quantifying risk of end result specifications
TRANSCRIPT
1
Quantifying Risk of End Result
Specifications
CalAPA Fall Conference October 25 – 26, 2017
Sacramento, CA
Tony Limas
Granite Construction Inc.
Today’s Discussion
2
Specification Tolerances – Should We care? Evolution of Specifications Best Practice for Establishing Specification Limits Types of Risk Measuring Risk - Examples Risk vs. Number of Observations Questions…
Managing Risk
3
Statistics – Ugh…
4
Specification Tolerances When specifications contain unreasonable or
unattainable material tolerances it is likely that
a contractor, providing a product using all the
care and skill normally exercised within the
industry, will fail to meet the specified
acceptance requirements. Such specifications
are said to be unbalanced assigning excessive
risk to the contractor and thus not suitable for
use.
FHWA - NHI Course No. 13442
5
Evolution of Specifications
Pre 1958
Acceptance Primarily based on Inspections vs Test Results
Specification tolerances Primarily based on Anecdotal or
shoot from the hip criteria
Contractors Struggled to Meet Acceptance Limits
Post 1958
1958 AASHTO Road Test Collected “Real Time” Test Data
Variability of Material Properties Better Understood
Information was used to establish End-Result Spec Limits 6
Evolution of Specifications (con’t)
Specifications Must:
Recognize Total Variability of Materials and Construction
Properties (Standard Deviation)
Must Apply Reasonable Risk to All Parties
7
Types of Risks
Buyer’s Risk β = Risk of Accepting “Bad” Material
Seller’s Risk α = Risk of Rejecting “Good” Material
FHWA Recommended Seller’s Risk (α): 5.0% Max.
Typically 2s About the Mean
8
9
Are Risks
Determine Buyer’s and
Seller’s Risk of
Proposed Spec Limits
Modify Spec limits,
Sample Size
and/or lot Size
Finalize The Specifications
No
Yes Acceptable
Yes
Specification
Development
Process
Measuring Risk Standard Deviation Is the measure of dispersion of a set of data from its mean. It measures
the absolute variability of a distribution; the higher the dispersion or variability,
the greater is the standard deviation and greater will be the magnitude of the
deviation of the value from their mean.
10
Measuring Risk
Transportation Related Material Properties Are:
Symmetrically/Normally Distributed About the Mean
Mean
Test Results Test Results
11
Measuring Risk (con’t) N
o. o
f S
am
ple
s
12
Mean
Material Properties Distribution PWL N
o. o
f S
am
ple
s
-3s -2s -1s +1s +2s +3s
68%
95%
99.7%
Air Voids (S) = 0.75
Target ± 0.75%
13
PWL = 68%
Target
Sellers Risk (α) N
o. o
f S
am
ple
s
-3s -2s -1s +1s +2s +3s
68%
95%
99.7%
Air Voids (s) = 0.75
Target ± 0.75%
16%
14
Sellers Risk
α = 32%
Sellers Risk (α) N
o. o
f S
am
ple
s
-3s -2s -1s +1s +2s +3s
68%
95%
99.7%
Air Voids (s) = 0.75
Target ± 1.5%
2.5%
15
Seller’s Risk
α = 5%
Target
Sellers Risk (α) N
o. o
f S
am
ple
s
-3s -2s -1s +1s +2s +3s
68%
95%
99.7%
Air Voids (s) = 0.75
Target ± 1.5%
16
Target Mean
Seller’s
Risk >5.0%
Risk (α) Evaluation Examples
Based on Specification Tolerances (vs SD)
USL = Upper Specification limit
LSL = Lower Specification Limit
Mean or Target Value
Standard Deviation: Population (S) or Sample (s)
Z Score Chart for Normal Distribution
17
Risk Evaluation Examples
Z Score Chart
18
Risk (α) Evaluation Examples
Z Score Chart
(USL - x̄)/S= Z score
(LSL - x̄)/S= Z score
Z of ≥1.96 = ≤ 5.0% Risk
19
Risk Evaluation Examples
Caltrans Proposed Binder Content Tolerance
CT Proposal ± 0.3% (1 observation)
Evaluate the Risk Associated with the Proposed Limits
20
Risk Evaluation Examples
What is the Variation for Binder Content?
Based on Statewide Pooled Data from QC/QA Projects
Population Standard Deviation (S) = 0.20
21
22
Seller’s Risk (With 0.3% Tolerance)
S
(n=1)x̄ PWL
Risk
(α)
0.20 5.0 86 14%
Binder Content
1.7 3.7 4.7 5.0 5.3 6.3 7.3
Upper limitLower limit
Target
5.0%
16%7%7%
NTS
86%
23
Sellers (other) Risk(With 0.3% Tolerance)
S
(n=2)*x̄ PWL
Risk
(α)
0.141 5.0 96 4%
Binder Content
1.7 3.7 4.7 5.0 5.3 6.3 7.3
Upper LimitLower Limit
Target
5.0%
16%2%2%
NTS
96%
*Avg. of Two Independent Samples
15
Balancing Risk and Cost A
gen
cy a
nd
/or
Co
ntr
act
or
Ris
k
Dir
ect
Co
st (
$)
1 2 3 4 5 6 7
Number of Test Samples (n)
Total Variability (SD)
Variability = variability + variability + variability
(sampling) (test method) (mat./const.)
S2QC/QA = S2
s + S2t + S2
m/c
3
26
Sellers Risk(With 0.4% Tolerance)
S
(n=1)x̄ PWL
Risk
(α)
0.20 5.0 95 5%
Binder Content
3.8 4.2 4.6 5.0 5.4 5.8 6.2
Upper LimitLower Limit
Target
5.0%
16%2.5% 1.72.5%
NTS
95%
27
Seller’s Risk(With -0.3 +0.5% Skewed Tolerance)
S
(n=1)PWL
Risk
(α)
0.20 5.0 92 8%
Binder Content
3.8 4.2 4.7 5.0 5.5 6.0 6.5
Upper LimitLower Limit
Target
5.0%
16%1% 1.77%
NTS
49%43%
x̄
28
Seller’s Risk(With -0.3 +0.5% Skewed Tolerance)
S
(n=1)PWL
Risk
(α)
0.20 5.1 95 5%
Binder Content
4.7 5.1 5.5
Upper LimitLower Limit
Mean
5.1%
16%2.5%2.5%
NTS
47.5%47.5%
x̄Target Value + 0.10
29
Skewed Binder Content Effect on Volumetrics
Air Voids
- 4.0 +
Design Binder
5.0%
16%
NTS
Target Binder + 0.105.1%
Percent Defective
3
30
Seller’s Risk(With 0.4% Tolerance)
S
(n=1)x̄ PWL
Risk
(α)
0.20 5.0 95 5%
Binder Content
3.8 4.2 4.6 5.0 5.4 5.8 6.2
Upper LimitLower Limit
Target
5.0%
16%2.5% 1.72.5%
NTS
95%
Evaluating Risk Examples (con’t)
Local Agency Relative Density Specification Local Agency 92 – 97 % (n=1)
Contractors’ Could Not Meet Specifications
Spec was Evaluated to Determine Contractors Risk
31
Risk Evaluation Examples
What is the Variation for Relative Density?
Sample Standard Deviation (s) = 1.84
Based on <30 observations from projects
32
9
33
Seller’s Risk(With 2.5% Tolerance)
S
(n=1)x̄ PWL
Risk
(α)
1.84 94.5 82 18%
Relative Density92.0 94.5 97.0
Upper LimitLower Limit
Target
16%9%9%
NTS
82%
34
Seller’s Risk(With 4.5% Tolerance)
S
(n=1)x̄
PW
L
Risk
(α)
1.84 94.5 98 2.0%
Relative Density90.0 94.5 99.0
Upper LimitLower Limit
Target
16%1%1%
NTS
98%
Option 1= Open Spec Band ±2.0%
Relative Density Specifications
35
Relative Density Pay Factor
97.1 0r Higher (Over-asphalted mix) 90% Pay Factor
92-97% (Ideal) 100% Pay Factor
89 – 91.9 (Marginal Air Voids) 85% Pay Factor
88.9 Or Less Reject (RQL)
Pay Factors
For all asphalt concrete pavement subject to acceptance testing, the
finished asphalt concrete pavements that do not conform to the
specified relative compaction requirements will be paid for using the
following pay factors:
36
Buyers Risk (β)(With 4.5% Tolerance)
S
(n=1)x̄
Buyer’s
Risk (β)
1.84 88.9 28%
Relative Density
88.9 90.0
Lower Limit
16%28%
NTS
RQL
Reject
Rejectable Quality Limit = 89.9
37
Buyers Risk (β)
88.9 LSL Target USL
16%Buyers
Risk (β)
NTS
AQL
RQL
α
38
Seller’s Risk(With 2.5% Tolerance)
S
(n=2)*x̄ PWL
Risk
(α)
1.30 94.5 98 2%
Relative Density92.0 94.5 97.0
Upper LimitLower Limit
Target
16%1%1%
NTS
98%
Avg. of Two Independent Samples
Risk vs Number of Observations (n)
The myth of the Single Representative Sample:
“The idea persists that a test on a single sample shows
the "true" quality of the material, and that if any test result
is not within some limit, there is something wrong with the
material, construction, sampling or testing. Thus, terms
such as investigational, check, and referee samples are
in common use to either confirm or document these
"failures.“ Nature dislikes identities; variation is the rule.
Therefore, any acceptance or process control sampling
must account for variability of materials or construction.
Multiple sampling accomplishes this objective”
FHWA - NHI Course No. 13442
39
Risk Vs Number of Test A
gen
cy a
nd
/or
Co
ntr
act
or
Ris
k
1 2 3 4 5 6 7
Number of Test Samples (n)
Best Practice:
Never make a decision to reject material
based on a single observation!
40
3
41
Seller’s Risk(QC/QA Multiple Observations)
S
(n=1)x̄ PWL
Risk
(α)
0.20 5.0 95 5%
Binder Content
3.8 4.2 4.6 5.0 5.4 5.8 6.2
Upper LimitLower Limit
Target
16%2.5% 1.72.5%
NTS
95%
42
Buyer’s/Seller’s Risk (Standard Spec With Single Observation)
Asphalt Content
16%
NTS
RQL Population
.
AQL Population
Single Test Specification
FHWA Peer Review Team Recommendation:
For other items without pay factors it is recommended that if one
test falls outside the specification limit then another test will
be taken. If the specification limit is met on the subsequent
test, production continues without any penalties.
If the second consecutive test falls outside the specification limit,
production will cease until the contractor demonstrates that the
specification limit can be met.
43
44
Sellers Risk (Test Result with Check or Referee Test)
Asphalt Content
16%
NTS
RQL Population
.
.
.
AQL Population
45
Sellers Risk (Population Defined with Additional Test)
Asphalt Content
16%
NTS
RQL Population
.
AQL Population
.
.
.. .. .....
...
Solution To Single Test Dilemma
The 2007 FHWA Peer Review Team Recommendations:
Pay equations need to be established for binder content for standard
and method specifications
Penalties should be commensurate with the performance of the
pavement.
46
And Remember
Never Reject Material Based on a Single Observation!
47
48