raising steam from a cold condition
TRANSCRIPT
-
7/27/2019 Raising Steam From a Cold Condition
1/3
Name: Patrick Edwards
Raising steam from a cold condition
When commencing the start- up operation for boilers under condition
the following observations must be made;
If the boiler was taken off line and inspected or repaired were
done tools must be replaced, examine all pipe lines to ensure
that work that was done on then were completed and ensuring
that all fittings were done and properly fitted.
Fit lower manhole cover
Check that the blow down valve is clear.
Check internal fittings if they are correct.
Remove all blanks from the pipe lines are removed and other
area that were blocked off.
Fill the boiler 1 quarter way using warm water if possible, apply
first treatment with feed water through the top manhole;
ensuring that air vent is opened.
Set 1 fire at lowest rate possible; using smallest burner available,
by- passing air heater if fitted. Change furnaces over everytwenty minutes.
After about an hour start circulation by feed pump and blow
down valve connection (if no means of circulation is available
continue to apply low fire rate until boiler throughout the
furnace).
Continue to circulate for 4 hours if there is no method of natural
circulation is available to promote the removal small amount of
water, rising the temperature of the boiler at a rate of 6-7degrees c per hour.
At the end of this set away all furnaces, but still at the slow rate
but at this time close all air vents
Nipping up all bolts and all new joints.
-
7/27/2019 Raising Steam From a Cold Condition
2/3
Name: Patrick Edwards
Stop circulation and steam pressure can be slowly increased
during the 7-8 hours within 100kN/m square.
Test the water gauge. The boiler is ready for operation.
About 12-hours must be allowed for the completion of thisoperation if means of circulation is provided.
Raising steam under hot condition
The conditions that must be observed when raising steam under these
conditions which indicates low superheat conditions are as follows;
For higher steam temperatures it is placed above 2 rows of screen
tubes in a position known as interdeck position, and as many rows of
generation tubes to produce the required superheated temperature.The quality of steam produced is dependent up the width of the super
heater.
Superheated temperature with be below 455 degrees c, the final
superheated condition is dependent upon the presence of fitted
controlled dampers in the gas baffles to regulator the gas flow over the
superheater.
-
7/27/2019 Raising Steam From a Cold Condition
3/3
Name: Patrick Edwards
Operation to follow after the burner as failed
In the initial condition if the burner fails to start after 10 second after
the failure as occurred via the spark or other method, initial igniter safety
shut off valves must be closed and failure problem corrected. If air flow is
maintained at purge rate then re-purge is not necessary. There must be at
least 1 minute lapse before retrial of the re-start process is attempted.
The continual re-start process without carrying out inspections and
checks is prohibited; each burners must be observed independently and any
loss of flame must result in the immediate closure of the shut off valve.