quantitative risk analysis report - welcome to...
TRANSCRIPT
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 1 of 77
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 1 of 77
FOREWARD
Quantitative risk analysis can be defined as “The development of a quantitative estimate of risk based on engineering evaluation and mathematical techniques for combining estimates of incident consequences and frequencies in correlation with measures to combat accidental menace”. It also helps to determine what damage could be caused by accidental releases of toxic, flammable or explosive materials and the incidents which could lead to their release. When such incidents represent a major hazard to life or property, then efforts should be made to reduce damage, which the incident could cause as well as reduce the probability of such incidents occurring. Probability of such occurrence can well be minimized by altering such things as the manufacturing process, the safety systems, the procedures for training, testing and maintenance. For reducing the damage which the incident could cause the measures adopted could be introducing process changes or alternative process, reducing the inventories of hazardous materials, providing robust secondary containment system, modifying site layouts, removing to a different site of safer ambience or by improving control and management techniques. Carrying out a risk analysis study is a statutory requirement in India under the Factories Act 1948 for factories coming under the preview of “Hazardous Process” as defined in the act. This is required while obtaining permission for the initial location of the factory or when any expansion is proposed or as a regular process to be augmented periodically as per the need. Statutory authorities can also call for risk analysis study to be carried out by a plant if in their opinion it is deemed to be necessary. The risk analysis study along with disaster analysis survey is being undertaken BY M/S SONAR BHARAT ENVIRONMENT & ECOLOGY PVT.LTD, KOLKATA, at the behest of M/S BHARAT PETROLEUM CORPORATION LIMITED, OIL INSTALLATION, BUDGE BUDGE, WEST BENGAL.
The whole objective was to evaluate the consequences of a fire / explosion occurring in the terminal and to evaluate their system, procedures, practices and infrastructure to deal with such incidents.
Various products handled by the Terminal are : Motor Sprit (MS) High Speed Diesel (HSD) Superior Kerosene Oil (SKO) Light Diesel Oil (LDO) Furnace Oil (FO) Aviation Turbine Fuel (ATF) Ethanol
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 2 of 77
CONTENTS
Sl.No. Description Page No.
Chapter -1 Executive Summary 3-6
Chapter -2
Installation Details
7-17
Chapter -3 Process Description
18-18
Chapter-4 Risk Analysis 19-23
Chapter-5 Hazard Identification 24-25
Chapter-6 Maximum credible accident analysis (MCAA) approach
26-45
Chapter-7 Risk Assessment
46-51
Chapter-8 Consequence Analysis 52-72
Chapter-9 Risk and Failure Probability 73-74
Chapter-10 Recommendation & Conclusion 75-77
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 3 of 77
Chapter-1
EXECUTIVE SUMMARY
BUDGE BUDGE OIL INSTALLATION of BHARAT PETROLEUM CORPORATION LIMITED LTD. is situated at BUDGE BUDGE, Dist : 24 Parganas (S) in West Bengal. The Installation was commissioned in the year 1910. Facilities at the installation being very old, are in immediate need of replacement. The company therefore proposes a revamping programme for the installation. It plays a crucial role in the distribution of petroleum oils to 5 districts around 24 Parganas (S). The products are received through road, rail & barge etc. Mode of transportations and dispatched to the consumers is through road and rail. It occupies an important place in the Bharat Petroleum Oil distribution network. The products handled by the Installation are MS, HSD, SKO,ATF, FO , LDO & Ethanol.
The total area covering in the installation is 39 Acres. NEAREST FACILITIES : Name of Place Telephone No FIRE STATION - Budge Budge (2 KM) Approx. 24701271 POLICE STATION - Port Police Station, Budge Budge 24701213 (1 KM) Approx.
- GOVT. HOSPITAL - Budge Budge ESI Hospital, 24701396 Mahestala (4.5 KM) Approx. AMBULANCE - Budge Budge Municipality 24701366 (1.5 KM) Appeox. RAILWAY STATION - BUDGE BUDGE (3 KM) Approx BUS STAND - Budge Budge (2 KM) Approx.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 4 of 77
ADJOINING PROPERTIES
The population density is around 3700 / Km2 around the installation. There are some shops on the south-east and habitation on the north at a distance of more than 0.5 km from the terminal.
The terminal is bounded on the east by MG Road, River Hooghly on the west, BPCL’s Lube Plant, Tank farm for lube storage & LDO on north and HPCL tank farm and HPCL Tanker loading Gantry on south.
STORAGE FACILITIES:
Present gross tankage capacity of the Installation is 78086 Kl in 18 above ground and 9 underground tanks.
The existing tanks and other allied facilities like TLF Gantry will be dismantled.
11 above ground tanks and 9 underground tanks along with other facilities like new TLF gantry and TW gantry, automation Equipments will be installed in phases.
In the 1st phases 11 aboveground and 9 underground tanks will be dismantled.
11new above ground tanks and 9 new underground tanks, TLF gantry will be installed while existing 9 above ground tanks with aggregate capacity of 50522 Kl will remain in operation till commissioning of the 1st phase..
In the 2nd phase, 9 existing above ground tanks will be demolished and 6 new above ground tank will be installed. After commissioning of the 11 new above ground tanks & 9 underground tanks capacity of the installation will stand at 50522 Kl.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 5 of 77
MANPOWER OF BUDGE BUDGE INSTALLATION :
Total manpower of the Terminal is 246 as mentioned hereunder:
SR. INSTALLATION MANAGER - 01 SR.MANAGER LOBP INCHARGE - 01 OFFICER - 35 STAFF (Clerical & Field) - 59 SECURITY (COMPANY) - 15 SECURITY (Contractor) - 26 WORKMAN (Contractor) - 109 TOTAL = 246
ACTIVITIES
BUDGE BUDGE Installation of BHARAT PETROLEUM CORPORATION LIMITED is involved in the process of receipt, storage and distribution of petroleum products. There is no manufacturing process involved in the present activities of BUDGE BUDGE Installation. These petroleum products are received by BTPN wagons from NRL / Haldia refineries and part of LDO is also received by marine tankers from KRL / outside countries.
.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 6 of 77
The main facilities are summarized as under
Storage
Proposed .- 11 Above Ground and 9 Under Ground tanks)
TLF Gantry 2 Gantry of 8 bays each with 16 loading points..
Tanker wagon unloading facility – Tank wagon Gantry for unloading 50 BTPN wagons.
DG Sets. 3 no’s rating of which are 500 KVA -2 125 KVA -1
FIRE FIGHTING FACILITIES Fire Water Storage. 2 x 4976 kl Jockey Pumps. 2 x 60 kl Fire Water pumps. 3 x 682 kl, 2 x 682 kl(Stand by) Storage Tank with active water protection.
I. Fixed Roof & Floating Roof tanks are fitted with sprinkler System and foam system.
II. Floating Roof tanks are planned with Rim seal protection. III. Hydrants Monitors are provided at all strategic point including TLF area, Tank farms, Pump House, Tank Truck parking area, etc.
Fire extinguishers. As per OISD-117
Hydrants & Monitors. As per OISD-117
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 7 of 77
Chapter 2
INSTALLATION DETAILS
2.0 INTRODUCTION
M/s B.P.C.L will has undertaken a revamping programme for replacement of
the existing tanks along with other facilities like TLF gantry etc. The
Installation is located on a plot measuring 39.acres
2.1 DESCRIPTION OF INSTALLATION FACILITY
Tank Wagon Loading / Unloading facility, and unloading from the
Ocean Tankers. Tank Farm Truck Loading facilities/TW loading facility. Fire- fighting system including 2 nos. fire water tanks each of 4976
KL capacity Electrical installation Instrumentation Drinking water and rain water Harvesting System. Building Utility
LAND, LOCATION AND LAYOUT
Budge Budge oil installation of Bharat petroleum corporation limited . Is
situated at Budge Budge, dist: 24 parganas (s) in West Bengal. The installation
was commissioned in the year 1910. It plays a crucial role in the distribution of
petroleum oils to 5 districts nearer to 24 parganas (s). The products are
received through road, rail & barge. Mode of transportations for dispatch to the
consumers are through road. It occupies an important place in the Bharat
Petroleum oil distribution network. The products handled by the installation are
MS, HSD, SKO, ATF, FO, LDO, MTO & SBP.
The layout has been prepared strictly as per prescribed OISD standards and
guidelines. The safety distances are maintained as per the standard
guidelines. The road network is designed in such a way that the movement of
vehicle carrying bulk petroleum products is smooth.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 8 of 77
PROCESS DESCRIPTION AND OPERATING PROCEDURES
The Product are received through BTPN railway wagons / Ocean Tankers
Unloading of different products in their designated tanks through TWD Pumps
Storage in Above Ground Tanks & Under Ground Tank
Loading in Tank Wagons & Tank Trucks through TWF/TLF Pumps
.
The detail process descriptions are discussed below :
2.2 PRODUCT PIPELINE SYSTEMS
The pipeline from railway siding / jetty to installation and within the terminal
have been constructed and designed in accordance with relevant API
codes/OISD standards.
The following pipeline systems are in existence:
a) From the Unloading Gantry to the terminal unloading pump house:
Dedicated pipelines for HSD / MS / SKO / FO /LDO/ ATF have been laid in
between two spurs to receive products from rakes. Products are received
through BTPN wagons, Ocean Tankers. Pipe lines have been laid between
the jetty and the storage tanks for receiving products from the Ocean
Tanker.
b) Pipelines within the terminal consists of the followings :
1. Pipelines from Unloading pump house to the Tank Farm : There
are dedicated pipelines for individual products.
2. Pipelines from Tanks to Loading pump house : There are dedicated
pipelines for individual products.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 9 of 77
Pipelines from Loading pump house to the TLF Gantry. There are dedicated
pipelines for individual products. Tank wise dedicated pipelines have been
provided. The lines connecting the loading arms are of 3”NB Size. The loading
arms and the metering assembly are of 3”NB Size.
2.3 Receipt
Petroleum products are received through:
1) Tank wagons received is mainly from Numaligarh
2) Import through Ocean Tankers
2.4 Petroleum Product Unloading
Petroleum products received by BTPN wagons at TW unloading gantry
located at site. Materials are unloaded through pumps earmarked for each
product. dedicated pipe lines for HSD/SKO/FO/MS/ATF/ LDO have been laid
to receive product from rakes.
Ocean Tankers are unloaded from Budge Budge oil jetty through dedicated
pipe lines.
Tank Wagon Unloading Pumps
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 10 of 77
2.5 TANK FARM:
The POL installation is provided with storage tanks for Class A, B & C
petroleum products.
Product MS HSD SKO FO ETHANOL
Class A B B C A
The tanks for Class A are floating roof tanks and fixed roof tanks are provided
for Class B & class C products. The design and construction of storage tanks
are according to Indian regulations IS 803 and/or API 650. All tanks are
provided with sprinklers and foam feeding devices as per the OISD
regulations. All the storage tanks are equipped with automatic level indicators
with high / high high level alarms.
The design of the installation is according to Indian standards OISD 117,116
and as per recommendation of Chief Controller of Explosives, Nagpur
(CCOE)
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 11 of 77
STORAGE
Storage of products: The following storage capacities are envisaged:
PROPOSED ABOVE GROUNG STORAGE
SL NO
TANK NO DIA (M) LENGTH (M) GROSS CAPACITY
PRODUCT
1 T1 29.00 13.500 8917 HSD 2 T2 29.00 13.500 8917 HSD 3 T3 20.00 13.500 4241 ATF 4 T4 20.00 13.500 4241 ATF 5 T5 24.00 12.000 5429 MS 6 T6 24.00 12.000 5429 MS 7 T7 12.60 13.500 1683 SKO 8 T8 12.60 13.500 1683 SKO 9 T9 20.00 13.500 4241 FO 10 T10 20.00 13.500 4241 LDO 11 T11 4.00 16.000 200 Ethanol
PROPOSED UNDERGROUNG STORAGE
SL NO
TANK NO DIA (M) LENGTH (M) CAPACITY PRODUCT
1 UG T1 3.20 12.60 100 SPEED 2 UG T2 3.20 12.60 100 SPEED-97 3 UG T3 3.20 12.60 100 HI-SPEED 4 UG T4 3.20 12.60 100 ATF 5 UG T5 3.20 12.60 100 SLOP 6 UG T6 4.00 16.00 200 HEXANE 7 UG T7 4.00 16.00 200 MTO 8 UG T8 4.00 16.00 200 SBP 9 UG T9 4.00 16.00 200 ETHANOL
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 12 of 77
Tank Truck Loading Pumps
2.6 Fire detection and protection system
The fire protection and detection system are in accordance with OISD 117.
Portable fire extinguishers of 10-75 kg are installed on pump stations, tank
farms and buildings, the size depending on the object concerned. Electrical
rooms are protected by Carbon dioxide (CO2) fire extinguishers. Mobile fire
fighting vehicles with foam monitors, hoses, etc.have been provided. Fixed
fire fighting monitors are located at the pump station and truck loading
gantries, each with a capacity of 144 m3/hr. sufficient hydrants are installed in
the POL installation, with the hydrants spaced at a maximum distance of 30m.
The tanks are equipped with fixed cooling water and foam installations and
mobile vehicles and equipment (monitors, hoses, branch pipes, etc.) are
provided to handle field fires.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 13 of 77
Table below will show fire water storage tank, fire water pumps,
Fire Water Storage Tank
Sr.No No’s Capacity (KL) 1 2 4976
Fire Water Pump
Sr.No Category No’s Capacity 1
Main Pump ( Engine Driven)
3 682 KL/Hr
2 Stand By 682 KL/Hr
2 Jockey Pump ( Electric Motor Driven)
1 60 KL/Hr
1 Stand By 60 KL/Hr
FIRE ALARM SYSTEM
Conventional type Fire alarm systems are provided in following areas; a) Truck Loading b) Tank Farm c) Office / Admn. Building d) Sub-Stations
SOURCE OF SIGNALING
The source of signaling is considered as ESD. These are considered for
the areas where manual warning is to be initiated on notice of fire. They
are mostly provided for open areas or near to access doors, truck
loading, pump house, tank farm, administrative building, etc.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 14 of 77
2.7 ELECTRICAL INSTALLATION
The scope covers the basic concepts of the following:
Receiving of HT Power supply from Main 11kV Power Grid Distribution Transformer. Distribution of LT power supply. Cabling System. Building and Area Lighting. Approach Road Lighting (Approx. 1.2 kms) Earthing and Lightning Protection. Power Factor Improvement. Battery Bank & Battery Charger. UPS system. Diesel Generating Set.
2.8 PLANT AUTOMATION SYSTEM
CCTV Cameras will be installed for supervision of key activities in the
installation (e.g. pump stations, truck loading facilities and other strategic
areas) as well as for the supervision of security of the installation.
The fire water pumps will be activated automatically. The jockey pump will
maintain the pressure automatically.
VHF communication system containing a base station with antenna (1 set) and
number of portable VHF Trans-receivers (41 sets) with charger units will be
provided for providing communication within the plant premises. The base
station will be located in the administrative office. Public address system is at
the security room.
The fire water pumps will be activated automatically. When the fire-water
header pressure is low, the jockey pump maintains the pressure automatically.
The foam is sucked through Venturi system. The storage installation is having
3 KM range siren for onsite /off site disaster management.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 15 of 77
Automation in the operational activity will be implemented .Automated
operation on tank body valve when product level reaches critical height.
Installation of ROV, High High level Alarm, lader gauge, Servo level gauge,
ESD, Safety PLC to be integrated with process fields
2.9 HYDROCARBON DETECTORS
The Class-A tank farm and product pump house manifold are planned to be
equipped with Hydrocarbon detectors. These detectors will sense any
leakages and communicate the same to the control room with audible alarm
at Tank farm locations.
Main objective of the Hydrocarbon Detectors is to detect hydrocarbon gas
concentrations in the Installation and initiate alarm or shutdown system as the
case may be, at pre-defined levels to prevent any hazardous events and act
as independent safety layers for mitigation of consequences to achieve
overall process safety requirements of the plant. Hydrocarbon Detection
system is designed to perform its function during normal, abnormal and
design basis conditions. Control system is based on open architecture system
topology with fault tolerant network capabilities.
The major components of the TFMS system are as follows:
Field Instruments
Radar Level gauge
Local Level Indicator
a. Automation System for Petroleum Product Loading Stations
The automation system for truck loading stations consists of the following
sections: This system ensures optimization of economy and safety in
operation.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 16 of 77
Volumetric Flow Meters
Batch Controllers
Plant control system Programmable Logic Controller (SMPS)
Operator’s Interface console
i. Metering System
ii Batch Controller
iii Plant control system Programmable Logic Controller (SMPS)
iv Control and Interlocking System
v Integrated Control System
vi Emergency Shutdown System
2.10 WATER SUPPLY SYSTEM
Drinking Water System
Water requirement for domestic and other purposes are met from
supplies by KMWSA
Rain Water Harvesting System
There is a well laid out Rain water Harvesting System
Waste Water Treatment
Waste water is generated due to area cleaning /housekeeping and
occasional tank cleaning operations (Once in five years) at the POL
terminal.
Oil contaminated waste water is generated mainly from pump areas,
manifolds, truck loading, etc. only when spillage is washed with water as
well as occasional tank washing. The direct discharge areas i.e. those
areas within the POL terminal where leakage is likely to occur during
normal operations is to be provided with leak-proof curbing. These
curbed areas are connected to the Oil-Water Separator (OWS) system
for treatment of oily wastewater generated. Indirect discharge areas
such as dykes, etc. are connected to the OWS. The capacity is
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 17 of 77
adequate to take care of, the oily waste water to be handled from the
facility during the monsoon season.
The separated oil consisting of a comparatively dry floating layer is
removed and is drained into a common draw –off pipe discharge to the
oil pit. This collected oil is sold to third party for off-site recovery or
recycling.
Separate storm water drainage system is provided at the facility. The
non-contaminated rain water is discharged directly to a drain However,
particularly during the monsoon; any oil-contaminated rain water is led
to the OWS for treatment prior to discharge.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 18 of 77
Chapter-3
PROCESS DESCRIPTION
RECEIVE PETROLEUM PRODUCTS
BY TANK WAGON/OCEAN
TANKER
STORE IN ABOVE GROUND (FIXED & FLOATING ROOF TANK) UNDER GROUND TANKS.
LOAD TANK WAGON AND TANK TRUCK
FOR DELIVERY,
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 19 of 77
Chapter-4
RISK ANALYSIS 4.1 PREAMBLE
As the Installation handle various petroleum products which have got potential
of fire / explosion hazard for itself, hence it is necessary to evaluate the Risk
due to the Installation. Accordingly, M/s. Sonar Bangla Environment & Exports
(P) Ltd. (SBEE) has been retained by M/s.BPCL as consultant to carryout
Risk Analysis Study for the proposed revamping project.
4.2 SCOPE OF THE STUDY
The risk assessment has been carried out in line with the requirements of
various statutory bodies:
Identification of potential hazard areas;
Identification of representative failure cases;
Identification of possible initiating events;
Assess the overall damage potential of the identified hazardous events
and the impact zones from the accidental scenarios;
Consequence analysis for all the possible events;
4.3 PROPOSED FACILITY
M/s B.P.C.L will has undertaken a revamping programme for replacement of
the existing tanks for storage of MS, HSD, SKO, FO, LDO & ATF and small
quantity of ethanol. Proposed storage capacity of each product is given
below:
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 20 of 77
PROPOSED ABOVE GROUNG STORAGE
SL NO
TANK NO DIA (M) LENGTH (M) GROSS CAPACITY
PRODUCT
1 T1 29.00 13.500 8917 HSD
2 T2 29.00 13.500 8917 HSD
3 T3 20.00 13.500 4241 ATF
4 T4 20.00 13.500 4241 ATF
5 T5 24.00 12.000 5429 MS
6 T6 24.00 12.000 5429 MS
7 T7 12.60 13.500 1683 SKO
8 T8 12.60 13.500 1683 SKO
9 T9 20.00 13.500 4241 FO
10 T10 20.00 13.500 4241 LDO
11 T11 4.00 16.000 200 Ethanol
PROPOSED UNDERGROUNG STORAGE
SL NO
TANK NO DIA (M) LENGTH (M) CAPACITY PRODUCT
1 UG T1 3.20 12.60 100 SPEED
2 UG T2 3.20 12.60 100 SPEED-97
3 UG T3 3.20 12.60 100 HI-SPEED
4 UG T4 3.20 12.60 100 ATF
5 UG T5 3.20 12.60 100 SLOP
6 UG T6 4.00 16.00 200 HEXANE
7 UG T7 4.00 16.00 200 MTO
8 UG T8 4.00 16.00 200 SBP
9 UG T9 4.00 16.00 200 ETHANOL
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 21 of 77
4.4 Hazard Identification
Identify potentially hazardous materials that can cause loss of human life/injury, loss of properties and deterioration of the environment due to loss of containment.
Identify potential scenarios, which can cause loss of containment and consequent hazards like fire, explosion and toxicity.
4.5 Consequence Analysis
Analysis of magnitude of consequences of different potential hazard
scenarios and their effect zones. Consequence analysis is a measure of potential hazards and is
important for taking precautionary measures for risk reduction as well as mitigation of effect in case of such accidents happening.
This report has been prepared by applying the standard techniques of risk assessment and the information provided by Budge Budge BPCL.
4.6 Glossary Of Terms Used In Risk Assessment
The common terms used in Risk Assessment and Disaster Management are elaborated below: “Risk” is defined as a likelihood of an undesired event (accident, injury or death) occurring within a specified period or under specified circumstances. This may be either a frequency or a probability depending on the circumstances. “Hazard” is defined as a physical situation, which may cause human injury, damage to property or the environment or some combination of these criteria. “Hazardous Substance” means any substance or preparation, which by reason of its chemical or physico-chemical properties or handling is liable to cause harm to human beings, other living creatures, plants, micro-organisms, property or the environment. “Hazardous Process” is defined as any process or activity in relation to an industry, which may cause impairment to the health of the persons engaged or connected therewith or which may result in pollution of general environment. “Disaster” is defined as a catastrophic situation that causes damage, economic disruptions, loss of human life and deterioration of health and health services on a scale sufficient to warrant an extraordinary response from outside the affected area or community. Disaster occasioned by man is factory fire explosions and release of toxic gases or chemical substances etc.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 22 of 77
“Accident” is an unplanned event, which has a probability of causing personal injury or property damage or both. “Emergency” is defined as a situation where the demand exceeds the resources. This highlights the tropical nature of emergency “It is seen after experience that enough is not enough in emergency situations. Situations of this nature are avoidable but it is not possible to avoid them always.” “Emergency Preparedness” is one of the key activities in the overall management. Preparedness, though largely dependent upon the response capacity of the persons engaged in direct action, will require support from others in the organization before, during and after an emergency.
4.7 SCOPE OF STUDY
The risk assessment has been carried out in line with the requirements of various statutory bodies for similar type of projects: Identification of potential hazard areas Identification of representative failure cases Identification of possible initiating events Assess the overall damage potential of the identified hazardous events
and the impact zones from the accidental scenarios; Consequence analysis for all the possible events; Furnish specific recommendations on the minimization of the worst
accident possibilities.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 23 of 77
FLOW CHART FOR RISK ANALYSIS STUDY
YES
START
PLANT VISIT
DATA COLLECTION PROCESS DESCRIPTION PROCESS CONTROL LOOPS PRI/PFD OPERATING MANUAL START UP/SHUT DOWN PLOT PLAN METEOROLOGICAL DATA PAST ACCIDENTS DATA ALL RELEVANT PHYSICAL CHEMICAL DATA OF
SELECT THE
CLASSIFY VESSEL/EQUIPMENT
INVENTORY ANALYSIS
CALCULATE EFFECT
IDENTIFICATION OF HAZARD
IS FE/FET IN SEVERITY
ADOPT CHECK LIST APPROACH
CONSEQUENCE
PLOT DAMAGE DISTANCE
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 24 of 77
Chapter-5
HAZARD IDENTIFICATION 5.1 INTRODUCTION
Identification of hazards in the terminal is of primary significance in the
analysis, quantification and cost effective control of accidents involving
chemicals and process. A classical definition of hazard states that hazard is in
fact the characteristic of system/plant/process that presents potential for an
accident. Hence, all the components of a system/plant/process need to be
thoroughly examined to assess their potential for initiating or propagating an
unplanned event/sequence of events, which can be termed as an accident.
Typical schemes of predictive hazard evaluation and quantitative risk analysis
suggest that hazard identification step plays a key role.
Estimation of probability of an unexpected event and its consequence form
the basis of quantification of risk in terms of damage to property, environment
or personnel. Therefore, the type, quantity, location and conditions of release
of a toxic or flammable substance have to be identified in order to estimate its
damaging effects, the area involved and the possible precautionary measures
required to be taken. The following two methods for hazard identification have
been employed in the study.
Identification of hazardous storage units based on relative ranking
technique, viz, Fire-Explosion and Toxicity index (FE & TI); and
Maximum Credible Accident Analysis (MCAA)
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 25 of 77
5.2 CLASSIFICATION OF MAJOR HAZARDOUS SUBSTANCE
Hazardous substances may be classified into three main classes namely
flammable substances, unstable substances and toxic substances.
Flammable substances require interaction with air for their hazard to be
realized; under certain circumstances vapours arising from flammable
substances when mixed with air may be explosive especially in confined
spaces. However, if present in sufficient quantity such clouds may explode in
open air also.
Unstable substances are liquids or solids, which may decompose with such
violence so as to give rise to blast waves.
Finally, toxic substances are dangerous and cause substantial damage to life
when released into the atmosphere. The ratings for a large number of
chemicals based on flammability, reactivity and toxicity are given NFPA
Codes 49 and 345M.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 26 of 77
Chapter -6
MAXIMUM CREDIBLE ACCIDENT ANALYSIS (MCAA) APPROACH 6.1 INTRODUCTION
A Maximum Credible Accident (MCA) can be characterized, as an accident
with a maximum damage potential, which is still believed to be probable.
MCA analysis does not include quantification of probability of occurrence of
an accident. Moreover, since it is not possible to indicate exactly a level of
probability that is still believed to be credible, selection of MCA is somewhat
arbitrary. In practice, selection of accident scenarios representative for a
MCA-Analysis is done on the basis of engineering judgment and expertise in
the field of risk analysis studies, especially accident analysis.
Major hazards posed by flammable storage can be identified taking recourse
to MCA analysis. This encompasses certain techniques to identify the hazards
and calculate the consequent effects in terms of damage distances of heat
radiation, toxic releases, vapour cloud explosion etc. A host of probable or
potential accidents of the major units in the complex arising due to use,
storage and handling of the hazardous materials are examined to establish
their credibility. Depending upon the effective hazardous attributes and their
impact on the event, the maximum effect on the surrounding environment and
the respective damage caused can be assessed.
As an initial step in this study, a selection has been made of the processing
and storage units and activities, which are believed to represent the highest
level of risk for the surroundings in terms of damage distances. For this
selection, following factors have been taken into account:
Type of compound viz. flammable or toxic Quantity of material present in a unit or involved in an activity and Process or storage conditions such as temperature, pressure, flow,
mixing and presence of incompatible material.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 27 of 77
In addition to the above factors, location of a unit or activity with respect to
adjacent activities is taken into consideration to account for the potential
escalation of an accident. This phenomenon is known as the Domino Effect.
The units and activities, which have been selected on the basis of the above
factors, are summarized, accident scenarios are established in hazard
identification studies, whose effect and damage calculations are carried out in
Maximum Credible Accident Analysis Studies.
6.2 METHODOLOGY
Following steps are employed for visualization of MCA scenarios:
Chemical inventory analysis Identification of chemical release and accident scenarios Analysis of past accidents of similar nature to establish credibility to
identified scenarios; and Short-listing of MCA scenarios
6.3 COMMON CAUSES OF ACCIDENTS
Based on the analysis of past accident information, common causes of
accidents are identified as:
Poor house keeping
Improper use of tools, equipment, facilities
Unsafe or defective equipment facilities
Lack of proper procedures
Improvising unsafe procedures
Failure to follow prescribed procedures
Jobs not understood
Lack of awareness of hazards involved
Lack of proper tools, equipment, facilities
Lack of guides and safety devices, and
Lack of protective equipment and clothing
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 28 of 77
6.4 FAILURES OF HUMAN SYSTEMS
An assessment of past accidents reveal human factor to be the cause for over
60% of the accidents while the rest are due to other component failures. This
percentage will increase if major accidents alone are considered for analysis.
Major causes of human failures reported are due to:
Stress induced by poor equipment design, unfavorable environmental
conditions, fatigue, etc.
Lack of training in safety and loss prevention
Indecision in critical situation; and
Inexperienced staff being employed in hazardous situation
Often, human errors are not analyzed while accident reporting and accident
reports only provide information about equipment and/or component failures.
Hence, a great deal of uncertainty surrounds analysis of failure of human
systems and consequent damages.
6.5 MAXIMUM CREDIBLE ACCIDENT ANALYSIS (MCAA)
Hazardous substances may be released as a result of failures or
catastrophes, causing possible damage to the surrounding area. This section
deals with the question of how the consequences of release of such
substances and the damage to surrounding area can be determined by
means of models.
It is intended to give an insight into how the physical effects resulting from
release of hazardous substances can be calculated by means of models and
how vulnerability models can be used to translate the physical effects in terms
of injuries and damage to exposed population and environment. A disastrous
situation in general is due to outcome of fire, Vapour Cloud explosion or toxic
hazards in addition to other natural causes, which eventually lead to loss of
life, property and ecological imbalance.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 29 of 77
Major hazards posed by flammable storage can be identified taking recourse
to MCA analysis. MCA analysis encompasses certain techniques to identity
the hazards and calculate the consequent effect in terms of damage distances
of heat radiation, toxic release, vapour cloud explosion etc. A host of probable
or potential accidents of the major units in the complex arising due to use,
storage and handling of the hazardous materials are examined to establish
their credibility. Depending upon the effective hazardous attributes and their
impact on the event, the maximum effect on the surrounding environment and
the respective damage caused can be assessed. The MCA analysis involves
ordering and ranking various sections in terms of potential vulnerability.
6.6 ANALYSIS OF PAST ACCIDENTS Numerous accidents involving different hydrocarbons in process plants have
been reported. Table provides a worldwide list of all such accidents reported
since 1917. More than 1000 people have received injuries of various intensity
and more than 200 people died due to these accidents. The major causes of
accident involving fraction are given below.
i) Fire, over pressure, explosions 19
Nos
ii) Overfilling, loading/unloading and pipeline ruptures 5 Nos
iii) Collision and impact of rail/road tankers during transportation 2 Nos ---
45 Nos
It can be seen that the storage areas and transportation vehicles of C
fractions are most vulnerable to accidents. More than 10 accidents out of the
45 incidents examined have ended in BLEVE situation. Rest of them has
caused fires and explosions.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 30 of 77
MAJOR ACCIDENT IN PROCESS INDUSTRIES (LIGHTER FRACTIONS OF HYDROCARBONS)
Sl. No.
Year Location Chemical Event Deaths/Injuries
01 1944 Cleveland, Ohio Gasoline Fire & Explosion
128 D, 200-400 I
02 1949 Perth, NJ Hydrocarbon Fire 4 D 03 1955 Whiting, Ind. Naphtha Explosion 2 D, 30 I 04 1956 New York, USA Ehylene -- -- 05 1958 Signal Hill, California Oil Forth Fire 2 D 06 1962 Ras Tanura, Saudi
Arabia Propane Fire 1 D, 114 I
07 1963 Rexas, USA Polypropylene Explosion - 08 1964 Fackass Flats, Mev. Hydrogen Explosion - 09 1966 Feyzin, France Propane Fire &
Explosion 18 D, 81 I
10 1966 Larose, La NGL Fire (on pipeline)
7 D
11 1966 W. Germany Methane Explosive (failure of pipe)
3 D, 83 I
12 1967 Buenos Aires Propane -- -- 13 1968 Pernis, Netherlands Oil slopes Explosion 9 D, 85 I 14 1968 Terrylown, USA Propane -- -- 15 1968 Kennedale, Texac Gasoline Explosion (on
road tnkers) 28 I
16 1969 Pnerts la Cruz Light Hydrocarbon
Explosion 5 D
17 1970 Liden Niji Oil Refinery Fire -- 18 1970 Port Hudson, MO Propane Explosion (on
pipeline) --
19 1970 Mont Belview, Tex Butane Explosion (on pipeline)
--
20 1971 Longview, Tex Ethylene Explosion 4 D, 60 I 21 1972 Hearne, Tex Crude Oil Fire &
Explosion 1 D, 2 I
22 1972 Lynchbriod Va Propane Fire & explosion 1 D, 2 I 23 1972 Netherlands Hydrogen Explosion 4 D, 4 I, 24 1972 New Jersey, Turnpike,
New Jersey Propane Explosion (on
road tanker) 2 D
25 1972 Brazil Butane Explosion UVCE
37 D, 53 I
26 1972 Billings, Mont. Butane Explosion 4 I 27 1973 St. Amandles-Eaux
France Propane Explosion (on
road tanker) 5 D, 40 I
28 1973 Staten Island, NY Gasoline Fire (in empty storage tank)
40 D
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 31 of 77
Sl. No.
Year Location Chemical Event Deaths/Injuries
29 1974 Decatur, III Propane Explosion (on railway)
7 D, 152 I
30 1974 Florida, USA Propane Explosion -- 31 1974 Griffith Ind. Propane Fire -- 32 1974 India Crude Oil Explosion -- 33 1974 Czechoslovakia Ethylene Explosion UVCE 14 D, 79 I, 34 1974 Mississippi,
USA Butane Explosion UVCE 24 I,
35 1975 Beck, Netherlands
Hydrocarbons Explosion 1 D
36 1975 Lousiania, USA Propane Flammable -- 37 1975 Philadelphia Pa Crude Oil
Vapour Explosion 8 D, 2 I
38 1975 Antwerp Belgium
Ethylene Explosion UVCE --
39 1976 Los Angles, California
Gasoline -- 6 D, many injured
40 1977 India Hydrogen Explosion 20 I 41 1978 Waverly, Tenn Propane Explosion (on
railway) 12 D, 50 I
42 1979 Bantry Bay, Eise Oil Explosion (on oil tanker at terminal)
50 D,
43 1988 India Naphtha Pool Fire 25 D, 23 I
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 32 of 77
PAST ACCIDENTS (C3 Fraction)
Table-10
Accidents Year
Date Country Address Injuries Scene
5230 1951-0707
USA Port Newwark, New Jersy
11 Explosion and fire of 70 tanks at a tank yard
3914 1955-0719
D Ludwigshafen 2 Explosion and fire at tank wagon
4255 1956-0729
USA Amarillo, Taxes .> 32 BLEVE of 3 oil tanks
8888 1956-1022
USA Cottage Grove, Oregon
12 BLEVE of LPG storage tank
0224 1957-0108
CDN Montreal 1 Overflow butane sphere
0375 1958-0103
D Celle Explosion of tank wagons
353 1959-0528
USA MC KAittrict 2 Explosion of storage tanks
308 1966-0104
F Feyzin 48 Explosion of tanks at refinery
3906 1968-0101
USA Dunreith BLEVE of tank wagon after derailment caused by broken rail
307 1969-1205
USA Laurel, Mississippi 33 Derailment of train with 15 tank wagons, Explosion & Fire
7624 1969-1203
NL Unknown Rupture of tank by fire
361 1970-1621
USA Cresent City, LLinols
66 Derailment and explosion of nine tank wagons
373 1971-1019
USA Houston, Texas 50 Derailment of 18 tank wagons explosion and fire
3891 1971-1118
NL Nieuwenhoorm Explosion of cylinder caused fire of Terminal
3455 1972-0209
USA Twksburry, Massachusetts
21 Collision tank vehicle with lines of tank causing BLEVE of storage tank
681 1972-0330
BR RIO De Janerio 53 BLEVE of a l tank
2521 1973-0705
USA Kingam, Arizona 96 BLEVE of tank wagon caused explosion and fire of LPG distribution plant
471 1973 USA New York Rupture of propylene of storage tank, level of tank
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 33 of 77
Accidents Year Date
Country Address Injuries Scene
2549 1974-0111
USA West Saint Paul, Minnesoia
6 Explosion of tank
2544 1974-0212
USA Oneonta, New York 25 Derailment and explosion of tank wagons
667 1974-0417
D Bielefeld, Brackwedde
Derailment of 36 tank wagons, fire explosion and BLEVE
7527 1974-1202
NL Haariennermeer- 1 Fire at car repair
4260 1975-0622
USA DES Moines, IOWA 3 Derailment and rupture of tank wagons
7352 1976-0825
NL Loosdrecht Fire and explosion in car
3918 1976-0831
USA Gadsen, Alabama 28 Explosion of tank vehicle and storage tanks during transipment
2071 1976-1126
USA Belt, Montana 22 Derailment and explosion of several tank wagons
4137 1977-0206
USA Boynton Beach, Florida
BLEVE of LPG cylinders caused by derailment freight train
669 1977-0220
USA Dallas, Taxas 1 Derailment of tank wagons
4235 1977-0423
USA Long Island, New York
1 BLEVE cylinders on lorry
3377 1977-0519
USA Hawley, Pennsylvania
Fire and BLEVE of tank on tar
2522 1977-0519
USA Pocono Mountains Pennsylvania
1 Leakage supply line caused explosion vans
618 1978-0222
USA Waverly, jernessee 43 Derailment of several tank wagons caused by broken wheel
2119 1978-0530
USA Texas City, Texas 10 11 tank explored by unknown cause in 45 minutes
209 1978-1218
NL NIJMEGEN BLEVE of tank vehicle at fuel station during transshipment
2736 1978-1218
NL Zwolle 6 Explosion of gas cylinder in measure car
1591 1979-0549
NL Vlaardingen 2 Fire in van and explosion of gas cylinder
1639 1979-0601
NL S. Gravenzande 2 Explosion of gas cylinder during fire in barn
1634 1979-0704
NL Ostflakgee Explosion of two cylinders and one oil tank
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 34 of 77
Accidents Year
Date Country Address Injuries Scene
2575 1979-0713
NL Rotterdam Explosion of cylinder in van
1630 1979-0817
NL De MEEM Overheating of kettle with tar caused explosion of gas cylinder
953 1979-0908
USA Pakton, Taxas 8 Derailment of 33 train wagons with chemicals, explosion and fire for 2.5 days
1568 1979-1203
NL Haarlemmermeer Explosion of tank in car
1181 1980-0105
NL Rotterdam 1 Fire in bus station, LPG tank explored
1166 1980-0108
NL Eriecom, River Waa 2 Collision of tanker “Kombi 21” and vessel “Rodort 6” explosion, fire
3922 1980-0303
USA Los Angles, California 2 Overturn and explosion of tank vehicle loaded with gasoline
0706 1980-0606
NL Rotterdam Fire in factory store
2701 1980-0804
NL RAAITE Fire in motor compartment of car, BLEVE of tank
0919 1980 NL Road Breeda to BAVEL
Mobile milling machine with gas tank explored
1520 1980-1125
NL OOSTERMOLDGE 1 Explosion of tank in car during assemble
3419 1980 D Kries Borken Weseko 2 Fire and explosion of tank vehicle
1836 1981-0302
NL Weirden Fire and explosion of gas cylinders in stored caravans
2052 1981-0409
NL Apeldoorn Fire of carabans near LPG installation
2092 1981-0510
NL Haarlem Fire and explosion of storage Barn
2504 1981-0713
NL Beuwingen 1 Explosion of gas cylinder in house
2561 1981-0816
NL Oldeholtrade, Wolvega
1 Explosion of gas tank in car by collision
3988 1981 NL Tiel 1 VW Transporter on fire, tank exploded
4350 1981 USA Unknown 17 BLEVE of cylinder in converted coach
5535 1981 6B Yately, Hahpshire Explosion of car tank in garage
7640 1982-0113
NL Alkmaar Fire and rupture of cylinder explosion of a plumber gas
3949 1982- NL Den hag Cylinder
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 35 of 77
0525 3960 1982-
0601 NL Haarklem Explosion of a cylinder in
car Accidents Year
Date Country Address Injuries Scene
3972 1982-0621
NL Grootbroek 1 Cycling person hit fatally by fragment of cylinder
4054 1982-0626
CDN Blairmore, Alberta Derailment and rupture of several tank wagons
7642 1982-0916
NL Unknown Rupture of gas tank in car by overspeed
5681 1982-0928
USA Livingston, Louisiana Derailment freightain by overspeed
4449 1982 ET SUEZ 19 Fire and explosion of gas pipeline
8227 1984-0315
NL Unknown Plastic deformation of tank due to overtheating by fire
8228 1984-0709
NL Rosmalen Rupture of a car link due to fire
7942 1984-0723
USA Romeoville and lemont
22 Explosion and fire at refinery llinois
8235 1984-0921
NL Bruchterveld, Hardenberg
Rupture of cylinder
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 36 of 77
RELEASE OF HAZARDOUS SUBSTANCE
POOL
VAPOUR
FLASH
IGNITION
FIRE
YES
CONTINUOUS
IGNITION
DISPERSION
VAPOUR CLOUD
EXPLOSION
PRESSURE HEAT
EFFECTS
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 37 of 77
6.7 PROPERTIES OF MATERIALS HANDLED
Petroleum products like, Motor Spirit (MS), Superior Kerosene Oil (SKO),
High Speed Diesel (HSD) and FO are handled in the Terminal. All these
products are a combination of hydrocarbons and are highly inflammable.
Motor Spirit is a class-A type petroleum liquid (Flash Point <23°C), Superior
Kerosene and High speed diesel are of class B type (Flast Point between
23°C and 65°C) and FO are of C type(Flash point>65o)according to
convention. The products, when spilled from the containment will cause fire if
they get a contact with an ignition source. Incomplete combustion of these
hydrocarbons may generate carbon monoxide, which may cause toxicity as
well as explosion. However, fire is the main hazard. Lower the flash point,
higher is the possibility of ignition and hazard. The light hydrocarbons will
evaporate from these petroleum oil liquids, which may catch fire if they get
into contact with an ignition source. Properties of the products handled are
given in Table.
PROPERTIES OF LIQUID HANDLED
Properties Products
MS SKO HSD FO
1 Boiling point, ºC (range)
30-150 150-300 260-380 50-215
2 Density at 15 ºC 0.73 0.81 0.80 0.95 3 Flash point, ºC <23 >35 >32 >66 4 Vapour press. At 38 ºC
(kg/Cm2 abs) 6-10 0.2 0.1 <0.1 psi
5 Heat of combustion BTU/LB
18,800 21700 18,700 18,800
6 Auto ignition temp ºC 280 210 380 220-250 7 LFL (% V/V) 1.4 0.5 .5 1 8 UFL (% V/V) 7.6 5.0 5.0 5
LFL : Lower Flammability Limit UFL: Upper Flammability Limit
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 38 of 77
6.8 HAZARDS OF EQUIPMENT/PIPELINE HANDLING PETROLEUM PRODUCTS
The hazard of equipment/pipeline handling petroleum products is the potential
loss of integrity of the containment with subsequent release of liquid causing
fire. The pipelines carry large quantities of petroleum liquid. A rare pipeline
fracture would release large quantities of hydrocarbons. The products would
get collected in the neighbourhood of the pipeline and may lead to a fire
hazard if it gets source of ignition and proper precautions are not taken.
Catastrophic failures of the shell of a storage tank are very rare phenomenon,
which may occur due to earthquake or due to aerial bombardment during war.
However, vapour coming out through the vent line of fixed roof tank or through
vapour seal round the shell in floating roof tanks may be ignited through
lighting. However, such cases are also very rare. In such cases the whole
tank may be on fire. Corrosion in the tanks may cause small holes causing
release of petroleum liquid from the tanks. However, in such cases the oil will
be contained in the dyke. In case of oil spill collected on ground an oil pool will
be formed. An ignited pool of oil is called Pool Fire. It creates long smoky
flames. The wind may tilt the flame towards ground causing secondary fires
and damages. Radiation from the flame can be very intense near the fire but
falls of rapidly beyond 3-4 pool diameters. Such fires are very destructive
within the plant area and near the source of generation.
In case of formation of holes on the above ground pipeline the liquid may
escape in the form of jet and may catch fire if it gets an ignition source.
Damage due to heat radiation from such jets is mostly limited to objects in the
path. However, the ignited jet can impinge on other vessels and the pipelines
causing domino effect.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 39 of 77
6.9 BRIEF REVIEW OF INBUILT DESIGN SAFETY
The followings the minimum consideration have been made for tanks:
a) The design and construction of the tanks are carried out according to the
API 650 (latest edition). The floating roof tanks are designed for an internal
pressure equal to atmospheric pressure. Class B fixed roof tanks are
designed for 1.0 kPa of over pressure and -0.5 kPa of vacuum. The design
product filling and withdrawal rates for tanks shall be 1500 cbm/hr
irrespective of the pump-in and pump-out rates. There are separate
nozzles for Product inlet and outlet. All tank drains (rest evacuation and
water drain off) shall be installed at the lowest point of the tank, in order to
guarantee good draining.
b) Annular bottom plates shall be provided for all above ground storage
tanks.
c) Tank bottom design shall include butt welded annular plates. Rectangular
and sketch plates are lap welded such that there is positive and
uninhibited flow of water across the tank bottom to the centre sump. Any
pad or permanent structure in the tank has been provided with appropriate
weep holes to avoid the entrapment of water.
d) Tank shell is butt welded. Consecutive tiers offset by one third of a plate
length such that the vertical butt welded seams are only in line every third
tier.
e) Tank roof design for cone roof are with internal roof truss with a frangible
fillet weld to be made between top curb angle and roof plates which will
rupture in case of tank internal explosion in preference to rupture of the
tank at any other location.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 40 of 77
f) All tanks shall be equipped with surrounding handrails, staircases etc.
g) Appropriate spiral stairways shall be provided to each Tank for efficient
operations. Stair treads and walkways are made of open galvanized
grating.
h) Each tank will be provided with roof manholes, and with two shell
manholes orientated at 180 to each other in order to facilitate venting prior
to tank entry.
i) Fixed Roof Product tanks have been provided with pressure– vacuum (PV)
valves with 100 % capacity redundancy. Floating roof tanks are fitted with
free vents with 100% redundancy in venting capacity. Floating Roof Tanks
shall be provided with RIM Vents and other standard accessories. The
Underground tanks shall be provided with free vent. The vent outlets for
free vents are provided with birds nets with appropriate holding devices
j) Appropriate manual dip hatches and gauge nozzles shall be fitted to the
roof of each tank.
k) Tanks shall be fitted with an appropriate number of earthing bosses,
holding down bolts, wind girders and water spray deflectors according to
code requirements and local climatic condition.
l) The tanks shall be provided with sprinklers and foam feeding devices
according to the regulations.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 41 of 77
m) Underground tanks shall be installed in underground pit. The pits shall be
backfilled with sand/murrum. The tanks shall be provided with holding
down arrangement. External Wrapping and Coating are provided to take
care of Soil corrosion.
n) The product storage tanks in the tank farms shall be equipped with level
indicators. For sampling and hand gauging a separate guide pole shall be
installed. Gauging poles in the floating roof tanks are hot dip galvanised
after cutting the slots.
o) The tanks shall be properly earthed for protection against lightning and
discharge of possible static electricity.
6.9. Product Pipeline Systems
The pipeline from railway siding to terminal and within the terminal is
constructed in accordance relevant API codes/OISD standards.
The entire pipeline system shall be protected against thermal expansion by
way of a properly designed pressure relieving system connected to the
product tanks.
Pump House at the Terminal
Sufficient numbers of Loading and Unloading Product Pump Units (PPUs)
shall be installed, which are connected to the pipelines.
The thermal relief valve system has been designed in such a way that the
outlet of TRV end up to the corresponding product tank. The pipe material and
structural steel are painted to protect against atmospheric corrosion.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 42 of 77
6.10 Fire detection and protection system
Fire Protection System has been designed for fighting fire for 4 hrs. The
firewater system has been designed as per OISD standards. In addition
portable fire fighting equipments have been placed at the pump station, tank
farms, truck loading station, sub-station and office building for use as first-aid.
Key features are:
Fixed Roof tanks shall be fitted with Water Sprinklers system and fixed
foam pouring system.
In addition to OISD requirements all Fixed Roof tanks shall be provided with roof
cooling arrangement
Floating Roof tanks shall be provided with Sprinklers and Foam system.
Hydrants/ Monitors shall be provided at TWD siding, TLF area, Tank Farms,
Pump Houses, office/ lab etc.
The installation will made in such a way, that
1) The source of fire would be recognized and registered by the fire
alarm,
2) The water pumps shall be activated for fighting fire,
3) Sufficient foaming agents to fight the fire shall be available at least for 1
hour,
4) The necessary fire fighting measures can be carried out within few
minutes.
Necessary steps are taken to ensure starting of fire protection drill once the
alarm is raised by the fire alarm system. Portable fire extinguishers of 10 - 75
kg shall be installed on pump stations, truck facilities and buildings; the size
depends on the object concerned. Electrical rooms are protected by Carbonic
Acid (CO2) fire extinguishers. Furthermore, mobile fire fighting with foam
monitors, hoses, etc. shall be also considered.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 43 of 77
Fixed fire fighting monitors shall be located at all places of operation e.g. the
pump houses, TWD siding , Tank farms, and truck loading station, each with a
capacity of 144 m³/h. Sufficient hydrants have been installed in the tank
storage terminal, distance between two monitors / hydrants is maximum 30 m.
Water Supply Water storage Tanks (2 No’s of 4976 KL Each above ground) shall be
installed for supplying water for 4 hours without external supply. A closed loop
pipeline system ensures that all parts of the tank storage terminal will be
supplied with extinguishing and cooling water. Fire water will be supplied
from KMWSA.
Foam Devices
The tanks shall be equipped with fixed foam pipelines. As the tanks of class A
products are floating roof tanks, only a rim fire with a foam application rate of
12 LPM/sqm have been taken into account. For all other tanks full surface
with 5 LPM/sqm foam rate have been considered. The surface cooling rate
shall be 3 LPM / sqm for all tanks within 30 m of the tank on fire while for other
tanks it shall be 1 LPM/sqm. Foam shall be sufficient for a one hour extinguishing
process.
For surface / spill fires foam spraying on the tank farms shall be executed by
fixed and/or mobile monitors and hoses.
Sufficient portable fire extinguishers, hoses, monitors, fire protection suits,
breathing apparatuses etc. are available as per requirement.
Tank fields
The water accumulated during fire fighting within the tank farms can be
released from the separate emergency drain pipes with butterfly valves
through the surface drain to channel leading to Oil water separator units or to
the outside surface drain through an oil trap depending upon the
contamination level of the water. The valves are usually closed and sealed.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 44 of 77
6.11. Safety valves
To prevent building of pressure and consequent damage two numbers of pressure
vacuum valves will be provided on the roof of Tank no 5 & earmarked for storage of
M.S
6.12 Fire Alarm System
Conventional type Fire alarm system will be provided in following areas;
a) Truck Unloading/Loading (Manual Call Points)
b) Tank Farm (Manual Call Points).
c) Office / Admn. Building .
d) Sub-Stations .
6.13 Source of Signaling
The source of signaling is considered as manual call points. These are
considered for the areas where manual warning is to be initiated on
notice of fire. They are mostly provided for open areas or near to access
doors, truck loading, pump house, tank farm, administrative building, etc.
6.14 Portable Fire Fighting Apparatus
Following types of fire extinguishers and other fire fighting apparatus
specified for installation in vulnerable areas of the plant, administrative
block, control room, fire water pump house. MCC etc as per OISD
guidelines.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 45 of 77
Sl. No. Type of Area Protable Extinguishers
i Lube Godown 1 No. 10 Kg DCP extinguisher for every 200 m2 or min.2 Nos. in each Godown whichever is higher.
ii Lube filling shed 1 No. 10 Kg DCP extinguisher for 200 m2 or min. 2 Nos.in each Shed whichever is higher.
iii Storage of Class-A/B in packed containers and stored in open/closed area
1 No. 10 Kg DCP extinguisher for 100 m2 or min. 2Nos. in each Storage Area whichever is higher.
iv
Pump house upto 50 HP (Class A & B) Above 50-100 HP Beyond 100 HP
1 No. 10 Kg DCP for 2 pumps. 1 No. 10 Kg DCP for each pump. 2 Nos. of 10 kg or 1 no. of 25 kg DCP for each pump
v Pump House (Class – C) Up to 50 HP Above 50 HP
1 no. 10Kg DCP for every 4 pumps up to 50 HP. 2 nos. 10 Kg DCP or 1x25 kg DCP for 4 pumps.
vi Tank Truck loading and unloading for POL/specially products
1 No. 10 Kg DCP extinguisher for each bay plus 1 No. 75 Kg DCP extinguisher for each gantry.
vii Tank wagon loading and unloading gantry (siding)
1 No. 10 Kg DCP extinguisher for every 30 m of gantry/siding plus 1 No. 75 Kg DCP extinguisher for each gantry/siding.
viii Above ground tank
2 Nos. 10 Kg DCP extinguishers for each tank plus 4Nos. 25 Kg DCP extinguishers for each Tank Farm positioned at four corners. In case of adjoining tank farms, the no. of 25 Kg extinguishers can be reduced by 2 nos. per tank farm.
ix Under ground Tank Farms
2 N o s. 10 Kg DCP extinguisher for each Tank Farm
x Other Pump House 1 No. 10 Kg DCP extinguisher for every two pumps or min 2 Nos. 10 Kg DCP extinguisher for each Pump House whichever is higher.
xi Admn. Building/Store House 1 N o. 10 Kg DCP extinguisher for every 200 m2 or min. 2 Nos. 10 Kg DCP extinguishers for each floor of Building/Store whichever is higher.
xii Generator Room upto 250 KVA Above 250 KVA
1 no. 10 kg. DCP AND 1 NO. 4.5 KG. CO2 for every generator 2 nos. 4.5 kg. & 1 no. 10 kg. DCP
xiii Main Switch Room 1 No. 4.5 Kg CO2 extinguisher for every 25 m2 plus 1No. 9 Liter sand bucket.
xiv Computer Room/Cabin 2 N os. of 2 Kg CO2 or 2 Nos. of 2.5 Kg Clean Agent extinguisher per Computer Room and 1 No. 2 Kg CO2 or 1 No. 1.0 Kg Clean Agent extinguisher per cabin.
xv Security Cabin 1 No. 10 Kg DCP extinguisher per cabin. xvi Canteen 1 No. 10 Kg DCP extinguisher for 100 m2 . xvii Laboratory 1 No. 10 Kg DCP extinguisher & 1 No. 4.5 Kg CO2
extinguisher. xviii Effluent Treatment Plant 1 No. 75 Kg. & 2 nos. 10 Kg. DCP Extinguisher xix Workshop 1 No. 10 Kg DCP extinguisher & 1 No. 2 Kg CO2
extinguisher. xx Transformer 1 No. 10 Kg. DCP extinguisher per transformer. xxi UPS/Charger Room 1 No. 2 Kg. CO2 extinguisher.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 46 of 77
Chapter-7
RISK ASSESSMENT
7.1 Introduction
The Budge Budge Installation of Bharat Petroleum Corporation Ltd which
includes the facilities for receipt, storage and dispatch of petroleum products
mainly poses fire hazard due to unwanted and accidental release of
hydrocarbons. However, due safeguard has been taken in design, installation
and operation of the system to prevent any unwanted release of hydrocarbons
from their containment. However, in the event of release of hydrocarbons from
their containment, there is a risk of fire. The chances of explosion are less.
This section deals with various failure cases leading to various hazard
scenarios, analysis of failure modes and consequence analysis.
Consequence analysis is basically a quantitative study of hazard due to
various failure scenarios to determine the possible magnitude of damage
effects and to determine the distances up-to which the damage may be
affected. The reason and purpose for consequence analysis are manifolds
like.
Computation of risk
Aid better plant layout
Evaluate damage and protective measures necessary for saving
properties & human lives
Ascertain damage potential to public and evolve protective measures
Formulate safe design criteria and protection system
Formulate effective Disaster Management plan
The results of consequences analysis are useful for getting information about
all known and unknown effects that are of importance when failure scenarios
occur and to get information about how to deal with possible catastrophic
events. It also gives the plant authorities, workers district authorities and the
public living in the area an understanding of the hazard potential and remedial
measures to be taken.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 47 of 77
7.2 Modes of Failure
There are various potential sources of large/small leakages in any installation.
The leakages may be in the form of gasket failure in a flanged joint, snapping
of small dia pipeline, leakages due to corrosion, weld failure, failure of loading
arms, leakages due to wrong opening of valves & blinds, pipe bursting due to
overpressure, pump mechanical seal failure and many other sources of
leakage.
7.3 Damage Criteria
The damage effect of all such failures mentioned above are mainly due to
thermal radiation from pool fire or jet fire due to ignition of hydrocarbons
released since the petroleum products are highly inflammable specially Motor
sprit oil whose flash points are low.
The petroleum products released accidentally due to any reason will normally
spread on the ground as a pool or released in the form or jet in case of
release from a pressurized pipeline through small openings. Light
hydrocarbons present in the petroleum products will evaporate and may get
ignited both in case of jet as well as liquid pool causing jet fire or pool fire.
Accidental fire on the storage tanks due to ignition of vapour from the tanks or
due to any other reason may also be regarded as pool fire.
Thermal radiation due to pool fire or jet flame may cause various degrees of
burns on human bodies. Also its effect on inanimate objects like equipment,
piping, building and other objects need to be evaluated. The damage effects
due to thermal radiation intensity are elaborated in the Table .
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 48 of 77
DAMAGE DUE TO INCIDENT THERMAL RADIATION INTENSITY
Incident Thermal Radiation Intensity
KW/M2
Type of damage
37.5 Can cause heavy damage to process equipment, piping building etc. (100% lethality)
32.0 Maximum Flux level for thermally protected tanks.
12.5 Minimum energy required for piloted ignition of work(50%lethality)
8.0 Maximum heat flux for un insulated tanks
4.5 Sufficient to cause pain to personnel if unable to reach cover within 20 sec. (% of 1st Degree Burn)
1.6 Will cause no discomfort to long exposure.
0.7 Equivalent to solar radiation
PHYSIOLOGICAL EFFECTS OF THRESHOLD THERMAL DOSES
Dose Threshold KJ/M2
Effect
375 3rd Degree Burn
250 2nd Degree Burn
125 1st Degree Burn
65 Threshold of pain, no reddening or blistering of skin caused.
1st Degree Burn > Involve only epidermis, blister may occur example-
sun Burn.
2nd Degree Burn > Involve whole of epidermis over the area of burn
plus some Portion of dermis.
3rd Degree Bun > Involve whole of epidermis and dermis;
subcutaneous Tissues may also be damaged.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 49 of 77
In case of Motor Spirit having relatively higher vapour pressure, there is a
possibility of vapour cloud explosion. Damage effects due to blast over pressure is
given in Table.
DAMAGE EFFECTS DUE TO BLAST OVER PRESSURE
Blast Over Pressure (Bar) Damage Type
0.30 Major Damage to Structures
0.17 Eardrum Rupture
0.10 Repairable Damage
0.03 Damage of Glass
0.01 Crack of Windows
7.4 Dispersion and Stability Class
In calculation of effects due to release of hydrocarbons dispersion of vapour
plays an important role as indicated earlier. The factors which affects
dispersion is mainly Wind Velocity, Stability Class, Temperature as well as
surface roughness. One of the characteristics of atmosphere is stability,
which plays an important role in dispersion of pollutants. Stability is
essentially the extent to which it allows vertical motion by suppressing or
assisting turbulence. It is generally a function of vertical temperature profile of
the atmosphere. The stability factor directly influences the ability of the
atmosphere to disperse pollutants emitted into it from sources in the plant. In
most dispersion problems relevant atmospheric layer is that nearest to the
ground. Turbulence induced by buoyancy forces in the atmosphere is closely
related to the vertical temperature profile.
Temperature of the atmospheric air normally decreases with increase in
height. The rate of decrease of temperature with height is known as the Lapse
Rate. It varies from time to time and place to place. This rate of change of
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 50 of 77
temperature with height under adiabatic or neutral condition is approximately
1 °C per 100 metres. The atmosphere is said to be stable, neutral or unstable
according to the lapse rate is less than, equal or greater than dry adiabatic
lapse rate i.e. 1°C per 100 metres.
Pasquill has defined six stability ranging from A to F
A = Extremely unstable
B = Moderately unstable
C = Slightly unstable
D = Neutral
E = Stable
F = Highly Stable
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 51 of 77
7.5 Selected Failure cases The mode of approach adopted for consequence is first to select the probable
failure scenarios. The failure scenarios selected are indicated Table.
LIST OF FAILURE CASES Sl.No Failure Scenarios Likely
Consequences Credible/
No Credible Failure
Frequency 1 Tanks on Fire
i. MS Tank ii. SKO Tank iii. HSD Tank iv. FO Tank v. ATF Tank
Thermal Radiation
Partially credible
5 x 10-6
2 Vessel connection failure for inlet / outlet lines of MS.SKO,HSD(Road tanker loading)
Thermal Radiation for MS,SKO & HSD and also explosion for MS
Partially credible
5 x 10-6
3 TLF Pumps discharge lines Full bore failure for MS,SKO & HSD (Road Tanker Loading)
do
Non Credible
3 x 10-6
5 Gasket failure in pump discharge line SKO,MS, & HSD (Road Tanker Loading Pump)
Thermal radiation Credible 0.5 x 10-6 P/H of opration.
6 Failure of 3’ dia loading arm MS,SKO,HSD
-do- Partially Credible
3 x 10-8 P/H of operation
7 Failure of 3’ dia unloading hose MS,SKO,HSD
-do- Credible 3 x 10-5P/H of operation
8 Mechanical seal failure for MS.SKO & HSD pumps for Tank truck loading
Thermal radiation Credible
It will be seen that most of the probable cases of failures have been considered for consequence analysis.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 52 of 77
Chapter-8 CONSEQUENCE ANALYSIS :
8.1 Consideration for Maximum credible Accident scenario: HAZARD ASSESSMENT (QUANTIFICATION) 8.1.1 Hazard Distances In The Event of Storage Tanks on Fire Scenario-1 Calculation of hazard distance due to storage Tank on Fire (HSD)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
1 T1 29.00 x 13.50 8917.00 HSD Fixed Roof Storage tank of HSD on Fire .Entire roof surface will burn
METEOROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum relative humidity of 41 % have been
considered for the calculation of hazard distance.
Result
Event No Scenario
Tank diameter
Radiation Intensity inside tank
Hazard Distance from the centre of the tank (m)
(m) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
1. HSD
29 36.15 Within
Tank Within Tank 16.3 29.5
.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 53 of 77
Scenario-2 Calculation of hazard distance due to storage Tank on Fire (MS)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
2 T5 24.00 x 12.00 5429 MS Floating roof
Storage tank of MS on Fire.Entire roof surface will burn
METEOROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum relative humidity of 41 % have
been considered for the calculation of hazard distance.
Result
Event No Scenario
Tank diameter
Radiation Intensity inside tank
Hazard Distance from the centre of the tank (m)
(m) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
2. MS
24 26.60 Within
Tank 13.30 16.60 27.30
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 54 of 77
Scenario-3 Calculation of hazard distance due to storage Tank on Fire (SKO)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
3 T7 12.60 x 13.50 1683 SKO Fixed Roof Storage tank of SKO on Fire.Entire roof surface will burn
METEOROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum relative humidity of 41 % have
been considered for the calculation of hazard distance.
Result
Event No Scenario
Tank diameter
Radiation Intensity inside tank
Hazard Distance from the centre of the tank (m)
(m) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
3 SKO
12.60 42.05 Within
Tank 8.00 11.80 26.1
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 55 of 77
Scenario-4 Calculation of hazard distance due to storage Tank on Fire (ATF)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
3 T9 20.00 x 13.50 4241 ATF Fixed Roof Storage tank of ATF on Fire .Entire roof surface will burn
METEOROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum relative humidity of 41 % have
been considered for the calculation of hazard distance.
Result
Event No Scenario
Tank diameter
Radiation Intensity inside tank
Hazard Distance from the centre of the tank (m)
(m) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
4 ATF
20.00 35.70 Within
Tank 11.70 15.50 23.80
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 56 of 77
Scenario-5 Calculation of hazard distance due to storage Tank on Fire (FO)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
3 T10 20.00 x 13.50 4241 FO Fixed Roof
Storage tank of FO on Fire .Entire roof surface will burn
METEOROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum relative humidity of 41 % have
been considered for the calculation of hazard distance.
Result
Event No Scenario
Tank diameter
Radiation Intensity inside tank
Hazard Distance from the centre of the tank (m)
(m) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
5 FO
20.00 36.05 Within
Tank Within Tank 14.3 26.5
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 57 of 77
8.1.2 HAZARD DISTANCES IN CASE OF POOL FIRE
Scenario -1 (Spillage within dyke area, complete containment failure)
Calculation of hazard distance in case of pool Fire – (MS)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
Pool Area M2
2 T5 24.00 x 12.00 5429 MS Floating roof 4279
METEOROLOGICAL DATA CONSIDERED
Temperature(Max ) 36.8o C/ 309.8oK
Humidity(Min)
41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2
Result
Sl no Scenario
Pool Area Radiation Intensity inside pool
Distance from the edge of the pool (m)
(m2) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
1. MS 4279 20.05
Within pool
Within pool
2.3 37.05
Scenario -2(Spillage within dyke area, complete containment failure)
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 58 of 77
Calculation of hazard distance in case of pool Fire – (HSD)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
Pool Area M2
1 T1 29.00 x 13.50 8917 HSD Fixed Roof 7727
METEOROLOGICAL DATA CONSIDERED
Temperature(Max ) 36.8o C/ 309.8oK
Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2
Result
Sl no Scenario
Pool Area Radiation Intensity inside pool
Distance from the edge of the pool (m)
(m2) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
1. HSD 7727 20.00
Within pool
Within pool
1.7 27.00
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 59 of 77
Scenario -3(Spillage within dyke area, complete containment failure)
Calculation of hazard distance in case of pool Fire – (SKO)
Tank Farm
Tank No.
Dimension Dia & Height(m)
Capacity (KL)
Product Tank Type
Pool Area M2
3 T7 12.60 x 13.50 1683 SKO Fixed Roof 3982
METEOROLOGICAL DATA CONSIDERED
Temperature(Max ) 36.8o C/ 309.8oK
Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2
Result
Sl no Scenario
Pool Area Radiation Intensity inside pool
Distance from the edge of the pool (m)
(m2) (kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
3 SKO 3982 20.03
Within pool
Within pool
1.4 26.00
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 60 of 77
8.1.3 CALCULATION OF HAZARD DISTANCE DUE TO POOL FIRE
PIPELINE RUPTURE AT TLF GANTRY
Scenario -1 Pipeline rupture (open area) Specification considered 1. Product MS 2. Pipeline dia 300mm 3. Pump discharge 300KL/H 4. Duration 900 Second(There will always be people around the area. Spillage is likely to be identified within the short period and hence 5 min duration is considered ) 5. Pump discharge pressure 4Kg/M2
METEROLOGICAL DATA CONSIDERED
Temperature(Max ) 36.8o C/ 309.8oK
Humidity(Min) 63%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2 Quantification of hazard
Sl no Scenario
Radiation Intensity inside pool
Distance from the centre of the pool (m)
(kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
1. MS 20.60 Within Pool Within Pool 46.77 80.67
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 61 of 77
Scenario -2 Pipeline rupture (open area) Specification considered 1. Product HSD 2. Pipeline dia 500mm 3. Pump discharge 450KL/H 4. Duration 900 Second(There will always be people around the area. Spillage is likely to be identified within the short period and hence 5 min duration is considered ) 5. Pump discharge pressure 4Kg/M2
METEROLOGICAL DATA CONSIDERED
Temperature(Max ) 36.8o C/ 309.8oK
Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2 Quantification of hazard
Sl no Scenario
Radiation Intensity inside pool
Distance from the centre of the pool (m)
(kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
2 HSD 20.3 Within Pool Within Pool 82.26 144.06
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 62 of 77
Scenario -3 Pipeline rupture (open area) Specification considered 1. Product SKO 2. Pipeline dia 150mm 3. Pump discharge 120KL/H 4. Duration 900 Second(There will always be people around the area. Spillage is likely to be identified within the short period and hence 5 min duration is considered ) 5. Pump discharge pressure 4Kg/M2
METEROLOGICAL DATA CONSIDERED
Temperature(Max ) 36.8o C/ 309.8oK
Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2 Quantification of hazard
Sl no Scenario
Radiation Intensity inside pool
Distance from the centre of the pool (m)
(kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
3. SKO 20.01 Within Pool Within Pool 29.22 40.02
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 63 of 77
8.1.4 CALCULATION OF HAZARD DISTANCE DUE TO POOL FIRE FOR GASKET FAILURE IN PUMP DISCHARGE LINE
Scenario -1 Gasket Failure (25 % of the perimeter of Gasket) Specification considered 1. Product MS 2. Pipeline dia 300mm 3. Gasket Thickness 0.5mm 4. Pump discharge 300KL/H 5. Duration 1800 Second 6. Pump discharge pressure 4Kg/M2
METEROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK
Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2
Quantification of hazard
Sl no Scenario
Radiation Intensity inside pool
Distance from the centre of the pool (m)
(kW/ m2) 37.5 kW/m2
21.5 kW/m2
12.5 kW/m2
4 kW/m2
1 MS 20.3 Within Pool
Within Pool 22.51 42.31
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 64 of 77
Scenario -2 Gasket Failure (25 % of the perimeter of Gasket) Specification considered 1. Product HSD 2. Pipeline dia 500mm 3. Gasket Thickness 0.5mm 4. Pump discharge 450KL/H 5. Duration 1800 Second 6. Pump discharge pressure 4Kg/M2
METEROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK
Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2
Quantification of hazard
Sl no Scenario
Radiation Intensity inside pool
Distance from the centre of the pool (m)
(kW/ m2) 37.5 kW/m2
12.5 kW/m2
12.5 kW/m2
4 kW/m2
2 HSD 20.3 Within Pool
Within Pool 75.6 61.99
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 65 of 77
Scenario -3 Gasket Failure (25 % of the perimeter of Gasket) Specification considered 1. Product SKO 2. Pipeline dia 150mm 3. Gasket Thickness 0.5mm 4. Pump discharge 120KL/H 5. Duration 1800 Second 6. Pump discharge pressure 2Kg/M2
METEROLOGICAL DATA CONSIDERED
Temperature(Max) 36.8o C/ 309.8oK
Humidity(Min) 41%
Maximum temperature of 36.8o C and minimum humidity of 41 % have been considered for the calculation of damage distance in the case of pool fire radiation heat intensity in KW/M2
Quantification of hazard
Sl no Scenario
Radiation Intensity inside pool
Distance from the centre of the pool (m)
(kW/ m2) 37.5 kW/m2
21.5
kW/m2
12.5 kW/m2
4 kW/m2
3 SKO 20.2 not attained
not attained 17.92 29.12
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 66 of 77
8.2 VAPOUR CLOUD MODELING
SCENARIO: 1 (Complete containment failure due to pipeline rupture within the dyke area )
Specification considered
Tank Farm
Tank No. Dimension Dia & Height (Mtrs)
Capacity (KL)
Product
2 T5 24.00 x 12.00 5424 MS
METEROLOGICAL DATA CONSIDERED Temperature( Min ) 36.8o C/ 309.8oK Humidity( Max) 85% Atmospheric Stability Very stable- F Wind Velocity( Min) 11 KMPH
Wind Direction ( larger vapour cloud) S.W
Pasquill Category F ( Very stable)
Dispersion outputs for MS release from 500mm dia pipeline Calculation of distance upto LFL/ UFL Result
Event No
Material Spilled
Release mode
Spill area (dyke area)
Evaporation/ Dispersion Rate
Distance up to LFL
Distance up to UFL
14000 ppm 76000 ppm
m2 (kg/s) DW CW DW CW
1. Motor spirit Continuous 4279 103.58 35 24.3 9.3 11.2
(DW – Down Wind; CW – Cross Wind)
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 67 of 77
Consequence output for Unconfined Vapour Cloud Explosion (UVCE) In the event of MS vapour cloud finding source of ignition after complete release of 5444 KL MS
Damage distances from Vapour Cloud explosion from rupture of 400 mm Pipeline
Event No Material Spilled
Meteorological Conditions ( max) Wind Speed 2 km/hr Stability F
Amount in Explosive Limits (kg)
Damage Distance in meters for Different Overpressure
0.3 bar 0.1 bar 0.03 bar 0.01 bar
1. Motor spirit 586 96.1 152.4 321.2 789.6
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 68 of 77
8.3 REFERENCES/ MODELS USED
The calculations were conducted using OUTFLOW/ SOURCE STRENGTH ESTIMATION and CONSEQUENCE models as per the Indian Standards IS 15656: 2006 HAZARD IDENTIFICATION & RISK ANALYSIS - CODE OF PRACTICE and internationally accepted models and equations. RiskChem Engineering uses its proprietary software for consequence analysis based on these models and equations. The software has been in use over the past 15 years and the results have been accepted by various regulatory authorities in India and abroad. A copy has been purchased by the Factory Inspectorate of Tamil Nadu
POOL FIRE MODEL
Guidelines for Evaluating the Characteristics of Vapour Cloud Explosions, Flash fires and BLEVEs, (1994) by Center for Chemical Process Safety of the American Institute of Chemical Engineers1, NY.
SPILL MODEL
Spreading and Evaporation
Shell SPILLS model (Fleischer 1980)
Guidelines for use of VAPOUR CLOUD DISPERSION MODELS by Hanna and Drivas
(1996) by Center for Chemical Process Safety of the American Institute of Chemical Engineers*' NY
VAPOUR CLOUD EXPLOSION
Shock wave model
a) TNO, Methods for the Determination of Possible Damage (Green Book), CPR
16E, 1st ed. (1992).
b) Hanna, S. R., Drivas, P. J.
Guidelines for use of VAPOUR CLOUD DISPERSION MODELS by Hanna and Drivas (1996) by Center for Chemical Process Safety of the American Institute of Chemical Engineers', NY
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 69 of 77
DENSE GAS MODELLING
Heavy gas dispersions based on Thorney Island Observations (1985).
Guidelines for use of VAPOUR CLOUD DISPERSION MODELS by S R Hanna and P J Drivas (1996) by Center for Chemical Process Safety of the American Institute of Chemical Engineers', NY
EFFECTS OF THERMAL RADIATION
World Bank (1985) Manual of Industrial Hazard Assessment techniques Office of Environmental and Scientific Affairs, World Bank, Washington, D. C.
EXPLOSION DAMAGES
Guidelines for Evaluating the Characteristics of Vapour Cloud Explosions, Flash fires and BLEVEs, (1994) by Center for Chemical Process Safety of the American Institute of Chemical Engineers', NY
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 70 of 77
8.4 ACTION DURING FIRE
8.4.1 Storage Tank in Fire
a) A fire burning at the vent will not normally flash back into tank and
explode, if the tank contains product since flame arresters are provided
b) Start cooling of tanks by using water sprinklers provided on tanks as well as
by wet jets.
c) Close all valves since any removal of product will result in air being sucked
inside, with the resultant flash back and explosion.
d) Close manhole covers of other tanks if they are open. Also stop loading /
Receipt of tank wagons, into / out of the tank since it will result in eviction of
vapour due to displacement and subsequent intensification of fire.
e) Use foam to extinguish fire. Small fire can be handled with portable fire
extinguishers.
f) Fire in tank will normally burn quietly till the oxygen is consumed unless
temperature of the product is allowed to increase uncontrolled. Hence, care
must be taken to ensure that product temperature does not go high by cooling
with water sprinklers & jets. This also avoids possibility of tank rupture due to
hydrostatic pressure
g) When sufficient air vapour mixture is available inside the tank as in the case
during removal of products from tank on fire there is a distant possibility of
tank roof collapse or blow out. In such cases, immediate action should be
taken to ensure that the fire does not spread to other areas. If there is product
spill to outside, foam should be used to cover the same.
H) In such cases, foam should be pumped inside the tank for blanketing the fire
and simultaneously taking action to cool the tank shell with water and also
removing the product by pumping it cut to some other tank.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 71 of 77
i) Uncontrolled use of water on the burning product will result in product spill over
and spread of fire. In the case of heavy ends this will result in boil over and
frothing at the surface.
j) When heavy ends like HSD burn, a layer of hot oil is formed below the surface,
which extends towards the bottom. Temperature of this layer is of the order of
250° C to 300° C much above the boiling point of water. When water turns into
steam, it expands appx. 1600 times and this result in boil over. The boil over
may overflow the tank resulting in spreading of fire. Hence, in such fire, cool
down the tank by continuous water jet on the tank shell, transfer the product to
other tanks and judiciously use foam to smoothen fire.
8.4.2 Pool Fire at TLF Gantry.
A) Discharge DCP to prevent fire from spreading.
B) Shut down the pumps by cutting of power supply.
C) Remove any person who is working in the effected area.
D) Close the valves of either side to starve the fire close all tank wagon valves and
manifold valves.
E) Put foam on burning oil spills
F) Put foam on oil spills. Do not splash burning oil.
G) Use DCP or CO2 fire extinguisher on electrical fire.
H) Wet down the structure close to the fire with water
8.4.3 Gasket Failure
a. Stop Pumping
b. Close the valves of either side of flange
c. Dig pits to collect oil.
d. Built earth dykes around the oil pool to prevent spreading of burning oil.
e. Take care of the oil dropping from the leak even after extinguishing fire as
fire may occur again due to heating of oil dropped. Try to collect the oil in
containers.
f. Take action for replacement of gasket/ repair leak with due care.
.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 72 of 77
8.5.4 General
a) In case of F/R tanks, fires normally occur at F/R seats. Efforts should be
made to put foam in the correct place simultaneously cooling the tank shell
from outside
b) Incase of Oil spill the same should be blanketed with foam in order to
avoid contact with source of ignition.
c) Use DCP or CO2 fire extinguisher on Electrical fire.
d) Wet down structure close to the fire with water.
e) Discharge DCP to prevent fire from spreading.
f) In case flammable liquid pool due to containment failure, pipeline rupture
within the dyke area it is suggested to cover the flame with foam blanket.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 73 of 77
Chapter-9
RISKS AND FAILURE PROBABILITY
The term Risk involves the quantitative evaluation of likelihood of any undesirable
event as well as likelihood of harm of damage being caused to life,property and
environment. This harm or damage may only occur due to sudden/accidental release
of any hazardous material from the containment. This sudden/accidental release of
hazardous material can occur due to failure of component systems. It is difficult to
ascertain the failure probability of any system because it will depend on the
components of the system. Even if failure occurs, the probability of fire and the extent
of damage will depend on many factors like,
A) Quantity and physical properties of material released.
B) Source of ignition
C) Wind velocity and direction
D) Presence of population, properties etc nearly.
Failure frequency of different components like pipes, valves, instruments, pressure
vessels and other equipment manufactured in India are not available. The statutory
authority has tried to collect the information and form an acceptable data bank to be
used under Indian condition.
Failure frequency data for some components accepted in U.S.A and European
Countries are given Table.
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 74 of 77
FAILURE FREQUENCY DATA
Sl.No Item Failure Frequency / 106 years
1 Shell Failure a) Process/pressure vessel b) Pressurized Storage Vessel
3 1
2 Full Bore Vessel Connection Failure (Diameter MM) <25 40 50 80 100 >150
30 10 7.5 5 4 3
3 Full Bore Process Pipeline Failure D< 50mm 50<d<150mm D>150mm
0.3* 0.09* 0.03*
4 Articulated Loading / Unloading arm Failure
30 x 108 **
* Failure frequency expressed in (n/106 years) ** Failure frequency expressed in (hr of operation)
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 75 of 77
Chapter-10
RECOMMENDATIONS & CONCLUSIONS
The recommendations & conclusions as revealed from Risk Analysis study are as
follows:
i) The individual Risk value of 1.0 E-6/ year as evident from the ISO Risk
contour is not always confined within the plant premises.Hazard distances
arrived from the consequence analysis also reveals that in most of the
cases hazard is not always confined within the plant premises.
ii) Health check and maintenance of the equipment including storage tanks and
pipelines should be done at regular intervals to avoid any major failure.
History sheet of all major equipment giving the details of fabrication data /
design data to be maintained.
iii) Instruments and trip interlocks should be checked and calibrated at regular
intervals to prevent any wrong signaling and consequent failures.
iv) Fire fighting system as well as portable fire-fighting appliances should be
always kept in good working condition. Safety appliances should be also
checked and kept in good working condition.
v) Mock Drills should be conducted at regular intervals.
vi) To reduce the failure frequency due care has been taken in design,
construction, inspection and operation. Well-established codes of practices
have been followed for design, inspection and construction of the facility.
vii) The installation should be operated by experienced personnel trained for
operation of such facility and also in fire fighting. Safe operating practice (
SOP) to be drawn and critical SOP to be displayed near the TLF,Tankfarm,
Pump house and manifold
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 76 of 77
viii) Smoking should be strictly prohibited inside the installation.
ix) Non -sparking tools should be used for maintenance to avoid any
spark.
x) The storage tanks, pipelines and facilities in Tank Lorry Filling Shed
should be properly earthed to avoid accumulation of static electricity.
Bounding to be ensured for TLF operation. Tripping arrangement
recommended in case of failure in earthing / bounding system.
xi) Entry of personnel should be restricted inside the licensed area.
xii) A elaborate Disaster Control Management Plan containing a mutual
aid agreement should be drawn to meet major exigencies.
xiii) Two High Velocity Long Range (HVLR) monitors are to be positioned
for each tank farm area specially for MS, HSD & SKO tank farm.
xiv) Rim Seal protection system is to be maintained properly.
xv) Failure data must be recorded.
xvi) Maintenance schedule is to be drawn and the same should be
strictly adhered to.
xvii) Vapour Clooud Consequence and its recommendation to be included.
xviii) VDS should be installed and to be continuously monitored
xix) High level alarm to be connected to MOV so as to close the valve and to
be maintained properly.
xx) ESD to be maintained in order
QUANTITATIVE RISK ANALYSIS REPORT BPCL: BUDGE BUDGE OIL INSTALLATION
Page 77 of 77
xxi) Emergency electrical panel should include fire siren system and
electrically operated gate.
xxii) Illumination in security Room , Emergency Control Room
xxiii) Illumination in the plant area, water replenishment Pump are to be
connected to emergency panel.
xxiv) MOV should have the provision of Operation from outside the dyke
through push button for emergency operation.