36. (This problem is valued at 10 points). A project in Miami to develop a new baseball park has an actual cost in month 17 of $340,000, a planned cost of $480,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes. 37. (This problem is valued at 20 points). Use extra sheets as necessary. Crash Normal Activity Follows Time Cost Time Cost Manpower A -- 3 30 4 20 2 B -- 3 25 6 10 1 C A 2 50 2 50 2 D A 1 50 2 40 1 E B.,C 1 30 2 20 2 Complete the following (you will need extra paper) 1. Construct the AON and AOA diagrams and find and CLEARLY MARK the critical path. What is the cost for completing the project on the normal schedule? 2. Can activity D be delayed without affecting the completion of the project? If so, by how many days? 3. “CRASH” the normal project schedule by two days. 4. Draw a load diagram or other tool to make a suggestion how you would level manpower demand. (DO NOT PLACE YOUR SOLUTION HERE, BUT USE THE ANSWER SHEET BELOW AND EXTRA SHEETS AS NEEDED. PUT YOUR NAME ON ALL SHEETS).

Upload: varat-koirala

Post on 11-Nov-2015

14 views

Category:

Documents


8 download

DESCRIPTION

dsfdsf dsfd fdsds

TRANSCRIPT

36. (This problem is valued at 10 points). A project in Miami to develop a new baseball park has an actual cost in month 17 of $340,000, a planned cost of $480,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.

37. (This problem is valued at 20 points). Use extra sheets as necessary.

Crash Normal Activity Follows Time Cost Time Cost ManpowerA--3304202B--3256101CA2502502DA1502401EB.,C1302202

Complete the following (you will need extra paper)1. Construct the AON and AOA diagrams and find and CLEARLY MARK the critical path. What is the cost for completing the project on the normal schedule?2. Can activity D be delayed without affecting the completion of the project? If so, by how many days?3. CRASH the normal project schedule by two days.4. Draw a load diagram or other tool to make a suggestion how you would level manpower demand. (DO NOT PLACE YOUR SOLUTION HERE, BUT USE THE ANSWER SHEET BELOW AND EXTRA SHEETS AS NEEDED. PUT YOUR NAME ON ALL SHEETS).