInput: Amount of gas provided to the engine

    Output: Speed or performance of the vehicleSystem: Engine and other components

    SYSTEM

    Input X Output Y

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    6/8

    Page 6 of8

    Ramin Shamshiri EMM5622, EXAM II

    Question 3

    An engineer inspects a piece of equipment and estimates the probability of the equipment running at peak

    efficiency to be 80%. She/he then receives a report that the operating temperature of the machine has

    exceeded an 80C critical level. Past records of operating performance suggest that the probability of

    exceeding the 80C temperature when the machine is working at peak efficiency is 0.4. Also, the probability

    of the temperature being exceeded if the machine is not working at peak efficiency is 0.85.

    a. Revise the engineers initial probability estimate based on this additional information from pastrecords

    b. Draw a probability tree for this situationSolution a:

    Event A: Exceeding 80CEvent B: Running at peak efficiency

    => => Posterior probability of variables B after variable () has occurred

    Total=

    Total=

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    7/8

    Page 7 of8

    Ramin Shamshiri EMM5622, EXAM II

    Solution b:

  • 7/30/2019 Ramin_Shamshiri_Risk_Analysis_Exam2.pdf

    8/8

    Page 8 of8

    Ramin Shamshiri EMM5622, EXAM II

    Question 4

    Using the data of example 4.21 as provided in Table 4.23 (from the textbook), and assuming five identical

    components connected in series, compute , and function for a system in series. Thecomponent hazard function is given by the following equation:

    Solution: