rahinah ibrahim stanford university architect craig long kansas university engineer jorge fuentes...

58
RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN Stanford University Owner

Upload: austin-page

Post on 29-Dec-2015

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

RAHINAH IBRAHIMStanford UniversityArchitect

CRAIG LONGKansas UniversityEngineer

JORGE FUENTESStanford UniversityConstruction Manager

ROXANNE ZOLINStanford University

Owner

Page 2: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SACRAMENTO, CALIFORNIA, USA

Precipitation:Temperatures:

Seismic Zones Map Wind Speed Zones Map

Page 3: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN- Site Location Plan

Page 4: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

REDESIGN

Page 5: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

REDESIGN: AEC 1

Gym

Cafe

Perspective View

•Nominal cost for construction•Makes building very compact•Maintain no view for 4 nos Faculty rooms

Page 6: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

REDESIGN: AEC 2

Improving Indoor Quality•Increase Faculty rooms from 16 to 20.•Provide views to all Faculty rooms.•Faculty Lounge has view of river.

Improving Outdoor Quality•Additional landscape-integrated steps•Café on top of 2F floor slab protected from afternoon sun

Gym

Cafe

Perspective View

Page 7: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Auditorium Span

Pratt-Type Truss

• Openings for hallways and circulation

• Satisfies the architectural constraints

REDESIGN: AEC 2

Page 8: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Framing

Original Framing

•Complex Geometry

•Difficult Connections

•High Fabrication cost

REDESIGN: AEC 2

Page 9: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Framing

New Framing

•Simplified Geometry

•Simpler Connections

•Standardized Fabrication

$avings

REDESIGN: AEC 2

Page 10: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Redesign Alternatives Schedule Comparisons

Page 11: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Redesign Estimates

4278235

185250

4278235

159109

0

500000

1000000

1500000

2000000

2500000

3000000

3500000

4000000

4500000

Alternative 1 ($4.46M) Alternative 2 ($4.44M)

(in 2001 $US)

Changes

Original Cost

Page 12: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

General & Redesign Constructibility Issues & Alternatives

Limited access to site due to levy

Floodplain- best solution is to elevate structure

Page 13: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE

Page 14: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

TEAM DESIGN APPROACH

C- Build an Offshore Oil Rig

E- Design a Bridge

A- Design A Highrise

Building on piers to minimize hydraulic impact

Page 15: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: Concept

ROTATING SQUARES- for floor expansion

GOLDEN SECTION-for vertical expansion

Page 16: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN

SECTION

VIEW FROM BUILDING

Page 17: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN

1ST FLOOR PLAN

3RD FLOOR PLAN

2ND FLOOR PLAN

Administration

Faculty/Student Offices

Classrooms/Lab

Terrace

Restroom

Circulation

Page 18: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: AEC 1

•Live Loads Terrace, Interior Atrium – 100 psf Corridors, Computer Lab – 100 psf Auditorium, Classrooms & Offices – 50 psf Roof – 20 psf

•Dead Loads Cast-in-Place Concrete – 150 lb/ft3

Steel Construction – 60 psf Flooring, ceiling, lights – 15 psf HVAC – 5 psf Partitions – 20 psf Exterior Cladding – 30 psf

Structural Constraints – Gravity Loads

Page 19: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: AEC 1

• Seismic Constraints Moderate seismic activity; Zone 3

Occupancy category, I = 1.0

Sandy soil with subsurface rock

• Wind Constraints Design wind speed, V45 = 90 mph

Structural Constraints – Lateral Loads

Page 20: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

•Structural Piers

•Lower Level Structure

•Foundation Concerns

•COST

SQUARE BASE DESIGN: AEC 1

Impact of elevated structure

•Water corrosion

•Soil difficulty

•Additional lateral load

Flooded structure made complicated by...

Page 21: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: AEC 2

Structural system that defies gravity

Page 22: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Concept Due to Rotating Concept

Slender Roof Framing

Traditional Framing System

“Table Top” Stable Platform

SQUARE BASE DESIGN: AEC 2

Page 23: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: AEC 3

King-Post Truss

•Post Tension Concrete Beam 24” x 30”

•5000 psi Concrete

•Steel Tension Cords

Difficult Detailing

SQUARE BASE DESIGN: AEC 3

Page 24: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: AEC 4

North – South Truss

•Cantilever Gravity Resisting System

•Cantilever Lateral Resisting System

East - West Truss

•Decorative Element

•Completes the Square

External trusses to perform aesthetically and structurally

Page 25: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: AEC 5

Flexible open plan design

1ST FLOOR PLAN 3RD FLOOR PLAN 2ND FLOOR PLAN

Core Placement Study

Page 26: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Two-Joists with Elevated Floor

•Space for Building Services

•Required Additional Columns

Two-Way Slab System

Waffle Slab

•Column Free Environment

•More Complicated HVAC Routing

SQUARE BASE DESIGN: AEC 5

Page 27: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: AEC 6

Freeflowing interior spaces

Page 28: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Open Plan Structural Solutions

Option 2

•Steel/Concrete Composite System

•Shear Wall Service Core

Option 1

•Cast-in-Place Concrete Frame

•Shear Wall Service Core

SQUARE BASE DESIGN: AEC 6

Page 29: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Option 1

2nd Floor Plan

Column 1’x1’

Beam 12”x24”

3rd Floor Plan

Two-Way Slab

6”x6” Tube Brace

SQUARE BASE DESIGN: AEC 6

Page 30: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Option 2

3rd Floor Plan

Joist W16x26

W8x24

SQUARE BASE DESIGN: AEC 6

Roof Plan

¾” Dia. Cable

16” Open-Web Joist

Page 31: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Foundation System

Drilled Pier

2’-6” Diameter / 30’ Depth

Drilled Pier Array

1-6” Diameter typical

CIP Transition Piece to Shear Wall

SQUARE BASE DESIGN: AEC 6

Foundation Isometric

Page 32: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN- AEC 7

SECTION

Administration

Faculty/Student Offices

Classrooms/Lab

Terrace

Restroom

CirculationPreliminary Core Plan

Page 33: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: CM

CM ( slide)Comparison of Estimates (Totals, structural costs and

elevating elements costs- piers and floor + lift)Schedule length comparison (including phase milestones)Critical Construction IssuesConstruction alternativesConcrete vs Concrete/Steel CompositeEstimate and schedule

Page 34: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

SQUARE BASE DESIGN: CM

CM ( slide)Comparison of Estimates (Totals, structural costs and

elevating elements costs- piers and floor + lift)Schedule length comparison (including phase milestones)Critical Construction IssuesConstruction alternativesConcrete vs Concrete/Steel CompositeEstimate and schedule

Page 35: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Square Alternatives Schedule Comparisons

Page 36: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Square Alternatives Cost Breakdown

85474

687439

288361

85474

607950

217721

0

500000

1000000

1500000

2000000

2500000

3000000

3500000

4000000

Concrete Alternative ($3.70M) Steel/Concrete Alternative ($3.62M)

(in 2001 $US)

ElevatingStructureLandscaping

Electrical

Mechanical

Conveying

Int. Const.

Roofing

Exterior Closure

OtherSuperstructureSubstructures

Site Work

Page 37: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Square Design Constructibility Issues & Alternatives

Long span members

Constructing 1st level- before or after 2nd level

Page 38: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN

Page 39: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN- Concept

GOLDEN SECTION- for floor expansion- for vertical expansion

Page 40: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN- Plans

Administration

Faculty/Student Offices

Classrooms/Lab

Terrace

Restroom

Circulation

Page 41: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN- Section & Elevation

Lobby Atrium

Exposed Corridor

Balconies

Page 42: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN: AEC 1

More columns for structural stability

Page 43: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN- AEC 2

Core Placement Study

Fulfilling fire egress requirements

•Minimum distance between exits is 80ft.•Minimum egress width is 5’-6”.•Minimum 20ft atrium opening.•Minimum 3 exits at 2nd Floor, others 2 nos.•Sprinklered egress on all floors.

Page 44: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DOUBLE SQUARE DESIGN- AEC 2

Core Placement Study

Fulfilling fire egress requirements

•Minimum distance between exits is 80ft.•Minimum egress width is 5’-6”.•Minimum 20ft atrium opening.•Minimum 3 exits at 2nd Floor, others 2 nos.•Sprinklered egress on all floors.

Page 45: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Options 1

DOUBLE SQUARE DESIGN: AEC 2

Laterally Braced Frame

•4.5” Steel-Concrete Slab

•Columns W18x40 typ

External Bracing Conflicts

with Architect’s Vision

Composite Column Below Waterline

Page 46: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Options 2

DOUBLE SQUARE DESIGN: AEC 2

Cast-in-Place Frame

•10” Shear Wall

•12” x 12” Columns Typ.

Complex Framing Requirements

Conflict with CM Budget

10” Inclined Slab in Auditorium

Page 47: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Structural Options 3

DOUBLE SQUARE DESIGN: AEC 2

Composite Steel-Concrete

•SMRF at Exterior Frame

•Bracing Auditorium Framing

Page 48: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Double Square Alternatives Schedule Comparisons

Page 49: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Double Square Alternatives Cost Breakdown

66018

911701

167660

66018

753171

337352

74869

1029200

193608

0

500000

1000000

1500000

2000000

2500000

3000000

3500000

4000000

Concrete MRF Alternative ($3.83M)

All Steel Braced Frame Alternative($3.84M)

Steel MRF w/ Concrete CoreAlternative ($3.98M)

(in 2001 $US)

ElevatingStructureLandscaping

Electrical

Mechanical

Conveying

Int. Const.

Roofing

Exterior Closure

OtherSuperstructureSubstructures

Site Work

Page 50: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Double Square Contractibility Issues & Alternatives

Complex structure- more uncertainty, more riskHeight limit- 20’ on equipment

Page 51: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Comparison of Estimates to Budget

3892500

5500000

4463485

6306787

4437344

6269851

3703077

5232350

3624245

5120964

3826177

5406288

3837246

5421929

3977216

5619702

0

1000000

2000000

3000000

4000000

5000000

6000000

7000000

BUDGET Redesign 1 Redesign 2 Square 1 Square 2 DoubleSquare 1

DoubleSquare 2

DoubleSquare 3

2001 Cost ($US)

2015 [email protected]% ($US)

Page 52: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Site Layouts

accessaccess

TC

TC trailers

trailers

Mat’l laydown

Mat’l laydown

20’ Clearance

Page 53: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

EQUIPMENT SELECTION

Page 54: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

Construction Trade-off Analysis

Adv Disadv

Redesign Traditional const built on floodplainexpensive

Square Base Long-span beams

Double Square Complex-more uncertainty

Page 55: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

DECISION MATRIX

SQUARE BASE DESIGN•Strong concept and good interior plan.•The structural system is integral in the building aesthetic.•Looks complicated but can be build with current equipment and tools.

DOUBLE SQUARE DESIGN•Weaker concept with too much columns going to the ground.•Structural analysis is complicated and time consuming.•More foundation works and complex auditorium construction

DOUBLE SQUARE DESIGN•Most inhibited rooms have good external view.•Has more columns to pass building loads to the ground.•Has bigger staging area to work with.

SQUARE BASE DESIGN•Requires effort to work around the fire requirements.•Long huge spans to support building loads.•Requires precise sequencing of tasks during construction.

REDESIGNNeed to have less angular smaller rooms.•Auditorium causes less flexible 3rd Floor layout.•Most expensive among these three options.

REDESIGN•Better quality learning and working spaces.•Less complicated to framing system.•Conventional construction method.

PROS CONS

Page 56: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

RECOMMENDATIONS

We are recommending the Square Base Design for further development:

A- The quality of space and the overall design is good while building is able to satisfy all technical requirements.

E- The structural system is simple yet elegant and plays an integral part of the design.

C- Even though it looked complicated, it is actually cheaper and simpler to build.

Page 57: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

TEAM DYNAMICS

C- Build an Offshore Oil Rig

E- Design a Bridge

A- Design A Highrise2. SHIFT IN DESIGN APPROACH

1. DUAL BACKGROUND PROFESSIONALSArchitect is also Construction ManagerEngineer is also ArchitectConstruction Manager is also Engineer

3. HAVING GOOD RELATIONSHIP WITH THE OWNER

Page 58: RAHINAH IBRAHIM Stanford University Architect CRAIG LONG Kansas University Engineer JORGE FUENTES Stanford University Construction Manager ROXANNE ZOLIN

VALUABLE LESSONS

So far, we have learned:

A- It is better to start collaborating earlier in design.

E- Solutions only work through communication

C- Time management is very crucial.

Thank you

In Spring 2001:

A- Use IT tools more efficiently.

E- Be more assertive in communicating structural necessities

C- Managing time and scheduling teamwork.