Rail Investment in the East Midlands
Spencer Gibbens, Route Enhancements Manager
Date 00.00.00 Presentation title to go here 2
East Midlands Trains Performance
• Improvement of over 10% in PPM since 2005/06
EMT PPM MAA
80%
82%
84%
86%
88%
90%
92%
94%
20
05
/06
20
06
/07
20
07
/08
20
08
/09
20
09
/10
20
10
/11
20
11
/12
PP
M M
AA
pe
rce
nta
ge
Ongoing investment – Nottingham Hub
£47m partnership
Nottingham Re-signalling / Lines Speed Improvement
• Completed by March 2014
• Remodelled layout for Nottingham
• Additional Platform
• Headline speed of 125mph
• Journey time reduction to Sheffield of 8 mins
• Journey time reduction to Nottingham 5 mins
Other enhancements
• Access for All
• NSIP
• Partnership schemes
• Freight
Continued growth in demand
• Significant growth in passengers by 2020:
–East Midlands to London = 27%
–Nottingham to Birmingham = 42%
–East Mids to East England = 36%
• Freight growth even higher, reaching 50% by 2015
• Need to meet this growth without compromising on performance
Pic here
Future investment
• Cleaner, quieter journeys
• Capacity for passenger andfreight growth
• Faster journeys
• Improved performance MAP BEING
UPDATED
Creating capacity, cutting carbon
Timescales
• September 2011: Initial Industry Plan published
• July 2012: Government publishes HLOS / SOFA
• January 2013: Strategic Business Plan published
• Summer 2013: Enabling works commence
• 2014: Main programme of work starts