quest ccs project - ieaghg.org pdfs... · quest ccs project pccc2 conference . bergen, norway ....

26
Heavy Oil Shell Canada Restricted QUEST CCS PROJECT PCCC2 Conference Bergen, Norway Sept 19, 2013 Use this area for cover image (height 6.5cm, width 8cm) Steve Peplinski – Quest Engineering Manager

Upload: dinhbao

Post on 24-Aug-2018

239 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

QUEST CCS PROJECT

PCCC2 Conference Bergen, Norway

Sept 19, 2013 Use this area for cover image

(height 6.5cm, width 8cm)

Steve Peplinski – Quest Engineering Manager

Page 2: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Location

September 19, 2013 2 PCCC2 Conference

Alberta

Canada

Quest Fort Saskatchewan

Fort McMurray

Edmonton

Calgary

Page 3: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Introduction - The Athabasca Oil Sands Project

September 19, 2013, 3 PCCC2 Conference

Peace River

Calgary

Edmonton

Corridor Pipeline

Fort McMurray

Muskeg River Mine

Ore

Scotford Upgrader

Bitumen to Synthetic cru(255,000 bpd)

Scotford Refinery

(Shell only)

Page 4: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

General Features

September 19, 2013

4 PCCC2 Conference

Quest CCS Project - fully integrated CCS (capture, transport & storage)

JV among Shell (60%); Chevron (20%); and Marathon (20%) – part of AOSP

Located at Scotford Upgrader Complex

One million tonnes CO2 per year capacity for 25 years

35% reduction of Upgrader CO2 emissions Project Approval – Sept 2012

Page 5: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Hardware

PCCC2 Conference

SALT SEALS

Cement

SHALE SEALS

TARGET FORMATION

Capture at the Scotford Upgrader from 3 Hydrogen Manufacturing Units

CO2 transported by 12 inch pipeline to storage, with 6 inch laterals

Pipeline to 65 km north of the Upgrader

Route selected to meet stakeholder requirements: 28 km follows existing ROW Drilled under North Saskatchewan

River 30+ re-routes to accommodate

landowner wishes

Base plan: 3 injection wells and associated monitoring

September 19, 2013 5

Page 6: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Storage

May 14, 2013 6 PCCC2 Conference

SALT SEALS

Intermediate Casing

Main Injection Casing

Cement

Surface Casing

Tubing

SHALE SEALS

TARGET FORMATION

Packer Assembly

Perforations allow CO2 to penetrate the formation

Saline aquifer storage

Injection Formation - Basal Cambrian Sands (BCS)

2,300 m depth, Prairies deepest sandstone

Multiple caprock and salt seal layers in the storage complex

No significant faulting visible from wells or seismic

The BCS is well below hydrocarbon bearing formations and potable water zones in the region

Relatively few wells drilled into the BCS, none within 10 km of the proposed storage site

Wells and Drilling

Conventional drilling methods

Page 7: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Well Program Drilling finished, completions

ongoing

Capture & Pipeline Engineering finalized

Site underground construction complete

First module delivery Q4 2013

Major Equipment deliveries complete

Pipeline construction begins Q3 2013

Community Advisory Panel Initial kickoff in January,

with regular updates

Final Regulatory Approvals Pipeline laterals expected end

2013 September 19, 2013 7 PCCC2 Conference

Timeline and Upcoming Activities

Page 8: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Process Selection & Integration

1. Why activated amine (ADIP-x)? 2. HMU integration issues 3. CO2 Compression, integration with

pipeline and wells

September 19, 2013 8 PCCC2 Conference

Page 9: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Why activated amine (ADIP-x)?

Process Selection completed in Q1 2010 with the following constraints:

Design Basis capacity of 1.2 million tonnes per year, On-stream factor of 90% = 1.08 million tonnes per year calendar day capacity

Maximum pressure drop through the CO2 facility less than 70 kPa

Temperature of the PSA inlet gas after CO2 capture shall not exceed 35°C in order to maintain the H2 absorption capacity

Chemical solvent carryover to the PSA should be less than 1 ppmw. Chemical solvents can contaminate the PSA’s adsorbents.

Onsite electrical power availability limited due to HV substation constraints

Limited plot space available next to HMU units

September 19, 2013 9 PCCC2 Conference

Page 10: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Selection Drivers

Why activated amine (ADIP-x)? - CO2 Source Selection

10 Sept 19,2013 PCCC2 Conference

Scotford Upgrader

Pre-combustion

Post-combustion

Steam Methane

Reformers

• Fired heater

• Boilers • Gas

turbines

Parameter Post-Comb

D/S of PSA

U/S of PSA

System pressure

X X √

CO2 concentration

X √ √

CO2 partial pressure

X X √

Other impurities

X √ √

Plot space X X √

Downstream of PSA

Upstream of PSA

H2, CO2, CO, CH4

Page 11: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Why activated amine (ADIP-x)?

CRITERIA ADIP-X MDEA SELEXOL MEMBRANE PSA METHANOL

ABSORPTION AMMONIA

ABSORPTION LIQUE-

FACTION

HSE RISKS

CAPEX

OPEX

HMU RELIABILITY EFFECTS

COMMERCIAL

CONSTRUCTABILITY

Influencing Factors

Construction in brownfield location influenced 75% of options

Commercial scalability unproven for 5 of 8 options

Local Opex factors - steam versus electricity costs

September 19, 2013 11 PCCC2 Conference

Page 12: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Quest – Capture Facilities

12 Sept 19, 2013

PCCC2 Conference

Scotford Upgrader

Steam

HC Gas H2 + CO2

HP Steam Utili

ties

H2

CO2 to

atmospher

e

Reformer Hydrocrac

kers (Upgrader & Refinery)

PSA

CO2+CO+H2

Quest

Tie-In

Page 13: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Capture Design

September 19, 2013 13 PCCC2 Conference

Page 14: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Capture 3D Model – Amine Stripper & CO2 Compression

Sept ember 19, 2013 14 PCCC2 Conference

Amine Stripper

Compressor building

Compressor

Intercooling

TEG Dehydratio

n

Page 15: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Integration with Existing HMUs

September 19, 2013 15 PCCC2 Conference

H2 Manufacturing Unit Pressure Swing Adsorption (PSA) H2 Separation

Steam + NG

Product H2

CH4 + Slip H2 & CO2

HMU operation

Steam Balance

PSA adsorbent fill

Control system

Loss of

CO2

Storage Complex 2 km deep

Storage Site

3

CO2 Pipeline

2 1

Amine Unit Compressor

CO2

Dense phase transport Capacity Let down at choke

valve

Off gas Fuel

akeup Fuel (NG)

Page 16: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Integration with Existing HMUs

What does HMU do when Quest is online/offline?

Verify reformer box trip occurrences via dynamic analysis

Confirm steam balance within HMUs for FGR on/off

Loss in H2 production due to Quest?

PSA revised adsorbent fill to post Quest optimized loading

70 Kpa pressure drop forced piping upsizing

Issues – removing CO2 impacts HMU NOx production

Low NOx burners c/w testing (burner management system relook)

Flue gas recirculation permutations September 19, 2013 16 PCCC2 Conference

Page 17: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

HMU NOx

September 19, 2013 17 PCCC2 Conference

Emission Source Air Contaminant/

Parameter Current Limit Requested

Limit

Expansion HMU flue stack (S-44103) Nitrogen oxides 62.7 kg/h 130.0 kg/h

Base plant Train 1 hydrogen manufacturing unit flue stack (S-24103)

Nitrogen oxides 47.5 kg/h 76.5 kg/h

Base plant Train 2 hydrogen manufacturing unit flue stack (S-24203)

Nitrogen oxides 47.5 kg/h 76.5 kg/h

0

50

100

150

200

250

300

350

$- $0.50 $1.00 $1.50 $2.00 $2.50 $3.00 $3.50 $4.00 $4.50

NO

x, k

g/h

Scotford HMU NOx Reduction (Total)

Quest, CO2 Lean

Low Nox Burner (LNB)

Flue Gas Recirculation (FGR)

LNB+ FGR

Current Regulatory (EIA)

Page 18: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

HMU 1 & 2 Scope

September 19, 2013 18 PCCC2 Conference

Amine Absorbers

Flue Gas Recirculat

ion

Page 19: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Compressor Operating Envelope Integrally Geared, 8 Stages with inlet guide vanes

September 19, 2013 19 PCCC2 Conference

6

7

8

9

10

11

12

13

14

15

16

0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5

Pres

sure

, Mpa

Flow rate, Million tpa

PSV Set Pressure

Dense Phase Pressure

Guide Vane Position 65

-10

Page 20: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Integration of Capture/Pipeline/Wells - envelope

September 19, 2013 20 PCCC2 Conference

3

5

7

9

11

13

15

0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5

Pr

ess

ur

e, M

pa

Flow rate, Million tpa

PSV Set

Dense Phase Pressure

Guide Vane Position 65

High Injectivity - FTHP

-10

Base Injectivity - FTHP

Pres. at upstream of choke valve for Compressor discharge

of 11 Mpa

Page 21: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Quest is the first commercial scale CCS project in Canada

Pace setter for other efforts to manage CO2 footprint in Alberta

Abundant learnings for future projects

Key success factors

Early and extensive stakeholder engagement

Use of proven technology

System optimization (fit for purpose) and integration are important to minimize life cycle cost

HMU integration

Utilities integration

Capture optimization

Worth considering

Capture ready HMU’s or CO2 producers

Improvements in compressor configuration

Early injectivity data

Sept 19, 2013 21 PCCC2 Conference

Learnings and Conclusion

Page 22: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

www.shell.ca/Quest

Thank You!

Page 23: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Into ‘Execute’ phase to startup in 2015

2013 major activities: Completion of detailed engineering

Begin major construction end 2012 (mod yard work)

Major Equipment delivery and setting onsite

MMV baseline data gathering

Begin operations readiness and training

Completion of regulatory applications (pipeline laterals)

Ongoing stakeholder management

September 19, 2013

23 PCCC2 Conference

Next Steps

Page 24: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Costs/Revenues and Funding Agreements

PCCC2 Conference

SALT SEALS

Cement

SHALE SEALS

TARGET FORMATION

Total cost of Quest – Cdn$1.4 billion Includes Pre FID, capital and 10 years opex Capital Ratio: 80% Capture, 10% pipeline, 10% wells

Revenues – GHG offsets (credits) Net amount – stored CO2, less direct and indirect emissions Credits to be used first by Shell’s Alberta assets for

regulatory compliance

Government Funding Support – Cdn$865 million Cdn$120 million Canadian Federal Government (Pre FID) Cdn$ 745 million Alberta Province (Construction, Startup and

10 years operation) Extensive knowledge sharing Stringent monitoring (MMV) plan NPV Zero commitment

September 19, 2013 24

Page 25: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

Provincial GHG framework established CCS Act passed in Nov 2010, establishing overall structure

Pore space regulations in place with Quest successfully acquiring required area in May 2011

Participation in Regulatory Framework Assurance (RFA) process and GHG Offset Protocol revisions

No Federal framework to date – possible 2013

Regulatory approvals near complete Federal compliance achieved – EIA submitted, completed

internal and public review

Bundled provincial application submitted – Upgrader amendment, Pipeline, Well and Storage

3 rounds of Information Requests (200+) by provincial regulator, the ERCB

ERCB public hearing March 2012

Summer works and drilling permits to follow ERCB Decision Report September 19, 2013 25 PCCC2 Conference

Regulatory Framework

Page 26: QUEST CCS PROJECT - ieaghg.org pdfs... · QUEST CCS PROJECT PCCC2 Conference . Bergen, Norway . Sept 19, 2013 . Use this area for cover image ... Total cost of Quest – Cdn$1.4 billion

Heavy Oil Shell Canada

Restricted

General Assessment – Very Positive Major project attributes (technical, costs, regulatory,

stakeholders) tracking as planned

Project Successes Government fiscal support Pore space tenure Capture and Pipeline Front End Engineering and Design (FEED)

completion and Assurance Test Well and aquifer property verification Stakeholder engagement Pipeline routing finalization DNV certification of the storage development plan Regulatory Hearing

Challenges Capital Costs Schedule Pressure Regulatory Uncertainty (GHG Protocols, Federal framework)

September 19, 2013 26 PCCC2 Conference

General Project Assessment