rain water horvesting
TRANSCRIPT
-
7/28/2019 Rain Water Horvesting
1/36
A PROJECT REPORT ON RAIN WATER HARVESTING
SynopsisWater in essential commodity but becoming scare now a day. The demand for water that too
portable water is increasing day by day to meet the water needs for even increasing population.
Surface water resource are utilized to the maximum extent and are very much depleted. Ground
water resources are also over exploited and have resulted in decline in ground water levels in the
most parts of the country. Bore wells are silting up, getting short of water or yielding polluted
water. In this content to meet the ever-increasing demand for water that too portable water, its
necessary to harvest rainwater, which falls on the terrace of the buildings. The water collected from
the terrace is of good quality and can be stored in sump tank either for direct use or can be diverted
to the existing bore well/ open well fort ground water recharge and storage. Keeping in this view, a
roof top rainwater harvesting system is designed for KSPCB Office building located at Bangalore.
For the present study of 28 years rainfall data ofBangalore town is used.
About 12 peoples work in the Karnataka state pollution control board office Bangalore.
The daily water requirement us estimated as 160lpcd. The water is mainly used for drinking and
flushing or cleaning toilets, gardening etc at present water needs are met by public water supply.
So to achieve self-dependency in water supply it is planned to harvest rainwater that falls on the
terrace of the building.
The total quantity of the rainwater that can be harvested annually from the building rooftop is
estimated and is found to be 2.07,900 liters. This quantity is enough to full fill the water designed
requirements for 145 days (nearly seven months), provided all the rainwater is harvested. But it is
not economically feasible and also not necessary taking into account various factors. Hence, a sump
is designed to store the rainwater originated from the buildings terse and its size is kept as 4m X
2.5mX 2m. it can store up to 20,000 liters of water. Since harvested rainwater is to be user mainly
for drinking purpose, a rapid sand filter is designed to improve the quality of rainwater the size of
the filter is kept as 1.25mX1.25mX1.5m. The total cost of the rainwater
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 1
-
7/28/2019 Rain Water Horvesting
2/36
A PROJECT REPORT ON RAIN WATER HARVESTING
Harvesting system is estimated and is equal to Rs. 50,000.00. The cost of the sump tank works out
to be Rs. 40, 600.00 and is equal to 81.20% of the total cost of the entire the system.
The water harvested during rainy days can full fill the water needs for the entire rainy season.
Excess water (over flow water) from sump tank can be diverted to recharge the bore well. (Already
short of water) existing in the KSPCB office building premises. This water can be utilized to meet the
water needs during the other seasons of the years.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 2
-
7/28/2019 Rain Water Horvesting
3/36
A PROJECT REPORT ON RAIN WATER HARVESTING
Contents
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 3
-
7/28/2019 Rain Water Horvesting
4/36
A PROJECT REPORT ON RAIN WATER HARVESTINGCONTENTS
CHAPTER 1 INTRODUCTION
1.1 GENERAL
1.1 RAINWATER HARVESTING TECHNIQUES1.2 ROOF TOP RAIN WATER HARVESTING1.3 NEEDS FOR RAIN WATER HARVESTING1.4 BENEFITS1.5 USES OF WATER1.6 SUITABILITY OF RAIN WATER1.7 STUDY AREACHAPTER 2 RAINWATER HARVESTING SYSTEM DISCRIPTION
3.1 ROOF TOP RAINWATER HARVESTING STRATEGY
3.2 COMPONENTS PARTS OF RRWH
3.3 TREATMENT OF STORED RAINWATER
3.4 COST
3.5 MANTENANCE TIPS FOR RRWH STRUCTURES
CHAPTER 3 DESIGN DETAILS
3.1 SIZING THE SYSTEM
3.2 SELECTION OF SYSTEM
3.3 PLACEMENT OF SYSTEM
3.4 DESIGN OF WATER CONVEYANCE SYSTEM
3.5 FILTER DESIGN
3.6 SELECTION OF SUITABLE LIFTING DEVICE
CHAPTER 4 DESIGN AND ESTIMATES
CONCLUSION
DRAWINGS
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 4
-
7/28/2019 Rain Water Horvesting
5/36
A PROJECT REPORT ON RAIN WATER HARVESTING
CHAPTER 1
INTRODUCTION
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 5
-
7/28/2019 Rain Water Horvesting
6/36
A PROJECT REPORT ON RAIN WATER HARVESTING
1 . INTRODUCTION
1.1GENERALThe rapid pace of the development and the increase in the population has led to the exploitation
of water resources, resulting in the over use of the surface supplies and over exploitation of ground
water.
Dependency on ground water to meet the needs of the domestic and industrial sectors resulted in
loweringof ground water levels. As a result, drying up of wells and bore well are witnessed in many
areas. There any further indiscriminate use of ground water should not take place. Also bore wells
are yielding polluted in many areas. As the ground water levels has depleted to an alarmingly
considerable levels, the problem of fluoride menace started showing its furious and venomous
effects on the health of people.
According to the UNO report, by the year 2050, the world wide availability of fresh water will
have decreased by a third as a result of global warming, population growth and west full habits. The
natural under ground aquifers will be at all time low levels. Scarcity of fresh water will become the
limiting factor for healthy livable communities using water conservation techniques like roof top
rainwater harvesting system helps reduce the negative impact on our water supply keeping our
cities and towns vibrant and healthy.
In this content it is very much essential to harvest rainwater to meet the fresh water demand of
increasing population. The rainwater collected from the roof top is of good quality and can be
stored in tank, sump either for direct use are can be diverted to the existing open well, bore well for
ground water recharge and storage.
1.2RAINWATER HARVESTING TECHNIQUESHarvesting rainwater is very simple when it rains collect this water without allowing it to go as
runoff. These are various techniques to do it
Broadly rainwater can be harvested for two purposes.
Stored for ready use in containers above or below ground level (sump). Recharge into the ground water for with drawl later
(Ground water recharge).
As indicated above rainwater falling on the terrace collected and stored in storage tank and for
direct use or diverted into a well for groundwater recharge. Rainfall over the open the spaces
around the building may also be a diverted for recharge purpose.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 6
-
7/28/2019 Rain Water Horvesting
7/36
A PROJECT REPORT ON RAIN WATER HARVESTING
1.5 BENEFITS.
Provides self sufficiency to water supply Provides high quality water, soft and low in minerals Improves the quality of groundwater through dilution when recharged to groundwater It is expensive and reduces soil erosion in urban areas Rooftop rainwater harvesting structures are easy to construct, operate and maintain. In areas with less rainfall, rainwater harvesting has been providing relief to people. Saves money. Avoid the costs associated with the purchasing water from the centralized
water system. Operating costs are lower than the cost of purchasing water from the
centralized water system.
Saves energy. By reducing water use, energy demands to pump water from the watertreatment plant to the service area are reduced.
Saves water. Reduce the demand on the scare surface and water sources. Treated water is an expensive resource and so using free rainwater instead wherever
possible makes sound ecological sense.
1.6USES OF RAINWATER
Gardening, car washing and domestic non-portable purposes like washing cloths and dishes,bathing, toilets, swabbing the flour etc.
It is ideal for washing cloths because rainwater is soft. For water intensive tasks such as dust control, cleaning processes during manufacture,washings vehicles and other specialized cleaning processes such as printed circuit board
manufacture and in agriculture and animal husbandry where farm yards and animal stalls
must be regularly hosed down.
In large offices and public buildings, rainwater can be used for flushing toilets and urinalsand for cleaning.
For all purposes including portable purpose i.e. drinking and cooking but only after filteringand boiling the water.
1.7SUTABILITY OF SYSTEM Ideally rainwater harvesting is for any person planning to build a house or who is in the
process of building a house on an independent plot.
Persons with built houses can also harvest rainwater by retrofitting such a built house forrainwater harvesting.Persons in apartment can also harvest rainwater, but a community
approach is required in such a case.
Industries and factories can also harvest rainwater since large roof areas are usuallyavailable in such constructions.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 8
-
7/28/2019 Rain Water Horvesting
8/36
A PROJECT REPORT ON RAIN WATER HARVESTING
1.8STUDY AREAAvailability of rain water from roof tops is so high in the urban areas and it properly harvested
it will help in reducing the water scarcity problem of cities and towns commonly runoff water
from roof top are led off into the drains instead the outlets can be connected to a storage tank
and let into existing open wells/ bore wells /recharge pits. This method is less expensive and
very effective and if implemented in good spirit by each house housing society will help in
augmenting the ground water availability of the area.
Keeping this in view it is planned to design and install a roof top rainwater harvesting
structure to KSPCB building located in Bangalore. At present the water needs of the KSPCB
office is met by public water supply system. But it is in sufficient and not assured. So to achieve
self-dependency on water it is planned to harvest rainwater that falls on the terrace of the
building. For the present study, about 28 years annual rain fall existing data is used and areshown is table No.1.
TABLE No.1 ANNUAL RAIN FALL DATA
SI.
No.
YEAR ANNUAL RAIN
FALL IN mm
AVERAGE RAIN
FALL
1 1975 944.30 786.90
2 1976 778.70 648.90
3 1977 562.10 468.40
4 1978 1031.6 859.7
5 1979 751.90 626.6
6 1980 748.70 623.90
7 1981 991.90 826.6
8 1982 898.2 748.5
9 1983 1144.2 953.5
10 1984 693.60 578.0
11 1985 784.20 653.5
12 1986 814.60 678.8
13 1987 1130.0 941.70
14 1988 1347.6 1102.3
15 1989 1345.8 1102.1516 1990 1324.1 110.1.34
17 1991 701.50 584.60
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 9
-
7/28/2019 Rain Water Horvesting
9/36
A PROJECT REPORT ON RAIN WATER HARVESTING
18 1992 779.80 649.80
19 1993 632.20 526.80
20 1994 635.40 529.521 1995 3932.3 327.69
22 1996 751.30 626.10
23 1997 581.40 484.50
24 1998 1117.0 930.80
25 1999 925.20 771.00
26 2000 1038.6 865.70
27 2001 927.60 773.00
28 2002 738.20 615.10
Therefore,
Total amount of rainfall=32276.7mm
Total No. Of years =28 years
Therefore The average annual rainfall=834.88mm
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 10
-
7/28/2019 Rain Water Horvesting
10/36
A PROJECT REPORT ON RAIN WATER HARVESTING
CHAPTER-2RAIN WATER
HARVESTING SYSTEMDISCRIPTION
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 11
-
7/28/2019 Rain Water Horvesting
11/36
A PROJECT REPORT ON RAIN WATER HARVESTING
3.RAIN WATER HARVESTING SYSTEM DISCRIPTION3.1 RRWH STRATEGY
Collect water from the roof top Draw it down from pipes Filter the water and than Store in a sump or tank for later use
OR
Led the water into a well to increase ground water content
OR
Charge the ground water through a soak pit
The systems are simple to install in new buildings and need only minimum maintenance by the
user.
3.2 COMPONENT PARTS OF RRWH1. Down water pipes.
Pipes should be designed well
1. 90mm dia PVC pipes resistant to ultra violet (UV) raysappear to be the best as down waterpipes.
2. 3-4 down water pipes seems sufficient 90-110sq m (1000-1200 sq.ft approximately) roofarea.
3. A grill or mesh (Nahani trap or floor trap) has to be fixed at the entrance (inlets) of the downwater pipe in the terrace to arrest the large particles such as papers, leaves etc.
4. Sloping roof should have a gutter of PVC (half cut PVC pipes) or zinc or mild steel fitted alongthe sloping sides to collect water and channel it into the down water pipe system. Install
continuous leaf screen made of inches were mesh in a metal frame above the gutters to
prevent debris from entering the system.
5. Ground level tank occupy space and should not hinder moment or appear unsightly.6. Below the ground sump is a good option. Because they do not abstract moment less costly
to build and are hidden from you.But always provide an outlet for excess collection of water from the storage system. Once
collected filtered rainwater needs to be stored in cool and dark condition to discourage growth of
algae and bacteria.
A concrete water tank buried under ground is ideal but sump may also be considering either in
stone or brick masonry. The sides and floor of the tank are coated with waterproof material. The
size of the tank depends on the amount of water to be collected and cost resistance. But usually its
size is determined for the maximum daily rainfall of the place obtained from the rainfall records.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 12
-
7/28/2019 Rain Water Horvesting
12/36
A PROJECT REPORT ON RAIN WATER HARVESTING
3.3 TREATMENT OF STORED WATERIt is common perception that water stored for long goes bad. Water needs three conditions to go
bad thus when air, sunlight and organic matters are present within it. But excluding organic matter
through filtration and by strong rainwater in a closed container without assess to sunlight and air,water will remain for along time.
TABLE 2.0
Recommended doses of bleaching powder of disinfecting water.
Storage
Capacity of
Tank
DOSAGE OF BLEACHING POWDER IN gms
FULL TANK TANK TANK TANK
5000 50 37.50 25.00 12.50
6000 60 45 30 15
7000 70 52.5 35 17.5
8000 80 60 40 20
9000 90 67.5 45 22.5
10000 100 75 50 25
3.4 COSTSA rain water harvesting system has higher initial cost than buying water from the central water
supplier but the payback period is less than 1-2 years cost up to 50% on water bill may be saved by
re using water the largest cost of the system is the storage tank.
But it should be remembered however that currently cost of centralized water sypply is heavily
subsidized and these cost are bound to go up subtsansly alternate source will no longer remain
cheap. There fore plan for the future since the rainwater is future proofed for costs.
BASIC COST INCLUDEPipes Rs. 15/- 30/- per running feet
Bends and elbows Rs. 20/- 75/-
Filter tanks Rs. 1500/- Ls
Storage system Rs. 2/- to 4/- per liter depending upon whether the tank is made up of ferrow
cement or masonry or R.C.C.
The construction cost (Excluding costs of storage system) can range from Rs. 25,000/- to Rs. 40,000/-
or more
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 13
-
7/28/2019 Rain Water Horvesting
13/36
A PROJECT REPORT ON RAIN WATER HARVESTING
3.5 MAINTANCE TIPS FOR RRWH STRUCTURES Keep the roof or terrace as clean as possible Do not store rusting iron, insecticides or detergents on the roof Remove algae from the roof tiles and asbestos sheets before the man soon Always keep surroundings of the tank clean and hygienic Provide the rain flush arrangement to drain off initial one or two rains Change the filter media or wash is every rainy season. Always provide for adequate overflow storage system for unexpectedly heavy rains. Dry the tank completely and clean from inside thoroughly before the man soon Cover all inlets and outlets pipes with closely knit nylon net or fine cloth to avoid entry of
insects, worms and mosquitoes
Leakage of cracks in the Ferro cement storage tank shall be immediately attended to bycement plastering. This will avoid major repairs due to the prorogation of cracks.
The filter material shall be washed thoroughly before replacing in the filter tank. Clean the in side of the (sump) cistern yearly. Minimize the amount of debris in the gutters
and keep leaver out of the filters. Clean gutters on a regular basis for maximum collection of
rainwater.
FILTERFilter the rainwater before storage
Filtering can be as basic as a floor trap placed before the water enters the down water pipeor pieces of sponge placed at the inlet of the down water pipe.
A PVC drum with gravel, sand and charcoal is a good filter before rain water is stored A PVC drum with sponge at the inlet and outlet is also a filter. A small filter tank can also be devised it has to be provided to filter small or minute dust
particles before diverting the rain water into the storage tank or open well or bore well a
slow sand filter(surface down flow type) can be designed for this purpose.
RAPID SAND FILTERIt consists of following three parts
1. Enclosure tank2. Base material3. Filter media of sand
ENCLOSURE TANKA water tight tank is constructed in either in stone masonry o r brick masonry. The sides and floor
are also coated with water proof material a filter tank of normal size of 2X2X26.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 14
-
7/28/2019 Rain Water Horvesting
14/36
A PROJECT REPORT ON RAIN WATER HARVESTING
BASE MATERIALThe base material used is jelly and it is placed at the bottom of the tank. It is laid in two layers.
The lower layer should be of bigger size jelly (40mm) and top most layer should be of small size jelly(20mm). The thickness of each layer is generally kept as 15 cm.
FILTER MEDIA OF SANDThe sand to be used for filter should be free from clay, vegetable matter, organic impurities etc. it
should also be uniform in nature and size. A layer of sand is placed above the jelly. The depth of
sand layer is generally kept as 15cms. The effective size of the sand varies from 0.2mm to 0.3mm.
The finer the sand is better will be the efficiency of filter regarding removal of bacteria but in that
case the outlet from filter is lowered.
The rate of filtration for a normal slow and sand filter varies from 100-200liters/hr/sqm of filter area.
The filtration process improves the biological, physical and chemical characteristic of rainwater.
Slow and filter is highly efficient in removing bacterial load from water (98-99%). It thus provides
safe drinking water at low recurrent cost. However, for complete removal of bacteria the
disinflation is essential.
It can remove the turbidity to the extent of about 50ppm.
A nylon mesh has to be provided in between the two layers (base material and filter media of
sand). The top of the filter chamber should be covered with 1M.S.cover.
The filter should be designed in such a way that there is no risk of contamination and minimum
chances of blockage.
STORAGE SYSTEMIt is ad visible to determine the storage system at the planning stage of the building itself.
A storage system may be a Roof level storage tank. (for multi storied buildings) Ground level drum or masonry tank. Under ground tank (sump) Partially bellow tank and partially above ground tank.
Proper location of storage system is very essential and is as follows:
Roof level tanks may need to be @ the rear of the house or on the sides, so that it is neitherobstructive nor visually offensive.
Ground level drums or tanks occupy space and should not hinder moment or appearunsightly.
Below the ground the sump is a good option because they do not obstruct movement, lesscostly to building to build and are hidden
But always provide an outlet for excess collection from the storage system.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 15
-
7/28/2019 Rain Water Horvesting
15/36
A PROJECT REPORT ON RAIN WATER HARVESTING
Once collected, filtered rainwater needs to be stored in cool and dark conditions to discourage
the growth of algae and bacteria. A concrete rainwater tank buried under ground is ideal. But sump
may also be constructed in stone or brick masonry. The side and floor of the tank are coated with
waterproof material. The size of the tank depends upon the amount of water to be collected and
cost restraints. But usually its size is determined for maximum daily rainfall of the place obtained
from the rainfall records.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 16
-
7/28/2019 Rain Water Horvesting
16/36
A PROJECT REPORT ON RAIN WATER HARVESTING
CHAPTER 3
Design Details
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 17
-
7/28/2019 Rain Water Horvesting
17/36
A PROJECT REPORT ON RAIN WATER HARVESTING
DESIGN DETAILSDesign the roof keeping in mind the rain water harvesting requirements. That means if the roof is
flat, slope the roof in the direction of the storage system or recharge well. Sloping roofs should have
adequate gutter and down spots to handle the entire rain water incident on it.
3.1 STEP -1 SIZING OF SYSTEMThe size of rainwater collecting system depends on the size of roof. The amount of rain falls
(yearly) and the water demands for the system.
Calculate the average annual rainfall for the area using the data obtained from the rain gauge
station of the area.
Catchments area of roof = (width X length) of building
Rain water that can be harvested annually =C area of roof X
Annual rains fall.
Where c = runoff co-efficient for the roof top = 0.5.
To find how much rainwater will be collected, it is a common practice to assume a collecting
efficiency of 80% - 90%. But, a better system of calculation uses reliability of rainfall as an indicator.
3.2 STEP-2 SELECTION OF THE CLISTERN
The size of the cistern depends on the amount of rainwater to be collected and cost restraints.
Choose a cistern that fits the needs of water harvesting system. All cisterns should be of water tight,
durable and have a clean, smooth interior. The cover needs to be tight fitting to prevent
evaporation. It is best to place the cistern out of direct sun light to prevent algae and bacterial
growth, which can clog the system. Various types of cisterns can be used for storing rainwater and
are given in Table 3
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 18
-
7/28/2019 Rain Water Horvesting
18/36
A PROJECT REPORT ON RAIN WATER HARVESTING
TABLE 3
CISTERN TYPE ADVANTAGES DIS-ADVANTAGES
Fiber glass type Prevents algae growth and
evaporation, rust resistant,
durable
Higher initial costs, degradable
costs, require exterior coatings.
polyethylene Various sizes, shapes alterable,
inexpensive, movable, durable
Can determine the rate of over
time if not treated foe U>R
radiation (prove to be corrosion
and dust)
Steel drums Available, durable, movable Prove to corrosion and rust
Concrete tank or Ferro cement,
stone
Durable, permanent Potential to crack difficulties to
maintain
SUMP DESIGNConstruction is a common building practice. Collecting rainwater after filtration in the sump
would be most cost effective. The size of the sump is determined for maximum daily rainfall
obtained from the rainfall records of the place.
3.3 STEP-3 PLACEMENT OF THE CISTERNPlace a cistern at a high point on the plot and elevate approximately 3 to 4 feet on s sturdy, load
bearing foundation or structure. Above ground cisterns are less expensive than a below ground
cistern and easier to maintain. Storing water below ground has aesthetic appeal while keeping the
water out of the sun.
3.4 STEP-4 DESIGN IF WATER CONVEYANCE SYSTEM
If the roof is flat, slope the roof in the direction of the sump. Pitched roofs should be provided
with adequate gutters and down spouts to handle the entire rainwater incident on it. Install
continuous leaf screens made of inch wide mesh in a metal frame, above the gutters to preventdebris from entering the system. Down water pipes should preferably be HDPE/PVC resistant to
ultra-violet rays. The national building code says that if the intensity of rain in the place is 50mm per
hour then one 75mm down pipe will serve a 40sqmtr. Roof area and one 100mm down pipe will
serve as 85sqmtr. Roof area. Usually two 100mmdia pipes are good enough for a 100 sq mtr. Roof
area.
DEPARTMET OF CIVIL ENGINEERING GAPT. BANGALORE 19
-
7/28/2019 Rain Water Horvesting
19/36
A PROJECT REPORT ON RAIN WATER HARVESTING
Inter connect the rain water pipes (down water pipes) is there exists more than one. To convey
water from filter to sump provide a 110mm dia PVC pipe below ground.
3.5 STEP-5 FILTER DESIGNA rapid sand filter is to be provided to filter small and minute dust particles before diverting the
rainwater into the sump. The size of the filter tank is determined for the maximum intensity of
rainfall obtained from the rainfall records of the place. The filter media used is sand and its effective
size varies from 0.35mm to 0.6mm. The rate of normal rapid sand filter varies from 3000-6000 liters
per hour sq m of filter area.
Rain water discharge rate = intensity if rain fall X roof area
Area of filter tank required
Determine the dimensions of the filter chamber in terms of length and breadth. Provide
suitable depth taking into consideration amount of free board to be required and profile of
base material to be adopted.
3.6 STEP-6 SELECTION OF SUITABLE WATER LIFTING DEVICEProvide a proper sump to lift water from the sump and supply it to the water supply tank
or line for the distribution.
Surplus spillover water from the sump may be directed to the existing open or bore well.
In the absence of sump or open well or bore well the rainwater may be re-charged into
the ground through percolation.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 20
-
7/28/2019 Rain Water Horvesting
20/36
A POJECT REPORT ON RAIN WATER HARVESTING
CHAPTER 4Design and Estimates
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 21
-
7/28/2019 Rain Water Horvesting
21/36
A PROJECT REPORT ON RAIN WATER HARVESTINGDESIGN AND ESTIMATE OF THE SYSTEM4.1 CALCULATION OF RAIN WATER QUANTITY
The total quantity of rainwater that can be harvested annually from the rooftop of the existing
building located in the KSPCB premises is estimated .to estimate the rainwater quantity, the
available 28 years rainfall data is used.
The average annual rainfall
= 32276.7/28
=834.88mm
The roof area of the building is measured and the total roof area= 327.62sq.m. The rain water
quantity is estimated for the reliable annual rain fall and its value is generally taken as 80% average
annual rain fall (AAR).
Reliable annual rain fall = 80% of AAR
= 80/100x834.88
= 667.90mm
=668mtrs. Or The total quantity of rainfall water that can be harvested annually=C x roof area
X Reliable annual rainfall
Where,
C =runoff co-efficient for roof catchments and its value is 0.95 for R.C.C. roof
The total quantity if rain water that can be harvested annually = C x roof area x reliable
annual rain fall=0.95x327.62x0.668
= 0.95 =207.90cm
=2, 07,900liters.
WATER DEMAND
For drinking purposes = 05 liters
For washing faces, hands etc = 10 liters
For cleaning and flushing toilets = 25 liters
For gardening purpose = 35 liters
For other use = 05 liters
Total = 80 liters
About 120members work in KPSCB Office Daily.
Water demand per day = 80 X 12 = 960lpd
No. of days that can be utilized = 207900/960 = 216.56
says as 215 days (7 months)
If all rain water is harvested that water can be used for 215 days but it is not economically feasible
and not practicable due to various factors. Hence sump tank is designed to accommodate for
maximum daily rainfall.
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 22
-
7/28/2019 Rain Water Horvesting
22/36
A PROJECT REPORT ON RAIN WATER HARVESTING
DESIGN OF SUMP The capacity of the sump should be such that it should accommodatemaximum daily rainfall. The maximum daily rainfall is found to be 60mm/day from rainfall records.
Therefore,
Capacity of sump = maximum daily rainfall X roof area= 60/1000 X 327.62
= 19.657 cum
Say as 20 cum
Or 20,000 liters (1 cum = 1000 liters)
Therefore,
Tank capacity = 20.00 cum
Area of sump = Sump tank capacity
depth of sump tank = 20.00/2.00 = 10.00 sq.m
keep the depth of the sump tank as 2.0 m
Length of sump is kept as 4m.
Therefore, the width of the sump tank = c/s area length
Width of sump tank = 10/4
=2.5cm.
The size of the tank is 4m X 2.5m X 2m.
The details of the sump tank are shown in figure 2. The sump tank is provided with a man hole of
size 600mmX600mm with a cover for inspection and maintenance purposes. The excess water
(overflow water) from the sump tank is diverted to bore well for recharge purposes.
DESIGN OF FILTERThe size of the filter is determined bases on the maximum intensity of rainfall and infiltration rate of
sand medium used. The max intensity of rainfall from rainfall records is found to be 30mm/hour the
filter designed is rapid sand filter, the effective 6000 liters/hrs/sq.m of the filter area. The higher
value (6000 liter/hrs/sq.m) is considered for the design.
The maximum intensity of rainfall = 30mm/hr
Therefore, Max. Runoff from rooftop = Max.intensity of rain fall x roof area x 0.95
= 30/1000 x 327.62 x 0.95
= 9.34 cum/hrOr 9340 liters / hr
Area of filter tank required = Runoff/infiltration rate of sand
= 9340/6000
A = 1.56 sq.m
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 23
-
7/28/2019 Rain Water Horvesting
23/36
A PROJECT REPORT ON RAIN WATER HARVESTING
ROOF TOP RAIN WATER HARVESTINGIt is the principle of collecting & storing the rainwater,the which falls on the terrace of the house or
building .the water collected from the terrace is of the good quality & can be stored in tanks or
sumps either for direct use or can be diverted to the existing borewell or open well for ground water
recharge and storage
There are five components to a rain water harvesting system.the water is collected on the rooftop
and transported by gutter and down water pipes through a filter to a sump where the water is
stored.the stored water is lifted using a proper pump and supplied to meet the various needs.it is
possible to collect 10000lit of rain water of a typical roof of 100m2,for ever 100mm rain fall.
NEED FOR ROOFTOP RAIN WATER HARVESTING
TO MEET EVER INCREASING DEMAND FOR WATER. TO DEVELOP ECOLOGICAL AND FINICIAL SENSE NOT TO WASTE TO PURE NATURAL
RESOURSES AVAILABLE IN LARGE QUANTITY IN ONES ROOF.
TO ENCOURAGE WATER CONSERVESTION AND SELF-DEPENDNESS. TO AVOID PURCHASE OF WATER FROM TANKERS WHICH IS UNRELIABLE IN QUALITY AND IS
ALSO EXPANSIVE.
TO AVOID FLOODING OF ROADS.
DEPARTMENT OF CIVIL ENGINEERING GAPT . BANGALORE 7
RAINWATER
ROOF TOPHARVESTING
DIRECTSTORAGE
SURPLUSWATER
OPEN SOACEHARVESTING
GROUNDWATER
RECHARGE
-
7/28/2019 Rain Water Horvesting
24/36
A PROJECT REPORT ON RAINWATER HARVESTING
Therefore length and breath =1.25*1.25
Provide the depth of the filter as 1.5m
Therefore the recommened size of the filter is 1.25*1.25*1.25*1.50m
Depth of sand =20cm
Depth of 20mm jelly =20cm
Depth of 40mm jelly =25cm
Free board =80cm
The location of sump tank and the filter tank alone with pipe n/w are shown in below..
Fig 1 TABLE 1
ESTIMATION FOR SUMP TANK
SL NO PARTICULAR NO LENGTH BREATH DEPTH QUANTITY
1
2
3
4
5
6
Earthwork
excavation
Cc bed for
foundation
sump
BBM for
superstructure
a)long wall
b)short wall
plastering
for sump
tank
a)long wall
b)short wall
Rcc slab tocover sump
tant @ top
Deducation
to man hole
MS STEEL
cover plate
1
1
2
2
2
2
1
1
1
6.80
6.80
6.30
3.90
6.00
4.20
6.60
0.60
LS
5.00
5.00
0.30
0.30
_
_
4.50
0.60
_
2.15
0.15
2.00
2.00
2.00
2.00
0.10
0.10
_
73.10cum
5.10cum
7.56
4.68
12.24cum
24.00
16.80
40.80sqm
2.97
0.04
2.93cum
DEPARTMENT OF CIVIL ENGINEERING GAPT. BANGALORE 24
-
7/28/2019 Rain Water Horvesting
25/36
A PROJECT REPORT ON RAIN WATER HARVESTING
TABLE 2 ESTMATION FOR PIPE LINE
SL NO PARTICULARS UNIT QUALITY RATE
RS
PS
AMOUNT
RS
PS
1
2
3
PROVINDING
AND FIXING
90mm dia PVC
PIPE
HORIZONTAL
VERTICAL
EARTHWORK
EXCAVATION
AND
REFILLING THE
TRENCH
PROVIDING
AND LAYING
110mm dia
PIPES BELOW
GL
Rm
Rm
Rm
Rm
55.622
3.4
1.2
1.2
50.92
50.92
75
95
2503
153
2656
54
114
2824
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE 25
-
7/28/2019 Rain Water Horvesting
26/36
A PROJECT REPORT ON RAIN WATER HARVESTING
TABLE-3 ABSTRACT ESTIMATION FOR SUMP
SL NO PARTICULARS UNIT QUALITY RATE AMOUNT
1
2
3
4
5
6
EARTHWORK
EXCAVATION
FOR SUMP
CCB FOR
FOUNDATION
BBM FOR
SUPER
STRUTURE
RCC SLAB
OVER TANK
MILD STEEL
Plastering
both side
walls
5%WORK
CHARGE
FOR
ROUNDING
Cum
Cum
Cum
Cum
LS
Sqm
73.1
5.1
12.24
2.93
40.8
45
1506.34
1550
3063.61
75.5
TOTAL
GRAND
TOTAL
3289.5
7682.334
18972
8976.377
450
3080.4
42000.61
2100.031
44100.64
0.36
44101
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE 26
-
7/28/2019 Rain Water Horvesting
27/36
A PROJECT REPORT ON RAIN WATER HARVESTING
TABEL-4 ABSTRACT ESTIMATION FOR FILTER
SL NO PARTICULARS UNIT QUANTITY RATE AMOUNT1
2
3
4
BED CONCRET
FOR FILTER
BBM FOR SUPER
STRUCTURE
PLASTERING
FOR WALLS
MILD STEEL
COVER
ADD 5%WORK
CHARGE
ESTABLISHMENT
FOR ROUNDING
OFF
Cum
Cum
Sqm
--
0.27
1.13
7.5
Total
Grand total
1506.34
1550
75.55
LS
406.7118
1751.5
566.625
1002824.837
141.2418
2966.079
3.92136
2970
TABLE-5 TOTAL COST OF PROJECT
SLNO ITEM OF WORK COST
1
2
3
4
SUMP TANK
FILTER
PIPELINE
CHAINAGE PUMP OF 1HP
MOTOR
40600
2750
2824
5000
TOT COST 51174
SAY 52000
TOTAL COST OF PROJECT IS FIFTY TWO THOUSAND ONLY.
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE 27
-
7/28/2019 Rain Water Horvesting
28/36
A PROJECT REPORT ON RAIN WATER HARVESTING
Conclusion
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE 28
-
7/28/2019 Rain Water Horvesting
29/36
A PROJECT REPORT ON RAIN WATER HARVESTING
CONCLUSION
To achieve self sufficient in water supply roof top rain water harvesting structure is designed for
KPSCB office building,Bangalore. The water demand is estimated as 960lpd. The amount of water
that can be harvested annually is estimated as 207900 liters. A sump capacity is estimated as
20000liters. A filter having size 1.25*1.25*1.5m proposed to improve the quality of water. The total
cost of the system is estimated as Rs 5000000.
The cost of the sump tank is works out to be Rs 4060000 and is equal to the 81.20% of total
cost of the system. The water harvesting during rainy days can fulfill the water requirements for
entire rainy seasons.
The excess water (over flow water) form sump tank can be diverted to recharge the
borewell.(already short of water ) existing in the KPSCB office building premises. This water can be
utilized to meet water needs during other seasons of the year.
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE 29
-
7/28/2019 Rain Water Horvesting
30/36
A PROJECT REPORT ON RAIN WATER HARVESTING
Drawings
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE 30
-
7/28/2019 Rain Water Horvesting
31/36
A PROJECT REPORT ON RAIN WATER HARVESTING
TECHNICAL TOUR
INTRODUCTION TO KARANJA DAM
The karanja dam is an earten dam with zonal section type. The total height of the dam is 20.6m but
water storage capacity is upto 11mtr. But the live storage of water of dam is 4m and the total
catchment area at project is about 2025.28 sq kms ie,782 sq miles.
CANALS PROVIDED TO KARANJA DAM
canal is constructed to convey water from dam either for irrigation or water supply purpose. But in a
karanja dam there are two canal are constructed one is right bank canal,both canals are of fully
cutting. The discharge capacity of left canal is 16.935cumecs,and the length of the left canal is 131
kms the ratio for side slope of canal is 1:1 for the both the canal and canal lining is done by shah bad
flooring or cc bed.
The FLOORING main purpose of canal lining is to prevent seepage and to protect the bank from
erosion.
FORE SHORE LITE TO KARANJA DAM:
From the karanja reservoir the lift irrigation can be done,the jack well be located on right bank of the
karanja river away from 7km upstream side from the dam site.
The maximum discharge available on left canal 1.98 cumces the length of intake channel is 213.35
m or 700ft max discharge required from intake channel is 3.455 cum and rising mains are 4 nos
pressure pipes of 1m dia,having length about 1370m.
And the length of lift canal is 24kms there are 5nos of 200hp pumps sets are provided
including one stand by..
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE
-
7/28/2019 Rain Water Horvesting
32/36
A PROJECT REPORT ON RAIN WATER HARVESTING
TECHNICAL TOUR
SAILENT FEATURES OF KARANJA DAM AND ITS APPURENANT WORK
GENERAL
A. Name of the project :: karanja irrigation project.B. Location :: karanja a tributary river manjra which joins river
GODAVARI..
2)Village :: Byalhalli.
3)Taluka :: Bhalki
4)District :: Bidar
5)Co-ordinates :: a)latitude 7753
b)longitudinal 7719
C. Hydrology
1)total catchment area at site ::2025.28 sq kms
2)weighted annual rain fall dependability ::930mm
3)75% dependable net flow at project site ::271.54mt cum
4)proposed annual utilization ::252.49mt cum
d.Dam and reservoir.
1.Gross storage capacity :: 217.65 mt cum
2.Live storage capacity :: 207.65mt cum
3.Top of dam :: Rl 590.00m
4.MWL :: Rl 587.15m
5.FTL :: Rl 584.15m
6. MWL :: 577.84M
7. Lowest river bed level :: Rl 568.45m
8. Type of dam :: earthen dam with zonal section
9. Total length of dam :: 3480m
10. Top width of dam :: 4mt
11. Height of dam above deepest bed level :: 20.60m12. free board :: 5.85m
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE
A PROJECT REPORT ON RAIN WATER HARVESTING
-
7/28/2019 Rain Water Horvesting
33/36
sypnois
DEPARTMENT OF CIVIL ENGINEERING GAPT.BANGALORE 0
-
7/28/2019 Rain Water Horvesting
34/36
-
7/28/2019 Rain Water Horvesting
35/36
-
7/28/2019 Rain Water Horvesting
36/36