Page 1: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

QUENTIN ROAD STUDYDundee Road to Lake Cook Road

Public Meeting No. 1December 9, 2015

Cook CountyDepartment of Transportation and Highways

Page 2: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

2

RE-INITIATE QUENTIN ROAD STUDYDESCRIBE PLANNING APPROACH

REVIEW EXISTING CONDITIONSGATHER INPUT AND INFORMATION

Welcome!

Page 3: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Project Study Limits

3

Page 4: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009 Public Hearing

Provide a more balanced study approach

Complete additional environmental studies

Consider additional alternatives

Include multi-modal elements

Focus on safety

New Cook County Department of Transportation and Highways leadership

Committed to a transparent and collaborative process

Partnership with the Forest Preserves of Cook County

Embracing innovative and sustainable approach

Project History

4

Page 5: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Planning Approach – Environmental Studies

New field studies and data collection Tree inventory Wetland delineations Groundwater surveys Coordination and consultation with resource agencies

5

Page 6: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

6

New analyses and data collection Traffic counts Crash reports and operations history Context sensitive alternatives analysis Multi-modal considerations

Planning Approach –Technical Studies

Page 7: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Focus on the unique context of Quentin Road

Deer Grove Preserves Camp Reinberg Quality natural resources

High quality wetlands Mature trees

Unique habitats

7

Existing Conditions Inventory

Page 8: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Aging and continuing deterioration of the facility

Bridge is over 100 years old Structural condition requires

load posted bridge

Rutted and cracked pavement Undefined roadway edges Poor drainage

Existing Conditions Inventory

8

Page 9: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Safety Needs

Little or no pedestrian or bike accommodations

No shoulders No turn lanes Uncontrolled pedestrian and

equestrian crossings

Existing Conditions Inventory

9

Page 10: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

High congestion levels during peak periods

Limited gaps in traffic – for safe turning movement

Safe access to Deer Grove and cross access between Deer Grove East and West – for pedestrians, bikes, and equestrians

Direct stormwater runoff into Salt & Buffalo Creeks, wetlands, and forest preserve

Public and private utilities Minimize impacts and mitigate

responsibly – enhance and replace 10

Project Challenges –Traffic, Safety, Environment

Page 11: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Quentin Road’s Regional Context

Strive to balance transportation needs with the unique setting of Quentin Road

Critical to transportation network Regional and local connectivity Provides access to and links multiple destinations,

including Deer Grove Forest Preserves

11

Page 12: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Evaluation of shoulders and ditches vs. curbs Inclusion of additional pedestrian and bike facilities

and connections Evaluation of travel lane needs Consideration for narrow lane widths Inclusion of sustainable design elements

Water quality – rain gardens/vegetated swales Drainage outfalls Habitat enhancement – wildlife crossings

Potential Alternatives

12

Page 13: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Concepts for Deer Grove/Camp Reinberg

Emphasize User Safety

Evaluate tunnel crossing Evaluate at-grade crossing

with traffic control (signals or stop signs)

Balance with needs of Camp Reinberg and Deer Grove as a whole Minimize tree impacts Complement new uses

13

Page 14: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

Study Timeline

The Environmental Assessment Report (EA) is expected to be completed by 2017

ScopingSolicit public input on issues andconcerns the project should address

Purpose & NeedEstablish why the project is needed

AlternativesIdentify and consider alternatives that address the project’s Purpose & Need

ScreeningReview alternatives to determine if they are reasonable and feasible considering human & natural environment, engineering, and costX

Draft Environmental Assessment (EA)Documents affected environment, range of alternatives and analyses of the impacts

Public Involvement

We Are Here

Public Information Meeting Public Information Meeting Public Hearing

2015 2016 2017

Final EAAnnounce Proposed Action based

on comments received on Draft EA

Page 15: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

What Will You See At This Public Meeting?

Series of exhibits Project team and staff are available to

answer questions Please provide input and comments

Comment period open until December 23rd

Future public meetings Fall 2016 (Present alternatives) Spring 2017 (Present recommendation)

15

Page 16: QUENTIN ROAD STUDY - Cook County, Illinois · Studies of Quentin Road have been ongoing since the 1980s Previous study efforts were roadway centric Conclusions from December 2009

THANK YOU FOR COMINGQuentin Road Public Meeting No. 1

Next presentation will begin shortly

Public Meeting No. 1December 9, 2015

Cook CountyDepartment of Transportation and Highways