Page 1: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

R2 LCO Review Outbrief

2011-09-01

Page 2: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Summary

• Thanks• Very impressed with:– Amount of work– Comprehensive architecture and artifacts– Knowledge of staff– Quality of presentations– Comprehensive demo of R1- well worth it!– Frankness and completeness of discussions– Logistics were excellent as usual- tx Paul!– Ability to stay on Schedule– Cell phone discipline

Page 3: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Report out rules of engagement

• We will add / delete / modify comments in our final report

• Would like to present entire out brief and then take questions

Page 4: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Good Stuff• CI architecture appears to be very well planned,

documented, and logical.• The work that CI has done to test the platform agent

on the target hardware was outstanding, and dramatically lowered risk.

• Prototypes were well planned, well executed, and of great value.

• Good that CI reached out to MBARI to benefit from their experience and lessons learned

Page 5: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are Release 2 LCO Review Entry Criteria Met?

1. Are Release 2 LCO artifacts provided and adequate?Artifact Set Content Provided Adequate

Management System Life Cycle PlanRisk RegisterElaboration Execution Plan

YesYesYes

YesNo – out of dateNo - Lacks tasks, schedule, resources

Requirements Use cases (mature)User workflows (candidate)System and subsystem requirements (candidate)

YesNoYes

Unknownn/aNone for UX; not yet mapped to use cases

Design Architecture Specification (candidate)Technology List (baselined)Prototype Reports

Yes

YesYes

Yes

YesYes

Implementation None

Deployment None

Page 6: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are Release 2 LCO Review Exit Criteria Met?

Page 7: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are the use cases understood by the stakeholders, and do they provide a complete

description of the release scope?

• To our knowledge, the Marine IOs, EPE, and the project scientists were not asked to review the applicable use cases

Page 8: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are the core user workflows understood and agreed to by the stakeholders?

• We do not know what the core workflows are• We do not know who the stakeholders are

Page 9: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are the candidate requirements understood by the stakeholders, and do they cover the critical

use cases? • Requirements have not yet been mapped to

use cases for Rel 2• We do not know which use cases are ‘critical’

Page 10: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are the critical risks identified, and have they been mitigated through exploratory prototypes?

• We saw evidence that prototypes were put in place to mitigate technical risks – good job

• The risk register was not updated to reflect this mitigation

• We did not see evidence of mitigation strategies for programmatic risks

Page 11: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are the candidate architectures viable as demonstrated through analysis and

prototyping? • Yes

Page 12: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Is the Elaboration phase execution plan credible?

• The Elaboration Plan appears difficult to utilize to manage the Elaboration Phase

• The Elaboration Plan was not complete– lacking schedule and tasking details

Page 13: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Actions from R1 Reviews – Findings, Recommendations, and Suggestions• Were items satisfactorily addressed from

Release 1 reviews?– Response to findings/recommendations was

discussed in the homework presentation. – Due to time constraints, supporting evidence was

not presented for all item resolutions

Page 14: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Are Release 2 LCO Review Exit Criteria Satisfactorily Met?

• Is this a viable User Interface strategy, team and approach? No– Concerned that one single interface cannot apply to

multiple audiences– Not clear that the correct people (e.g., at the marine IOs)

have been interviewed• Have all of the applicable user interfaces been

identified? No• Have these user interfaces been appropriately

characterized for this stage? No• Have R1 user interfaces been adequately proven to

support L2 start? No data to make the assessment

Page 15: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings – Use Cases

• There was no identified engagement of appropriate program groups (e.g., marine IOs, data working groups) in the Use Case validation process prior to the LCO. CI expected that consensus on the use cases would take place at the LCO. This consensus process should be a very detailed and concerted working group effort spanning weeks/months as opposed to a day or two.

• Holding this LCO review does not remove the need to engage the stakeholders to achieve consensus on Use Cases. • For example, there is no use case for Navy embargoed

data streams.

Page 16: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings – User Interface

• UX does not appear to be sufficiently planned or mature enough to meet goal of pixel-perfect GUIs by LCA for Release 2.

Page 17: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings - Schedule

• The IMS is not well understood by the team, thus affecting their ability to effectively plan. (Ex: some team members did not truly understand the scope for the release)

Page 18: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings - Management

• Spiral development methodology is being used to defer more difficult tasks to later releases .

• Inadequate staffing continues to be a critical risk to CI schedule.

• OL needs to provide leadership and support for system integration between the IOs.

Page 19: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings - Risks

• There appear to be significant R2 risks that need active mitigation efforts.

• The risk register is not current – It has not been updated as a result of recent

prototypes– It does not include the risk of having a 3-4X

increase in number of use cases in R2 vs R1

• Risks do not appear to be pro-actively managed (too many realized risks)

Page 20: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings - Risks, Cont.

• Schedule and Budget impacts as a result of pushing 40% of Release 1 into Release 2 have not been fully developed. This deferment activity should be entered into the risk register as it may have drastic impacts on the ability to deploy Release 2 in time to support the Marine IO deployment.

Page 21: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings - Technical

• Apparent lack of formal trade study process• There continues to be no decision on how

assets will be managed for OOI (SAF vs. CI)– OL should take lead in resolving this issue

Page 22: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Findings – Review Process• Overall, the presentations appeared to lack

quantitative backup data. (e.g., lack of staff loading and schedule detail; lack of risk metrics)

• There is a misunderstanding of the board’s role in representing the stakeholders at this and previous reviews; the board cannot function as a working group

• It appears that CI has treated each of their milestone reviews so far (R1 LCO, LCA, IOC; R2 LCO) as a progress reporting event rather than as a gate review.

Page 23: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations – User Community

• Continue to include Rel 1 early adopters as part of Rel 2 user community (and make sure we don’t break what is already there)

• There needs to be a formal mechanism for soliciting feedback from users

• Continue to reach out to outside organizations like MBARI, and expand the list of organizations consulted

Page 24: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations – Use Cases

• There appears to be a need for end-to-end threads that exercise the entire system as it will be used operationally.

Page 25: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations – Use Cases and Requirements

• Mapping of use cases to requirements should be accomplished during Inception rather than during Elaboration.

• A requirements verification matrix should be included in the artifacts at all reviews.

• Use case format should include a field for the associated requirements.

Page 26: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations - Schedule

• CI must know and present a critical path schedule to their entire team.

• Overall schedule risk should be re-assessed.

Page 27: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations - Management

• For issues involving cross-IO boundaries, OL needs to be pro-active and own and manage the issues.

• CI needs to quickly hire more systems engineers and developers.

• OL and CI need to jointly prioritize requirements and deliverables to pro-actively prepare for budget fluctuations.

• CI should assign a person, as a local representative, to both Marine IOs to support integration.

• Project Management support must be given to UX.

Page 28: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations - Risks• Risk 2329 should be promoted to the system level.• Reinstitute the formal risk management process.• Add a new risk for Release 1 maintenance

consuming Release 2 resources.• A new risk should be added for the ATBD schedule,

and promoted to the system level.• Mitigation approaches need to be identified and

implemented for risks to R2 LCA.

Page 29: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations – Review Process

• Review charge (LCO, LCA, etc.) should be well understood by all parties (board, development team, management team). In other words there was confusion as to what should be accomplished at the review.– Provide complete written charge four weeks prior

to the review

• PRR for Release n should precede LCO for Release n+1

Page 30: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Recommendations - Review Process

• Allocate more time for questions from the board

• Two weeks before review, provide evidence to review chair that all entry criteria are met; if not, review should not proceed

Page 31: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Stoplight ChartTechnology Area Technical Risk Assessment Management Assessment

UX Red (very few screens wireframed)

Red (no plan)

COI Green/Yellow (complexity) Green

CEI Green/Yellow (scalability risk)

Green

DM Green Yellow (status tracking, staffing)

S&A Green Yellow (under staffed)

Marine Integration, Sensor Sets, and Dataset Agents

Green Green

Architecture Green/Yellow (new technologies, will it scale?)

Green

CyberPoP Green Green

Page 32: R2 LCO Review Outbrief 2011-09-01. Summary Thanks Very impressed with: – Amount of work – Comprehensive architecture and artifacts – Knowledge of staff

Summary Conclusion

• Exit criteria for LCO were not met • Conduct delta LCO – specifics will be

provided in final board report– Includes: • Working review and finalization of use cases• Mapping of R2 requirements to use cases• UX plan and screens• Staffing and resource-loaded schedule with critical

path• Updated risk register with mitigation plans

• OOI board members are available to assist