quarterly activities report june 2019 june 2019 quarter ...€¦ · asx / media announcement asx:...

32
ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 1 / 27 Capital Structure Ordinary Shares 505,700,000 Unlisted Options ($0.25-$1.99) 115,000,000 (av. price $0.44/share) Board Rob McDonald Indept. Chairman Patrick Walta Managing Director Bryn Hardcastle Non Exec. Director Nick Cernotta Indept. Non Exec. Director Peter Watson Indept. Non Exec. Director Evan Cranston Non Exec. Director Oonagh Malone Company Secretary Media Enquiries Shane Goodwin Head of Corporate Affairs [email protected] +61 434 039 106 June 2019 Quarter Executive Summary Production New Century continues to make steady progress in the ramp up of its Century Zinc Mine. Quarter-on-quarter zinc production continues to rise, up a further 12% in the June 2019 quarter to 20,450t zinc metal. Recoveries The Company achieved highly satisfactory recoveries following the initial commissioning of cleaner circuit 1B, with recoveries up to 55% recorded at a 6Mtpa throughput rate during April. New Century does however continue to be hampered by slower than expected operational ramp up. Additional throughput from commissioning of the 3 rd hydraulic mining cannon in May resulted in a bottleneck through cleaner 2A, significantly impacting overall plant recoveries. Improved performance since May has resulted in operations achieving recoveries of up to 48% at the expanded 8Mtpa throughput rate. July operations are on track for a new record month of production and a monthly average recovery expected in the mid-40s. The recovery bottleneck is due for imminent removal via the commissioning of cleaner 2B, scheduled to be online early August 2019, allowing further recovery optimisation. Cashflow Management Capital burn continues, albeit at a very low rate after factoring in development capital and exploration. Whilst net cash used during the quarter totalled $16.1M, this included one-off expansion capital charges of $11M, exploration spend of ~ $1M and annual sustaining capital charges of $2.6M. Adjusting for these charges, the net operational cash burn was only ~$1.6M. Given ~70% of total operating costs are fixed, there is a clear pathway to a significant increase in cash generation as production volumes are increased. The final clear area for economic improvement remains treatment charges, which have recently peaked at 10-year highs of US$280/t and are expected to trend back down toward the long term average of US$127/t.

Upload: others

Post on 28-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

ASX / MEDIA ANNOUNCEMENT ASX: NCZ

Quarterly Activities Report June 2019

Office Level 4, 360 Collins Street, Melbourne VIC 3000 Phone +61 (3) 9070 3300 Email [email protected] Website www.newcenturyresources.com 1 / 27

Capital Structure

Ordinary Shares

505,700,000

Unlisted Options ($0.25-$1.99)

115,000,000 (av. price $0.44/share)

Board

Rob McDonald Indept. Chairman

Patrick Walta Managing Director

Bryn Hardcastle Non Exec. Director

Nick Cernotta Indept. Non Exec. Director

Peter Watson Indept. Non Exec. Director

Evan Cranston Non Exec. Director

Oonagh Malone Company Secretary

Media Enquiries

Shane Goodwin

Head of Corporate Affairs

[email protected]

+61 434 039 106

June 2019 Quarter Executive Summary

Production

New Century continues to make steady progress in the ramp up

of its Century Zinc Mine. Quarter-on-quarter zinc production

continues to rise, up a further 12% in the June 2019 quarter to

20,450t zinc metal.

Recoveries

The Company achieved highly satisfactory recoveries following

the initial commissioning of cleaner circuit 1B, with recoveries

up to 55% recorded at a 6Mtpa throughput rate during April.

New Century does however continue to be hampered by slower

than expected operational ramp up. Additional throughput from

commissioning of the 3rd hydraulic mining cannon in May

resulted in a bottleneck through cleaner 2A, significantly

impacting overall plant recoveries.

Improved performance since May has resulted in operations

achieving recoveries of up to 48% at the expanded 8Mtpa

throughput rate. July operations are on track for a new record

month of production and a monthly average recovery expected

in the mid-40s.

The recovery bottleneck is due for imminent removal via the

commissioning of cleaner 2B, scheduled to be online early

August 2019, allowing further recovery optimisation.

Cashflow Management

Capital burn continues, albeit at a very low rate after factoring

in development capital and exploration. Whilst net cash used

during the quarter totalled $16.1M, this included one-off

expansion capital charges of $11M, exploration spend of ~ $1M

and annual sustaining capital charges of $2.6M. Adjusting for

these charges, the net operational cash burn was only

~$1.6M. Given ~70% of total operating costs are fixed, there is

a clear pathway to a significant increase in cash generation as

production volumes are increased.

The final clear area for economic improvement remains

treatment charges, which have recently peaked at 10-year highs

of US$280/t and are expected to trend back down toward the

long term average of US$127/t.

Page 2: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

2 / 27

New Century closed the quarter with A$40M in cash and receivables, the A$60M Varde senior

secured debt facility fully drawn, and a A$40M Varde junior facility undrawn but remaining subject

to pre-conditions. The Company is progressing achievement of these conditions for the junior

facility in the near term.

Current cash and short term receivables position as at 30 July 2019 is A$27.0M (made up of A$13.3M

in cash and A$13.7M in shipment invoices due imminently), with the cash position lower than 30

June 2019 due to intra quarter working capital fluctuations and outflows against expansion and

sustaining capital spend.

In addition, the Company holds A$12.3M in restricted cash currently being used for cash backed

bonding requirements associated with financial assurance and power generation contracts.

Key Board & Management Additions

New Century completed two key hires during the quarter. Rob McDonald has been appointed as

Chairman and Mark Chamberlain as CFO. The appointment of high calibre personnel in Rob and

Mark is representative of New Century’s continued growth as a business.

Forward Quarter Guidance

New Century maintains its September 2019 quarter guidance of 23,000t to 29,000t zinc metal and

C1 cash costs of US$0.95/lb to US$1.07/lb.

June 2019 Quarter Highlights

Processing Plant Performance

• Record quarterly zinc metal production, with June 2019 quarter totalling 20,450t (vs 18,170t in March 2019 quarter – 12% increase quarter-on-quarter)

• Progressive recovery ramp up to 55% (at 6Mtpa, two cannons) achieved to date

• Ramp up to 8Mtpa (three cannons) generated a recovery bottleneck through cleaner 2A (removed via commissioning of cleaner 2B, doubling overall cleaner 2 capacity)

• Imminent implementation of full cleaning circuit (cleaner 2B-4B online early August 2019), allowing for both efficient 8-9Mtpa operations and capacity for up to 12Mtpa

• Improved recovery performance through July 2019 (results up to 48%) and monthly average recoveries expected in the mid-40s

• July 2019 operations on track for a new record month of production

Quarterly Cashflow Performance

• A$50.0M in receipts from customers during the June quarter (vs A$48.6M March quarter), below expectation due to an 18% decrease in zinc price over the period

Page 3: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

3 / 27

• Improving market conditions forecast to allow a reduction in treatment charges and increased overall profitability from concentrate production

• Quarterly direct production expenditure of A$44.1M, in line with expectations

• Quarterly expenditure of one-off expansion capital totalling A$11.0M

• Quarterly expenditure on sustaining capital totalling A$2.65M

Overall Performance Guidance

• September 2019 quarter guidance maintained at 23,000t – 29,000t zinc metal & C1 Costs of US$0.95/lb – US$1.07/lb (payable metal inc. treatment charges)

• Century operations to double plant capacity over FY20 through refurbishment of the second train of flotation cells

• Plant capacity expansion to assist driving down C1 Costs to a LOM average target of US$0.56/lb (tailings only operations)

• New Century on track to become a top 10 zinc producer over the next 12 months through completion of plant refurbishment process

Quarterly Hydraulic Mining Performance

• Third mining cannon online & now delivering ~8Mtpa mining rate

• Continued strong reconciliation of mining grade to the ore reserve model, with the ore grade mined during the June 2019 quarter averaging 2.92% Zn

• New Century is targeting ramp up to a 12Mtpa mining rate in FY20 in line with additional plant capacity and addition of a 4th mining cannon

Quarterly Shipping & Sales Performance

• Milestone 100,000t of zinc concentrate shipments (China, Europe & Australia) since the commencement of operations achieved during the June quarter

• Average impurity penalties and treatment charges continue to be maintained in line with standard market pricing and remain competitive with other miners

• Current 10-year high concentrate treatment charges now falling, in response to increasing smelter utilisation in China

• Execution of a new long-term offtake contract with a large zinc smelting group & expansion of existing offtake contract with Concord Resources

Page 4: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

4 / 27

Figure 1: Century’s quarterly metal production performance and annualised mining rate

Figure 2: Century’s average daily metal production ramp up & average monthly zinc recovery trend

Board & Management Changes

• Appointment of Rob McDonald as Chairman of the Board

• Appointment of Mark Chamberlain to the position of Chief Financial Officer

0

1

2

3

4

5

6

7

8

-

5,000

10,000

15,000

20,000

25,000

30,000

Q1 FY19 Q2 FY19 Q3 FY19 Q4 FY19 Q1 FY20

Annualised Mining Rate (Mtpa)

Zinc Metal Production (t)

Zinc Metal Production Annualised Mining Rate (Mtpa)

20

25

30

35

40

45

50

55

60

-

50

100

150

200

250

300

Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19

Zinc Recovery (%)

Zinc Metal Production (t/operating day)

Av. Daily Zn Metal Production (t) Zinc Recovery (%)

Q1 FY19 Q2 FY19 Q3 FY19 Q4 FY19

Page 5: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

5 / 27

Exploration Highlights

• Kick off of initial exploration drilling work for 2019, focused on the assessment of high potential targets on the Century mining lease

• Three hole scouting program completed, successfully defining the regional setting for potential large scale dislocated blocks of the original Big Zinc ore body to the north of the open pit

• Detailed modelling underway and follow up targeted drilling being planned

In-situ Resource Expansion Study Delivered

• Metal Production: Projected LOM average 233ktpa zinc and 29ktpa lead (in concentrates) & total silver production up to 18.9Moz in zinc and lead concentrates

• Cash Flow: Combined operations have the potential to generate over A$1,500M in after-tax free cash flow based on updated analyst zinc pricing and TC projections

• Mine Life: Development of Century in-situ operations in addition to existing tailings operations to provide an increase in mine life, now totalling 7 years to mid-2026

• Capex: Improved capital expenditure profile, with the ramp up to revised full tailings operational capacity of 12Mtpa reducing by 34% to A$40M

• Opex: Attractive overall projected operating costs (average life-of-mine C1 cost):

Figure 3: Average life-of-mine C1 cost projections for development of tailings and in-situ resources based on

parameters used in the In-situ Expansion Study

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

2020 2021 2022 2023 2024 2025 2026

C1 C

ost

, U

SD$/l

b p

ayable

Zn

Financial Year

12Mtpa Tailings 10Mtpa Tailings + SB/EFB 10Mtpa Tailings + SB/EFB + SK

Page 6: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

6 / 27

• Earnings: Strong estimated EBITDA profile from combined tailings & in-situ ops:

Figure 4: Estimated EBITDA projections for tailings only and combined tails/in-situ operations based on

parameters used in the In-situ Expansion Study

0

100

200

300

400

500

600

2020 2021 2022 2023 2024 2025 2026

EBIT

DA

, A

$M

Financial Year

12Mtpa Tailings 10Mtpa Tailings + SB-EFB 10Mtpa Tailings + SB-EFB + SK

Page 7: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

7 / 27

Operational Developments

Overall Production & Cost Guidance

During the quarter the Company released its first forward quarter guidance:

Table 1: Century’s forward quarter C1 cost and metal production guidance

Guidance Period Zinc Metal Production Range C1 Cost Range

Sep 19 Q 23,000t – 29,000t US$0.95/lb – US$1.07/lb

Throughout FY20 the Company will focus on completing the refurbishment of existing idle plant,

enabling a doubling of processing capacity as mining rate increases to 12Mtpa.

New Century maintains a competitive advantage over other zinc producers in its ability to leverage

a proportionally high percentage fixed cost base (~70% of site costs are fixed). Increasing metal

production via the continued refurbishment of existing idle plant allows efficient use of this fixed

cost base and the ability for the Company to materially reduce C1 costs whilst increasing EBITDA.

The Company is targeting progressive lowering of C1 costs to an overall LOM average of US$0.56/lb.

The operations are also on track to become a top 10 zinc producer through the completion of the

plant refurbishment process.

Figure 5: Century’s quarterly C1 cost trend (including TCs) against the zinc price

0.00

0.25

0.50

0.75

1.00

1.25

1.50

1.75

Q1 FY19 Q2 FY19 Q3 FY19 Q4 FY19 Q1 FY20

US$/lb

TC Component of C1 C1 Costs Zinc Price

LOM C1 Cost

Target

Page 8: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

8 / 27

Quarterly Cashflow Performance

Table 2 provides an extract from the Company’s Appendix 5B (Quarterly Financial Report) reported

in conjunction with this Quarterly Activities Report. Further commentary on individual items within

Table 2 is provided below.

Table 2: Extract of the Quarterly Financial Report including applicable details of each expenditure

Consolidated statement of cash flows Jun Q

$A’000 Details

1. Cash flows from op. activities

1.1 Receipts from customers

50,011

Below expectations primarily due to quarterly zinc price

decline (18%) and 10-year high concentrate treatment

charges - See Figure 6

1.2 Payments for

(a) exploration & evaluation (946) In line with expectations

(b) development

(57,681)

Quarterly Costs:

(44,056) Production costs (in line with expectations)

Annual Costs:

(1,901) Sustaining capex – dredging initial costs

(749) Native title payments

One Off Costs:

(9,491) Expansionary capex

(1,484) Sust. Capex inc Wunma 5-yr survey initial costs

(c) production - -

(d) staff costs (3,975) In line with expectations

(e) administration and corporate costs (2,292) In line with expectations

1.3 Dividends received - -

1.4 Interest received 123 In line with expectations

1.5 Interest and other costs of finance paid (720) In line with expectations

1.6 Income taxes paid - -

1.7 Research and development refunds - -

1.8 Other (MMG support fees) (652) In line with expectations

1.9 Net cash from / (used in) op. activities (16,132)

Receipts from Customers & Treatment Charges

As detailed in Table 2, during the June quarter the operations generated total receipts from

customers of A$50.0M. Despite increasing metal production, receipts from customers were only

marginally higher than the March quarter due to an 18% fall in the zinc price.

Page 9: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

9 / 27

Receipts from customers were also adversely affected by the current 10-year high concentrate

treatment charges in the zinc market. A waterfall chart (Figure 6) detailing the development of

Century’s receipts from customers for the June 2019 quarter is provided below, showing the strong

negative effect the current treatment charges have on overall profitability of production.

Figure 6: Waterfall chart showing the progressive development of receipts from customers for the June quarter

(*Conc. receivables represents the difference between provisional invoices and projected future final invoices

that are obtained on completion of shipments)

Figure 7: Spot concentrate treatment changes over the last 10 years

$0

$50

$100

$150

$200

$250

$300

TC per tonne of conc. (US$)

Spot TC Av. Spot TC

Av. 10 yr spot TC US$127/t

Spot TCs have peaked

& now trending down

from 10 year highs

(~US$280/t)

Page 10: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

10 / 27

As shown in Figure 7, treatment charges have increased ~500% since the start of Century operations

in September 2018. However, based on analyst reports and direct market interactions, spot

treatment charges are believed to have peaked and are trending down, providing more favourable

market conditions for Century operations going forward.

The reduction in treatment charges is predominately due to increased Chinese smelter utilisation

rates, which approximately two years ago were significantly reduced due to new domestic

environmental regulations. These regulations forced the suspension or shutdown of many smelters

in China until refurbishment or rebuilding activities were complete. With these smelters now

completing this process and coming back online, treatment charges have begun to retreat from

their 10-year highs.

The reduction of treatment charges going forward improves economic returns for Century

operations via increased receipts from customers and reduced C1 costs (outside of progressive

increase in quarterly metal production). By way of example, treatment charges reverting back to

a 10 year average (~US$127/t) reduces the C1 costs of Century operations by approximately

US$0.15/lb and would add ~A$10M in additional earnings on Century’s June 2019 quarter

operational performance alone.

Expansion & Sustaining Capital Expenditure

The Company continues to invest in the plant refurbishment and ramp up process, with one-off

capital items totalling A$10.9M during the June quarter, divided into both expansion and sustaining

capital. One-off expansion capital items were predominately associated with completion of the

initial expansion phase to 8Mtpa (including final costs associated with the commissioning of cleaner

1B, plant wide launder spray and reagent dosing line upgrades, front end density stability initiatives

and contractor payments associated with the initial restart of operations). One-off sustaining

capital items were predominately associated with initial dredging costs as well as initial costs of

the 5-yearly refurbishment (survey) of the Wunma.

One-off expansion capital items associated with the development of Century operations are

expected to be completed over the course of FY20 in line with the completion of the ramp up

process. This will enable the growing EBITDA profile of the operations to flow through to free cash

flow generation (see quarterly production costs vs receipts from customers in Table 2).

Over the quarter the Company also incurred annual sustaining capital items totalling A$2.65M,

primarily associated with dredging costs and native title payments.

Cashflow

Total cash burn for the quarter was A$16.1M, however net of capital items and exploration the

outflows were only A$1.6M.

Given ~70% of total operating costs are fixed, there is a clear pathway to a significant increase in

cash generation as production volumes are increased.

Page 11: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

11 / 27

Quarterly Processing Plant Performance

• Production of 20,450t zinc-in-concentrate in the June quarter (12% increase on March quarter)

• Successful achievement of recoveries up to 55% at a 6Mtpa mining rate (two cannons)

• Expansion to three cannons highlighted a bottleneck in cleaner 2A, with initiatives well

advanced to remove the bottleneck, allowing for efficient operations up to 9Mtpa

• Entire cleaning circuit on schedule to be online in early August 2019, providing sufficient

cleaner capacity for 12Mtpa operations

• Continued plant refurbishment activities scheduled to double plant capacity through FY20

• July operations on track to be a further record month of production, with increased recovery

performance (results up to 48%) since May & monthly average expected in the mid-40s and

continuing to improve in line with expanding cleaner circuit capacity

During the quarter the Company continued the ramp up of the Century Zinc Mine operations. Overall

zinc metal output increased by 12% during the June quarter, with 20,450t of zinc metal produced

in 42,500t of concentrate grading 48.1% zinc (vs 37,500t at 48.3% zinc during the March quarter).

Silver content of 150g/t in concentrate remained in line with previous quarter operations.

Early April operations achieved up to 55% recovery at a 6Mtpa mining rate (two cannons online).

However, overall quarterly recovery performance was hampered in late April and May by instability

during commissioning of throughput expansion under three cannon operations (6Mtpa to 8Mtpa) and

identification of a bottleneck through cleaner 2A. Importantly, the operations achieved a strong

exit rate to the quarter, with the recovery growth trend re-established during June and results up

to 48% recovery achieved in July to date.

Cleaner 2B is scheduled to be online in early August (see Figures 8, 9 & 14), removing the identified

bottleneck and doubling capacity through this section of the plant for efficient 8-9Mtpa operations.

Further, the remainder of the cleaner circuit (cleaners 3B and 4B) will also be brought online in

August, providing cleaning capacity for eventual ramp up to 12Mtpa. A total of 44% additional

cleaner capacity is scheduled to come online as part of the continued plant refurbishment process.

Overall, June quarter recovery was in line with the March quarter (44% June Q vs 45% March Q).

Table 3: Quarterly processing plant performance at Century

Processing Performance

Concentrate Grade Zinc Metal

Dec 18 Q 25,500t 47.0% Zn 12,080t

Mar 19 Q 37,500t 48.3% Zn 18,170t

Jun 19 Q 42,500t 48.1% Zn 20,450t

Q-on-Q Difference +12% - +12%

Concentrate quality was also maintained in line with previous quarter performance (4-6% lead and

5-7.5% silica). Century concentrate continues to deliver low levels of typical penalty elements

common in other zinc concentrates such as iron, manganese, cadmium, mercury and arsenic.

Page 12: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

12 / 27

Century also remains a low jarosite forming zinc concentrate (jarosite formation during smelting

being a major component of recent environmental restrictions placed on Chinese zinc smelters).

New Century is targeting continued plant refurbishment (currently 55% online) and expansion to

full plant capacity during FY20, providing the ability progress to 12Mtpa operations in line with

additional hydraulic mining throughput (see Figure 14).

Figures 8 & 9: Water and air commissioning of cleaner 4B (left) & commissioning of new reagent dosing stations

on cleaner 3B (right) in readiness for early August operations of the full cleaner circuit

Figures 10 & 11: Full plant reagent dosing line upgrade complete and operational (left) & ball mill cyclone packs

upgraded (right) as part of the progressive plant optimisation process

Page 13: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

13 / 27

Figure 12: Century’s plant ramp recovery ramp up showing steadily climbing recoveries up to 55% (with a target

62%) achieved to date, and the recovery bottleneck generated by throughput expansion (bottleneck due for

imminent removal via commissioning of the entire cleaning circuit in early August 2019)

Figure 13: Simplified plant plan view and scheduled refurbishment process for expansion to 12Mtpa

Zn Roughers Zn Scavengers

Zn Scavengers

Ball M

ill 03

Ball Mill 02

SAG M

ill

Zn Cleaner 1A

Zn Cleaner 1B

Zn Cleaner 2A Zn Cleaner

3A Zn Clnr 4A

Zn Cleaner 2B Zn Cleaner

3B Zn Clnr

4B

UFMs

Operational

To be Recommissioned

Legend:

Not under refurbishment

Stage 1 August 2019: Bringing cleaner 2B online removes bottleneck for efficient 8-9Mtpa operations, 3B and 4B for future 12Mtpa expansion

Stage 2 November 2019: Additional scavenger flotation capacity online for further increased recoveries and/or throughput

Zn Roughers

Stage 3 March 2020: Commissioning 2nd rougher train allows expansion

to 12Mtpa in conjunction with fourth mining cannon

Page 14: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

14 / 27

Quarterly Hydraulic Mining Performance

• Hydraulic mining expansion to three cannon operations, now achieving ~8Mtpa mining rate

• Mining grades reconciling strongly with ore reserve model, averaging 2.92% Zn as expected

• Mining of 1.60Mt in the June 2019 quarter (vs 1.39Mt in the March 2019 quarter)

During the quarter the Company focused on the expansion to three hydraulic mining cannons. The

third cannon and associated infrastructure was commissioned and fully operational from May, with

the average mining rate increasing 15% quarter-on-quarter (1.60Mt June Q vs 1.39Mt March Q).

Average mined grade during the quarter was 2.92% Zn, which continues to reconcile strongly with

the Ore Reserve model and mine plan.

The operations are now achieving ~8Mtpa throughput, with capacity for up to 9Mtpa. New Century

is targeting ramp up in hydraulic mining capacity to 12Mtpa (over FY20) once steady state recoveries

approaching nameplate have been established for the current mining rate.

The Company is focused on ensuring no further recovery performance interruptions during the

12Mtpa ramp up. This is to be achieved via a structured refurbishment process of initially the full

cleaner (online early August 2019) and scavenger (online November 2019) circuits, prior to addition

of a 4th mining cannon with the expanded rougher circuit (online March 2020). See Figure 12.

Approximately 6% of the overall tailings Ore Reserve has been mined to date.

Table 4: Quarterly mining performance at Century

Mining Performance

Mining Rate Mined Grade Cannons in Use

Dec 18 Q 1.50Mt 2.95% Zn 2

Mar 19 Q 1.39Mt 2.92% Zn 2

Jun 19 Q 1.60Mt 2.92% Zn 2 (3rd online May)

Q-on-Q Difference +15% - -

Figure 14: Hydraulic mining operations to date at the Century Zinc Mine

Page 15: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

15 / 27

Quarterly Shipping & Sales Performance

• Milestone 100,000t of zinc concentrate shipments (China, Europe & Australia) achieved during

the June quarter

• Average impurity penalty and treatment charges incurred by New Century continue to be

maintained in line with standard market pricing and remain competitive with other miners

• Current 10-year high spot treatment charges anticipated to fall, in line with increasing smelter

utilisation in China

• Execution of a new long-term offtake contract with a large zinc smelting group & expansion of

existing offtake contract with Concord Resources, replacing lapsed offtakes with Mercuria and

Transamine

During the quarter the Company continued to maintain shipping rates in line with monthly

production. All production has been sold to date, with a milestone achievement of the first 100,000t

of zinc concentrate produced and shipped from the operations. Concentrate has been shipped to

smelters in China, Europe and Australia.

Figure 15: Century zinc concentrate shipments to date

As with previous quarters, New Century’s concentrate impurity penalty rate and treatment charges

remain in line with standard market pricing and are also competitive with other global zinc miners.

Page 16: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

16 / 27

During the quarter, New Century executed a new long-term offtake contract with one of the largest

zinc smelting groups in the world, with both mining and smelting assets. The offtake, while initially

minor in scale and subject to completion of the first shipment, represents New Century’s second

offtake contract directly with a smelting group.

In addition, and following the successful completion of initial shipments, the existing long-term

offtake contract with Concord Resources has also been expanded.

Details of each contract remain confidential, however the terms are market competitive with

treatment charges linked to a percentage of the annual benchmark price.

First shipments under the new/expanded long-term contracts are in progress.

New Century continues to progress toward a target of delivering production into majority (up to

80%) long term contract arrangements as opposed to majority spot contract sales. The Company

has elected to use the new/expanded agreements to replace previously allocated tonnage with

Transamine and Mercuria, whose long-term contracts have lapsed as they were yet to achieve the

original contracted steady state specification.

The Company maintains an active commercial relationship with both Mercuria and Transamine for

spot contract shipments as required, having received tender bids for and executed spot sale

shipments with these groups to date.

Page 17: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

17 / 27

In-situ Expansion Study Completed

During the quarter the Company released the In-situ Expansion Study, which investigated the

incorporation of Century’s in-situ Mineral Resources into the current tailings only mine plan.

Figure 16: Overview of existing Reserves & Resources at the Century Zinc Mine

The full details of the In-situ Expansion Study are provided in the ASX release dated 25 June 2019,

however summary technical and financial projections and overall project highlights are below. The

Company confirms that all material assumptions underpinning the production targets and forecast

financial information derived from those production targets in the Expansion Study announcement

continue to apply and have not materially changed.

While the Study has highlighted robust potential of the existing Mineral Resources at Century, the

Company remains fully committed to the ramp up of its tailings operations during the course of

FY20.

Development of in-situ resources remains contingent on completion of a Bankable Feasibility Study

(BFS) and board consideration of a decision to mine. The BFS is targeted for completion in Q4 FY20.

The Company does not anticipate any material capital costs associated with the development of in-

situ operations being incurred during FY20.

Page 18: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

18 / 27

In-situ Resource Expansion Study Highlights

• Strong production potential (10Mtpa tailings + 2Mtpa in-situ model):

� Zinc production LOM average of 233ktpa zinc-in-concentrate including ramp up period (total production 1,630kt) from both tailings and in-situ deposits

� Lead production LOM average of 29ktpa lead-in-concentrate including ramp up period (total production 159kt) from in-situ deposits

� Total silver production of up to 18.9Moz in zinc and lead concentrates

• Excellent overall in-situ project economics (in addition to tailings operations):

� A$422M in additional after tax free cashflow; and

� A$268M in additional overall Century operations NPV (after tax)

� Combined operations have the potential to generate over A$1,500M in after-tax free cash flow based on updated analyst consensus zinc pricing and TC projections

• Strong estimated EBITDA profile from combined tailings and in-situ operations:

Figure 17: Average life-of-mine C1 cost projections for development of tailings and in-situ resources based on

parameters used in the In-situ Expansion Study

• Attractive overall operating costs (average life-of-mine C1 cost projections):

� Case 1: Current tailings only operations (ramping up to 12Mtpa) LOM C1 costs of US$0.56/lb Zn including ramp up

� Case 2: Combined tailings (10Mtpa) and South Block & East Fault Block operations (2Mtpa) LOM average C1 costs of US$0.55/lb Zn including ramp up, with in-situ mining and processing costs offset by lead & silver credits

� Case 3: Combined tailings (10Mtpa) and all in-situ deposit operations (2Mtpa) LOM average C1 costs of US$0.50/lb including ramp up, with in-situ mining and processing costs offset by lead & silver credits

0

100

200

300

400

500

600

2020 2021 2022 2023 2024 2025 2026

EBIT

DA

, A

$M

Financial Year

12Mtpa Tailings 10Mtpa Tailings + SB-EFB 10Mtpa Tailings + SB-EFB + SK

Page 19: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

19 / 27

Figure 18: Estimated EBITDA projections for tailings only and combined tails/in-situ operations based on

parameters used in the In-situ Expansion Study

• Improved capital expenditure profile:

� Case 1: Current tailings only operations (ramping up to 12Mtpa): A$40M capex, to be incurred over FY20

� Case 2: Capex estimate for South Block / East Fault Block deposits estimated at A$55M (in addition to Case 1 capital), spread over ~2 years from decision to mine

� Case 3: Capital estimate for development of all in-situ deposits estimated at A$97M (in addition to Case 1 capital)

• Mine life extension:

� Development of Century in-situ operations in addition to existing tailings operations to provide an increase in mine life, now totalling 7 years to mid-2026

� Silver King extension potential, with the ore body remaining open along a structurally controlled strike with multiple drilling hits outside of the existing resource

� Watson’s Lode resource potential, with the mineralisation at this target to be assessed for further drilling and resource definition

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

2020 2021 2022 2023 2024 2025 2026

C1 C

ost

, U

SD$/l

b p

ayable

Zn

Financial Year

12Mtpa Tailings 10Mtpa Tailings + SB/EFB 10Mtpa Tailings + SB/EFB + SK

Page 20: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

20 / 27

Table 5: Expansion Study Technical Summary (see table notes below)

Table 1 Notes:

1. For further details on projected annual production figures for all products see the In-situ Expansion Study Announcement

2. Average metal grades based on life of mine material reporting to the processing plant

3. Average recoveries based on steady state operations exclusive of ramp up

4. Zinc concentrate from all deposits to be combined (in-situ and tailings initially processed via separate existing zinc rougher circuits, followed by combined feed for

the zinc scavenger and zinc cleaner circuits)

5. Lead concentrate from all in-situ deposits to be combined and processed through the existing individual lead rougher/scavenger and cleaning circuits), In-situ

Expansion Study Announcement

6. Strip ratio for South Block / East Fault Block open pits only

Approximate Technical Parameters – Life-of-Mine

Units 12 Mtpa Tailings 10Mtpa Tailings + South Block / East Fault Block

10Mtpa Tailings + South Block / East Fault Block +

Silver King

Mine Life (from 01 July 2019) - 7 years (through to mid-2026)

Estimated Start Date - In Operation 1H CY2021

Mining1

Tailings - Ore Mined Mt 72.3 72.3 72.3

Tailings - Waste Mined Mt 0 0 0

In-situ - Ore Mined Mt - 7.7 9.3

In-situ - Waste Mined Mt - 62.2 62.8

Open Pit Strip Ratio6 - - 8.1 8.1

Processing

Tailings - Av. Zinc Grade2 % 3.0% 3.0% 3.0%

Tailings - Av. Lead Grade2 % 0.6% 0.6% 0.6%

Tailings - Av. Silver Grade2 g/t 12 12 12

In-situ - Av. Zinc Grade2 % - 4.8% 5.0%

In-situ - Av. Lead Grade2 % - 1.2% 4.3%

In-situ - Av. Silver Grade2 g/t - 39 54

Tailings - Zinc Recovery3 % 62% 62% 62%

Tailings - Lead Recovery3 % - - -

Tailings - Silver Recovery3 % 43% 43% 43%

In-situ - Zinc Recovery3 % - 75% 76%

In-situ - Lead Recovery3 % - 68% 71%

In-situ - Silver Recovery3 % - 65% 69%

Production1

Zinc Metal Recovered kt 1,293 1,563 1,630

Lead Metal Recovered kt - 63 159

Silver Metal Recovered kOz 11,876 17,488 18,909

Zinc Concentrate Grade4 % 49% 50% 50%

Silver in Zn Conc. Grade4 g/t 140 160 160

Lead Concentrate Grade5 % - 68% 69%

Silver in Pb Conc. Grade5 g/t - 350 510

Zinc Concentrate Production kt 2,639 3,126 3,261

Lead Concentrate Production kt - 93 230

Page 21: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

21 / 27

Table 6: Expansion Study Financial Summary (see table notes below)

Table 2 Notes:

1. Commodity pricing assumption represents average over life of mine based on Consensus Economics forecasts, June 2019.

2. Tailings economics based on the Restart Feasibility Study (Nov 2017), up to date actual operating cost data, with revised commodity, exchange rate and treatment

charge assumptions as well as considering current depletion of the Ore Reserve and existing tailings ramp up progress.

3. Capital Expenditure represents further capital requirements for tailings ramp-up and all capital requirements including appropriate contingency allowances for in-

situ development

4. C1 is defined as direct cash operating costs produced, net of by-product credits, divided by the amount of payable zinc produced. Direct cash operating costs

include all mining, processing, transport, treatment costs and smelter recovery deductions through to refined metal.

5. Calculated reduction (negative value) or increase (positive value) in LOM average operating costs due to incremental cost increase of respective in-situ operation

Case

6. Net rehabilitation is expected to remain the same as increased disturbance for East Fault Block and Silver King are offset by savings through integrated mining

and rehabilitation of the waste rock dumps.

7. USD:AUD of 0.73 used for FY20 and then 0.70 for every subsequent year.

Financial Parameters (approximate)

Metal Prices & Exchange Rate1

Zinc US$2,650/t (US$1.20/lb)

Lead US$2,165/t (US$0.98/lb)

Silver US$19/oz

AUD/USD $0.707

Units 12 Mtpa Tailings2 10Mtpa Tailings + South Block / East

Fault Block

10Mtpa Tailings + South Block / East Fault Block + Silver

King

Project Cash Flows

Net Smelter Revenue A$M 3,504 4,432 4,949

C1 Operating Costs (payable Zn)4 USD/lb Zn 0.56 0.55 0.50

C1 Operating Cost Differential5 USD/lb Zn - -0.01 -0.05

EBITDA A$M 1,704 2,102 2,404

Capital Expenditure3 A$M 40 95 137

Sustaining Capital & Rehabilitation6 A$M 127

Valuation

Free Cashflow (after tax) A$M 1,128 1,365 1,549

NPV8 A$M 879 1,024 1,146

IRR (incremental on 12Mtpa tailings) % - 46% 80%

Page 22: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

22 / 27

Quarterly Exploration Developments

Geological activities in the June quarter focussed on the execution of the near mine exploration

programme supported by the Queensland Governments Collaborative Exploration Initiative.

Three drill holes were completed for a total of 1,600m, targeting a dislocated portion of the Century

orebody hypothesized to have spalled into the adjacent crater structure following a meteorite

impact ~470 million years ago.

Figures 19 & 20: Reconstruction of the original Big Zinc orebody (left) & orebody final form prior to mining

operations (right), inc. a conceptual target slumping location of the missing section (denoted by a yellow star)

Figures 21 & 22: Reconnaissance drill hole locations with crater floor contours (left) and topographic map (right)

The programme was successful in confirming the conceptual model, and better defining the crater

architecture. The presence of Century footwall sequence slump blocks in the target area, and

identification of distinct crater features vastly improved the understanding of the mechanisms and

vectors of mass movement on the crater margin.

Detailed modelling and interpretation of the results over the next quarter is anticipated to generate

further targets with potential for dislocated Century blocks.

Potential

displaced portion

of the original

orebody

Termite

Range Fault

Nikkis

Fault

Interpreted

formation of

original orebody

Orebody

structure

prior to

mining

operations

Page 23: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

23 / 27

Corporate Developments

Debt Facility Developments

During the quarter the Company continued the process of achieving all conditions precedent

relating to the existing A$40M unsecured junior facility from Varde Partners. This facility forms

part of A$100M in total debt facilities provided by Varde, with the other A$60M being a senior

secured facility that is fully approved and has been drawn. Details of the facilities are provided in

the ASX release dated 18 February 2019.

The Varde junior facility remains available and New Century continues to progress toward

achievement of the conditions required to draw the facility, which are to be satisfied by 30 August

2019 unless otherwise extended by the parties.

Board Changes

Subsequent to the quarter’s end the Company announced the appointment of Mr Robert McDonald

to the position of Chairman of the Company.

Mr McDonald has more than 40 years of broad experience in the international mining sector. His

early career within the Rio Tinto Group involved various operational business development, deal

making and strategic planning roles for Hamersley Iron, RTZ Services and Rio Tinto Minera SA.

This experience was followed by 20 years of investment banking, initially with BA Australia, then

as director and principal of Resource Finance Corporation, and subsequently as a Managing Director

of N.M. Rothschild & Sons. In these roles he was responsible for a wide range of advisory services

including company formation, mergers and acquisitions, business origination, strategic advice on

value creation/recognition, risk management, fairness opinions, debt and equity capital raisings

and corporate restructurings.

Since retiring from Rothschild a decade ago, Mr McDonald has continued as a trusted investment

banking advisor to a select group of major international mining and investment companies,

including acting as a senior advisor to China Minmetals (whose subsidiary, MMG Ltd, was the

previous owner of the Century Zinc Mine).

He has also maintained an active involvement in publicly listed and private mining and mining

service companies through various board roles including as non-executive director and chairman of

New Century's operating partner, Sedgman Ltd.

In conjunction with the appointment of Mr McDonald, there has been two other planned board

changes with Mr Evan Cranston stepping into a non-executive director role and with Mr Tolga

Kumova stepping down from the Board.

The Company plans to continue the process of board evolution over 2019, in line with its planned

growth towards establishing the business as a significant base metal producer on the ASX.

Page 24: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

24 / 27

Management Changes

During the quarter the Company announced the appointment of Mark Chamberlain, an experienced

finance executive and former CFO of OceanaGold Corporation (ASX:OGG, TSX:OGC), to the position

of Chief Financial Officer.

Mark, who is both a qualified accountant and lawyer, has over 30 years’ experience covering a

broad range of financial disciplines in the resources industry. He has developed and lead Finance,

Accounting and Treasury divisions at successful Australian mining companies such as OceanaGold,

Newcrest Mining (ASX:NCM) and WMC Resources. These roles included the management of all

aspects of funding – corporate, project and structured, financial and commodity price risk

management, corporate reporting, financial modelling & planning, taxation, cash & working capital

management as well as M&A transactions.

As CFO of OceanaGold over a period of six years, Mark was part of the team which oversaw the

growth of the business from a market capitalisation of A$350M to over A$2,500M. This included

development of the company from an aspiring single asset junior to an established mid-tier operator

with a diverse globally spread investor base and track record of delivering strong EBITDA margins

and return on invested capital for shareholders.

Previously, with Newcrest Mining, he was General Manager - Treasury and Financial Analysis

responsible for capital management and funding, risk management and project analysis.

Mark has also held positions as Corporate Lawyer and Assistant Treasurer at Western Mining

Corporation and was involved with project negotiations, project and corporate financing and

commercial initiatives.

Page 25: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

25 / 27

Other Projects: Kodiak Coal Project (NCZ 70%)

The Kodiak Coal Project is currently on care and maintenance.

The Company continues to consider options with regard to the future of the Kodiak Coking Coal

Project in Alabama, USA, including the disposal of the asset.

To learn more, please visit: www.newcenturyresources.com

For further information, please contact:

New Century Resources Media enquiries

Patrick Walta Shane Goodwin

Managing Director Head of Corporate Affairs

P: +61 3 9070 3300 P: +61 434 039 106

E: [email protected] E: [email protected]

Page 26: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

26 / 27

Statement of JORC 2012 Compliant Resources & Reserves

Mineral Resources

Tonnes (Mt)

Zn (%)

Pb (%)

Ag (g/t)

Zn (t) Pb (t) Ag (Oz)

South Block (Indicated)

6.1 5.3 1.5 43 322,000 90,000 8,550,000

East Fault Block (Indicated)

0.6 9.8 1.1 42 63,000 7,300 872,000

Silver King (Inferred) 2.7 6.9 12.5 120 186,000 337,500 10,500,000

TOTAL 9.4 6.1 4.6 65 571,000 434,800 19,922,000

Ore Reserves Tonnes (Mt)

ZnEq (%)

Zn (%)

Ag (g/t) Zn (t) Pb (t) Ag (Oz)

Century Tails (Proved)

77.3 3.1 3.0 12 2,287,662 - 29,734,819

Zinc Equivalent Calculation

ZnEq was calculated for each block of the Century Tailings Deposit from the estimated block grades.

The ZnEq calculation takes into account, recoveries, payability (including transport and refining

charges) and metal prices in generating a zinc equivalent value for each block grade for Ag and Zn.

ZnEq = Zn%+ + Ag troy oz/t*0.002573. Metal prices used in the calculation are: Zn US$3,000/t, and

Ag US$17.50/troy oz.

Competent Persons Statement

Mineral Resources

The information in this announcement that relates to Inferred Mineral Resources on the Silver King

Deposit was first reported by the Company in its prospectus released to ASX on 20 June 2017. The

South Block Deposit was first reported by the Company to the ASX on 15 January 2018 and the East

Fault Block Deposit was first reported by the Company to the ASX on 25 June 2019. The Company

confirms that it is not aware of any new information or data that materially affects the information

included in the original market announcements, and in the case of estimates of Mineral Resources,

that all material assumptions and technical parameters underpinning the estimates in the relevant

market announcement continue to apply and have not materially changed. The Company confirms

that the form and context in which the Competent Person's findings are presented have not been

materially modified from the original market announcement.

Ore Reserves

The information in this announcement that relates to the Ore Reserve at the Century Tailings

Deposit was first reported by the Company in its ASX announcement titled "New Century Reports

Page 27: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

27 / 27

Outstanding Feasibility Results that Confirm a Highly Profitable, Large Scale Production and Low

Cost Operation for the Century Mine Restart" dated 28 November 2017. The Company confirms that

it is not aware of any new information or data that materially affects the information included in

the original market announcement, and in the case of estimates of Ore Reserves, that all material

assumptions and technical parameters underpinning the estimates in the relevant market

announcement continue to apply and have not materially changed. The Company confirms that the

form and context in which the Competent Person's findings are presented have not been materially

modified from the original market announcement.

Appendix 1:

The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 30 June

2019:

Project Location Status Interest

Century Zinc Mine Queensland, Australia

ML 90058 Mt Isa Granted 100%

ML 90045 Mt Isa Granted 100%

EPM 10544 Mt Isa Granted 100%

EPM 26722 Mt Isa Granted 100%

EPM 26772 Mt Isa Granted 100%

EPM 26812 Mt Isa Granted 100%

EPM 26873 Mt Isa Granted 100%

EPM 26868 Mt Isa Granted 100%

EPM 26874 Mt Isa Granted 100%

EPM 26778 Mt Isa Application 100%

EPM 26976 Mt Isa Application 100%

Kodiak Coking Coal Project Alabama, USA

Coke Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Atkins Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Gholson Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Clark Seam, Gurnee Property Shelby & Bibb Counties Lease 70%

Page 28: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 1

+Rule 5.5

Appendix 5B

Mining exploration entity and oil and gas exploration entity quarterly report

Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/13, 01/09/16

Name of entity

NEW CENTURY RESOURCES LIMITED

ABN Quarter ended (“current quarter”)

53 142 165 080 30 JUNE 2019

Consolidated statement of cash flows Current quarter $A’000

Year to date (12 months) $A’000

1. Cash flows from operating activities#

50,011 157,280 1.1 Receipts from customers

1.2 Payments for

(946) (5,035) (a) exploration & evaluation

(b) development (57,681) (184,842)

(c) production - -

(d) staff costs (3,975) (14,977)

(e) administration and corporate costs (2,292) (9,194)

1.3 Dividends received (see note 3) - -

1.4 Interest received 123 408

1.5 Interest and other costs of finance paid (720) (956)

1.6 Income taxes paid - -

1.7 Research and development refunds - -

1.8 Other (MMG support fees) (652) (2,587)

1.9 Net cash from / (used in) operating activities

(16,132) (59,903)

# A detailed description of items in Section 1 is provided in the June 2019 Quarterly Activities Report

2. Cash flows from investing activities

- (407)

2.1 Payments to acquire:

(a) property, plant and equipment

(b) tenements (see item 10) - -

(c) investments - -

(d) other non-current assets - (12,035)

Page 29: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 2

Consolidated statement of cash flows Current quarter $A’000

Year to date (12 months) $A’000

2.2 Proceeds from the disposal of:

- 584 (a) property, plant and equipment

(b) tenements (see item 10) - -

(c) investments - -

(d) other non-current assets - 2,200

2.3 Cash flows from loans to other entities - -

2.4 Dividends received (see note 3) - -

2.5 Other - -

2.6 Net cash from / (used in) investing activities

- (9,658)

3. Cash flows from financing activities

- - 3.1 Proceeds from issues of shares

3.2 Proceeds from issue of convertible notes - -

3.3 Proceeds from exercise of share options 123 435

3.4 Transaction costs related to issues of shares, convertible notes or options

- (15)

3.5 Proceeds from borrowings - 71,438

3.6 Repayment of borrowings - (11,438)

3.7 Transaction costs related to loans and borrowings

- (2,902)

3.8 Dividends paid - -

3.9 Other - -

3.10 Net cash from / (used in) financing activities

123 57,518

4. Net increase / (decrease) in cash and cash equivalents for the period

51,093 46,249 4.1 Cash and cash equivalents at beginning of

period

4.2 Net cash from / (used in) operating activities (item 1.9 above)

(16,132)

(59,903)

4.3 Net cash from / (used in) investing activities (item 2.6 above)

-

(9,658)

4.4 Net cash from / (used in) financing activities (item 3.10 above)

123

57,518

4.5 Effect of movement in exchange rates on cash held

(687)

191

4.6 Cash and cash equivalents at end of period

34,397

34,397

Page 30: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 3

5. Reconciliation of cash and cash equivalents at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts

Current quarter $A’000

Previous quarter $A’000

5.1 Bank balances 34,283 50,979

5.2 Call deposits 114 114

5.3 Bank overdrafts - -

5.4 Other (provide details) - -

5.5 Cash and cash equivalents at end of quarter (should equal item 4.6 above)

34,397^

51,093

^ Cash and Cash Equivalents excludes the debtor of the final MMG support Payment for $5,575,000 received 1st July

6. Payments to directors of the entity and their associates Current quarter $A'000

6.1 Aggregate amount of payments to these parties included in item 1.2 686

6.2 Aggregate amount of cash flow from loans to these parties included in item 2.3

-

6.3 Include below any explanation necessary to understand the transactions included in items 6.1 and 6.2

Payments to directors/director associates for director fees, legal fees and other fees

7. Payments to related entities of the entity and their associates

Current quarter $A'000

7.1 Aggregate amount of payments to these parties included in item 1.2 111

7.2 Aggregate amount of cash flow from loans to these parties included in item 2.3

-

7.3 Include below any explanation necessary to understand the transactions included in items 7.1 and 7.2

Payments to key management personnel

8. Financing facilities available Add notes as necessary for an understanding of the position

Total facility amount at quarter end

$A’000

Amount drawn at quarter end

$A’000

8.1 Loan facilities - -

8.2 Credit standby arrangements - -

8.3 Other (please specify) AUD$100,000** AUD$60,000

8.4 Include below a description of each facility above, including the lender, interest rate and whether it is secured or unsecured. If any additional facilities have been entered into or are proposed to be entered into after quarter end, include details of those facilities as well.

** Working Capital facilities with Varde Partners comprising a secured facility of $60 million which is approved and available for use and an unsecured facility of $40 million which is subject to conditions precedent prior to drawdown. For further details see the Company’s ASX announcement dated 18 February 2019 and the June 2019 Quarterly Activities Report.

Page 31: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 4

9. Estimated cash outflows for next quarter* $A’000

9.1 Exploration and evaluation 918

9.2 Development# 16,959

9.3 Production 48,367

9.4 Staff costs 4,003

9.5 Administration and corporate costs 2,283

9.6 Other (provide details if material) -

9.7 Total estimated cash outflows 72,530

* Excludes receipts from customers associated with zinc production. Refer to forward quarter production guidance releasedin the June 2019 Quarterly Activities Report (23,000t to 29,000t zinc metal)

# Quarterly development capital cash outflows are associated with ~A10M in expansion capex (including the full cleaner circuit commissioning and preparations for expanded scavenger circuit commissioning) and ~A$7M sustaining capex (including continued annual dredging and one off Wunma refurbishment). See the June 2019 Quarterly Activities Report for further details.

10. Changes intenements(items 2.1(b) and2.2(b) above)

Tenement reference and location

Nature of interest Interest at beginning of quarter

Interest at end of quarter

10.1 Interests in miningtenements andpetroleum tenementslapsed, relinquishedor reduced

NA - - -

10.2 Interests in miningtenements andpetroleum tenementsacquired or increased

NA - - -

Compliance statement

1 This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.

2 This statement gives a true and fair view of the matters disclosed.

Sign here: Date: 31 July 2019 (Managing Director)

Print name: Patrick Walta

Notes

1. The quarterly report provides a basis for informing the market how the entity’s activities have beenfinanced for the past quarter and the effect on its cash position. An entity that wishes to disclose

Page 32: Quarterly Activities Report June 2019 June 2019 Quarter ...€¦ · ASX / MEDIA ANNOUNCEMENT ASX: NCZ Quarterly Activities Report June 2019 Office Level 4, 360 Collins Street, Melbourne

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report

+ See chapter 19 for defined terms 1 September 2016 Page 5

additional information is encouraged to do so, in a note or notes included in or attached to this report.

2. If this quarterly report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.

3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.