quarterly review october 5, 2001 1 quarterly review october 5, 2001

119
1 Quarterly Review October 5, 2001 QUARTERLY REVIEW October 5, 2001

Upload: brian-atkins

Post on 11-Jan-2016

218 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

1

Quarterly ReviewOctober 5, 2001

QUARTERLY REVIEW

October 5, 2001

Page 2: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

2

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 3: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

3

Quarterly ReviewOctober 5, 2001

GNIRS Quarterly Review

Table of Contents

• Introduction Pg 4

• Project Summary Pg 7

• Configuration & Integration Pg 29

• Project Management Pg 67

• Appendices Pg 89

Page 4: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

4

Quarterly ReviewOctober 5, 2001

Introduction• This is the 6th GNIRS Quarterly Review

• GNIRS is in the final design and fabrication phase– All bench assemblies are complete– Mechanism testing is underway– Integration will start this month

• We are still on track for delivery in fall of 2002

Page 5: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

5

Quarterly ReviewOctober 5, 2001

Outline

• Project summary– Last QR Response– Progress Overview– Cost and Schedule Status

• Problems and Concerns • Configuration Update• Technical Progress• Project management• Plans for next review

Page 6: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

6

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 7: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

7

Quarterly ReviewOctober 5, 2001

Project Summary

• Response to last QR report• Progress overview• Summary schedule• Work left• Budget and expenditures to date

Page 8: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

8

Quarterly ReviewOctober 5, 2001

Response to June QR - Issues to be reviewed

• Late delivery of the OIWFS– Contingency plan

• 2 month schedule slip

• Completion of planned items

• Documentation– ATP payment milestone

– Rotary Prototype report

– Linear prototype report

– Change orders

• Status of dewar warm-up controller

• Definition of systems engineering effort

• Fabrication delays– Vendor performance

– Amount of rework

• Flexure rig availability

• Rolling wave (labor)

• Staffing – in design drafting area

• IFU late delivery

• Status of bulkhead assembly

• Software– NIRI Code version

– OCSwish

Page 9: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

9

Quarterly ReviewOctober 5, 2001

Response to June QR

• Late delivery of the OIWFS - Contingency plan

– The contingency plan that was agreed upon was to install the OIWFS bench with mass models and continue with integration. Gemini would be responsible for integrating the OIWFS components at a later date.

– Implementing this plan was not necessary as the components did eventually arrive and can be integrated without serious schedule impact.

• 2 month schedule slip– The project is considered to be behind schedule by about 2 months. This

lag was specific to the Design and Fabrication phase of the project. Schedule re-planning has been done to minimize the impact on the integration phase. The effect is to deliver the instrument in September rather than in August.

Page 10: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

10

Quarterly ReviewOctober 5, 2001

Task StatusITEM STATUS COMMENT

Complete design of all fixed assemblies Not Complete – 17 of 19 fixed assemblies completed design

Should complete by mid-November

Complete fabrication of all mechanisms Not Complete – Focus Assembly still in fabrication Should complete early October

Complete fabrication of all benches Complete

Complete fabrication of Bulkhead Assembly Not Complete – Release delayed for completeness, delivery impacted by changes and expanded work scope

Delivery scheduled in November; includes vacuum test of complete assembly

Complete fabrication of most dewar components Not Complete Completion expected mid-December

Complete 75% of mechanism and optical sub-assembly testing

Not Complete – Mechanism testing delayed by higher priority work on benches and Bulkhead Assembly

Testing should complete by mid-December

Receive all optics Not Complete – Replica mirror contract had to be re-bid due to vendor non-performance; one camera lens failed inspection

Optics should complete by mid-November

Complete electronics thermal enclosure fabrication and checkout

Complete

Complete initial software coding (of Component controller code)

Complete – Component Controller Code finished EPICS code still in work

Start testing of Component controller software Complete – Code has been tested as far as possible until more hardware becomes available.

All testing should be complete by mid-December

Complete OIWFS component integration Not Complete – OIWFS bench required rework as components did not match ICD as specified; documentation incomplete

Integration should be complete by mid-December

Page 11: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

11

Quarterly ReviewOctober 5, 2001

Response to June QR

• Planned Completions by this Quarterly Review – 3D and 2D design of all fixed assemblies

– Fabrication of all mechanisms

– Fabrication of all benches

– Fabrication of the Bulkhead Assembly

– Fabrication of most dewar components

– 75% of mechanism and optical subassembly testing

– Receive all optics

– Electronics thermal enclosure fabrication and checkout

– Initial software coding

– Start testing of Component Controller software

– OIWFS component integration

Page 12: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

12

Quarterly ReviewOctober 5, 2001

Response to June QR

• Documentation and change orders– A draft outline of the ATP and commissioning plan has been

submitted to Gemini and reviewed. ATP is being developed, at Gemini’s request, in conjunction with the commissioning and training plan.

– A change order is in process which addresses acceptance testing, training and commissioning in Chile. Jay Elias has the action to produce a plan which will be based on the outline already submitted to Gemini.

– The rotary and linear prototype test reports were not deliverables. These items were reported on at the Mid-Fab Review and by internal emails and SDN’s sufficient to proceed with the design of the affected mechanisms.

Page 13: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

13

Quarterly ReviewOctober 5, 2001

Response to June QR

• Dewar warm-up controller– This controller is an ancillary box which is not needed until we

begin actual cold testing of the instrument. Fabrication is therefore a low priority task which has been scheduled to be done at a later date.

• Systems engineering effort– This effort has been reported as completed on all our status reports

as all tasks associated with the initial engineering effort in the baseline plan have been accomplished. There is a sustaining engineering function in which the systems engineer (Jay Elias) oversees the entire design effort and gives support as required. This will continue until the instrument is delivered to Gemini.

Page 14: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

14

Quarterly ReviewOctober 5, 2001

Response to June QR

• Fabrication delays due to vendor performance and rework– We have experienced several delays from various vendors who are

fabricating components for the instrument, including rework on several components. This has had the most serious impact on the start of mechanism testing. We are past this period and all but one mechanism has finished mechanical fabrication.

– The Bulkhead Assembly and Dewar Shells have been delayed due to design changes to incorporate ballast weights and the cryo manifold. The delay amounts to about 1 month, but is not pacing the project as the vendor has also been contracted to do vacuum testing on the assembled Bulkhead Assembly and Dewar Shells. This task is considered part of integration testing.

Page 15: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

15

Quarterly ReviewOctober 5, 2001

Response to June QR

• Flexure rig need date– The flexure rig need date of mid-February 2002 was impossible to

attain due to the time required to procure the rig and build a building to house it. A more realistic date for having the facility in place and operational is mid-April. We had intended to test as soon as practicable in order to identify any flexure issues. We have adjusted our schedule to accommodate the predicted availability date.

• Rolling wave (labor)– The charts in the Project Management section show that we still

have a peak in labor resource need in the month of November. The peak is down from that shown in the last QR and is dissipating. This peak should be gone by the end of December.

Page 16: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

16

Quarterly ReviewOctober 5, 2001

Response to June QR

• Staffing in the design drafting area– At the time of the last QR design drafting was a critical path item. This is

no longer the case as the designers have accomplished the backlog of work that kept them on the critical path.

• IFU late delivery– Because of the delay, we are proceeding with mass modules. We will try

to accommodate Gemini in integrating the IFU when it becomes available.

• Status of Bulkhead Assembly– The design took longer than originally planned, and the final release to

fabrication was further delayed in order to ensure that the design was complete. Some design changes were required after the release. This is a complicated assembly with many parts. The unit is currently in fabrication and will be completed in October. It will then be leak tested with the Dewar Shells, which are also in fabrication at the same vendor. Images of these assemblies are shown in the Appendix.

Page 17: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

17

Quarterly ReviewOctober 5, 2001

Response to June QR

• Software: Which version of the NIRI Code is being used?– GNIRS is not using the NIRI code. This decision was based on much

discussion and on the recommendation of Hubert himself.

• Software: Look at using OCSwish– We have finally received the OCSwish tool and are using it. So far we

see no problems in using it for integration with our EPICS code. This is discussed in more detail in the software portion of this review.

Page 18: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

18

Quarterly ReviewOctober 5, 2001

Summary Project PlanJ F M A M J J A S O N D J F M A M J J A S O N D

CY-2001 CY-2002

Fixed Assemblies Design/Fab

Integration/Alignment

Bench Design/Fab/Assy

OIWFS/Post-Slit/Pre-Slit

WFS Integration/Alignment

Mechanism Design/Fab/Assy/Test

IFU Modules

Software Development/Code/Test

SW Plan/Low-Level/High-Level Code

Electronics Design/Fab/Test

Manuals

ATP

Ship

Training

MFR

Rotary Mechanism Flexure Tests

Mirrors/Lenses/Filters/Gratings/Prisms

Flexure Testing

N D J F M A M J J A S O N DCY-2000

Risk Reduction Prototypes

PFR

Structural Analysis

Bench Design/Fab/Assy

OIWFS/Post-Slit/Pre-Slit

Mechanism Design/Fab/Assy/Test

9 Mechanisms

Electronics Design/Fab/Test

Optics Procurement

OIWFS Hardware

Rotary Mechanism Flexure Tests

Systems Engineering

Mirrors/Lenses/Filters/Gratings/Prisms

Page 19: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

19

Quarterly ReviewOctober 5, 2001

Revised Bench Integration Plan9/15 10/1 10/15 11/1 11/15 12/1 12/15 1/1 1/15 2/1 2/15

Rad ShieldsDesign 11/8 Fab 12/15

Bulkhead Assy 11/28- Fab- Test

Assemble & Wire 2/4- Shields- Wiring- Cooling

1/8

Pre-Slit Integration 11/28 - Offner - POM - FW - IFU Mass - SD

Bench Painting

9/27 Post-Slit Integration 12/10 - PT - GT - ACQM - Focus - Camera - Collimator

Mate Benches 12/15

Install into top assy 2/5

OIWFS Integration

Camera Barrel Testing 11/15

Mechanism Testing 12/10

Warm Optics Test

Cold Tests

Page 20: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

20

Quarterly ReviewOctober 5, 2001

Project Status - Progress from August ’99

WBS element Mar Review Jun Review Oct Review5.0 Overall project 53% 66% 80%5.1 Management & Reporting 51% 61% 71%5.2 Systems Engineering 100% 100% 100%5.3 Mechanical 52% 70% 87%5.3.1 Mechanisms 66% 84% 92%5.3.2 Benches 55% 70% 100%5.3.3 Fixed Assemblies 16% 36% 62%5.4 Electronics 63% 59% 86%5.5 Software 49% 63% 85%5.6 Integration 0% 0% 2%5.7 Deliverables 0% 0% 0%5.8 Procurement 54% 67% 77%

Page 21: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

21

Quarterly ReviewOctober 5, 2001

Progress Overview

• The delivery date of the instrument is now September 25, 2002– Delays in vendor fabrication

– Bench and mechanism rework and testing delays

– Late release of assemblies to fabrication

• The project is currently 80% complete overall

• We have completed 131 of 224 total project milestones

• Our critical path is 3D and 2D design and fabrication of Radiation Shields

• Optics are complete except for the POM, Acquisition Mirror, one camera lens

• Electronics design and fabrication is 86% complete

• Software Component Controller code is functional – Limited testing completed

Page 22: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

22

Quarterly ReviewOctober 5, 2001

Comments on Last Quarter of Work

• Design activity concentrated on– Bench modifications and completion– Bulkhead Assembly fabrication– Fixed Assembly design and fabrication– General design cleanup (configuration control)

• Procurement– Mechanical – Optical

• Mechanism warm test and fit checks• Envelope waiver• ATP & Commissioning Plan

Page 23: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

23

Quarterly ReviewOctober 5, 2001

Progress and Schedule Comments

• The beginning integration tasks have been re-planned– No significant impact on fall-2002 delivery – now September 2002– We have 6 weeks schedule contingency left

• The mechanical design effort is virtually complete– Our schedule has been impacted by Bench and Bulkhead assembly

changes– 3D design is nearly complete

• Radiation Shields and the Thermal Distribution Assembly remain

• Fabrication will continue through November• Mechanism assembly/test has begun

– Filter wheel ready for cold test– Grating and Prism Turrets are ready for final warm test– Acquisition Mirror has been warm tested

Page 24: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

24

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 25: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

25

Quarterly ReviewOctober 5, 2001

Budget and Expenditures• Baseline Estimate (Jan 99 to completion)

• Labor $3,391,232• Capital $ 836,462• Total $4,227,694

• Current Forecast March Review June Review October Review

Labor $2,866,775$3,002,938 $2,957,389Capital $1,074,798$1,181,900 $1,138,285Total $3,941,573$4,184,838 $4,095,674

• Performance ratios March Review June Review October Review

BCWS $ 1,754,979 $ 2,863,855 $ 3,085,811 BCWP $ 1,611,542 $ 2,011,383 $ 2,526,319ACWP $ 1,742,651 $ 2,113,212 $ 2,762,963CPI 0.92 0.95 0.91SPI 0.92 0.70 0.82

Page 26: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

26

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 27: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

27

Quarterly ReviewOctober 5, 2001

Problems and Concerns• Optics – Pick-off and Acquisition mirrors, Camera lens

• New vendor contracted for replica optics - November delivery• Last camera lens has predicted November delivery

• Mechanical rework• Delay in mechanism testing• Design additions• Impact on vendor delivery of Bulkhead and Dewar Shell Assemblies

• OIWFS• OIWFS delivery was incomplete

• documentation incomplete

• Component interfaces were not well defined in the “ICD”

• IFU anticipated delivery in March 2002• We will use mass models and proceed

• Flexure testing delayed to mid-April 2002• Flexure rig delivery later than planned

Page 28: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

28

Quarterly ReviewOctober 5, 2001

Configuration Image

Page 29: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

29

Quarterly ReviewOctober 5, 2001

Configuration - Overview

• Additions• Envelope waivers• Weight & CG update• Design/fabrication status

Page 30: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

30

Quarterly ReviewOctober 5, 2001

Configuration - Additions• Cryocooler related items: differential pressure switch implementation

requested by Gemini in order to protect system against loss of pressure due to compressor shut-down; also has software implications (detector protection); helium gas heater required to ensure reliable operation at low temperature; system developed for Phoenix; minimal heat dissipation into environment with line insulation.

• Ballast weights: need indicated at last QR; 10-lb increments; allow shift of instrument moment up to ~350 ft-lb.

• Cable/hose routing & brackets: routing of all coolant/gas lines, cables with required brackets and attachment points. Patch panel on instrument facilitates installation, removal and service.

Page 31: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

31

Quarterly ReviewOctober 5, 2001

Configuration - Additions

• Cryocooler related items:– Differential pressure switch– Helium gas heater

• Ballast weights– Need indicated last QR; now located

• Cable/hose routing & brackets– Attachment points– Instrument patch panel

Page 32: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

32

Quarterly ReviewOctober 5, 2001

Configuration Image

Page 33: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

33

Quarterly ReviewOctober 5, 2001

Configuration - Envelope

• Envelope waiver approved prior to last QR• Additional waiver requested to accommodate

Instrument Patch Panel and He manifold approved

Page 34: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

34

Quarterly ReviewOctober 5, 2001

Configuration Image

Page 35: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

35

Quarterly ReviewOctober 5, 2001

Configuration - Weight• Weight updated

– New value is 3996 lb (1813 kg)– Change of +66 lb from June QR

• Mostly DPS & Gas Heater

– Small change does not justify effort to recompute center of gravity location given existence of ballast weights

• Weight estimates history– 3/01: 4113 lb (1866 kg)– 6/01: 3930 lb (1782 kg)– 9/01: 3996 lb (1813 kg)– Requirement (budget): 4413 lb (2000 kg)

Page 36: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

36

Quarterly ReviewOctober 5, 2001

Configuration - Design Status• Few remaining items: “punch list”

– Optical:• Telescope simulator

– Mechanical• Shields• Thermal distribution system• Test fixtures• Telescope simulator

– Electrical• Cabling • Dewar and mechanism wiring

– Software• Sequencer and interfaces

Page 37: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

37

Quarterly ReviewOctober 5, 2001

Configuration - Design Status

• Configuration control - drawing status (9/26/01)

– 957 drawings defined on the instrument• Released

– Assemblies - 156

– Details - 663

• Not Released– Assemblies - 54

– Details - 84

– Percent of drawings released – 86%

Page 38: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

38

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 39: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

39

Quarterly ReviewOctober 5, 2001

Integration & Test - Overview

• Subsystem testing– Fit checks

– Mechanism tests

– Optics tests

• Integration and alignment

Page 40: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

40

Quarterly ReviewOctober 5, 2001

Subsystem TestingGNIRS Subsystem tests

Test StatusSubsystem Test Type Warm Shop Warm Clean Cold Remarks

Environmental Cover M Partial Requires dewar shell for completion

Complete Bench O,E Cold check in assembled instrumentPre-Slit Bench M PartialOffner+Pickoff O Needs pickoff mirrorFilter Wheels (2) M Done Needs rest of bench for next stageSlit+Decker Slides M Partial In rework

Post-Slit Bench M Done Waiting for completion of mechanism testsCollimator Compensator M In fabPrism Turret M Needs fixturingGrating Turret M Needs fixturingAcquisition Mirror M Done Needs mirror replication & cleaningCamera Turret M Refers to assembled turretHub M Done Needs fixturing, cleaningShort Red Camera O Missing lensShort Blue Camera O Needs cleaningLong Red Camera O In fabLong Blue Camera O In fabFocus Mechanism M In fabDetector Mount E Status ?

OIWFS O,E Done Optical alignment after cleaningGimbal Mirror M Done Done Mechanisms tested at IfAFilter Wheel M Done Mechanisms tested at IfA; no cold testing on FWFocus Stage M Done Done Mechanisms tested at IfADetector Mount E Done Done Mechanisms tested at IfA

Test Types:M: mechanical, including optomechanical and switchesO: opticalE: detector tests

Test not possible or not requiredDone Testing complete for this phase

Page 41: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

41

Quarterly ReviewOctober 5, 2001

Subsystem Testing

• Qualifies sub-assemblies for integration– Performance can be checked prior to final integration

– Problems are isolated

– Maximum time for problem fixes

Page 42: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

42

Quarterly ReviewOctober 5, 2001

Subsystem Testing

• Fit checks– Done prior to final cleaning and painting

– Check of interfaces

– Includes vignetting checks

– Complete for all bench assemblies and all mechanisms except focus and collimator; including OIWFS assemblies

Page 43: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

43

Quarterly ReviewOctober 5, 2001

Subsystem Testing

• Testing of mechanisms as outlined in previous reviews– Warm functionality

– Warm flexure

– Cold functionality

– Tests (especially cold tests) without optics

Page 44: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

44

Quarterly ReviewOctober 5, 2001

Subsystem Testing

• Mechanism test plans– Test fixtures required for 3 turrets (2 fixtures)

– Forward bench tested as assembly• requires adaptor for cold test (test filter wheels, decker and slit

slides).

– Complete acquisition mirror & environmental cover tests

• requires assembled bench and dewar shell respectively

Page 45: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

45

Quarterly ReviewOctober 5, 2001

Subsystem Testing• Mechanism test status

– Initial warm tests complete for:• All 3 turrets• Filter wheels• Acquisition Mirror• All OIWFS mechanisms• Slit/decker slide in rework, retest on completion

– Final warm tests (after cleaning, w/ motor drives):• All OIWFS mechanisms done• Waiting for cleaning & fixturing on 4 mechanisms

– Cold tests will start in late October

Page 46: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

46

Quarterly ReviewOctober 5, 2001

Subsystem Testing

• Optics testing of “powered” sub-assemblies– Four cameras

– Offner relay

– Verifies performance, not required for alignment

– Camera tests require calculation of thermal, wavelength shifts

Page 47: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

47

Quarterly ReviewOctober 5, 2001

Subsystem Testing

• Optics test status– Short blue camera is ready for test

– Remaining camera tests waiting for mechanical fabrication(LR & LB) or lens fabrication (SR) to be completed

– Offner waiting for pick-off mirror (vendor problems)

Page 48: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

48

Quarterly ReviewOctober 5, 2001

Subsystem Testing

• Bench Temperature Control– Warm bench test– Cold test (9.4 kg mass 20 minute time constant)– Adjust control parameters for final

configuration

Page 49: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

49

Quarterly ReviewOctober 5, 2001

OIWFS Issues

• There are missing or corrupted detector micro-code files– readout from mux shows no noise

– potentially more serious, requires IFA support

• Some setup information incomplete

• Electronics documentation incomplete

• Operating software is working

• Mechanism status (9/20/01)– Zero is displaced on gimbal Y-axis

– Otherwise, hardware appears ok

Page 50: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

50

Quarterly ReviewOctober 5, 2001

Bench Integration• Add subsystems to bench after qualification

– Main (Post-Slit) bench painting complete • ready for sub-assembly integration

• integrate prism and grating turrets, acquisition mirror after tests

• add focus, collimator assembly on completion of fab & test (Dec.)

– Integrate Pre-Slit assembly (Offner, filter wheels, slit/decker) as a unit• testing should complete by end of November or early December

• add to main bench

– OIWFS assembly and alignment • As time allows

• Should complete by end of November

Page 51: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

51

Quarterly ReviewOctober 5, 2001

Bench Integration• Add subsystems to bench after qualification• 3 major assemblies integrated in parallel

– Main (Post-Slit) bench

– Pre-Slit assembly

– OIWFS

• Dewar assembly also parallel

Page 52: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

52

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 53: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

53

Quarterly ReviewOctober 5, 2001

Bench Integration

• Integration into bench permits warm optics and mechanical check (uses warm MUX)– Check (re-check) fit, alignment, repeatability

– Check image quality (“warm” predictions)

– Check flexure compensation calibration & performance (but not flexure calculations)

Page 54: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

54

Quarterly ReviewOctober 5, 2001

Dewar Integration

• Integration of cold structure into vacuum vessel – Dewar shell tested at vendor; should be delivered by December – Cryostat integration in parallel to bench integration

• Shield installation• Wiring and cold-stationing• Trusses, window, environmental cover

• Re-test with MUX– Possible limited flexure test

• Install engineering array• Last chance for installation of OIWFS prism or IFU without

disassembly

Page 55: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

55

Quarterly ReviewOctober 5, 2001

Dewar Integration

• Integration of cold structure into vacuum vessel • Re-test with MUX• Install engineering array• Last chance for easy OIWFS prism, IFU

installation

Page 56: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

56

Quarterly ReviewOctober 5, 2001

Dewar Integration

• Initial cool-down followed by tests outlined in August ‘99 test plan– Start February 2002

– Flexure testing using NOAO facility (copy of Gemini rig)• Scheduled for April 2002

• Opportunities for IFU installation during testing– Schedule penalty varies

Page 57: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

57

Quarterly ReviewOctober 5, 2001

Acceptance and Commissioning

• Acceptance Test Plan– Pre-ship AT - Tucson– Post-ship AT - CP lab– Final-AT - Gemini South telescope

• Commissioning Plan– Probably 2 runs– Flows into science verification

• Complete sequence ~4 months long

Page 58: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

58

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 59: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

59

Quarterly ReviewOctober 5, 2001

Software Components

• Top Level– Instrument Sequencer– Interfaces to detector, wavefront sensor, components controller,

OCS

• Components Controller– Control (CAD, CAR, Apply)– Status and Alarm database (SAD)

• Low Level Software– Motor Control– Temperature readback– Pressure monitoring

Page 60: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

60

Quarterly ReviewOctober 5, 2001

Software Work Remaining - Design

• Alarm and Status Propagation– Minor impact at various levels

– All other design complete

• WCS/DHS header information

Page 61: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

61

Quarterly ReviewOctober 5, 2001

Software Work Remaining - Coding

• Low Level (Hardware Interfacing)– No remaining coding planned

• Components control– Alarm and Health propagation

• Instrument Sequencer and Interfaces– Alarm and Health propagation

– Engineering User interface (ongoing)

Page 62: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

62

Quarterly ReviewOctober 5, 2001

Software Work Remaining - Testing

• Low Level– Prefer fully wired system for end-to-end test– Motors

• Multiple motors simultaneously• Determine distances between limits, switches, etc• Set speeds, acceleration, backlash parameters• Actual mechanism(s) needed

– Temperature Probes• Set calibration curve and individual offsets

– Pressure Sensor• Verify operation in final configuration

Page 63: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

63

Quarterly ReviewOctober 5, 2001

Software Work Remaining - Testing

• Upper Level -- EPICS– Engineering screens provide next level of test

• Top Level -- OCS compliance– use OCSwish

• new tool, in use in Hawaii, verifies OCS interface,

Page 64: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

64

Quarterly ReviewOctober 5, 2001

Software Work Remaining

• Simulation allows testing without hardware– Works only for motors.

• Hardware testing to take 2-5 days• Additional work

– Lab Support

– Conversion to GEM7 or GEM8

Page 65: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

65

Quarterly ReviewOctober 5, 2001

Software Work Remaining

• Software is done when – Motors, temperature readback, etc, work at command

line (low level)

– Engineering Screens provide required control and readback

– OCSwish/Acceptance test proves compliance with Gemini system

– GNIRS works on the telescope

Page 66: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

66

Quarterly ReviewOctober 5, 2001

Software Interface Issues

• Array Controller– Testing will verify correct interface to instrument sequencer

• OCS– OCSwish has been tested and is working

• OIWFS– Limited testing done shows mechanisms are functional

– We assume the OIWFS will provide good data• We have no means of testing actual data output

Page 67: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

67

Quarterly ReviewOctober 5, 2001

Project Management

• Project Status• Schedule & Planning• Milestones• Budget and Expenditures• Organization• Plans for Next Review

Page 68: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

68

Quarterly ReviewOctober 5, 2001

Project Status – Overview

• Critical path is Radiation Shield design and fabrication

• Bench integration starts in October– All three benches (Pre and Post Slit, OIWFS)

• Mechanisms and optics integration into benches starts in October– Bench fit checks are done

• Software and electronics checkout slated for completion by 15 December– Further checkout is waiting for mechanisms to be finished

Page 69: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

69

Quarterly ReviewOctober 5, 2001

Project Status – WBS 5.2 Systems Engineering

• Systems Engineering activities over this quarter included– Oversight of the top level design and interfaces

– Writing of the Acceptance Test Plan & Commissioning Plan

– Optical element evaluation• Included prisms/gratings/mirrors/lenses

– Envelope waiver submission

– Mechanism warm tests

– Bench temperature control tests

Page 70: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

70

Quarterly ReviewOctober 5, 2001

Project Status – WBS 5.3 MechanicalMechanism %Camera 90

Detector Focus 67

Environ Cover 99

Acquisition Mirror 93

Slit Decker 90

Filter Wheel 95

Grating Turret 97

Gratings 100

Prism Turret 98

Prisms 100

Motor Drives 100

Bench %Post-Slit 100

OIWFS 100

Collimator 95

POM/Offner 100

Fixed Assembly %Entrance Window 100Cryo-cooler 59Thermal Dist. 26Bulkhead Rad Shield 5LN2 Pre-Cool 91Opt Bench Mount 100Environ Cover Filter 15Bulkhead 75Front Rad Shield 8Rear Rad Shield 18Front Dewar Shell 70Rear dewar Shell 61Vert Inst Frame 77Horiz Inst Frame 57Dewar Mount Truss 44TE Mount Truss 70Shipping Container 0Handling Fixture 100

Page 71: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

71

Quarterly ReviewOctober 5, 2001

Project Status – WBS 5.3 Mechanical

• All mechanism fabrication complete except two camera barrels and the focus assembly.

• All benches complete; collimator assembly nearly done

• Fixed assembly 3D design remaining – Radiation shields (passive and active)

– Thermal distribution assembly

– Cryo-cooler and manifold

• Fixed assembly 2D detailing in-work– Dewar mount truss assembly

Page 72: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

72

Quarterly ReviewOctober 5, 2001

Project Status – WBS 5.4 Electrical

• Design activities are completed• Work remaining

– Fabricate the Thermal Enclosure to Dewar cables

– Harness the cold mechanisms and cold bench as they become available

– Support software testing

– Harness the Bulkhead Assembly

– Dewar warm-up controller fabrication

Page 73: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

73

Quarterly ReviewOctober 5, 2001

Project Status – WBS 5.5 Software

• Component Controller code virtually complete• Code has been tested as far as possible before integration

• Testing with mechanisms is underway

• High level (EPICS) code 70% complete

• Gemini OCSwish module received

Page 74: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

74

Quarterly ReviewOctober 5, 2001

Project Status – WBS 5.8 Procurement

• Major items remaining in procurement are the Bulkhead Assembly and Dewar Shells

• Two replica mirrors remain to be fabricated– New vendor is under contract, delivery expected in

November

• There are no major vendor fabrication contracts left to let– Remaining work is small parts/components

Page 75: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

75

Quarterly ReviewOctober 5, 2001

Project Status – Optics

• Lenses and Windows• Only one BaF2 lens for short red camera remains

• Vendor remaking the last lens

• Testing will proceed with the defective lens

• Camera testing is underway

• Mirrors• All mirrors received except for POM and Acquisition Mirror

• Filters• 7 filters ordered through UH consortium; 2 failed spec and

vendor may replace

Page 76: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

76

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 77: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

77

Quarterly ReviewOctober 5, 2001

Project Milestones by Quarter

As of 9/21/01

Calendar Year Quarter

Number of Milestones

DueRunning

Total

Number of Milestones

CompRunning

Total1999 4th 1 1 1 12000 1st 15 16 15 162000 2nd 13 29 13 292000 3rd 8 37 8 372000 4th 18 55 18 552001 1st 20 75 20 752001 2nd 32 107 32 1072001 3rd 40 147 24 1312001 4th 56 203 0 1312002 1st 13 216 0 1312002 2nd 3 219 0 1312002 3rd 5 224 0 1312002 4th 0 224 0 131

TOTAL 224 131

Page 78: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

78

Quarterly ReviewOctober 5, 2001

GNIRS Staffing FTE by Month

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

Month

FTE

Plan FTE Actual FTE

Page 79: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

79

Quarterly ReviewOctober 5, 2001

GNIRS Work by Month

0

1000

2000

3000

4000

5000

6000

Month

Hour

s

Actual Baseline Sep'01 Plan

Page 80: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

80

Quarterly ReviewOctober 5, 2001

Planned FTE ProjectionOct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept

FTE Type NameME Muller 1 1 0.75 1 1 1 1 1 1 1 1 1ME Hileman 1MD Andrew 1 1 0.75 0.75 1 1 1 1 1 1 0.5 0.25MD Downey 1 1 0.75MD Rosin 1MD Circle 1 1 0.5EE Penegor 0.25 0.25 0.25 0.25 0.25 0.25 0.1 0.1 0.1 0.1 0.25ET George 0.75 0.75 0.75 1 0.75 0.75 0.75 0.75 0.75 0.75 1 0.5IM Stein 1 1 0.75 1 1 1 0.5 0.5 0.5IM Bennett 0.75 1IM Harris 1 1 0.5IM Lederer 1 1P Wolff 1P Ruckle 1 1 0.75 1 1 1 1 1 1 1 1 1

OE Ming 0.25 0.25 0.25 0.25 0.25 0.25GT Pina 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

ENG Distler 0.5 0.5 0.5 0.5 0.25 0.25 0.25 0.25 0.25 0.25 0.25PA Eklund 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5AA Bowersock 1 1 0.75 1 1 1 1 1 1 1 1 1PE Davis 1 1 0.75 1 1 1PS Elias 1 1 0.75 1 1 1 1 1 1 1 1 1

PSS Joyce 0.5 0.5 0.75 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5PM Gaughan 1 1 0.75 1 1 1 1 1 1 1 1 1

Total 19 16.25 11.25 11.25 11 11 9.1 9.1 9.1 8.6 8.5 7.253040 2600 1800 1800 1760 1760 1456 1456 1456 1376 1360 1160

Spend Rate ($/mo) $114,480 $97,760 $67,360 $67,360 $65,840 $65,840 $54,288 $54,288 $54,288 $51,248 $50,640 $43,040

Total $ to go $786,432 21024

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept19.25 16.25 8.75 11.25 11 11 9.1 9.1 9.1 8.6 8.5 7.25

0

5

10

15

20

25

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept

FTE

Page 81: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

81

Quarterly ReviewOctober 5, 2001

FTE Projection• Table shows the resources forecast over the next fiscal year• There is a peak in the resources needed in Nov - Dec

– “Rolling wave” is spread over two months– The MS Project “wave” is an attribute of how MS Project works

when it assembles monthly data• It misrepresents the amplitude of the wave in November by the way it

handles its calendar– Hours actually spread over adjacent months can compress into one month,

showing resources overloaded one month and under utilized the next, making a peak need in resources look worse than it actually is

• We estimate approximately 21,000 hrs total needed to finish the project– This does not include commissioning or the impact of the pending

change order for delivery to Chile

Page 82: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

82

Quarterly ReviewOctober 5, 2001

GNIRS Cum ulative Work

0100002000030000400005000060000700008000090000

Month

Hours

Actual Baseline Sep'01 Plan

77,730h

[78,469h w/sci.]

79,725h

52,649h

Page 83: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

83

Quarterly ReviewOctober 5, 2001

GNIRS Capital Spend Plan

$0

$200,000

$400,000

$600,000

$800,000

$1,000,000

$1,200,000

$1,400,000

Month

Dolla

rs

Actual Baseline Sep'01 Plan

$759,192

$1,188,797

$1,070,777

Page 84: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

84

Quarterly ReviewOctober 5, 2001

Organization Chart

Page 85: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

85

Quarterly ReviewOctober 5, 2001

Director, NOAOJ. Mould

Director, NOAOJ. Mould

Gemini Projects Project Manager

N. Gaughan

Gemini Projects Project Manager

N. Gaughan

Administrative AssistantM. Bowersock

Administrative AssistantM. Bowersock

Project Scientist, Systems

Engineering J. Elias

Project Scientist, Systems

Engineering J. Elias

Mechanical EngineersG. Muller

E. Hileman

Mechanical EngineersG. Muller

E. Hileman

OpticalEngineerM. Liang

OpticalEngineerM. Liang

Electrical Engineer

J. Penegor

Electrical Engineer

J. Penegor

Mechanical DesignersJ. AndrewD. Rosin

E. DowneyD. Circle

Mechanical DesignersJ. AndrewD. Rosin

E. DowneyD. Circle

ProgrammerR. Wolff

ProgrammerR. Wolff

Project AssistantD. Eklund (.5)

Project AssistantD. Eklund (.5)

Electrical TechR. George

Electrical TechR. George

Support ScientistsD. Joyce

B. Gregory

Support ScientistsD. Joyce

B. Gregory

Procurement & Vender Liaison

A. Davis

Procurement & Vender Liaison

A. Davis

ETSL. Daggert

ETSL. Daggert

General Technician

J. Pina

General Technician

J. Pina

ProgrammerP. Ruckle

ProgrammerP. Ruckle

Instrument Makers

J. AndrewJ. Stein

R. BennettL. LedererR. Davis

Instrument Makers

J. AndrewJ. Stein

R. BennettL. LedererR. Davis

M&PB. Ditsler

M&PB. Ditsler

Page 86: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

86

Quarterly ReviewOctober 5, 2001

Plans for Next Review• The next Quarterly Review will be held in the January 2002 timeframe• The project will be into the Integration Phase

– Alignment and testing will have begun

• Mechanical design will be complete– Some rework items as identified in integration may remain

• Mechanical fabrication will be complete– except for items associated with flexure testing and shipping container– Some rework items as identified in integration may remain

• Mechanism and optical subassembly testing should be completed• Electronics fabrication and checkout completed

– Some cables may remain to be fabricated– Some rework items as identified in integration may remain

• Component Controller Software completed and tested with the Electronics– EPICS level software will still be in work

• OIWFS components integration onto the OIWFS bench will be completed

Page 87: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

87

Quarterly ReviewOctober 5, 2001

Conclusions

• The current project status shows us to be over 80% complete

• We have re-planned integration to preserve fall 2002 delivery – We are on track to deliver in September 2002

• We are very near the end of the design phase

• We are nearing the end of the fabrication phase

• Mechanism testing has started

• The estimated cost of GNIRS is not significantly changed from the August ’99 baseline– Estimated total cost: $4,095,674 - January ’99 to delivery

Page 88: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

88

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 89: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

89

Quarterly ReviewOctober 5, 2001

Appendix A – ImagesAppendix B – Milestones,

WBS ChartAppendix C – Envelope Waiver

Page 90: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

90

Quarterly ReviewOctober 5, 2001

Appendix A

Configuration and

Fabrication Images

Page 91: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

91

Quarterly ReviewOctober 5, 2001

Connector Feedthrough Panel

Page 92: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

92

Quarterly ReviewOctober 5, 2001

Aft Bulkhead

Page 93: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

93

Quarterly ReviewOctober 5, 2001

Aft Bulkhead Weldment

Page 94: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

94

Quarterly ReviewOctober 5, 2001

Aft Dewar Shell Top End

Page 95: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

95

Quarterly ReviewOctober 5, 2001

Forward Dewar Shell Top End

Page 96: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

96

Quarterly ReviewOctober 5, 2001

Forward Bulkhead Weldment

Page 97: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

97

Quarterly ReviewOctober 5, 2001

Forward Bulkhead Weldment

Page 98: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

98

Quarterly ReviewOctober 5, 2001

Bench with Slit-Slide

Page 99: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

99

Quarterly ReviewOctober 5, 2001

Bench on Handling Cart

Page 100: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

100

Quarterly ReviewOctober 5, 2001

Bench with Assemblies

Page 101: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

101

Quarterly ReviewOctober 5, 2001

Bench with Camera Turret Spindle

Page 102: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

102

Quarterly ReviewOctober 5, 2001

Bench with Collimator Gimbal Mount Ring

Page 103: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

103

Quarterly ReviewOctober 5, 2001

Camera Barrel

Page 104: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

104

Quarterly ReviewOctober 5, 2001

Camera Barrel

Page 105: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

105

Quarterly ReviewOctober 5, 2001

Collimator

Page 106: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

106

Quarterly ReviewOctober 5, 2001

Foreoptics Bench

Page 107: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

107

Quarterly ReviewOctober 5, 2001

Foreoptics Bench

Page 108: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

108

Quarterly ReviewOctober 5, 2001

Acquisition Mirror

Page 109: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

109

Quarterly ReviewOctober 5, 2001

Slit-Slide

Page 110: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

110

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 111: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

111

Quarterly ReviewOctober 5, 2001

Appendix B

Milestones

WBS Chart

Page 112: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

112

Quarterly ReviewOctober 5, 2001

Milestones since MFR (3/01)5.4.1.2.5 Motor Drive / Cryohead Control Chassis Complete 8/29/00 4/9/01 4/9/015.3.1.8.2.6 Grating Turret Drafting Complete 6/7/00 4/10/01 4/10/015.3.3.9.1.5 Bulkhead Assembly Design Complete 9/26/00 4/10/01 4/10/015.3.1.2.2.2.4 Long Red Camera Drafting Complete 10/4/00 4/13/01 4/13/015.3.1.104.5 Motor Drive Assembly Complete 8/2/00 4/16/01 4/16/015.3.1.2.3.1.3 Long Blue Camera Design Complete 5/31/00 4/17/01 4/17/015.3.2.4.2.3.3 Offner Assembly Fabrication Complete 9/11/00 4/24/01 4/24/015.3.3.14.1.4 Vertical Installation Frame Assembly Design Complete 12/4/00 4/27/01 4/27/015.3.3.15.1.5 Horizontal Installation Frame Assembly Design Complete 12/5/00 4/27/01 4/27/015.3.3.17.1.5 Thermal Enclosure Mount Assembly Design Complete 1/23/01 4/30/01 4/30/015.3.3.19.4 Handling Fixtures Complete NA 5/18/01 5/18/015.3.2.3.3.2.4 Collimator Compensating Mount Design Complete NA 5/23/01 5/23/015.3.2.3.2.1.5 Collimator Cover Box Design Complete 5/5/00 5/30/01 5/30/015.3.3.13.1.5 Rear Dewar Shell Design Complete 3/29/01 5/31/01 5/31/015.3.3.9.2.6 Bulkhead AssemblyDrafting Complete 2/21/01 6/1/01 6/1/015.3.1.8.6.4 Grating Fabrication Complete 11/28/00 6/1/01 6/1/015.3.3.12.1.5 Front Dewar Shell Design Complete 2/26/01 6/1/01 6/1/015.3.3.6.1.3 LN2 Pre-Cool Assemby Design Complete 11/16/00 6/6/01 6/6/015.3.1.2.3.2.4 Long Blue Camera Drafting Complete 11/27/00 6/6/01 6/6/015.3.3.17.2.6 Thermal Enclosure Mount Assembly Drafting Complete 3/14/01 6/8/01 6/8/015.3.2.3.2.2.4 Collimator Cover Box Drafting Complete 8/7/00 6/11/01 6/11/015.3.1.7.3.2 Filter Wheel Assembly Fabrication Complete 1/10/01 6/11/01 6/11/015.3.3.3.1.4 Cryo Cooler Design Complete 9/26/00 6/12/01 6/12/015.3.3.2.2.4 Detector Mount Assembly Drafting Complete 1/4/01 6/15/01 6/15/015.3.3.12.2.6 Front Dewar Shell Drafting Complete 3/16/01 6/19/01 6/19/015.3.2.1.8.3.2 Bottom Camera Cover Fabrication Complete 7/21/00 6/25/01 6/25/015.3.2.1.8.4.4 Bottom Camera Cover Complete 7/26/00 6/28/01 6/28/015.3.3.13.2.6 Rear Dewar Shell Drafting Complete NA 6/28/01 6/28/015.3.1.6.5.3.2 Slit/Decker Assembly Fabrication Complete 3/5/01 6/29/01 6/29/015.3.2.1.6.3.2 LCFMH Fabrication Complete 8/1/00 6/29/01 6/29/015.8.1.3.1 Flat Mirrors Acceptance 6/2/00 6/29/01 6/29/015.3.1.3.2.4 Detector Focus Assembly Drafting Complete 1/26/01 7/2/01 7/2/015.3.2.2.3.1 Receive and Inspect IFA WFS electronics 9/5/00 6/29/01 7/3/015.3.1.2.6.3.4 Camera Hub Fabrication Complete 12/4/00 7/5/01 7/5/015.3.2.1.6.4.4 LCFMH Complete 8/4/00 7/5/01 7/5/015.3.2.4.2.4.4 Offner Assembly Complete 9/22/00 7/16/01 7/16/015.3.2.3.3.3.4 Collimator Compensating Mount Drafting Complete NA 7/19/01 7/19/015.3.3.3.2.4 Cryo Cooler Drafting Complete 11/21/00 7/23/01 7/23/015.3.3.7.3.2 Optical Bench Mount Assembly Fabrication Complete 5/3/01 7/23/01 7/23/015.3.3.6.2.4 LN2 Pre-Cool Assemby Drafting Complete 12/7/00 7/25/01 7/25/015.3.2.3.1.3.3 CollimatorHousing Fabrication Complete 2/13/01 7/25/01 7/25/015.3.2.1.3.3 Post-Slit Bench Fabrication Complete 11/20/00 7/30/01 7/30/015.3.2.2.1.3.4 OIWFS Assembly Fabrication Complete 11/30/00 7/31/01 7/31/015.3.3.7.4.4 Optical Bench Mount Assembly Complete 5/21/01 8/9/01 8/9/015.3.2.3.2.3.2 Collimator Cover Box Fabrication Complete 8/8/00 8/17/01 8/17/015.3.2.1.7.3.2 Top Camera Cover Fabrication Complete 7/19/00 8/17/01 8/17/015.3.3.2.3.5 Detector Mount Assembly Fabrication Complete 2/22/01 8/22/01 8/22/015.3.2.1.7.4.4 Top Camera Cover Assembly Complete 7/24/00 8/22/01 8/22/01

Page 113: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

113

Quarterly ReviewOctober 5, 2001

WBS - Total Project

Page 114: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

114

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 115: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

115

Quarterly ReviewOctober 5, 2001

Appendix C

Envelope Waiver

Page 116: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

116

Quarterly ReviewOctober 5, 2001

This Page Intentionally Left Blank

Page 117: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

117

Quarterly ReviewOctober 5, 2001

Envelope Waiver

Supplemental Envelope Waiver Request

 

This request supplements our May 2001 envelope waiver request. It details some additional minor envelope violations due to routing of the high-pressure helium lines and other connections. The violations are indicated in the figures below, and described in more detail afterward.

This waiver request has been granted via e-mail as of September 27 by Doug Simons.

Page 118: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

118

Quarterly ReviewOctober 5, 2001

Figure 1. Summary of GNIRS envelope violations, include those previously approved by Gemini. The Gemini instrument envelope is shown overlaid on the instrument itself.

Page 119: Quarterly Review October 5, 2001 1 QUARTERLY REVIEW October 5, 2001

119

Quarterly ReviewOctober 5, 2001

There are four areas where the helium lines violate the envelope:

The first location is at the bottom of the instrument, where the lines and manifold protrude approximately 66 mm outside the envelope. Although the instrument "feet" extend still further (92 mm), they can be removed if required. The footprint of the hoses is also much smaller, and we believe that it should be possible to miss them, even when the instrument is mounted up-looking and it is necessary to access the side-looking instrument located immediately above.

Hose loops from the forward cryoheads protrude outside the instrument in two locations (either side). The protrusion is about 100 mm in depth and roughly twice that in length, as indicated in the figure.

We are providing a connector panel at the instrument. All cables and hoses that run to the Gemini connector panel on the rotator would run from this instrument panel, facilitating installation of the instrument. However, the panel also protrudes outside the envelope, by a maximum of ~120 mm. The panel runs about half the height of the instrument, so there is still good access to the corners of the ISS cube, where GNIRS will be attached.